· 2010-08-10 · Heights, Geelong West and Geelong North (See Figure 1.1). The catchment is...
Transcript of · 2010-08-10 · Heights, Geelong West and Geelong North (See Figure 1.1). The catchment is...
K:\INFRA_MGMT\RW\FLOOD STUDIES\RIPPLESIDE CAT FS\8. FINAL DOCS - MAPS\R.W00201.004.01.FINALREPORT.DOC 6/8/10 13:08 O C E A N I C S A U S T R A L I A
Rippleside Catchment
Main Drain Augmentation
Final Report
Prepared For: City of Greater Geelong
Prepared By: WBM Oceanics Australia
Offices
Brisbane Denver
Karratha Melbourne
Morwell Newcastle
Sydney Vancouver
K:\INFRA_MGMT\RW\FLOOD STUDIES\RIPPLESIDE CAT FS\8. FINAL DOCS - MAPS\R.W00201.004.01.FINALREPORT.DOC 6/8/10 13:08 O C E A N I C S A U S T R A L I A
DOCUMENT CONTROL SHEET
Document: R.W00201.004.01.FinalReport.doc
Title: Rippleside Catchment
Main Drain Augmentation
Final Report
Project Manager: Allan Charteris
Author: Allan Charteris
Client: City of Greater Geelong
Client Contact: Richard Wojnarowski
Client Reference: Tender No. T00049
WBM Oceanics Australia
Melbourne Office: Level 5, 99 King Street MELBOURNE VIC 3000 Australia PO Box 604 Collins Street West VIC 8007 Telephone (03) 9614 6400 Facsimile (03) 9614 6966 www.wbmpl.com.au ACN 010 830 421
Synopsis: This report documents findings of flood investigations in the catchment of Rippleside, Geelong.
REVISION/CHECKING HISTORY
REVISION
NUMBER
DATE CHECKED BY ISSUED BY
1 28/02/2001 WJW ABC
DISTRIBUTION
DESTINATION REVISION
0 1 2 3 4 5 6 7 8 9 10
City of Greater Geelong
WBM File
WBM Library
2
1
1
2
1
1
CONTENTS I
K:\INFRA_MGMT\RW\FLOOD STUDIES\RIPPLESIDE CAT FS\8. FINAL DOCS - MAPS\R.W00201.004.01.FINALREPORT.DOC 6/8/10 13:08 IO C E A N I C S A U S T R A L I A
CONTENTS
Contents i
List of Appendices iii
List of Figures iii
List of Tables iv
1 INTRODUCTION 1-1
1.1 Background 1-1
1.2 Catchment Description 1-1
1.3 History of Flooding 1-2
1.3.1 Lantana Ave – Montgomery Ave 1-3
1.3.2 The Fairway and Geelong Golf Club 1-4
1.3.3 Calvert Ave and Lily Street 1-6
1.3.4 Other Areas 1-6
2 PROJECT METHODOLOGY 2-1
2.1 Preliminary Tasks 2-1
2.1.1 Project Initiation 2-1
2.1.2 Data Collation and Review 2-1
2.1.3 Barwon Water 2-2
2.2 Digital Elevation Model 2-2
2.3 Hydrological and Hydraulic Modelling, and Mapping of Existing Conditions 2-2
2.3.1 Hydrologic Analysis 2-2
2.3.1.1 Model Development 2-2
2.3.1.2 Design Event Modelling 2-3
2.3.2 Hydraulic Analysis 2-3
2.3.2.1 Model Selection and Development 2-3
2.3.2.2 Boundary Conditions 2-4
2.4 Mitigation Option Assessment and Mapping 2-4
2.4.1 Review of Existing Flooding Impacts 2-4
2.4.1.1 Impact Identification 2-4
2.4.1.2 Floor Level and Building Survey 2-5
2.4.1.3 Flood Damage 2-5
CONTENTS II
K:\INFRA_MGMT\RW\FLOOD STUDIES\RIPPLESIDE CAT FS\8. FINAL DOCS - MAPS\R.W00201.004.01.FINALREPORT.DOC 6/8/10 13:08 II O C E A N I C S A U S T R A L I A
2.4.2 Mitigation Option Assessment 2-5
3 DIGITAL ELEVATION MODEL 3-1
3.1 Catchment DEM 3-1
3.2 Study Area DEM 3-1
4 EXISTING CONDITIONS 4-1
4.1 Hydrology 4-1
4.1.1 Model Description 4-1
4.1.2 Global Parameters 4-1
4.1.2.1 Loss Parameters 4-1
4.1.2.2 Fraction Impervious 4-1
4.1.2.3 Reach Storage Relationships 4-2
4.1.3 Sub-Catchment Definition 4-2
4.1.4 Model Verification 4-3
4.1.4.1 Volume Checks 4-3
4.1.4.2 Rational Method Checks 4-3
4.2 Hydraulics 4-4
4.2.1 Model Selection 4-4
4.2.2 Model Development 4-5
4.2.2.1 Model Geometry 4-5
4.2.2.2 Model Resolution 4-5
4.2.3 Model Boundary Conditions 4-6
4.3 Flood Mapping 4-6
4.4 Building Inundation 4-7
4.5 Flood Hazard Mapping 4-7
4.6 Flooding Issues 4-8
5 MITIGATION ASSESSMENT 5-1
5.1 Mitigation Option Elements 5-1
5.2 Preferred Approach for Augmentation 5-4
5.3 Flood Hazard Mapping 5-5
5.4 Other Impacts 5-5
6 ECONOMIC ASSESSMENT 6-1
6.1 Flood Damages Assessment 6-1
6.1.1 Stage Damage Curves 6-1
LIST OF APPENDICES III
K:\INFRA_MGMT\RW\FLOOD STUDIES\RIPPLESIDE CAT FS\8. FINAL DOCS - MAPS\R.W00201.004.01.FINALREPORT.DOC 6/8/10 13:08 III O C E A N I C S A U S T R A L I A
6.1.2 Outside Buildings 6-1
6.1.3 Damages 6-2
6.2 Benefit Cost Ratio 6-3
6.2.1 Cost 6-3
6.2.2 Benefit 6-5
6.2.3 Benefit Cost 6-5
6.3 Intangible Damages/Benefits 6-5
6.4 Funding Mechanisms – Special Rates and Charges 6-6
6.5 Development Control in Flood Prone Areas 6-7
6.6 Discussion 6-8
7 STORMWATER MANAGEMENT PLAN 7-1
8 CONCLUSION 8-1
LIST OF APPENDICES
APPENDIX A: SURVEY REPORT A-1
APPENDIX B: MITIGATION OPTIONS – ELEMENT IMPACTS B-1
APPENDIX C: SPECIAL RATES AND CHARGES – LEGAL ADVICE C-1
APPENDIX D: DESIGN FLOW INFORMATION D-1
LIST OF FIGURES
Figure 1.1 Study Area 1-2
Figure 1.2 Flooding at Ballarat Road – December 1978 1-3
Figure 1.3 Flooding Cnr Marlo and Lantana – December 1978 1-3
Figure 1.4 Flooding at Montgomery Ave – December 1978 1-4
Figure 1.5 Flooding Downstream of Golf Club Car Park 1-4
Figure 1.6 Flooding Downstream of Golf Club Car Park 1-5
Figure 1.7 Flooding in The Fairway 1-5
Figure 1.8 Flooding in Baxter Road Retarding Basin – December 1992 1-6
Figure 2.1 Underground Drainage Network Error! Bookmark not defined.
Figure 3.1 5m DEM and Catchment Boundary 3-1
Figure 3.2 1m DEM of Flood Mapping Area 3-2
LIST OF TABLES IV
K:\INFRA_MGMT\RW\FLOOD STUDIES\RIPPLESIDE CAT FS\8. FINAL DOCS - MAPS\R.W00201.004.01.FINALREPORT.DOC 6/8/10 13:08 IV O C E A N I C S A U S T R A L I A
Figure 3.3 1m DEM of Flood Mapping Area - Perspective View 3-3
Figure 4.1 RORB (Hydrology) Model Layout Error! Bookmark not defined.
Figure 4.2 TUFLOW (Hydraulic) Model Layout Error! Bookmark not defined.
Figure 4.3 100y Design Event Flood Inundation Error! Bookmark not defined.
Figure 4.4 Inundation Above Floor Level Error! Bookmark not defined.
Figure 4.5 Hazard Mapping – Existing Case 100 Year Design EventError! Bookmark not defined.
Figure 4.6 Flooding Issues in the Rippleside Catchment 4-1
Figure 5.1 Weddell Road Retarding Basin Storage Characteristics 5-4
Figure 5.2 Mitigation Option Elements Error! Bookmark not defined.
Figure 5.3 Augmented System Elements Error! Bookmark not defined.
Figure 5.4 100y Design Event Flood Extent for Augmented SystemError! Bookmark not defined.
Figure 5.5 100y Above Floor Level Inundation – After AugmentationError! Bookmark not defined.
Figure 5.6 Hazard Mapping – Augmented Case 100 Year Design EventError! Bookmark not defined.
Figure 6.1 Rippleside Flood Damage Curves 6-2
Figure 6.2 Areas Suitable for Alternative Flood Relief Strategies Error! Bookmark not defined.
LIST OF TABLES
Table 4-1 Impervious Fraction for Planning Scheme Zone 4-2
Table 4-2 Hydrological Model Verification 4-4
Table 4-3 TUFLOW Manning’s n Coefficients 4-5
Table 4-4 Number of Properties Inundated Above Floor Level 4-7
Table 4-5 Hazard Categories 4-7
Table 5-1 Effect of Options on Existing Flooding 5-3
Table 6-1 Guideline Per metre Costs for Pipe Augmentation Works 6-3
Table 6-2 Estimated Cost of Augmentation Works 6-3
Table 6-3 Detailed Breakdown of Cost Estimate 6-4
INTRODUCTION 1-1
K:\INFRA_MGMT\RW\FLOOD STUDIES\RIPPLESIDE CAT FS\8. FINAL DOCS - MAPS\R.W00201.004.01.FINALREPORT.DOC 6/8/10 13:08 1-1 O C E A N I C S A U S T R A L I A
1 INTRODUCTION
1.1 Background
The City of Greater Geelong has embarked on a process to investigate existing drainage capacity and
to develop a plan for the upgrade of the system to mitigate existing flood problems. The Drainage
Augmentation Study for the Rippleside Catchment is specifically concerned with:
• defining (simulating) and mapping existing flooding characteristics and drainage system
deficiencies in the Catchment;
• assessing the nature and magnitude of impacts associated with existing flooding;
• identifying potential augmentation strategies to reduce damages associated with flooding
impacts; and,
• evaluating and identifying opportunities of funding capital and maintenance works associated
with the recommendations of the study.
This report documents the findings of WBM’s investigations of flooding in the Rippleside catchment
and presents mitigation options to minimise flooding impacts.
1.2 Catchment Description
The catchment of Rippleside is the largest urban catchment in Geelong (approximately 750 Ha) and
is located north of the city ranging over the suburbs of Hamlyn Heights, Herne Hill, Manifold
Heights, Geelong West and Geelong North (See Figure 1.1).
The catchment is characterised by significant and almost complete urbanisation with few “open
space” areas. These are limited to areas within the Geelong Golf Club, a dedicated drainage reserve
between Weddell and Baxter Roads, and a small portion of undeveloped area at the top of the
catchment.
The existing drainage infrastructure is typically very old, much of it in place and unchanged since
subdivision and development 30 to 60 years ago. Current drainage problems within the Rippleside
Catchment are similar to those experienced by many older urban catchments which contain
hydraulically constrained and aging stormwater systems. The characteristics of these catchments are
usually typified by high levels of development, extensive areas of imperviousness and limited
retention of dedicated drainage reserves or open channel systems. Additionally, the underground
drainage systems are typically under capacity and there is a lack of conveyance and/or storage
capacity above ground for major flows.
