2007 MITSUBISHI LECTURE · 1 2007 MITSUBISHI LECTURE PART 2 CASE STUDIES Pells Sullivan Meynink...

21
1 2007 MITSUBISHI LECTURE 2007 MITSUBISHI LECTURE HIGHWALL, STOCKPILE AND DUMPS: SAFETY AND PRODUCTIVITY Tim Sullivan Pells Sullivan Meynink Pells Sullivan Meynink P e l l s S u l l i v a n M e y n i n k MINING AND RISK ? MINING AND RISK ? P e l l s S u l l i v a n M e y n i n k SURFACE MINING SURFACE MINING Traditionally two General Subdivisions: Hard Rock and Soft Rock. But “…….all geotechnical materials are part of one continuous spectrum”. “…….one continuous science extending from soft soils to hard rocks. All geotechnical materials behave according to the same engineering principles…” “…….differences a function of degree rather than fundamental nature” (Johnston 1991). P e l l s S u l l i v a n M e y n i n k OPEN CUT MINE SLOPE DESIGN OPEN CUT MINE SLOPE DESIGN Application of scientific methods and engineering principles to the materials of the earth’s crust for the solution of engineering problems. MINE SLOPE DESIGN: Soil mechanics, Rock mechanics, Hydrogeology and Geology. Geologically based science. Fundamental corner stone of all mine slope design is geology. Success with mine design depends on the ability to understand the geology. In particular, the Patterns, Subtleties and Variations. P e l l s S u l l i v a n M e y n i n k ENGINEERING AND SCIENTIFIC ENGINEERING AND SCIENTIFIC DISCIPLINES DISCIPLINES P e l l s S u l l i v a n M e y n i n k GENERAL SLOPE DESIGN OBJECTIVES GENERAL SLOPE DESIGN OBJECTIVES What are the general slope design rules? “achieve an optimum design – a compromise between a slope which is steep enough to be economically acceptable and one which is flat enough to be safe” (Hoek and Bray, 1981).” What is the practical reality to statements such as: “steep enough to be economically acceptable” or “flat enough to be safe”. The other general definition of the optimum pit slope design is: “The best design is the one which falls down the day that the last truck leaves the pit”.

Transcript of 2007 MITSUBISHI LECTURE · 1 2007 MITSUBISHI LECTURE PART 2 CASE STUDIES Pells Sullivan Meynink...

Page 1: 2007 MITSUBISHI LECTURE · 1 2007 MITSUBISHI LECTURE PART 2 CASE STUDIES Pells Sullivan Meynink CASE EXAMPLES “…slopes seldom fail without giving adequate warning” (Hoek and

1

2007 MITSUBISHI LECTURE2007 MITSUBISHI LECTURE

HIGHWALL, STOCKPILE AND DUMPS:SAFETY AND PRODUCTIVITY

Tim SullivanPells Sullivan Meynink

Pells Sullivan Meynink Pells

Sulli

van

Mey

n ink

MINING AND RISK ?MINING AND RISK ?

Pells

Sulli

van

Mey

n ink

SURFACE MININGSURFACE MINING

Traditionally two General Subdivisions:– Hard Rock and– Soft Rock.

But

“…….all geotechnical materials are part of one continuous spectrum”.

“…….one continuous science extending from soft soils to hard rocks. All geotechnical materials behave according to the same engineering principles…”

“…….differences a function of degree rather than fundamental nature” (Johnston 1991).

Pells

Sulli

van

Mey

n ink

OPEN CUT MINE SLOPE DESIGNOPEN CUT MINE SLOPE DESIGNApplication of scientific methods and engineering principles to the materials of the earth’s crust for the solution of engineering problems.

MINE SLOPE DESIGN:

• Soil mechanics,• Rock mechanics,• Hydrogeology and• Geology.

Geologically based science.

Fundamental corner stone of all mine slope design is geology.

Success with mine design depends on the ability to understand the geology.

In particular, the Patterns, Subtleties and Variations.

Pells

Sulli

van

Mey

n ink

ENGINEERING AND SCIENTIFIC ENGINEERING AND SCIENTIFIC DISCIPLINESDISCIPLINES

Pells

Sulli

van

Mey

n ink

GENERAL SLOPE DESIGN OBJECTIVESGENERAL SLOPE DESIGN OBJECTIVES

What are the general slope design rules?

“achieve an optimum design – a compromise between a slope which is steep enough to be economically acceptable and one which is flat enough to be safe” (Hoek and Bray, 1981).”

