2008 GOB - Project Summary by Building & Year Denver Public Schools Facilities Faciliites Planning Management A Lincoln 2009 FIRE DETECTION 001 FIRE DETECTION - Design for replacement of entire fire alarm system and removal of old equipment not used in new system. Comply with DPS Design and Construction Standards SECTION 16721: FIRE ALARM SYSTEMS (POINT GRAPHIC SYSTEMS) and all other applicable 2012 ADA COMPLIANCE 001 REGULATORY - EGRESS / DOOR HARDWARE - Replace exterior door hardware for ADA compliance - A/E should conduct a door hardware schedule. Scope includes exterior doors (with panics if necessary), stairwell doors and hinges. A/E should identify any possible abatement issues to DPS Bond Hazmat project managers for remediation as early as possible. SAFETY / STAGE RIGGING 001 HEALTH SAFETY / STAGE RIGGING - See Consultants Report (Danny Reid) Admin Building 2010 FIRE DETECTION 001 FIRE DETECTION - Provide a full analysis of the entire fire detection system and fire sprinkler system in relation to Denver High-Riser requirements and design correction for all deficiencies. Design correct coverage and location of fire alarm sensors and remote lights which have become improperly placed during remodeling and renovations. Comply with DPS Design and Construction Standards SECTION 15300: STANDPIPE AND FIRE SPRINKLER STANDARDS and SECTION 16721: FIRE ALARM SYSTEMS (POINT GRAPHIC SYSTEMS) and all other applicable DPS Standards. Patch and Repair. All City E Stands 2009 OUTDOOR BLEACHERS 002 SAFETY - BLEACHERS - REPLACE ALL BLEACHER SEATING All City W Stands 2009 OUTDOOR BLEACHERS 003 SAFETY - BLEACHERS - REPLACE ALL BLEACHER SEATING All City (inclusive) 2009 FENCING (EXTERIOR) 001 FENCING (EXTERIOR) - Replace chain link fencing with 10' high vinyl coated fencing. Provide upper section of fine mesh to reduce unauthorized access. 2011 2008 bond for the web Page 1 of 91

Transcript of 2008 GOB - Project Summary by Building & Year Denver...

2008 GOB - Project Summary by Building & Year Denver Public Schools Facilities Faciliites Planning Management

A Lincoln 2009 FIRE DETECTION 001 FIRE DETECTION - Design for replacement of entire fire alarm system and removal of old equipment not used in new system. Comply with DPS Design and Construction Standards SECTION 16721: FIRE ALARM SYSTEMS (POINT GRAPHIC SYSTEMS) and all other applicable

2012 ADA COMPLIANCE 001 REGULATORY - EGRESS / DOOR HARDWARE - Replace exterior door hardware for ADA compliance - A/E should conduct a door hardware schedule. Scope includes exterior doors (with panics if necessary), stairwell doors and hinges. A/E should identify any possible abatement issues to DPS Bond Hazmat project managers for remediation as early as possible.

SAFETY / STAGE RIGGING 001 HEALTH SAFETY / STAGE RIGGING - See Consultants Report (Danny Reid)

Admin Building 2010 FIRE DETECTION 001 FIRE DETECTION - Provide a full analysis of the entire fire detection system and fire sprinkler system in relation to Denver High-Riser requirements and design correction for all deficiencies. Design correct coverage and location of fire alarm sensors and remote lights which have become improperly placed during remodeling and renovations. Comply with DPS Design and Construction Standards SECTION 15300: STANDPIPE AND FIRE SPRINKLER STANDARDS and SECTION 16721: FIRE ALARM SYSTEMS (POINT GRAPHIC SYSTEMS) and all other applicable DPS Standards. Patch and Repair.

All City E Stands 2009 OUTDOOR BLEACHERS 002 SAFETY - BLEACHERS - REPLACE ALL BLEACHER SEATING

All City W Stands 2009 OUTDOOR BLEACHERS 003 SAFETY - BLEACHERS - REPLACE ALL BLEACHER SEATING

All City (inclusive) 2009 FENCING (EXTERIOR) 001 FENCING (EXTERIOR) - Replace chain link fencing with 10' high vinyl coated fencing. Provide upper section of fine mesh to reduce unauthorized access.

2011 2008 bond for the web Page 1 of 91

2008 GOB - Project Summary by Building & Year Denver Public Schools Facilities Faciliites Planning Management

All City (inclusive) 2011 TRACK (SYNTHETIC) 001 Track (Synthetic) - RESUFACE RUNNING TRACK - REPAIR DAMAGE (INCLUDED IN FIELD REPLACEMENT COST - PROJECT IS FOR SEPARATE TRACK REFURBISHMENT)

All District Facilities 2009 FIRE DETECTION 001 FIRE ALARM SYSTEM - REPLACE EXISTING FIRE DEPARTMENT RADIO CALL BOX TRANSMITTERS IN ALL SCHOOLS

LEARNING LANDSCAPE 000 LEARNING LANDSCAPE - Contract and obtain site surveys for each new Learning Landscape project.

REGULATORY - RADIO TRANSMITTER MOVE 002 REGULATORY - RADIO TRANSMITTER MOVE - RELOCATE COMMUNICATIONS EQUIPMENT FROM LOOKOUT MOUNTAIN TO MOUNT MORRISON

BUILDING (REMODEL) 001 "BUCKET" FOR REMODELING AND MODULAR BUILDINGS FOR ECE EXPANSION TO FULL DAY PROGRAMS - INDIVIDUAL SITES TO BE DETERMINED

2010 HEALTH SAFETY / PAINT BOOTHS 000 HEALTH SAFETY / PAINT BOOTHS - Verify status & condition on-site. Repair, upgrade and make existing paint spray booths compliant with current codes. Remove booths that are not needed. See DSP HazMat PMs for list of schools and checkk list for evaluation.

2011 TECHNOLOGY 001 21st CENTURY LEARNING TECHNOLOGY MENU

2012 INTRUSION DETECTION 001 INTRUSION DETECTION - SECURITY INTEGRATION OF EXISTING SYSTEMS AND ENHANCEMENT WITH BUILDING AUTOMATION AND INTEGRATION

VIDEO SECURITY 002 Video Security - UPGRADE AND EXTEND DISTRICT VIDEO SURVEYLANCE SYSTEM

BUILDING (REMODEL) 002 PROVIDE BUILDING MODIFICATIONS RELATED TO CO-LOCATION OF NEW SCHOOLS WITH CURRENT OPERATIONS

2014

2008 bond for the web Page 2 of 91

2008 GOB - Project Summary by Building & Year Denver Public Schools Facilities Faciliites Planning Management

All District Facilities 2014 PROFESSIONAL CONSULTING & LEGAL 001 FUNDS FOR MISCELLANEOUS LEGAL, ESTIMATING AND CONSULTING SERVICES FOR ADMINISTRATION OF THE 2008 GOB

Amesse 2009 FOLDING LUNCHRM TABLES 001 FOLDING LUNCHRM TABLES - INSTALL SURFACE MOUNTED POCKET TABLES

IRRIGATION 001 IRRIGATION - Replace the item

LEARNING LANDSCAPE 001 LEARNING LANDSCAPE - Construct Learning Landscape per UCD Master Plan. Include 2" playground surface asphalt overlay..

FINISH RESTORATION 001 FINISH RESTORATION / PAINT - Repaint all surfaces to include but not limited to, all tile and hard ceilings, walls, doorjambs, doors, woodwork, ductwork, univents, radiators and built-in wood or metal cabinets, bathroom partitions painted or baked-on finish. All rooms, corridors, stairwells, closets, storage, mechanical rooms and piping per DPS piping color code. Duct cleaning is required in this scope.

ABSORPTION CHILLER 001 ABSORPTION CHILLER - Replace the item

2011 ROOFING 005 ROOFING - BUILT-UP - Built-Up roofing to include the following: Gravel, 4-ply membrane,replace existing perlite with 1/2" wood fiber, 1/8" taper insulation, replace exsiting polyisocyanurate insulation with 2 layers of 2" polyisocyanurate insulation, replace flashing per DPS specs at all walls, drains, conduits, flues, gas lines, exhausts curbs, thru-wall and overflow scuppers, skylights, A/C lines, expansion joints, and parapets. Replace all gaspipe and similiar stand supports bases with concete pavers, paint all existing gas piping per DPS specs. Replace and seal all existing pipe collars. Inspect/replace all applicable drains and gutters.

008 ROOFING - BUILT-UP - Built-Up roofing to include the following: Gravel, 4-ply membrane,replace existing perlite with 1/2" wood fiber, 1/8" taper insulation, replace exsiting polyisocyanurate insulation with 2 layers of 2" polyisocyanurate insulation, replace flashing per DPS specs at all walls, drains, conduits, flues, gas lines, exhausts curbs, thru-wall and overflow scuppers, skylights, A/C lines, expansion joints, and parapets. Replace all gaspipe and similiar stand supports bases with concete pavers, paint all existing gas piping per DPS specs. Replace and seal all existing pipe collars. Inspect/replace all applicable drains and gutters.

2008 bond for the web Page 3 of 91

2008 GOB - Project Summary by Building & Year Denver Public Schools Facilities Faciliites Planning Management

Archuleta 2009 TECHNOLOGY CONSTRUCTION SUPPORT 002 TECHNOLOGY CONSTRUCTION SUPPORT - Install dedicated air conditioning unit in the MDF.

LEARNING LANDSCAPE 001 Complete LL by installing missing elements.

Asbury 2011 FIRE SUPPRESSION / SPRINKLER 001 FIRE SPRINKLER SYSTEM - Design new fire sprinkler system throughout entire building. Comply with DPS Design and Construction Standards SECTION 15300: STANDPIPE AND FIRE SPRINKLER STANDARDS and all other applicable DPS Standards. Patch and Repair.

LEARNING LANDSCAPE 001 LEARNING LANDSCAPE - Construct Learning Landscape per UCD Master Plan. Include 2" playground surface asphalt overlay..

2012 FINISH RESTORATION 001 FINISH RESTORATION / CARPET - Replace the item

REGULATORY / LIGHT FIXTURES 001 REGULATORY LIGHT FIXTURES - Replace all T-12 and incandescent lighting fixtures with T-8 or T5HO fixtures. Properly dispose of all existing lamps and fixtures. Comply with DPS Design and Construction Standards SECTIONS 16501: LAMPS, 16502 BALLASTS AND CONTROLS and 16510: LUMINAIRES and all other applicable DPS Standards. Patch and Repair.

TOILET ROOM (INCLUSIVE) 001 Toilet Room (inclusive) - Replace all fixtures, plumbing piping and partitions. Paint walls and Ceilings. Replace tile as required. Lighting to be updated. Repair any associated surface damage, i.e., glazed block, etc.

Ash Grove 2010 FINISH RESTORATION 001 FINISH RESTORATION - VCT TILE Replace exsting tile in cafeteria, hallway, stairwell with new VCT per DPS specification. Include adjoining storage rooms. Coordinate with DPS Hazmat PM. Price excludes abatement.

2011 WINDOWS 001 METAL WINDOWS - Replace the item

2008 bond for the web Page 4 of 91

2008 GOB - Project Summary by Building & Year Denver Public Schools Facilities Faciliites Planning Management

Ashley 2009 VIDEO SECURITY 001 Video Security - Install A/C in MDF, build wall to close off MDF from book storage room

2010 FIRE SUPPRESSION / SPRINKLER 001 FIRE SPRINKLER SYSTEM - Design for replacement of entire fire alarm system and removal of old equipment not used in new system. Comply with DPS Design and Construction Standards SECTION 16721: FIRE ALARM SYSTEMS (POINT GRAPHIC SYSTEMS) and all other applicable DPS Standards. Patch and Repair.

LEARNING LANDSCAPE 001 LEARNING LANDSCAPE - Construct Learning Landscape per UCD Master Plan. Reference @ WWW.learninglandscapes.org. - Conduct soils asphalt and other pertinent testing prior to bid development.

2012 ADA COMPLIANCE 001 ADA COMPLIANCE - LEVEL 1 - Comply with DPS Design and Construction Standards SECTION 00700: ACCESSIBILITY STANDARDS and all other applicable DPS Standards. See ADA Level 1 Database provided. Deficiency remedies provided in ADA database should serve as the PM guide only and should not be provided to the A/E for purposes of developing the project scope of work. A/E is directed to conduct a building survey limited to the areas identified in the survey. Other ADA deficiencies may be included if they meet the level 1 status and have not been identified in the survey. All questions of possible oversight of a deficiency shall be directed to DPS Facility Planning through the DPS Project Manager.

FINISH RESTORATION 001 FINISH RESTORATION / CARPET - Replace the item

TOILET ROOM (INCLUSIVE) 001 Toilet Room (inclusive) - Replace all fixtures, plumbing piping and partitions. Paint walls and Ceilings. Replace tile as required. Lighting to be updated. Repair any associated surface damage, i.e., glazed block, etc.

Balarat (all facilities) 2013 BUILDING (REMODEL) 001 BUILDING (REMODEL) - REPAIR / REPLACE VARIOUS OUT BUILDINGS AT BALARAT

BUILDING (REMODEL) 001 BUILDING (REMODEL) - REMODEL DORMITORIES (3) TO ACCOMMODATE ADDITIONAL STUDENT CAPACITY

2008 bond for the web Page 5 of 91

2008 GOB - Project Summary by Building & Year Denver Public Schools Facilities Faciliites Planning Management

Balarat Elk Lodge 2013 ROOFING 006 ROOFING - BUILT-UP - Built-Up roofing to include the following: Gravel, 4-ply membrane,replace existing perlite with 1/2" wood fiber, 1/8" taper insulation, replace exsiting polyisocyanurate insulation with 2 layers of 2" polyisocyanurate insulation, replace flashing per DPS specs at all walls, drains, conduits, flues, gas lines, exhausts curbs, thru-wall and overflow scuppers, skylights, A/C lines, expansion joints, and parapets. Replace all gaspipe and similiar stand supports bases with concete pavers, paint all existing gas piping per DPS specs. Replace and seal all existing pipe collars. Inspect/replace all applicable drains and gutters.

Barnum 2009 FINISH RESTORATION 001 FINISH RESTORATION / PAINT - Repaint all surfaces to include but not limited to, all tile and hard ceilings, walls, doorjambs, doors, woodwork, ductwork, univents, radiators and built-in wood or metal cabinets, bathroom partitions painted or baked-on finish. All rooms, corridors, stairwells, closets, storage, mechanical rooms and piping per DPS piping color code. Duct cleaning is required in this scope.

2010 LEARNING LANDSCAPE 001 LEARNING LANDSCAPE - Construct Learning Landscape per UCD Master Plan. Reference @ WWW.learninglandscapes.org. - Conduct soils asphalt and other pertinent testing prior to bid development. .

Barrett 2009 FOLDING LUNCHRM TABLES 001 FOLDING LUNCHRM TABLES - INSTALL SURFACE MOUNTED POCKET TABLES

FIRE SUPPRESSION / SPRINKLER 001 FIRE SPRINKLER SYSTEM - Design new fire sprinkler system throughout entire building. Comply with DPS Design and Construction Standards SECTION 15300: STANDPIPE AND FIRE SPRINKLER STANDARDS and all other applicable DPS Standards. Patch and Repair.

FIRE DETECTION 001 FIRE DETECTION SYSTEM - Panel only. No longer supported by Manufacture

ASPHALT PAVING 001 ASPHALT / VEHICLE PARKING AND DRIVEWAYS - 2" overlay with geotec material.

2011 WINDOWS 001 METAL WINDOWS - Replace the item

2013 REGULATORY / LIGHT FIXTURES 2008 bond for the web Page 6 of 91

2008 GOB - Project Summary by Building & Year Denver Public Schools Facilities Faciliites Planning Management

Barrett 2013 001 REGULATORY / LIGHT FIXTURES - Replace incandescents in gym, cafeteria and stairwells.

Beach Court 2010 HEALTH SAFETY / HAZARD ABATEMENT 001 HEALTH SAFETY HAZARD ABATEMENT -TREATED TIMBERS - Replace treated wood timber with recycled plastic timbers. Coordinate with ongoing parent project learning landscape projects.

LEARNING LANDSCAPE 001 LEARNING LANDSCAPE - Construct Learning Landscape per UCD Master Plan. Include 2" playground surface asphalt overlay. Remove existing and replace playground asphalt. Coordinate with treated timbers replacement. See master plan draft at www.learninglanscapes.org - Conduct soils asphalt and other pertinent testing prior to bid development.

2012 ADA COMPLIANCE 001 ADA COMPLIANCE - LEVEL 1 - Comply with DPS Design and Construction Standards SECTION 00700: ACCESSIBILITY STANDARDS and all other applicable DPS Standards. See ADA Level 1 Database provided. Deficiency remedies provided in ADA database should serve as the PM guide only and should not be provided to the A/E for purposes of developing the project scope of work. A/E is directed to conduct a building survey limited to the areas identified in the survey. Other ADA deficiencies may be included if they meet the level 1 status and have not been identified in the survey. All questions of possible oversight of a deficiency shall be directed to DPS Facility Planning through the DPS Project Manager.

FINISH RESTORATION 001 FINISH RESTORATION / CARPET - Replace the item

2013 FIRE SUPPRESSION / SPRINKLER 001 FIRE SPRINKLER SYSTEM - Design new fire sprinkler system throughout entire building. Comply with DPS Design and Construction Standards SECTION 15300: STANDPIPE AND FIRE SPRINKLER STANDARDS and all other applicable DPS Standards. Patch and Repair.

BLAIR 2009 LEARNING LANDSCAPE 002 INSTALL MISSING ELEMENTS TO COMPLETE LEARNING LANDSCAPE

Bradley 2009 FOLDING LUNCHRM TABLES 001 FOLDING LUNCHRM TABLES - INSTALL SURFACE MOUNTED POCKET TABLES

2008 bond for the web Page 7 of 91

2008 GOB - Project Summary by Building & Year Denver Public Schools Facilities Faciliites Planning Management

Bradley 2009 ASPHALT PAVING 001 ASPHALT / VEHICLE PARKING AND DRIVEWAYS - Replace the item

LEARNING LANDSCAPE 002 Complete LL by installing missing elements.

Bromwell 2009 REMODEL - SAFETY 002 BUILDING (REMODEL) - Install safety shower, eyewash, chemical storage cabinet and fume hood

FOLDING LUNCHRM TABLES 001 FOLDING LUNCHRM TABLES - INSTALL POCKET TABLES, UTILIZING EXISTING POCKET

BOILER 001 BOILER - Replace the item

002 BOILER - Replace the item

2010 WINDOWS 001 WINDOWS - METAL - Replace with current DPS standards. Coordinate with flooring and lab classroom work.

FINISH RESTORATION 001 FINISH RESTORATION - QUARRY TILE - Scope to include demo of existing seamless flooring and site prep. Include all kitchen and adjoining offices. Coordinate equipment disconnect , removal of equipment and food supplies, and final cleanup, with DPS Food Services kitchen. Flooring elevations to increase by 1/2". Adjust floor drains with plumbing, Walls and ceilings to be painted unless they are vinyl tiles.

Brown 2010 FLOORING / CARPET 001 FINISH RESTORATION - CARPET - Replace all worn classroom and office carpeting and base trim per DPS specs. Coordinate all necessary hazmat testing and abatement with DPS HazMat PMs. Scope to include breakdown and/or relocation of all non-fixed equipment. Maintain all vinyl flooring areas around sinks currently existing. Brown - Scope to include all of the 1st floor including the hallways with existing carpet, rooms 208, 216, 215, 214, and LMC on the 2nd, as well as staff lounge and custodial areas currently carpeted in the basement.

ASPHALT PAVING

2008 bond for the web Page 8 of 91

2008 GOB - Project Summary by Building & Year Denver Public Schools Facilities Faciliites Planning Management

Brown 2010 ASPHALT PAVING 001 ASPHALT REPLACEMENT - Replacement of existing areas of asphalt parking , concrete driveways, curbing, and walkways (if necessary), to be conducted in accordance with DPS specifications. Include all pertinent civil engineering, testing, and permitting as necessary. Striping, ADA parking space allocations and signage to be included per DPS/City of Denver code. Replace all impacted landscaping, sod, and irrigation equipment if necessary. Brown - (15,275 sf) Include parking blocks in lieu of piping. Mitigate grading site-wide. See DPS Planning for site specific plans and QA/QC evaluation/recommendations.

Bryant Webster

BUILDING SHELL / WOOD WINDOWS 001 Replace windows - restored windows 2003

2009 LEARNING LANDSCAPE 002 LEARNING LANDSCAPE - Complete LL -- remove asphalt play and replace -- install raised concrete area and install shade shelter - construct ampitheatre

2012 ADA COMPLIANCE 001 ADA COMPLIANCE - LEVEL 1 - Comply with DPS Design and Construction Standards SECTION 00700: ACCESSIBILITY STANDARDS and all other applicable DPS Standards. See ADA Level 1 Database provided. Deficiency remedies provided in ADA database should serve as the PM guide only and should not be provided to the A/E for purposes of developing the project scope of work. A/E is directed to conduct a building survey limited to the areas identified in the survey. Other ADA deficiencies may be included if they meet the level 1 status and have not been identified in the survey. All questions of possible oversight of a deficiency shall be directed to DPS Facility Planning through the DPS Project Manager.

REMODEL - SAFETY 002 REMODEL - SAFETY - Install safety shower, eyewash, chemical storage cabinet and fume hood

FINISH RESTORATION 001 FINISH RESTORATION / SEAMLESS FLR - replace all seamless with ceramic/quarry tile

TOILET ROOM (INCLUSIVE) 001 Toilet Room (inclusive) - Replace all fixtures, plumbing piping and partitions. Paint walls and Ceilings. Replace tile as required. Lighting to be updated. Repair any associated surface damage, i.e., glazed block, etc.

BUILDING (REMODEL) 001 BUILDING (REMODEL) - Remodel Library to provide additional space for K8 conversion collection of materials

2013 FIRE SUPPRESSION / SPRINKLER

2008 bond for the web Page 9 of 91

2008 GOB - Project Summary by Building & Year Denver Public Schools Facilities Faciliites Planning Management

Bryant Webster 2013 FIRE SUPPRESSION / SPRINKLER 001 FIRE SPRINKLER SYSTEM - Design new fire sprinkler system throughout entire building. Comply with DPS Design and Construction Standards SECTION 15300: STANDPIPE AND FIRE SPRINKLER STANDARDS and all other applicable DPS Standards. Patch and Repair.

Carson 2009 FOLDING LUNCHRM TABLES 001 FOLDING LUNCHRM TABLES - INSTALL POCKET TABLES, UTILIZING EXISTING POCKET

Castro 2010 FINISH RESTORATION 001 FINISH RESTORATION - CARPET - Replace all worn classroom and office carpeting and base trim per DPS specs. Coordinate all necessary hazmat testing and abatement with DPS HazMat PMs. Scope to include breakdown and/or relocation of all non-fixed equipment. Maintain all vinyl flooring areas around sinks currently existing in elementary areas. Castro- Replace damaged vinyl on stairs in the gym (no carpet replacement on gym floor). Replace office carpeting, add corridor tile replacement as an alternate and complete if funding permits.

2012 WINDOWS 001 METAL WINDOWS - Replace the item

CEC Middle College Denver 2009 VIDEO SECURITY 001 Video Security - Install Rack in MDF, move Equip.

2010 FINISH RESTORATION 001 FINISH RESTORATION - QUARRY TILE - Scope to include demo of existing seamless flooring and site prep. Include all kitchen and adjoining offices. Coordinate equipment disconnect , removal of equipment and food supplies, and final cleanup, with DPS Food Services kitchen. Flooring elevations to increase by 1/2". Adjust floor drains with plumbing, Walls and ceilings to be painted unless they are vinyl tiles.

Centennial 2009 FOLDING LUNCHRM TABLES 001 FOLDING LUNCHRM TABLES - INSTALL SURFACE MOUNTED POCKET TABLES

2008 bond for the web Page 10 of 91

2008 GOB - Project Summary by Building & Year Denver Public Schools Facilities Faciliites Planning Management

Centennial 2011 IRRIGATION 002 IRRIGATION - Replace portion of irrigation (Building Lawn) - Learning Landscape completed earlier.

2012 REMODEL - SAFETY 001 REMODEL - SAFETY - Install safety shower, eyewash, chemical storage cabinet and fume hood

FINISH RESTORATION 001 FINISH RESTORATION / SEAMLESS FLR - replace all seamless with ceramic/quarry tile

Cheltenham 2009 FOLDING LUNCHRM TABLES 001 FOLDING LUNCHRM TABLES - INSTALL SURFACE MOUNTED POCKET TABLES

2010 IRRIGATION 001 IRRIGATION - Repair/replace existing irrigation system, piping, controls, heads, backflows, electrical and connections per DPS standards. Cheltenham - Site area to includes 54,000 sf and includes building perimeter and right of way along Julien, 16th, and Irving. Site already on central clock which should be utilized. Add alternate for landscape irrigation and area within courtyard, funding permitting. See DPS Planning for site plans and QA/QC evaluations/recommendations.

ADA COMPLIANCE 001 ADA COMPLIANCE - LEVEL 1 - Comply with DPS Design and Construction Standards SECTION 00700: ACCESSIBILITY STANDARDS and all other applicable DPS Standards. See ADA Level 1 Database provided. Deficiency remedies provided in ADA database should serve as the PM guide only and should not be provided to the A/E for purposes of developing the project scope of work. A/E is directed to conduct a building survey limited to the areas identified in the survey. Other ADA deficiencies may be included if they meet the level 1 status and have not been identified in the survey. All questions of possible oversight of a deficiency shall be directed to DPS Facility Planning through the DPS Project Manager.

ABSORPTION CHILLER 001 ABSORBTION CHILLER - Replace with Centrifugal Water Chiller. Water treament included w/18 month warranty. Startup and commissioning included. Comply with DPS Design and Construction Standards SECTION 15650: REFRIGERATION, and all other applicable DPS Standards. Patch and repair.

WINDOWS 001 WINDOWS - METAL - Replace with current DPS standards. Coordinate with ongoing chiller replacement work on site.

2008 bond for the web Page 11 of 91

2008 GOB - Project Summary by Building & Year Denver Public Schools Facilities Faciliites Planning Management

Cole 2009 VIDEO SECURITY 001 Video Security - Re-check location

FINISH RESTORATION 001 FINISH RESTORATION / CARPET - Replace the item

TOILET ROOM (INCLUSIVE) 001 Toilet Room (inclusive) - Replace all fixtures, plumbing piping and partitions. Paint walls and Ceilings. Replace tile as required. Lighting to be updated. Repair any associated surface damage, i.e., glazed block, etc.

LEARNING LANDSCAPE 001 Install shade structure and complete Learning Landscape. Design and install missing elements

2012 FIRE SUPPRESSION / SPRINKLER 001 FIRE SUPPRESSION / SPRINKLER SYSTEM - Install new Fire Sprinkler system throughout building. Construction Documents prepared - project Not executed.

Colfax 2009 ADA COMPLIANCE 001 ADA COMPLIANCE - LEVEL 1 - Comply with DPS Design and Construction Standards SECTION 00700: ACCESSIBILITY STANDARDS and all other applicable DPS Standards. See ADA Level 1 Database provided. Deficiency remedies provided in ADA database should serve as the PM guide only and should not be provided to the A/E for purposes of developing the project scope of work. A/E is directed to conduct a building survey limited to the areas identified in the survey. Other ADA deficiencies may be included if they meet the level 1 status and have not been identified in the survey. All questions of possible oversight of a deficiency shall be directed to DPS Facility Planning through the DPS Project Manager.

FINISH RESTORATION 001 FINISH RESTORATION / PAINT - Repaint all surfaces to include but not limited to, all tile and hard ceilings, walls, doorjambs, doors, woodwork, ductwork, univents, radiators and built-in wood or metal cabinets, bathroom partitions painted or baked-on finish. All rooms, corridors, stairwells, closets, storage, mechanical rooms and piping per DPS piping color code. Duct cleaning is required in this scope.

REGULATORY / LIGHT FIXTURES 001 REGULATORY / LIGHT FIXTURES - Replace fixtures in Kitchen and 4 classrooms.

College View 2009 VIDEO SECURITY 001 Video Security - Re-check location, Build Wall in MDF, install A/C

2008 bond for the web Page 12 of 91

2008 GOB - Project Summary by Building & Year Denver Public Schools Facilities Faciliites Planning Management

College View 2009 FIRE DETECTION 001 FIRE DETECTION SYSTEM - Panel only. No longer supported by Manufacture

2010 FINISH RESTORATION 001 FINISH RESTORATION - CARPET - Replace all worn classroom and office carpeting and base trim per DPS specs. Coordinate all necessary hazmat testing and abatement with DPS HazMat PMs. Scope to include breakdown and/or relocation of all non-fixed equipment. Maintain all vinyl flooring areas around sinks currently existing in elementary areas.

Columbian 2009 FOLDING LUNCHRM TABLES 001 FOLDING LUNCHRM TABLES - INSTALL SURFACE MOUNTED POCKET TABLES

FINISH RESTORATION 001 FINISH RESTORATION / PAINT - Repaint all surfaces to include but not limited to, all tile and hard ceilings, walls, doorjambs, doors, woodwork, ductwork, univents, radiators and built-in wood or metal cabinets, bathroom partitions painted or baked-on finish. All rooms, corridors, stairwells, closets, storage, mechanical rooms and piping per DPS piping color code. Duct cleaning is required in this scope.

FINISH RESTORATION 001 FINISH RESTORATION / CARPET - Replace the item

FIRE DETECTION 001 FIRE DETECTION SYSTEM - Kidde panel- obsolete cannot get parts for repair

LEARNING LANDSCAPE 001 LEARNING LANDSCAPE - CORRECT DRAINAGE PROBLEMS AT LEARNING LANDSCAPE. CLEAR DRAINS AND/OR INSTALL DRYWELLS TO ABSORB EXCESS SURFACE DRAINAGE. (Drain at north side of building, off gymnasium, will require engineering to solve water load from entering building at this set of doors. Work will include drain modification and concrete replacement)

2010 VIDEO SECURITY 001 A/C INSTALLATION IN MDF - Design a console type, split-system, air-conditioning system for the Main Distribution Frame (MDF) room. Comply with DPS Design and Construction Standards SECTION 15651: COMPUTER ROOM AIR CONDITIONING and all other applicable DPS Standards. Coordinate roof-mounted equipment design with any existing roof membrane warranty in effect. Design proper protective enclosure for condenser location including but not limited to damage from hail. Patch and repair.

