new doc 18Title new doc 18 Author CamScanner Subject new doc 18
2008_Bud_Work_Doc_Ed1v1.doc
-
Upload
semirahid3616 -
Category
Documents
-
view
112 -
download
3
description
Transcript of 2008_Bud_Work_Doc_Ed1v1.doc
ABU DHABI NATIONAL OIL COMPANY
Effective Date
Volume Section Version
1.2
Page 1 of 55
BUDGET WORKING DOCUMENT
Endorsed By:
Approved By:
Finance Director
Edition 1 v1 (updated notes and budget input forms to be issued August/September 2007, as necessary)
document.docdocument.docdocument.doc
BUDGET WORKING DOCUMENT
BUDGET 2008 &
FINANCIAL PLAN 2008 - 2012
ABU DHABI NATIONAL OIL COMPANY
Effective Date
Volume Section Version
1.2
Page 2 of 55
BUDGET WORKING DOCUMENT
Endorsed By:
Approved By:
Finance Director
TABLE OF CONTENTS
PART A: BUDGET PREPARATION
1 INTRODUCTION 4
1.1 Context 4
1.2 Overview 4
2 TIMETABLE 5
3 PROCESS OVERVIEW 6
3.1 Corporate Budget Objectives (‘Targets’), Manpower and Financial Budgets & Plans 6
3.2 Budget & Financial Plan Preparation 8
3.3 Extraordinary Operating Expenditure getting the budget into the system 8
3.4 Corporate Cash Budget 8
3.5 Business Units 8
3.6 Currency 8
3.7 Exchange Rate 8
3.8 Resolution Of Special Problems and Focal Points 9
4 REVENUE BUDGET 10
4.1 Hydrocarbon Revenue 10
4.2 Non-hydrocarbon Revenue 10
4.3 Non-hydrocarbon Miscellaneous Revenue 11
4.4 Data requirements for Group Financial Plan 12
5 OPERATING BUDGET 13
5.1 Preparation of the Operating Expenditure Budget by Directorates/Divisions 13
5.2 Direct Manpower Cost 14
5.3 Material Cost 15
5.4 Contracted Services 16
5.5 Administration & General 17
5.6 Financial & Other Expenses 18
5.7 Hydrocarbon & Non-hydrocarbon Purchases 18
5.8 Logistical Costs 18
5.9 Others 19
5.10 Data requirements for Group Financial Plan 20
6 RECHARGE BUDGET 20
6.1 Corporate Budget Recharges 20
6.2 Data requirements for Group Financial Plan 21
document.docdocument.docdocument.doc
ABU DHABI NATIONAL OIL COMPANY
Effective Date
Volume Section Version
1.2
Page 3 of 55
BUDGET WORKING DOCUMENT
Endorsed By:
Approved By:
Finance Director
7 CAPITAL BUDGET 22
7.1 Corporate Budget Capital 22
7.2 Data requirements for Group Financial Plan 23
8 CASH BUDGET 24
8.1 Process Over view Cash 24
8.2 Cash Budget Elements 25
9 SUBMISSION OF BUDGET 26
9.1 2008 Corporate Budget 26
9.2 Group Financial Plan 27
10 COMMENTARY REQUIREMENTS 28
10.1 Corpporate Budget Commentary 28
10.2 Group Financial Plan 29
PART B: BUDGET LOADING
(FINANCE USE ONLY)
11 LOADING OF BUDGET DATA 30
11.1 Budget Input Template (BIT) 30
11.2 Operating Budget Loading 30
11.3 Capital Work-In-Progress Loading 31
11.4 Group Financial Plan 35APPENDICES & ATTACHMENTS
12 APPENDICES 36
12.1 Budget Timetable 36
12.2 Budget Preparation Reports 37
12.3 Manpower Cost Rates For New Recruits 38
12.4 Insurance Premiums 39
12.5 Exchange Rates 41
12.6 Utilities Rates 42
12.7 Manpower Rates For Capitalised Expenses 42
12.8 Abbreviations 43
13 ATTACHMENTS 44document.docdocument.docdocument.doc
ABU DHABI NATIONAL OIL COMPANY
Effective Date
Volume Section Version
1.2
Page 4 of 55
BUDGET WORKING DOCUMENT
Endorsed By:
Approved By:
Finance Director
(see excel file…2008 budget forms.xls - to be issued August / September 2007)
document.docdocument.docdocument.doc
ABU DHABI NATIONAL OIL COMPANY
Effective Date
Volume Section Version
1.2
Page 5 of 55
BUDGET WORKING DOCUMENT
Endorsed By:
Approved By:
Finance Director
PART A
1. INTRODUCTION
1.1 Context
The Budget Working Document provides the general framework within which the ADNOC budget and Financial Plan is prepared. This document is to assist all ADNOC Directorates/Divisions in budget preparation and provide the basis, responsibilities, assumptions, currency, forms, etc., used in carrying out budgeting activities.
This document applies to budget preparation for ADNOC business units & Supreme Petroleum Council’s Divisions. It reflects executive management’s requirements to provide the budget on an “ADNOC Group Consolidation” basis and is expanded to cover preparation of the ‘Group Financial Plan’, which will provide a top down view of the Group’s total activity set - in terms of gross financial inputs and outputs, major developments and other key deliverables - over a 5-year horizon. Refer to the overview below.
1.2 Overview
Principal process inputs and responsibilities include:1) Budget and Plan inputs:
a) 2008: Targets and detailed Manpower, Opex, Revenue, Capex, etc. and supporting detailb) 2009-12: summary data on financials and activities
2) Business management, CEO and Boards provide challenge on HQ and JV budgets/plans 3) HQ Directorates provide presentations to CEO; Finance supports process4) Business Line Directorates provide assurance and challenge on Group budgets/plans5) Finance Directorate will :
a) co-ordinate collation of corporate Budget & Group Financial Plan for HQ and Group entitiesb) assure quality and consistency (compute taxes, eliminations, etc.) at a Group levelc) prepare budget booklets, summary variance analysis and other executive level reporting
document.docdocument.docdocument.doc
ABU DHABI NATIONAL OIL COMPANY
Effective Date
Volume Section Version
1.2
Page 6 of 55
BUDGET WORKING DOCUMENT
Endorsed By:
Approved By:
Finance Director
Budget & Plan Process OverviewUser Inputs
OPCO JV & ASR, Subs
Manpower Nos.& Cost
Opex & recoveries
Capital Projects
Revenue & Volumes
Divisional Targets
CEO &/or Boards –Review, Challenge, Revise.
Finance Directorateto review for: Consistency Compliance, Collate & Challenge
to prepare - Variance analysis
- Tax & Royalty
ADNOC Group Consolidated
Budget & Financial Plan
simple ‘Budget Book: HQ Takreer, net JV,
ASR, Subs dividends
Elimination & reclassify
HQ & Takreer
Financial Plan: HQ Takreer, ASR,
gross JV and Subs
• Detailed HQT data for 2008
• Summary data for 2009-12
2. TIMETABLEThe CEO issues the timetable for budget preparation each year. The budgeting period usually commences in July, with the setting of budget targets, and is finalised in December.
The timetable for the current year is included at Appendix 12.1, and a summary of key submission dates noted below:
document.docdocument.docdocument.doc
ABU DHABI NATIONAL OIL COMPANY
Effective Date
Volume Section Version
1.2
Page 7 of 55
BUDGET WORKING DOCUMENT
Endorsed By:
Approved By:
Finance Director
Key Submission by Directorates• Targets 30th Sept
• Manpower numbers 4th Oct
• Capital Close outs 11th Oct
• Budget Input Templates 18th Nov
Above includes opex, revenue, recoveries and capital
• Group Company Budget 5th &19th Nov
• CEO Presentations M&R and Manpower 7th-26th Nov
E&P, Others, Civil Projects 11th ++ Dec
Budget Book issued to CEO by Finance 9th December
Financial Plan issued to CEO by Finance 13th January** note: initial year only for implementation, future years to be accelerated
document.docdocument.docdocument.doc
ABU DHABI NATIONAL OIL COMPANY
Effective Date
Volume Section Version
1.2
Page 8 of 55
BUDGET WORKING DOCUMENT
Endorsed By:
Approved By:
Finance Director
3. PROCESS OVERVIEW
3.1 Corporate Budget Objectives (‘Targets’), Manpower and Financial Budgets & Plans
1) Each business unit prepares a Statement of Budget Targets. This statement consists of an overview of the objectives for the budget year, the work plan required to meet those objectives and any changes in the key resources (e.g. manpower, utilities, and capital) required to carry out the work plan.
The Statement of Budget Targets will take into account the organisational objectives of the concerned business unit, as defined in the ADNOC Organisation Manual and/or any other revisions approved by the CEO.
These are consolidated at the directorate level, and approved by the CEO.
2) Manpower plans are prepares by each Directorate – with details of existing manpower and changes thereto on a quarterly basis for the period 4Q 2007 through 4Q 2008.