What is the practical reality to statements such as:

“steep enough to be economically acceptable”or

“flat enough to be safe”.

The other general definition of the optimum pit slope design is:

“The best design is the one which falls down the day that the last truck leaves the pit”.

Page 2: 2007 MITSUBISHI LECTURE · 1 2007 MITSUBISHI LECTURE PART 2 CASE STUDIES Pells Sullivan Meynink CASE EXAMPLES “…slopes seldom fail without giving adequate warning” (Hoek and

2

Pells

Sulli

van

Mey

n ink

SIMPLE GEOLOGY SIMPLE GEOLOGY –– RISK?RISK?

Pells

Sulli

van

Mey

n ink

COMPLEX GEOLOGY – RISK?

Pells

Sulli

van

Mey

n ink

HOW EFFECTIVELY HOW EFFECTIVELY CAN WE CAN WE

UNDERSTAND THE UNDERSTAND THE GEOLOGY?GEOLOGY?

COMPARISON OF COMPARISON OF DRILLINGDRILLING

AND INTERPRETED AND INTERPRETED FAULTSFAULTS

Pells

Sulli

van

Mey

n ink

TECHNICAL COMPLEXITY AND RISK?TECHNICAL COMPLEXITY AND RISK?

Pells

Sulli

van

Mey

n ink

MINE GEOMETRY AND RISK?MINE GEOMETRY AND RISK?

Pells

Sulli

van

Mey

n ink

MINE GEOMETRY AND RISK?MINE GEOMETRY AND RISK?

Page 3: 2007 MITSUBISHI LECTURE · 1 2007 MITSUBISHI LECTURE PART 2 CASE STUDIES Pells Sullivan Meynink CASE EXAMPLES “…slopes seldom fail without giving adequate warning” (Hoek and

3

Pells

Sulli

van

Mey

n ink

MINE GEOMETRY AND RISK?MINE GEOMETRY AND RISK?

EXCAVATING A SLOT NEXT TO AN UNSTABLE HIGHWALL

Page 4: 2007 MITSUBISHI LECTURE · 1 2007 MITSUBISHI LECTURE PART 2 CASE STUDIES Pells Sullivan Meynink CASE EXAMPLES “…slopes seldom fail without giving adequate warning” (Hoek and

1

2007 MITSUBISHI LECTURE2007 MITSUBISHI LECTURE

PART 2CASE STUDIES

Pells Sullivan Meynink

CASE EXAMPLESCASE EXAMPLES“…slopes seldom fail without giving adequate warning” (Hoek

and Bray 1974)

Five Scales Of Problem:• Very Large Post Failure Deformations• Large Blocky Failures and

Collapses – Highwalls and dump• Bench Failure• Rockfall• Small Individual Blocks

Pells

Sulli

van

Mey

n ink

FREEPORT OVERALL VIEWFREEPORT OVERALL VIEW

Pells

Sulli

van

Mey

n ink

PRE FAILURE PRE FAILURE -- SOUTH WALLSOUTH WALL

Pells

Sulli

van

Mey

n ink

OVERALL OVERALL VIEW OF VIEW OF

FLOW PATHFLOW PATH

Pells

Sulli

van

Mey

n ink

FLOW PATH LOWER SLOPEFLOW PATH LOWER SLOPE

Pells

Sulli

van

Mey

n ink

MID HEIGHT BENCH 80m WIDE ? ENOUGH??

DEATHS OCCURRED HERE

Page 5: 2007 MITSUBISHI LECTURE · 1 2007 MITSUBISHI LECTURE PART 2 CASE STUDIES Pells Sullivan Meynink CASE EXAMPLES “…slopes seldom fail without giving adequate warning” (Hoek and

2

FLOW PATH IN TOEFLOW PATH IN TOE

Pells

Sulli

van

Mey

n ink

FLOW PATH MID SLOPEFLOW PATH MID SLOPE

Pells

Sulli

van

Mey

n ink

CRESTCREST

Pells

Sulli

van

Mey

n ink

FINE GRAINED ALTERED ROCK

SECTION THROUGH SLIDESECTION THROUGH SLIDE

Pells

Sulli

van

Mey

n ink

DRILL, SHOVEL AND TRUCKSDRILL, SHOVEL AND TRUCKS

Pells

Sulli

van

Mey

n ink

DRILL,TRUCK AND SHOVELDRILL,TRUCK AND SHOVEL

Pells

Sulli

van

Mey

n ink

Page 6: 2007 MITSUBISHI LECTURE · 1 2007 MITSUBISHI LECTURE PART 2 CASE STUDIES Pells Sullivan Meynink CASE EXAMPLES “…slopes seldom fail without giving adequate warning” (Hoek and

3

TRUCKTRUCK

Pells

Sulli

van

Mey

n ink

MONITORINGMONITORINGSYSTEMS?SYSTEMS?