2008 bond for the web Page 13 of 91

2008 GOB - Project Summary by Building & Year Denver Public Schools Facilities Faciliites Planning Management

Columbine 2009 FINISH RESTORATION 001 FINISH RESTORATION / TILE - Replace the item

FINISH RESTORATION 001 FINISH RESTORATION / VINYL TILE - Replace existing VAT or VCT with new VCT except VCT entryways in classrooms which have been replaced.. Price does not include abatement.

VIDEO SECURITY 001 Video Security - Re-check, build wall, install A/C

CONCRETE / SITE STEPS 001 CONCRETE / SITE STEPS - Replace the item - Update required after 2003 completion of Learning Landscape.

IRRIGATION 001 IRRIGATION - Replace the item - Update required after 2003 completion of Learning Landscape.

LEARNING LANDSCAPE 001 LEARNING LANDSCAPE - Complete Learning Landscape per UCD Master Plan. - ECE area - restripe parking lot. - Update required after 2003 completion of Learning Landscape.

2012 WINDOWS 001 Replace

Columbine P E C 2009 REGULATORY / LIGHT FIXTURES 001 REGULATORY LIGHT FIXTURES - Replace all T-12 and incandescent lighting fixtures with T-8 or T5HO fixtures. Properly dispose of all existing lamps and fixtures. Comply with DPS Design and Construction Standards SECTIONS 16501: LAMPS, 16502 BALLASTS AND CONTROLS and 16510: LUMINAIRES and all other applicable DPS Standards. Patch and Repair.

BUILDING (REMODEL) 001 Renovation of lower level to accommodate New Schools Program. Work to consist of painting, new electrical, and data to support a 50-student computer lab.

Cory 2009 FINISH RESTORATION 001 FINISH RESTORATION / VINYL TILE - Replace existing VAT or VCT with new VCT. Price does not include abatement.

2010 2008 bond for the web Page 14 of 91

2008 GOB - Project Summary by Building & Year Denver Public Schools Facilities Faciliites Planning Management

Cory 2010 REGULATORY / LIGHT FIXTURES 001 REGULATORY LIGHT FIXTURES - Replace all T-12 and incandescent lighting fixtures with T-8 or T5HO fixtures. Properly dispose of all existing lamps and fixtures. Comply with DPS Design and Construction Standards SECTIONS 16501: LAMPS, 16502 BALLASTS AND CONTROLS and 16510: LUMINAIRES and all other applicable DPS Standards. Patch and Repair.

WINDOWS 001 WINDOWS - METAL - Replace with current DPS standards. Cory is listed as a historic landmark. Coordinate design review with Denver Landmark Preservation Commission.

2011 LEARNING LANDSCAPE 001 LEARNING LANDSCAPE - Construct Learning Landscape per UCD Master Plan. Include 2" playground surface asphalt overlay..

Cowell 2009 VIDEO SECURITY 001 Video Security - Re-check, Install Rack MDF or High Density

FOLDING LUNCHRM TABLES 001 FOLDING LUNCHRM TABLES - INSTALL SURFACE MOUNTED POCKET TABLES

ADA COMPLIANCE 001 ADA COMPLIANCE - LEVEL 1 - Comply with DPS Design and Construction Standards SECTION 00700: ACCESSIBILITY STANDARDS and all other applicable DPS Standards. See ADA Level 1 Database provided. Deficiency remedies provided in ADA database should serve as the PM guide only and should not be provided to the A/E for purposes of developing the project scope of work. A/E is directed to conduct a building survey limited to the areas identified in the survey. Other ADA deficiencies may be included if they meet the level 1 status and have not been identified in the survey. All questions of possible oversight of a deficiency shall be directed to DPS Facility Planning through the DPS Project Manager.

REGULATORY / LIGHT FIXTURES 001 REGULATORY / LIGHT FIXTURES - Replace incandescent Gym lights.

2011 WINDOWS 001 METAL WINDOWS - Replace the item

2008 bond for the web Page 15 of 91

2008 GOB - Project Summary by Building & Year Denver Public Schools Facilities Faciliites Planning Management

D C I S 2013 ROOFING 002 ROOFING - BUILT-UP - Built-Up roofing to include the following: Gravel, 4-ply membrane,replace existing perlite with 1/2" wood fiber, 1/8" taper insulation, replace exsiting polyisocyanurate insulation with 2 layers of 2" polyisocyanurate insulation, replace flashing per DPS specs at all walls, drains, conduits, flues, gas lines, exhausts curbs, thru-wall and overflow scuppers, skylights, A/C lines, expansion joints, and parapets. Replace all gaspipe and similiar stand supports bases with concete pavers, paint all existing gas piping per DPS specs. Replace and seal all existing pipe collars. Inspect/replace all applicable drains and gutters.

012 ROOFING - BUILT-UP - Built-Up roofing to include the following: Gravel, 4-ply membrane,replace existing perlite with 1/2" wood fiber, 1/8" taper insulation, replace exsiting polyisocyanurate insulation with 2 layers of 2" polyisocyanurate insulation, replace flashing per DPS specs at all walls, drains, conduits, flues, gas lines, exhausts curbs, thru-wall and overflow scuppers, skylights, A/C lines, expansion joints, and parapets. Replace all gaspipe and similiar stand supports bases with concete pavers, paint all existing gas piping per DPS specs. Replace and seal all existing pipe collars. Inspect/replace all applicable drains and gutters.

013 ROOFING - BUILT-UP - Built-Up roofing to include the following: Gravel, 4-ply membrane,replace existing perlite with 1/2" wood fiber, 1/8" taper insulation, replace exsiting polyisocyanurate insulation with 2 layers of 2" polyisocyanurate insulation, replace flashing per DPS specs at all walls, drains, conduits, flues, gas lines, exhausts curbs, thru-wall and overflow scuppers, skylights, A/C lines, expansion joints, and parapets. Replace all gaspipe and similiar stand supports bases with concete pavers, paint all existing gas piping per DPS specs. Replace and seal all existing pipe collars. Inspect/replace all applicable drains and gutters.

014 ROOFING - BUILT-UP - Built-Up roofing to include the following: Gravel, 4-ply membrane,replace existing perlite with 1/2" wood fiber, 1/8" taper insulation, replace exsiting polyisocyanurate insulation with 2 layers of 2" polyisocyanurate insulation, replace flashing per DPS specs at all walls, drains, conduits, flues, gas lines, exhausts curbs, thru-wall and overflow scuppers, skylights, A/C lines, expansion joints, and parapets. Replace all gaspipe and similiar stand supports bases with concete pavers, paint all existing gas piping per DPS specs. Replace and seal all existing pipe collars. Inspect/replace all applicable drains and gutters.

015 ROOFING - BUILT-UP - Built-Up roofing to include the following: Gravel, 4-ply membrane,replace existing perlite with 1/2" wood fiber, 1/8" taper insulation, replace exsiting polyisocyanurate insulation with 2 layers of 2" polyisocyanurate insulation, replace flashing per DPS specs at all walls, drains, conduits, flues, gas lines, exhausts curbs, thru-wall and overflow scuppers, skylights, A/C lines, expansion joints, and parapets. Replace all gaspipe and similiar stand supports bases with concete pavers, paint all existing gas piping per DPS specs. Replace and seal all existing pipe collars. Inspect/replace all applicable drains and gutters.

016 ROOFING - BUILT-UP - Built-Up roofing to include the following: Gravel, 4-ply membrane,replace existing perlite with 1/2" wood fiber, 1/8" taper insulation, replace exsiting polyisocyanurate insulation with 2 layers of 2" polyisocyanurate insulation, replace flashing per DPS specs at all walls, drains, conduits, flues, gas lines, exhausts curbs, thru-wall and overflow scuppers, skylights, A/C lines, expansion joints, and parapets. Replace all gaspipe and similiar stand supports bases with concete pavers, paint all existing gas piping per DPS specs. Replace and seal all existing pipe collars. Inspect/replace all applicable drains and gutters.

017 ROOFING - BUILT-UP - Built-Up roofing to include the following: Gravel, 4-ply membrane,replace existing perlite with 1/2" wood fiber, 1/8" taper insulation, replace exsiting polyisocyanurate insulation with 2 layers of 2" polyisocyanurate insulation, replace flashing per DPS specs at all walls, drains, conduits, flues, gas lines, exhausts curbs, thru-wall and overflow scuppers, skylights, A/C lines, expansion joints, and parapets. Replace all gaspipe and similiar stand supports bases with concete pavers, paint all existing gas piping per DPS specs. Replace and seal all existing pipe collars. Inspect/replace all applicable drains and gutters.

STAGE CURTAIN / AUDITORIUM 001 STAGE CURTAIN / AUDITORIUM - Replace all curtains and make rigging corrections

2008 bond for the web Page 16 of 91

2008 GOB - Project Summary by Building & Year Denver Public Schools Facilities Faciliites Planning Management

D O T S 2013 TECHNOLOGY - INFRASTRUCTURE 001 INSTRUCTIONAL MANAGEMENT SYSTEM / STUDENT PERFORMANCE SYSTEM

001 Replace End-of-Life School Based District Equipment

D P S Training Technology 2010 ASPHALT PAVING 001 ASPHALT REPLACEMENT - Replace 110,168 sq.ft of asphalt on "old public service lot" with 2" overlay with geotec material. To be conducted in accordance with DPS specifications nclude all pertinent civil engineering, testing, and permitting as necessary. Striping, ADA parking space allocations, and signage to be included per DPS/City of Denver code. Restrip to segregate and allow for large DPS fleet vehicles. Remove fencing dividing current lot. Add concrete to lot main drive. See DPS Planning for site specific plans and QA/QC evaluation/recommendations.

2011 FIRE SUPPRESSION / SPRINKLER 001 FIRE SUPPRESSION / BACKFLOW PREVENTOR - INSTALL FIRE SUPPRESSION BACKFLOW PROTECTION

Denison 2011 LEARNING LANDSCAPE 001 LEARNING LANDSCAPE - Construct Learning Landscape per UCD Master Plan. Include 2" playground surface asphalt overlay..

2013 REGULATORY / LIGHT FIXTURES 001 REGULATORY LIGHT FIXTURES - Replace all T-12 and incandescent lighting fixtures with T-8 or T5HO fixtures. Properly dispose of all existing lamps and fixtures. Comply with DPS Design and Construction Standards SECTIONS 16501: LAMPS, 16502 BALLASTS AND CONTROLS and 16510: LUMINAIRES and all other applicable DPS Standards. Patch and Repair.

Denver School of the Arts 2010 ROOFING 008 ROOFING - BUILT-UP - Regarding Deck# 08- Built-Up roofing to include the following: Gravel, 4-ply membrane,replace existing perlite with 1/2" wood fiber, 1/8" taper insulation, replace exsiting polyisocyanurate insulation with 2 layers of 2" polyisocyanurate insulation, replace flashing per DPS specs at all walls, drains, conduits, flues, gas lines, exhausts curbs, thru-wall and overflow scuppers, skylights, A/C lines, expansion joints, and parapets. Replace all gaspipe and similiar stand supports bases with concete pavers, paint all existing gas piping per DPS specs. Replace and seal all existing pipe collars. Inspect/replace all applicable drains and gutters.

2008 bond for the web Page 17 of 91

2008 GOB - Project Summary by Building & Year Denver Public Schools Facilities Faciliites Planning Management

Denver School of the Arts 2010 ROOFING 009 ROOFING - BUILT-UP - Regarding Deck# 09- Built-Up roofing to include the following: Gravel, 4-ply membrane,replace existing perlite with 1/2" wood fiber, 1/8" taper insulation, replace exsiting polyisocyanurate insulation with 2 layers of 2" polyisocyanurate insulation, replace flashing per DPS specs at all walls, drains, conduits, flues, gas lines, exhausts curbs, thru-wall and overflow scuppers, skylights, A/C lines, expansion joints, and parapets. Replace all gaspipe and similiar stand supports bases with concete pavers, paint all existing gas piping per DPS specs. Replace and seal all existing pipe collars. Inspect/replace all applicable drains and gutters.

012 ROOFING - BUILT-UP - Regarding Deck# 12- Built-Up roofing to include the following: Gravel, 4-ply membrane,replace existing perlite with 1/2" wood fiber, 1/8" taper insulation, replace exsiting polyisocyanurate insulation with 2 layers of 2" polyisocyanurate insulation, replace flashing per DPS specs at all walls, drains, conduits, flues, gas lines, exhausts curbs, thru-wall and overflow scuppers, skylights, A/C lines, expansion joints, and parapets. Replace all gaspipe and similiar stand supports bases with concete pavers, paint all existing gas piping per DPS specs. Replace and seal all existing pipe collars. Inspect/replace all applicable drains and gutters.

013 ROOFING - BUILT-UP - Regarding Deck# 13- Built-Up roofing to include the following: Gravel, 4-ply membrane,replace existing perlite with 1/2" wood fiber, 1/8" taper insulation, replace exsiting polyisocyanurate insulation with 2 layers of 2" polyisocyanurate insulation, replace flashing per DPS specs at all walls, drains, conduits, flues, gas lines, exhausts curbs, thru-wall and overflow scuppers, skylights, A/C lines, expansion joints, and parapets. Replace all gaspipe and similiar stand supports bases with concete pavers, paint all existing gas piping per DPS specs. Replace and seal all existing pipe collars. Inspect/replace all applicable drains and gutters.

014 ROOFING - BUILT-UP - Regarding Deck# 14- Built-Up roofing to include the following: Gravel, 4-ply membrane,replace existing perlite with 1/2" wood fiber, 1/8" taper insulation, replace exsiting polyisocyanurate insulation with 2 layers of 2" polyisocyanurate insulation, replace flashing per DPS specs at all walls, drains, conduits, flues, gas lines, exhausts curbs, thru-wall and overflow scuppers, skylights, A/C lines, expansion joints, and parapets. Replace all gaspipe and similiar stand supports bases with concete pavers, paint all existing gas piping per DPS specs. Replace and seal all existing pipe collars. Inspect/replace all applicable drains and gutters.

019 ROOFING - BUILT-UP - Regarding Deck# 19- Built-Up roofing to include the following: Gravel, 4-ply membrane,replace existing perlite with 1/2" wood fiber, 1/8" taper insulation, replace exsiting polyisocyanurate insulation with 2 layers of 2" polyisocyanurate insulation, replace flashing per DPS specs at all walls, drains, conduits, flues, gas lines, exhausts curbs, thru-wall and overflow scuppers, skylights, A/C lines, expansion joints, and parapets. Replace all gaspipe and similiar stand supports bases with concete pavers, paint all existing gas piping per DPS specs. Replace and seal all existing pipe collars. Inspect/replace all applicable drains and gutters.

020 ROOFING - BUILT-UP - Regarding Deck# 20- Built-Up roofing to include the following: Gravel, 4-ply membrane,replace existing perlite with 1/2" wood fiber, 1/8" taper insulation, replace exsiting polyisocyanurate insulation with 2 layers of 2" polyisocyanurate insulation, replace flashing per DPS specs at all walls, drains, conduits, flues, gas lines, exhausts curbs, thru-wall and overflow scuppers, skylights, A/C lines, expansion joints, and parapets. Replace all gaspipe and similiar stand supports bases with concete pavers, paint all existing gas piping per DPS specs. Replace and seal all existing pipe collars. Inspect/replace all applicable drains and gutters.

021 ROOFING - BUILT-UP - Regarding Deck# 21- Built-Up roofing to include the following: Gravel, 4-ply membrane,replace existing perlite with 1/2" wood fiber, 1/8" taper insulation, replace exsiting polyisocyanurate insulation with 2 layers of 2" polyisocyanurate insulation, replace flashing per DPS specs at all walls, drains, conduits, flues, gas lines, exhausts curbs, thru-wall and overflow scuppers, skylights, A/C lines, expansion joints, and parapets. Replace all gaspipe and similiar stand supports bases with concete pavers, paint all existing gas piping per DPS specs. Replace and seal all existing pipe collars. Inspect/replace all applicable drains and gutters.

2008 bond for the web Page 18 of 91

2008 GOB - Project Summary by Building & Year Denver Public Schools Facilities Faciliites Planning Management

Denver School of the Arts 2010 ROOFING 028 ROOFING - BUILT-UP - Regarding Deck# 28- Built-Up roofing to include the following: Gravel, 4-ply membrane,replace existing perlite with 1/2" wood fiber, 1/8" taper insulation, replace exsiting polyisocyanurate insulation with 2 layers of 2" polyisocyanurate insulation, replace flashing per DPS specs at all walls, drains, conduits, flues, gas lines, exhausts curbs, thru-wall and overflow scuppers, skylights, A/C lines, expansion joints, and parapets. Replace all gaspipe and similiar stand supports bases with concete pavers, paint all existing gas piping per DPS specs. Replace and seal all existing pipe collars. Inspect/replace all applicable drains and gutters.

ROOFING 018 ROOFING - EPDM - Regarding Deck#18 EPDM roofing to include the following: Replacement of all existing ballasted EPDM with fully-adhered EPDM membrane, inspact/repalce 1/2" cover bord, add 1.5" Isocyanuarte insulation, to be added on top of 3" foil-faced isocyanurate insualtion. Replace flashing per DPS specs at all walls, drains, conduits, flues, gas lines, exhausts curbs, thru-wall and overflow scuppers, skylights, A/C lines, expansion joints, and parapets. paint all existing gas piping per DPS specs. Replace and seal all existing pipe collars.

022 ROOFING - EPDM - Regarding Deck#22 - EPDM roofing to include the following: Replacement of all existing ballasted EPDM with fully-adhered EPDM membrane, inspact/repalce 1/2" cover bord, add 1.5" Isocyanuarte insulation, to be added on top of 3" foil-faced isocyanurate insualtion. Replace flashing per DPS specs at all walls, drains, conduits, flues, gas lines, exhausts curbs, thru-wall and overflow scuppers, skylights, A/C lines, expansion joints, and parapets. paint all existing gas piping per DPS specs. Replace and seal all existing pipe collars.

023 ROOFING - EPDM - Regarding Deck#23 - EPDM roofing to include the following: Replacement of all existing ballasted EPDM with fully-adhered EPDM membrane, inspact/repalce 1/2" cover bord, add 1.5" Isocyanuarte insulation, to be added on top of 3" foil-faced isocyanurate insualtion. Replace flashing per DPS specs at all walls, drains, conduits, flues, gas lines, exhausts curbs, thru-wall and overflow scuppers, skylights, A/C lines, expansion joints, and parapets. paint all existing gas piping per DPS specs. Replace and seal all existing pipe collars

Doull 2009 FOLDING LUNCHRM TABLES 001 FOLDING LUNCHRM TABLES - INSTALL SURFACE MOUNTED POCKET TABLES

LEARNING LANDSCAPE 001 LEARNING LANDSCAPE - Construct Learning Landscape per UCD Master Plan. Include 2" playground surface asphalt overlay..

REGULATORY / LIGHT FIXTURES 001 REGULATORY LIGHT FIXTURES - Replace all T-12 and incandescent lighting fixtures with T-8 or T5HO fixtures. Properly dispose of all existing lamps and fixtures. Comply with DPS Design and Construction Standards SECTIONS 16501: LAMPS, 16502 BALLASTS AND CONTROLS and 16510: LUMINAIRES and all other applicable DPS Standards. Patch and Repair.

2011 FIRE DETECTION 001 FIRE DETECTION SYSTEM - Replace Fire Detection System

2008 bond for the web Page 19 of 91

2008 GOB - Project Summary by Building & Year Denver Public Schools Facilities Faciliites Planning Management

Eagleton 2009 FOLDING LUNCHRM TABLES 001 FOLDING LUNCHRM TABLES - INSTALL SURFACE MOUNTED POCKET TABLES

ADA COMPLIANCE 001 ADA COMPLIANCE - LEVEL 1 - Comply with DPS Design and Construction Standards SECTION 00700: ACCESSIBILITY STANDARDS and all other applicable DPS Standards. See ADA Level 1 Database provided. Deficiency remedies provided in ADA database should serve as the PM guide only and should not be provided to the A/E for purposes of developing the project scope of work. A/E is directed to conduct a building survey limited to the areas identified in the survey. Other ADA deficiencies may be included if they meet the level 1 status and have not been identified in the survey. All questions of possible oversight of a deficiency shall be directed to DPS Facility Planning through the DPS Project Manager.

FINISH RESTORATION 001 FINISH RESTORATION / PAINT - Repaint all surfaces to include but not limited to, all tile and hard ceilings, walls, doorjambs, doors, woodwork, ductwork, univents, radiators and built-in wood or metal cabinets, bathroom partitions painted or baked-on finish. All rooms, corridors, stairwells, closets, storage, mechanical rooms and piping per DPS piping color code. Duct cleaning is required in this scope.

FINISH RESTORATION 001 FINISH RESTORATION / SEAMLESS FLR - replace all seamless with ceramic/quarry tile

East 2010 ROOFING 008 ROOFING - BUILT-UP - Regarding Deck# 08- Built-Up roofing to include the following: Gravel, 4-ply membrane,replace existing perlite with 1/2" wood fiber, 1/8" taper insulation, replace exsiting polyisocyanurate insulation with 2 layers of 2" polyisocyanurate insulation, replace flashing per DPS specs at all walls, drains, conduits, flues, gas lines, exhausts curbs, thru-wall and overflow scuppers, skylights, A/C lines, expansion joints, and parapets. Replace all gaspipe and similiar stand supports bases with concete pavers, paint all existing gas piping per DPS specs. Replace and seal all existing pipe collars. Inspect/replace all applicable drains and gutters. - Note - East is listed as a historic landmark. Coordinate design with Denver Landmark Commission.

ADA COMPLIANCE 001 ADA COMPLIANCE - DOOR HARDWARE - A/E should conduct a room by room door hardware schedule. Scope includes all doors, utility closets, exterior doors (with panics if necessary), stairwell doors and hinges. Excluded are cabinetry doors. A/E should identify any possible abatement issues to DPS Bond Hazmat project managers for remediation as early as possible.

ROOM / SCIENCE / FUME HOODS 001 SCIENCE FUME HOOD REPLACEMENT - Science rooms at East include 237, 243, 407, 405, and 409. Confirm rooms requiring fume hoods.

ROOM / SCIENCE LABS 001 SCIENCE LAB SAFETY SHOWER/EYE WASH FOUNTAINS - Room/Science Labs - Install safety showers and eyewash fountains in 6 science classrooms. Confirmed current need and room use in the following rooms 237, 243, 407, 405, 400, and 409. Verify scope and need with DPS HazMat PMs.

FINISH RESTORATION

2008 bond for the web Page 20 of 91

2008 GOB - Project Summary by Building & Year Denver Public Schools Facilities Faciliites Planning Management

East 2010 FINISH RESTORATION 001 FINISH RESTORATION - QUARRY TILE - Scope to include demo of existing seamless flooring and site prep. Include all kitchen and adjoining offices. Coordinate equipment disconnect , removal of equipment and food supplies, and final cleanup, with DPS Food Services kitchen. Flooring elevations to increase by 1/2". Adjust floor drains with plumbing, Walls and ceilings to be painted unless they are vinyl tiles. East -estimated at 7460 sf,. consider computer room in cafeteria as an alternate. Replace carpeting with VCT tile in cafeteria as an alternate.

TOILET ROOM (INCLUSIVE) 001 Toilet Rooms (Inclusive - Design for complete remodeling of all restrooms in the building, including restroom portion of all locker rooms. Comply with all applicable DPS Standards for design and construction. Comply with ICC/ANSI A117.1 except where technically infeasible. A/E to include cost of work and repairs needed for investigation – DPS O&M will not be involved to assist w/ investigation. Plumbing includes replacement of all fixtures, replacement of concealed galvanized pipe with copper to below floor level to exposed section in crawl space or exposed below ceiling level. Design shall specify extent of pipe replacement, and shall be approved by DPS QA/QC. Wash basins shall be replaced with individual hand sinks. Design shall specify fixtures to be provided by Denver Water and installed by contractor. Existing ventilation systems shall be investigated for compliance with current code requirements. Design shall specify needed improvements for mechanical ventilation in all restrooms. All lighting fixtures not conforming to DPS Design and Construction Standards shall be replaced with conforming fixtures. Coordinate w/ DPS Sustainability Planner. All toilet partitions shall be replaced. All flooring shall be replaced with quarry tile. All walls, ceiling, and previously painted surfaces shall be repainted. Walls shall be repaired prior to repainting. At minimum, comply with federal ADA standards. Consult with DPS Planning.

IRRIGATION 002 IRRIGATION - Install and repair existing irrigation system, piping, controls, heads, backflows, electrical and connections per DPS standards. - East - Site area to include all lawn areas, approximatley 130,000 sf with no sports fields. Part of lawn on north and east side replaced in 2008. Work to be in conjuntion with other external projects requiring site coordination. See DPS Planning for site plans and QA/QC evaluations/recommendations.

2011 ASPHALT PAVING 001 ASPHALT / VEHICLE PARKING AND DRIVEWAYS - Correct drainage damage to asphalt parking. Cut ane remove asphalt ane install concrete drainage swales to direct water to catch basins.

SHELL / MASONRY 001 SHELL MASONRY - TUCK POINTING - East - East is listed as a historic landmark. Coordinate design with Denver Landmark Commission. See DPS Planning for site plans and evaluations/recommendations.

2012 FIRE SUPPRESSION / SPRINKLER 001 FIRE SPRINKLER SYSTEM - Design new fire sprinkler system throughout entire building. Comply with DPS Design and Construction Standards SECTION 15300: STANDPIPE AND FIRE SPRINKLER STANDARDS and all other applicable DPS Standards. Patch and Repair.

2013 STAGE CURTAIN / AUDITORIUM 001 Replace the item

2008 bond for the web Page 21 of 91

2008 GOB - Project Summary by Building & Year Denver Public Schools Facilities Faciliites Planning Management

Ebert 2009 VIDEO SECURITY 001 Video Security - Build wall, install A/C

2013 FINISH RESTORATION 001 FINISH RESTORATION / PAINT - Repaint all surfaces to include but not limited to, all tile and hard ceilings, walls, doorjambs, doors, woodwork, ductwork, univents, radiators and built-in wood or metal cabinets, bathroom partitions painted or baked-on finish. All rooms, corridors, stairwells, closets, storage, mechanical rooms and piping per DPS piping color code. Duct cleaning is required in this scope.

Edison 2009 TOILET ROOM (INCLUSIVE) 001 Toilet Room (inclusive) - Replace all fixtures, plumbing piping and partitions. Paint walls and Ceilings. Replace tile as required. Lighting to be updated. Repair any associated surface damage, i.e., glazed block, etc.

2012 FIRE SUPPRESSION / SPRINKLER 001 FIRE SPRINKLER SYSTEM - Design new fire sprinkler system throughout entire building. Comply with DPS Design and Construction Standards SECTION 15300: STANDPIPE AND FIRE SPRINKLER STANDARDS and all other applicable DPS Standards. Patch and Repair.

WINDOWS 001 WOOD WINDOWS - REPLACE OR REPAIR WOOD WINDOWS

Ellis 2009 VIDEO SECURITY 001 Video Security - Install A/C

FOLDING LUNCHRM TABLES 001 FOLDING LUNCHRM TABLES - INSTALL SURFACE MOUNTED POCKET TABLES

BUILDNG (NEW) 001 PLACE MODULAR CLASSROOMS FOR ECE EXPANSION FULL DAY PROGRAMS

2011 ASPHALT PAVING 001 ASPHALT / VEHICLE PARKING AND DRIVEWAYS - 2" overlay with geotec material.

2008 bond for the web Page 22 of 91

2008 GOB - Project Summary by Building & Year Denver Public Schools Facilities Faciliites Planning Management

Fairmont 2009 FOLDING LUNCHRM TABLES 001 FOLDING LUNCHRM TABLES - INSTALL SURFACE MOUNTED POCKET TABLES

VIDEO SECURITY 001 Video Security - Move DVR to MDF, Build wall, install A/C

ROOFING 001 ROOFING - BUILT-UP - Built-Up roofing to include the following: Gravel, 4-ply membrane,replace existing perlite with 1/2" wood fiber, 1/8" taper insulation, replace exsiting polyisocyanurate insulation with 2 layers of 2" polyisocyanurate insulation, replace flashing per DPS specs at all walls, drains, conduits, flues, gas lines, exhausts curbs, thru-wall and overflow scuppers, skylights, A/C lines, expansion joints, and parapets. Replace all gaspipe and similiar stand supports bases with concete pavers, paint all existing gas piping per DPS specs. Replace and seal all existing pipe collars. Inspect/replace all applicable drains and gutters.

002 ROOFING - BUILT-UP - Built-Up roofing to include the following: Gravel, 4-ply membrane,replace existing perlite with 1/2" wood fiber, 1/8" taper insulation, replace exsiting polyisocyanurate insulation with 2 layers of 2" polyisocyanurate insulation, replace flashing per DPS specs at all walls, drains, conduits, flues, gas lines, exhausts curbs, thru-wall and overflow scuppers, skylights, A/C lines, expansion joints, and parapets. Replace all gaspipe and similiar stand supports bases with concete pavers, paint all existing gas piping per DPS specs. Replace and seal all existing pipe collars. Inspect/replace all applicable drains and gutters.

003 ROOFING - BUILT-UP - Built-Up roofing to include the following: Gravel, 4-ply membrane,replace existing perlite with 1/2" wood fiber, 1/8" taper insulation, replace exsiting polyisocyanurate insulation with 2 layers of 2" polyisocyanurate insulation, replace flashing per DPS specs at all walls, drains, conduits, flues, gas lines, exhausts curbs, thru-wall and overflow scuppers, skylights, A/C lines, expansion joints, and parapets. Replace all gaspipe and similiar stand supports bases with concete pavers, paint all existing gas piping per DPS specs. Replace and seal all existing pipe collars. Inspect/replace all applicable drains and gutters.

004 ROOFING - BUILT-UP - Built-Up roofing to include the following: Gravel, 4-ply membrane,replace existing perlite with 1/2" wood fiber, 1/8" taper insulation, replace exsiting polyisocyanurate insulation with 2 layers of 2" polyisocyanurate insulation, replace flashing per DPS specs at all walls, drains, conduits, flues, gas lines, exhausts curbs, thru-wall and overflow scuppers, skylights, A/C lines, expansion joints, and parapets. Replace all gaspipe and similiar stand supports bases with concete pavers, paint all existing gas piping per DPS specs. Replace and seal all existing pipe collars. Inspect/replace all applicable drains and gutters.