These are analysed by:
a) Main type of employee, i.e. UAE national, UAE Graduate entry and Expatriate.
b) Category i.e. grouped by grade bands
c) New employees, grade progressions (for UAE graduate entrants), retirements and other changes
Finance Directorate is responsible for costing of the manpower budget, based on existing salary and benefit structures (subject to any other directive from senior management). The manpower budget will include total employee costs – including all directly identifiable benefits (specifically house rentals, medical insurance) but not training.
Note that ‘contractors’ are included in each Directorates operating/capital budget, as noted below.
Human Resources Directorate, in conjunction with Finance Directorate, issue full instructions to all HQ directorates on preparation of the corporate manpower budget.
3) Each business unit prepares a financial budget based upon its approved Statement of Budget Targets and relevant financial guidelines. The budgets of the component parts of ADNOC will be based on:
a) Statement of corporate budget objectives and Summary Guidelines issued by the CEO.
b) Statement of Budget Targets as issued by each directorate/division and approved by the CEO – refer to CEO letter “Budget and Group Financial Plan: Targets & Guidelines’.
c) Issue of financial guidelines by the Finance Director – see letter ‘Corporate Budget & Group Financial Plan (2008-12): Preparation’ - and this Budget Working Document.
d) Annual production and sales of crude oil by field;
document.docdocument.docdocument.doc
ABU DHABI NATIONAL OIL COMPANY
Effective Date
Volume Section Version
1.2
Page 9 of 55
BUDGET WORKING DOCUMENT
Endorsed By:
Approved By:
Finance Director
e) Annual production of natural gas by field;
document.docdocument.docdocument.doc
ABU DHABI NATIONAL OIL COMPANY
Effective Date
Volume Section Version
1.2
Page 10 of 55
BUDGET WORKING DOCUMENT
Endorsed By:
Approved By:
Finance Director
f) Annual throughput for refineries and other production plants in terms of capacity utilisation;
g) Other production and sales targets as appropriate to current circumstances (e.g. annual production and sales of gas, petrochemicals and fertilizer);
h) Assumptions regarding prices of above mentioned products for the budget year. Note that M&R Directorate develop underlying key product price assumptions, whilst GFCD are be responsible for ensuring efficient communication of such data to all relevant Group entities;
i) Identification of major exploration and development projects to be started or discontinued during the budget year;
j) Other major projects and activities (e.g. process improvement, research and development, major training) to be started or discontinued during the budget year;
k) Business Line Directorates must identify and quantify any major injections of new capital (to be provided by HQ via loans, share capital or other financing) that may be required by existing (or new) subsidiaries, and
l) Any policy guidelines or specific targets which management wishes to lay down. These may relate, for example, to recruitment, training plans, salary levels or benefits.
4) The financial budgets of the directorates are reviewed internally at various management levels and by the Finance Directorate and are presented by the concerned budget holders to the CEO for approval.
5) The ADNOC Corporate Budget is prepared using:
a) Budgets of the business units and SPC Divisions.
b) Budgets of the joint ventures and sole risk projects; and
c) Budgets for corporate costs and revenues such as dividends, royalties and tax.
6) The ADNOC Group Consolidated Budget is prepared using:
a) ADNOC budget and
b) Budgets of the group companies, after consideration of minority interests.
c) Elimination of significant intercompany sales, purchases and other transactions
(i.e. dividends, rents)
7) After review and endorsement by the Finance Director, the CEO submits the ADNOC budget and
ADNOC Group Consolidated Budget to the SPC for approval.
8) The ADNOC Group Financial Plan is prepared using similar inputs as the Consolidated Budget,
but summarise key financial and activities over a 5 year period:
a) gross financial inputs (operating costs, capex, deprecation, tax and royalty) and outputs
(revenues, gross and net profit)
b) major developments (capital projects and schemes)
c) manpower
document.docdocument.docdocument.doc
ABU DHABI NATIONAL OIL COMPANY
Effective Date
Volume Section Version
1.2
Page 11 of 55
BUDGET WORKING DOCUMENT
Endorsed By:
Approved By:
Finance Director
3.2 Budget & Financial Plan Preparation
1) All ADNOC Directorates/Divisions shall prepare the budget based on their budget year Objectives and Targets.
2) Budget Preparation Reports are to be used for forecasting revenue, operating expenses, recharges and capital expenditure for the remaining period of the current year (i.e. September to December to provide ‘2007 Outlook’) and ‘2008 Budget’.
3) Ensure that the budget is achievable, reasonable and corresponds to the budget year activity.4) Prepare budget in total and on a monthly basis for each budget item on the summary and
detailed schedules respectively, other than the capital expenditure budget. The capital expenditure budget is prepared on a project basis with annual incidence.
5) The monthly expenditure for each budget element is to be based on its level of activity rather than phasing the annual budget equally (although by default if is assumed that opex & recoveries are phased evenly through the budget year).
6) Materials or services that are not expected to be delivered or performed during the current year are to be included as part of the next year budget. Particular care must be taken to re-budget in 2008 opex related activities that may not be completed during the current year – and to make adjustment to the 2007 Outlook accordingly.
7) Concerned Managers are to prepare budget for revenues, expenses, recharges and capital expenditure that are directly controllable by them.
3.3 Extraordinary Operating Expenditure
1) Extraordinary operating expenditure is defined as unusual, non-recurring and/or infrequent transactions. Unusual and non-recurring means that the expenditure cannot be reasonably predicted to recur. Expenditures brought about by unforeseen events may also be classified as extraordinary.
2) Extraordinary operating expenditure is shown as a separate item in the operating budget, and requires special consideration on phasing.
3.4 Corporate Cash Budget
Group Treasury Division (GTD) prepares the Corporate Cash Budget in coordination with GFCD and directorates and group companies.
Note that for Group Financial Plan purposes, the overall cash generations is prepared on a top down basis (assuming net cash = net profit + deprecation less capital expenditure for each year)
3.5 Business Units
Use business unit codes as per ADNOC chart of accounts for the budget preparation list/copies.
3.6 Currency
The budget is prepared to the nearest thousand UAE Dirhams (AED).
3.7 Exchange Rates
Use exchange rates issued by GTD for conversion of foreign currencies budgets. (See Appendix 12.5)
document.docdocument.docdocument.doc
ABU DHABI NATIONAL OIL COMPANY
Effective Date
Volume Section Version
1.2
Page 12 of 55
BUDGET WORKING DOCUMENT
Endorsed By:
Approved By:
Finance Director
Directorate/ DivisionDIRECTORATE BUDGET
FOCAL POINTExt Mobile
Finance Budget Team
Ext Mobile
ADNOC TECHNICAL INSTITUTE Asharaf Mohammed 22830 Abdul Rahman 24751 4478088
ADMINISTRATIONTawfiq Shraideh 23185
Abdul Rahman 24751 4478088Halima Ahmed 23895
CIVIL PROJECTS
Ibraheem Al Hosani 24789
Abdul Rahman 24751 4478088Jeya Kumar 24947
Mytheen Saleem 23719
EXPLORATION & PRODUCTION Fatima Al Rumaithi 24954 Abdulaziz Al Mazrouei 24809 4441319
GNRCKhaleefa Al Mehairi 24947
Moh'd Hamdan 23723 6181874Shereen Al Romaithi 24949
GROUP FINANCIAL POLICIES & SYSTEMS
Abdel A'al Tambal 23997 Abdulaziz Al Mazrouei 24809 4441319
GROUP TREASURY Charles McFerren 24145 Abdulaziz Al Mazrouei 24809 4441319
Khaleda Al-Fardan 23987
HUMAN RESOURCES
Mohamed Mazherul Haque 23504 Moh'd Hamdan 23723 6181874
Mariam Al Suwaidi 23465
INTERNAL AUDIT Ahmed Matar 23996 Moh'd Hamdan 23723 6181874
LEGAL Mahmoud Hessou 23267 Abdulaziz Al Mazrouei 24809 4441319
MARKETING & REFINING
Abdulla Karsoua 23313
Abdul Rahman 24751 4478088Rashed Al Ramas 23837
Sara Al Tamimi 23274
Oasis Achieve Project TeamMohamed AlMazrouei 23600
Abdulaziz Al Mazrouei 24809 4441319Eissa Al Khamiri 24489
ORGANISATION DEVELOPMENT T.B.A Abdul Rahman 24751 4478088
PETROCHEMICALSMariam Al Katheeri 23627
Moh'd Hamdan 23723 6181874Khawla Al Hosani 23305
PETROLEUM INSTITUTE Fatima Al Shaali 607-5608
SCHOLARSHIP Saeed Al Amoodi 24226 Abdulaziz Al Mazrouei 24809 4441319
SHARED SERVICES Souhail Kefaya 23989 Abdul Rahman 24751 4478088
SPC – FINANCE & LEGAL T.B.A Abdulaziz Al Mazrouei 24809 4441319
SPC - PECDRashed Al Qubaisi 23450
Abdul Rahman 24751 4478088Hana A. Al Mahri 24167
TRAININGAhmed Al Nuwais 23995
Abdul Rahman 24751 4478088Sheikh Fahim 24358
Others
Roger Martin 24715 6610335
Abbas Siddiq 23374
Farha Ali Obeid 23833
3.8 Resolution of Special Problems and Focal PointsAny problems of principle arising during budget preparation should be referred to the Group Budgeting & Control team (GBCD) for resolution. Contacts are noted as below:
document.docdocument.docdocument.doc
ABU DHABI NATIONAL OIL COMPANY
Effective Date
Volume Section Version
1.2
Page 13 of 55
BUDGET WORKING DOCUMENT
Endorsed By:
Approved By:
Finance Director
4.REVENUE BUDGET – the following data is required for Budget year 2008 and update to 2007 Outlook only. See last paragraph re summary requirements for Group Financial Plan 2008-2012
4.1 Hydrocarbon Revenue
Hydrocarbon revenue includes revenue from sales of hydrocarbon products such as crude oil, refined products, condensate, gas, petrochemicals, and hydrocarbon related services to third parties etc. (and service revenue earned by providing facilities).