Pells

Sulli

van

Mey

n ink

NCHANGANCHANGA

Pells

Sulli

van

Mey

n ink

UNBENCHED FOOTWALL – 220m HIGH

OVERALL VIEW OF FAILUREOVERALL VIEW OF FAILURE

Pells

Sulli

van

Mey

n ink

CRESTCREST

Pells

Sulli

van

Mey

n ink

SHOVEL DESTROYEDSHOVEL DESTROYED

Pells

Sulli

van

Mey

n ink

Page 7: 2007 MITSUBISHI LECTURE · 1 2007 MITSUBISHI LECTURE PART 2 CASE STUDIES Pells Sullivan Meynink CASE EXAMPLES “…slopes seldom fail without giving adequate warning” (Hoek and

4

SECTION THROUGH FAILURESECTION THROUGH FAILURE

Pells

Sulli

van

Mey

n ink

27ºKINK BANDS

SUMMARY OF FAILURE INFORMATIONSUMMARY OF FAILURE INFORMATION

Pells

Sulli

van

Mey

n ink

NchangaPrevious failure20,000,000 tonnesJune 1985

NchangaPrevious failure20,000,000 tonnesJune 1985

HISTORY OF FAILURESANTAMINA PERUANTAMINA PERU

Pells

Sulli

van

Mey

n ink

OVERALL SETTINGOVERALL SETTING

Pells

Sulli

van

Mey

n ink

LAKE SEDIMENTS LEFT IN VALLEY

SHOVEL AND TRUCK SHOVED ACROSS PIT SHOVEL AND TRUCK SHOVED ACROSS PIT FLOORFLOOR

Pells

Sulli

van

Mey

n ink

Page 8: 2007 MITSUBISHI LECTURE · 1 2007 MITSUBISHI LECTURE PART 2 CASE STUDIES Pells Sullivan Meynink CASE EXAMPLES “…slopes seldom fail without giving adequate warning” (Hoek and

5

BULLDOZER BURIEDBULLDOZER BURIED

Pells

Sulli

van

Mey

n ink

?

INTACT ROCK BUNDLAKE

SEDIMENTS

DRILLSDRILLS

Pells

Sulli

van

Mey

n ink

CLOSE UP OF DRILLCLOSE UP OF DRILL

Pells

Sulli

van

Mey

n ink

ABERFAN ABERFAN –– EXCAVATING THE TOEEXCAVATING THE TOE

Pells

Sulli

van

Mey

n ink

OVERALL VIEW OF ABERFANOVERALL VIEW OF ABERFAN

Pells

Sulli

van

Mey

n ink

PREVIOUS SLIDE

ABERFAN WASTE DUMPABERFAN WASTE DUMP

21ST October 1966.144 deaths, including 116 children.

Colliery waste had been dumped above the village for more than 20 years.

Two previous dump failures had occurred; 1944 and 1963. The 1963 failure was in the same location as the 1966 failure.

Because mine personnel were not injured and the downstream environment was not significantly damaged, the 1944 and 1963 slides were ignored.

Pells

Sulli

van

Mey

n ink

Page 9: 2007 MITSUBISHI LECTURE · 1 2007 MITSUBISHI LECTURE PART 2 CASE STUDIES Pells Sullivan Meynink CASE EXAMPLES “…slopes seldom fail without giving adequate warning” (Hoek and

6

SUMMARY OF ISSUES AND FINDINGSSUMMARY OF ISSUES AND FINDINGS

GEOTECHNICAL FACTORS

Dump formed over springs, lead to softening of the toe.Dumped materials a mixture of rock, coal slurry and water.High moisture content of dump material lead to liquefaction.Failure took a few minutes.

CONCLUSIONS OF INQUIRY

“…the Aberfan Disaster is a terrifying tale of bungling ineptitude by many men charged with tasks for which they were totally unfitted, and of total lack of direction from above. Not villains but decent men, led astray by foolishness or by ignorance or by both in combination, are responsible for what happened at Aberfan.”