005 ROOFING - BUILT-UP - Built-Up roofing to include the following: Gravel, 4-ply membrane,replace existing perlite with 1/2" wood fiber, 1/8" taper insulation, replace exsiting polyisocyanurate insulation with 2 layers of 2" polyisocyanurate insulation, replace flashing per DPS specs at all walls, drains, conduits, flues, gas lines, exhausts curbs, thru-wall and overflow scuppers, skylights, A/C lines, expansion joints, and parapets. Replace all gaspipe and similiar stand supports bases with concete pavers, paint all existing gas piping per DPS specs. Replace and seal all existing pipe collars. Inspect/replace all applicable drains and gutters.

008 ROOFING / BUILT UP - Replace BU Roofing

010 ROOFING - BUILT-UP - Built-Up roofing to include the following: Gravel, 4-ply membrane,replace existing perlite with 1/2" wood fiber, 1/8" taper insulation, replace exsiting polyisocyanurate insulation with 2 layers of 2" polyisocyanurate insulation, replace flashing per DPS specs at all walls, drains, conduits, flues, gas lines, exhausts curbs, thru-wall and overflow scuppers, skylights, A/C lines, expansion joints, and parapets. Replace all gaspipe and similiar stand supports bases with concete pavers, paint all existing gas piping per DPS specs. Replace and seal all existing pipe collars. Inspect/replace all applicable drains and gutters.

2008 bond for the web Page 23 of 91

2008 GOB - Project Summary by Building & Year Denver Public Schools Facilities Faciliites Planning Management

Fairmont 2009 ROOFING 011 ROOFING - BUILT-UP - Built-Up roofing to include the following: Gravel, 4-ply membrane,replace existing perlite with 1/2" wood fiber, 1/8" taper insulation, replace exsiting polyisocyanurate insulation with 2 layers of 2" polyisocyanurate insulation, replace flashing per DPS specs at all walls, drains, conduits, flues, gas lines, exhausts curbs, thru-wall and overflow scuppers, skylights, A/C lines, expansion joints, and parapets. Replace all gaspipe and similiar stand supports bases with concete pavers, paint all existing gas piping per DPS specs. Replace and seal all existing pipe collars. Inspect/replace all applicable drains and gutters.

012 ROOFING - BUILT-UP - Built-Up roofing to include the following: Gravel, 4-ply membrane,replace existing perlite with 1/2" wood fiber, 1/8" taper insulation, replace exsiting polyisocyanurate insulation with 2 layers of 2" polyisocyanurate insulation, replace flashing per DPS specs at all walls, drains, conduits, flues, gas lines, exhausts curbs, thru-wall and overflow scuppers, skylights, A/C lines, expansion joints, and parapets. Replace all gaspipe and similiar stand supports bases with concete pavers, paint all existing gas piping per DPS specs. Replace and seal all existing pipe collars. Inspect/replace all applicable drains and gutters.

2010 FIRE SUPPRESSION / SPRINKLER 001 FIRE SPRINKLER SYSTEM - Design new fire sprinkler system throughout entire building. Comply with DPS Design and Construction Standards SECTION 15300: STANDPIPE AND FIRE SPRINKLER STANDARDS and all other applicable DPS Standards. Patch and Repair.

VENTILLATION / CENTRAL FAN / AHU 001 VENTILLATION - CENTRAL FAN - AHU - Attention this scope of work cannot proceed unless it is bundled with H ENS C Temp Controls /Environment Scope. Design for HVAC replacement, and the removal of material and equipment no longer needed. Comply with DPS Design and Construction Standards Division 15 (applicable sections) and all other applicable DPS Standards. Patch and repair. Replace all unit-ventilators, replace steam and condensate feeds back to main, and replace all steam traps including drip and end of main. Include case work required to accommodate new unit-ventilators. All other central air-handling units need commercial cleaning, duct work repaired as needed, new motors, replace branch piping if needed, steam traps, fan bearings and damper sections. Replace all Exhaust Fans including dampers. Replace steam traps as needed. Ductwork cleaning as needed.

TEMP CONTROLS / ENVIRONMENT 001 TEMP CONTROLS - ENVIRONMENT - Attention this scope of work cannot proceed unless it is bundled with H VNT C Ventilation/Central Fan/ AHU Scope. Design for temperature controls replacement, and the removal of material and equipment no longer needed. Comply with DPS Design and Construction Standards SECTIONS 15950: CONTROLS, 15975: INTEGRATED BUILDING AUTOMATION SYSTEM (IBAS) and all other applicable DPS Standards. Patch and repair. Install digital controls and control devices in new unit-ventilators, retrofit all other central air-handling units with new digital controls, electric damper operators, electric valves and operators. Exhaust fan control should be tied in with HVAC system where required or as was original intent. Include convectors, radiators, cabinet heaters, fan-coil units, reheats or other terminal heating equipment in DDC upgrade. Include IBAS interface.

2011 FINISH RESTORATION 001 FINISH RESTORATION / VINYL TILE - Replace existing VAT or VCT with new VCT in corridors and rooms: 105,107,200A, 212, and stairs. Price does not include abatement.

SHELL / MASONRY 001 SHELL / MASONRY - Masonry repair,replace,tuck point &caulking as needed

2008 bond for the web Page 24 of 91

2008 GOB - Project Summary by Building & Year Denver Public Schools Facilities Faciliites Planning Management

Fairmont 2011 TOILET ROOM (INCLUSIVE) 001 Toilet Room (inclusive) - Replace all fixtures, plumbing piping and partitions. Paint walls and Ceilings. Replace tile as required. Lighting to be updated. Repair any associated surface damage, i.e., glazed block, etc.

BUILDING (ADDITION) 001 BUILDING (ADDITION) - Expand space for Library collections. Provide addition and/or space reconfiguration to accommodate larger reading room and accessory library functions.

Fairview 2009 FOLDING LUNCHRM TABLES 001 FOLDING LUNCHRM TABLES - INSTALL SURFACE MOUNTED POCKET TABLES

TOILET ROOM (INCLUSIVE) 001 Toilet Room (inclusive) - Replace all fixtures, plumbing piping and partitions. Paint walls and Ceilings. Replace tile as required. Lighting to be updated. Repair any associated surface damage, i.e., glazed block, etc.

FIRE SUPPRESSION / SPRINKLER 001 FIRE SPRINKLER SYSTEM - Design new fire sprinkler system throughout entire building. Comply with DPS Design and Construction Standards SECTION 15300: STANDPIPE AND FIRE SPRINKLER STANDARDS and all other applicable DPS Standards. Patch and Repair.

FIRE DETECTION 001 FIRE DETECTION SYSTEM - high voltage panel. Obsolete Replace entire Fire Alarm System.

Force 2009 FOLDING LUNCHRM TABLES 001 FOLDING LUNCHRM TABLES - INSTALL SURFACE MOUNTED POCKET TABLES

REGULATORY / LIGHT FIXTURES 001 REGULATORY LIGHT FIXTURES - Replace all T-12 and incandescent lighting fixtures with T-8 or T5HO fixtures. Properly dispose of all existing lamps and fixtures. Comply with DPS Design and Construction Standards SECTIONS 16501: LAMPS, 16502 BALLASTS AND CONTROLS and 16510: LUMINAIRES and all other applicable DPS Standards. Patch and Repair.

2010 HEALTH SAFETY / HAZARD ABATEMENT 001 HEALTH SAFETY HAZARD ABATEMENT - Replace treated wood timber with recycled plastic timbers. Coordinate with learning landscape project at Force

LEARNING LANDSCAPE

2008 bond for the web Page 25 of 91

2008 GOB - Project Summary by Building & Year Denver Public Schools Facilities Faciliites Planning Management

Force 2010 LEARNING LANDSCAPE 001 LEARNING LANDSCAPE - Construct Learning Landscape per UCD Master Plan. Include 2" playground surface asphalt overlay. Remove existing and replace playground asphalt. Coordinate with treated timbers replacement. See master plan draft at www.learninglanscapes.org - Conduct soils asphalt and other pertinent testing prior to bid development.

2011 FIRE DETECTION 001 FIRE DETECTION SYSTEM - Panel only. No longer supported by Manufacture

Ford 2009 FOLDING LUNCHRM TABLES 001 FOLDING LUNCHRM TABLES - INSTALL SURFACE MOUNTED POCKET TABLES

ADA COMPLIANCE 001 ADA COMPLIANCE - LEVEL 1 - Comply with DPS Design and Construction Standards SECTION 00700: ACCESSIBILITY STANDARDS and all other applicable DPS Standards. See ADA Level 1 Database provided. Deficiency remedies provided in ADA database should serve as the PM guide only and should not be provided to the A/E for purposes of developing the project scope of work. A/E is directed to conduct a building survey limited to the areas identified in the survey. Other ADA deficiencies may be included if they meet the level 1 status and have not been identified in the survey. All questions of possible oversight of a deficiency shall be directed to DPS Facility Planning through the DPS Project Manager.

FINISH RESTORATION 001 FINISH RESTORATION / PAINT - Repaint all surfaces to include but not limited to, all tile and hard ceilings, walls, doorjambs, doors, woodwork, ductwork, univents, radiators and built-in wood or metal cabinets, bathroom partitions painted or baked-on finish. All rooms, corridors, stairwells, closets, storage, mechanical rooms and piping per DPS piping color code. Duct cleaning is required in this scope.

2010 LEARNING LANDSCAPE 001 LEARNING LANDSCAPE - Construct Learning Landscape per UCD Master Plan. Include 2" playground surface asphalt overlay. Remove existing and replace playground asphalt. Coordinate with treated timbers replacement. See master plan draft at www.learninglanscapes.org - Conduct soils asphalt and other pertinent testing prior to bid development.

ABSORPTION CHILLER 001 ABSORBTION CHILLER - Replace with Centrifugal Water Chiller. Water treament included w/18 month warranty. Startup and commissioning included. Comply with DPS Design and Construction Standards SECTION 15650: REFRIGERATION, and all other applicable DPS Standards. Patch and repair.

WINDOWS 001 WINDOWS - METAL - Replace with current DPS standards. Coordinate with ongoing chiller work on-site .

2008 bond for the web Page 26 of 91

2008 GOB - Project Summary by Building & Year Denver Public Schools Facilities Faciliites Planning Management

Fox Street 2013 ROOFING 004 ROOFING - BUILT-UP - Built-Up roofing to include the following: Gravel, 4-ply membrane,replace existing perlite with 1/2" wood fiber, 1/8" taper insulation, replace exsiting polyisocyanurate insulation with 2 layers of 2" polyisocyanurate insulation, replace flashing per DPS specs at all walls, drains, conduits, flues, gas lines, exhausts curbs, thru-wall and overflow scuppers, skylights, A/C lines, expansion joints, and parapets. Replace all gaspipe and similiar stand supports bases with concete pavers, paint all existing gas piping per DPS specs. Replace and seal all existing pipe collars. Inspect/replace all applicable drains and gutters.

Garden Place 2009 VIDEO SECURITY 001 Video Security - Re-check MDF size to install rack

ROOFING 001 ROOFING - BUILT-UP - Built-Up roofing to include the following: Gravel, 4-ply membrane,replace existing perlite with 1/2" wood fiber, 1/8" taper insulation, replace exsiting polyisocyanurate insulation with 2 layers of 2" polyisocyanurate insulation, replace flashing per DPS specs at all walls, drains, conduits, flues, gas lines, exhausts curbs, thru-wall and overflow scuppers, skylights, A/C lines, expansion joints, and parapets. Replace all gaspipe and similiar stand supports bases with concete pavers, paint all existing gas piping per DPS specs. Replace and seal all existing pipe collars. Inspect/replace all applicable drains and gutters.

003 ROOFING - BUILT-UP - Built-Up roofing to include the following: Gravel, 4-ply membrane,replace existing perlite with 1/2" wood fiber, 1/8" taper insulation, replace exsiting polyisocyanurate insulation with 2 layers of 2" polyisocyanurate insulation, replace flashing per DPS specs at all walls, drains, conduits, flues, gas lines, exhausts curbs, thru-wall and overflow scuppers, skylights, A/C lines, expansion joints, and parapets. Replace all gaspipe and similiar stand supports bases with concete pavers, paint all existing gas piping per DPS specs. Replace and seal all existing pipe collars. Inspect/replace all applicable drains and gutters.

004 ROOFING - BUILT-UP - Built-Up roofing to include the following: Gravel, 4-ply membrane,replace existing perlite with 1/2" wood fiber, 1/8" taper insulation, replace exsiting polyisocyanurate insulation with 2 layers of 2" polyisocyanurate insulation, replace flashing per DPS specs at all walls, drains, conduits, flues, gas lines, exhausts curbs, thru-wall and overflow scuppers, skylights, A/C lines, expansion joints, and parapets. Replace all gaspipe and similiar stand supports bases with concete pavers, paint all existing gas piping per DPS specs. Replace and seal all existing pipe collars. Inspect/replace all applicable drains and gutters.

006 ROOFING - BUILT-UP - Built-Up roofing to include the following: Gravel, 4-ply membrane,replace existing perlite with 1/2" wood fiber, 1/8" taper insulation, replace exsiting polyisocyanurate insulation with 2 layers of 2" polyisocyanurate insulation, replace flashing per DPS specs at all walls, drains, conduits, flues, gas lines, exhausts curbs, thru-wall and overflow scuppers, skylights, A/C lines, expansion joints, and parapets. Replace all gaspipe and similiar stand supports bases with concete pavers, paint all existing gas piping per DPS specs. Replace and seal all existing pipe collars. Inspect/replace all applicable drains and gutters.

008 ROOFING - BUILT-UP - Built-Up roofing to include the following: Gravel, 4-ply membrane,replace existing perlite with 1/2" wood fiber, 1/8" taper insulation, replace exsiting polyisocyanurate insulation with 2 layers of 2" polyisocyanurate insulation, replace flashing per DPS specs at all walls, drains, conduits, flues, gas lines, exhausts curbs, thru-wall and overflow scuppers, skylights, A/C lines, expansion joints, and parapets. Replace all gaspipe and similiar stand supports bases with concete pavers, paint all existing gas piping per DPS specs. Replace and seal all existing pipe collars. Inspect/replace all applicable drains and gutters.

2013 FINISH RESTORATION 2008 bond for the web Page 27 of 91

2008 GOB - Project Summary by Building & Year Denver Public Schools Facilities Faciliites Planning Management

Garden Place 2013 FINISH RESTORATION 001 FINISH RESTORATION / CARPET - Replace the item

TOILET ROOM (INCLUSIVE) 001 Toilet Room (inclusive) - Replace all fixtures, plumbing piping and partitions. Paint walls and Ceilings. Replace tile as required. Lighting to be updated. Repair any associated surface damage, i.e., glazed block, etc.

Gilpin 2010 ROOFING 001 ROOFING - EPDM - Regarding Deck#01 - EPDM roofing to include the following: Replacement of all existing ballasted EPDM with fully-adhered EPDM membrane, inspact/repalce 1/2" cover bord, add 1.5" Isocyanuarte insulation, to be added on top of 3" foil-faced isocyanurate insualtion. Replace flashing per DPS specs at all walls, drains, conduits, flues, gas lines, exhausts curbs, thru-wall and overflow scuppers, skylights, A/C lines, expansion joints, and parapets. paint all existing gas piping per DPS specs. Replace and seal all existing pipe collars.

IRRIGATION 001 IRRIGATION - Add/repair existing irrigation system, piping, controls, heads, backflows, electrical and connections per DPS standards. - Gilpin - Site area to include all lawn areas around main buidling and play areas, approximatley 35,000 sf. Include learning landscape irrigation repair/replacement with vandal-resistant equipment as an alternate, funding permitting. See DPS Planning for site plans and QA/QC evaluations/recommendations.

2011 WINDOWS 001 METAL WINDOWS - Replace the item

2012 TOILET ROOM (INCLUSIVE) 001 Toilet Room (inclusive) - Replace all fixtures, plumbing piping and partitions. Paint walls and Ceilings. Replace tile as required. Lighting to be updated. Repair any associated surface damage, i.e., glazed block, etc.

Godsman 2009 FOLDING LUNCHRM TABLES 001 FOLDING LUNCHRM TABLES - INSTALL SURFACE MOUNTED POCKET TABLES

VIDEO SECURITY 001 Video Security - Build room, install A/C

BOILER

2008 bond for the web Page 28 of 91

2008 GOB - Project Summary by Building & Year Denver Public Schools Facilities Faciliites Planning Management

Godsman 2009 BOILER 001 BOILER - Replace boiler as per DPS guide specs 15555. Replace in boiler room: pumps, hydronic specality items, associated pipe and all valves. Ref. spec. 15110, and all div. 15 that apply including water treatment associated with this project ref. 15548

REGULATORY / LIGHT FIXTURES 001 REGULATORY LIGHT FIXTURES - Replace all T-12 and incandescent lighting fixtures with T-8 or T5HO fixtures. Properly dispose of all existing lamps and fixtures. Comply with DPS Design and Construction Standards SECTIONS 16501: LAMPS, 16502 BALLASTS AND CONTROLS and 16510: LUMINAIRES and all other applicable DPS Standards. Patch and Repair.

BUILDING (NEW) 001 PLACE MODULAR CLASSROOMS FOR ECE EXPANSION FULL DAY PROGRAMS

2012 ADA COMPLIANCE 001 ADA COMPLIANCE - LEVEL 1 - Comply with DPS Design and Construction Standards SECTION 00700: ACCESSIBILITY STANDARDS and all other applicable DPS Standards. See ADA Level 1 Database provided. Deficiency remedies provided in ADA database should serve as the PM guide only and should not be provided to the A/E for purposes of developing the project scope of work. A/E is directed to conduct a building survey limited to the areas identified in the survey. Other ADA deficiencies may be included if they meet the level 1 status and have not been identified in the survey. All questions of possible oversight of a deficiency shall be directed to DPS Facility Planning through the DPS Project Manager.

FINISH RESTORATION 001 FINISH RESTORATION / PAINT - Repaint all surfaces to include but not limited to, all tile and hard ceilings, walls, doorjambs, doors, woodwork, ductwork, univents, radiators and built-in wood or metal cabinets, bathroom partitions painted or baked-on finish. All rooms, corridors, stairwells, closets, storage, mechanical rooms and piping per DPS piping color code. Duct cleaning is required in this scope.

ROOFING 006 ROOFING - BUILT-UP - Built-Up roofing to include the following: Gravel, 4-ply membrane,replace existing perlite with 1/2" wood fiber, 1/8" taper insulation, replace exsiting polyisocyanurate insulation with 2 layers of 2" polyisocyanurate insulation, replace flashing per DPS specs at all walls, drains, conduits, flues, gas lines, exhausts curbs, thru-wall and overflow scuppers, skylights, A/C lines, expansion joints, and parapets. Replace all gaspipe and similiar stand supports bases with concete pavers, paint all existing gas piping per DPS specs. Replace and seal all existing pipe collars. Inspect/replace all applicable drains and gutters.

HEALTH SAFETY / HAZARD ABATEMENT 001 HEALTH SAFETY / HAZARD ABATEMENT - REPLACE TREATED WOOD TIMBERS WITH RECYCLED PLASTIC TIMBERS

LEARNING LANDSCAPE 001 LEARNING LANDSCAPE - Construct Learning Landscape per UCD Master Plan. Include 2" playground surface asphalt overlay..

2008 bond for the web Page 29 of 91

2008 GOB - Project Summary by Building & Year Denver Public Schools Facilities Faciliites Planning Management

Goldrick 2009 FOLDING LUNCHRM TABLES 001 FOLDING LUNCHRM TABLES - INSTALL SURFACE MOUNTED POCKET TABLES

FIRE DETECTION 001 FIRE DETECTION SYSTEM - Panel only. No longer supported by Manufacture

BUILDNG (NEW) 001 PLACE MODULAR CLASSROOMS FOR ECE EXPANSION FULL DAY PROGRAMS

2013 ADA COMPLIANCE 001 ADA COMPLIANCE - LEVEL 1 - Comply with DPS Design and Construction Standards SECTION 00700: ACCESSIBILITY STANDARDS and all other applicable DPS Standards. See ADA Level 1 Database provided. Deficiency remedies provided in ADA database should serve as the PM guide only and should not be provided to the A/E for purposes of developing the project scope of work. A/E is directed to conduct a building survey limited to the areas identified in the survey. Other ADA deficiencies may be included if they meet the level 1 status and have not been identified in the survey. All questions of possible oversight of a deficiency shall be directed to DPS Facility Planning through the DPS Project Manager.

FINISH RESTORATION 000 FINISH RESTORATION / PAINT - Repaint all surfaces to include but not limited to, all tile and hard ceilings, walls, doorjambs, doors, woodwork, ductwork, univents, radiators and built-in wood or metal cabinets, bathroom partitions painted or baked-on finish. All rooms, corridors, stairwells, closets, storage, mechanical rooms and piping per DPS piping color code. Duct cleaning is required in this scope.

ROOFING 003 ROOFING - BUILT-UP - Built-Up roofing to include the following: Gravel, 4-ply membrane,replace existing perlite with 1/2" wood fiber, 1/8" taper insulation, replace exsiting polyisocyanurate insulation with 2 layers of 2" polyisocyanurate insulation, replace flashing per DPS specs at all walls, drains, conduits, flues, gas lines, exhausts curbs, thru-wall and overflow scuppers, skylights, A/C lines, expansion joints, and parapets. Replace all gaspipe and similiar stand supports bases with concete pavers, paint all existing gas piping per DPS specs. Replace and seal all existing pipe collars. Inspect/replace all applicable drains and gutters.

005 ROOFING - BUILT-UP - Built-Up roofing to include the following: Gravel, 4-ply membrane,replace existing perlite with 1/2" wood fiber, 1/8" taper insulation, replace exsiting polyisocyanurate insulation with 2 layers of 2" polyisocyanurate insulation, replace flashing per DPS specs at all walls, drains, conduits, flues, gas lines, exhausts curbs, thru-wall and overflow scuppers, skylights, A/C lines, expansion joints, and parapets. Replace all gaspipe and similiar stand supports bases with concete pavers, paint all existing gas piping per DPS specs. Replace and seal all existing pipe collars. Inspect/replace all applicable drains and gutters.

ROOFING 001 ROOFING - BUILT-UP - Built-Up roofing to include the following: Gravel, 4-ply membrane,replace existing perlite with 1/2" wood fiber, 1/8" taper insulation, replace exsiting polyisocyanurate insulation with 2 layers of 2" polyisocyanurate insulation, replace flashing per DPS specs at all walls, drains, conduits, flues, gas lines, exhausts curbs, thru-wall and overflow scuppers, skylights, A/C lines, expansion joints, and parapets. Replace all gaspipe and similiar stand supports bases with concete pavers, paint all existing gas piping per DPS specs. Replace and seal all existing pipe collars. Inspect/replace all applicable drains and gutters.

2008 bond for the web Page 30 of 91

2008 GOB - Project Summary by Building & Year Denver Public Schools Facilities Faciliites Planning Management

Goldrick 2013 ROOFING 002 ROOFING - BUILT-UP - Built-Up roofing to include the following: Gravel, 4-ply membrane,replace existing perlite with 1/2" wood fiber, 1/8" taper insulation, replace exsiting polyisocyanurate insulation with 2 layers of 2" polyisocyanurate insulation, replace flashing per DPS specs at all walls, drains, conduits, flues, gas lines, exhausts curbs, thru-wall and overflow scuppers, skylights, A/C lines, expansion joints, and parapets. Replace all gaspipe and similiar stand supports bases with concete pavers, paint all existing gas piping per DPS specs. Replace and seal all existing pipe collars. Inspect/replace all applicable drains and gutters.

004 ROOFING - BUILT-UP - Built-Up roofing to include the following: Gravel, 4-ply membrane,replace existing perlite with 1/2" wood fiber, 1/8" taper insulation, replace exsiting polyisocyanurate insulation with 2 layers of 2" polyisocyanurate insulation, replace flashing per DPS specs at all walls, drains, conduits, flues, gas lines, exhausts curbs, thru-wall and overflow scuppers, skylights, A/C lines, expansion joints, and parapets. Replace all gaspipe and similiar stand supports bases with concete pavers, paint all existing gas piping per DPS specs. Replace and seal all existing pipe collars. Inspect/replace all applicable drains and gutters.

006 ROOFING - BUILT-UP - Built-Up roofing to include the following: Gravel, 4-ply membrane,replace existing perlite with 1/2" wood fiber, 1/8" taper insulation, replace exsiting polyisocyanurate insulation with 2 layers of 2" polyisocyanurate insulation, replace flashing per DPS specs at all walls, drains, conduits, flues, gas lines, exhausts curbs, thru-wall and overflow scuppers, skylights, A/C lines, expansion joints, and parapets. Replace all gaspipe and similiar stand supports bases with concete pavers, paint all existing gas piping per DPS specs. Replace and seal all existing pipe collars. Inspect/replace all applicable drains and gutters.

007 ROOFING - BUILT-UP - Built-Up roofing to include the following: Gravel, 4-ply membrane,replace existing perlite with 1/2" wood fiber, 1/8" taper insulation, replace exsiting polyisocyanurate insulation with 2 layers of 2" polyisocyanurate insulation, replace flashing per DPS specs at all walls, drains, conduits, flues, gas lines, exhausts curbs, thru-wall and overflow scuppers, skylights, A/C lines, expansion joints, and parapets. Replace all gaspipe and similiar stand supports bases with concete pavers, paint all existing gas piping per DPS specs. Replace and seal all existing pipe collars. Inspect/replace all applicable drains and gutters.

011 ROOFING - BUILT-UP - Built-Up roofing to include the following: Gravel, 4-ply membrane,replace existing perlite with 1/2" wood fiber, 1/8" taper insulation, replace exsiting polyisocyanurate insulation with 2 layers of 2" polyisocyanurate insulation, replace flashing per DPS specs at all walls, drains, conduits, flues, gas lines, exhausts curbs, thru-wall and overflow scuppers, skylights, A/C lines, expansion joints, and parapets. Replace all gaspipe and similiar stand supports bases with concete pavers, paint all existing gas piping per DPS specs. Replace and seal all existing pipe collars. Inspect/replace all applicable drains and gutters.

012 ROOFING - BUILT-UP - Built-Up roofing to include the following: Gravel, 4-ply membrane,replace existing perlite with 1/2" wood fiber, 1/8" taper insulation, replace exsiting polyisocyanurate insulation with 2 layers of 2" polyisocyanurate insulation, replace flashing per DPS specs at all walls, drains, conduits, flues, gas lines, exhausts curbs, thru-wall and overflow scuppers, skylights, A/C lines, expansion joints, and parapets. Replace all gaspipe and similiar stand supports bases with concete pavers, paint all existing gas piping per DPS specs. Replace and seal all existing pipe collars. Inspect/replace all applicable drains and gutters.

023 ROOFING - BUILT-UP - Built-Up roofing to include the following: Gravel, 4-ply membrane,replace existing perlite with 1/2" wood fiber, 1/8" taper insulation, replace exsiting polyisocyanurate insulation with 2 layers of 2" polyisocyanurate insulation, replace flashing per DPS specs at all walls, drains, conduits, flues, gas lines, exhausts curbs, thru-wall and overflow scuppers, skylights, A/C lines, expansion joints, and parapets. Replace all gaspipe and similiar stand supports bases with concete pavers, paint all existing gas piping per DPS specs. Replace and seal all existing pipe collars. Inspect/replace all applicable drains and gutters.

2008 bond for the web Page 31 of 91

2008 GOB - Project Summary by Building & Year Denver Public Schools Facilities Faciliites Planning Management

Gove 2012 ROOFING 001 ROOFING - BUILT-UP - Built-Up roofing to include the following: Gravel, 4-ply membrane,replace existing perlite with 1/2" wood fiber, 1/8" taper insulation, replace exsiting polyisocyanurate insulation with 2 layers of 2" polyisocyanurate insulation, replace flashing per DPS specs at all walls, drains, conduits, flues, gas lines, exhausts curbs, thru-wall and overflow scuppers, skylights, A/C lines, expansion joints, and parapets. Replace all gaspipe and similiar stand supports bases with concete pavers, paint all existing gas piping per DPS specs. Replace and seal all existing pipe collars. Inspect/replace all applicable drains and gutters.

002 ROOFING - BUILT-UP - Built-Up roofing to include the following: Gravel, 4-ply membrane,replace existing perlite with 1/2" wood fiber, 1/8" taper insulation, replace exsiting polyisocyanurate insulation with 2 layers of 2" polyisocyanurate insulation, replace flashing per DPS specs at all walls, drains, conduits, flues, gas lines, exhausts curbs, thru-wall and overflow scuppers, skylights, A/C lines, expansion joints, and parapets. Replace all gaspipe and similiar stand supports bases with concete pavers, paint all existing gas piping per DPS specs. Replace and seal all existing pipe collars. Inspect/replace all applicable drains and gutters.

003 ROOFING - BUILT-UP - Built-Up roofing to include the following: Gravel, 4-ply membrane,replace existing perlite with 1/2" wood fiber, 1/8" taper insulation, replace exsiting polyisocyanurate insulation with 2 layers of 2" polyisocyanurate insulation, replace flashing per DPS specs at all walls, drains, conduits, flues, gas lines, exhausts curbs, thru-wall and overflow scuppers, skylights, A/C lines, expansion joints, and parapets. Replace all gaspipe and similiar stand supports bases with concete pavers, paint all existing gas piping per DPS specs. Replace and seal all existing pipe collars. Inspect/replace all applicable drains and gutters.

004 ROOFING - BUILT-UP - Built-Up roofing to include the following: Gravel, 4-ply membrane,replace existing perlite with 1/2" wood fiber, 1/8" taper insulation, replace exsiting polyisocyanurate insulation with 2 layers of 2" polyisocyanurate insulation, replace flashing per DPS specs at all walls, drains, conduits, flues, gas lines, exhausts curbs, thru-wall and overflow scuppers, skylights, A/C lines, expansion joints, and parapets. Replace all gaspipe and similiar stand supports bases with concete pavers, paint all existing gas piping per DPS specs. Replace and seal all existing pipe collars. Inspect/replace all applicable drains and gutters.