INTRODUCTION 1-2
K:\INFRA_MGMT\RW\FLOOD STUDIES\RIPPLESIDE CAT FS\8. FINAL DOCS - MAPS\R.W00201.004.01.FINALREPORT.DOC 6/8/10 13:08 1-2 O C E A N I C S A U S T R A L I A
Figure 1.1 Study Area
The topography of the catchment is somewhat different from the typical floodplain catchment. Where
one would usually find steeper upper catchment areas and a broad floodplain in lower areas,
Rippleside exhibits quite the opposite relief. The upper parts of the catchment (above Vines Road) are
very flat, almost as a plateau. The grade changes significantly below Vines Road and the lower parts
of the catchment are relatively steep. The drainage paths become well defined and somewhat incised,
particularly in the drain through the southern part of the Geelong Golf Club.
The outlet of the catchment is to Rippleside Beach via a culvert that runs from the retarding basin at
Baxter Road, below the Geelong-Melbourne Railway and under Rippleside Park. The railway
virtually forms a dam wall preventing overland flows from progressing further down the catchment.
1.3 History of Flooding
The flooding history in the catchment is varied with problems often attributed to limited underground
capacity resulting in overland flows for which there exists no defined floodway. In a number of cases,
dwellings have been built in the flowpath and occasionally as “slab on ground” (eg Lily and Graham
St).
INTRODUCTION 1-3
K:\INFRA_MGMT\RW\FLOOD STUDIES\RIPPLESIDE CAT FS\8. FINAL DOCS - MAPS\R.W00201.004.01.FINALREPORT.DOC 6/8/10 13:08 1-3 O C E A N I C S A U S T R A L I A
1.3.1 Lantana Ave – Montgomery Ave
Significant flooding was experienced in the Lantana Av – Montgomery Ave area due to a local storm
on 17 December 1978.
At Ballarat Road, the outbound road was cut and flood depths of approximately 0.5-1.0m were
observed due to ponding above the median strip (Figure 1.2). Ponding behind the railway lead to
flooding at the Lantana Ave Marlo St intersection (Figure 1.3), again with flood depths of
approximately 0.5-1.0 m observed. Significant overland flows were also observed in Montgomery
Ave (Figure 1.4).
Figure 1.2 Flooding at Ballarat Road – December 1978
Figure 1.3 Flooding Cnr Marlo and Lantana – December 1978
INTRODUCTION 1-4
K:\INFRA_MGMT\RW\FLOOD STUDIES\RIPPLESIDE CAT FS\8. FINAL DOCS - MAPS\R.W00201.004.01.FINALREPORT.DOC 6/8/10 13:08 1-4 O C E A N I C S A U S T R A L I A
Figure 1.4 Flooding at Montgomery Ave – December 1978
Flooding in this event was observed to be brief and property inundation above floor level was not
reported.
1.3.2 The Fairway and Geelong Golf Club
Numerous flooding incidents have been reported by the Golf Club with particular problems in the
carpark and practise fairway areas (See Figure 1.5 and Figure 1.6).
Figure 1.5 Flooding Downstream of Golf Club Car Park
INTRODUCTION 1-5
K:\INFRA_MGMT\RW\FLOOD STUDIES\RIPPLESIDE CAT FS\8. FINAL DOCS - MAPS\R.W00201.004.01.FINALREPORT.DOC 6/8/10 13:08 1-5 O C E A N I C S A U S T R A L I A
Figure 1.6 Flooding Downstream of Golf Club Car Park
Figure 1.7 Flooding in The Fairway
Figure 1.7 illustrates the effect of this type of flooding on The Fairway, the road directly downstream
from the effected Golf Club areas.
The Golf Club report that this type of flooding is relatively frequent, in 1994 suggesting that the type
of flooding presented in the above photos has occurred 2-3 times since 1989.
INTRODUCTION 1-6
K:\INFRA_MGMT\RW\FLOOD STUDIES\RIPPLESIDE CAT FS\8. FINAL DOCS - MAPS\R.W00201.004.01.FINALREPORT.DOC 6/8/10 13:08 1-6 O C E A N I C S A U S T R A L I A
1.3.3 Calvert Ave and Lily Street
Reports of flooding and inundation to almost floor level in these areas were recorded following flood
events in 1988. Several properties were inundated and evidence of flooding of garages and garden
sheds was observed.
Reports indicated that flooding in these areas was a relatively frequent occurrence. Photographic
documentation was not available.
1.3.4 Other Areas
Significant flooding has been observed on many occasions in the Baxter Rd retarding basin.
Figure 1.8 Flooding in Baxter Road Retarding Basin – December 1992
Minor flooding in December 1992 resulted in the inundation illustrated in Figure 1.8. On other
occasions, flood levels have been observed above the crest of Baxter Road (to the left of Figure 1.8).
While the purpose of the retarding basin is to provide flood storage and is fulfilling that role, there is
concern that peak flood levels in the area may impact upon adjacent housing during less frequent
events.
PROJECT METHODOLOGY 2-1
K:\INFRA_MGMT\RW\FLOOD STUDIES\RIPPLESIDE CAT FS\8. FINAL DOCS - MAPS\R.W00201.004.01.FINALREPORT.DOC 6/8/10 13:08 2-1 O C E A N I C S A U S T R A L I A
2 PROJECT METHODOLOGY
The methodology to undertake the Rippleside Drainage Augmentation Study was detailed in WBM’s
proposal and forms part of the contract documentation. This section provides a brief overview of the
methodology adopted during the project with particular reference to any alterations required to
overcome difficulties encountered during the course of the project.
The methodology was developed in accordance with the requirements of the study brief with a
particular emphasis on ensuring that recommended augmentation options are realistically
implemented within local hydraulic, economic and political constraints.
2.1 Preliminary Tasks
2.1.1 Project Initiation
Project initiation occurred in May 2000 with a meeting of the City of Greater Geelong’s Project
Officer (Mr Richard Wojnarowski) and WBM project staff (Allan Charteris, Wesley Walden, Lloyd
Heinrich). Following the meeting a ½ day site inspection was undertaken where Council’s Project
Officer identified key elements of the system and related flooding issues to WBM.
During the course of the project additional site inspections were undertaken by WBM staff to clarify
flood and drainage issues.
2.1.2 Data Collation and Review
Upon commissioning, all relevant data and information for the Catchment and its drainage systems
was obtained from Council and Barwon Water. Review of this information was undertaken to
identify any significant data gaps and to gain a complete understanding of issues in the Rippleside
catchment.
Council provided detailed information regarding systems that are currently under their responsibility
as well as some information suitable for providing infill to the data gaps identified in the City of
Greater Geelong data set.
Additional data was retrieved from Barwon Water, including cadastral information, ground level
contours over the entire catchment, and planning scheme information. The underground drainage
information has been comprehensively reviewed.
Figure 2.1 shows the major underground drainage network within the floodmapping area. The key
features of the drainage system, typically pipes with diameter greater than 600mm, are illustrated. In
some areas, limited or very old information has been provided for the drainage network. Additional
information regarding these areas was provided by the City of Greater Geelong and the data set was
deemed complete.
PROJECT METHODOLOGY 2-2
K:\INFRA_MGMT\RW\FLOOD STUDIES\RIPPLESIDE CAT FS\8. FINAL DOCS - MAPS\R.W00201.004.01.FINALREPORT.DOC 6/8/10 13:08 2-2 O C E A N I C S A U S T R A L I A
2.1.3 Barwon Water
Barwon Water have supplied the following data:
� Cadastre over the Rippleside catchment
� Planning Scheme Zones over the catchment
� 1m contours over the catchment
The initially supplied contour data set covered only part of the catchment of Rippleside. Additional
time was required to complete the data set by digitising the remainder of the catchment from the
Corio 2500 series maps.
2.2 Digital Elevation Model
Preparation of the Digital Elevation Models used in the study is discussed in Section 3. Briefly, the
process for the preparation of the DEMs is described below.
The DEM for the mapping area was developed using the points and break lines derived from
photogrammetry. Establishment of the DTM involved the development of Triangulated Irregular
Network (TIN) using these points and breaklines to establish a continuous triangular 3D shape of the
area. For mapping purposes the continuous TIN is sampled at the requisite model resolution to create
a grid of data points forming the DEM. Vertical Mapper, which operates within the MapInfo GIS
package, was used to create the DEM. Within the flood mapping area the sampling resolution for the
DEM is 1m. Based on our past experience, we have found that this level of detail is well suited to
simulating the topography of heavily urbanised environments.
The DEM was reviewed to identify any anomalies. Site inspections were undertaken to verify terrain
shape.
2.3 Hydrological and Hydraulic Modelling, and Mapping of Existing Conditions
This Section discusses our approach to developing hydrological and hydraulic models, simulating
existing flooding characteristics and developing flood maps for existing conditions.
2.3.1 Hydrologic Analysis
2.3.1.1 Model Development
A RORB (Version 4.2) hydrological model was developed for the entire catchment to simulate
rainfall runoff characteristics and generate inflows for the hydraulic model. The RORB hydrological
model simulates catchment storage and routing characteristics, including the incorporation of
retarding basins or areas that provide natural retardation of flows. The development of hydrological
model involves the following key steps:
• subcatchment definition was undertaken using available topographical information for the study
area. Existing information is considered sufficient in this regard. Subcatchment delineation took
PROJECT METHODOLOGY 2-3
K:\INFRA_MGMT\RW\FLOOD STUDIES\RIPPLESIDE CAT FS\8. FINAL DOCS - MAPS\R.W00201.004.01.FINALREPORT.DOC 6/8/10 13:08 2-3 O C E A N I C S A U S T R A L I A
into consideration compatibility with the required extent of hydraulic analysis as well as land use
characteristics.
• landuse characteristics were identified from the current planning scheme zonings. This
information along with available aerial photography was used to derive proportions of
perviousness and imperviousness within each subcatchment.
• model loss parameters were applied in accordance with the catchment characteristics and based
on similar hydrological investigations in the region.
• channel routing methods within RORB was selected in consideration of reach type and
incorporating physical data relating to length and slope.
• storage and routing parameters (k and m) were determined from theoretical calculations for the
derivation of default values.
Historical stream flow information for hydrological model calibration does not exist in the study area.
Verification of peak flows generated by the RORB models was undertaken in consideration of values
derived using the Rational Method. As part of this process RORB model parameters were adjusted to
achieve consistency between both approaches.
2.3.1.2 Design Event Modelling
RORB was used to derive hydrographs as input to the hydrodynamic model of the drainage system.
Temporal patterns and design rainfall intensities were derived from Australian Rainfall and Runoff
IFD curves and maps. This process involved the derivation of design rainfall events covering a range
of return periods and durations for each drainage sub area. The 5, 10, 20, 50, and 100 year ARI events
were simulated.
2.3.2 Hydraulic Analysis
2.3.2.1 Model Selection and Development
Originally, the study was to be undertaken using MIKE11, a 1D hydraulic modelling package from
DHI. Initial testing of the model shows good correlation with anecdotal evidence of flooding within
the catchment, particularly in the lower portions. However, the complex distribution of flows in the
upper sections of the model has difficult to model with an appropriate degree of certainty. This is due
to a number of factors, including:
• The requirement in MIKE11 to predefine flow paths as model branches. These are typically
defined in consideration of relatively low flows. However the alignment of these paths can
change in higher flow situations, either by short circuiting, breakouts with looped anabranch
flows or transverse flow between parallel channels.
• The ability of MIKE11 to handle sheet flow situations through, for example, residential areas.
Predefinition of these types of flow paths as 1 dimension branches does not take into
consideration the effect of momentum in the 2D horizontal plane.
PROJECT METHODOLOGY 2-4
K:\INFRA_MGMT\RW\FLOOD STUDIES\RIPPLESIDE CAT FS\8. FINAL DOCS - MAPS\R.W00201.004.01.FINALREPORT.DOC 6/8/10 13:08 2-4 O C E A N I C S A U S T R A L I A
In consideration of these, and in consultation with the City of Greater Geelong, it was decided to
migrate the modelling to a 2D platform, TUFLOW, which has the capability to overcome the
problems above while providing the necessary level of detail.
Section 4.2 describes the selection and development of the 2D hydraulic model.
2.3.2.2 Boundary Conditions
The hydraulic model requires downstream boundary conditions and lateral inflow boundary
conditions representing the runoff from the catchment.
The downstream boundary condition has been specified as a constant tailwater level reflecting the
mean tidal level in Corio Bay.