Pells

Sulli

van

Mey

n ink

THREDBO LANDSLIDE

1997

18 DEATHS

Pells

Sulli

van

Mey

n ink

LOCATION IN LOCATION IN THE VILLAGETHE VILLAGE

LANDSLIDE MASSLANDSLIDE MASSONLY 1300 mONLY 1300 m³³

Pells

Sulli

van

Mey

n ink

VIEW OF TOP OF SLIDEVIEW OF TOP OF SLIDE

Pells

Sulli

van

Mey

n ink

MUDFLOW THROUGH THE LODGESMUDFLOW THROUGH THE LODGES

Pells

Sulli

van

Mey

n ink

“LOST FORGOTTEN OR IGNORED”

Over 40 year history of similar but infrequent slides in the area.

Site originally classified as “unstable and unbuildable”

Loose dumped fill at 40° over an old landslide.

High pressure water pipeline – Asbestos cement with simple push couplings– Approved and constructed through the site.

Pells

Sulli

van

Mey

n ink

Page 10: 2007 MITSUBISHI LECTURE · 1 2007 MITSUBISHI LECTURE PART 2 CASE STUDIES Pells Sullivan Meynink CASE EXAMPLES “…slopes seldom fail without giving adequate warning” (Hoek and

1

2007 MITSUBISHI LECTURE2007 MITSUBISHI LECTURE

Part 3 Large Blocky Failures

HighwallsAnd

Benches

Pells Sullivan Meynink Pells

Sulli

van

Mey

n ink

CARTENGA COAL MINE COLUMBIACARTENGA COAL MINE COLUMBIA

Pells

Sulli

van

Mey

n ink

DRAGLINE SPOIL DUMP

BRIDGE

Pells

Sulli

van

Mey

n ink

LOADERLOADER

Pells

Sulli

van

Mey

n ink

Pells

Sulli

van

Mey

n ink

Pells

Sulli

van

Mey

n ink

?

Pells

Sulli

van

Mey

n ink

TOE OF FAILURETOE OF FAILURE

Pells

Sulli

van

Mey

n ink

Pells

Sulli

van

Mey

n ink

OVERALL VIEW OF HIGHWALL FAILUREOVERALL VIEW OF HIGHWALL FAILURE

Pells

Sulli

van

Mey

n ink

Page 11: 2007 MITSUBISHI LECTURE · 1 2007 MITSUBISHI LECTURE PART 2 CASE STUDIES Pells Sullivan Meynink CASE EXAMPLES “…slopes seldom fail without giving adequate warning” (Hoek and

2

Pells

Sulli

van

Mey

n ink

GEOLOGICAL SETTING GEOLOGICAL SETTING UNDERCUTTING A DIP SLOPEUNDERCUTTING A DIP SLOPE

Pells

Sulli

van

Mey

n ink

10º

UNDERCUT HIGHWALL

Pells

Sulli

van

Mey

n ink

Mt. KEITH OVERALL SETTING Mt. KEITH OVERALL SETTING -- CUTBACKCUTBACK

Pells

Sulli

van

Mey

n ink

HAUL ROAD ON OUTSIDE OF CUTBACK

Pells

Sulli

van

Mey

n ink

TRUCK IN WATERTRUCK IN WATER

Pells

Sulli

van

Mey

n ink

Pells

Sulli

van

Mey

n ink

ROCK MASS FABRIC IN CUTBACKROCK MASS FABRIC IN CUTBACK

Pells

Sulli

van

Mey

n ink

DAYLIGHTING PLANES

SLOPE AT THE LIMIT WITH STRUCTURE PARALLEL OR DAYLIGHTING

CONTINUOUS ROCK STRUCTURE FABRIC

Pells

Sulli

van

Mey

n ink

CLOSE UP OF ROCK FABRICCLOSE UP OF ROCK FABRIC

Pells

Sulli

van

Mey

n ink

“SMOOTH” INFILLED JOINTS

Pells

Sulli

van

Mey

n ink

ROCK MASS FABRICROCK MASS FABRIC

Pells

Sulli

van

Mey

n ink

REAR RELEASEPLANES

Page 12: 2007 MITSUBISHI LECTURE · 1 2007 MITSUBISHI LECTURE PART 2 CASE STUDIES Pells Sullivan Meynink CASE EXAMPLES “…slopes seldom fail without giving adequate warning” (Hoek and