Description Object Code Directorate Explanation & GuidelinesCrude oil & condensate
4110 – 4139 M&R Budget should be prepared based on marketing assumptions, selling price and quantity. Submit sales summary showing production and sales quantities and prices.
Refined products 4140 – 4169 M&R Submit details of refined products sales, selling price and quantity.
Gas & petrochemical 4170 – 4189 M&R Submit details of gas and petrochemicals sales, selling price and quantity.
Fertilizers 4191 – 4192 PCD Submit details of ammonia and urea sales, selling price and quantity.
4.2 Non-hydrocarbon Revenue
Description Object Code Directorate Explanation & GuidelinesUse of assets 4470 – 4479 E & P 4471 Use of assets charges to the
OPCOsMarketing fees 4480 – 4489 M&R 4481 Budget should be based on future
marketing activities conducted for third parties
Gas supply facilities & transportation revenues
4430 – 4439 E & P
GFCD
4432–4439 Gas supply facilities & transportation revenue budget is based on approved rates.
document.docdocument.docdocument.doc
ABU DHABI NATIONAL OIL COMPANY
Effective Date
Volume Section Version
1.2
Page 14 of 55
BUDGET WORKING DOCUMENT
Endorsed By:
Approved By:
Finance Director
4.3 Non-hydrocarbon Miscellaneous Revenue
Where appropriate, use subsidiary codes to identify the source of income received.
Description Object Code
Directorate Explanation & Guidelines
Dividends 4410 GFCD/UCD Where appropriate, use business unit codes to identify the source of dividends.
Dividend – others 4420 GFCD Dividends from investments in non-group companies, such as Abu Dhabi Ship Building.
Interest Income 4450 – 4459 GTD
Petroleum Port Service 4510 – 4519 SPC 4511 For using the petroleum ports such as Jebel Dhana/Ruwais, Zirku and Das Island ports, a charge based on Net Registered Ton (NRT) is levied on the ship owner. Port operators on behalf of SPC.
Port charges revenue for the budget year should be estimated on the following basis:
1) Prepare estimate of the tonnage likely to pass through the ports, and
2) Apply the agreed charge for NRT to the estimated tonnage.
4512 The agreed charge payable to port operator should be determined and applied to tonnage for the budget year.
Property rental 4521 Admin
Technical services agreement
4522 UCD
Other non-hydrocarbon services
4523 UCD
Industrial services income
4540 – 4549 UCD
Industrial services income
4540 – 4549 UCD
document.docdocument.docdocument.doc
ABU DHABI NATIONAL OIL COMPANY
Effective Date
Volume Section Version
1.2
Page 15 of 55
BUDGET WORKING DOCUMENT
Endorsed By:
Approved By:
Finance Director
Miscellaneous revenues
Description Object Code
Directorate Explanation & Guidelines
Penalties 4571 UCD
Tender fees 4572 UCD
RHC Water & Electricity 4573 ADMIN
Subscriptions 4574 ADMIN
Medical recoveries 4575 ADMIN
Oil pollution Recoveries 4576 SPC
Other miscellaneous 4577 UCD
Exceptional items 4590 – 4599 GFCD
4.4 Data requirements for Group Financial Plan
Budget Input Templates (BITs) forms have been revised and expanded to collect summary revenue data for each year of the Financial Plan (i.e. 2009 through 2012). BITs will be provided in both hardcopy and soft copy formats to Budget Focal points of concerned Directorates.
document.docdocument.docdocument.doc
ABU DHABI NATIONAL OIL COMPANY
Effective Date
Volume Section Version
1.2
Page 16 of 55
BUDGET WORKING DOCUMENT
Endorsed By:
Approved By:
Finance Director
5. OPERATING BUDGET the following data is required for Budget year 2008 and update to 2007 Outlook only. See last paragraph re summary requirements for Group Financial Plan 2008-2012
5.1 Preparation of the Operating Expenditure Budget by Directorates/Divisions includes:
1) An assessment of current year’s expenditure i.e. the ‘2007 Outlook’.
2) Computation of monthly expenses budget, based on the operational assumptions and activities.
3) The operating expenses for the budget year are to be prepared based on:
a) Operational assumptions/plans and approved budget targets.
b) Historical trend and current year forecast.
4) When forecasting the operating expenditure:
a) Examine the Year to date expenditure for the current year, ascertain the reasons for variations e.g. whether expenditures have been incurred earlier than planned or are likely to be incurred later than planned, or are one-time exceptional variances.
b) Where the original assumptions made for the current year are no longer valid and the year to date reflects such changes, the later is used to estimate expenditures for rest of the year.
c) The current year’s budget should not be used as a sole basis for forecasting the remaining period of the current year. The current year remaining activities need to be reviewed.
d) Particular care must be taken to re-budget in 2008 opex related activities that may not be completed during the current year – and to make adjustment to the 2007 Outlook accordingly.
e) Business unit managers should forecast the expenses for the remaining months of the current year and provide a budget for the budget year for all expense accounts under their direct control or custodial responsibility.
document.docdocument.docdocument.doc
ABU DHABI NATIONAL OIL COMPANY
Effective Date
Volume Section Version
1.2
Page 17 of 55
BUDGET WORKING DOCUMENT
Endorsed By:
Approved By:
Finance Director
5.2 Direct Manpower Cost
1) Manpower numbersNote that the Manpower cost is input by GFCD on behalf of all Directorates, based on their approved manpower budget numbers, submissions to HR Directorate of manpower changes and other revisions as approved by senior management.The only exceptions to this are that Directorates/Users are to include in the operating expenses budgets the costs of CONTRACT staff, according to guidelines and instructions issued by HRD and GFCD.
2) Manpower costs
GFCD will apply existing salary and benefits for computing the total payroll cost, applied to the approved manpower numbers. For new recruits, the respective average actual salary for grade mid-point is used.
Directorates/Divisions provide GFCD with the estimated cost of overtime and other special allowances, as past/current amounts may not be appropriate for the future.
Description Object Code Directorate Explanation & Guidelines
Direct manpower costs 6020 – 6079 GFCD - UCD
For new recruits use average actual salaries for relevant grade.1) Overtime cost should be budgeted for
employees who are in grade 10 and below as compensation for authorised overtime. This should not exceed 50 hours per month for normal and shift work schedules and 25 hours per month for rest days and official holidays.
2) Overtime is calculated as a percentage of basic salary.
3) Actual overtime for the last 8 months can be used to compute the percentage on basic salary latest available actual.
6034-6037 Car purchase allowance for eligible employees is to be budgeted based on their entitlement.
Refer to Appendix 12.3 Manpower Cost rates for new recruits. Actual rates are to be used for existing employees.
Secondees to ADNOC 6080 – 6089 GFCD - UCD
document.docdocument.docdocument.doc
ABU DHABI NATIONAL OIL COMPANY
Effective Date
Volume Section Version
1.2
Page 18 of 55
BUDGET WORKING DOCUMENT
Endorsed By:
Approved By:
Finance Director
document.docdocument.docdocument.doc
ABU DHABI NATIONAL OIL COMPANY
Effective Date
Volume Section Version
1.2
Page 19 of 55
BUDGET WORKING DOCUMENT
Endorsed By:
Approved By:
Finance Director
5.3 Material Cost
Description Object Code Directorate Explanation & Guidelines
Material cost 6100 – 6199 UCD Include cost of materials used in operation and support services, i.e. chemicals, catalyst, consumable, fire and safety, etc.
Calculation bases are:
1) Major Material Categories: Quantity based on operating plan and the consumption pattern for the budget year.
2) A lump sum forecast may be made for Minor Materials Category considering any major factors anticipated in the budget year. Emphasis must be placed on spare parts charged under Direct Charge Orders, anticipated consumption during major maintenance overhaul and changes in operating parameters that have an impact on material usage.
3) The materials cost budget must be consistent with the Requisitioning Plan.
4) Contact Shared Services Directorate – Procurement Services Division for material price guidelines.