Catchment runoff was modelled using the hydrological (RORB) model, as previously discussed, and
the output will subsequently provide inflows to the hydraulic model.
The hydrological model provides flow outputs at nodes at designated locations throughout the
catchment. The conventional approach is to then simulate these inflows in the hydraulic model as a
series of individual point discharges. This approach is suitable when simulating the discharge from a
single pipe outlet, however, in reality runoff will also enter the drainage system as dispersed inflows
(overland flows) along the length of the drainage system. Based on our previous experience with
modelling urban drainage systems similar to the Rippleside Catchment, we have found that the
performance of the hydraulic model in simulating discharges and water levels is sensitive to the
proposed method of simulating inflows.
In response to the above issue, WBM Oceanics Australia has developed in-house software that
interfaces hydrological model output and TUFLOW. This software provides the flexibility of
generating a number of smaller lateral inflow boundary conditions along flow paths in the model to
simulate dispersed overland flow more accurately.
2.4 Mitigation Option Assessment and Mapping
This section outlines our approach when assessing the flooding characteristics of the existing
drainage system and identifying possible mitigation options to alleviate flooding problems.
2.4.1 Review of Existing Flooding Impacts
2.4.1.1 Impact Identification
Results from the existing flood simulations would be reviewed to identify major constriction or
conveyance deficiencies that are contributing to flooding impacts. In this regard, the impact
identification involved:
• Design event simulation for a range a design flood events to consider the capacity of various
components of the existing system, and when and where flood problems are likely to occur;
• Identification and documentation of flood prone areas where properties and infrastructure are
subject to flooding under varying ranges of event frequency;
PROJECT METHODOLOGY 2-5
K:\INFRA_MGMT\RW\FLOOD STUDIES\RIPPLESIDE CAT FS\8. FINAL DOCS - MAPS\R.W00201.004.01.FINALREPORT.DOC 6/8/10 13:08 2-5 O C E A N I C S A U S T R A L I A
• Identification of under sized components of the system that may be causing flooding and
backwater effects;
• Assessment of the influence of hydrograph peak timings from various subcatchments within the
study area and the influence that this has on flooding impacts at particular locations; and
• GIS database analysis to provide a comprehensive list of all properties and infrastructure that is
affected by flooding in the catchment.
2.4.1.2 Floor Level and Building Survey
A detailed survey was conducted by City of Greater Geelong focussing on properties where model
results indicate a significant threat from flooding. Floor level, property size and condition and other
information was collected to be used in subsequent damages assessments.
2.4.1.3 Flood Damage
A damages assessment for properties and infrastructure was carried out based on the ANUFLOOD
method. The method contains appropriate relationships between depth of flooding and damages for a
range of building types (eg. low level house of low value, high set house of medium value, high value
commercial property) etc. These relationships account for such factors as the time of flood warning
and the relative degree of flood preparedness of the community.
Annual Average Damage predictions for urban areas are calculated from the damage curves and are
used as a starting point for establishing cost/benefit ratios of the augmentation options considered.
2.4.2 Mitigation Option Assessment
From the review of existing flooding a series of mitigation options were developed. Structural options
will be considered to alleviate drainage bottle necks and storage problem areas. Typical structural
measures considered included:
• Modification and resizing of major culverts and waterway openings which may be causing
flooding impacts;
• Development of structural measures such as levee banks to protect properties from flooding; and
• Construction of major flood retarding structures to protect downstream areas.
PROJECT METHODOLOGY 2-6
K:\INFRA_MGMT\RW\FLOOD STUDIES\RIPPLESIDE CAT FS\8. FINAL DOCS - MAPS\R.W00201.004.01.FINALREPORT.DOC 6/8/10 13:08 2-6 O C E A N I C S A U S T R A L I A
DIGITAL ELEVATION MODEL 3-1
K:\INFRA_MGMT\RW\FLOOD STUDIES\RIPPLESIDE CAT FS\8. FINAL DOCS - MAPS\R.W00201.004.01.FINALREPORT.DOC 6/8/10 13:08 3-1 O C E A N I C S A U S T R A L I A
3 DIGITAL ELEVATION MODEL
3.1 Catchment DEM
A broad scale Digital Elevation Model (DEM) was developed for the entire catchment for use in
hydrology components of the study. Barwon Water provided contours over the entire catchment at
approximately 1.5m intervals (data derived from 6’ contour information). These data were used to
create a DEM with a 5m horizontal resolution. Figure 3.1 shows the entire catchment DEM.
Figure 3.1 5m DEM and Catchment Boundary
3.2 Study Area DEM
The detailed Digital Elevation Model (DEM) of the study area was developed from a range of data
sources. It involved a combination of existing photogrammetry, new photogrammetry from existing
low level aerial photography and ground controlled terrestrial survey. Information collected as part of
the survey program was as follows:
DIGITAL ELEVATION MODEL 3-2
K:\INFRA_MGMT\RW\FLOOD STUDIES\RIPPLESIDE CAT FS\8. FINAL DOCS - MAPS\R.W00201.004.01.FINALREPORT.DOC 6/8/10 13:08 3-2 O C E A N I C S A U S T R A L I A
• Existing Photogrammetry – existing photogrammetric data from within the study area gathered
as part of the 1992 survey.
• Low Level Aerial Photography (Barwon Water 1992) – low level aerial photography collected
by Barwon Water was obtained and reviewed for use in photogrammetric analysis. The
photography was used to prepare digital terrain information of the remainder of the study area.
• Aerial Survey Photo Control – photo control survey collected as part of the Barwon Water
survey in 1992 was used to validate photogrammetry.
Appendix A presents the survey report regarding the photogrammetry data extracted from the
existing photography. Vertical accuracy of the photogrammetry was 0.1m.
The DEM for the mapping area was developed using the points and break lines derived from
photogrammetry. Figure 3.2 and Figure 3.3 illustrate the detailed DEM of the study area.
Figure 3.2 1m DEM of Flood Mapping Area
DIGITAL ELEVATION MODEL 3-3
K:\INFRA_MGMT\RW\FLOOD STUDIES\RIPPLESIDE CAT FS\8. FINAL DOCS - MAPS\R.W00201.004.01.FINALREPORT.DOC 6/8/10 13:08 3-3 O C E A N I C S A U S T R A L I A
Figure 3.3 1m DEM of Flood Mapping Area - Perspective View
The detailed 1m DEM was used as the basis for the preparation of the hydraulic model for the study
area. It also provides the foundation for the derivation of flood extent and presentation of other flood
mapping.
EXISTING CONDITIONS 4-1
K:\INFRA_MGMT\RW\FLOOD STUDIES\RIPPLESIDE CAT FS\8. FINAL DOCS - MAPS\R.W00201.004.01.FINALREPORT.DOC 6/8/10 13:08 4-1 O C E A N I C S A U S T R A L I A
4 EXISTING CONDITIONS
Assessment of the existing flood conditions throughout the catchment is presented in this section.
This information provides the base for the assessment of the effectiveness of mitigation measures
tested in Section 0.
4.1 Hydrology
4.1.1 Model Description
Hydrological modelling was performed in this study using the runoff and stream routing program
RORB (Laurenson and Mein, 1997). RORB simulates the hydrological behaviour of a catchment by
discretising the area into a series of sub-catchments joined by a series of reaches. Rainfall-runoff is
simulated for each catchment with the hydrographs routed through the stream network using a non-
linear storage routing procedure.
RORB is widely used in Victoria and is the package recommended by Melbourne Water for the
assessment of hydrological characteristics of ungauged catchment in metropolitan areas.
4.1.2 Global Parameters
4.1.2.1 Loss Parameters
RORB generates runoff by subtracting losses at each timestep from the rainfall occurring in that time
period, losses were assumed to comprise an initial loss followed by a continuing loss. An initial loss
of 12.5 mm was adopted, and continuing losses were considered as a constant proportion of the
rainfall in each timestep. Continuing loss in RORB for impervious areas is a predefined fraction of
the rainfall where 10% of the rainfall per timestep is lost. The following volumetric runoff
coefficients were adopted:
100y event 0.60
50y event 0.55
20y event 0.45
10y event 0.40
5y event 0.35
4.1.2.2 Fraction Impervious
The fraction of the catchment that is impervious is a key input to the hydrologic modelling.
Impervious fractions for various planning scheme codes were identified based on previous experience
in similar studies within metropolitan Melbourne (undertaken on behalf of Melbourne Water) and
adopted in consultation with City of Greater Geelong. Key impervious fractions are presented in
Table 4-1 below:
EXISTING CONDITIONS 4-2
K:\INFRA_MGMT\RW\FLOOD STUDIES\RIPPLESIDE CAT FS\8. FINAL DOCS - MAPS\R.W00201.004.01.FINALREPORT.DOC 6/8/10 13:08 4-2 O C E A N I C S A U S T R A L I A
Table 4-1 Impervious Fraction for Planning Scheme Zone
Zone Impervious Fraction
General Residential 0.4
General Commercial 0.8
General Industrial 0.8
Public Open Space 0.1
Roads 0.9
General Farming 0.1
Special Public Purpose (e.g. school) 0.6
The planning scheme data were used to establish a spatially weighted average of the impervious
fractions for each hydrologic modelling sub-area.
4.1.2.3 Reach Storage Relationships
RORB simulates the linkages between sub-catchments as reach storages with the storage discharge
relationship defined by the following equation;
S = 3600kQm
Where S represents the storage (m3), Q is the discharge (m3/s), m is a dimensionless exponent and k is
non-dimensional empirical coefficient. k is defined by the product of the catchment value kc and the
individual reach ki. Both m and kc are defined as calibration parameters. These were defined based
on previous experience in RORB modelling in metropolitan Melbourne.
For all catchments m was assumed to be equivalent to 0.8 and kc was calculated using the following
equation;
kc = 1.53A0.53
where A is equivalent to the catchment area. This equation was sourced from Melbourne Water and is
recommended by Melbourne Water for use in urban catchments throughout metropolitan Melbourne.
Melbourne Water has undertaken considerable research to establish this relationship and is
considered the most appropriate for use in metropolitan Melbourne.
4.1.3 Sub-Catchment Definition
Sub-catchments used in the hydrologic modelling process were defined using a combination of City
of Greater Geelong drainage scheme plans and topographic data. Where drainage scheme data was
not available sub-catchments were defined using topographic data.
Assessment of the hydrological characteristics of the catchment was undertaken using RORB.
Sub-catchment breakdown is presented in Figure 4.1, also showing the location (in red) of
checkpoints for hydrological model verification (Section 4.1.4).
EXISTING CONDITIONS 4-3
K:\INFRA_MGMT\RW\FLOOD STUDIES\RIPPLESIDE CAT FS\8. FINAL DOCS - MAPS\R.W00201.004.01.FINALREPORT.DOC 6/8/10 13:08 4-3 O C E A N I C S A U S T R A L I A
4.1.4 Model Verification
No data were available for model calibration. To determine the overall validity of the hydrologic
modelling, checks of peak flow against recognised calculation methods were undertaken and are
presented below.
4.1.4.1 Volume Checks
As a preliminary check to ensure the RORB model was correctly configured, the runoff volume
generated by the numeric model was compared against the volume derived by distributing the rainfall
depth over the catchment area. The primary purpose of this check is to ensure there were no model
leaks or short circuits.
The runoff volume for each catchment was estimated by distributing a 2 hour 100yr ARI rainfall
event over the catchment and recording the volume of runoff generated at the outlet of the catchment.
To ensure no loss of rainfall occurred the catchment parameters were set as follows, initial loss = 0
mm and runoff coefficient = 1. The volume of runoff generated by the model was compared to the
volume calculated by multiplying the catchment area by the rainfall depth.
In all cases, the difference in runoff volume estimated by both methods was less than 1% of the total
runoff volume and thus the volume checks were satisfied.
4.1.4.2 Rational Method Checks
In addition to the volume checks a further check of each RORB model was performed to verify the
peak flows generated. The RORB model was configured and run assuming that the catchment
contained no storages, these results were compared to the peak flow estimated using the Rational
Method, defined by the following equation;
Q C I Atc100 100 1000 278= . . ,
Where Q100 Peak discharge
C100 Runoff coefficient for a 1% probability event
Itc,100 100 year ARI rainfall intensity for a storm of duration tc
tc Time of concentration of the catchment
A Catchment Area
A runoff coefficient of 0.6 was adopted in line with the hydrologic modelling assumptions. The
rainfall intensity was estimated using the Algebraic Method outlined in Book 2 of Australian Rainfall
and Runoff (Institution of Engineers, 1998). The critical storm duration was checked by comparing
the duration of the critical storm from the RORB results with the time of concentration estimated
using the Bransbury Williams method.