3

Pells

Sulli

van

Mey

n ink

SHEAR ALONG JOINT PLANESSHEAR ALONG JOINT PLANES

Pells

Sulli

van

Mey

n ink

SHEAR AND DILATION ON MAJOR PLANES

Pells

Sulli

van

Mey

n ink

PREVIOUS FAILURE OF SAME TYPE IN THE PREVIOUS FAILURE OF SAME TYPE IN THE SAME SLOPE AT HIGHER ELEVATION ALSO SAME SLOPE AT HIGHER ELEVATION ALSO

AFFECTING HAUL ROADAFFECTING HAUL ROAD

Pells

Sulli

van

Mey

n ink

HAUL ROAD RE-ROUTED

PREVIOUS

NEW

Pells

Sulli

van

Mey

n ink

TRITRI--STAR COAL MINE STAR COAL MINE MARYLAND USAMARYLAND USA

1717THTH April 2007 April 2007 –– 2 killed2 killed

Pells

Sulli

van

Mey

n ink

Pells

Sulli

van

Mey

n ink

OVERALL OVERALL VIEW OF VIEW OF

HIGHWALL HIGHWALL COLLAPSECOLLAPSE

Pells

Sulli

van

Mey

n inkBULLDOZER AND

BACKHOE BURIED

Pells

Sulli

van

Mey

n ink

KIDSTON KIDSTON –– OVERALL VIEWOVERALL VIEW

Pells

Sulli

van

Mey

n ink

CABLE BOLTED FOOTWALL STEEPENED BELOW HAUL ROAD Pe

llsSu

lliva

nM

eyn i

nk

PREPRE--SPLIT DRILL RIG SPLIT DRILL RIG DRILLING SECOND LIFT OF TRIPLE BENCHDRILLING SECOND LIFT OF TRIPLE BENCH

Pells

Sulli

van

Mey

n ink

Failure plane and collapseDrill rig located here

Page 13: 2007 MITSUBISHI LECTURE · 1 2007 MITSUBISHI LECTURE PART 2 CASE STUDIES Pells Sullivan Meynink CASE EXAMPLES “…slopes seldom fail without giving adequate warning” (Hoek and

4

Pells

Sulli

van

Mey

n ink

CHARACTER OF FAILURE PLANECHARACTER OF FAILURE PLANE

Pells

Sulli

van

Mey

n ink

Pells

Sulli

van

Mey

n ink

HOLES HALF FULL OF GROUT AND CABLES HOLES HALF FULL OF GROUT AND CABLES NOT GROUTEDNOT GROUTED

Pells

Sulli

van

Mey

n ink

Pells

Sulli

van

Mey

n ink

COAL MINECOAL MINE

Pells

Sulli

van

Mey

n ink

UNCONTROLLED PLACEMENT OF UNCONTROLLED PLACEMENT OF WET TERTIARY IN DUMPWET TERTIARY IN DUMP

Pells

Sulli

van

Mey

n ink

EQUIPMENT EQUIPMENT DAMAGEDAMAGE

Pells

Sulli

van

Mey

n ink

LOSS OF PRODUCTIONLOSS OF PRODUCTION

Page 14: 2007 MITSUBISHI LECTURE · 1 2007 MITSUBISHI LECTURE PART 2 CASE STUDIES Pells Sullivan Meynink CASE EXAMPLES “…slopes seldom fail without giving adequate warning” (Hoek and

5

Pells

Sulli

van

Mey

n ink

LOSS OF DRAGLINE? LOSS OF DRAGLINE? AND PRODUCTION LOSSESAND PRODUCTION LOSSES

Pells

Sulli

van

Mey

n ink

LAWLERS GOLD MINELAWLERS GOLD MINE -- FAIRYLAND PITFAIRYLAND PIT

BATTER SCALE FAILURE -27th January 2003 – FATALITY

Catastrophic failure of a portion of the western wall of the Fairyland open pit occurred near an excavator that was digging and loading ore into haul trucks. An ore control technician directing the activities of the excavator was fatally injured when buried under the rockfall.

Immediate suspension of mining and mobilisation of the Mine Rescue Team. Notification of all relevant authorities. An investigation by the Western Australian Police commenced immediately and by the Department of Mineral and Petroleum Resources early the next day. Nature of the failure prevented immediate rescue attempts. Recovery of the body 41 hours after the event

Earlier inspection of the wall shortly before the event by a geotechnical consultant and other staff gave no indication that failure was imminent.