5) Hydrocarbon fuel consumed internally should not be budgeted.
document.docdocument.docdocument.doc
ABU DHABI NATIONAL OIL COMPANY
Effective Date
Volume Section Version
1.2
Page 20 of 55
BUDGET WORKING DOCUMENT
Endorsed By:
Approved By:
Finance Director
5.4 Contracted Services
document.docdocument.docdocument.doc
ABU DHABI NATIONAL OIL COMPANY
Effective Date
Volume Section Version
1.2
Page 21 of 55
BUDGET WORKING DOCUMENT
Endorsed By:
Approved By:
Finance Director
Description Object Code Directorate Explanation & Guidelines
Contracted services 6200 – 6399 UCD 6250-6259 Utilities rates for latest actual
6290-6299 as below:
1) Cost of telecommunication services includes expenses incurred on telephone, telex, facsimile, Internet, and voice/data transmission services. It also includes telephone bills paid to third party, and for mobile and residential telephones of senior ADNOC staff.
2) Telecommunication cost should be budgeted based on:
a) Planned level of service
b) Expansion of existing facilities
Historical trend of telecommunication expenses.6350-6359: as below:Contracted manpower cost is the cost of manpower procured by the company from external agencies (i.e. labour contracts). The budget should be based on:1. The number of estimated personnel
(on chart & others) required by each responsibility centre for the remaining period of the current year and budget year.
2. Current rate or contractual rate.3. The existing contracts that are to be
renewed in the budget year should be revalued based on conditions prevailing in the market.
4. Use object code:a) 6351 to budget for contracted
manpower for established organizational position.
b) 6358 to record anticipated costs for overtime.
c) 6359 to budget for manpower not included in the established organizational position.
document.docdocument.docdocument.doc
ABU DHABI NATIONAL OIL COMPANY
Effective Date
Volume Section Version
1.2
Page 22 of 55
BUDGET WORKING DOCUMENT
Endorsed By:
Approved By:
Finance Director
5.5 Administration & General
Description Object Code Directorate Explanation & Guidelines
Administration & general expenses
6400 – 6499 UCD 6431-6432 Follow budget insurance premium guidelines described in Statement of Financial Guidelines. See Appendix 11.4
Training TD/UCD 6440-6459
Career development (“technical” careers) covered by concerned directorates
1) The training costs are budgeted centrally by the Training Division
Professional services UCD 6461 – 6465
“Professional Services” e.g. audit, legal, consultancy etc…
Printing, Postage & Stationary
ADMIN 6488
1) Concerned directorates to provide Administration Directorate with budgeted quantity for printing, postage & stationery for the budget year.
2) Administration Directorate calculates budgeted cost of printing, postage & stationery by applying current market price for the total requirements for the budget year.
Donations and Awards ADMIN 6489Includes the long service award, which represents company awards to employees per eligibility.
document.docdocument.docdocument.doc
ABU DHABI NATIONAL OIL COMPANY
Effective Date
Volume Section Version
1.2
Page 23 of 55
BUDGET WORKING DOCUMENT
Endorsed By:
Approved By:
Finance Director
5.6 Financial & Other Expenses
Description Object Code Directorate Explanation & Guidelines
Loan interest & bank charges 6510–6519 GFCD - GTD
Exchange gain/loss 6520-6529 GFCD - GTD
Bad debts 6530-6539 GFCD
Inventory adjustments 6540-6549 GFCD
Other financial expenses 6560-6569 FD
5.7 Hydrocarbon & Non-hydrocarbon Purchases
Description Object Code Directorate Explanation & Guidelines
Hydrocarbon purchases 6610-6619 M&R
Non-hydrocarbon purchases 6620-6629 M&R
5.8 Logistical Costs
Logistical costs are costs incurred in distributing and selling marketable products. These are categorized as follows:
Description Object Code Directorate Explanation & Guidelines
Logistical costs 6630-6639 M&R
Movement in stock 6640-6649 GFCD
document.docdocument.docdocument.doc
ABU DHABI NATIONAL OIL COMPANY
Effective Date
Volume Section Version
1.2
Page 24 of 55
BUDGET WORKING DOCUMENT
Endorsed By:
Approved By:
Finance Director
5.9 Others
Description Object Code Directorate Explanation & Guidelines
Capitalised expenses 6660-6669 UCD Use this account to capitalise project expenditure previously charged to operating expenses. The expenses related to manpower costs should be capitalised on the following basis:
1) Use the current year budgeted manpower rate (See Appendix 11.9), which includes salary, benefits, accommodation and medical for Capital Budget - ADNOC Supervision Cost.
2) No internal allocation of manpower costs should be budgeted or charged to G&G capital projects
Royalties & Tax 6800-6809 GFCD
Operating cost – J.V.&SR 6810-6819 FD/E&P G&G costs should be budgeted as capital project and at year-end, its costs should be charged to operating expenses
Depreciation & Amortization 6900-6959 GFCDThe fixed assets write-off should include all capital budget expenditures to be charged to expenses. This occurs when they are below the minimum limit of capitalisation (i.e., AED 10,000 for individual capital item) as per ADNOC Accounting Policies & Principles
G&G costs, Minor Assets & Other Write-offs
Gain/Loss on Sales of Fixed Assets
Unsuccessful Exploration
6971-6999 FD/UCD .
document.docdocument.docdocument.doc
ABU DHABI NATIONAL OIL COMPANY
Effective Date
Volume Section Version
1.2
Page 25 of 55
BUDGET WORKING DOCUMENT
Endorsed By:
Approved By:
Finance Director
document.docdocument.docdocument.doc
ABU DHABI NATIONAL OIL COMPANY
Effective Date
Volume Section Version
1.2
Page 26 of 55
BUDGET WORKING DOCUMENT
Endorsed By:
Approved By:
Finance Director
5.10 Data requirements for Group Financial Plan
Budget Input Templates (BITs) forms have been revised and expanded to collect summary operating expenses data for each year of the Financial Plan (i.e. 2009 through 2012). BITs will be provided in both hardcopy and soft copy formats to Budget Focal points of concerned Directorates.
6. RECHARGE BUDGET - the following data is required for Budget year 2008 and update to 2007 Outlook only. See last paragraph re summary requirements for Group Financial Plan 2008-2012
6.1 Corporate Budget Recharge
Recharge cost is defined as transfer of cost, based on agreement, from ADNOC to group companies.
1) Recharge cost should be calculated based on:
a) Agreed rates, amount or formula.
b) Contractual amount and the existing contractual agreement should be reviewed for updating the recharge cost.
2) Recharge of ATI Training Costs and Scholarship Program Costs to group companies should be based on approved Recharge of Training and Scholarship Program Costs Policies.
3) Use the group company subsidiary code to identify where the cost is to be recharged.
Description Object Code
Directorate Explanation & Guidelines
Secondees 6701 HR
ADNOC Technical Institute 6702 ATI
Scholars abroad 6703 SCHL
Courses & seminar fees 6704 TD
Ruwais School tuition fees 6705 ADMIN
Technical Assistance 6706 UCD
Abu Dhabi Accommodation 6707 ADMIN
Ruwais Housing Complex rent 6708 ADMIN
RHC – Common facilities 6709 ADMIN
Medical Services (Abu Dhabi) 6710 ADMIN
Medical Services (Remote Area) 6711 ADMIN
Medical Evacuation (Medevac) 6712 ADMIN
document.docdocument.docdocument.doc
ABU DHABI NATIONAL OIL COMPANY
Effective Date
Volume Section Version
1.2
Page 27 of 55
BUDGET WORKING DOCUMENT
Endorsed By:
Approved By:
Finance Director
Environment & safety protection 6713 E&P
Description Object Code
Directorate Explanation & Guidelines
Social/welfare & other costs 6714 ADMIN
Capitalized expenses 6715 UCD
IT charges 6716 SSD
Insurance premiums & asset valuations
6717 GTD/SSD Use the latest approved rates. Refer to Appendix 12.4.
PPA & oil spill costs 6718 SPC Recharges are calculated based on costs, plus a margin for overheads and divided among the beneficiaries.
Gas processing, operating costs, transport & handling
6719 E&P
Utilities Various UCD Use the latest approved utilities rates for recharge to both group companies and third parties. Refer to Appendix 12.6.
Other recharges 6723 HR&A
Group National Recruit 6725 GNRD
Waste management 6726 ADMIN
6.2 Data requirements for Group Financial Plan
Budget Input Templates (BITs) forms have been revised and expanded to collect summary recharged expenses data for each year of the Financial Plan (i.e. 2009 through 2012). BITs will be provided in both hardcopy and soft copy formats to Budget Focal points of concerned Directorates.
document.docdocument.docdocument.doc
ABU DHABI NATIONAL OIL COMPANY
Effective Date
Volume Section Version
1.2
Page 28 of 55
BUDGET WORKING DOCUMENT
Endorsed By:
Approved By:
Finance Director
7. CAPITAL BUDGET - Data requirements for the 2008 Budget and 2007 Outlook are noted below. Also refer to the final paragraph for requirements for the Group Financial Plan.
7.1 Corporate Budget Capital
1) The Capital Budget represents a plan for capital expenditure and is prepared to:
a) Provide an assessment of the current status for each project.
b) Provide a basis for reviewing and approving capital expenditure plan for the budget year on each project.
c) Estimate the extent of capitalisation in the current year.