Bransbury Williams
The Bransbury Williams formula is recommended as a reasonable approach to estimate the time of
concentration of a catchment as it includes provision to allow for slope of the catchment when
calculating response times;
EXISTING CONDITIONS 4-4
K:\INFRA_MGMT\RW\FLOOD STUDIES\RIPPLESIDE CAT FS\8. FINAL DOCS - MAPS\R.W00201.004.01.FINALREPORT.DOC 6/8/10 13:08 4-4 O C E A N I C S A U S T R A L I A
tL
A Sc
e
=
58
0 1
0 2
.
.
Where tc time of concentration
L mainstream length measured from catchment divide
A catchment area
Se equal area slope of the main stream projected to the catchment divide
The Bransbury Williams method is used principally for the estimation of flows in ungauged rural
catchments. Limitations in the use of this method in urban areas chiefly relate to the lumping of
parameters at a single point in the catchment such that there is no distribution of catchment
characteristics. Nevertheless, past experience has shown these methods to be very useful in providing
first pass estimates of time of concentration and peak flow.
Table 4-2 below presents the results of the model verification.
Table 4-2 Hydrological Model Verification
Location Rational Method Flow
(m3/s)
RORB Peak Flow
(m3/s)
Node 13 19.3 17.0
Node 35 21.0 21.3
Node 52 North 12.4 12.1
Node 52 South 21.6 21.8
Node 52 Total 41.8 43.1
The estimates of flow obtained from the Bransbury Williams method agree with the values obtained
from RORB. This comparison yields a high degree of confidence in the performance of the RORB
model and is considered suitable for use in the preparation of design event hydrology information for
subsequent hydraulic modelling.
4.2 Hydraulics
4.2.1 Model Selection
Hydraulic assessment of the flooding characteristics within the Rippleside catchment was undertaken
using a fully 2D modelling approach that included the provision of key elements of the underground
drainage system. The model provided full dynamic interaction of the overland and underground
systems. WBM’s modelling system TUFLOW was favoured over other similar systems (eg. Mike21)
for the following reasons:
• Fully geo-referenced flood modelling capability allowing direct integration of the DEM
information within the model.
EXISTING CONDITIONS 4-5
K:\INFRA_MGMT\RW\FLOOD STUDIES\RIPPLESIDE CAT FS\8. FINAL DOCS - MAPS\R.W00201.004.01.FINALREPORT.DOC 6/8/10 13:08 4-5 O C E A N I C S A U S T R A L I A
• Dynamic simulation of 1D elements means that culverts, bridges, weirs and other 1 dimensional
elements are modelled at the same time as the overland system and allow direct interaction
between the two conveyance mechanisms.
• Fully integrated with GIS for floodmapping of the resulting flood extent and inundation depths
allowing easy interrogation of flood information against other GIS related data (eg. floor levels,
property boundaries).
• Suitability for time varying simulations with robust wetting and drying algorithms promoting
model stability and accurate representation of floodplain hydraulics.
4.2.2 Model Development
Drainage design information was used to provide detailed information in the development of the
TUFLOW hydraulic model. Overland flood flow paths were established from on-site inspections and
review of the detailed Digital Elevation Model.
4.2.2.1 Model Geometry
The geometry of the 2D model was established by constructing a uniform grid of rectangular cells
using the following information:
• The detailed Digital Elevation Model developed from photogrammetry of the study area;
• Major waterway openings associated with road crossings (eg. Weddell Rd); and
• Key control points based on specific ground survey.
• As discussed previously, 1D components of the model included key elements of the underground
drainage system, hydraulic structures and extensions upstream and downstream of the 2D
modelling domain. These components of the model were established using the detailed drainage
information provided by City of Greater Geelong.
The model was developed using typical roughness parameters for the urban areas. Table 4-3 below
presents the key Manning’s n coefficients used in the model.
Table 4-3 TUFLOW Manning’s n Coefficients
Commercial/Industrial 0.280
Residential 0.280
Roads 0.022
Grassed Floodways 0.033
Railway 0.080
4.2.2.2 Model Resolution
One of the key considerations in establishing a 2D hydraulic model relates to the selection of an
appropriate grid size. Grid size or model resolution must be balanced in consideration of the goals of
EXISTING CONDITIONS 4-6
K:\INFRA_MGMT\RW\FLOOD STUDIES\RIPPLESIDE CAT FS\8. FINAL DOCS - MAPS\R.W00201.004.01.FINALREPORT.DOC 6/8/10 13:08 4-6 O C E A N I C S A U S T R A L I A
the study and computation efficiency. Accordingly, the grid resolution must be selected to provide a
suitable compromise of the following:
• The grid resolution must be fine enough to provide sufficient representation of the modelling
domain to accurately simulate the physical characteristics the study area; and
• The grid resolution must result in a model with number of elements that will not result in
unrealistically long run times. Model run times of greater than 10 hours are generally not
considered to be practical.
The computation cell size for the TUFLOW model was set at 5m. In adopting the grid size for the
Rippleside 2D model the above mentioned issues were considered in accordance with the final
objectives of the study and production of detailed flood maps. A 5m grid size over the study area
provides a good definition of land shape, key controls and waterways.
In TUFLOW, the computation nodes are located at cell centres, midsides and corners, such that the
spatial resolution of the underlying terrain is twice that of the model (ie. 2.5m). Water levels are
calculated at cell corners and velocities at cell midsides.
The model domain and underground network are shown in Figure 4.2. All hydraulic parameters
describing the underground pipe network were provided in the City of Greater Geelong data set. It
has been assumed that there is no restriction to the entry of stormwaters into the underground system
and that the pipes are free from debris, etc such that they flow at design capacity.
4.2.3 Model Boundary Conditions
Boundary conditions for flood water inflows are provided by the hydrologic (RORB) modelling.
Point inflows, from an adjoining sub-catchment, are input at the edge of the model. Local inflows,
derived from a catchment within the 2D model domain, are distributed as inflows at a number of
locations along the reach, depending on the length of reach and size of catchment.
The downstream boundary condition for the mapping area is a constant tail water level set at mean
sea level in Corio Bay. Sensitivity testing indicated that setting this level at high or low water did not
influence flooding in the study area of the Rippleside catchment.
4.3 Flood Mapping
For each event, simulations of the range of selected durations were undertaken. The maxima of these
simulations provides the flood level envelope. Flood extents are derived from comparison of these
data with the DEM and are shown in Figure 4.3.
Figure 4.3 displays the inundation extent for the design 100y event. Complete mapping for the
existing conditions for the 5y, 10y, 20y, 50y and 100y design flood events is provided on separate
plans. The number of properties inundated above floor level is shown in Table 4-4.
EXISTING CONDITIONS 4-7
K:\INFRA_MGMT\RW\FLOOD STUDIES\RIPPLESIDE CAT FS\8. FINAL DOCS - MAPS\R.W00201.004.01.FINALREPORT.DOC 6/8/10 13:08 4-7 O C E A N I C S A U S T R A L I A
Table 4-4 Number of Properties Inundated Above Floor Level
Design Event 5y 10y 20y 50y 100y
Number of Properties
Inundated above Floor Level
5 5 6 13 21
4.4 Building Inundation
The modelling indicates flood inundation to a number of residential and commercial properties in the
drainage system. Floor level survey was gathered by City of Greater Geelong and compared with the
inundation depths generated by the model. In total, approximately 130 floor levels were gathered and
of these it was found that 21 properties were inundated above floor level.
Figure 4.4 below shows the 100y design flood extent and surveyed property locations. Properties
shown in red indicated a flood level above the floor level at that location, while points in green
indicate a floor level above 100y design flood level.
The floor level survey revealed many properties with floor levels near the 100y design flood level. Of
the 130 properties surveyed, 56 were within 25mm of the 100y design flood level at that location.
Due to sub-scale features (ie topographic features on a less than 5m scale) flooding of individual
properties may or may not occur.
4.5 Flood Hazard Mapping
Public Safety is a significant issue for Council. In terms of flooding and drainage, public safety
relates to direct risks from flooding (eg. injury or death resulting from drowning) and indirect (eg.
injury from car accidents resulting from poorly drained roadways).
A measure of Public Safety or Risk is often defined relating to flood depth and/or flood velocity. In
this investigation, safety criteria have been adopted using velocity and depth criteria as defined by
Melbourne Water (as instructed by Council). The criteria are defined in Table 4-5 below. The
quantity RISK is defined as:
RISK = maximum ( Velocity x Depth , Depth )
Table 4-5 Hazard Categories
Risk Category Criteria
Low RISK ≤ 0.4
Moderate 0.4 < RISK ≤ 0.8
High RISK > 0.8
EXISTING CONDITIONS 4-8
K:\INFRA_MGMT\RW\FLOOD STUDIES\RIPPLESIDE CAT FS\8. FINAL DOCS - MAPS\R.W00201.004.01.FINALREPORT.DOC 6/8/10 13:08 4-8 O C E A N I C S A U S T R A L I A
Within the catchment of Rippleside RISK is presented for the existing case (related to the 100 year
design event) in Figure 4.5. The figure indicates that areas of high and unacceptable RISK are
limited to flooded areas of significant depth inundation. Areas of particular concern are:
• Lantana Ave
• Grace McKellar
• Golf Course areas
• Lily Street
• Retarding basins upstream of Weddell Road
• Baxter Road Retarding Basin
4.6 Flooding Issues
The design flood modelling has illustrated a number of flood related issues for investigation.
Residents within the area have previously identified many of these issues. Figure 4.6 below identifies
the key flooding issues for which subsequent mitigation options will seek to minimise.
1 Flooding in Colville Ct
2 Overland flow through Bayview Parade properties
3 Overland flow through Lily St properties
4 Flooding Behind Railway in Lantana Ave and Marlo St
5 Flooding through Montgomery Street properties
6 Flooding along Hepner Place
7 Overland flow along The Fairway
8 No increase in Flooding at Baxter Road
The identification of these issues leads to the preparation of mitigation options. These are presented in
the next section.
It should be noted that:
• Floods greater than the one percent flood can occur. During such floods an area greater than that
shown would be inundated. Conversely properties within the area shown can be affected by
floods of lesser magnitude.
• Local flooding of other areas, or in excess of levels shown, may occur. The extent of flooding
shown relates to flooding from mapped reaches of Council's drainage systems only, and does not
adjacent catchments or private drainage systems.
• Local increases in flood levels, depths and/or velocities shown may result from local factors such
as drain blockages, and local obstructions to overland flows such as fences, buildings and cars.
EXISTING CONDITIONS 4-9
K:\INFRA_MGMT\RW\FLOOD STUDIES\RIPPLESIDE CAT FS\8. FINAL DOCS - MAPS\R.W00201.004.01.FINALREPORT.DOC 6/8/10 13:08 4-9 O C E A N I C S A U S T R A L I A
EXISTING CONDITIONS 4-10
K:\INFRA_MGMT\RW\FLOOD STUDIES\RIPPLESIDE CAT FS\8. FINAL DOCS - MAPS\R.W00201.004.01.FINALREPORT.DOC 6/8/10 13:08 4-10 O C E A N I C S A U S T R A L I A
EXISTING CONDITIONS 4-11
K:\INFRA_MGMT\RW\FLOOD STUDIES\RIPPLESIDE CAT FS\8. FINAL DOCS - MAPS\R.W00201.004.01.FINALREPORT.DOC 6/8/10 13:08 4-11 O C E A N I C S A U S T R A L I A
EXISTING CONDITIONS 4-12
K:\INFRA_MGMT\RW\FLOOD STUDIES\RIPPLESIDE CAT FS\8. FINAL DOCS - MAPS\R.W00201.004.01.FINALREPORT.DOC 6/8/10 13:08 4-12 O C E A N I C S A U S T R A L I A
EXISTING CONDITIONS 4-13
K:\INFRA_MGMT\RW\FLOOD STUDIES\RIPPLESIDE CAT FS\8. FINAL DOCS - MAPS\R.W00201.004.01.FINALREPORT.DOC 6/8/10 13:08 4-13 O C E A N I C S A U S T R A L I A
EXISTING CONDITIONS 4-1
K:\INFRA_MGMT\RW\FLOOD STUDIES\RIPPLESIDE CAT FS\8. FINAL DOCS - MAPS\R.W00201.004.01.FINALREPORT.DOC 6/8/10 13:08 4-1 O C E A N I C S A U S T R A L I A
MITIGATION ASSESSMENT 5-1
K:\INFRA_MGMT\RW\FLOOD STUDIES\RIPPLESIDE CAT FS\8. FINAL DOCS - MAPS\R.W00201.004.01.FINALREPORT.DOC 6/8/10 13:08 5-1 O C E A N I C S A U S T R A L I A
5 MITIGATION ASSESSMENT
Review of the existing flood situation in Rippleside has identified a number of significant flooding
issues. In this section drainage augmentation options to address these issues are evaluated.