Cause; proximity to pit wall.

Pells

Sulli

van

Mey

n ink

Pells

Sulli

van

Mey

n ink

LOCATION OF FAILURELOCATION OF FAILURE

Pells

Sulli

van

Mey

n ink

Page 15: 2007 MITSUBISHI LECTURE · 1 2007 MITSUBISHI LECTURE PART 2 CASE STUDIES Pells Sullivan Meynink CASE EXAMPLES “…slopes seldom fail without giving adequate warning” (Hoek and

1

2007 MITSUBISHI LECTURE2007 MITSUBISHI LECTURE

Part 4Rockfall Issues

AndConclusions

Pells Sullivan Meynink

MantosMantos

Pells

Sulli

van

Mey

n ink

Diagrama de sucesos

Accidente Fatal29 de octubre de 2003

Operaciones Mina Rajo AbiertoDivisión Mantos Blancos

Zona de probable Zona de probable desprendimiento de la desprendimiento de la

roca.roca.

Berma que delimita distanciaBerma que delimita distanciapara interactuar con elpara interactuar con el

talud del sector.talud del sector.

Talud 37Talud 37°° de pendiente.de pendiente.

Cargador Frontal 8703,Cargador Frontal 8703,operado por Jorge Campos,operado por Jorge Campos,a quien se le iba a entregara quien se le iba a entregar

el material de limpieza.el material de limpieza.

Imagen frontal del sector del suceso.

PosiciPosicióón final den final deCamioneta siniestradaCamioneta siniestrada

Imagen tomada desde el banco 780 hacia el banco 756.

Barra de perforaciBarra de perforacióón, con n, con 6 metros de avance 6 metros de avance aproximadamente.aproximadamente.

Berma que delimita el Berma que delimita el acecamientoacecamiento a la zona de a la zona de

riesgo identificado.riesgo identificado.

Imagen tomada desde el banco 756.

Page 16: 2007 MITSUBISHI LECTURE · 1 2007 MITSUBISHI LECTURE PART 2 CASE STUDIES Pells Sullivan Meynink CASE EXAMPLES “…slopes seldom fail without giving adequate warning” (Hoek and

2

45 45 mtmt..25 25 mtmt..

Distancias de la camioneta hasta el talud y berma delimitadora de distancia.

Imagen tomada en el banco 684, sector del incidente.

Fragmentos de la roca.Fragmentos de la roca.

Fragmentos de la roca.Fragmentos de la roca.

Imagen tomada en el banco 684, sector del incidente.

Zona del impacto directo Zona del impacto directo de la roca en la camioneta.de la roca en la camioneta.

Imagen tomada en el banco 684, sector del incidente.

22°° zona de impacto de la zona de impacto de la roca (cabina)roca (cabina)

Zona de posiciZona de posicióón final de la n final de la roca.roca.

Page 17: 2007 MITSUBISHI LECTURE · 1 2007 MITSUBISHI LECTURE PART 2 CASE STUDIES Pells Sullivan Meynink CASE EXAMPLES “…slopes seldom fail without giving adequate warning” (Hoek and

3

SMALL RAVELLING FAILURESMALL RAVELLING FAILUREEVEN SMALL ROCKS CAN BE A PROBLEMEVEN SMALL ROCKS CAN BE A PROBLEM

Pells

Sulli

van

Mey

n ink

RESULTANT VEHICLE DAMAGERESULTANT VEHICLE DAMAGE

Pells

Sulli

van

Mey

n ink

PLACEMENT OF PLACEMENT OF SUMPS AND PUMPS SUMPS AND PUMPS

CONTROL OF CONTROL OF PERSONNEL PERSONNEL

ACCESSACCESS

Pells

Sulli

van

Mey

n ink

PROCEDURES AND CONTROLS FOR LIGHT PROCEDURES AND CONTROLS FOR LIGHT VEHICLE ACCESSVEHICLE ACCESS

Pells

Sulli

van

Mey

n ink

LARGE EXCAVATING EQUIPMENTLARGE EXCAVATING EQUIPMENTUSUALLY A PRODUCTION ISSUEUSUALLY A PRODUCTION ISSUE

Pells

Sulli

van

Mey

n ink

LARGE EXCAVATING EQUIPMENTLARGE EXCAVATING EQUIPMENTUSUALLY A PRODUCTION ISSUEUSUALLY A PRODUCTION ISSUE

BUT IT DEPENDS ON CIRCUMSTANCESBUT IT DEPENDS ON CIRCUMSTANCES

Pells

Sulli

van

Mey

n ink

Page 18: 2007 MITSUBISHI LECTURE · 1 2007 MITSUBISHI LECTURE PART 2 CASE STUDIES Pells Sullivan Meynink CASE EXAMPLES “…slopes seldom fail without giving adequate warning” (Hoek and