2) The Capital Budget consists of:
a) The Capital Expenditures Budget for ongoing projects, new projects
b) The Capital Closeout Budget for existing projects.
c) Cancelled Projects.
3) Capital Budget should be prepared based on capital investment requirements and budget targets.
Projects Category Responsibility
ADNOC Exploration Program E&P
Capital Projects UCD
ADNOC Intangibles E&P/SSD
Furniture, Equipment and Vehicles ADMIN
Educational & Training Equipment TD
Information Technology SSD-IST
RMS Equipment ADMIN –GSD-GSP
4) For capital budgets Motor Vehicles, Furniture & Equipment or Personnel Computer Equipment refer to form CB9 (see section 13 “Attachments”).
Formats for presentation of project capital requirements will agreed by Finance with the respective Division on a case by case basis. In practice Civil Projects Division is the primary sponsor of major projects and will continue to use their existing formats and templates. Typically, these formats will include as a minimum the information included below.
5) For Existing Projects
a) The original authorised expenditure for the entire project.b) The accumulated expenditure up to the year prior to the current year.
document.docdocument.docdocument.doc
ABU DHABI NATIONAL OIL COMPANY
Effective Date
Volume Section Version
1.2
Page 29 of 55
BUDGET WORKING DOCUMENT
Endorsed By:
Approved By:
Finance Director
c) The expenditure incurred in the current year up to August 31.
The concerned Responsibility Centre Manager for the project should provide the following:
a) Revised budget for the entire project based on the budget year assumptions,b) Commitment made and the assignment of budget elements to third parties for the
execution,c) Forecasted expenditure at the end of the current year,d) Incidence of expenditure in the budget year, and the year following the budget year and
beyond.6) Proposal to Close Capitals Projects (PCCP)
a) Prepare a list of PCCP for the year which should includes the following:
(i) Project number
(ii) Description of the project
(iii) Budgeted amount approved for the project.
(iv) Previous year’s cumulative actual expenditures on the project.
(v)Forecast of expenditure for the current year, this forecast should take into account actual expenditure to date, accruals, commitment, contingency, etc., for the project
(vi) Total cost of project.
b) Use the form CAPEX-II (See section 13 “Attachments”)
7.2 Data requirements for Group Financial Plan
1) Plan Data
Budget submissions in earlier years included the requirement to provided details of all years’ expenditures on major projects to provide the estimated final cost (EFC). Typically, this was for projects approved or supported by senior management. The intent of the Group Financial Plan is to provide management with an indication of the total funding requirements for new major projects and schemes – whether approved, tentative/provisional/conditional or optional. Therefore, additional data is now required for future projects that may not be fully approved. Directorates are to provide indicative EFCs for all major projects with an estimated total costs of AED 200 million or greater. This will include:
a) Nature or project – a brief description of the capital works (<50 words)
b) EFC and annual incidence (for all years) – note that estimates of future annual costs are to be provided before any allowance for future price inflation – i.e. they are to be expressed in 2008/9 monies.
c) ADNOC % interest (but note that summary of GROSS spend and outputs are to be included in the Plan submission)
document.docdocument.docdocument.doc
ABU DHABI NATIONAL OIL COMPANY
Effective Date
Volume Section Version
1.2
Page 30 of 55
BUDGET WORKING DOCUMENT
Endorsed By:
Approved By:
Finance Director
d) Nature of output/deliverable and financial impact – e.g. amount of production, cost saving, HSE or other value generated on commencement of the project.
2) Confidentiality and Sensitivity
Due to the sensitivity of some projects, it may be necessary to only include in the Financial Plan certain general statements/data on future projects. Directorates should consult fully with FCD on how such projects may be reflected in the Group Financial Plan
8 .CASH BUDGET – cash budget data is only required for 2008. Cash projections for the out-years of the Financial Plan period (i.e. 2009- 2012) will be derived from Directorates expenditure and income submissions and overviewed by FCD for working capital and certain non-cash impacts.
8.1 Process Overview Cash
1) The Cash budget is a statement of cash inflows and outflows for the budget year. It identifies the periods and amount of cash excess or deficit. Its objectives are to:
a) Plan the cash requirements for the budget year,
b) Project the cash position during the year to provide adequate financing for cash deficit and plan investment for cash surplus,
c) Monitor and control the timing of cash flow, credit and collection activities.
2) The cash budget exercise involves an estimate of cash receipts and disbursements based on the financial budgets and financial commitments such as loan repayments, borrowings, cash calls, etc.
3) Cash Budget is prepared by each Directorate based on their financial budgets and according to the following formats identified. Using form ADNOC D see Attachment 8.
4) FCD provides the assistance if required to concerned Directorates and the information needed to GTD.
5) The following items should be excluded from the Cash Budgets:
a) Depreciation & Amortization
b) Employee End of Service Benefits (EOSB)
c) Accruals before they become due for payment, and
d) Capitalised Expenses (G&G, Manpower Cost) under ADNOC Supervision in capital projects and OPEX Budget.
6) FD provides manpower cost for Cash Budget.
7) Provide projected cash budget elements in summary for:
a) Revenues,
b) Recharges to group companies,
c) Operating Expenses (OPEX) excluding manpower cost,
d) Capital Expenditures (CAPEX), etc.
document.docdocument.docdocument.doc
ABU DHABI NATIONAL OIL COMPANY
Effective Date
Volume Section Version
1.2
Page 31 of 55
BUDGET WORKING DOCUMENT
Endorsed By:
Approved By:
Finance Director
e) Assumptions used to prepare Cash Budgets such as credit period, contractual agreements, recharge arrangements, etc. is disclosed separately with the Cash Budget.
8) Each Directorate is responsible for submitting its cash budget and summary of projected cash budget elements to:
a) GTD, for compilation of ADNOC cash budget, and
b) GFCD for review.
9) GTD is responsible for the review of individual Directorate cash budget and consolidation of the overall Cash Budget in order to provide an overview of cash position. (See section 13 “Attachments”).
8.2 Cash Budget Elements
The Cash Budget is composed of the projected amounts for the following elements:
Element Responsibility & Source Of Data
A. CASH INFLOWSHydrocarbon Revenue M&R based on Hydrocarbon Revenue BudgetNon-hydrocarbon Revenue M&R based products Revenue BudgetHydrocarbon Services M&R based on approved agreements for services and fees.
GFCD for: ADGAS payments Gas Gathering Facilities (ADGAS) Gas Transportation Tariff, Ammonia/Urea (FERTIL) Insurance Management FeesE&P for: Use of Assets Charge SPC for: PPA Revenue
Dividends & Advances GFCDLoan Repayments GTDInterest Income GTDRecharges to group companies UCDOther Income UCDB. CASH OUTFLOWSRoyalties and Tax GFCD based on Royalties & Tax CalculationCash Calls E&PProcessing Fees GFCD based on budgets of TAKREER, GASCO & FERTILOperating Expenses All Directorates based on OPEX budgetsCapital Expenditures UCD based on CAPEX budgets, where applicableCAPEX & OPEX - Sole Risks E&P based on OPCOs Budget.Borrowing Repayments GTD
document.docdocument.docdocument.doc
ABU DHABI NATIONAL OIL COMPANY
Effective Date
Volume Section Version
1.2
Page 32 of 55
BUDGET WORKING DOCUMENT
Endorsed By:
Approved By:
Finance Director
Element Responsibility & Source Of Data
Interest Expenses GTDLogistical Costs M&ROther Expenses UCDC. TRANSFER TO ADIATransfer to ADIA and ADIC GTD
document.docdocument.docdocument.doc
ABU DHABI NATIONAL OIL COMPANY
Effective Date
Volume Section Version
1.2
Page 33 of 55
BUDGET WORKING DOCUMENT
Endorsed By:
Approved By:
Finance Director
9. SUBMISSION OF BUDGET
9.1 Corporate Budget 2008
The Corporate Budget is prepared on the basis of business units. Each directorate shall submit the budget for the Directorate as a whole, and individual budgets for the business units of that directorate. The following are to be included in each budget presentation package:
BUDGET SUBMISSION
Description Explanation & Guidelines
Corporate Budget Objectives & Targets
Refer to 3.1 Corporate Budget Objectives
Manpower Plan The manpower plan includes:
The basic assumptions used to generate expected manpower levels
A summary of those manpower levels on quarterly and annual basis
Analysis of differences between the manpower plan for the budget year and the outlook for the balance of the year.
The manpower plan must agree with the manpower plans supplied to Finance Directorate and used to calculate manpower costs.
Operating Summary Summary should include the following:
A short form budget, highlighting the major revenue and expenditure areas, and the differences between the current year outlook and the budget for next year.
Assumptions used,
Major changes in budgets, and
Overall comments by category, explaining increase/decrease by category between
(i) Budget year (2008) and current year Outlook (2007).
(ii) 2007 Outlook and 2007 Original Budget.
Categories include:
Hydrocarbon sales revenue,
Non-hydrocarbon sales revenue.
Non-hydrocarbon miscellaneous revenue.
Direct manpower costs.
Material costs.
Contracted services.