5.1 Mitigation Option Elements
Figure 5.2 below presents the various mitigation option elements tested at Rippleside. Following
consultation with the City of Greater Geelong a range of option elements were developed. The
following describes 12 of the elements tested (selected as practical options for addressing individual
flooding issues). A brief rationale behind their development is included.
0 Do Nothing
The “Do Nothing” or maintain the status quo option needs to be considered as a base from
which comparisons can be made.
1 Lily Street – Augment pipe system along the length of Lily Street
This option is aimed at addressing flooding issues in Lily Street and potentially in the
Bayview Parade area. Pipes located under Lily St as locating the pipes under the drainage line
would require placement through properties with residences (some as slab on ground)
1a Lily Street – Augment pipe system in lower Lily Street only
The most sever flooding in Lily Street is at the lower end. This option to address the most
severe flooding directly with possible follow on improvements in the upper system
2 Retarding Basin upstream of Lantana Ave
This option is designed to reduce/control the volume of floodwater entering the Lantana Ave
area from the upper catchment. Some redirection of upper cathcment flows in included to
minimise the depth of flooding in Lanatana Ave with possible follow on effects downstream
in Montgomery Ave and Ballarat Rd
3 Upgrade pipe capacity under Ballarat Rd
This option is to directly address the lack of capacity under Ballarat Rd with follow on effects
at Montgomery Ave
4 Upgrade pipe capacity under Hepner Pl
This option is to address flooding in Hepner Place due to exceeded pipe capacity.
4a Upgrade pipe capacity under Hepner Pl and add Retarding Basin below Hepner Pl
Increasing flow conveyance in Hepner Pl may increase flooding in downstream areas. This
option is aimed at reducing any such adverse impacts
5 Retarding Basin upstream of Hepner Place
An alternative to Option 4/4a. Construction of a retarding basin upstream of Hepner Place in
the Golf Course to reduce/control flood flows along Hepner Place
6 Pipe upgrade through Grace McKellar
An attempt to reduce flooding in the Grace McKellar property by increasing the capacity of
the underground system. Includes pipe upgrades under Ballarat Rd.
7 Retarding Basin in Hurst Reserve
This option designed to reduce/control overland flood flows through the Bayview Parade
area. Some excavation of the park is included to maximise storage
8 Pipe upgrade along The Fairway
Flood flows along The Fairway restrict access to and from properties in the street and pose a
MITIGATION ASSESSMENT 5-2
K:\INFRA_MGMT\RW\FLOOD STUDIES\RIPPLESIDE CAT FS\8. FINAL DOCS - MAPS\R.W00201.004.01.FINALREPORT.DOC 6/8/10 13:08 5-2 O C E A N I C S A U S T R A L I A
public safety risk. This option is designed to minimise that risk by providing additional
underground capacity.
9 Upgrade pipe capacity from Lantana Ave through to Ballarat Rd
This option designed to address flooding issues in the Lantana Ave/Montgomery Ave area
and at Ballarat Rd.
Each of these elements has various impacts on the existing flood characteristics of Rippleside.
Appendix B illustrates the flooding impact graphically as an increase or decrease in flood level
resulting from the hydraulic influence of each element.
The floor level survey data has been integrated with the option assessment. Of the 130 properties that
were surveyed, comparisons of flood and floor levels indicate that 21 buildings are inundated above
floor level in the 100y design event. Only 9 floors are inundated by greater than 0.1m. Table 5-1
below indicates the relief provided to relevant flooded floors by each of the elements tested. In the
table, Floors Affected means the number of floors flooded in the existing case for which the element
is attempting to provide relief. Floors Relieved is the number of those floors for which relief is
provided. Elsewhere indicates secondary flood effects (positive or negative) of the option.
Within the catchment there are two areas where flooding is of particular concern due to the frequency
of flooding (from resident complaints) and the severity of the depth of flooding leading t a significant
public safety risk. These areas are:
• Drainage line parallel to Lily Street
• Lantana Ave through to Ballarat Rd
In both cases only a limited number of properties are inundated above floor level for the 100y design
event.
Lily Street
Although only 2 floors are inundated in the 100y event, 27 properties in this area are affected by
flooding. Pipe upgrades in Lily Street (Option 1 and 1a) appear to adequately address the flooding of
floors at units at the corner of Lily and Graham Streets and reduce flood levels in the area. However,
the gully line runs through many properties and complete flood relief through the provision of 100y
capacity drainage is unlikely to be practical.
Lantana Ave to Ballarat Rd
Flooding in this area is due primarily to the ponding of flood waters behind barriers. In Lantana Ave
the Railway line constrains flood conveyance while on Ballarat Rd, the road and the median strip
prevent adequate flood conveyance. In total, some 30 properties are affected with 5 properties
inundated above floor level.
Options 2, 3, 6 and 9 all provide differing mechanism for flood relief. However, in each case, flood
levels reduce below floor level for only 2 of the properties flood affected above floor level.
MITIGATION ASSESSMENT 5-3
K:\INFRA_MGMT\RW\FLOOD STUDIES\RIPPLESIDE CAT FS\8. FINAL DOCS - MAPS\R.W00201.004.01.FINALREPORT.DOC 6/8/10 13:08 5-3 O C E A N I C S A U S T R A L I A
Table 5-1 Effect of Options on Existing Flooding
Case Floors Affected Floors Relieved Elsewhere
1. Lily St Pipe Upgrade 2 2 Increase in flood
levels in Baxter
Rd RB
1a. Lower Lily St Pipe Upgrade 2 2 Increase in flood
levels in Baxter
Rd RB
2. Lantana Ave Retarding Basin 5 2 1 additional floor
relieved
3. Ballarat Rd Pipe Upgrade 5 2
4. Hepner Pl Pipe Upgrade 2 2 Increase in flood
levels in Baxter
Rd RB
4a. Hepner Pl Pipe Upgrade and
Weddell Road RB
2 2
5. Hepner Pl Retarding Basin 2 2
6. Grace McKellar Pipe Upgrade 6 2 1 additional floor
relieved
7. Hurst Reserve Retarding Basin 5 1 4 additional floors
flooded
8. The Fairway Pipe Upgrade 0 0
9. Lantana Ave – Ballarat Rd Pipe
Upgrade
5 3
MITIGATION ASSESSMENT 5-4
K:\INFRA_MGMT\RW\FLOOD STUDIES\RIPPLESIDE CAT FS\8. FINAL DOCS - MAPS\R.W00201.004.01.FINALREPORT.DOC 6/8/10 13:08 5-4 O C E A N I C S A U S T R A L I A
5.2 Preferred Approach for Augmentation
From review of the affect of each of the flood options a combination of elements was identified that
best addresses flooding issues in the Rippleside catchment. Figure 5.3 below illustrates the combined
elements, as listed below:
1a Lily Street – Augment pipe system in lower Lily Street (2 x 1350 RCP x 150m)
4a Upgrade pipe capacity under Hepner Place (1 x 1500 RCP x 25m, 2 x 1200 RCP x 235m,
2 x 1350 RCP x 35m) and add Retarding Basin below Hepner Place
6 Pipe upgrade through Grace McKellar (1 x 1050 RCP x 70m, 1 x 1200 RCP x 70m,
2 x 1050 RCP x 130) and under Ballarat Rd (4 x 1050 RCP x 20m, 4 x 1200 RCP x 20m)
8 Pipe upgrade along The Fairway (2 x 900 RCP x 380m)
The retarding basin proposed below Hepner place is designed with a bund wall set to a level of
14.5m AHD. The design capacity at full level is 15,850m3. The storage curve for the retarding basin
is shown in Figure 5.1 below
12
12.5
13
13.5
14
14.5
15
0 5000 10000 15000 20000
Storage (m3)
Wa
ter
Le
ve
l (m
AH
D)
Figure 5.1 Weddell Road Retarding Basin Storage Characteristics
Existing Case design flow information is provided in Appendix D.
Figure 5.4 displays the inundation extent for the design 100y event for the preferred combination of
options. Complete mapping for the preferred case for the 5y, 10y, 20y, 50y and 100y design flood
events is provided on separate plans.
Of the 21 properties that experience flooding above floor level in the 100y design event the
augmentation relieves the threat to only 7. Properties that remain likely to be inundated in the 100y
design event are shown in Figure 5.5.
MITIGATION ASSESSMENT 5-5
K:\INFRA_MGMT\RW\FLOOD STUDIES\RIPPLESIDE CAT FS\8. FINAL DOCS - MAPS\R.W00201.004.01.FINALREPORT.DOC 6/8/10 13:08 5-5 O C E A N I C S A U S T R A L I A
For the properties in the Grace McKellar and Montgomery Ave areas it is likely that sub-scale
features will dominate local flooding behaviour and that above floor level inundation will not occur in
the existing or preferred cases. This is also likely to be true also for the property in Calvert St.
None of the mitigation options assessed adequately deals with flooding in the Colville Ct area.
Mitigation options further upstream (outside the study area) may need to be employed to reduce the
threat of flooding in these areas.
5.3 Flood Hazard Mapping
Figure 5.6 illustrates flood hazard following the introduction of the augmentation scheme. As with
the existing case, areas of high and unacceptable risk are limited to those areas of significant flood
inundation depth. Areas that remain categorised as high risk are:
• Lantana Ave
• Golf Course areas
• Retarding basins upstream of Weddell Road
• Baxter Road Retarding Basin
Significantly, high risk areas in Lily Street and through Grace McKellar have been reduced as a result
of the augmentation works.
5.4 Other Impacts
Any drainage augmentation scheme will have other impacts beyond those directly associated with
flooding. Most apparent are those impacts that effect the community and environment during
construction works.
Social impacts during construction can include disruption to traffic flows and significant
inconvenience for residents in those areas that are nearest to the proposed works. Where works are
proposed in industrial or commercial areas, there may be impacts to trade or manufacture for the
companies in the area as a result of restricted access for larger vehicles due to, for example, road
closures.
For this augmentation scheme, such social impacts to residential areas would be limited to those
works associated with the Lily Street upgrade. The commercial areas in Hepner Place could also be
impacted during construction works. Careful management of the construction activities along with
planning of the timing of such works to coincide with lower traffic volumes will assist in minimising
disruptions. Residents would also need to be informed of the impending likely disruptions to allow
for time for the resident to implement any compensatory action (eg commercial business stocking
up).
Works to increase the drainage capacity under Ballarat Rd could have a major impact on the
community through disruption to traffic flows. As Ballarat Rd is the responsibility of VicRoads,
management and construction of the augmentation works in this area may also be the responsibility of
VicRoads.
MITIGATION ASSESSMENT 5-6
K:\INFRA_MGMT\RW\FLOOD STUDIES\RIPPLESIDE CAT FS\8. FINAL DOCS - MAPS\R.W00201.004.01.FINALREPORT.DOC 6/8/10 13:08 5-6 O C E A N I C S A U S T R A L I A
The environmental impacts associated with construction site activities are well documented and relate
primarily to impacts associated with uncontrolled export of sediment from the construction site, either
as dust or in stormwater runoff. Sediment control and construction site environmental management
are now recognised elements of the management of any construction site. A range of management
strategies are available for the identification of environmental threats and values associated with the
construction site activities as well as methods to minimise any such impacts (eg silt screens and
siltation basins).