4

FIXED INFRASTRUCTUREFIXED INFRASTRUCTURE

Pells

Sulli

van

Mey

n ink

OPERATOR ESCAPED UNINJUREDOPERATOR ESCAPED UNINJURED

Pells

Sulli

van

Mey

n ink

ROCKFALLROCKFALL-- WHO IS AT RISK?WHO IS AT RISK?

Pells

Sulli

van

Mey

n ink

ANCILLARY EQUIPMENT ?ANCILLARY EQUIPMENT ?

Pells

Sulli

van

Mey

n ink

LOCATION OF SUMPS AND ANCILLARY LOCATION OF SUMPS AND ANCILLARY EQUIPMENT, ACCESS ON FOOT? EQUIPMENT, ACCESS ON FOOT?

Pells

Sulli

van

Mey

n ink

Sump & pump location? Character of highwall ?

OPERATORS AND LIGHT VEHICLES ?OPERATORS AND LIGHT VEHICLES ?

Pells

Sulli

van

Mey

n ink

Page 19: 2007 MITSUBISHI LECTURE · 1 2007 MITSUBISHI LECTURE PART 2 CASE STUDIES Pells Sullivan Meynink CASE EXAMPLES “…slopes seldom fail without giving adequate warning” (Hoek and

5

SLOPE FORM EXACERBATES ROCK FALL SLOPE FORM EXACERBATES ROCK FALL PROBLEMS PROBLEMS –– NO EFFECTIVE BENCHESNO EFFECTIVE BENCHES

Pells

Sulli

van

Mey

n ink

STEEP BENCH SLOPESSTEEP BENCH SLOPESPOTENTIAL FOR SUDDEN FAILUREPOTENTIAL FOR SUDDEN FAILURE

Pells

Sulli

van

Mey

n ink

ROCK FALL FENCESROCK FALL FENCESFALSE SECURITY ?FALSE SECURITY ?

Pells

Sulli

van

Mey

n ink

ACCESS CONTROLS ACCESS CONTROLS

Pells

Sulli

van

Mey

n ink

IMPORTANCE OF PROCEDURES AND IMPORTANCE OF PROCEDURES AND CONTROLSCONTROLS

Pells

Sulli

van

Mey

n ink

LARGER SCALE WALL FAILURES CONTRIBUTING FACTORSFATALITIES AND SERIOUS INJURY INCIDENTS

•••Slope failure onto mine personnel

?•••Large pit wall failure 1

?••Highwall failure onto equipment

•••••Failure leads to mudflow

•••••Failure undercuts equipment 1

••Loss of equipment over pit edge

••••Large pit wall failure

••Failure onto pre-split drilling rig

Inadequate Control of

Access

Inadequate Control of

Excavation

Poor Understanding of Significance of Monitoring

Failure to Appreciate

Post Failure Deformation

Failure to Appreciate

Role of Water

Risky Geological / Geotechnical

Setting Or Design Too

Steep

Inadequate Implementation of

Design

Poor Pit Design

Element

FAILURE TO HEED

EXPLICIT WARNINGS

CONTROL OF INPIT ACCESS AND EXCAVATION

GEOTECHNICAL ISSUESPIT DESIGN ISSUES

INCIDENT

Note 1 Failure to appreciate significance of previous incident (history)

• Principal Factor or Concern• Minor Factor or Concern

Page 20: 2007 MITSUBISHI LECTURE · 1 2007 MITSUBISHI LECTURE PART 2 CASE STUDIES Pells Sullivan Meynink CASE EXAMPLES “…slopes seldom fail without giving adequate warning” (Hoek and

6

LARGER SCALE FAILURESLARGER SCALE FAILURES

Pells

Sulli

van

Mey

n ink

The contributing factors in order of decreasing frequency:– Geotechnical Issues – 14 cases.– Access, Procedures and Controls – 3 cases.– Warnings Ignored – 2 cases.– Open Cut Design Issues,

including implementation of design – 2 cases.