005 ROOFING - BUILT-UP - Built-Up roofing to include the following: Gravel, 4-ply membrane,replace existing perlite with 1/2" wood fiber, 1/8" taper insulation, replace exsiting polyisocyanurate insulation with 2 layers of 2" polyisocyanurate insulation, replace flashing per DPS specs at all walls, drains, conduits, flues, gas lines, exhausts curbs, thru-wall and overflow scuppers, skylights, A/C lines, expansion joints, and parapets. Replace all gaspipe and similiar stand supports bases with concete pavers, paint all existing gas piping per DPS specs. Replace and seal all existing pipe collars. Inspect/replace all applicable drains and gutters.

006 ROOFING - BUILT-UP - Built-Up roofing to include the following: Gravel, 4-ply membrane,replace existing perlite with 1/2" wood fiber, 1/8" taper insulation, replace exsiting polyisocyanurate insulation with 2 layers of 2" polyisocyanurate insulation, replace flashing per DPS specs at all walls, drains, conduits, flues, gas lines, exhausts curbs, thru-wall and overflow scuppers, skylights, A/C lines, expansion joints, and parapets. Replace all gaspipe and similiar stand supports bases with concete pavers, paint all existing gas piping per DPS specs. Replace and seal all existing pipe collars. Inspect/replace all applicable drains and gutters.

007 ROOFING - BUILT-UP - Built-Up roofing to include the following: Gravel, 4-ply membrane,replace existing perlite with 1/2" wood fiber, 1/8" taper insulation, replace exsiting polyisocyanurate insulation with 2 layers of 2" polyisocyanurate insulation, replace flashing per DPS specs at all walls, drains, conduits, flues, gas lines, exhausts curbs, thru-wall and overflow scuppers, skylights, A/C lines, expansion joints, and parapets. Replace all gaspipe and similiar stand supports bases with concete pavers, paint all existing gas piping per DPS specs. Replace and seal all existing pipe collars. Inspect/replace all applicable drains and gutters.

2008 bond for the web Page 32 of 91

2008 GOB - Project Summary by Building & Year Denver Public Schools Facilities Faciliites Planning Management

Gove 2012 ROOFING 008 ROOFING - BUILT-UP - Built-Up roofing to include the following: Gravel, 4-ply membrane,replace existing perlite with 1/2" wood fiber, 1/8" taper insulation, replace exsiting polyisocyanurate insulation with 2 layers of 2" polyisocyanurate insulation, replace flashing per DPS specs at all walls, drains, conduits, flues, gas lines, exhausts curbs, thru-wall and overflow scuppers, skylights, A/C lines, expansion joints, and parapets. Replace all gaspipe and similiar stand supports bases with concete pavers, paint all existing gas piping per DPS specs. Replace and seal all existing pipe collars. Inspect/replace all applicable drains and gutters.

009 ROOFING - BUILT-UP - Built-Up roofing to include the following: Gravel, 4-ply membrane,replace existing perlite with 1/2" wood fiber, 1/8" taper insulation, replace exsiting polyisocyanurate insulation with 2 layers of 2" polyisocyanurate insulation, replace flashing per DPS specs at all walls, drains, conduits, flues, gas lines, exhausts curbs, thru-wall and overflow scuppers, skylights, A/C lines, expansion joints, and parapets. Replace all gaspipe and similiar stand supports bases with concete pavers, paint all existing gas piping per DPS specs. Replace and seal all existing pipe collars. Inspect/replace all applicable drains and gutters.

010 ROOFING - BUILT-UP - Built-Up roofing to include the following: Gravel, 4-ply membrane,replace existing perlite with 1/2" wood fiber, 1/8" taper insulation, replace exsiting polyisocyanurate insulation with 2 layers of 2" polyisocyanurate insulation, replace flashing per DPS specs at all walls, drains, conduits, flues, gas lines, exhausts curbs, thru-wall and overflow scuppers, skylights, A/C lines, expansion joints, and parapets. Replace all gaspipe and similiar stand supports bases with concete pavers, paint all existing gas piping per DPS specs. Replace and seal all existing pipe collars. Inspect/replace all applicable drains and gutters.

011 ROOFING - BUILT-UP - Built-Up roofing to include the following: Gravel, 4-ply membrane,replace existing perlite with 1/2" wood fiber, 1/8" taper insulation, replace exsiting polyisocyanurate insulation with 2 layers of 2" polyisocyanurate insulation, replace flashing per DPS specs at all walls, drains, conduits, flues, gas lines, exhausts curbs, thru-wall and overflow scuppers, skylights, A/C lines, expansion joints, and parapets. Replace all gaspipe and similiar stand supports bases with concete pavers, paint all existing gas piping per DPS specs. Replace and seal all existing pipe collars. Inspect/replace all applicable drains and gutters.

012 ROOFING - BUILT-UP - Built-Up roofing to include the following: Gravel, 4-ply membrane,replace existing perlite with 1/2" wood fiber, 1/8" taper insulation, replace exsiting polyisocyanurate insulation with 2 layers of 2" polyisocyanurate insulation, replace flashing per DPS specs at all walls, drains, conduits, flues, gas lines, exhausts curbs, thru-wall and overflow scuppers, skylights, A/C lines, expansion joints, and parapets. Replace all gaspipe and similiar stand supports bases with concete pavers, paint all existing gas piping per DPS specs. Replace and seal all existing pipe collars. Inspect/replace all applicable drains and gutters.

013 ROOFING - BUILT-UP - Built-Up roofing to include the following: Gravel, 4-ply membrane,replace existing perlite with 1/2" wood fiber, 1/8" taper insulation, replace exsiting polyisocyanurate insulation with 2 layers of 2" polyisocyanurate insulation, replace flashing per DPS specs at all walls, drains, conduits, flues, gas lines, exhausts curbs, thru-wall and overflow scuppers, skylights, A/C lines, expansion joints, and parapets. Replace all gaspipe and similiar stand supports bases with concete pavers, paint all existing gas piping per DPS specs. Replace and seal all existing pipe collars. Inspect/replace all applicable drains and gutters.

014 ROOFING - BUILT-UP - Built-Up roofing to include the following: Gravel, 4-ply membrane,replace existing perlite with 1/2" wood fiber, 1/8" taper insulation, replace exsiting polyisocyanurate insulation with 2 layers of 2" polyisocyanurate insulation, replace flashing per DPS specs at all walls, drains, conduits, flues, gas lines, exhausts curbs, thru-wall and overflow scuppers, skylights, A/C lines, expansion joints, and parapets. Replace all gaspipe and similiar stand supports bases with concete pavers, paint all existing gas piping per DPS specs. Replace and seal all existing pipe collars. Inspect/replace all applicable drains and gutters.

2008 bond for the web Page 33 of 91

2008 GOB - Project Summary by Building & Year Denver Public Schools Facilities Faciliites Planning Management

Gove 2012 ROOFING 015 ROOFING - BUILT-UP - Built-Up roofing to include the following: Gravel, 4-ply membrane,replace existing perlite with 1/2" wood fiber, 1/8" taper insulation, replace exsiting polyisocyanurate insulation with 2 layers of 2" polyisocyanurate insulation, replace flashing per DPS specs at all walls, drains, conduits, flues, gas lines, exhausts curbs, thru-wall and overflow scuppers, skylights, A/C lines, expansion joints, and parapets. Replace all gaspipe and similiar stand supports bases with concete pavers, paint all existing gas piping per DPS specs. Replace and seal all existing pipe collars. Inspect/replace all applicable drains and gutters.

Grant 2011 WINDOWS 001 METAL WINDOWS - FAIR condition - repair and maintenance REQUIRED to restore materials to stable condition -

2012 ADA COMPLIANCE 001 ADA COMPLIANCE - DOOR HARDWARE - A/E should conduct a room by room door hardware schedule. Scope includes all doors, utility closets, exterior doors (with panics if necessary), stairwell doors and hinges. Excluded are cabinetry doors. A/E should identify any possible abatement issues to DPS Bond Hazmat project managers for remediation as early as possible.

ADA COMPLIANCE 001 REGULATORY - EGRESS / DOOR HARDWARE - Replace exterior door hardware for ADA compliance - A/E should conduct a door hardware schedule. Scope includes exterior doors (with panics if necessary), stairwell doors and hinges. A/E should identify any possible abatement issues to DPS Bond Hazmat project managers for remediation as early as possible.

FINISH RESTORATION 001 FINISH RESTORATION / PAINT - Repaint all surfaces to include but not limited to, all tile and hard ceilings, walls, doorjambs, doors, woodwork, ductwork, univents, radiators and built-in wood or metal cabinets, bathroom partitions painted or baked-on finish. All rooms, corridors, stairwells, closets, storage, mechanical rooms and piping per DPS piping color code. Duct cleaning is required in this scope.

TOILET ROOM (INCLUSIVE) 001 Toilet Room (inclusive) - Replace all fixtures, plumbing piping and partitions. Paint walls and Ceilings. Replace tile as required. Lighting to be updated. Repair any associated surface damage, i.e., glazed block, etc.

2013 STAGE CURTAIN / AUDITORIUM 001 STAGE CURTAIN / AUDITORIUM - Replace all curtains and make rigging corrections

2008 bond for the web Page 34 of 91

2008 GOB - Project Summary by Building & Year Denver Public Schools Facilities Faciliites Planning Management

Grant Ranch 2009 LEARNING LANDSCAPE 001 Install missing learning landscape elements.

Green Valley 2009 FINISH RESTORATION 001 FINISH RESTORATION / CARPET - Replace the item

LEARNING LANDSCAPE 001 Install missing learning landscape elements

Green Valley High 2009 BUILDING (NEW) 001 BUILDING (NEW) - New High School for 800 Students (option to 450 student start) - including ground loop heating and cooling

Greenlee 2009 BOILER 001 BOILER - Replace boiler as per DPS guide specs 15555C. Replace in boiler room: condensate return pumps, steam traps, condensate return pipe, boiler feed pipe, and all valves. Ref. spec. 15110, 15521, and all div. 15 that apply including water treatment associated with this project ref. 15548

002 BOILER - Replace boiler as per DPS guide specs 15555C. Replace in boiler room: condensate return pumps, steam traps, condensate return pipe, boiler feed pipe, and all valves. Ref. spec. 15110, 15521, and all div. 15 that apply including water treatment associated with this project ref. 15548

2013 FINISH RESTORATION 001 FINISH RESTORATION / VINYL TILE - Replace existing VAT or VCT with new VCT. Price does not include abatement.

BUILDING (REMODEL) 003 BUILDING (REMODEL) - K8 CONVERSION - ENLARGE LMC BY ABSORBING ADJACENT CORRIDOR LOBBY AREA (RESULTS IN 2180 SF TOTAL)

ROOFING 002 ROOFING / BUILT UP - Replace roofing deck 3

2008 bond for the web Page 35 of 91

2008 GOB - Project Summary by Building & Year Denver Public Schools Facilities Faciliites Planning Management

Greenwood 2009 LEARNING LANDSCAPE 001 Install missing learning landscape elements.

Gust 2009 FOLDING LUNCHRM TABLES 001 FOLDING LUNCHRM TABLES - INSTALL SURFACE MOUNTED POCKET TABLES

2010 REGULATORY / LIGHT FIXTURES 001 REGULATORY LIGHT FIXTURES - Replace all T-12 and incandescent lighting fixtures with T-8 or T5HO fixtures. Properly dispose of all existing lamps and fixtures. Comply with DPS Design and Construction Standards SECTIONS 16501: LAMPS, 16502 BALLASTS AND CONTROLS and 16510: LUMINAIRES and all other applicable DPS Standards. Patch and Repair.

WINDOWS 001 WINDOWS - METAL - Replace with current DPS standards. Coordinate with light fixture replacement.

Hamilton 2009 SAFETY / WORK SPACE 001 HEALTH SAFETY / WORK SPACE - Abate crawlspace and install ventillation fan(s) on southern end of crawlspace to reduce humidity. Provide override for continuous fan operation to create non-confined crawlspace.

2011 ADA COMPLIANCE 001 ADA COMPLIANCE / ELEVATOR - Car 42x72/Cntrls @ 62"/No Aud. -- NEJ

ADA COMPLIANCE 001 REGULATORY - EGRESS / DOOR HARDWARE - Replace exterior door hardware for ADA compliance - A/E should conduct a door hardware schedule. Scope includes exterior doors (with panics if necessary), stairwell doors and hinges. A/E should identify any possible abatement issues to DPS Bond Hazmat project managers for remediation as early as possible.

ASPHALT PAVING 001 ASPHALT / VEHICLE PARKING AND DRIVEWAYS - 2" overlay with geotec material.

003 ASPHALT / VEHICLE PARKING AND DRIVEWAYS - 2" overlay with geotec material.

FINISH RESTORATION 001 FINISH RESTORATION / TILE - Quarry tile substrate is loose,replace with new quarry tile

IRRIGATION 2008 bond for the web Page 36 of 91

2008 GOB - Project Summary by Building & Year Denver Public Schools Facilities Faciliites Planning Management

Hamilton 2011 001 IRRIGATION - Replace the item

ROOFING 005 ROOFING - BUILT-UP - Built-Up roofing to include the following: Gravel, 4-ply membrane,replace existing perlite with 1/2" wood fiber, 1/8" taper insulation, replace exsiting polyisocyanurate insulation with 2 layers of 2" polyisocyanurate insulation, replace flashing per DPS specs at all walls, drains, conduits, flues, gas lines, exhausts curbs, thru-wall and overflow scuppers, skylights, A/C lines, expansion joints, and parapets. Replace all gaspipe and similiar stand supports bases with concete pavers, paint all existing gas piping per DPS specs. Replace and seal all existing pipe collars. Inspect/replace all applicable drains and gutters.

019 ROOFING - BUILT-UP - Built-Up roofing to include the following: Gravel, 4-ply membrane,replace existing perlite with 1/2" wood fiber, 1/8" taper insulation, replace exsiting polyisocyanurate insulation with 2 layers of 2" polyisocyanurate insulation, replace flashing per DPS specs at all walls, drains, conduits, flues, gas lines, exhausts curbs, thru-wall and overflow scuppers, skylights, A/C lines, expansion joints, and parapets. Replace all gaspipe and similiar stand supports bases with concete pavers, paint all existing gas piping per DPS specs. Replace and seal all existing pipe collars. Inspect/replace all applicable drains and gutters.

HOT WATER HEATER 001 HOT WATER HEATER - REPLACE EXISTING HOT WATER HEATER

VENTILLATION / CENTRAL FAN / AHU 001 VENTILLATION / CENTRAL FAN / AHU - Attention this scope of work cannot proceed unless it is bundled with H ENS C Temp Controls /Environment Scope. Univent system needs complete replacement, replace supply and return feeds back to main, include case work required to accommodate new univents. All other Central Air Handling Units need commercial cleaning, duct work repaired as needed, new motors, new pumps, replace branch piping if needed, fan bearings and damper sections. Replace all Exhaust Fans including dampers

WINDOWS 001 METAL WINDOWS - Replace the item

TEMP CONTROLS / ENVIRONMENT 001 TEMP CONTROLS / ENVIRONMENT - Attention this scope of work cannot proceed unless it is bundled with H VNT C Ventilation/Central Fan/ AHU Scope. Install digital controls and control devices in new univents, retrofit all other central air handling units with new digital controls, electric damper operators, electric valves and operators. Exhaust Fan control should be tied in with HVAC system where required or as was original intent. Include Convectors, Radiators, Caninet heaters, Fancoil Units, Reheats or other terminal heating equipment in DDC upgrade.

Harrington 2009 FINISH RESTORATION 001 FINISH RESTORATION / PAINT - Repaint all surfaces to include but not limited to, all tile and hard ceilings, walls, doorjambs, doors, woodwork, ductwork, univents, radiators and built-in wood or metal cabinets, bathroom partitions painted or baked-on finish. All rooms, corridors, stairwells, closets, storage, mechanical rooms and piping per DPS piping color code. Duct cleaning is required in this scope.

WINDOWS 001 Window glazing and repair

2008 bond for the web Page 37 of 91

2008 GOB - Project Summary by Building & Year Denver Public Schools Facilities Faciliites Planning Management

Harrington 2009 VIDEO SECURITY 001 Video Security - Install AC in MDF

2010 ASPHALT PAVING 001 ASPHALT REPLACEMENT - At the west side of building, replace 15,750 sq.ft of asphalt with 2" overlay with geotec material in accordance with DPS specifications. Include all pertinent civil engineering, testing, and permitting as necessary. Striping, ADA parking space allocations per ADA standards, signage to be included per DPS/City of Denver code. Replace all impacted landscaping, sod, and irrigation equipment as necessary. Coordinate with learning landscape project. See DPS Planning for site specific plans and QA/QC evaluation/recommendations. Harrington - Mitigate drainage issue per QA/QC recommendation for concrete swale.

LEARNING LANDSCAPE 001 LEARNING LANDSCAPE - Construct Learning Landscape per UCD Master Plan. Remove existing and replace playground asphalt. Include 2" playground surface asphalt overlay. Coordinate with parking lot paving. See master plan draft at www.learninglanscapes.org - Conduct soils asphalt and other pertinent testing prior to bid development.

Henry 2009 ROOFING 005 ROOFING - BUILT-UP - Built-Up roofing to include the following: Gravel, 4-ply membrane,replace existing perlite with 1/2" wood fiber, 1/8" taper insulation, replace exsiting polyisocyanurate insulation with 2 layers of 2" polyisocyanurate insulation, replace flashing per DPS specs at all walls, drains, conduits, flues, gas lines, exhausts curbs, thru-wall and overflow scuppers, skylights, A/C lines, expansion joints, and parapets. Replace all gaspipe and similiar stand supports bases with concete pavers, paint all existing gas piping per DPS specs. Replace and seal all existing pipe collars. Inspect/replace all applicable drains and gutters.

008 ROOFING - BUILT-UP - Built-Up roofing to include the following: Gravel, 4-ply membrane,replace existing perlite with 1/2" wood fiber, 1/8" taper insulation, replace exsiting polyisocyanurate insulation with 2 layers of 2" polyisocyanurate insulation, replace flashing per DPS specs at all walls, drains, conduits, flues, gas lines, exhausts curbs, thru-wall and overflow scuppers, skylights, A/C lines, expansion joints, and parapets. Replace all gaspipe and similiar stand supports bases with concete pavers, paint all existing gas piping per DPS specs. Replace and seal all existing pipe collars. Inspect/replace all applicable drains and gutters.

ABSORPTION CHILLER 001 ABSORPTION CHILLER - Replace the item

HEALTH SAFETY / CLRM VENTILLATION 003 HEALTH SAFETY / CLRM VENTILLATION - Retro entire AHU#003 system to include converting the supply and return fans to fariable air volume (VAV) in lieu of constant volume fans. Include requiremed fan maintenance or fan replaement to allow the fans to perform property throughout the entire airflow range as required by the system. Replace high velocity/medium pressure ductwork to SMACNA compliant specifications for medium pressure duct. Replace pressure dependent zone terminals with pressure independent VAV terminals. Provide new DDC controls and space sensors for system. Provide control front end capable of expansion to full school buidling. Extend return air duct to the administration area to improve return air path and alleviate noise above teachers' lounge.

2012 ADA COMPLIANCE 2008 bond for the web Page 38 of 91

2008 GOB - Project Summary by Building & Year Denver Public Schools Facilities Faciliites Planning Management

Henry 2012 001 REGULATORY - EGRESS / DOOR HARDWARE - Replace exterior door hardware for ADA compliance - A/E should conduct a door hardware schedule. Scope includes exterior doors (with panics if necessary), stairwell doors and hinges. A/E should identify any possible abatement issues to DPS Bond Hazmat project managers for remediation as early as possible.

DIMMER SYSTEM (STAGE AND PERFORMANCE) 001 DIMMER SYSTEM (STAGE AND PERFORMANCE) - Replace the item

Hill 2009 LUNCHROOM TABLES 002 REMOVE AND REPLACE CAFETERIA TABLES

FIRE DETECTION 001 FIRE DETECTION SYSTEM - Panel only. No longer supported by Manufacture

2010 BOILER 001 BOILER REPLACEMENT - Design for replacement of two boilers, and the removal of material and equipment no longer needed.This is a complete replacement. Include condensate return tank. Include startup and commissioning. Replace existing heat exchanger with new domestic hw Aerco Boiler.In the boiler room replace: condensate return pumps, steam traps, condensate return pipe, boiler feed pipe, and all valves. Design shall include water treatment. Asbestos management by DPS and not included in this scope. Comply with DPS Design and Construction Standards SECTION 15555C: CAST IRON BOILER PERFORMANCE SPEC, 15110: VALVES, 15521: STEAM AND CONDENSATE PIPING SPECIALTIES and all other applicable DPS Standards. Patch and repair insulation.

002 BOILER REPLACEMENT - Design for replacement of two boilers, and the removal of material and equipment no longer needed.This is a complete replacement. Include condensate return tank. Include startup and commissioning. Replace existing heat exchanger with new domestic hw Aerco Boiler.In the boiler room replace: condensate return pumps, steam traps, condensate return pipe, boiler feed pipe, and all valves. Design shall include water treatment. Asbestos management by DPS and not included in this scope. Comply with DPS Design and Construction Standards SECTION 15555C: CAST IRON BOILER PERFORMANCE SPEC, 15110: VALVES, 15521: STEAM AND CONDENSATE PIPING SPECIALTIES and all other applicable DPS Standards. Patch and repair insulation.

WINDOWS 001 WINDOWS - METAL - Replace with current DPS standards. - Hill is highly eligible for landmark status. Coordinate design review with Denver Landmark Preservation Commission. Coordinate with boiler replacement.

2012 ADA COMPLIANCE 001 ADA COMPLIANCE - DOOR HARDWARE - A/E should conduct a room by room door hardware schedule. Scope includes all doors, utility closets, exterior doors (with panics if necessary), stairwell doors and hinges. Excluded are cabinetry doors. A/E should identify any possible abatement issues to DPS Bond Hazmat project managers for remediation as early as possible.

ADA COMPLIANCE

2008 bond for the web Page 39 of 91

2008 GOB - Project Summary by Building & Year Denver Public Schools Facilities Faciliites Planning Management

Hill 2012 ADA COMPLIANCE 001 REGULATORY - EGRESS / DOOR HARDWARE - Replace exterior door hardware for ADA compliance - A/E should conduct a door hardware schedule. Scope includes exterior doors (with panics if necessary), stairwell doors and hinges. A/E should identify any possible abatement issues to DPS Bond Hazmat project managers for remediation as early as possible.

FINISH RESTORATION 000 FINISH RESTORATION / PAINT - Repaint all surfaces to include but not limited to, all tile and hard ceilings, walls, doorjambs, doors, woodwork, ductwork, univents, radiators and built-in wood or metal cabinets, bathroom partitions painted or baked-on finish. All rooms, corridors, stairwells, closets, storage, mechanical rooms and piping per DPS piping color code. Duct cleaning is required in this scope.

FINISH RESTORATION 000 FINISH RESTORATION / TILE - Quarry tile substrate is loose,replace with new quarry tile

ROOFING 001 ROOFING - BUILT-UP - Built-Up roofing to include the following: Gravel, 4-ply membrane,replace existing perlite with 1/2" wood fiber, 1/8" taper insulation, replace exsiting polyisocyanurate insulation with 2 layers of 2" polyisocyanurate insulation, replace flashing per DPS specs at all walls, drains, conduits, flues, gas lines, exhausts curbs, thru-wall and overflow scuppers, skylights, A/C lines, expansion joints, and parapets. Replace all gaspipe and similiar stand supports bases with concete pavers, paint all existing gas piping per DPS specs. Replace and seal all existing pipe collars. Inspect/replace all applicable drains and gutters.

012 ROOFING - BUILT-UP - Built-Up roofing to include the following: Gravel, 4-ply membrane,replace existing perlite with 1/2" wood fiber, 1/8" taper insulation, replace exsiting polyisocyanurate insulation with 2 layers of 2" polyisocyanurate insulation, replace flashing per DPS specs at all walls, drains, conduits, flues, gas lines, exhausts curbs, thru-wall and overflow scuppers, skylights, A/C lines, expansion joints, and parapets. Replace all gaspipe and similiar stand supports bases with concete pavers, paint all existing gas piping per DPS specs. Replace and seal all existing pipe collars. Inspect/replace all applicable drains and gutters.

013 ROOFING - BUILT-UP - Built-Up roofing to include the following: Gravel, 4-ply membrane,replace existing perlite with 1/2" wood fiber, 1/8" taper insulation, replace exsiting polyisocyanurate insulation with 2 layers of 2" polyisocyanurate insulation, replace flashing per DPS specs at all walls, drains, conduits, flues, gas lines, exhausts curbs, thru-wall and overflow scuppers, skylights, A/C lines, expansion joints, and parapets. Replace all gaspipe and similiar stand supports bases with concete pavers, paint all existing gas piping per DPS specs. Replace and seal all existing pipe collars. Inspect/replace all applicable drains and gutters.

Hilltop Bus Garage 2009 UTILITY / BACKFLOW PREVENTERS 001 UTILITY / BACKFLOW PREVENTERS (CONTAINMENT) - INSTALL DUAL CONTAINMENT. DPS STANDARD INSTALLATION

2008 bond for the web Page 40 of 91

2008 GOB - Project Summary by Building & Year Denver Public Schools Facilities Faciliites Planning Management

Hilltop Trans Train Bldg 2009 UTILITY / BACKFLOW PREVENTERS 001 UTILITY / BACKFLOW PREVENTERS (CONTAINMENT) - INSTALL DUAL CONTAINMENT. DPS STANDARD INSTALLATION

2011 FIRE SUPPRESSION / SPRINKLER 001 FIRE SUPPRESSION / BACKFLOW PREVENTOR - INSTALL FIRE SUPPRESSION BACKFLOW PROTECTION

Hilltop Trans Trn Safety 2009 UTILITY / BACKFLOW PREVENTERS 001 UTILITY / BACKFLOW PREVENTERS (CONTAINMENT) - INSTALL DUAL CONTAINMENT. DPS STANDARD INSTALLATION

Hilltop Transportation 2009 UTILITY / BACKFLOW PREVENTERS 001 UTILITY / BACKFLOW PREVENTERS (CONTAINMENT) - Replace the item

2011 FIRE SUPPRESSION / SPRINKLER 001 FIRE SUPPRESSION / BACKFLOW PREVENTOR - INSTALL FIRE SUPPRESSION BACKFLOW PROTECTION

Holm 2009 FOLDING LUNCHRM TABLES 001 FOLDING LUNCHRM TABLES - INSTALL SURFACE MOUNTED POCKET TABLES

FIRE DETECTION 001 FIRE DETECTION SYSTEM - Replace Fire Detection System

FINISH RESTORATION 001 FINISH RESTORATION / PAINT - Repaint all surfaces to include but not limited to, all tile and hard ceilings, walls, doorjambs, doors, woodwork, ductwork, univents, radiators and built-in wood or metal cabinets, bathroom partitions painted or baked-on finish. All rooms, corridors, stairwells, closets, storage, mechanical rooms and piping per DPS piping color code. Duct cleaning is required in this scope.

2010 ABSORPTION CHILLER

2008 bond for the web Page 41 of 91

2008 GOB - Project Summary by Building & Year Denver Public Schools Facilities Faciliites Planning Management

Holm 2010 ABSORPTION CHILLER 001 ABSORBTION CHILLER - Replace with Centrifugal Water Chiller. Water treament included w/18 month warranty. Startup and commissioning included. Comply with DPS Design and Construction Standards SECTION 15650: REFRIGERATION, and all other applicable DPS Standards. Patch and repair.

WINDOWS 001 WINDOWS - METAL - Replace with current DPS standards. Coordinate with ongoing chiller replacement on-site.

2011 ASPHALT PAVING 001 ASPHALT / VEHICLE PARKING AND DRIVEWAYS - 2" overlay with geotec material.

HOWELL 2009 LEARNING LANDSCAPE 002 INSTALL MISSING ELEMENTS TO COMPLETE LEARNING LANDSCAPE

Jefferson 2009 OUTDOOR BLEACHERS 002 Outdoor Bleachers - INSTALL SAFETY RAILING, RISER BOARDS

004 Outdoor Bleachers - INSTALL SAFETY RAILING, RISER BOARDS

FIRE DETECTION 001 FIRE DETECTION SYSTEM - Replace existing ionization detectors with photo detectors

2011 ADA COMPLIANCE 001 REGULATORY - EGRESS / DOOR HARDWARE - Replace exterior door hardware for ADA compliance - A/E should conduct a door hardware schedule. Scope includes exterior doors (with panics if necessary), stairwell doors and hinges. A/E should identify any possible abatement issues to DPS Bond Hazmat project managers for remediation as early as possible.

SAFETY / STAGE RIGGING 001 HEALTH SAFETY / STAGE RIGGING - See Consultants Report (Danny Reid)

ASPHALT PAVING 001 ASPHALT / VEHICLE PARKING AND DRIVEWAYS - 2" overlay with geotec material.

002 ASPHALT / VEHICLE PARKING AND DRIVEWAYS - 2" overlay with geotec material.

CONCRETE / SITE STEPS 2008 bond for the web Page 42 of 91

2008 GOB - Project Summary by Building & Year Denver Public Schools Facilities Faciliites Planning Management

Jefferson 2011 001 CONCRETE / SITE STEPS - Replace the item

FINISH RESTORATION 001 FLOORING / WOOD FLOORING - 15600sf

2012 VENTILLATION / CENTRAL FAN / AHU 001 VENTILLATION / CENTRAL FAN / AHU - Commercial cleaning of units and duct work new motors and fan bearings damper sections controls and devices. Inspect duct work and repair as needed.Univent system needs commercial cleaning of units and new motors, fan bearings, dampers and cover hardware

TEMP CONTROLS / ENVIRONMENT 001 TEMP CONTROLS / ENVIRONMENT - Replace the item

Johnson 2009 ROOFING 009 ROOFING - BUILT-UP - Built-Up roofing to include the following: Gravel, 4-ply membrane,replace existing perlite with 1/2" wood fiber, 1/8" taper insulation, replace exsiting polyisocyanurate insulation with 2 layers of 2" polyisocyanurate insulation, replace flashing per DPS specs at all walls, drains, conduits, flues, gas lines, exhausts curbs, thru-wall and overflow scuppers, skylights, A/C lines, expansion joints, and parapets. Replace all gaspipe and similiar stand supports bases with concete pavers, paint all existing gas piping per DPS specs. Replace and seal all existing pipe collars. Inspect/replace all applicable drains and gutters.