Minor earthworks would be required in areas where augmentation of the underground pipe system is
required. More significant earthworks would be required for the construction of the retarding basin
below Hepner Place. In all cases, recognised environmental management and sediment control
techniques would need to be employed throughout the construction phase.
The social and environmental impacts of drainage augmentation construction activities are generally
well known and predictable. Through adequate management their impact is generally low.
MITIGATION ASSESSMENT 5-7
K:\INFRA_MGMT\RW\FLOOD STUDIES\RIPPLESIDE CAT FS\8. FINAL DOCS - MAPS\R.W00201.004.01.FINALREPORT.DOC 6/8/10 13:08 5-7 O C E A N I C S A U S T R A L I A
MITIGATION ASSESSMENT 5-8
K:\INFRA_MGMT\RW\FLOOD STUDIES\RIPPLESIDE CAT FS\8. FINAL DOCS - MAPS\R.W00201.004.01.FINALREPORT.DOC 6/8/10 13:08 5-8 O C E A N I C S A U S T R A L I A
MITIGATION ASSESSMENT 5-9
K:\INFRA_MGMT\RW\FLOOD STUDIES\RIPPLESIDE CAT FS\8. FINAL DOCS - MAPS\R.W00201.004.01.FINALREPORT.DOC 6/8/10 13:08 5-9 O C E A N I C S A U S T R A L I A
MITIGATION ASSESSMENT 5-10
K:\INFRA_MGMT\RW\FLOOD STUDIES\RIPPLESIDE CAT FS\8. FINAL DOCS - MAPS\R.W00201.004.01.FINALREPORT.DOC 6/8/10 13:08 5-10 O C E A N I C S A U S T R A L I A
MITIGATION ASSESSMENT 5-11
K:\INFRA_MGMT\RW\FLOOD STUDIES\RIPPLESIDE CAT FS\8. FINAL DOCS - MAPS\R.W00201.004.01.FINALREPORT.DOC 6/8/10 13:08 5-11 O C E A N I C S A U S T R A L I A
ECONOMIC ASSESSMENT 6-1
K:\INFRA_MGMT\RW\FLOOD STUDIES\RIPPLESIDE CAT FS\8. FINAL DOCS - MAPS\R.W00201.004.01.FINALREPORT.DOC 6/8/10 13:08 6-1 O C E A N I C S A U S T R A L I A
6 ECONOMIC ASSESSMENT
An economic evaluation of the proposed augmentation has been undertaken to consider the
benefit/cost of the proposed works and to assess possible funding mechanism available to the City of
Greater Geelong.
6.1 Flood Damages Assessment
Flood damage assessment is an important component of any flood plain management framework.
This type of analysis enables the flood plain manager to gain an understanding of the magnitude of
assets under threat each year by flooding.
6.1.1 Stage Damage Curves
ANUFLOOD residential stage damage curves were used for this flood damage assessment. These
curves were sourced from the RAM (Rapid Appraisal Method) report (NRE, 2000). The non-
residential stage-damage curves, also ANUFLOOD curves, were sourced from a journal paper by
Smith (1994) “Flood Damage Estimation – A review of urban stage-damage curves and loss
functions”. The curves used are in 1993-dollar terms and have been indexed to 2000 units using a
CPI factor of 1.14.
ANUFLOOD has 15 non-residential stage damage curves. For each building size (small, medium
and large), there are 5 curves representing 5 value classes. As the Rippleside Study considered only 3
value classes (poor, average and good) the ANUFLOOD curves were reduced to 3 value classes per
building size by averaging the 2 lowest and the 2 highest curves. This reduces the number of curves
used for the non-residential damage assessment from 15 to 9.
For the Large non-residential curves, a building size in m2 is required as the damage values are given
in $/m2. As this data was not collected in the Rippleside survey, it was assumed that the average large
non-residential building size was 1000m2. This assumption is consistent with the RAM classification
of buildings as large if the area exceeds 1000m2.
It is widely recognised and documented in the RAM report (NRE, 2000) that the ANUFLOOD
curves underpredict flood damages. Increases of 60% have been applied to both the residential and
non-residential curves as recommended in RAM.
Ratios to convert Potential damages to Actual damages are used as per the recommendations from the
RAM report. That is, for a relatively unprepared community with less than 12 hours warning time a
factor (ratio) of 0.7 is used to reduce the potential damages to actual damages. Flood damages were
calculated from water surface profiles generated for the 5, 10, 20, 50 and 100 year design events.
6.1.2 Outside Buildings
Damages to equipment outside of the building are not included in the stage damage curves used.
Such damages may include damage to fences, driveways, lower level laundries, outdoor equipment
etc. The loss of plants, lawn, landscaping is difficult to quantify and is not included in this but rather
should be included in the intangibles. Thus, an estimate of “ground equipment damages” has been
ECONOMIC ASSESSMENT 6-2
K:\INFRA_MGMT\RW\FLOOD STUDIES\RIPPLESIDE CAT FS\8. FINAL DOCS - MAPS\R.W00201.004.01.FINALREPORT.DOC 6/8/10 13:08 6-2 O C E A N I C S A U S T R A L I A
made as a function of ground level inundation. That is, assume a sliding scale from $0 to $1000 with
$1000 being the maximum. The full $1000 damage is experienced once the flood level has reached
the floor level of the building. The sliding scale works on the difference between the ground level
and the floor level (eg a ground level of 1m, floor level of 2m, flood level of 1.5m receives ground
equipment damages of $500).
Ground damages for properties where floodwaters enter the property for which there is no
information on floor level (as it has been assumed not to overtop floorlevel) has been arbitrarily set at
the average ground damages cost for properties where floor level surveys have occurred.
6.1.3 Damages
Using the ANUFLOOD curves for the catchment of Rippleside the AAD (Average Annual Damage)
has been calculated to be $63,000 for the existing situation.
This Damages Assessment has been integrated with a “board brush” mitigation option assessment. In
this manner the cost benefit of measures likely to reduce the impact of flooding on the community
within Rippleside can be assessed. For the preferred approach the AAD has been calculated as
$59,000.
Figure 6.1 illustrates the event based flood damage curves.
Rippleside Flood Damages
Existing and Augmented Condition
$-
$100
$200
$300
$400
$500
$600
$700
$800
0% 5% 10% 15% 20% 25% 30% 35% 40% 45% 50%
AEP (%)
Da
ma
ge
s (
$1
00
0)
Existing
Augmented
Limit of Flood Data. Curves formed by
extrapolation beyond this line
Figure 6.1 Rippleside Flood Damage Curves
ECONOMIC ASSESSMENT 6-3
K:\INFRA_MGMT\RW\FLOOD STUDIES\RIPPLESIDE CAT FS\8. FINAL DOCS - MAPS\R.W00201.004.01.FINALREPORT.DOC 6/8/10 13:08 6-3 O C E A N I C S A U S T R A L I A
6.2 Benefit Cost Ratio
Benefit Cost Ratio (BCR) is a measure of the benefit of implementing a project, in consideration of
the direct and tangible costs. A BCR greater than 1 indicates that the total benefit received over the
lifetime of the project exceeds the cost of undertaking the works. A BCR less than 1 indicates that the
costs exceed the benefits over the lifetime of the project.
6.2.1 Cost
To calculate BCR an estimate of undertaking the construction works for the augmentation is required.
The City of Greater Geelong has provided indicative costs for pipe augmentation works as presented
in Table 6-1 below.
Table 6-1 Guideline Per metre Costs for Pipe Augmentation Works
Pipe Size Works Under
Unpaved Areas Works Under Roads Areas
(mm) ($ / linear m) ($ / linear m)
900 $350 $650
1050 $450 $800
1200 $500 $900
1350 $700 $1,150
1500 $850 $1,350
1650 $1,050 $1,600
Where pipe augmentation works include the provision of parallel pipes, rather than adopting a cost of
twice the linear cost, a saving of 20% per m is applied as an estimate to account for construction
savings.
Additionally the cost of works to create a Retarding Basin (option 4a) below Hepner Place are
estimated based on the length of the bund wall required, in this case approx 150m. An estimated cost
of $250 per linear metre of bund wall has been adopted. Maintenance costs for the basin have not
been included in the calculations.
The estimated cost of works for the augmentation is shown in Table 6-2 below with a detailed
breakdown of Costs in Table 6-3. Note that a contingency amount, typically 10-20% of the total
project cost, has not been included in the cost estimate.
Table 6-2 Estimated Cost of Augmentation Works
Option Element Cost ($)
Option 1a $ 350,000.00
Option 4a $ 636,250.00
Option 6 $ 329,500.00
Option 8 $ 504,000.00
Total $ 1,819,750.00
ECONOMIC ASSESSMENT 6-4
K:\INFRA_MGMT\RW\FLOOD STUDIES\RIPPLESIDE CAT FS\8. FINAL DOCS - MAPS\R.W00201.004.01.FINALREPORT.DOC 6/8/10 13:08 6-4 O C E A N I C S A U S T R A L I A
Table 6-3 Detailed Breakdown of Cost Estimate
Option Item No Length/Area Unit Rate Amount Sum
Option 1a $ 350,000.00
Supply, trench, bed, lay, joint, backfill, compact and reinstate surface for 2x1350 RCP 2 150 m 1150 345000
Pits at 100m intervals 2 ea 2500 5000
Acquire reserve / easement Ha 150000
Option 4a $ 636,250.00
Supply, trench, bed, lay, joint, backfill, compact and reinstate surface for 1x1500 RCP 1 25 m 1350 33750
Supply, trench, bed, lay, joint, backfill, compact and reinstate surface for 2x1200 RCP 2 235 m 900 423000
Supply, trench, bed, lay, joint, backfill, compact and reinstate surface for 2x1350 RCP 2 35 m 700 49000
Pits at 100m intervals 3 ea 2500 7500
Acquire reserve / easement at end of Hepner Place 0.02 Ha 150000 3000
Retarding Basin Construction Costs 1 8000 m3 15 120000
Option 6 $ 329,500.00
Supply, trench, bed, lay, joint, backfill, compact and reinstate surface for 1x1050 RCP 1 70 m 450 31500
Supply, trench, bed, lay, joint, backfill, compact and reinstate surface for 1x1200 RCP 1 70 m 500 35000
Supply, trench, bed, lay, joint, backfill, compact and reinstate surface for 2x1050 RCP 2 130 m 450 117000
Supply, trench, bed, lay, joint, backfill, compact and reinstate surface for 4x1050 RCP 4 20 m 800 64000
Supply, trench, bed, lay, joint, backfill, compact and reinstate surface for 4x1200 RCP 4 20 m 900 72000
Pits at 100m intervals 4 ea 2500 10000
Acquire reserve / easement Ha 150000
Option 8 $ 504,000.00
Supply, trench, bed, lay, joint, backfill, compact and reinstate surface for 2x900 RCP 2 380 m 650 494000
Pits at 100m intervals 4 ea 2500 10000
Acquire reserve / easement Ha 150000
Project $1,819,750.00
ECONOMIC ASSESSMENT 6-5
K:\INFRA_MGMT\RW\FLOOD STUDIES\RIPPLESIDE CAT FS\8. FINAL DOCS - MAPS\R.W00201.004.01.FINALREPORT.DOC 6/8/10 13:08 6-5 O C E A N I C S A U S T R A L I A
6.2.2 Benefit
The benefit of the augmentation works is the difference between the average annual damages before
and after the augmentation represented as a Present Value over the design lifetime of the project. The
Present Value (PV) of the benefit was calculated using a discount rate of 6% and a project life of 30
years, as suggested by RAM, using the following formula.
t
t
ii
iaPV
)1(
1)1(
+
−+=
Where a is the AAD benefit, i is the discount rate and t is the term.
The AAD benefit is $4,000 ($63,000 - $59,000). The Present Value of this benefit over a 30 year
lifetime is $55,000. RAM suggests that a planning and discount horizon of 30 years be adopted for
assessment of economic benefits, even though there may be longer term benefits. It should be noted
that due to the asymptotic nature of the calculation of Present Value, use of a longer term does not
provide significant enhancement to the calculation of benefit (eg. PV for $4000 over a 50 year term at
6% discount rate is $63,000)
6.2.3 Benefit Cost
The Benefit Cost Ratio for the augmentation works is $55,000 / $1.74M = 0.03. This is an extremely
low BCR.