Administration & general expenses.
document.docdocument.docdocument.doc
ABU DHABI NATIONAL OIL COMPANY
Effective Date
Volume Section Version
1.2
Page 34 of 55
BUDGET WORKING DOCUMENT
Endorsed By:
Approved By:
Finance Director
Description Explanation & Guidelines
Financial & other expenses.
Hydrocarbon & non-hydrocarbon purchases.
Logistical costs.
Other costs.
Recharges.
As applicable.
(See section 13 – Budget Input Template)
Operating Commentary
Provide, for appropriate object codes, a detailed explanation for the increase/decrease between the budget year and current year outlook.
Cash Flow Budget Required for Directorates and autonomous divisions, and at corporate level.
Capital Expenditure Summary – New Projects
Summary should include the following:
A short form budget, highlighting the major projects that are to be undertaken.
Assumptions used
Scope of Projects For each new capital expenditure item, a scope document shall be prepared.
This shall include:
The scope of the project
Summary of the justification for the project.
Budget expenditure for the budget year.
Budget expenditure for subsequent year(s).
Capital Expenditure Summary – Continuing
Summary should include the following:
A short form budget, highlighting the major projects that are to be undertaken.
Assumptions used
Commentary A commentary on continuing projects is to be provided, including summaries for project slippages, delays and material project over/under runs.
9.2 Group Financial Plan
Finance Directorate will prepare a summary presentation on the Group Financial Plan during the first year of implementation. Directorate/Divisions are to support this process. (This is subject to revision and refinement in future years.)
document.docdocument.docdocument.doc
ABU DHABI NATIONAL OIL COMPANY
Effective Date
Volume Section Version
1.2
Page 35 of 55
BUDGET WORKING DOCUMENT
Endorsed By:
Approved By:
Finance Director
10. COMMENTARY REQUIREMENT
10.1 Corporate Budget Commentary
1) Commentary is primarily focussed on current years (Outlook) and next year (Budget), with emphasis on justifications for variances (increases or decreases) from approved budgets and new projects.
In particular, full commentary is required on significant variations between:
a) 2007 Original Budget and 2007 Outlookb) 2007 Outlook and 2008 Original Budget
Also, there is continuing requirement to provide information on the basis on which the budget was formulated (e.g. key variables/costs drivers, any oil price sensitivity, etc)
2) The ‘2007 Original Budget’ is the value as original submitted and approved by Executive Management (i.e. BEFORE any enhancements that may have been approved on a case by case basis by the CEO during the current year). This will enable GBCT to collate and provide management with justifications for variations from the Budget as originally approved.
3) In order to make this less onerous for Directorates, the LIMITS and tolerances have been established: this is to ensure that they may concentrate on provide quality explanations/justification on fewer but more significant variations.
The main parameters are now:a) For items where the Budget item is greater than AED 1 million:
(i) Comment required on all variations greater than (i) AED 100,000 or (ii) 10%.
b) For items where the Budget item is less than AED 1 million:(i) Commentary required on all variation greater than (i) AED 100,000
and (ii) 10%.
c) Additionally commentary is required:(i) for any new expenses items greater than AED 20,000 that are
reported in the 2007 Outlook and/or.(ii) New 2008 Original Budget items is excess of AED 20,000.
The Budget Input templates have pre-set formula/functions to help point out where these limits apply and require commentary.
4) Please note that these criteria apply only to determine those accounts that are financially significant. Commentaries on other accounts may be required if those accounts are significant due to control or other issues. Directorates should feel free to supply commentary on accounts that fall outside these criteria.
document.docdocument.docdocument.doc
ABU DHABI NATIONAL OIL COMPANY
Effective Date
Volume Section Version
1.2
Page 36 of 55
BUDGET WORKING DOCUMENT
Endorsed By:
Approved By:
Finance Director
Some practical examples of how these rules apply (all values in AED 000’s):
2007 Budget
as originally approved
2007 Outlook (for full year)
Increase or
(Decrease) AED
Increase or
(Decrease) %
Test (i) +/- AED 100k
Test (ii) +/-
10%
Comments mandatory
10 50 +40 +400 No Yes No
500 420 (80) (16)% No Yes No
0 50 +50 N/A No N/A Yes
1500 1580 +80 5% No No No
2000 2150 +150 +8% Yes No Yes
3000 2500 (500) (17)% Yes Yes Yes
The above example is for 2007 Budget vs. 2007 Outlook but the same rules apply for variations between 2007 Outlook and 2008 Original Budget
10.2 Group Financial Plan Commentary
For the first year of implementation of the Plan the main objective is to provide a high level view of the Groups key financial performance and relate this to the major deliverables. Therefore, variance analysis will be more focused on describing new projects/schemes (i.e. those in with an estimated final cost of AED 200 million or more) and the corresponding impact on capacities, production and manpower.
This may be refined for future years to meet management’s requirements.
document.docdocument.docdocument.doc
ABU DHABI NATIONAL OIL COMPANY
Effective Date
Volume Section Version
1.2
Page 37 of 55
BUDGET WORKING DOCUMENT
Endorsed By:
Approved By:
Finance Director
PART B
11. LOADING OF BUDGET DATA: This section primarily relates to loading of the 2008 Corporate Budget data (and to a certain extent future years expenditures on multi year major projects. See last section for loading/collation of the Group Financial Plan data.
11.1 Budget Input Template (BIT)
1) Budget Department will provide Budget Input Template (BIT) in MS Excel to all the concerned Directorate /Division.
2) The concerned Directorate / Divisions budget focal points will update the BIT with the 2007 outlook and the 2008 budget figures.
3) In order to facilitate the budget preparation GFPSD will provide access to each Directorate / Divisions budget focal points to review their past date in the system.
11.2 Operating Budget Loading
This process utilises the completed BIT received from the concerned directorate/division.
1) Login to JD Edwards Enterprise
2) Access the Budget Sheet Download screen, through the following steps:
a) “Budget (Opex) upload” in the commitment /AFE module
b) Work with budget Upload screen
c) Click add button and fill the explanation filed with the appropriate description.
d) The default value for the fiscal year should be the current year. Not the budget year . change this to the budget year if necessary.
e) Left click in the “OK” button
f) Click “find” button and then click on”Budget Details” from the tool bar.
g) Click the “Import” Icon from the screen.
h) The “Import Assistant”screen will appear . After specifying import options and defining the cell range, click Preview and then click Continue to import the data.
i) Left click in the “OK” button
j) This process is carried out to import the data from the BIT to the system.
3) Verify the data in the system and make changes if required
a) Left click in the “OK” button
b) Approve the data and make it final.
4) Click in “budget upload” from tool bar.
5) THE “Printer Selection” secreen will appear and left click on the “OK” button
6) The will create a “BO” batches in the system
document.docdocument.docdocument.doc
ABU DHABI NATIONAL OIL COMPANY
Effective Date
Volume Section Version
1.2
Page 38 of 55
BUDGET WORKING DOCUMENT
Endorsed By:
Approved By:
Finance Director
11.3 Capital Work-In-Progress Loading
1) Create Project Master Record
a) Login to JD Edwards.
b) Access the “Project Master Revisions” screen, through the following steps:
(i) “Commitments/AFE Menu”
(ii) “Project Setup & Phasing”
(iii) “Project Master Revisions”
c) Click on “Add” button to commence creation of new project master record.
d) Enter:
(i) Job Number, using seven-digit code.
(ii) Description, using project description.
(iii) Level of Detail
The default for this is “9”
(iv) Type Business Unit
The default for this is “JB”
(v) Company, using “00050” for ADNOC projects.
(vi) Contract type
Options include:
“EPC” – fixed price, lump-sum projects
“EPCM” – managed projects
“PASS” – purchased assets
“SHT” – shutdown
“EXM” – extraordinary expenditure
e) All other fields should be left blank.
f) Left click on the “OK” button.
g) Left click on the “Can (cell)” button.
h) Left click on the “Close” button.
document.docdocument.docdocument.doc
ABU DHABI NATIONAL OIL COMPANY
Effective Date
Volume Section Version
1.2
Page 39 of 55
BUDGET WORKING DOCUMENT
Endorsed By:
Approved By:
Finance Director
2) Attach Cost Code Structure
a) Login to JD Edwards
b) Access the “Copy Selected Master Codes” screen, through the following steps:
(i) “Commitments/AFE Menu
(ii) “Project Setup & Phasing”
(iii) “Copy Selected Master Codes”
c) Left click on “Find” button to retrieve chart types.
d) Select the appropriate chart type. This relates to the type of project, and for capital expenditure projects relates to the general ledger CWIP object.
Use PM1 for capital projects and PAS for purchased assets.
e) Double left click on selected chart type, bringing up the “Copy Selected Master Codes – [Copy Cost Codes]” screen.
f) Enter:
(i) Job (Project code) to which the chart type should be attached.