021 ROOFING - BUILT-UP - Built-Up roofing to include the following: Gravel, 4-ply membrane,replace existing perlite with 1/2" wood fiber, 1/8" taper insulation, replace exsiting polyisocyanurate insulation with 2 layers of 2" polyisocyanurate insulation, replace flashing per DPS specs at all walls, drains, conduits, flues, gas lines, exhausts curbs, thru-wall and overflow scuppers, skylights, A/C lines, expansion joints, and parapets. Replace all gaspipe and similiar stand supports bases with concete pavers, paint all existing gas piping per DPS specs. Replace and seal all existing pipe collars. Inspect/replace all applicable drains and gutters.

022 ROOFING - BUILT-UP - Built-Up roofing to include the following: Gravel, 4-ply membrane,replace existing perlite with 1/2" wood fiber, 1/8" taper insulation, replace exsiting polyisocyanurate insulation with 2 layers of 2" polyisocyanurate insulation, replace flashing per DPS specs at all walls, drains, conduits, flues, gas lines, exhausts curbs, thru-wall and overflow scuppers, skylights, A/C lines, expansion joints, and parapets. Replace all gaspipe and similiar stand supports bases with concete pavers, paint all existing gas piping per DPS specs. Replace and seal all existing pipe collars. Inspect/replace all applicable drains and gutters.

FOLDING LUNCHRM TABLES 001 FOLDING LUNCHRM TABLES - INSTALL SURFACE MOUNTED POCKET TABLES

ROOFING

2008 bond for the web Page 43 of 91

2008 GOB - Project Summary by Building & Year Denver Public Schools Facilities Faciliites Planning Management

Johnson 2009 ROOFING 002 ROOFING - BUILT-UP - Built-Up roofing to include the following: Gravel, 4-ply membrane,replace existing perlite with 1/2" wood fiber, 1/8" taper insulation, replace exsiting polyisocyanurate insulation with 2 layers of 2" polyisocyanurate insulation, replace flashing per DPS specs at all walls, drains, conduits, flues, gas lines, exhausts curbs, thru-wall and overflow scuppers, skylights, A/C lines, expansion joints, and parapets. Replace all gaspipe and similiar stand supports bases with concete pavers, paint all existing gas piping per DPS specs. Replace and seal all existing pipe collars. Inspect/replace all applicable drains and gutters.

004 ROOFING - BUILT-UP - Built-Up roofing to include the following: Gravel, 4-ply membrane,replace existing perlite with 1/2" wood fiber, 1/8" taper insulation, replace exsiting polyisocyanurate insulation with 2 layers of 2" polyisocyanurate insulation, replace flashing per DPS specs at all walls, drains, conduits, flues, gas lines, exhausts curbs, thru-wall and overflow scuppers, skylights, A/C lines, expansion joints, and parapets. Replace all gaspipe and similiar stand supports bases with concete pavers, paint all existing gas piping per DPS specs. Replace and seal all existing pipe collars. Inspect/replace all applicable drains and gutters.

005 ROOFING - BUILT-UP - Built-Up roofing to include the following: Gravel, 4-ply membrane,replace existing perlite with 1/2" wood fiber, 1/8" taper insulation, replace exsiting polyisocyanurate insulation with 2 layers of 2" polyisocyanurate insulation, replace flashing per DPS specs at all walls, drains, conduits, flues, gas lines, exhausts curbs, thru-wall and overflow scuppers, skylights, A/C lines, expansion joints, and parapets. Replace all gaspipe and similiar stand supports bases with concete pavers, paint all existing gas piping per DPS specs. Replace and seal all existing pipe collars. Inspect/replace all applicable drains and gutters.

007 ROOFING - BUILT-UP - Built-Up roofing to include the following: Gravel, 4-ply membrane,replace existing perlite with 1/2" wood fiber, 1/8" taper insulation, replace exsiting polyisocyanurate insulation with 2 layers of 2" polyisocyanurate insulation, replace flashing per DPS specs at all walls, drains, conduits, flues, gas lines, exhausts curbs, thru-wall and overflow scuppers, skylights, A/C lines, expansion joints, and parapets. Replace all gaspipe and similiar stand supports bases with concete pavers, paint all existing gas piping per DPS specs. Replace and seal all existing pipe collars. Inspect/replace all applicable drains and gutters.

010 ROOFING - BUILT-UP - Built-Up roofing to include the following: Gravel, 4-ply membrane,replace existing perlite with 1/2" wood fiber, 1/8" taper insulation, replace exsiting polyisocyanurate insulation with 2 layers of 2" polyisocyanurate insulation, replace flashing per DPS specs at all walls, drains, conduits, flues, gas lines, exhausts curbs, thru-wall and overflow scuppers, skylights, A/C lines, expansion joints, and parapets. Replace all gaspipe and similiar stand supports bases with concete pavers, paint all existing gas piping per DPS specs. Replace and seal all existing pipe collars. Inspect/replace all applicable drains and gutters.

015 ROOFING - BUILT-UP - Built-Up roofing to include the following: Gravel, 4-ply membrane,replace existing perlite with 1/2" wood fiber, 1/8" taper insulation, replace exsiting polyisocyanurate insulation with 2 layers of 2" polyisocyanurate insulation, replace flashing per DPS specs at all walls, drains, conduits, flues, gas lines, exhausts curbs, thru-wall and overflow scuppers, skylights, A/C lines, expansion joints, and parapets. Replace all gaspipe and similiar stand supports bases with concete pavers, paint all existing gas piping per DPS specs. Replace and seal all existing pipe collars. Inspect/replace all applicable drains and gutters.

020 ROOFING - BUILT-UP - Built-Up roofing to include the following: Gravel, 4-ply membrane,replace existing perlite with 1/2" wood fiber, 1/8" taper insulation, replace exsiting polyisocyanurate insulation with 2 layers of 2" polyisocyanurate insulation, replace flashing per DPS specs at all walls, drains, conduits, flues, gas lines, exhausts curbs, thru-wall and overflow scuppers, skylights, A/C lines, expansion joints, and parapets. Replace all gaspipe and similiar stand supports bases with concete pavers, paint all existing gas piping per DPS specs. Replace and seal all existing pipe collars. Inspect/replace all applicable drains and gutters.

LEARNING LANDSCAPE 001 LEARNING LANDSCAPE - Construct Learning Landscape per UCD Master Plan. Include 2" playground surface asphalt overlay..

FINISH RESTORATION 2008 bond for the web Page 44 of 91

2008 GOB - Project Summary by Building & Year Denver Public Schools Facilities Faciliites Planning Management

Johnson 2009 FINISH RESTORATION 001 FINISH RESTORATION / PAINT - Repaint all surfaces to include but not limited to, all tile and hard ceilings, walls, doorjambs, doors, woodwork, ductwork, univents, radiators and built-in wood or metal cabinets, bathroom partitions painted or baked-on finish. All rooms, corridors, stairwells, closets, storage, mechanical rooms and piping per DPS piping color code. Duct cleaning is required in this scope.

FINISH RESTORATION 001 FINISH RESTORATION / SEAMLESS FLR - replace all seamless with ceramic/quarry tile

FINISH RESTORATION 001 FINISH RESTORATION / TILE - Seamless floor worn out,replace with quarry tile

REGULATORY / LIGHT FIXTURES 001 REGULATORY LIGHT FIXTURES - Replace all T-12 and incandescent lighting fixtures with T-8 or T5HO fixtures. Properly dispose of all existing lamps and fixtures. Comply with DPS Design and Construction Standards SECTIONS 16501: LAMPS, 16502 BALLASTS AND CONTROLS and 16510: LUMINAIRES and all other applicable DPS Standards. Patch and Repair.

Kaiser 2009 FOLDING LUNCHRM TABLES 001 FOLDING LUNCHRM TABLES - INSTALL SURFACE MOUNTED POCKET TABLES

ABSORPTION CHILLER 001 ABSORPTION CHILLER - Replace the item

2013 FINISH RESTORATION 001 FINISH RESTORATION / SEAMLESS FLR - replace all seamless with ceramic/quarry tile

Kennedy 2010 REGULATORY / LIGHT FIXTURES 001 REGULATORY LIGHT FIXTURES - Replace all T-12 and incandescent lighting fixtures with T-8 or T5HO fixtures. Properly dispose of all existing lamps and fixtures. Comply with DPS Design and Construction Standards SECTIONS 16501: LAMPS, 16502 BALLASTS AND CONTROLS and 16510: LUMINAIRES and all other applicable DPS Standards. Patch and Repair.

WINDOWS 001 WINDOWS - METAL - Replace with current DPS standards. - Coordinate with ongoing light fixture replacement on-site.

2011 SAFETY / STAGE RIGGING 2008 bond for the web Page 45 of 91

2008 GOB - Project Summary by Building & Year Denver Public Schools Facilities Faciliites Planning Management

Kennedy 2011 SAFETY / STAGE RIGGING 001 HEALTH SAFETY / STAGE RIGGING - See Consultants Report (Danny Reid)

ADA COMPLIANCE 001 REGULATORY - EGRESS / DOOR HARDWARE - Replace exterior door hardware for ADA compliance - A/E should conduct a door hardware schedule. Scope includes exterior doors (with panics if necessary), stairwell doors and hinges. A/E should identify any possible abatement issues to DPS Bond Hazmat project managers for remediation as early as possible.

FINISH RESTORATION 001 FINISH RESTORATION / PAINT - Repaint all surfaces to include but not limited to, all tile and hard ceilings, walls, doorjambs, doors, woodwork, ductwork, univents, radiators and built-in wood or metal cabinets, bathroom partitions painted or baked-on finish. All rooms, corridors, stairwells, closets, storage, mechanical rooms and piping per DPS piping color code. Duct cleaning is required in this scope.

FINISH RESTORATION 001 FINISH RESTORATION / CARPET - Replace the item

FINISH RESTORATION 001 FINISH RESTORATION / TILE - Quarry tile substrate is loose,replace with new quarry tile

ARTIFICIAL TURF 001 ARTIFICIAL TURF - Remove existing sod athletic field and replace with artificial turf

Kennedy Vocational 2011 FINISH RESTORATION 001 FINISH RESTORATION / PAINT - Repaint all surfaces to include but not limited to, all tile and hard ceilings, walls, doorjambs, doors, woodwork, ductwork, univents, radiators and built-in wood or metal cabinets, bathroom partitions painted or baked-on finish. All rooms, corridors, stairwells, closets, storage, mechanical rooms and piping per DPS piping color code. Duct cleaning is required in this scope.

Kepner 2009 ROOFING 013 ROOFING - BUILT-UP - Built-Up roofing to include the following: Gravel, 4-ply membrane,replace existing perlite with 1/2" wood fiber, 1/8" taper insulation, replace exsiting polyisocyanurate insulation with 2 layers of 2" polyisocyanurate insulation, replace flashing per DPS specs at all walls, drains, conduits, flues, gas lines, exhausts curbs, thru-wall and overflow scuppers, skylights, A/C lines, expansion joints, and parapets. Replace all gaspipe and similiar stand supports bases with concete pavers, paint all existing gas piping per DPS specs. Replace and seal all existing pipe collars. Inspect/replace all applicable drains and gutters.

ROOFING 001 ROOFING / BUILT UP - Reroof building

2008 bond for the web Page 46 of 91

2008 GOB - Project Summary by Building & Year Denver Public Schools Facilities Faciliites Planning Management

Kepner 2009 ROOFING 006 ROOFING - BUILT-UP - Built-Up roofing to include the following: Gravel, 4-ply membrane,replace existing perlite with 1/2" wood fiber, 1/8" taper insulation, replace exsiting polyisocyanurate insulation with 2 layers of 2" polyisocyanurate insulation, replace flashing per DPS specs at all walls, drains, conduits, flues, gas lines, exhausts curbs, thru-wall and overflow scuppers, skylights, A/C lines, expansion joints, and parapets. Replace all gaspipe and similiar stand supports bases with concete pavers, paint all existing gas piping per DPS specs. Replace and seal all existing pipe collars. Inspect/replace all applicable drains and gutters.

007 ROOFING - BUILT-UP - Built-Up roofing to include the following: Gravel, 4-ply membrane,replace existing perlite with 1/2" wood fiber, 1/8" taper insulation, replace exsiting polyisocyanurate insulation with 2 layers of 2" polyisocyanurate insulation, replace flashing per DPS specs at all walls, drains, conduits, flues, gas lines, exhausts curbs, thru-wall and overflow scuppers, skylights, A/C lines, expansion joints, and parapets. Replace all gaspipe and similiar stand supports bases with concete pavers, paint all existing gas piping per DPS specs. Replace and seal all existing pipe collars. Inspect/replace all applicable drains and gutters.

008 ROOFING - BUILT-UP - Built-Up roofing to include the following: Gravel, 4-ply membrane,replace existing perlite with 1/2" wood fiber, 1/8" taper insulation, replace exsiting polyisocyanurate insulation with 2 layers of 2" polyisocyanurate insulation, replace flashing per DPS specs at all walls, drains, conduits, flues, gas lines, exhausts curbs, thru-wall and overflow scuppers, skylights, A/C lines, expansion joints, and parapets. Replace all gaspipe and similiar stand supports bases with concete pavers, paint all existing gas piping per DPS specs. Replace and seal all existing pipe collars. Inspect/replace all applicable drains and gutters.

010 ROOFING - BUILT-UP - Built-Up roofing to include the following: Gravel, 4-ply membrane,replace existing perlite with 1/2" wood fiber, 1/8" taper insulation, replace exsiting polyisocyanurate insulation with 2 layers of 2" polyisocyanurate insulation, replace flashing per DPS specs at all walls, drains, conduits, flues, gas lines, exhausts curbs, thru-wall and overflow scuppers, skylights, A/C lines, expansion joints, and parapets. Replace all gaspipe and similiar stand supports bases with concete pavers, paint all existing gas piping per DPS specs. Replace and seal all existing pipe collars. Inspect/replace all applicable drains and gutters.

011 ROOFING - BUILT-UP - Built-Up roofing to include the following: Gravel, 4-ply membrane,replace existing perlite with 1/2" wood fiber, 1/8" taper insulation, replace exsiting polyisocyanurate insulation with 2 layers of 2" polyisocyanurate insulation, replace flashing per DPS specs at all walls, drains, conduits, flues, gas lines, exhausts curbs, thru-wall and overflow scuppers, skylights, A/C lines, expansion joints, and parapets. Replace all gaspipe and similiar stand supports bases with concete pavers, paint all existing gas piping per DPS specs. Replace and seal all existing pipe collars. Inspect/replace all applicable drains and gutters.

2011 WINDOWS 001 METAL WINDOWS - Replace the item

2013 STAGE CURTAIN / AUDITORIUM 001 STAGE CURTAIN / AUDITORIUM - Replace all curtains and make rigging corrections

ADA COMPLIANCE 001 ADA COMPLIANCE - DOOR HARDWARE - A/E should conduct a room by room door hardware schedule. Scope includes all doors, utility closets, exterior doors (with panics if necessary), stairwell doors and hinges. Excluded are cabinetry doors. A/E should identify any possible abatement issues to DPS Bond Hazmat project managers for remediation as early as possible.

FINISH RESTORATION

2008 bond for the web Page 47 of 91

2008 GOB - Project Summary by Building & Year Denver Public Schools Facilities Faciliites Planning Management

Kepner 2013 FINISH RESTORATION 001 FINISH RESTORATION / CARPET - Replace the item

King 2009 FIRE DETECTION 001 FIRE DETECTION SYSTEM - Detectors only. New FACP installed

CHILLER 001 CHILLER - REPLACE CHILLER

2010 VENTILLATION / CENTRAL FAN / AHU 001 VENTILLATION - CENTRAL FAN - AHU - Attention this scope of work cannot proceed unless it is bundled with H ENS C Temp Controls /Environment Scope. Design for HVAC replacement, and the removal of material and equipment no longer needed. Comply with DPS Design and Construction Standards Division 15 (applicable sections) and all other applicable DPS Standards. Patch and repair. Replace all unit-ventilators, replace steam and condensate feeds back to main, and replace all steam traps including drip and end of main. Include case work required to accommodate new unit-ventilators. All other central air-handling units need commercial cleaning, duct work repaired as needed, new motors, replace branch piping if needed, steam traps, fan bearings and damper sections. Replace all Exhaust Fans including dampers. Replace steam traps as needed. Ductwork cleaning as needed.

WINDOWS 001 WINDOWS - GLAZING - Replace approximately 6000 sf of window glazing. Coordinate with ongoing ventillation & central fan and AHUs replacement on-site.

2013 STAGE CURTAIN / AUDITORIUM 001 STAGE CURTAIN / AUDITORIUM - Replace all curtains and make rigging corrections

ADA COMPLIANCE 001 REGULATORY - EGRESS / DOOR HARDWARE - Replace exterior door hardware for ADA compliance - A/E should conduct a door hardware schedule. Scope includes exterior doors (with panics if necessary), stairwell doors and hinges. A/E should identify any possible abatement issues to DPS Bond Hazmat project managers for remediation as early as possible.

FINISH RESTORATION 001 FINISH RESTORATION / PAINT - Repaint all surfaces to include but not limited to, all tile and hard ceilings, walls, doorjambs, doors, woodwork, ductwork, univents, radiators and built-in wood or metal cabinets, bathroom partitions painted or baked-on finish. All rooms, corridors, stairwells, closets, storage, mechanical rooms and piping per DPS piping color code. Duct cleaning is required in this scope.

FINISH RESTORATION 001 FINISH RESTORATION / SEAMLESS FLR - replace all seamless with ceramic/quarry tile

2008 bond for the web Page 48 of 91

2008 GOB - Project Summary by Building & Year Denver Public Schools Facilities Faciliites Planning Management

King 2013 ASPHALT PAVING 002 ASPHALT / VEHICLE PARKING AND DRIVEWAYS - Replace the item

003 ASPHALT / VEHICLE PARKING AND DRIVEWAYS - Expand parking to meet zoning requirements for high school students

Knapp 2009 FIRE DETECTION 001 FIRE DETECTION SYSTEM - Panel only. No longer supported by Manufacture

FINISH RESTORATION 000 FINISH RESTORATION / PAINT - Repaint all surfaces to include but not limited to, all tile and hard ceilings, walls, doorjambs, doors, woodwork, ductwork, univents, radiators and built-in wood or metal cabinets, bathroom partitions painted or baked-on finish. All rooms, corridors, stairwells, closets, storage, mechanical rooms and piping per DPS piping color code. Duct cleaning is required in this scope.

2010 IRRIGATION 001 IRRIGATION - Repair/replace existing irrigation system, piping, controls, heads, backflows, electrical and connections per DPS standards. Knapp - Site area to include all lawn areas around main buidling, no play areas, approximatley 53,000 sf. Exclude field and grass west of exisiting field. Consolidate 2 clocks into 1 central clock. See DPS Planning for site plans and QA/QC evaluations/recommendations.

Knight 2009 BUILDING (REMODEL) 001 Renovation of Knight to accommodate new ECE center

2010 FIRE SUPPRESSION / SPRINKLER 001 FIRE SPRINKLER SYSTEM - Design new fire sprinkler system throughout entire building. Comply with DPS Design and Construction Standards SECTION 15300: STANDPIPE AND FIRE SPRINKLER STANDARDS and all other applicable DPS Standards. Patch and Repair.

2011 FINISH RESTORATION 000 FINISH RESTORATION / PAINT - Repaint all surfaces to include but not limited to, all tile and hard ceilings, walls, doorjambs, doors, woodwork, ductwork, univents, radiators and built-in wood or metal cabinets, bathroom partitions painted or baked-on finish. All rooms, corridors, stairwells, closets, storage, mechanical rooms and piping per DPS piping color code. Duct cleaning is required in this scope.

FINISH RESTORATION

2008 bond for the web Page 49 of 91

2008 GOB - Project Summary by Building & Year Denver Public Schools Facilities Faciliites Planning Management

Knight 2011 FINISH RESTORATION 001 FINISH RESTORATION / TILE - floor is VAT and needs abatement and replaced with quarry tile

ROOFING 003 ROOFING / EPDM / PVC / SINGLE-PLY - Replace the item

LEARNING LANDSCAPE 001 LEARNING LANDSCAPE - Construct Learning Landscape per UCD Master Plan. Include 2" playground surface asphalt overlay..

2013 REGULATORY / LIGHT FIXTURES 001 REGULATORY LIGHT FIXTURES - Replace all T-12 and incandescent lighting fixtures with T-8 or T5HO fixtures. Properly dispose of all existing lamps and fixtures. Comply with DPS Design and Construction Standards SECTIONS 16501: LAMPS, 16502 BALLASTS AND CONTROLS and 16510: LUMINAIRES and all other applicable DPS Standards. Patch and Repair.

WINDOWS 001 METAL WINDOWS - Replace the item

Kunsmiller 2009 LUNCHROOM TABLES 002 REMOVE AND REPLACE CAFETERIA TABLES

BUILDING (REMODEL) 001 K-12 REMODELING OF KUNSMILLER - PHASE 1

BUILDING (REMODEL) 001 REMODEL SCHOOL FOR SHARED CAMPUS USE (WEST DENVER PREP)

2010 REGULATORY / LIGHT FIXTURES 001 REGULATORY LIGHT FIXTURES - Replace all T-12 and incandescent lighting fixtures with T-8 or T5HO fixtures. Properly dispose of all existing lamps and fixtures. Comply with DPS Design and Construction Standards SECTIONS 16501: LAMPS, 16502 BALLASTS AND CONTROLS and 16510: LUMINAIRES and all other applicable DPS Standards. Patch and Repair.

VENTILLATION / CENTRAL FAN / AHU

2008 bond for the web Page 50 of 91

2008 GOB - Project Summary by Building & Year Denver Public Schools Facilities Faciliites Planning Management

Kunsmiller 2010 VENTILLATION / CENTRAL FAN / AHU 001 VENTILLATION - CENTRAL FAN - AHU - Attention this scope of work cannot proceed unless it is bundled with H ENS C Temp Controls /Environment Scope. Design for HVAC replacement, and the removal of material and equipment no longer needed. Comply with DPS Design and Construction Standards Division 15 (applicable sections) and all other applicable DPS Standards. Patch and repair. Replace all unit-ventilators, replace steam and condensate feeds back to main, and replace all steam traps including drip and end of main. Include case work required to accommodate new unit-ventilators. All other central air-handling units need commercial cleaning, duct work repaired as needed, new motors, replace branch piping if needed, steam traps, fan bearings and damper sections. Replace all Exhaust Fans including dampers. Replace steam traps as needed. Ductwork cleaning as needed.

TEMP CONTROLS / ENVIRONMENT 001 TEMP CONTROLS - ENVIRONMENT - Attention this scope of work cannot proceed unless it is bundled with H VNT C Ventilation/Central Fan/ AHU Scope. Design for temperature controls replacement, and the removal of material and equipment no longer needed. Comply with DPS Design and Construction Standards SECTIONS 15950: CONTROLS, 15975: INTEGRATED BUILDING AUTOMATION SYSTEM (IBAS) and all other applicable DPS Standards. Patch and repair. Install digital controls and control devices in new unit-ventilators, retrofit all other central air-handling units with new digital controls, electric damper operators, electric valves and operators. Exhaust fan control should be tied in with HVAC system where required or as was original intent. Include convectors, radiators, cabinet heaters, fan-coil units, reheats or other terminal heating equipment in DDC upgrade. Include IBAS interface.

2011 FINISH RESTORATION 000 FINISH RESTORATION - VCT TILE Replace exsting tile in cafeteria, hallway, stairwell with new VCT per DPS specification. Include adjoining storage rooms.

ASPHALT PAVING 001 ASPHALT / VEHICLE PARKING AND DRIVEWAYS - 2" overlay with geotec material.

BUILDING (REMODEL) 002 K-12 REMODELING OF KUNSMILLER - PHASE 2

Lake 2010 IRRIGATION 001 IRRIGATION - Replace partial existing irrigation system, piping, controls, heads, backflows, electrical and connections per DPS standards. Lake - Site area to include lawn around main building and site perimeter, no play areas, approximatley 123,000 sf. Consolidate 2 clocks into 1 central clock. Area across 18th st. to be xeriscaped and irrigation abandoned. See DPS Planning for site plans and QA/QC evaluations/recommendations.

2011 FINISH RESTORATION 001 FINISH RESTORATION / SEAMLESS FLR - replace all seamless with ceramic/quarry tile

FINISH RESTORATION

2008 bond for the web Page 51 of 91

2008 GOB - Project Summary by Building & Year Denver Public Schools Facilities Faciliites Planning Management

Lake 2011 FINISH RESTORATION 001 FINISH RESTORATION / VINYL TILE - Replace existing VAT or VCT with new VCT except New Addn. Price does not include abatement.

REGULATORY / LIGHT FIXTURES 001 REGULATORY / LIGHT FIXTURES - Replace all lenses on fixtures in IMC

TOILET ROOM (INCLUSIVE) 001 Toilet Room (inclusive) - Replace all fixtures, plumbing piping and partitions. Paint walls and Ceilings. Replace tile as required. Lighting to be updated. Repair any associated surface damage, i.e., glazed block, etc.

2013 STAGE CURTAIN / AUDITORIUM 001 STAGE CURTAIN / AUDITORIUM - Replace all curtains and make rigging corrections

FIRE SUPPRESSION / SPRINKLER 001 FIRE SPRINKLER SYSTEM - Design new fire sprinkler system throughout entire building. Comply with DPS Design and Construction Standards SECTION 15300: STANDPIPE AND FIRE SPRINKLER STANDARDS and all other applicable DPS Standards. Patch and Repair.

Lincoln 2009 REGULATORY / LIGHT FIXTURES 001 REGULATORY LIGHT FIXTURES - Replace all T-12 and incandescent lighting fixtures with T-8 or T5HO fixtures. Properly dispose of all existing lamps and fixtures. Comply with DPS Design and Construction Standards SECTIONS 16501: LAMPS, 16502 BALLASTS AND CONTROLS and 16510: LUMINAIRES and all other applicable DPS Standards. Patch and Repair.

2012 ASPHALT PAVING 001 ASPHALT / VEHICLE PARKING AND DRIVEWAYS - 2" overlay with geotec material.

2013 TOILET ROOM (INCLUSIVE) 001 Toilet Room (inclusive) - Replace all fixtures, plumbing piping and partitions. Paint walls and Ceilings. Replace tile as required. Lighting to be updated. Repair any associated surface damage, i.e., glazed block, etc.

Lowry 2009 TECHNOLOGY CONSTRUCTION SUPPORT 002 TECHNOLOGY CONSTRUCTION SUPPORT - Install dedicated air conditioning unit in the MDF.

2008 bond for the web Page 52 of 91

2008 GOB - Project Summary by Building & Year Denver Public Schools Facilities Faciliites Planning Management

Lowry 2009 LEARNING LANDSCAPE 001 install missing learning landscape elements

MANN 2009 LEARNING LANDSCAPE 002 INSTALL MISSING ELEMENTS TO COMPLETE LEARNING LANDSCAPE

2010 FIRE SUPPRESSION / SPRINKLER 001 FIRE SPRINKLER SYSTEM - Design new fire sprinkler system throughout entire building. Comply with DPS Design and Construction Standards SECTION 15300: STANDPIPE AND FIRE SPRINKLER STANDARDS and all other applicable DPS Standards. Patch and Repair.

2013 STAGE CURTAIN / AUDITORIUM 001 STAGE CURTAIN / AUDITORIUM - Replace all curtains and make rigging corrections

ADA COMPLIANCE 001 ADA COMPLIANCE - DOOR HARDWARE - A/E should conduct a room by room door hardware schedule. Scope includes all doors, utility closets, exterior doors (with panics if necessary), stairwell doors and hinges. Excluded are cabinetry doors. A/E should identify any possible abatement issues to DPS Bond Hazmat project managers for remediation as early as possible.

FINISH RESTORATION 001 FINISH RESTORATION / PAINT - Replace the item

FINISH RESTORATION 001 FINISH RESTORATION / TILE - Quarry tile substrate is loose,replace with new quarry tile

FINISH RESTORATION 001 FLOORING / WOOD FLOORING - replace gym flooring

DIMMER SYSTEM (STAGE AND PERFORMANCE) 001 DIMMER SYSTEM (STAGE AND PERFORMANCE) - Replace the item

REGULATORY / LIGHT FIXTURES 001 REGULATORY / LIGHT FIXTURES - Replace T-12 fixtures in IMC and main entrance.

2008 bond for the web Page 53 of 91

2008 GOB - Project Summary by Building & Year Denver Public Schools Facilities Faciliites Planning Management

Manual 2009 DIMMER SYSTEM (STAGE AND PERFORMANCE) 001 DIMMER SYSTEM (STAGE AND PERFORMANCE) - Replace the item

FINISH RESTORATION 001 FINISH RESTORATION / TILE - Replace the item

HOT WATER HEATER 001 HOT WATER HEATER - REPLACE EXISTING HOT WATER HEATER

TOILET ROOM (INCLUSIVE) 001 Toilet Room (inclusive) - REPLACE TOILET FIXTURES

2010 ADA COMPLIANCE 001 ADA COMPLIANCE - DOOR HARDWARE - A/E should conduct a room by room door hardware schedule. Scope includes all doors, utility closets, exterior doors (with panics if necessary), stairwell doors and hinges. Excluded are cabinetry doors. A/E should identify any possible abatement issues to DPS Bond Hazmat project managers for remediation as early as possible.

FINISH RESTORATION 001 FINISH RESTORATION - PAINT - Scope includes repainted of all existing painted items, including ceilings, closets, stair rails and raisersand flooring in boiler rooms. Exclude piping. Include alljanitorial clostets, and storgage rooms. Contractor is responisble for moving shelving. Boxes (500 per school) are to be provided to each school to distribute as necessary. School is to box personal items & clear off walls in classroom. Provide secure storage for computers and other items, colors selected by principles, number/locations of colors base on DPS standards and A/E selections. Division 9 (prep,staple hole fills, patching, etc, prime, paint 2 coats. Coordinate with DOTS/Denver Fire for covering data/phone outlets, all fire systems, to be protected. Duct cleaning is included in scope prior to painting. Refinishing all stain doors to be added as alternates). See DPS standards regarding staging and moving. Manual - For 2nd & 3rd floors, no classrooms get painted (painted 1& 2 years ago respectively). Paint all offices, hallways, lockers, utility rooms, stairwells, verify bathrooms. Maual - All Other Floors/Basement - Paint all surfaces in all rooms. Manual School-wide- Windows are to be replaced in 2012 so no window frames should be repainted under this scope of work.