The BCR is low because the AAD benefit is low ($4,000). The benefits gained by the augmentation
works are only recognised over a few properties and provide benefit only in the less frequent events
(>20y return period).
6.3 Intangible Damages/Benefits
Floods impose intangible damages on the community. These include the emotional, mental and
physical ill health of the victims of the flood. It is always difficult to assess these damages in terms of
financial loss or cost but is clear that reduction in frequency or severity of flooding will have
considerable benefit to the well being of the community. This could in turn result in follow-on effects
relating to greater community support and acceptance strategies for flood mitigation proposed by
Council.
The emotional costs of flooding can persist for many years. A survey of flood victims undertaken 15
months following the 1974 floods of the Brisbane River found that approximately ¼ of victims had
not recovered from the emotional trauma of the flooding (Chamberlain, et al 1981). Hardest hit were
elderly members of the community and others of lower socio-economic status.
Communities that are prepared and aware of the risks of flooding tend to suffer less financial and
emotional hardship than those that are poorly prepared. The calculation of financial loss specifically
takes into consideration community preparedness in estimating damages. Damages in an unprepared
community can be as much as twice that of a prepared community. It is reasonable to assume that
intangible damages will react in a similar fashion with respect to community preparedness.
ECONOMIC ASSESSMENT 6-6
K:\INFRA_MGMT\RW\FLOOD STUDIES\RIPPLESIDE CAT FS\8. FINAL DOCS - MAPS\R.W00201.004.01.FINALREPORT.DOC 6/8/10 13:08 6-6 O C E A N I C S A U S T R A L I A
Loss of life in floods is remarkably low in Australia. For example, in the 1974 Brisbane floods 30,000
homes were inundated with the loss of only 12 lives. Typically loss of life in floods is due to
accidents such as road accidents or electrocution rather than people being swept away.
Floods can result in significant emotion stress within the community. Education and awareness, along
with suitable flood relief, provide an effective mechanism for the reduction in such intangible
damages.
6.4 Funding Mechanisms – Special Rates and Charges
Funding mechanisms available to Council for the upgrade of drainage infrastructure typically fall into
one of two categories:
• Private Benefit for which a user-charge typically applies associated with a direct link between
the infrastructure provided and the benefit received
• Public Benefit is related to infrastructure that provides a benefit to the wider community
throughout the municipality
Clearly, augmentation works undertaken within the catchment of Rippleside are for the direct benefit
of those residents with an existing flooding problem or threat. There exists an indirect benefit to those
residents within the catchment associated with increased trafficability of roads subject to flooding as
well as public health and safety issues and other intangible benefits.
Special Rates and Charges are the typical mechanism for funding of drainage works. Section 163 of
the Local Government Act 1989 sets out the provisions for the issue of a special rate, charge or
combination of these. The purpose of the rate or charge is to recoup costs associated with the
provision of infrastructure. The charge is typically a one-off payment while a rate is an incremental
payment made over a number of years.
Recent decisions handed down at the Administrative Appeals Tribunal suggests a more confined
application of special rates and charges particularly in relation to drainage augmentation schemes. In
essence the Ball decision (Appeal No 1993/37685) concluded:
• A special rate or charge can only be levied where a special benefit is received
• The special benefit must be received by the land owners (rather than the property)
• In this context, a special benefit was recognised by the Tribunal as an increase in property
values.
That is, while every property in the catchment receives, to a greater or lesser degree, a benefit from
the drainage augmentation works, that benefit does not translate into an increase in property values
and therefore not a special benefit. Thus, funding via special rates and charges is not applicable.
Furthermore, the Tribunal ruled that where:
… properties are already drained to lawful points of discharge and the provision of
additional capacity in the main drainage system, although obviously required to drain
the entire catchment, will not provide a special benefit to them as owners of their land.
Appeal No 1993/37685 pg 7
ECONOMIC ASSESSMENT 6-7
K:\INFRA_MGMT\RW\FLOOD STUDIES\RIPPLESIDE CAT FS\8. FINAL DOCS - MAPS\R.W00201.004.01.FINALREPORT.DOC 6/8/10 13:08 6-7 O C E A N I C S A U S T R A L I A
This would indicate that drainage augmentation works for any undersized drainage system does not
provide a special benefit to property owners in the catchment and therefore the ruling would imply
that in the case of the Rippleside Main Drain Augmentation funding cannot be sourced via special
rates and charges.
However, several other related rulings have occurred since the 1993 AAT decision regarding Ocean
Grove. Some of the decisions take an alternative interpretation of the application of Special Rates and
Charges to drainage infrastructure projects.
Additional legal advice in this regard has been sought (See Appendix C).
6.5 Development Control in Flood Prone Areas
The Victorian Planning Provision and the City of Greater Geelong Planning Scheme provide a
number of mechanisms, via zones and overlays, for the control of development in flood prone areas.
The zones and overlays that relate to flooding include:
• Urban Floodway Zone (UFZ)
• Floodway Overlay (FO)
• Rural Floodway Overlay (RFO)
• Land Subject to Inundation Overlay (LSIO)
• Special Building Overlay (SBO)
Overlays are shown on the planning scheme in addition to zonings and apply in addition to the
provisions of the zone. The application of the appropriate overlay is set out in the Geelong Planning
Scheme documentation as follows:
Applying Zones and Overlays
• Applying the Urban Floodway Zone to locations in the urban areas that are high
hazard and active floodways and where strict control over land use is required.
• Applying the Floodway Overlay to locations in the urban areas that are high
hazard and active floodways.
• Applying the Rural Floodway Overlay to locations in the rural areas that are
high hazard and active floodways.
• Applying the Land Subject to Inundation Overlay to locations in both the
urban and rural areas that are subject to periodic inundation but which are not
high hazard nor active floodplains.
• Applying the Special Building Overlay to land in urban areas that are subject to
inundation by surcharge flows from urban drainage systems, such as Barwon
Heads and Corio.
In the catchment of Rippleside, the Special Building Overlay can be used by Council as a method to
control development in flood prone areas, particularly where the flooding is as a result of surcharged
underground drainage (as is the case here).
ECONOMIC ASSESSMENT 6-8
K:\INFRA_MGMT\RW\FLOOD STUDIES\RIPPLESIDE CAT FS\8. FINAL DOCS - MAPS\R.W00201.004.01.FINALREPORT.DOC 6/8/10 13:08 6-8 O C E A N I C S A U S T R A L I A
6.6 Discussion
AAD is calculated from an integral of the Damage Curves (Figure 6.1). Although considerable
benefit from less frequent (and more severe) floods has been achieved, there is no discernible change
in the damage curves for events more frequent than 20 years. Properties in the flow path as “slab on
ground” do not receive any benefit from the augmentation works. Benefits to these properties would
significantly improve the Benefit Cost Ratio.
Benefits to these properties would be via mechanism other than drainage augmentation works. The
most appropriate mechanisms would appear to be:
• Individual flood protection (levees etc)
• Buy back of the property (with a view to creation of flood conveyance)
The suitability of each mechanism would need to be investigated on a case by case basis, which is
beyond the scope the current investigation. Nevertheless, a cursory review of the available survey
information and site inspection have been undertaken to provide some guidance in this regard. With
reference to Figure 6.2, it is considered that
• units at 257 Church Street would benefit from individual flood protection
• flood prone properties in the Montgomery Ave area could fall under a buyback scheme to create
a flood conveyance and/or storage in this critical area within the catchment
ECONOMIC ASSESSMENT 6-9
K:\INFRA_MGMT\RW\FLOOD STUDIES\RIPPLESIDE CAT FS\8. FINAL DOCS - MAPS\R.W00201.004.01.FINALREPORT.DOC 6/8/10 13:08 6-9 O C E A N I C S A U S T R A L I A
STORMWATER MANAGEMENT PLAN 7-1
K:\INFRA_MGMT\RW\FLOOD STUDIES\RIPPLESIDE CAT FS\8. FINAL DOCS - MAPS\R.W00201.004.01.FINALREPORT.DOC 6/8/10 13:08 7-1 O C E A N I C S A U S T R A L I A
7 STORMWATER MANAGEMENT PLAN
There have long been public health issues relating to the discharge of stormwater from the catchment
to the waters of Corio Bay at Rippleside Beach. Chiefly, these relate to high E. coli counts at the
beach leading to frequent beach closures. In addition, issues relating to the control of catchment
runoff containing a high nutrient load are also of concern.
Stormwater management and the preparation of a Stormwater Management Plan were originally
within the scope of this Drainage Augmentation Project. However, In recognition of the importance
of these issues, Council expanded the scope of the Stormwater Management component of the study
and released this as a separate brief.
WBM have undertaken preparation of a stormwater management plan as a separate project for
Council. However, in recognition of the linkages between stormwater management and flooding
cross-over between the two projects has occurred to ensure consistency between the two projects, as
follows:
• Stormwater modelling assessments for the design of wetlands and other stormwater control
features utilise equivalent hydrological and hydraulic modelling components. Hydraulic model
outputs are used to provide hydraulic boundary conditions for the stormwater management
modelling procedures.
• Stormwater control features in the main flood flow path are included in the hydraulic
assessments to ensure the features do not exacerbate existing flooding problems in the
catchment.
These feedback loops provide the flooding and stormwater assessments with a fully integrated
assessment of the impacts of proposed works in the catchment.
CONCLUSION 8-1
K:\INFRA_MGMT\RW\FLOOD STUDIES\RIPPLESIDE CAT FS\8. FINAL DOCS - MAPS\R.W00201.004.01.FINALREPORT.DOC 6/8/10 13:08 8-1 O C E A N I C S A U S T R A L I A
8 CONCLUSION
The Rippleside Drainage Augmentation study provides a comprehensive evaluation of flooding threat
within the catchment. Key findings of the study are as follows:
• Areas in the catchment are prone to frequent flooding due to the typically undersized
underground drainage capacity and/or little or no overland flood flow conveyance capacity
• The 100y design flood event inundates 727 properties in the flood mapping area. Of these,
modelling indicates a total of 21 are inundated above flood level (9 with above floor level
inundation of greater than 0.1m).
• Within the flood mapping area, model results indicate inundation above floor level for 6
properties during the 20y design flood.
• Few options for significant reductions in flood levels at properties inundated above floor level
exist due to the age of the system and limited opportunity to provide additional overland
conveyance and storage capacity.
• The Average Annual Damage due to flooding in the Rippleside catchment has been calculated as
$63,000 for the existing case and $59,000 for the augmentation option with an Average Annual
Benefit of $4,000.
Note that the findings of this study and the conclusions above relate to flood modelling results within
the designated study area (See Figure 1.1). Flooding in other areas of the catchment may occur and as
such may influence that assessment of flood risk in the catchment as well as the assessment of
Average Annual Damages and Benefit.
SURVEY REPORT A-1
K:\INFRA_MGMT\RW\FLOOD STUDIES\RIPPLESIDE CAT FS\8. FINAL DOCS - MAPS\R.W00201.004.01.FINALREPORT.DOC 6/8/10 13:08 A-1O C E A N I C S A U S T R A L I A
APPENDIX A: SURVEY REPORT
MITIGATION OPTIONS – ELEMENT IMPACTS B-1
K:\INFRA_MGMT\RW\FLOOD STUDIES\RIPPLESIDE CAT FS\8. FINAL DOCS - MAPS\R.W00201.004.01.FINALREPORT.DOC 6/8/10 13:08 B-1O C E A N I C S A U S T R A L I A
APPENDIX B: MITIGATION OPTIONS – ELEMENT IMPACTS
The following figures provide an illustrative presentation of the impact of each flood mitigation option element
tested with respect to the 100y design flood event. Increases and decreases in peak flood level are presented.
Mitigation Option ImpactsElement 1 - Lily Street Pipe Upgrade
Figure B-1
OCEANICS AUSTRALIA
Lege
nd
0.5
- 0.
7 D
ecre
ase
0.3
- 0.