Important conclusions are:

1. The overriding influence of geotechnical issues in these serious larger scale failures.

2. The concern that specific warnings apparently went unheeded in two of the cases.

ROCKFALL CONTRIBUTING FACTORS TO FATALITIES AND SERIOUS NEAR MISSES

••Rockfall onto drill

••Rockfall onto truck and excavator

•Rockfall hits light vehicle

•••Ravelling rockfall on light vehicle

••Rockfall through Windscreen

•Bench failure and rockfall

•••••Rockfall below Cutback

•Rockfall below Cutback

•Rockfall below Cutback

Inadequate Separation

between Unstable Area

and Access

Location of Sumps,

Pumps and Ancillary Services

Inadequate Awareness and Access

Controls

Poor Control of Cutback

Excavation

Berm Loss

Poor Blasting Practices

Inadequate Support of Poor Rock Mass Zone

Slope too Steep for

Geotechnical Conditions

Inadequate Catch Fence

Design

ACCESS PROCEDURES AND CONTROLSEXCAVATION PRACTICESDESIGN ISSUES

INCIDENT

SMALLER ROCK FALLSSMALLER ROCK FALLS

Pells

Sulli

van

Mey

n ink

The main issues from the rockfall examples are:

1. Not possible to stop rockfall in mining environment.

1. 2. Identification of rockfall areas is essential.

2. 3. Education and awareness throughout the workforce is essential.

3. 4. Protocols required for what to do in the event of rockfall.

4. 5. Control of access by personnel and smaller ancillary equipment into risk areas is essential.

5. 6. The placement of ancillary items of infrastructure such as sumps, pumps, etc. requires careful consideration.

6. 7. Adequate separation between areas actively generating potential instability, such as cutbacks, and areas of general access is mandatory.

SLOPE DESIGN ELEMENTSSLOPE DESIGN ELEMENTS

Pells

Sulli

van

Mey

n ink

DEEP OPEN CUT MINE SLOPE DESIGN ELEMENTS AND RISK AREAS

•1•Height

•1••Angle

OVERALL

•1•Height

•1••Angle

INTER-RAMP

•••••Berm Width

•••••Height

•••••Angle

BENCHGEOMETRY

EconomicsSafetyEnvironmental FactorsMining SystemsGeotechnical

Issues

RISK AREAMAIN CONTROLLING ORINFLUENCING FACTOR

COMPONENTSLOPE DESIGN ELEMENT

• Principal factor or main concern• Minor factor or concernNotes: 1 Assumes a sound Pit Slope Management Procedure is in place.

Pells

Sulli

van

Mey

n ink

SLOPE DESIGN ELEMENTSSLOPE DESIGN ELEMENTS

Pells

Sulli

van

Mey

n ink

Page 21: 2007 MITSUBISHI LECTURE · 1 2007 MITSUBISHI LECTURE PART 2 CASE STUDIES Pells Sullivan Meynink CASE EXAMPLES “…slopes seldom fail without giving adequate warning” (Hoek and

7

SHALLOW OPEN CUT DRAGLINE MINESLOPE DESIGN ELEMENTS AND RISK AREAS

•••Angle(mid light berm)

•••Height

SPOIL DUMP

•••Angle 1LOW WALL

••••Height

••••Angle

HIGHWALL

EconomicsSafetyMining EquipmentalSystemsGeotechnical Issues

RISK AREACONTROLLING ORINFLUENCING FACTOR

COMPONENTSLOPE DESIGN ELEMENT

1 It is assumed the location and hence height are defined by the LOX line and hence this element is fixed

Pells

Sulli

van

Mey

n ink

LESSONS LARGE FAILURESLESSONS LARGE FAILURES

Pells

Sulli

van

Mey

n ink

Role of HISTORY.

Importance of overall GEOLOGICAL SETTING.

Experience with MOVING SLOPES.

Critical role of pore pressure responses.

Understanding POST FAILURE BEHAVIOUR ANDDEFORMATIONS.

Experience base used to predict future performance, is it adequate or appropriate?

MONITORING must be right.

If the environment is different will the performance be the same; climate, stress, blasting?

LESSONS FROM SMALLER LESSONS FROM SMALLER FAILURESFAILURES

Potential risks at all scales.

Not feasible to completely remove the risk.

Those most at risk are people on foot, ancillary equipment and light vehicles.

Importance of:

AWARENESS, PROCEDURES and CONTROLS.

Pells

Sulli

van

Mey

n ink