ARTIFICIAL TURF 001 ARTIFICIAL TURF - Scope to include all civil testing and easements, permimeter fencing, all civil testing, detention ponds and related drainage subsystems, and subgrade w/drainage. Provide sleeving in field for school- provided scoreboard, pad for bleacher seating are optional, provide step system for slopes if required. Note that 2 lanes of exsiting track will be consumed by turf, so significant repair and resurfacing of track will be required. Provide industry standard athletic stripping, and dimensions. Provide sleeves for future electrical needs. DPS O&M Shops to retain slavage rights on irrrigation and other demo. Excess soil should remain on site if possible. Provide ADA access to seating areas.

2012 WINDOWS 001 METAL WINDOWS - Replace the item

2008 bond for the web Page 54 of 91

2008 GOB - Project Summary by Building & Year Denver Public Schools Facilities Faciliites Planning Management

Marrama 2009 FOLDING LUNCHRM TABLES 001 FOLDING LUNCHRM TABLES - INSTALL SURFACE MOUNTED POCKET TABLES

FIRE DETECTION 001 FIRE DETECTION SYSTEM - Detectors only. New FACP installed

ROOFING 007 ROOFING / EPDM / PVC / SINGLE-PLY - Replace the item

2010 ASPHALT PAVING 001 ASPHALT REPLACEMENT - Replace 43,000sq.ft of asphalt with 2" overlay with geotec material. Rework bus parking and drives for better bus manuvering. Add concrete curbing to on sloped drive. Add concrete bollard to protect electrical box. Replace concrete blocks. To be conducted in accordance with DPS drawings, specifications and referenced publications associated with this project. Include all pertinent civil engineering, testing, and permitting as necessary. Striping, ADA parking space allocations, as well as motorcycle parking, signage to be included per DPS/City of Denver code. Replace all impacted landscaping, sod, and irrigation equipment if necessary. Coordinate with learning landscape project. See DPS Planning for site specific plans and QA/QC evaluation/recommendations. Add concrete dumpster pad as alternate

LEARNING LANDSCAPE 001 LEARNING LANDSCAPE - Construct Learning Landscape per UCD Master Plan. Remove existing and replace playground asphalt. Include 2" playground surface asphalt overlay. Coordinate with parking lot paving. See master plan draft at www.learninglanscapes.org -Conduct soils asphalt and other pertinent testing prior to bid development.

2012 VENTILLATION / CENTRAL FAN / AHU 001 VENTILLATION / CENTRAL FAN / AHU - Replace the item

TEMP CONTROLS / ENVIRONMENT 001 TEMP CONTROLS / ENVIRONMENT - Replace the item

Maxwell 2009 FINISH RESTORATION 001 FINISH RESTORATION / VINYL TILE - Replace existing VAT or VCT with new VCT. Price does not include abatement.

LEARNING LANDSCAPE 001 Install missing Learning Landscape elements.

2008 bond for the web Page 55 of 91

2008 GOB - Project Summary by Building & Year Denver Public Schools Facilities Faciliites Planning Management

McGlone 2009 LUNCHROOM TABLES 001 Replace the item

VIDEO SECURITY 001 Video Security - Install A/C

FINISH RESTORATION 001 FINISH RESTORATION / PAINT - Repaint all surfaces to include but not limited to, all tile and hard ceilings, walls, doorjambs, doors, woodwork, ductwork, univents, radiators and built-in wood or metal cabinets, bathroom partitions painted or baked-on finish. All rooms, corridors, stairwells, closets, storage, mechanical rooms and piping per DPS piping color code. Duct cleaning is required in this scope.

FINISH RESTORATION 001 FINISH RESTORATION / SEAMLESS FLR - replace all seamless with ceramic/quarry tile

2010 IRRIGATION 001 IRRIGATION - Replace existing irrigation system, piping, controls, heads, backflows, electrical and connections per DPS standards. - McGlone- Site area to include all lawn areas around main building and site perimeter, approximatley 46,000 sf. Work to be conducted in conjunction with learning landscape project. See DPS Planning for site plans and QA/QC evaluations/recommendations.

LEARNING LANDSCAPE 001 LEARNING LANDSCAPE - Construct Learning Landscape per UCD Master Plan. Remove existing and replace playground asphalt. Include 2" playground surface asphalt overlay. Coordinate with irrigation replacement project. See master plan draft at www.learninglanscapes.org - Conduct soils asphalt and other pertinent testing prior to bid development.

McKinley Thatcher 2009 FOLDING LUNCHRM TABLES 001 FOLDING LUNCHRM TABLES - INSTALL SURFACE MOUNTED POCKET TABLES

2012 LEARNING LANDSCAPE 001 LEARNING LANDSCAPE - Construct Learning Landscape per UCD Master Plan. Include 2" playground surface asphalt overlay..

2013 ADA COMPLIANCE

2008 bond for the web Page 56 of 91

2008 GOB - Project Summary by Building & Year Denver Public Schools Facilities Faciliites Planning Management

McKinley Thatcher 2013 ADA COMPLIANCE 001 ADA COMPLIANCE - LEVEL 1 - Comply with DPS Design and Construction Standards SECTION 00700: ACCESSIBILITY STANDARDS and all other applicable DPS Standards. See ADA Level 1 Database provided. Deficiency remedies provided in ADA database should serve as the PM guide only and should not be provided to the A/E for purposes of developing the project scope of work. A/E is directed to conduct a building survey limited to the areas identified in the survey. Other ADA deficiencies may be included if they meet the level 1 status and have not been identified in the survey. All questions of possible oversight of a deficiency shall be directed to DPS Facility Planning through the DPS Project Manager.

FINISH RESTORATION 000 FINISH RESTORATION / PAINT - Repaint all surfaces to include but not limited to, all tile and hard ceilings, walls, doorjambs, doors, woodwork, ductwork, univents, radiators and built-in wood or metal cabinets, bathroom partitions painted or baked-on finish. All rooms, corridors, stairwells, closets, storage, mechanical rooms and piping per DPS piping color code. Duct cleaning is required in this scope.

McMeen 2009 ADA COMPLIANCE 001 ADA COMPLIANCE - LEVEL 1 - Comply with DPS Design and Construction Standards SECTION 00700: ACCESSIBILITY STANDARDS and all other applicable DPS Standards. See ADA Level 1 Database provided. Deficiency remedies provided in ADA database should serve as the PM guide only and should not be provided to the A/E for purposes of developing the project scope of work. A/E is directed to conduct a building survey limited to the areas identified in the survey. Other ADA deficiencies may be included if they meet the level 1 status and have not been identified in the survey. All questions of possible oversight of a deficiency shall be directed to DPS Facility Planning through the DPS Project Manager.

BUILDNG (NEW) 001 PLACE MODULAR CLASSROOMS FOR ECE EXPANSION FULL DAY PROGRAMS

Merrill 2009 OUTDOOR BLEACHERS 001 Outdoor Bleachers - INSTALL SAFETY RAILING, RISER BOARDS

BUILDING (REMODEL) 001 REMODEL BASEMENT FOR ECE CENTER PROGRAM

2010 FIRE DETECTION 001 FIRE DETECTION - Design for replacement of entire fire alarm system and removal of old equipment not used in new system. Comply with DPS Design and Construction Standards SECTION 16721: FIRE ALARM SYSTEMS (POINT GRAPHIC SYSTEMS) and all other applicable DPS Standards. Patch and Repair.

2011 2008 bond for the web Page 57 of 91

2008 GOB - Project Summary by Building & Year Denver Public Schools Facilities Faciliites Planning Management

Merrill 2011 BOILER 001 BOILER - Replace boiler as per DPS guide specs 15555C. Replace in boiler room: condensate return pumps, steam traps, condensate return pipe, boiler feed pipe, and all valves. Ref. spec. 15110, 15521, and all div. 15 that apply including water treatment associated with this project ref. 15548

REGULATORY / LIGHT FIXTURES 001 REGULATORY LIGHT FIXTURES - Replace all T-12 and incandescent lighting fixtures with T-8 or T5HO fixtures. Properly dispose of all existing lamps and fixtures. Comply with DPS Design and Construction Standards SECTIONS 16501: LAMPS, 16502 BALLASTS AND CONTROLS and 16510: LUMINAIRES and all other applicable DPS Standards. Patch and Repair.

VENTILLATION / CENTRAL FAN / AHU 001 VENTILLATION / CENTRAL FAN / AHU - Attention this scope of work cannot proceed unless it is bundled with H ENS C Temp Controls /Environment Scope. Univent system needs complete replacement, replace supply and return feeds back to main, include case work required to accommodate new univents. All other Central Air Handling Units need commercial cleaning, duct work repaired as needed, new motors, new pumps, replace branch piping if needed, fan bearings and damper sections. Replace all Exhaust Fans including dampers

WINDOWS 001 METAL WINDOWS - Replace the item

TEMP CONTROLS / ENVIRONMENT 001 TEMP CONTROLS / ENVIRONMENT - Attention this scope of work cannot proceed unless it is bundled with H VNT C Ventilation/Central Fan/ AHU Scope. Install digital controls and control devices in new univents, retrofit all other central air handling units with new digital controls, electric damper operators, electric valves and operators. Exhaust Fan control should be tied in with HVAC system where required or as was original intent. Include Convectors, Radiators, Caninet heaters, Fancoil Units, Reheats or other terminal heating equipment in DDC upgrade.

2012 ADA COMPLIANCE 001 REGULATORY - EGRESS / DOOR HARDWARE - Replace exterior door hardware for ADA compliance - A/E should conduct a door hardware schedule. Scope includes exterior doors (with panics if necessary), stairwell doors and hinges. A/E should identify any possible abatement issues to DPS Bond Hazmat project managers for remediation as early as possible.

FINISH RESTORATION 001 FINISH RESTORATION / VINYL TILE - Replace existing VAT or VCT with new VCT. Price does not include abatement.

Montbello 2009 TECHNOLOGY CONSTRUCTION SUPPORT 001 Install A/C in MDF

DIMMER SYSTEM (STAGE AND PERFORMANCE) 001 DIMMER SYSTEM (STAGE AND PERFORMANCE) - Replace the item

COOLING SYS / COOLING TOWER 2008 bond for the web Page 58 of 91

2008 GOB - Project Summary by Building & Year Denver Public Schools Facilities Faciliites Planning Management

Montbello 2009 001 COOLING SYS / COOLING TOWER - Replace the item

2013 ADA COMPLIANCE 001 ADA COMPLIANCE - DOOR HARDWARE - A/E should conduct a room by room door hardware schedule. Scope includes all doors, utility closets, exterior doors (with panics if necessary), stairwell doors and hinges. Excluded are cabinetry doors. A/E should identify any possible abatement issues to DPS Bond Hazmat project managers for remediation as early as possible.

Montclair 2009 LUNCHROOM TABLES 002 REMOVE AND REPLACE CAFETERIA TABLES

ROOFING 008 ROOFING - BUILT-UP - Built-Up roofing to include the following: Gravel, 4-ply membrane,replace existing perlite with 1/2" wood fiber, 1/8" taper insulation, replace exsiting polyisocyanurate insulation with 2 layers of 2" polyisocyanurate insulation, replace flashing per DPS specs at all walls, drains, conduits, flues, gas lines, exhausts curbs, thru-wall and overflow scuppers, skylights, A/C lines, expansion joints, and parapets. Replace all gaspipe and similiar stand supports bases with concete pavers, paint all existing gas piping per DPS specs. Replace and seal all existing pipe collars. Inspect/replace all applicable drains and gutters.

009 ROOFING - BUILT-UP - Built-Up roofing to include the following: Gravel, 4-ply membrane,replace existing perlite with 1/2" wood fiber, 1/8" taper insulation, replace exsiting polyisocyanurate insulation with 2 layers of 2" polyisocyanurate insulation, replace flashing per DPS specs at all walls, drains, conduits, flues, gas lines, exhausts curbs, thru-wall and overflow scuppers, skylights, A/C lines, expansion joints, and parapets. Replace all gaspipe and similiar stand supports bases with concete pavers, paint all existing gas piping per DPS specs. Replace and seal all existing pipe collars. Inspect/replace all applicable drains and gutters.

BUILDNG (NEW) 001 PLACE MODULAR CLASSROOMS FOR ECE EXPANSION FULL DAY PROGRAMS

2010 IRRIGATION 001 IRRIGATION - Replace existing irrigation system, piping, controls, heads, backflows, electrical and connections per DPS standards. - Montclair - Add 1 central clock. Site area to include all lawn areas around main building and approximatley 35,000 sf. Include right of way replacement/installation. Work to be conducted in conjunction with learning landscape project. See DPS Planning for site plans and QA/QC evaluations/recommendations.

LEARNING LANDSCAPE 001 LEARNING LANDSCAPE - Construct Learning Landscape per UCD Master Plan. Include 2" playground surface asphalt overlay. Work should be coordination with irrigation project . See master plan draft at www.learninglanscapes.org - Conduct soils asphalt and other pertinent testing prior to bid development.

2011 FIRE SUPPRESSION / SPRINKLER

2008 bond for the web Page 59 of 91

2008 GOB - Project Summary by Building & Year Denver Public Schools Facilities Faciliites Planning Management

Montclair 2011 FIRE SUPPRESSION / SPRINKLER 001 FIRE SPRINKLER SYSTEM - Design new fire sprinkler system throughout entire building. Comply with DPS Design and Construction Standards SECTION 15300: STANDPIPE AND FIRE SPRINKLER STANDARDS and all other applicable DPS Standards. Patch and Repair.

Moore 2010 LEARNING LANDSCAPE 001 LEARNING LANDSCAPE - Construct Learning Landscape per UCD Master Plan. Include 2" playground surface asphalt overlay. DD drawing set already produced by UCD. - Note - Moore is listed as a historic landmark. Coordinate design with Denver Landmark Commission. See master plan draft at www.learninglanscapes.org - Conduct soils asphalt and other pertinent testing prior to bid development.

2012 VENTILLATION / CENTRAL FAN / AHU 001 VENTILLATION / CENTRAL FAN / AHU - Attention this scope of work cannot proceed unless it is bundled with H ENS C Temp Controls /Environment Scope. Univent system needs complete replacement, replace steam and condensate feeds back to main, include case work required to accommodate new univents. All other Central Air Handling Units need commercial cleaning, duct work repaired as needed, new motors, replace branch piping if needed, fan bearings and damper sections. Replace all Exhaust Fans including dampers

TEMP CONTROLS / ENVIRONMENT 001 TEMP CONTROLS / ENVIRONMENT - Attention this scope of work cannot proceed unless it is bundled with H VNT C Ventilation/Central Fan/ AHU Scope. Install digital controls and control devices in new univents, retrofit all other central air handling units with new digital controls, electric damper operators, electric valves and operators. Exhaust Fan control should be tied in with HVAC system where required or as was original intent. Include Convectors, Radiators, Caninet heaters, Fancoil Units, Reheats or other terminal heating equipment in DDC upgrade.

2013 REMODEL - SAFETY 002 REMODEL - SAFETY - Install safety shower, eyewash, chemical storage cabinet and fume hood

FINISH RESTORATION 000 FINISH RESTORATION / PAINT - Repaint all surfaces to include but not limited to, all tile and hard ceilings, walls, doorjambs, doors, woodwork, ductwork, univents, radiators and built-in wood or metal cabinets, bathroom partitions painted or baked-on finish. All rooms, corridors, stairwells, closets, storage, mechanical rooms and piping per DPS piping color code. Duct cleaning is required in this scope.

FINISH RESTORATION 001 FINISH RESTORATION / SEAMLESS FLR - replace all seamless with ceramic/quarry tile

TOILET ROOM (INCLUSIVE) 001 Toilet Room (inclusive) - Replace all fixtures, plumbing piping and partitions. Paint walls and Ceilings. Replace tile as required. Lighting to be updated. Repair any associated surface damage, i.e., glazed block, etc.

2008 bond for the web Page 60 of 91

2008 GOB - Project Summary by Building & Year Denver Public Schools Facilities Faciliites Planning Management

Morey 2009 BOILER 001 BOILER - Replace the item

002 BOILER - Replace boiler as per DPS guide specs 15555C. Replace in boiler room: condensate return pumps, steam traps, condensate return pipe, boiler feed pipe, and all valves. Ref. spec. 15110, 15521, and all div. 15 that apply including water treatment associated with this project ref. 15548

003 BOILER - Replace boiler as per DPS guide specs 15555C. Replace in boiler room: condensate return pumps, steam traps, condensate return pipe, boiler feed pipe, and all valves. Ref. spec. 15110, 15521, and all div. 15 that apply including water treatment associated with this project ref. 15548

2013 ADA COMPLIANCE 001 REGULATORY - EGRESS / DOOR HARDWARE - Replace exterior door hardware for ADA compliance - A/E should conduct a door hardware schedule. Scope includes exterior doors (with panics if necessary), stairwell doors and hinges. A/E should identify any possible abatement issues to DPS Bond Hazmat project managers for remediation as early as possible.

FINISH RESTORATION 001 FINISH RESTORATION / SEAMLESS FLR - replace all seamless with ceramic/quarry tile

REGULATORY / LIGHT FIXTURES 001 REGULATORY / LIGHT FIXTURES - Replace incandescent fixtures in basement hallway.

TOILET ROOM (INCLUSIVE) 001 Toilet Room (inclusive) - Replace all fixtures, plumbing piping and partitions. Paint walls and Ceilings. Replace tile as required. Lighting to be updated. Repair any associated surface damage, i.e., glazed block, etc.

Munroe 2009 FOLDING LUNCHRM TABLES 001 FOLDING LUNCHRM TABLES - INSTALL SURFACE MOUNTED POCKET TABLES

2010 ADA COMPLIANCE 001 ADA COMPLIANCE - LEVEL 1 - Comply with DPS Design and Construction Standards SECTION 00700: ACCESSIBILITY STANDARDS and all other applicable DPS Standards. See ADA Level 1 Database provided. Deficiency remedies provided in ADA database should serve as the PM guide only and should not be provided to the A/E for purposes of developing the project scope of work. A/E is directed to conduct a building survey limited to the areas identified in the survey. Other ADA deficiencies may be included if they meet the level 1 status and have not been identified in the survey. All questions of possible oversight of a deficiency shall be directed to DPS Facility Planning through the DPS Project Manager.

FINISH RESTORATION

2008 bond for the web Page 61 of 91

2008 GOB - Project Summary by Building & Year Denver Public Schools Facilities Faciliites Planning Management

Munroe 2010 FINISH RESTORATION 001 FINISH RESTORATION - CARPET - Replace all worn classroom and office carpeting and base trim per DPS specs. Coordinate all necessary hazmat testing and abatement with DPS HazMat PMs. Scope to include breakdown and/or relocation of all non-fixed equipment. Maintain all vinyl flooring areas around sinks currently existing in elementary areas. Munroe- estimated at 2780 syds, include all corridors connecting to the east wing. Classrooms in east wing should be included as an alternate and completed if funding permits. Tile in all corridors and hallways and under sinks should be completed as an alternate if funding permits.

TOILET ROOM (INCLUSIVE) 001 Toilet Rooms (Inclusive) - Design for complete remodeling of all restrooms in the building, including restroom portion of all locker rooms. Comply with all applicable DPS Standards for design and construction. Comply with ICC/ANSI A117.1 except where technically infeasible. A/E to include cost of work and repairs needed for investigation – DPS O&M will not be involved to assist w/ investigation. Plumbing includes replacement of all fixtures, replacement of concealed galvanized pipe with copper to below floor level to exposed section in crawl space or exposed below ceiling level. Design shall specify extent of pipe replacement, and shall be approved by DPS QA/QC. Wash basins shall be replaced with individual hand sinks. Design shall specify fixtures to be provided by Denver Water and installed by contractor. Existing ventilation systems shall be investigated for compliance with current code requirements. Design shall specify needed improvements for mechanical ventilation in all restrooms. All lighting fixtures not conforming to DPS Design and Construction Standards shall be replaced with conforming fixtures. Coordinate w/ DPS Sustainability Planner. All toilet partitions shall be replaced. All flooring shall be replaced with quarry tile. All walls, ceiling, and previously painted surfaces shall be repainted. Walls shall be repaired prior to repainting. At minimum, comply with DPS Level 1 ADA standards. Consult with DPS Planning. Coordinate with ADA Upgrade: 8223 GB80237. Munroe - Design for remodeling of all restrooms in the older section of the building, including rooms H000CA, OFFCA, OFFD, KITA, GYMAA, GYMB, GYMC, H110A&B, H110F&G, H140A&B, H210A,B,C&D. All toilet partitions shall be replaced. Except: GYMB. All flooring shall be replaced with quarry tile. Except: GYMAA, GYMB. All walls, ceiling, and previously painted surfaces shall be repainted. Structural glazed tile to be repaired prior to painting.

2013 ROOFING 002 ROOFING - BUILT-UP - Built-Up roofing to include the following: Gravel, 4-ply membrane,replace existing perlite with 1/2" wood fiber, 1/8" taper insulation, replace exsiting polyisocyanurate insulation with 2 layers of 2" polyisocyanurate insulation, replace flashing per DPS specs at all walls, drains, conduits, flues, gas lines, exhausts curbs, thru-wall and overflow scuppers, skylights, A/C lines, expansion joints, and parapets. Replace all gaspipe and similiar stand supports bases with concete pavers, paint all existing gas piping per DPS specs. Replace and seal all existing pipe collars. Inspect/replace all applicable drains and gutters.

003 ROOFING - BUILT-UP - Built-Up roofing to include the following: Gravel, 4-ply membrane,replace existing perlite with 1/2" wood fiber, 1/8" taper insulation, replace exsiting polyisocyanurate insulation with 2 layers of 2" polyisocyanurate insulation, replace flashing per DPS specs at all walls, drains, conduits, flues, gas lines, exhausts curbs, thru-wall and overflow scuppers, skylights, A/C lines, expansion joints, and parapets. Replace all gaspipe and similiar stand supports bases with concete pavers, paint all existing gas piping per DPS specs. Replace and seal all existing pipe collars. Inspect/replace all applicable drains and gutters.

004 ROOFING - BUILT-UP - Built-Up roofing to include the following: Gravel, 4-ply membrane,replace existing perlite with 1/2" wood fiber, 1/8" taper insulation, replace exsiting polyisocyanurate insulation with 2 layers of 2" polyisocyanurate insulation, replace flashing per DPS specs at all walls, drains, conduits, flues, gas lines, exhausts curbs, thru-wall and overflow scuppers, skylights, A/C lines, expansion joints, and parapets. Replace all gaspipe and similiar stand supports bases with concete pavers, paint all existing gas piping per DPS specs. Replace and seal all existing pipe collars. Inspect/replace all applicable drains and gutters.

2008 bond for the web Page 62 of 91

2008 GOB - Project Summary by Building & Year Denver Public Schools Facilities Faciliites Planning Management

Munroe 2013 ROOFING 005 ROOFING - BUILT-UP - Built-Up roofing to include the following: Gravel, 4-ply membrane,replace existing perlite with 1/2" wood fiber, 1/8" taper insulation, replace exsiting polyisocyanurate insulation with 2 layers of 2" polyisocyanurate insulation, replace flashing per DPS specs at all walls, drains, conduits, flues, gas lines, exhausts curbs, thru-wall and overflow scuppers, skylights, A/C lines, expansion joints, and parapets. Replace all gaspipe and similiar stand supports bases with concete pavers, paint all existing gas piping per DPS specs. Replace and seal all existing pipe collars. Inspect/replace all applicable drains and gutters.

Newlon 2009 FIRE DETECTION 001 FIRE DETECTION SYSTEM - Detectors only. New FACP installed

FINISH RESTORATION 001 FINISH RESTORATION / PAINT - Repaint all surfaces to include but not limited to, all tile and hard ceilings, walls, doorjambs, doors, woodwork, ductwork, univents, radiators and built-in wood or metal cabinets, bathroom partitions painted or baked-on finish. All rooms, corridors, stairwells, closets, storage, mechanical rooms and piping per DPS piping color code. Duct cleaning is required in this scope.

FINISH RESTORATION 001 FINISH RESTORATION / SEAMLESS FLR - replace all seamless with ceramic/quarry tile

REGULATORY / LIGHT FIXTURES 001 REGULATORY / LIGHT FIXTURES - Replace incandscent fixtures in gym with T-8 fixtures.

2012 LEARNING LANDSCAPE 001 LEARNING LANDSCAPE - Construct Learning Landscape per UCD Master Plan. Include 2" playground surface asphalt overlay..

Noel 2009 VIDEO SECURITY 001 Video Security - Re-check room size to install rack

North Main Bldg 2009 RELOCATION COSTS 001 FFE and Relocation Costs of North High Renovation

BUILDING (REMODEL)

2008 bond for the web Page 63 of 91

2008 GOB - Project Summary by Building & Year Denver Public Schools Facilities Faciliites Planning Management

North Main Bldg 2009 BUILDING (REMODEL) 001 BUILDING (REMODEL) - REHAB AND COMPLETELY REMODEL NORTH HIGH SCHOOL INCLUDING SITE AS OUTLINED IN THE NORTH/VALDEZ MASTER PLAN (2005)

Northeast Bus Terminal 2010 HEALTH SAFETY / HAZARD ABATEMENT 001 HAZMAT UNDERDROUND STORAGE TANKS - Remove and remediate site as necessary. Remove a total of 8 underground storage tanks from site. 1) 1000-gal. oil/water separator; (7) USTs – 30K diesel, 10K unleaded, 2K oil, 2K antifreeze, 2K ATF, 1K window wash, 1K overflow tank for oil/water separator.

Oakland 2009 FOLDING LUNCHRM TABLES 001 FOLDING LUNCHRM TABLES - INSTALL SURFACE MOUNTED POCKET TABLES

FIRE DETECTION 001 FIRE DETECTION SYSTEM - Detectors only. New FACP installed

FINISH RESTORATION 001 FINISH RESTORATION / SEAMLESS FLR - replace all seamless with ceramic/quarry tile

2010 BOILER 002 BOILER REPLACEMENT - Design for replacement of two boilers, and the removal of material and equipment no longer needed.rhimes: This is a complete replacement. Include condensate return tank. Include startup and commissioning. Replace existing heat exchanger with new domestic hw Aerco Boiler.In the boiler room replace: condensate return pumps, steam traps, condensate return pipe, boiler feed pipe, and all valves. Design shall include water treatment. Asbestos management by DPS and not included in this scope. Comply with DPS Design and Construction Standards SECTION 15555C: CAST IRON BOILER PERFORMANCE SPEC, 15110: VALVES, 15521: STEAM AND CONDENSATE PIPING SPECIALTIES and all other applicable DPS Standards. Patch and repair insulation.

VENTILLATION / CENTRAL FAN / AHU 001 VENTILLATION - CENTRAL FAN - AHU - Attention this scope of work cannot proceed unless it is bundled with H ENS C Temp Controls /Environment Scope. Design for HVAC replacement, and the removal of material and equipment no longer needed. Comply with DPS Design and Construction Standards Division 15 (applicable sections) and all other applicable DPS Standards. Patch and repair. Replace all unit-ventilators, replace steam and condensate feeds back to main, and replace all steam traps including drip and end of main. Include case work required to accommodate new unit-ventilators. All other central air-handling units need commercial cleaning, duct work repaired as needed, new motors, replace branch piping if needed, steam traps, fan bearings and damper sections. Replace all Exhaust Fans including dampers. Replace steam traps as needed. Ductwork cleaning as needed.

TEMP CONTROLS / ENVIRONMENT

2008 bond for the web Page 64 of 91

2008 GOB - Project Summary by Building & Year Denver Public Schools Facilities Faciliites Planning Management

Oakland 2010 TEMP CONTROLS / ENVIRONMENT 001 TEMP CONTROLS - ENVIRONMENT - Design for temperature controls replacement, and the removal of material and equipment no longer needed. Comply with DPS Design and Construction Standards SECTIONS 15950: CONTROLS, 15975: INTEGRATED BUILDING AUTOMATION SYSTEM (IBAS) and all other applicable DPS Standards. Patch and repair. Install digital controls and central energy management system. Confirm that this is to include IBAS (note: parent project for Oakland also includes boiler and ventilation/central fan/AHU.)

2011 LEARNING LANDSCAPE 001 LEARNING LANDSCAPE - Construct Learning Landscape per UCD Master Plan. Include 2" playground surface asphalt overlay..

Opp School K R M A 2013 HW HTR / PLUMBING 001 Replace the item

BUILDING SHELL / DOOR HARDWARE 001 locks closer hinges

ROOFING / BUILT UP 018 Replace the item

019 Replace the item

020 Replace the item

021 Replace the item

022 Replace the item

ROOFING / METAL 023 Replace the item

Opp School Shops 2013 VENTILLATION / CENTRAL FAN / AHU 001 REPLACEMENT OF CONTROLS AND DEVICES COMMERCIAL CLAENING OF UNITS AND DUCT WORK NEW MOTORS AND FAN BEARINGS

BUILDING SHELL / OTHER EXT MATERIALS 001 replace capstone, rapid deterioration.

ROOFING / BUILT UP

2008 bond for the web Page 65 of 91

2008 GOB - Project Summary by Building & Year Denver Public Schools Facilities Faciliites Planning Management

Opp School Shops 2013 ROOFING / BUILT UP 015 Replace the item

016 Replace the item

017 Replace the item

028 Replace the item

029 Replace the item

030 Replace the item

031 Replace the item

ROOFING / EPDM / PVC / SINGLE-PLY 026 Replace the item

ROOFING / METAL 024 Replace the item

025 Replace the item

FIRE DETECTION 001 high voltage panel. Obsolete

Opportunity School 2009 LAVATORY UPGRADES 001 Renovation anduUpgrade to mens and womens (8) lavatories on the 2nd and 3rd floor of Administration building.