5 D
ecre
ase
0.1
- 0.
3 D
ecre
ase
No
Impa
ct
0.1
- 0.
3 In
crea
se
0.3
- 0.
5 In
crea
se
0.5
- 0.
7 In
crea
se
0.7
- 0.
9 In
crea
se
>0.9
Incr
ease
Mitigation Option ImpactsElement 1a - Lower Lily Street Pipe Upgrade
Figure B-1a
OCEANICS AUSTRALIA
Lege
nd
0.5
- 0.
7 D
ecre
ase
0.3
- 0.
5 D
ecre
ase
0.1
- 0.
3 D
ecre
ase
No
Impa
ct
0.1
- 0.
3 In
crea
se
0.3
- 0.
5 In
crea
se
0.5
- 0.
7 In
crea
se
0.7
- 0.
9 In
crea
se
>0.9
Incr
ease
Mitigation Option ImpactsElement 2 - Vines Road Retarding Basin
Figure B-2
OCEANICS AUSTRALIA
Lege
nd
0.5
- 0.
7 D
ecre
ase
0.3
- 0.
5 D
ecre
ase
0.1
- 0.
3 D
ecre
ase
No
Impa
ct
0.1
- 0.
3 In
crea
se
0.3
- 0.
5 In
crea
se
0.5
- 0.
7 In
crea
se
0.7
- 0.
9 In
crea
se
>0.9
Incr
ease
Mitigation Option ImpactsElement 3 - Pipe Upgrade Under Ballarat Rd
Figure B-3
OCEANICS AUSTRALIA
Lege
nd
0.5
- 0.
7 D
ecre
ase
0.3
- 0.
5 D
ecre
ase
0.1
- 0.
3 D
ecre
ase
No
Impa
ct
0.1
- 0.
3 In
crea
se
0.3
- 0.
5 In
crea
se
0.5
- 0.
7 In
crea
se
0.7
- 0.
9 In
crea
se
>0.9
Incr
ease
Mitigation Option ImpactsElement 4 - Pipe Upgrade Along Hepner Place
Figure B-4
OCEANICS AUSTRALIA
Lege
nd
0.5
- 0.
7 D
ecre
ase
0.3
- 0.
5 D
ecre
ase
0.1
- 0.
3 D
ecre
ase
No
Impa
ct
0.1
- 0.
3 In
crea
se
0.3
- 0.
5 In
crea
se
0.5
- 0.
7 In
crea
se
0.7
- 0.
9 In
crea
se
>0.9
Incr
ease
Mitigation Option ImpactsElement 4a - Pipe Upgrade Hepner Pl & Retarding Basin
Figure B-4a
OCEANICS AUSTRALIA
Lege
nd
0.5
- 0.
7 D
ecre
ase
0.3
- 0.
5 D
ecre
ase
0.1
- 0.
3 D
ecre
ase
No
Impa
ct
0.1
- 0.
3 In
crea
se
0.3
- 0.
5 In
crea
se
0.5
- 0.
7 In
crea
se
0.7
- 0.
9 In
crea
se
>0.9
Incr
ease
Mitigation Option ImpactsElement 5 - Retarding Basin Upstream of Hepner Pl
Figure B-5
OCEANICS AUSTRALIA
Lege
nd
0.5
- 0.
7 D
ecre
ase
0.3
- 0.
5 D
ecre
ase
0.1
- 0.
3 D
ecre
ase
No
Impa
ct
0.1
- 0.
3 In
crea
se
0.3
- 0.
5 In
crea
se
0.5
- 0.
7 In
crea
se
0.7
- 0.
9 In
crea
se
>0.9
Incr
ease
Mitigation Option ImpactsElement 6 - Pipe Upgrade Ballarat Rd and Grace McKellar
Figure B-6
OCEANICS AUSTRALIA
Lege
nd
0.5
- 0.
7 D
ecre
ase
0.3
- 0.
5 D
ecre
ase
0.1
- 0.
3 D
ecre
ase
No
Impa
ct
0.1
- 0.
3 In
crea
se
0.3
- 0.
5 In
crea
se
0.5
- 0.
7 In
crea
se
0.7
- 0.
9 In
crea
se
>0.9
Incr
ease
Mitigation Option ImpactsElement 7 - Retarding Basin Hurst Reserve
Figure B-7
OCEANICS AUSTRALIA
Lege
nd
0.5
- 0.
7 D
ecre
ase
0.3
- 0.
5 D
ecre
ase
0.1
- 0.
3 D
ecre
ase
No
Impa
ct
0.1
- 0.
3 In
crea
se
0.3
- 0.
5 In
crea
se
0.5
- 0.
7 In
crea
se
0.7
- 0.
9 In
crea
se
>0.9
Incr
ease
Mitigation Option ImpactsElement 8 - Pipe Upgrade The Fairway
Figure B-8
OCEANICS AUSTRALIA
Lege
nd
0.5
- 0.
7 D
ecre
ase
0.3
- 0.
5 D
ecre
ase
0.1
- 0.
3 D
ecre
ase
No
Impa
ct
0.1
- 0.
3 In
crea
se
0.3
- 0.
5 In
crea
se
0.5
- 0.
7 In
crea
se
0.7
- 0.
9 In
crea
se
>0.9
Incr
ease
Mitigation Option ImpactsElement 9 - Pipe Upgrade Lantana Ave to Ballarat Rd
Figure B-9
OCEANICS AUSTRALIA
Lege
nd
0.5
- 0.
7 D
ecre
ase
0.3
- 0.
5 D
ecre
ase
0.1
- 0.
3 D
ecre
ase
No
Impa
ct
0.1
- 0.
3 In
crea
se
0.3
- 0.
5 In
crea
se
0.5
- 0.
7 In
crea
se
0.7
- 0.
9 In
crea
se
>0.9
Incr
ease
SPECIAL RATES AND CHARGES – LEGAL ADVICE C-1
K:\INFRA_MGMT\RW\FLOOD STUDIES\RIPPLESIDE CAT FS\8. FINAL DOCS - MAPS\R.W00201.004.01.FINALREPORT.DOC 6/8/10 13:08 C-1O C E A N I C S A U S T R A L I A
APPENDIX C: SPECIAL RATES AND CHARGES – LEGAL ADVICE
DESIGN FLOW INFORMATION D-1
K:\INFRA_MGMT\RW\FLOOD STUDIES\RIPPLESIDE CAT FS\8. FINAL DOCS - MAPS\R.W00201.004.01.FINALREPORT.DOC 6/8/10 13:08 D-1O C E A N I C S A U S T R A L I A
APPENDIX D: DESIGN FLOW INFORMATION
DESIGN FLOW INFORMATION D-2
K:\INFRA_MGMT\RW\FLOOD STUDIES\RIPPLESIDE CAT FS\8. FINAL DOCS - MAPS\R.W00201.004.01.FINALREPORT.DOC 6/8/10 13:08 D-2O C E A N I C S A U S T R A L I A
Design Flows
Design flows for the 100, 50 and 20 year design events have been extracted from the model at each of
the augmentation option elements to provide information for future detailed design considerations.
Figure D1 shows the location of the extracted information. Table D-1 below summarises the design
event results and Figures D2-D5 present flow hydrographs for each event at each location.
Table D-1 Design Flow Summary
100y Design Flows
Lily Street Hepner Pl The Fairway Grace McKellar
Peak Time 1:15:00 1:35:00 0:55:00 1:30:00
Peak Flow 14.2 13.0 9.2 14.3
Overland 8.0 8.4 6.6 10.7
Underground 6.2 4.6 2.6 3.6
50y Design Flows
Lily Street Hepner Pl The Fairway Grace McKellar
Peak Time 1:10:00 1:25:00 1:00:00 1:20:00
Peak Flow 12.3 11.2 7.4 12.0
Overland 5.8 6.6 4.8 8.4
Underground 6.5 4.6 2.6 3.6
20y Design Flows
Lily Street Hepner Pl The Fairway Grace McKellar
Peak Time 0:50:00 1:35:00 1:00:00 1:20:00
Peak Flow 8.5 8.6 5.2 8.7
Overland 1.9 3.8 2.7 5.2
Underground 6.6 4.8 2.5 3.5
DESIGN FLOW INFORMATION D-3
K:\INFRA_MGMT\RW\FLOOD STUDIES\RIPPLESIDE CAT FS\8. FINAL DOCS - MAPS\R.W00201.004.01.FINALREPORT.DOC 6/8/10 13:08 D-3 O C E A N I C S A U S T R A L I A
DESIGN FLOW INFORMATION D-4
K:\INFRA_MGMT\RW\FLOOD STUDIES\RIPPLESIDE CAT FS\8. FINAL DOCS - MAPS\R.W00201.004.01.FINALREPORT.DOC 6/8/10 13:08 D-4 O C E A N I C S A U S T R A L I A
Figure D-2 100 Year Design Flow Hydrographs
Lily Street
-1
0
1
2
3
4
5
6
7
8
9
0:00:00 1:12:00 2:24:00 3:36:00 4:48:00
Time (Hours)
Flo
w (
cu
me
cs
)
Overland
Underground
Hepner Place
-1
0
1
2
3
4
5
6
7
8
9
0:00:00 1:12:00 2:24:00 3:36:00 4:48:00
Time (Hours)
Flo
w (
cu
me
cs
)
Overland
Underground
The Fairway
-1
0
1
2
3
4
5
6
7
0:00:00 1:12:00 2:24:00 3:36:00 4:48:00
Time (Hours)
Flo
w (
cu
me
cs
)
Overland
Underground
Grace McKellar
-2
0
2
4
6
8
10
12
0:00:00 1:12:00 2:24:00 3:36:00 4:48:00
Time (Hours)
Flo
w (
cu
me
cs
)
Overland
Underground
DESIGN FLOW INFORMATION D-5
K:\INFRA_MGMT\RW\FLOOD STUDIES\RIPPLESIDE CAT FS\8. FINAL DOCS - MAPS\R.W00201.004.01.FINALREPORT.DOC 6/8/10 13:08 D-5 O C E A N I C S A U S T R A L I A
Figure D-3 50 Year Design Flow Hydrographs
Lily Street
-1
0
1
2
3
4
5
6
7
0:00:00 1:12:00 2:24:00 3:36:00 4:48:00
Time (Hours)
Flo
w (
cu
me
cs
)
Overland
Underground
Hepner Place
-1
0
1
2
3
4
5
6
7
0:00:00 1:12:00 2:24:00 3:36:00 4:48:00
Time (Hours)
Flo
w (
cu
me
cs
)
Overland
Underground
The Fairway
-1
0
1
2
3
4
5
6
0:00:00 1:12:00 2:24:00 3:36:00 4:48:00
Time (Hours)
Flo
w (
cu
me
cs
)
Overland
Underground
Grace McKellar
-1
0
1
2
3
4
5
6
7
8
9
0:00:00 1:12:00 2:24:00 3:36:00 4:48:00
Time (Hours)
Flo
w (
cu
me
cs
)
Overland
Underground
DESIGN FLOW INFORMATION D-6
K:\INFRA_MGMT\RW\FLOOD STUDIES\RIPPLESIDE CAT FS\8. FINAL DOCS - MAPS\R.W00201.004.01.FINALREPORT.DOC 6/8/10 13:08 D-6 O C E A N I C S A U S T R A L I A
Figure D-4 20 Year Design Flow Hydrographs
Lily Street
-1
0
1
2
3
4
5
6
7
0:00:00 1:12:00 2:24:00 3:36:00 4:48:00
Time (Hours)
Flo
w (
cu
me
cs
)
Overland
Underground
Hepner Place
-1
0
1
2
3
4
5
6
0:00:00 1:12:00 2:24:00 3:36:00 4:48:00
Time (Hours)
Flo
w (
cu
me
cs
)
Overland
Underground
The Fairway
-0.5
0
0.5
1
1.5
2
2.5
3
0:00:00 1:12:00 2:24:00 3:36:00 4:48:00
Time (Hours)
Flo
w (
cu
me
cs
)
Overland
Underground
Grace McKellar
-1
0
1
2
3
4
5
6
0:00:00 1:12:00 2:24:00 3:36:00 4:48:00
Time (Hours)
Flo
w (
cu
me
cs
)
Overland
Underground