(ii) Range of accounts within the master codes to be transferred. This will usually relate to the chapters relevant to the particular project. If these fields are left blank, the entire range will be copied to the project.
g) Left click on “OK” button.
h) A Confirmation of Copy prompt will appear. Left click on “OK” button.
i) The chart will then be loaded to the project, and a display will show the number of lines added to the chart for the project. Note – the loading of the chart can be slow.
j) Left click on “Can (cell)” button to complete the attachment of the cost code structure.
k) Repeat above to add master codes from additional charts, as required.
l) When all additions have been completed, left click on the “Close” button.
document.docdocument.docdocument.doc
ABU DHABI NATIONAL OIL COMPANY
Effective Date
Volume Section Version
1.2
Page 40 of 55
BUDGET WORKING DOCUMENT
Endorsed By:
Approved By:
Finance Director
3) Delete Accounts
a) Access the “Original Budget Entry” through the following steps:
(i) “Commitments/AFE Menu”
(ii) Project Setup & Phasing
(iii) Original Budget Entry
b) Left click on “Find” button to retrieve projects
c) Double left click on selected project
d) Select the appropriate range of cost code & cost type
e) Click “Delete” button
f) Click “Ok” button
g) Click on “Close” button
3) Project Original Budgeta) Login to JD Edwards
b) Access the “Original Budget Entry” screen, through the following steps:
(i) “Commitments/AFE Menu
(ii) “Project Setup & Phasing”
(iii) “Original Budget Entry”
c) Left click on “Find” button to retrieve projects.
d) Double left click on selected project.
e) Enter:
(iv) G/L date as “01/01/08” to indicate that the project is to commence in the budget year.
You may receive a warning message: “Warning: Fiscal Year Not within Range”. This warning should be ignored for entry of projects in the budget year.
You may receive a warning message: “The information has changed. Before entering data, press FIND.” If this occurs:
- Left click on the “OK” button.
- Left click on the “Find” button.
(vii) Left click on the “Find” button.
(viii) Original Amount. Enter the budgeted amounts in the “Original Amount” field corresponding to the relevant cost code and cost type.
e) When all amounts have been entered, left click on the “OK” button.
f) Left click on the “OK” button.
g) Left click on the “Can (cell)” button.
h) Left click on the “Close” button.
document.docdocument.docdocument.doc
ABU DHABI NATIONAL OIL COMPANY
Effective Date
Volume Section Version
1.2
Page 41 of 55
BUDGET WORKING DOCUMENT
Endorsed By:
Approved By:
Finance Director
i) Note: You may only enter or edit the budget if the “Job Posting Edit” field is blank.
document.docdocument.docdocument.doc
ABU DHABI NATIONAL OIL COMPANY
Effective Date
Volume Section Version
1.2
Page 42 of 55
BUDGET WORKING DOCUMENT
Endorsed By:
Approved By:
Finance Director
4) Project Phasing – New Projects
a) Login to JD Edwards
b) Access the “CAX Budget Preparation – New Projects” screen, through the following steps:
(i) “Commitments/AFE Menu
(ii) “Project Setup & Phasing”
(iii) “CAX Budget Preparation”- Next year – New Project.
c) Left click on “Find” button to retrieve projects.
d) Double left click on selected project.
e) Enter the appropriate amounts in the following columns:
(i) Budget Year – the project phasing that is expected to be incurred in the budget year.
(ii) Next Year – the project phasing that is expected to be incurred in the year following the budget year.
(iii) Later Amount – the project phasing that is expected to be incurred in the second and subsequent years following the budget year. Note that this is being reviewed to cover input of Group Financial Plan data and Finance Directorate will advise user Directorates accordingly.
f) The Current Year Remainder and Current Year Total fields will be calculated based on the above. Confirm that these fields contain zero values. If not, then correct phasing amounts entered at step d).
g) Left click on the “OK” button.
h) Left click on the “Close” button.
6) Project Phasing – Continuing Projects
This is required for all continuing projects not closed as at 31 August, regardless of whether project completion is expected to occur after the end of the current year.
a) Login to JD Edwards
b) Access the “CAX Budget Preparation” screen, through the following steps:
(i) “Commitments/AFE Menu”
(ii) “Project Setup & Phasing”
(iii) “CAX Budget Preparation” – Next year – Ongoing Project
c) The screen will default to the budget year and budget preparation for ADNOC Project Company. Use the find features to locate the relevant project.
d) Double click on selected project.
document.docdocument.docdocument.doc
ABU DHABI NATIONAL OIL COMPANY
Effective Date
Volume Section Version
1.2
Page 43 of 55
BUDGET WORKING DOCUMENT
Endorsed By:
Approved By:
Finance Director
e) If the total budget amount is to be amended, enter the revised budget figures against the relevant cost code/cost type combination. This will generate the budget change amount. Confirm the change amount to supporting documentation.
document.docdocument.docdocument.doc
ABU DHABI NATIONAL OIL COMPANY
Effective Date
Volume Section Version
1.2
Page 44 of 55
BUDGET WORKING DOCUMENT
Endorsed By:
Approved By:
Finance Director
f) For each line in the project chart which contains a total budget figure, enter:
(i) Budget Year – the project phasing that is expected to be incurred in the budget year.
(ii) Next Year – the project phasing that is expected to be incurred in the year following the budget year.
(iii) Later Amount – the project phasing that is expected to be incurred in the second and subsequent years following the budget year.
g) The Current Year Remainder and Current Year Total fields will be calculated based on the above. Confirm that these fields contain the correct values. If not, then:
(i) Correct Revised Budget amounts entered at stepe), or
(ii)Correct phasing amounts entered at step f).
h) Left click on the “OK” button.
i) Left click on the “Close” button.
11.4 Group Financial Plan
Finance Directorate is reviewing the use of JDE Edwards to record all Group Financial Plan data – both financial and quantitative data re production/manpower, etc. Initially the intention is to either utilize JDE and/or Excel to collate data for the 2008-12 Plan period.
document.docdocument.docdocument.doc
ABU DHABI NATIONAL OIL COMPANY
Effective Date
Volume Section Version
1.2
Page 45 of 55
BUDGET WORKING DOCUMENT
Endorsed By:
Approved By:
Finance Director
APPENDICES
12.1 Budget Timetable
document.docdocument.docdocument.doc
ABU DHABI NATIONAL OIL COMPANY
Effective Date
Volume Section Version
1.2
Page 46 of 55
BUDGET WORKING DOCUMENT
Endorsed By:
Approved By:
Finance Director
document.docdocument.docdocument.doc
12.2 Budget Preparation Reports – Uploading (Capex) – Finance Use Only
The following is a sample of the Budget Preparation Report, as created using JD Edwards OneWorld.
Done
Financial Systems & Procedures Division
12.3 Manpower Cost Rates For New Recruits
Currency AED Group A+ Group A Group B Group C Group D
Code Description Grade 18-20 Grade 14-17 Grade 11-13 Grade 07-10 Grade 01-06 Remarks UAE Others UAE Others UAE Others UAE Others UAE Others
6021 Basic Salary 36,500 25,000 17,900 16,800 12,200 11,0000 7,100 5,8008 4,200 3,100 Per month
6022 Supplementary Allowance 11,000 7,200 6,700 5,700 4700 4,100 2,300 1,800 1,400 900 Per month
6023 Overtime Per month
6025 In Lieu of Air Tickets 7,900 3,100 2,100 1,200 700 Per month
6026 EOSB / Pension 9,100 4,0000 5,300 2,800 3,600 1,900 2,3003 1,000 1,800 500 Per month
6027 Air Ticket / Baggage Allowance 5,000 1000 1,000 700 300 Per month
6028 Education Assistance 3,000 1,200 1.700 1,200 800 1,200 700 0 Per month
6031 Allowances - Job related
*Shift All'ce 260 260 260 260 260 260 260 260 260 260 Per month
*Disturbance All'ce 180 180 180 180 180 180 180 180 180 180 Per month
*Site All'ce 4,000 750 4,000 740 3,800 720 2,500 500 1,100 Per month
6032 Allowances Social 2,600 1,900 1400 1.6 2,600 Per month
*Child All'ce 600 600 600 600 600 Per month
6033 Allowances Housing 8,700 10,200 6,900 5.0 2,000 1200 Per month
6034 Allowances Furniture 80,000 47,000 47,000 47,000 33,000 33,000 26,000 26,000 0.0 0.0 Once a time
6035 Allowance - Car As applicable - - - - - - - - - Every 2 years
6036 Allowances In Lieu of Electric 800 800 600 600 600 600 400 400 400 200 Per month
6037 Car, Maintenance & Fuel Allow. 13200 - - - - - - - - - Per annum
6042 Employee Insurance Others 900 600 400 400 300 300 200 100 100 100 Per monthDone
Financial Systems & Procedures Division
12.4 Insurance Premiums
Insurance Policy Object No. Guideline Budget To Be Prepared By
Fire & Extended Perils 6432 Based on declared asset value including additions for the renewal period and using premium rate(s).
Procurement Division (SSD) for ADNOC-HQ under BU 16920 without reallocation.
Third Party Liability 6432 Based on declared payroll/revenue/risk exposure wherever applicable using premium rate(s).
Includes M/S marine liability and aviation fuelling liability.
Procurement Division (SSD) – Group Risk Management Department for ADNOC-HQ under BU 16920 without reallocation.
Motor Insurance 6487 Use applicable policy rates calculated on the expected declared sums insured.