2013 BOILER 001 Replace boiler as per DPS guide specs 15555C. Replace in boiler room: condensate return pumps, steam traps, condensate return pipe, boiler feed pipe, and all valves. Ref. spec. 15110, 15521, and all div. 15 that apply including water treatment associated with this project ref. 15548

003 Replace boiler as per DPS guide specs 15555C. Replace in boiler room: condensate return pumps, steam traps, condensate return pipe, boiler feed pipe, and all valves. Ref. spec. 15110, 15521, and all div. 15 that apply including water treatment associated with this project ref. 15548

HEAT EXCH / DOMESTIC / PLUMB 001 Replace the item UNIT LEAKING

LIGHTING (NON-SPECIFIC) 000 Rpl 5,light fix -

ADA COMPLIANCE 2008 bond for the web Page 66 of 91

2008 GOB - Project Summary by Building & Year Denver Public Schools Facilities Faciliites Planning Management

Opportunity School 2013 001 Level 1 ADA compliance - See ADA Database

ROOFING / BUILT UP 001 Replace the item

002 Replace the item

003 Replace the item

004 Replace the item

005 Replace the item

006 Replace the item

007 Replace the item

008 Replace the item

009 Replace the item

011 Replace the item

012 Replace the item

013 Replace the item

014 Replace the item

ROOFING / EPDM / PVC / SINGLE-PLY 010 Replace the item

FIRE DETECTION 001 high voltage panel. Obsolete

HAZMAT / ASBESTOS ABATEMENT 004 Remove Duct Tape throughout building]

Palmer 2009 IRRIGATION 001 IRRIGATION - Replace the item

LEARNING LANDSCAPE 001 LEARNING LANDSCAPE - Construct Learning Landscape per UCD Master Plan. Include 2" playground surface asphalt overlay..

2013 FINISH RESTORATION

2008 bond for the web Page 67 of 91

2008 GOB - Project Summary by Building & Year Denver Public Schools Facilities Faciliites Planning Management

Palmer 2013 FINISH RESTORATION 000 FINISH RESTORATION / PAINT - Repaint all surfaces to include but not limited to, all tile and hard ceilings, walls, doorjambs, doors, woodwork, ductwork, univents, radiators and built-in wood or metal cabinets, bathroom partitions painted or baked-on finish. All rooms, corridors, stairwells, closets, storage, mechanical rooms and piping per DPS piping color code. Duct cleaning is required in this scope.

TOILET ROOM (INCLUSIVE) 001 Toilet Room (inclusive) - Replace all fixtures, plumbing piping and partitions. Paint walls and Ceilings. Replace tile as required. Lighting to be updated. Repair any associated surface damage, i.e., glazed block, etc.

Park Hill 2009 BOILER 001 BOILER - Replace boiler as per DPS guide specs 15555C. Replace in boiler room: condensate return pumps, steam traps, condensate return pipe, boiler feed pipe, and all valves. Ref. spec. 15110, 15521, and all div. 15 that apply including water treatment associated with this project ref. 15548

002 BOILER - Replace boiler as per DPS guide specs 15555C. Replace in boiler room: condensate return pumps, steam traps, condensate return pipe, boiler feed pipe, and all valves. Ref. spec. 15110, 15521, and all div. 15 that apply including water treatment associated with this project ref. 15548

REGULATORY / LIGHT FIXTURES 001 REGULATORY LIGHT FIXTURES - Replace all T-12 and incandescent lighting fixtures with T-8 or T5HO fixtures. Properly dispose of all existing lamps and fixtures. Comply with DPS Design and Construction Standards SECTIONS 16501: LAMPS, 16502 BALLASTS AND CONTROLS and 16510: LUMINAIRES and all other applicable DPS Standards. Patch and Repair.

2011 FIRE SUPPRESSION / SPRINKLER 001 FIRE SUPPRESSION / SPRINKLER SYSTEM - INSTALL FIRE SUPPRESSION SYSTEM THROUGHTOUT BUILDING

HEALTH SAFETY / HAZARD ABATEMENT 001 HEALTH SAFETY / HAZARD ABATEMENT - REPLACE TREATED WOOD TIMBERS WITH RECYCLED PLASTIC TIMBERS

ASPHALT PAVING 001 ASPHALT / VEHICLE PARKING AND DRIVEWAYS - 2" overlay with geotec material.

LEARNING LANDSCAPE 001 LEARNING LANDSCAPE - Construct Learning Landscape per UCD Master Plan. Include 2" playground surface asphalt overlay..

2013 REMODEL - SAFETY 002 REMODEL - SAFETY - Install safety shower, eyewash, chemical storage cabinet and fume hood

2008 bond for the web Page 68 of 91

2008 GOB - Project Summary by Building & Year Denver Public Schools Facilities Faciliites Planning Management

Park Hill 2013 FINISH RESTORATION 000 FINISH RESTORATION / SEAMLESS FLR - replace all seamless with ceramic/quarry tile

TOILET ROOM (INCLUSIVE) 001 Toilet Room (inclusive) - Replace all fixtures, plumbing piping and partitions. Paint walls and Ceilings. Replace tile as required. Lighting to be updated. Repair any associated surface damage, i.e., glazed block, etc.

Philips 2009 TOILET ROOM (INCLUSIVE) 001 Toilet Room (inclusive) - Replace all fixtures, plumbing piping and partitions. Paint walls and Ceilings. Replace tile as required. Lighting to be updated. Repair any associated surface damage, i.e., glazed block, etc.

2011 ASPHALT PAVING 001 ASPHALT / VEHICLE PARKING AND DRIVEWAYS - 2" overlay with geotec material.

002 ASPHALT / VEHICLE PARKING AND DRIVEWAYS - 2" overlay with geotec material.

2013 ROOFING 001 ROOFING / EPDM / PVC / SINGLE-PLY - Replace the item

008 ROOFING / EPDM / PVC / SINGLE-PLY - Replace the item

Pioneer 2009 REGULATORY / LIGHT FIXTURES 001 REGULATORY LIGHT FIXTURES - Replace all T-12 and incandescent lighting fixtures with T-8 or T5HO fixtures. Properly dispose of all existing lamps and fixtures. Comply with DPS Design and Construction Standards SECTIONS 16501: LAMPS, 16502 BALLASTS AND CONTROLS and 16510: LUMINAIRES and all other applicable DPS Standards. Patch and Repair.

2010 LEARNING LANDSCAPE 001 LEARNING LANDSCAPE - Construct Learning Landscape per UCD Master Plan. Include 2" playground surface asphalt overlay. See master plan draft at www.learninglanscapes.org - Conduct soils asphalt and other pertinent testing prior to bid development.

2012 FIRE SUPPRESSION / SPRINKLER

2008 bond for the web Page 69 of 91

2008 GOB - Project Summary by Building & Year Denver Public Schools Facilities Faciliites Planning Management

Pioneer 2012 FIRE SUPPRESSION / SPRINKLER 001 FIRE SPRINKLER SYSTEM - Design new fire sprinkler system throughout entire building. Comply with DPS Design and Construction Standards SECTION 15300: STANDPIPE AND FIRE SPRINKLER STANDARDS and all other applicable DPS Standards. Patch and Repair.

Place 2009 LEARNING LANDSCAPE 001 Install missing Learning Landscape elements.

ABSORPTION CHILLER 001 ABSORPTION CHILLER - Replace the item

REGULATORY / LIGHT FIXTURES 001 REGULATORY LIGHT FIXTURES - Replace all T-12 and incandescent lighting fixtures with T-8 or T5HO fixtures. Properly dispose of all existing lamps and fixtures. Comply with DPS Design and Construction Standards SECTIONS 16501: LAMPS, 16502 BALLASTS AND CONTROLS and 16510: LUMINAIRES and all other applicable DPS Standards. Patch and Repair.

2013 ADA COMPLIANCE 001 REGULATORY - EGRESS / DOOR HARDWARE - Replace exterior door hardware for ADA compliance - A/E should conduct a door hardware schedule. Scope includes exterior doors (with panics if necessary), stairwell doors and hinges. A/E should identify any possible abatement issues to DPS Bond Hazmat project managers for remediation as early as possible.

FINISH RESTORATION 001 FLOORING / WOOD FLOORING - 8850sf

Randolph 2009 TECHNOLOGY CONSTRUCTION SUPPORT 002 TECHNOLOGY CONSTRUCTION SUPPORT - Install dedicated air conditioning unit in the MDF.

VIDEO SECURITY 001 Video Security - Install A/C

ASPHALT PAVING 002 EXPAND PARKING CAPACITY TO ACCOMMODATE HIGH SCHOOL POPULATION OF 520 (NEED TO ADD 60 SPACES) - confirm quantity needed.

2008 bond for the web Page 70 of 91

2008 GOB - Project Summary by Building & Year Denver Public Schools Facilities Faciliites Planning Management

Rishel 2009 ROOFING 004 ROOFING / EPDM / PVC / SINGLE-PLY - Replace the item

BUILDING (REMODEL) 006 NEW SCHOOLS STARTUP REMODELING

2010 IRRIGATION 001 IRRIGATION - Replace existing irrigation system, piping, controls, heads, backflows, electrical and connections per DPS standards. - Richel - Site area to include all lawn areas around main buidling, no sports fields, approximatley 39,000 sf. Consolidate to 1 central clock. Relocate zone valves from crawl space to exterior. Work to be conducted in conjunction with learning landscape project. See DPS Planning for site plans and QA/QC evaluations/recommendations.

ADA COMPLIANCE 001 ADA COMPLIANCE - LEVEL 1 - Comply with DPS Design and Construction Standards SECTION 00700: ACCESSIBILITY STANDARDS and all other applicable DPS Standards. See ADA Level 1 Database provided. Deficiency remedies provided in ADA database should serve as the PM guide only and should not be provided to the A/E for purposes of developing the project scope of work. A/E is directed to conduct a building survey limited to the areas identified in the survey. Other ADA deficiencies may be included if they meet the level 1 status and have not been identified in the survey. All questions of possible oversight of a deficiency shall be directed to DPS Facility Planning through the DPS Project Manager.

ADA COMPLIANCE 001 ADA COMPLIANCE - DOOR HARDWARE - A/E should conduct a room by room door hardware schedule. Scope includes all doors, utility closets, exterior doors (with panics if necessary), stairwell doors and hinges. Excluded are cabinetry doors. A/E should identify any possible abatement issues to DPS Bond Hazmat project managers for remediation as early as possible.

2012 WINDOWS 001 METAL WINDOWS - Replace the item

2013 STAGE CURTAIN / AUDITORIUM 001 STAGE CURTAIN / AUDITORIUM - Replace all curtains and make rigging corrections

ROBERTS 2009 LEARNING LANDSCAPE 002 INSTALL MISSING ELEMENTS TO COMPLETE LEARNING LANDSCAPE

2008 bond for the web Page 71 of 91

2008 GOB - Project Summary by Building & Year Denver Public Schools Facilities Faciliites Planning Management

Sabin 2009 ROOFING 008 ROOFING / EPDM / PVC / SINGLE-PLY - Replace the item

FIRE DETECTION 001 FIRE DETECTION SYSTEM - Replace System

REGULATORY / LIGHT FIXTURES 001 REGULATORY LIGHT FIXTURES - Replace all T-12 and incandescent lighting fixtures with T-8 or T5HO fixtures. Properly dispose of all existing lamps and fixtures. Comply with DPS Design and Construction Standards SECTIONS 16501: LAMPS, 16502 BALLASTS AND CONTROLS and 16510: LUMINAIRES and all other applicable DPS Standards. Patch and Repair.

2011 HEALTH SAFETY / HAZARD ABATEMENT 001 HEALTH SAFETY / HAZARD ABATEMENT - REPLACE TREATED WOOD TIMBERS WITH RECYCLED PLASTIC TIMBERS

LEARNING LANDSCAPE 001 LEARNING LANDSCAPE - Construct Learning Landscape per UCD Master Plan. Include 2" playground surface asphalt overlay..

2013 TOILET ROOM (INCLUSIVE) 001 Toilet Room (inclusive) - Replace all fixtures, plumbing piping and partitions. Paint walls and Ceilings. Replace tile as required. Lighting to be updated. Repair any associated surface damage, i.e., glazed block, etc.

Samuels 2009 FOLDING LUNCHRM TABLES 001 FOLDING LUNCHRM TABLES - INSTALL SURFACE MOUNTED POCKET TABLES

FINISH RESTORATION 001 FINISH RESTORATION / PAINT - Repaint all surfaces to include but not limited to, all tile and hard ceilings, walls, doorjambs, doors, woodwork, ductwork, univents, radiators and built-in wood or metal cabinets, bathroom partitions painted or baked-on finish. All rooms, corridors, stairwells, closets, storage, mechanical rooms and piping per DPS piping color code. Duct cleaning is required in this scope.

ASPHALT PAVING 001 ASPHALT / VEHICLE PARKING AND DRIVEWAYS - 2" overlay with geotec material.

LEARNING LANDSCAPE 001 LEARNING LANDSCAPE - Construct Learning Landscape per UCD Master Plan. Include 2" playground surface asphalt overlay..

ABSORPTION CHILLER 2008 bond for the web Page 72 of 91

2008 GOB - Project Summary by Building & Year Denver Public Schools Facilities Faciliites Planning Management

Samuels 2009 001 ABSORPTION CHILLER - Replace the item

BUILDNG (NEW) 001 PLACE MODULAR CLASSROOMS FOR ECE EXPANSION FULL DAY PROGRAMS

Sandoval 2009 TECHNOLOGY CONSTRUCTION SUPPORT 002 TECHNOLOGY CONSTRUCTION SUPPORT - Sandoval Academia needs MDF room and two IDF rooms built. The design changed from the original request on this, and we were stuck with closets and not rooms. There is inadequate space for existing equipment, no room for S&S and radio equipment, and poor ventilation (No air conditioning). The new constructed MDF will require 220-volt circuits, 110-volt circuits and AC. Each of the IDF’s will require 110-volt circuits.

LEARNING LANDSCAPE 001 Install missing Learning Landscape elements.

Schenck 2009 REGULATORY / LIGHT FIXTURES 001 REGULATORY LIGHT FIXTURES - Replace all T-12 and incandescent lighting fixtures with T-8 or T5HO fixtures. Properly dispose of all existing lamps and fixtures. Comply with DPS Design and Construction Standards SECTIONS 16501: LAMPS, 16502 BALLASTS AND CONTROLS and 16510: LUMINAIRES and all other applicable DPS Standards. Patch and Repair.

BUILDNG (NEW) 001 PLACE MODULAR CLASSROOMS FOR ECE EXPANSION FULL DAY PROGRAMS

2013 ADA COMPLIANCE 001 ADA COMPLIANCE - LEVEL 1 - Comply with DPS Design and Construction Standards SECTION 00700: ACCESSIBILITY STANDARDS and all other applicable DPS Standards. See ADA Level 1 Database provided. Deficiency remedies provided in ADA database should serve as the PM guide only and should not be provided to the A/E for purposes of developing the project scope of work. A/E is directed to conduct a building survey limited to the areas identified in the survey. Other ADA deficiencies may be included if they meet the level 1 status and have not been identified in the survey. All questions of possible oversight of a deficiency shall be directed to DPS Facility Planning through the DPS Project Manager.

FINISH RESTORATION 001 FINISH RESTORATION / PAINT - Replace the item

2008 bond for the web Page 73 of 91

2008 GOB - Project Summary by Building & Year Denver Public Schools Facilities Faciliites Planning Management

Schmitt 2009 FOLDING LUNCHRM TABLES 001 FOLDING LUNCHRM TABLES - INSTALL SURFACE MOUNTED POCKET TABLES

REGULATORY / LIGHT FIXTURES 001 REGULATORY LIGHT FIXTURES - Replace all T-12 and incandescent lighting fixtures with T-8 or T5HO fixtures. Properly dispose of all existing lamps and fixtures. Comply with DPS Design and Construction Standards SECTIONS 16501: LAMPS, 16502 BALLASTS AND CONTROLS and 16510: LUMINAIRES and all other applicable DPS Standards. Patch and Repair.

BUILDNG (NEW) 001 PLACE MODULAR CLASSROOMS FOR ECE EXPANSION FULL DAY PROGRAMS

2012 IRRIGATION 001 IRRIGATION - Replace the item

LEARNING LANDSCAPE 001 LEARNING LANDSCAPE - Construct Learning Landscape per UCD Master Plan. Include 2" playground surface asphalt overlay..

2013 ADA COMPLIANCE 001 ADA COMPLIANCE - LEVEL 1 - Comply with DPS Design and Construction Standards SECTION 00700: ACCESSIBILITY STANDARDS and all other applicable DPS Standards. See ADA Level 1 Database provided. Deficiency remedies provided in ADA database should serve as the PM guide only and should not be provided to the A/E for purposes of developing the project scope of work. A/E is directed to conduct a building survey limited to the areas identified in the survey. Other ADA deficiencies may be included if they meet the level 1 status and have not been identified in the survey. All questions of possible oversight of a deficiency shall be directed to DPS Facility Planning through the DPS Project Manager.

FINISH RESTORATION 000 FINISH RESTORATION / PAINT - Repaint all surfaces to include but not limited to, all tile and hard ceilings, walls, doorjambs, doors, woodwork, ductwork, univents, radiators and built-in wood or metal cabinets, bathroom partitions painted or baked-on finish. All rooms, corridors, stairwells, closets, storage, mechanical rooms and piping per DPS piping color code. Duct cleaning is required in this scope.

Service Center 2009 WINDOWS 001 METAL WINDOWS - Replace the item

2010 ASPHALT PAVING

2008 bond for the web Page 74 of 91

2008 GOB - Project Summary by Building & Year Denver Public Schools Facilities Faciliites Planning Management

Service Center 2010 ASPHALT PAVING 002 ASPHALT REPLACEMENT - At north side of Service building, replace 2"overaly with geotec material of existing areas of asphalt parking and driveway(18,600sf), add striping ADA signage, and motorcycle parking. Level asphalt. To be conducted in accordance with DPS specifications. Include all pertinent civil engineering, testing, and permitting as necessary. Add alternate for concrete replacement to drive between bus shop and service building. Check drain for elevation. Add alternate for warehouse parking lot replacement. Replace all impacted landscaping, sod, and irrigation equipment if necessary. See attached site plan.

Skinner 2012 ADA COMPLIANCE 001 REGULATORY - EGRESS / DOOR HARDWARE - Replace exterior door hardware for ADA compliance - A/E should conduct a door hardware schedule. Scope includes exterior doors (with panics if necessary), stairwell doors and hinges. A/E should identify any possible abatement issues to DPS Bond Hazmat project managers for remediation as early as possible.

FINISH RESTORATION 000 FINISH RESTORATION / PAINT - Repaint all surfaces to include but not limited to, all tile and hard ceilings, walls, doorjambs, doors, woodwork, ductwork, univents, radiators and built-in wood or metal cabinets, bathroom partitions painted or baked-on finish. All rooms, corridors, stairwells, closets, storage, mechanical rooms and piping per DPS piping color code. Duct cleaning is required in this scope.

TOILET ROOM (INCLUSIVE) 001 Toilet Room (inclusive) - Replace all fixtures, plumbing piping and partitions. Paint walls and Ceilings. Replace tile as required. Lighting to be updated. Repair any associated surface damage, i.e., glazed block, etc.

ROOFING 014 ROOFING / EPDM / PVC / SINGLE-PLY - Replace the item

015 ROOFING / EPDM / PVC / SINGLE-PLY - Replace the item

2013 FIRE SUPPRESSION / SPRINKLER 001 FIRE SPRINKLER SYSTEM - Design new fire sprinkler system throughout entire building. Comply with DPS Design and Construction Standards SECTION 15300: STANDPIPE AND FIRE SPRINKLER STANDARDS and all other applicable DPS Standards. Patch and Repair.

Slavens 2009 FOLDING LUNCHRM TABLES 001 FOLDING LUNCHRM TABLES - INSTALL SURFACE MOUNTED POCKET TABLES

FIRE DETECTION 001 FIRE DETECTION SYSTEM - REPLACE FACP

2008 bond for the web Page 75 of 91

2008 GOB - Project Summary by Building & Year Denver Public Schools Facilities Faciliites Planning Management

Slavens 2010 WINDOWS 001 WINDOWS - METAL - Slavens is highly eligible for landmark status. Coordinate design review with Denver Landmark Preservation Commission.

2012 HEALTH SAFETY / HAZARD ABATEMENT 001 HEALTH SAFETY / HAZARD ABATEMENT - REPLACE TREATED WOOD TIMBERS WITH RECYCLED PLASTIC TIMBERS

IRRIGATION 001 IRRIGATION - Replace the item

LEARNING LANDSCAPE 001 LEARNING LANDSCAPE - Construct Learning Landscape per UCD Master Plan. Include 2" playground surface asphalt overlay..

2013 REMODEL - SAFETY 002 REMODEL - SAFETY - Install safety shower, eyewash, chemical storage cabinet and fume hood

BUILDING (REMODEL) 005 CONSTRUCT BUILDING REMODELING TO PROVIDE ADEQUATELY SIZED LIBRARY

SMILEY 2009 BUILDING (REMODEL) 002 NEW SCHOOLS STARTUP REMODELING

2010 ADA COMPLIANCE 001 ADA COMPLIANCE - DOOR HARDWARE - A/E should conduct a room by room door hardware schedule. Scope includes all doors, utility closets, exterior doors (with panics if necessary), stairwell doors and hinges. Excluded are cabinetry doors. A/E should identify any possible abatement issues to DPS Bond Hazmat project managers for remediation as early as possible.

FINISH RESTORATION

2008 bond for the web Page 76 of 91

2008 GOB - Project Summary by Building & Year Denver Public Schools Facilities Faciliites Planning Management

SMILEY 2010 FINISH RESTORATION 001 FINISH RESTORATION - PAINT - Scope includes repainted of all existing painted items, including ceilings, closets, stair rails and raisersand flooring in boiler rooms. Exclude piping. Include alljanitorial clostets, and storgage rooms. Contractor is responisble for moving shelving. Boxes (500 per school) are to be provided to each school to distribute as necessary. School is to box personal items & clear off walls in classroom. Provide secure storage for computers and other items, colors selected by principles, number/locations of colors base on DPS standards and A/E selections. Division 9 (prep,staple hole fills, patching, etc, prime, paint 2 coats. Coordinate with DOTS/Denver Fire for covering data/phone outlets, all fire systems, to be protected. Duct cleaning is included in scope prior to painting. Refinishing all stain doors to be added as alternates). See DPS standards regarding staging and moving. Smiley - New signage to be purchased for entire facility. Exclude rooms already painted under 08 Bond "New Schools Program" and 08 Bond "Toilet Renovations" (Summer 2009). Coordinate work with 08 Bond ADA Door Hardware Replacement.

TOILET ROOM (INCLUSIVE) 001 Toilet Rooms (Inclusive) - Design for complete remodeling of all restrooms in the building, including restroom portion of all locker rooms. Comply with all applicable DPS Standards for design and construction. Comply with ICC/ANSI A117.1 except where technically infeasible. A/E to include cost of work and repairs needed for investigation – DPS O&M will not be involved to assist w/ investigation. Plumbing includes replacement of all fixtures, replacement of concealed galvanized pipe with copper to below floor level to exposed section in crawl space or exposed below ceiling level. Design shall specify extent of pipe replacement, and shall be approved by DPS QA/QC. Wash basins shall be replaced with individual hand sinks. Design shall specify fixtures to be provided by Denver Water and installed by contractor. Existing ventilation systems shall be investigated for compliance with current code requirements. Design shall specify needed improvements for mechanical ventilation in all restrooms. All lighting fixtures not conforming to DPS Design and Construction Standards shall be replaced with conforming fixtures. Coordinate w/ DPS Sustainability Planner. All toilet partitions shall be replaced. All flooring shall be replaced with quarry tile. All walls, ceiling, and previously painted surfaces shall be repainted. Walls shall be repaired prior to repainting. At minimum, comply with DPS Level 1 ADA standards. Consult with DPS Planning.Design for complete remodeling of all restrooms in the building EXCEPT: 101E, 108A & 109B. Structural glazed tile to be repaired prior to painting.Design for complete remodeling of all restrooms in the building EXCEPT: 101E, 108A & 109B.

ROOFING 007 Built-Up Roofing - Deck# 07 - to include the following: Gravel, 4-ply membrane,replace existing perlite with 1/2" wood fiber, 1/8" taper insulation, replace exsiting polyisocyanurate insulation with 2 layers of 2" polyisocyanurate insulation, replace flashing per DPS specs at all walls, drains, conduits, flues, gas lines, exhausts curbs, thru-wall and overflow scuppers, skylights, A/C lines, expansion joints, and parapets. Replace all gaspipe and similiar stand supports bases with concete pavers, paint all existing gas piping per DPS specs. Replace and seal all existing pipe collars. Inspect/replace all applicable drains and gutters.

010 ROOFING - BUILT-UP - Regarding Deck# 10- Built-Up roofing to include the following: Gravel, 4-ply membrane,replace existing perlite with 1/2" wood fiber, 1/8" taper insulation, replace exsiting polyisocyanurate insulation with 2 layers of 2" polyisocyanurate insulation, replace flashing per DPS specs at all walls, drains, conduits, flues, gas lines, exhausts curbs, thru-wall and overflow scuppers, skylights, A/C lines, expansion joints, and parapets. Replace all gaspipe and similiar stand supports bases with concete pavers, paint all existing gas piping per DPS specs. Replace and seal all existing pipe collars. Inspect/replace all applicable drains and gutters.

012 ROOFING - BUILT-UP - Regarding Deck# 12- Built-Up roofing to include the following: Gravel, 4-ply membrane,replace existing perlite with 1/2" wood fiber, 1/8" taper insulation, replace exsiting polyisocyanurate insulation with 2 layers of 2" polyisocyanurate insulation, replace flashing per DPS specs at all walls, drains, conduits, flues, gas lines, exhausts curbs, thru-wall and overflow scuppers, skylights, A/C lines, expansion joints, and parapets. Replace all gaspipe and similiar stand supports bases with concete pavers, paint all existing gas piping per DPS specs. Replace and seal all existing pipe collars. Inspect/replace all applicable drains and gutters.

FIRE SUPPRESSION / SPRINKLER

2008 bond for the web Page 77 of 91

2008 GOB - Project Summary by Building & Year Denver Public Schools Facilities Faciliites Planning Management

SMILEY 2010 FIRE SUPPRESSION / SPRINKLER 001 FIRE SPRINKLER SYSTEM - Design new fire sprinkler system throughout entire building. Comply with DPS Design and Construction Standards SECTION 15300: STANDPIPE AND FIRE SPRINKLER STANDARDS and all other applicable DPS Standards. Patch and Repair.

2011 ASPHALT PAVING 001 ASPHALT / VEHICLE PARKING AND DRIVEWAYS - 2" overlay with geotec material.

Smith 2011 FIRE SUPPRESSION / SPRINKLER 001 FIRE SPRINKLER SYSTEM - Design new fire sprinkler system throughout entire building. Comply with DPS Design and Construction Standards SECTION 15300: STANDPIPE AND FIRE SPRINKLER STANDARDS and all other applicable DPS Standards. Patch and Repair.

2012 ROOFING 004 ROOFING - BUILT-UP - Built-Up roofing to include the following: Gravel, 4-ply membrane,replace existing perlite with 1/2" wood fiber, 1/8" taper insulation, replace exsiting polyisocyanurate insulation with 2 layers of 2" polyisocyanurate insulation, replace flashing per DPS specs at all walls, drains, conduits, flues, gas lines, exhausts curbs, thru-wall and overflow scuppers, skylights, A/C lines, expansion joints, and parapets. Replace all gaspipe and similiar stand supports bases with concete pavers, paint all existing gas piping per DPS specs. Replace and seal all existing pipe collars. Inspect/replace all applicable drains and gutters.

ADA COMPLIANCE 001 ADA COMPLIANCE - LEVEL 1 - Comply with DPS Design and Construction Standards SECTION 00700: ACCESSIBILITY STANDARDS and all other applicable DPS Standards. See ADA Level 1 Database provided. Deficiency remedies provided in ADA database should serve as the PM guide only and should not be provided to the A/E for purposes of developing the project scope of work. A/E is directed to conduct a building survey limited to the areas identified in the survey. Other ADA deficiencies may be included if they meet the level 1 status and have not been identified in the survey. All questions of possible oversight of a deficiency shall be directed to DPS Facility Planning through the DPS Project Manager.

FINISH RESTORATION 000 FINISH RESTORATION / PAINT - Repaint all surfaces to include but not limited to, all tile and hard ceilings, walls, doorjambs, doors, woodwork, ductwork, univents, radiators and built-in wood or metal cabinets, bathroom partitions painted or baked-on finish. All rooms, corridors, stairwells, closets, storage, mechanical rooms and piping per DPS piping color code. Duct cleaning is required in this scope.

REGULATORY / LIGHT FIXTURES 001 REGULATORY / LIGHT FIXTURES - Replace incandescent fixtures in gym.

TOILET ROOM (INCLUSIVE)

2008 bond for the web Page 78 of 91

2008 GOB - Project Summary by Building & Year Denver Public Schools Facilities Faciliites Planning Management

Smith 2012 TOILET ROOM (INCLUSIVE) 001 Toilet Room (inclusive) - Replace all fixtures, plumbing piping and partitions. Paint walls and Ceilings. Replace tile as required. Lighting to be updated. Repair any associated surface damage, i.e., glazed block, etc.

South 2009 OUTDOOR BLEACHERS 001 Outdoor Bleachers - REPLACE ALL BLEACHER SEATING

001 Outdoor Bleachers - INSTALL SAFETY RAILING, RISER BOARDS

ROOFING 019 ROOFING / EPDM / PVC / SINGLE-PLY - Replace the item

021 ROOFING / EPDM / PVC / SINGLE-PLY - Replace the item

022 ROOFING / EPDM / PVC / SINGLE-PLY - Replace the item

REGULATORY / LIGHT FIXTURES 001 REGULATORY LIGHT FIXTURES - Replace all T-12 and incandescent lighting fixtures with T-8 or T5HO fixtures. Properly dispose of all existing lamps and fixtures. Comply with DPS Design and Construction Standards SECTIONS 16501: LAMPS, 16502 BALLASTS AND CONTROLS and 16510: LUMINAIRES and all other applicable DPS Standards. Patch and Repair.

2010 FIRE SUPPRESSION / SPRINKLER 001 Fire Suppression - Design new fire sprinkler system throughout entire building. Comply with DPS Design and Construction Standards SECTION 15300: STANDPIPE AND FIRE SPRINKLER STANDARDS and all other applicable DPS Standards. Patch and Repair.