Administration Directorate – General Services Division for ADNOC HQ’s owned vehicles.
Petroleum Ports Authority for their vehicles.
Directorate’s capital project.
Bunkering Transit 6635 Use budgeted volume and applicable policy rates(s).
Marketing & Refining Directorate for hydrocarbon products shipments.
Theft & Dishonesty 6432 Use the existing lump sum premium to be allocated according to the declared values of the applicable risk factors.
Procurement Division (SSD) – Group Risk Management Department for ADNOC H.Q. under BU 16920.
Combined Construction All Risks Use contract values and applicable policy rate(s).
Concerned Directorates for their Capital Budget.
Financial Systems & Procedures Division
Insurance Policy Object No. Guideline Budget To Be Prepared By
Navigational Aids 6432 Use expected replacement values and applicable policy rates(s).
SPC under BU’s of Petroleum Ports Authority (29110), Oil Spill Response Centre (29120)
Medical Malpractice 6432 Use the existing lump sum premium based on the number of medical staff.
Shares services Directorate – Group Risk Management Department, and inform Administration Directorate accordingly.
Open Transit Insurance(excluding oil & related products)
6432 Based on expected shipment value/turnover and applicable policy rate(s).
Concerned Directorates.
Sports policy 6431 Based on the current sum insured and lump sum premium.
Shared services Directorate – Group Risk Management Department under BU 16920 without reallocation.
Medical insurance ( Daman) 6434 Employees medical insurance Administration Directorate - Medical Services Department under B U 17250
ADNOC Group Marine Hull and Machinery Blanket Policy:
6465 Based on the current insured and lump sum premium.
Based on the declared sum insured and applicable (tendered) rate(s). (The actual rate will be determined during the first quarter of.
hared services Directorate – Group Risk Management Department under BU 17420 without reallocation.
Group Companies Vessels etc. Shared Services Directorate – Group Risk Management Department, and the premium to be allocated to concerned Group Companies according to their sums insured.
ADNOC Fishing Boats 6332 Apply policy rates to the expected declared sums insured.
Human Resources & Administration Directorate
ADNOC Group Life, Accident, Illness, Medical Expenses and Dread Disease Scheme
6042 Apply the policy rate to the estimated basic salaries for, to calculate the insurance cost.
This rate is subject to adjustment based on the declared basic salaries at each year-end.
Group Finance Controller Division – Group Budget and Control Team
Financial Systems & Procedures Division
ABU DHABI NATIONAL OIL COMPANY
Effective Date
Volume Section Version
1.2
Page 51 of 55
BUDGET WORKING DOCUMENT
Endorsed By:
Approved By:
Finance Director
12.5 Exchange Rates Against UAE Dirham (AED) as at July 31st, 2007
Apply the exchange rates provided by GTD
CURRENCY DEALING RATES AS ON
Abbreviation CURRENCY NAME Factor1
GBP POUND STERLING 7.5016DKK DANISH KRONER 0.6836NZD NEW ZEALAND DOLLAR 2.8314NOK NORWEGIAN KRONER 0.6336SEK SWEDISH KRONER 0.5536CHF SWISS FRANC 3.0866USD U.S. DOLLAR 3.6780CAD CANADIAN DOLLAR 3.4773BHD BAHRAINI DINAR 9.7631JOD JORDANIAN DINAR 5.2548KWD KUWAITI DINAR 13.0919LBP LEBANESE POUND REFEROMR RIAL OMANI 9.5701QAR QATARI RIYAL 1.0142SAR SAUDI RIYAL 0.9847YER YEMENI RIYAL REFEREGP EGYPTIAN POUND 0.6920MAD MOROCCO DIRHAM 0.4539AUD AUSTRALIAN DOLLAR 3.1689HKD HONG KONG DOLLAR 0.4749INR INDIAN RUPEE 0.0923JPY JAPANESE YEN 0.0315LKR SRI LANKAN RUPEE 0.0339PKR PAK RUPEE 0.0615SGD SINGAPORE DOLLAR 2.4448CYP CYPRUS POUND 8.7646EUR EURO 5.0772USD PRIME RATE 8.2500GBP BASE RATE 5.7500
1 Factor: To calculate UAE Dirham, Currency * Factor= Value in AED e.g.500USD*3.673=1836.5
ABU DHABI NATIONAL OIL COMPANY
Effective Date
Volume Section Version
1.2
Page 52 of 55
BUDGET WORKING DOCUMENT
Endorsed By:
Approved By:
Finance Director
12.6 Utilities Rates
Apply the utilities rates as provided by TAKREER
Utilities Type Units Rate for Outlook
Rate for Budget
AED AED
Electricity MWh 163 163
Sea water ’000 M³ 56 56
Distillate water M³ 8 8
Potable water M³ 10 10
Note: These are rates from previous year and will be updated in September 2007
12.7 Manpower Rates for Capitalised Expenses
Grad
e
Gros
s Sa
lary
/M
onth
Sala
ry +
L F
/ M
onth
Gros
s Sa
lary
/M
onth
Sala
ry +
L F
/ M
onth
Acco
m/M
onth
Acco
m +
L F
/ M
onth
Acco
m/M
onth
Acco
m +
L F
/ M
onth
Med
ical
/Mon
th
Med
ical
+ L
F/
Mon
th
U A
E
Othe
rs
7 8,093 11,268 5,756 8,014 6,833 9,514 5,583 7,774 329 459 21,240 16,246 8 9,745 13,568 6,545 9,112 6,833 9,514 5,583 7,774 329 459 23,540 17,344 9 11,584 16,128 8,134 11,324 8,500 11,834 6,417 8,934 329 459 28,421 20,717 10 12,153 16,920 9,117 12,693 8,500 11,834 6,417 8,934 329 459 29,213 22,086 11 15,912 22,247 10,648 14,887 11,000 15,379 6,833 9,554 329 461 38,087 24,901 12 16,903 23,633 12,321 17,226 11,000 15,379 6,833 9,554 329 461 39,473 27,240 13 18,877 26,393 14,445 20,195 11,833 16,544 7,667 10,719 329 461 43,398 31,375 14 21,676 30,474 16,294 22,909 11,833 16,637 7,667 10,779 329 463 47,574 34,151 15 24,141 33,941 18,370 25,827 15,167 21,323 10,167 14,294 329 463 55,727 40,584 16 27,231 38,285 20,108 28,271 15,167 21,323 10,167 14,294 329 463 60,072 43,028 17 30,879 43,413 22,064 31,021 17,667 24,838 12,667 17,808 329 463 68,715 49,293 18 36,402 51,179 26,975 37,925 17,667 24,838 12,667 17,808 329 463 76,480 56,197
UAE / Others
Total cost / monthU A E Others U A E Others
ABU DHABI NATIONAL OIL COMPANY
Effective Date
Volume Section Version
1.2
Page 53 of 55
BUDGET WORKING DOCUMENT
Endorsed By:
Approved By:
Finance Director
Note: These are rates from previous year and will be updated in September 2007
ABU DHABI NATIONAL OIL COMPANY
Effective Date
Volume Section Version
1.2
Page 54 of 55
BUDGET WORKING DOCUMENT
Endorsed By:
Approved By:
Finance Director
12.8 Abbreviations
Abbreviation Directorate/Division
ATI ADNOC Technical Institute
GBCT Group Budget and Control Team
PCD Petrochemicals Directorate
CEO Chief Executive Officer
CPD Civil Projects Division
E&P Exploration & Production Directorate
GFCD Group Finance Controller Division
FD Finance Directorate
GFPSD Group Financial Policies and Systems Division
GNRD Group National Recruitment Division
GSD General Services Division
HR Human Resources Directorate
I.AUDIT Internal Audit Division
ISTD Information Systems & Technology Division
LEG Legal Division
M&R Marketing & Refining Directorate
OD Organisation Development Division
PECD Petroleum Export & Control Division
PI Petroleum Institute
PPA Petroleum Ports Authority
SCHL Scholarship Department
SPC Supreme Petroleum Council
SSD Shared Services Directorate
GTD Group Treasury Division
UCD User/Concerned Directorate
ADMIN Administration Directorate
ABU DHABI NATIONAL OIL COMPANY
Effective Date
Volume Section Version
1.2
Page 55 of 55
BUDGET WORKING DOCUMENT
Endorsed By:
Approved By:
Finance Director
13. ATTACHMENTS – (Refer to Excel File…2008 Budge & Plan Forms.xls)
Form Reference Submissions Required?
Budget Financial Plan
Budget Input Template – Opex, Revenue and Recharges Manpower and Financial Plan inputs
BIT-1 Required Required
Temporary Manpower Changes T-MPC Required Not required
Manpower Changes - 2007 outlook vs 2008 budget
MPC-1 Required Not required
Manpower Changes – 2008 budget MPC-2 Required Not required
Capital Budget – Equipment, Vehicles and Furniture
CB-12 Required Not required
Proposal To Close Projects CAPEX-II Required Not required
Capital Budget – Summary By Directorate CB-SUM Required Required
Cash Budget ADNOC-D Required Not required
Note: above forms will be issued in August / September 2007