2011 ADA COMPLIANCE 001 RREGULATORY - EGRESS / DOOR HARDWARE - Replace exterior door hardware for ADA compliance - A/E should conduct a door hardware schedule. Scope includes exterior doors (with panics if necessary), stairwell doors and hinges. A/E should identify any possible abatement issues to DPS Bond Hazmat project managers for remediation as early as possible.

FINISH RESTORATION 001 FINISH RESTORATION / CARPET - Replace the item

FINISH RESTORATION 408 FINISH RESTORATION / VINYL TILE - REMOVE EXISTING VCT AND REPLACE WITH NEW FLOORING

FINISH RESTORATION 001 FLOORING / WOOD FLOORING - Replace gym floor at N ROTC gym

2008 bond for the web Page 79 of 91

2008 GOB - Project Summary by Building & Year Denver Public Schools Facilities Faciliites Planning Management

South 2011 SAFETY / STAGE RIGGING 001 HEALTH SAFETY / STAGE RIGGING - See Consultants Report (Danny Reid)

ARTIFICIAL TURF 001 ARTIFICIAL TURF - Remove existing sod athletic field and replace with artificial turf.

ASPHALT PAVING 001 CRITICAL / TENNIS COURTS - Remove and replace entire Tennis Court Paving, Nets and Fencing.

Southmoor 2009 FOLDING LUNCHRM TABLES 001 FOLDING LUNCHRM TABLES - INSTALL SURFACE MOUNTED POCKET TABLES

Steck 2010 LEARNING LANDSCAPE 001 LEARNING LANDSCAPE - Construct Learning Landscape per UCD Master Plan. Include 2" playground surface asphalt overlay. - - Note - Steck is listed as a historic landmark. Coordinate design with Denver Landmark Commission. See master plan draft at www.learninglanscapes.org - Conduct soils asphalt and other pertinent testing prior to bid development.

2011 FIRE SUPPRESSION / SPRINKLER 001 FIRE SPRINKLER SYSTEM - Design new fire sprinkler system throughout entire building. Comply with DPS Design and Construction Standards SECTION 15300: STANDPIPE AND FIRE SPRINKLER STANDARDS and all other applicable DPS Standards. Patch and Repair.

2013 HOT WATER HEATER 001 HOT WATER HEATER - REPLACE EXISTING HOT WATER HEATER

Stedman 2009 FOLDING LUNCHRM TABLES 001 FOLDING LUNCHRM TABLES - INSTALL SURFACE MOUNTED POCKET TABLES

LEARNING LANDSCAPE 002 LEARNING LANDSCAPE - Complete LL -- install ampitheatre -- construct shade shelter -- erect gateway (slated 2003 GOB, confirm) -- build crusher fines path and irrigation for community garden, install concrete benches

2008 bond for the web Page 80 of 91

2008 GOB - Project Summary by Building & Year Denver Public Schools Facilities Faciliites Planning Management

Stedman 2012 FIRE SUPPRESSION / SPRINKLER 001 FIRE SPRINKLER SYSTEM - Design new fire sprinkler system throughout entire building. Comply with DPS Design and Construction Standards SECTION 15300: STANDPIPE AND FIRE SPRINKLER STANDARDS and all other applicable DPS Standards. Patch and Repair.

2013 ADA COMPLIANCE 001 ADA COMPLIANCE - LEVEL 1 - Comply with DPS Design and Construction Standards SECTION 00700: ACCESSIBILITY STANDARDS and all other applicable DPS Standards. See ADA Level 1 Database provided. Deficiency remedies provided in ADA database should serve as the PM guide only and should not be provided to the A/E for purposes of developing the project scope of work. A/E is directed to conduct a building survey limited to the areas identified in the survey. Other ADA deficiencies may be included if they meet the level 1 status and have not been identified in the survey. All questions of possible oversight of a deficiency shall be directed to DPS Facility Planning through the DPS Project Manager.

FINISH RESTORATION 001 FINISH RESTORATION / CARPET - Replace the item

Steele 2009 ADA COMPLIANCE 001 ADA COMPLIANCE - LEVEL 1 - Comply with DPS Design and Construction Standards SECTION 00700: ACCESSIBILITY STANDARDS and all other applicable DPS Standards. See ADA Level 1 Database provided. Deficiency remedies provided in ADA database should serve as the PM guide only and should not be provided to the A/E for purposes of developing the project scope of work. A/E is directed to conduct a building survey limited to the areas identified in the survey. Other ADA deficiencies may be included if they meet the level 1 status and have not been identified in the survey. All questions of possible oversight of a deficiency shall be directed to DPS Facility Planning through the DPS Project Manager.

TOILET ROOM (INCLUSIVE) 001 Toilet Room (inclusive) - Replace all fixtures, plumbing piping and partitions. Paint walls and Ceilings. Replace tile as required. Lighting to be updated. Repair any associated surface damage, i.e., glazed block, etc.

BUILDING (NEW) 001 INSTALL MODULAR CLASSROOMS OR RELOCATE EXISTING PLANETARIUM, EXPLORATORIUM TO NEW LOCATION AND REMODEL EXISTING SPACES FOR REGULAR CLASSROOM USE

FIRE SUPPRESSION / SPRINKLER 001 FIRE SPRINKLER SYSTEM - Design new fire sprinkler system throughout entire building. Comply with DPS Design and Construction Standards SECTION 15300: STANDPIPE AND FIRE SPRINKLER STANDARDS and all other applicable DPS Standards. Patch and Repair.

REGULATORY / LIGHT FIXTURES

2008 bond for the web Page 81 of 91

2008 GOB - Project Summary by Building & Year Denver Public Schools Facilities Faciliites Planning Management

Steele 2009 REGULATORY / LIGHT FIXTURES 001 REGULATORY LIGHT FIXTURES - Replace all T-12 and incandescent lighting fixtures with T-8 or T5HO fixtures. Properly dispose of all existing lamps and fixtures. Comply with DPS Design and Construction Standards SECTIONS 16501: LAMPS, 16502 BALLASTS AND CONTROLS and 16510: LUMINAIRES and all other applicable DPS Standards. Patch and Repair.

Swansea 2009 VIDEO SECURITY 001 Video Security - Re-check

FOLDING LUNCHRM TABLES 001 FOLDING LUNCHRM TABLES - INSTALL SURFACE MOUNTED POCKET TABLES

2013 FINISH RESTORATION 001 FINISH RESTORATION / PAINT - Repaint all surfaces to include but not limited to, all tile and hard ceilings, walls, doorjambs, doors, woodwork, ductwork, univents, radiators and built-in wood or metal cabinets, bathroom partitions painted or baked-on finish. All rooms, corridors, stairwells, closets, storage, mechanical rooms and piping per DPS piping color code. Duct cleaning is required in this scope.

REGULATORY / LIGHT FIXTURES 001 REGULATORY LIGHT FIXTURES - Replace all T-12 and incandescent lighting fixtures with T-8 or T5HO fixtures. Properly dispose of all existing lamps and fixtures. Comply with DPS Design and Construction Standards SECTIONS 16501: LAMPS, 16502 BALLASTS AND CONTROLS and 16510: LUMINAIRES and all other applicable DPS Standards. Patch and Repair.

Teller 2009 FINISH RESTORATION 000 FINISH RESTORATION / PAINT - Repaint all surfaces required to include but not limited, All tile and hard ceilings, walls, doorjambs, doors, woodwork, ductwork, univents, radiators and built-in wood or metal cabinets, bathroom partitions, painted or baked-on finishes. All rooms, corridors, stairwells, closets, storage, mechanical rooms and piping per DPS piping color code. Duct cleaning is required in this scope, but costs are listed under an HVAC asset and listed separately

FINISH RESTORATION 001 FINISH RESTORATION / CARPET - Replace the item

2010 LEARNING LANDSCAPE 001 LEARNING LANDSCAPE - Construct Learning Landscape per UCD Master Plan. Include 2" playground surface asphalt overlay. See master plan draft at www.learninglanscapes.org - Conduct soils asphalt and other pertinent testing prior to bid development.

2008 bond for the web Page 82 of 91

2008 GOB - Project Summary by Building & Year Denver Public Schools Facilities Faciliites Planning Management

Teller 2011 FIRE DETECTION 001 FIRE DETECTION SYSTEM - Panel only. No longer supported by Manufacture

FIRE SUPPRESSION / SPRINKLER 001 FIRE SPRINKLER SYSTEM - Design new fire sprinkler system throughout entire building. Comply with DPS Design and Construction Standards SECTION 15300: STANDPIPE AND FIRE SPRINKLER STANDARDS and all other applicable DPS Standards. Patch and Repair.

2013 ROOFING 010 ROOFING / EPDM / PVC / SINGLE-PLY - Replace the item

Traylor 2009 FOLDING LUNCHRM TABLES 001 FOLDING LUNCHRM TABLES - INSTALL SURFACE MOUNTED POCKET TABLES

BOILER 001 BOILER - Replace boiler as per DPS guide specs 15555. Replace in boiler room: pumps, hydronic specality items, associated pipe and all valves. Ref. spec. 15110, and all div. 15 that apply including water treatment associated with this project ref. 15548

002 BOILER - Retube boiler replace controls

REGULATORY / LIGHT FIXTURES 001 REGULATORY LIGHT FIXTURES - Replace all T-12 and incandescent lighting fixtures with T-8 or T5HO fixtures. Properly dispose of all existing lamps and fixtures. Comply with DPS Design and Construction Standards SECTIONS 16501: LAMPS, 16502 BALLASTS AND CONTROLS and 16510: LUMINAIRES and all other applicable DPS Standards. Patch and Repair.

BUILDNG (NEW) 001 PLACE MODULAR CLASSROOMS FOR ECE EXPANSION FULL DAY PROGRAMS

2013 DIMMER SYSTEM (STAGE AND PERFORMANCE) 001 DIMMER SYSTEM (STAGE AND PERFORMANCE) - Replace the item

FINISH RESTORATION 001 FINISH RESTORATION / CARPET - Replace the item

2008 bond for the web Page 83 of 91

2008 GOB - Project Summary by Building & Year Denver Public Schools Facilities Faciliites Planning Management

University Park 2009 FIRE SUPPRESSION / SPRINKLER 001 FIRE SPRINKLER SYSTEM - Design new fire sprinkler system throughout entire building. Comply with DPS Design and Construction Standards SECTION 15300: STANDPIPE AND FIRE SPRINKLER STANDARDS and all other applicable DPS Standards. Patch and Repair.

BOILER 001 BOILER - Replace boiler as per DPS guide specs 15555C. Replace in boiler room: condensate return pumps, steam traps, condensate return pipe, boiler feed pipe, and all valves. Ref. spec. 15110, 15521, and all div. 15 that apply including water treatment associated with this project ref. 15548

002 BOILER - Replace boiler as per DPS guide specs 15555C. Replace in boiler room: condensate return pumps, steam traps, condensate return pipe, boiler feed pipe, and all valves. Ref. spec. 15110, 15521, and all div. 15 that apply including water treatment associated with this project ref. 15548

REGULATORY / LIGHT FIXTURES 001 REGULATORY LIGHT FIXTURES - Replace all T-12 and incandescent lighting fixtures with T-8 or T5HO fixtures. Properly dispose of all existing lamps and fixtures. Comply with DPS Design and Construction Standards SECTIONS 16501: LAMPS, 16502 BALLASTS AND CONTROLS and 16510: LUMINAIRES and all other applicable DPS Standards. Patch and Repair.

2012 IRRIGATION 001 IRRIGATION - Replace the item

LEARNING LANDSCAPE 001 LEARNING LANDSCAPE - Construct Learning Landscape per UCD Master Plan. Include 2" playground surface asphalt overlay..

2013 TOILET ROOM (INCLUSIVE) 001 Toilet Room (inclusive) - Replace all fixtures, plumbing piping and partitions. Paint walls and Ceilings. Replace tile as required. Lighting to be updated. Repair any associated surface damage, i.e., glazed block, etc.

ROOFING 002 ROOFING - BUILT-UP - Built-Up roofing to include the following: Gravel, 4-ply membrane,replace existing perlite with 1/2" wood fiber, 1/8" taper insulation, replace exsiting polyisocyanurate insulation with 2 layers of 2" polyisocyanurate insulation, replace flashing per DPS specs at all walls, drains, conduits, flues, gas lines, exhausts curbs, thru-wall and overflow scuppers, skylights, A/C lines, expansion joints, and parapets. Replace all gaspipe and similiar stand supports bases with concete pavers, paint all existing gas piping per DPS specs. Replace and seal all existing pipe collars. Inspect/replace all applicable drains and gutters.

005 ROOFING - BUILT-UP - Built-Up roofing to include the following: Gravel, 4-ply membrane,replace existing perlite with 1/2" wood fiber, 1/8" taper insulation, replace exsiting polyisocyanurate insulation with 2 layers of 2" polyisocyanurate insulation, replace flashing per DPS specs at all walls, drains, conduits, flues, gas lines, exhausts curbs, thru-wall and overflow scuppers, skylights, A/C lines, expansion joints, and parapets. Replace all gaspipe and similiar stand supports bases with concete pavers, paint all existing gas piping per DPS specs. Replace and seal all existing pipe collars. Inspect/replace all applicable drains and gutters.

2008 bond for the web Page 84 of 91

2008 GOB - Project Summary by Building & Year Denver Public Schools Facilities Faciliites Planning Management

University Park 2013 ROOFING 007 ROOFING - BUILT-UP - Built-Up roofing to include the following: Gravel, 4-ply membrane,replace existing perlite with 1/2" wood fiber, 1/8" taper insulation, replace exsiting polyisocyanurate insulation with 2 layers of 2" polyisocyanurate insulation, replace flashing per DPS specs at all walls, drains, conduits, flues, gas lines, exhausts curbs, thru-wall and overflow scuppers, skylights, A/C lines, expansion joints, and parapets. Replace all gaspipe and similiar stand supports bases with concete pavers, paint all existing gas piping per DPS specs. Replace and seal all existing pipe collars. Inspect/replace all applicable drains and gutters.

009 ROOFING - BUILT-UP - Built-Up roofing to include the following: Gravel, 4-ply membrane,replace existing perlite with 1/2" wood fiber, 1/8" taper insulation, replace exsiting polyisocyanurate insulation with 2 layers of 2" polyisocyanurate insulation, replace flashing per DPS specs at all walls, drains, conduits, flues, gas lines, exhausts curbs, thru-wall and overflow scuppers, skylights, A/C lines, expansion joints, and parapets. Replace all gaspipe and similiar stand supports bases with concete pavers, paint all existing gas piping per DPS specs. Replace and seal all existing pipe collars. Inspect/replace all applicable drains and gutters.

010 ROOFING - BUILT-UP - Built-Up roofing to include the following: Gravel, 4-ply membrane,replace existing perlite with 1/2" wood fiber, 1/8" taper insulation, replace exsiting polyisocyanurate insulation with 2 layers of 2" polyisocyanurate insulation, replace flashing per DPS specs at all walls, drains, conduits, flues, gas lines, exhausts curbs, thru-wall and overflow scuppers, skylights, A/C lines, expansion joints, and parapets. Replace all gaspipe and similiar stand supports bases with concete pavers, paint all existing gas piping per DPS specs. Replace and seal all existing pipe collars. Inspect/replace all applicable drains and gutters.

Valdez 2009 FOLDING LUNCHRM TABLES 001 FOLDING LUNCHRM TABLES - INSTALL SURFACE MOUNTED POCKET TABLES

VIDEO SECURITY 001 Video Security - Install A/C

FIRE DETECTION 001 FIRE DETECTION SYSTEM - high voltage panel. Obsolete Replace entire Fire Alarm System.

2010 ABSORPTION CHILLER 001 ABSORBTION CHILLER - Replace with Centrifugal Water Chiller. Water treament included w/18 month warranty. Startup and commissioning included. Comply with DPS Design and Construction Standards SECTION 15650: REFRIGERATION, and all other applicable DPS Standards. Patch and repair.

COOLING SYS / COOLING TOWER 001 COOLING SYS/COOLING TOWER REPLACEMENT -Include water treatment w/ 18 month warranty. Include VFD on fan motor. Recommend Marley tower with bird screens. Startup and commissioning included. Design for cooling tower replacement, and the removal of material and equipment no longer needed. Comply with DPS Design and Construction Standards SECTION 15650: REFRIGERATION, and all other applicable DPS Standards. Patch and repair.

REGULATORY / LIGHT FIXTURES

2008 bond for the web Page 85 of 91

2008 GOB - Project Summary by Building & Year Denver Public Schools Facilities Faciliites Planning Management

Valdez 2010 REGULATORY / LIGHT FIXTURES 001 REGULATORY LIGHT FIXTURES - Replace all T-12 and incandescent lighting fixtures with T-8 or T5HO fixtures. Properly dispose of all existing lamps and fixtures. Comply with DPS Design and Construction Standards SECTIONS 16501: LAMPS, 16502 BALLASTS AND CONTROLS and 16510: LUMINAIRES and all other applicable DPS Standards. Patch and Repair.

WINDOWS 001 WINDOWS - METAL - Coordinate with light fixture replacement, chiller replacement, and cooling tower replacement.

2011 IRRIGATION 001 IRRIGATION - Replace the item

LEARNING LANDSCAPE 001 LEARNING LANDSCAPE - Construct Learning Landscape per UCD Master Plan. Include 2" playground surface asphalt overlay..

2012 ADA COMPLIANCE 001 ADA COMPLIANCE - No Access to Instruct. Areas -- Provide Elevators to serve split levels

FINISH RESTORATION 001 FINISH RESTORATION / SEAMLESS FLR - replace all seamless with ceramic/quarry tile

Valverde 2009 BOILER 001 BOILER - Replace boiler as per DPS guide specs 15555C. Replace in boiler room: condensate return pumps, steam traps, condensate return pipe, boiler feed pipe, and all valves. Ref. spec. 15110, 15521, and all div. 15 that apply including water treatment associated with this project ref. 15548

002 BOILER - Replace boiler as per DPS guide specs 15555C. Replace in boiler room: condensate return pumps, steam traps, condensate return pipe, boiler feed pipe, and all valves. Ref. spec. 15110, 15521, and all div. 15 that apply including water treatment associated with this project ref. 15548

2011 ADA COMPLIANCE 001 ADA COMPLIANCE - LEVEL 1 - Comply with DPS Design and Construction Standards SECTION 00700: ACCESSIBILITY STANDARDS and all other applicable DPS Standards. See ADA Level 1 Database provided. Deficiency remedies provided in ADA database should serve as the PM guide only and should not be provided to the A/E for purposes of developing the project scope of work. A/E is directed to conduct a building survey limited to the areas identified in the survey. Other ADA deficiencies may be included if they meet the level 1 status and have not been identified in the survey. All questions of possible oversight of a deficiency shall be directed to DPS Facility Planning through the DPS Project Manager.

FINISH RESTORATION

2008 bond for the web Page 86 of 91

2008 GOB - Project Summary by Building & Year Denver Public Schools Facilities Faciliites Planning Management

Valverde 2011 FINISH RESTORATION 001 FINISH RESTORATION / PAINT - Repaint all surfaces to include but not limited to, all tile and hard ceilings, walls, doorjambs, doors, woodwork, ductwork, univents, radiators and built-in wood or metal cabinets, bathroom partitions painted or baked-on finish. All rooms, corridors, stairwells, closets, storage, mechanical rooms and piping per DPS piping color code. Duct cleaning is required in this scope.

ASPHALT PAVING 003 ASPHALT / PARKING - Construct parking lot expansion for Valverde parking. Est. 12000 sf parking lot to be constructed west of existing parking lot on south side of school on Tejon Street.

IRRIGATION 001 IRRIGATION - Replace the item

LEARNING LANDSCAPE 001 LEARNING LANDSCAPE - Construct Learning Landscape per UCD Master Plan.

2013 FIRE SUPPRESSION / SPRINKLER 001 FIRE SPRINKLER SYSTEM - Design new fire sprinkler system throughout entire building. Comply with DPS Design and Construction Standards SECTION 15300: STANDPIPE AND FIRE SPRINKLER STANDARDS and all other applicable DPS Standards. Patch and Repair.

WALLER 2009 LEARNING LANDSCAPE 002 INSTALL MISSING ELEMENTS TO COMPLETE LEARNING LANDSCAPE

Washington 2009 ADA COMPLIANCE 001 REGULATORY - EGRESS / DOOR HARDWARE - Replace exterior door hardware for ADA compliance - A/E should conduct a door hardware schedule. Scope includes exterior doors (with panics if necessary), stairwell doors and hinges. A/E should identify any possible abatement issues to DPS Bond Hazmat project managers for remediation as early as possible.

FINISH RESTORATION 001 FLOORING / WOOD FLOORING - 3630sf

ARTIFICIAL TURF 001 ARTIFICIAL TURF - Remove existing sod athletic field and replace with artificial turf.

2012 SAFETY / STAGE RIGGING

2008 bond for the web Page 87 of 91

2008 GOB - Project Summary by Building & Year Denver Public Schools Facilities Faciliites Planning Management

Washington 2012 SAFETY / STAGE RIGGING 001 HEALTH SAFETY / STAGE RIGGING - See Consultants Report (Danny Reid)

VENTILLATION / CENTRAL FAN / AHU 001 VENTILLATION / CENTRAL FAN / AHU - Attention this scope of work cannot proceed unless it is bundled with H ENS C Temp Controls /Environment Scope. Univent system needs complete replacement, replace supply and return feeds back to main, include case work required to accommodate new univents. All other Central Air Handling Units need commercial cleaning, duct work repaired as needed, new motors, new pumps, replace branch piping if needed, fan bearings and damper sections. Replace all Exhaust Fans including dampers

TEMP CONTROLS / ENVIRONMENT 001 TEMP CONTROLS / ENVIRONMENT - Attention this scope of work cannot proceed unless it is bundled with H ENS C Temp Controls /Environment Scope. Univent system needs complete replacement, replace steam and condensate feeds back to main, all steam traps including drip and end of main,include case work required to accommodate new univents. All other Central Air Handling Units need commercial cleaning, duct work repaired as needed, new motors, replace branch piping if needed, steam traps, fan bearings and damper sections. Replace all Exhaust Fans including dampers

WEST 2009 BUILDING (REMODEL) 002 NEW SCHOOLS STARTUP REMODELING

2010 ARTIFICIAL TURF 001 ARTIFICIAL TURF - Scope to include all civil testing and easements, permimeter fencing, all civil testing, detention ponds and related drainage subsystems, and subgrade w/drainage. Provide sleeving in field for school- provided scoreboard, pad for bleacher seating are optional, provide step system for slopes if required. Note that 2 lanes of exsiting track will be consumed by turf, so significant repair and resurfacing of track will be required. Provide industry standard athletic stripping, and dimensions. Provide sleeves for future electrical needs. DPS O&M Shops to retain slavage rights on irrrigation and other demo. Excess soil should remain on site if possible. Provide ADA access to seating areas.

ADA COMPLIANCE 001 ADA COMPLIANCE - DOOR HARDWARE - A/E should conduct a room by room door hardware schedule. Scope includes all doors, utility closets, exterior doors (with panics if necessary), stairwell doors and hinges. Excluded are cabinetry doors. A/E should identify any possible abatement issues to DPS Bond Hazmat project managers for remediation as early as possible.

HOT WATER HEATER 001 HOT WATER HEATER - Plumbing - Design new hot water heating system and the removal of old equipment. Comply with DPS Design and Construction Standards SECTION 15450: PLUMBING EQUIPMENT and all other applicable DPS Standards. Asbestos management by DPS and not included in this scope. Patch and Repair.

ROOFING

2008 bond for the web Page 88 of 91

2008 GOB - Project Summary by Building & Year Denver Public Schools Facilities Faciliites Planning Management

WEST 2010 ROOFING 019 ROOFING - BUILT-UP - Regarding Deck# 19- Built-Up roofing to include the following: Gravel, 4-ply membrane,replace existing perlite with 1/2" wood fiber, 1/8" taper insulation, replace exsiting polyisocyanurate insulation with 2 layers of 2" polyisocyanurate insulation, replace flashing per DPS specs at all walls, drains, conduits, flues, gas lines, exhausts curbs, thru-wall and overflow scuppers, skylights, A/C lines, expansion joints, and parapets. Replace all gaspipe and similiar stand supports bases with concete pavers, paint all existing gas piping per DPS specs. Replace and seal all existing pipe collars. Inspect/replace all applicable drains and gutters. - Note - West is listed as a historic landmark. Coordinate design with Denver Landmark Commission.

023 ROOFING - BUILT-UP - Regarding Deck# 23- Built-Up roofing to include the following: Gravel, 4-ply membrane,replace existing perlite with 1/2" wood fiber, 1/8" taper insulation, replace exsiting polyisocyanurate insulation with 2 layers of 2" polyisocyanurate insulation, replace flashing per DPS specs at all walls, drains, conduits, flues, gas lines, exhausts curbs, thru-wall and overflow scuppers, skylights, A/C lines, expansion joints, and parapets. Replace all gaspipe and similiar stand supports bases with concete pavers, paint all existing gas piping per DPS specs. Replace and seal all existing pipe collars. Inspect/replace all applicable drains and gutters. - Note - West is listed as a historic landmark. Coordinate design with Denver Landmark Commission.

024 ROOFING - BUILT-UP - Regarding Deck# 24- Built-Up roofing to include the following: Gravel, 4-ply membrane,replace existing perlite with 1/2" wood fiber, 1/8" taper insulation, replace exsiting polyisocyanurate insulation with 2 layers of 2" polyisocyanurate insulation, replace flashing per DPS specs at all walls, drains, conduits, flues, gas lines, exhausts curbs, thru-wall and overflow scuppers, skylights, A/C lines, expansion joints, and parapets. Replace all gaspipe and similiar stand supports bases with concete pavers, paint all existing gas piping per DPS specs. Replace and seal all existing pipe collars. Inspect/replace all applicable drains and gutters. - - Note - West is listed as a historic landmark. Coordinate design with Denver Landmark Commission.

2012 VENTILLATION / CENTRAL FAN / AHU 001 VENTILLATION / CENTRAL FAN / AHU - Replace the item

TEMP CONTROLS / ENVIRONMENT 001 TEMP CONTROLS / ENVIRONMENT - Replace the item

Westerly Creek 2009 TECHNOLOGY CONSTRUCTION SUPPORT 002 TECHNOLOGY CONSTRUCTION SUPPORT - Install dedicated air conditioning unit in the MDF.

LEARNING LANDSCAPE 001 Install shade structure

Whiteman 2009 ROOFING 003 ROOFING / EPDM / PVC / SINGLE-PLY - Replace the item

2008 bond for the web Page 89 of 91

2008 GOB - Project Summary by Building & Year Denver Public Schools Facilities Faciliites Planning Management

Whittier 2009 FOLDING LUNCHRM TABLES 001 FOLDING LUNCHRM TABLES - INSTALL SURFACE MOUNTED POCKET TABLES

ASPHALT PAVING 002 ASPHALT / VEHICLE PARKING AND DRIVEWAYS - 2" overlay with geotec material.

2010 ABSORPTION CHILLER 001 ABSORBTION CHILLER - Replace with Centrifugal Water Chiller. Water treament included w/18 month warranty. Startup and commissioning included. Comply with DPS Design and Construction Standards SECTION 15650: REFRIGERATION, and all other applicable DPS Standards. Patch and repair.

WINDOWS 001 WINDOWS - METAL - Metal Windows, Replace the item. Coordinate with chiller replacement

WINDOWS 001 WINDOWS - WOOD - Replace the item. Coordinate with ongoing chiller replacement project on-site.

2012 ROOFING 006 ROOFING - BUILT-UP - Built-Up roofing to include the following: Gravel, 4-ply membrane,replace existing perlite with 1/2" wood fiber, 1/8" taper insulation, replace exsiting polyisocyanurate insulation with 2 layers of 2" polyisocyanurate insulation, replace flashing per DPS specs at all walls, drains, conduits, flues, gas lines, exhausts curbs, thru-wall and overflow scuppers, skylights, A/C lines, expansion joints, and parapets. Replace all gaspipe and similiar stand supports bases with concete pavers, paint all existing gas piping per DPS specs. Replace and seal all existing pipe collars. Inspect/replace all applicable drains and gutters.

ADA COMPLIANCE 001 ADA COMPLIANCE - LEVEL 1 - Comply with DPS Design and Construction Standards SECTION 00700: ACCESSIBILITY STANDARDS and all other applicable DPS Standards. See ADA Level 1 Database provided. Deficiency remedies provided in ADA database should serve as the PM guide only and should not be provided to the A/E for purposes of developing the project scope of work. A/E is directed to conduct a building survey limited to the areas identified in the survey. Other ADA deficiencies may be included if they meet the level 1 status and have not been identified in the survey. All questions of possible oversight of a deficiency shall be directed to DPS Facility Planning through the DPS Project Manager.

FINISH RESTORATION 001 FINISH RESTORATION / PAINT - Repaint all surfaces to include but not limited to, all tile and hard ceilings, walls, doorjambs, doors, woodwork, ductwork, univents, radiators and built-in wood or metal cabinets, bathroom partitions painted or baked-on finish. All rooms, corridors, stairwells, closets, storage, mechanical rooms and piping per DPS piping color code. Duct cleaning is required in this scope.

TOILET ROOM (INCLUSIVE) 001 Toilet Room (inclusive) - Replace all fixtures, plumbing piping and partitions. Paint walls and Ceilings. Replace tile as required. Lighting to be updated. Repair any associated surface damage, i.e., glazed block, etc.

2008 bond for the web Page 90 of 91

2008 GOB - Project Summary by Building & Year Denver Public Schools Facilities Faciliites Planning Management

Yuma Street 2009 KITCHEN EQUIPMENT - REFRIGERATION 001 KITCHEN EQUIPMENT - REFRIGERATION - Replace Compressors at Yuma Street. Verify with QA/QC on priority for replacement of exisiting compressors.

2010 FINISH RESTORATION 001 FINISH RESTORATION - CARPET - Replace all office, conferencing, and lobby area carpeting and base trim per DPS specs. Coordinate all necessary hazmat testing and abatement with DPS Hazmat PMs. Scope to include breakdown and/or relocation of all non-fixed equipment. Add vinyl tile replacement as an alternate and replace as funding permits. Yuma Street - Include all offices and meeting rooms in the warehouse area area as well as first floor office areas.