2007 casesROBERTO C

212
ROBERTO C. SICAM and AGENCIA G.R. NO. 159617 de R.C. SICAM, INC., Petitioners, Present: YNARES-SANTIAGO, J., Chairperson, - versus - AUSTRIA- MARTINEZ, CHICO-NAZARIO, and NACHURA, JJ. LULU V. JORGE and CESAR JORGE, Promulgated: Respondents. August 8, 2007 x- - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - x D E C I S I O N

Transcript of 2007 casesROBERTO C

Page 1: 2007 casesROBERTO C

ROBERTO C. SICAM and AGENCIA G.R. NO. 159617de R.C. SICAM, INC.,

Petitioners,Present:

YNARES-SANTIAGO, J., Chairperson,

- versus - AUSTRIA-MARTINEZ,CHICO-NAZARIO, andNACHURA, JJ.

LULU V. JORGE and CESARJORGE, Promulgated:

Respondents. August 8, 2007x- - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - x

D E C I S I O N

AUSTRIA-MARTINEZ, J.:

Before us is a Petition for Review on Certiorari filed by Roberto C.

Sicam, Jr. (petitioner Sicam) and Agencia de R.C. Sicam, Inc. (petitioner

corporation) seeking to annul the Decision1[1] of the Court of Appeals dated

1

Page 2: 2007 casesROBERTO C

March 31, 2003, and its Resolution2[2] dated August 8, 2003, in CA G.R. CV

No. 56633.

It appears that on different dates from September to October 1987,

Lulu V. Jorge (respondent Lulu) pawned several pieces of jewelry with

Agencia de R. C. Sicam located at No. 17 Aguirre Ave., BF Homes

Parañaque, Metro Manila, to secure a loan in the total amount of P59,500.00.

On October 19, 1987, two armed men entered the pawnshop and took

away whatever cash and jewelry were found inside the pawnshop vault. The

incident was entered in the police blotter of the Southern Police District,

Parañaque Police Station as follows:

Investigation shows that at above TDPO, while victims were inside the office, two (2) male unidentified persons entered into the said office with guns drawn. Suspects(sic) (1) went straight inside and poked his gun toward Romeo Sicam and thereby tied him with an electric wire while suspects (sic) (2) poked his gun toward Divina Mata and Isabelita Rodriguez and ordered them to lay (sic) face flat on the floor. Suspects asked forcibly the case and assorted pawned jewelries items mentioned above.

Suspects after taking the money and jewelries fled on board a Marson Toyota unidentified plate number.3[3]

Petitioner Sicam sent respondent Lulu a letter dated October 19, 1987

informing her of the loss of her jewelry due to the robbery incident in the

pawnshop. On November 2, 1987, respondent Lulu then wrote a letter4[4] to

petitioner Sicam expressing disbelief stating that when the robbery

2

3

4

Page 3: 2007 casesROBERTO C

happened, all jewelry pawned were deposited with Far East Bank near the

pawnshop since it had been the practice that before they could withdraw,

advance notice must be given to the pawnshop so it could withdraw the

jewelry from the bank. Respondent Lulu then requested petitioner Sicam to

prepare the pawned jewelry for withdrawal on November 6, 1987 but

petitioner Sicam failed to return the jewelry.

On September 28, 1988, respondent Lulu joined by her husband,

Cesar Jorge, filed a complaint against petitioner Sicam with the Regional

Trial Court of Makati seeking indemnification for the loss of pawned

jewelry and payment of actual, moral and exemplary damages as well as

attorney's fees. The case was docketed as Civil Case No. 88-2035.

Petitioner Sicam filed his Answer contending that he is not the real

party-in-interest as the pawnshop was incorporated on April 20, 1987 and

known as Agencia de R.C. Sicam, Inc; that petitioner corporation had

exercised due care and diligence in the safekeeping of the articles pledged

with it and could not be made liable for an event that is fortuitous.

Respondents subsequently filed an Amended Complaint to include

petitioner corporation.

Thereafter, petitioner Sicam filed a Motion to Dismiss as far as he is

concerned considering that he is not the real party-in-interest. Respondents

opposed the same. The RTC denied the motion in an Order dated November

Page 4: 2007 casesROBERTO C

8, 1989.5[5]

After trial on the merits, the RTC rendered its Decision6[6] dated

January 12, 1993, dismissing respondents’ complaint as well as petitioners’

counterclaim. The RTC held that petitioner Sicam could not be made

personally liable for a claim arising out of a corporate transaction; that in

the Amended Complaint of respondents, they asserted that “plaintiff pawned

assorted jewelries in defendants' pawnshop”; and that as a consequence of

the separate juridical personality of a corporation, the corporate debt or

credit is not the debt or credit of a stockholder.

The RTC further ruled that petitioner corporation could not be held

liable for the loss of the pawned jewelry since it had not been rebutted by

respondents that the loss of the pledged pieces of jewelry in the possession

of the corporation was occasioned by armed robbery; that robbery is a

fortuitous event which exempts the victim from liability for the loss, citing

the case of Austria v. Court of Appeals;7[7] and that the parties’ transaction

was that of a pledgor and pledgee and under Art. 1174 of the Civil Code,

the pawnshop as a pledgee is not responsible for those events which could

not be foreseen.

Respondents appealed the RTC Decision to the CA. In a Decision

dated March 31, 2003, the CA reversed the RTC, the dispositive portion of

which reads as follows:

5

6

7

Page 5: 2007 casesROBERTO C

WHEREFORE, premises considered, the instant Appeal is GRANTED, and the Decision dated January 12, 1993,of the Regional Trial Court of Makati, Branch 62, is hereby REVERSED and SET ASIDE, ordering the appellees to pay appellants the actual value of the lost jewelry amounting to P272,000.00, and attorney' fees of P27,200.00.8[8]

In finding petitioner Sicam liable together with petitioner corporation,

the CA applied the doctrine of piercing the veil of corporate entity reasoning

that respondents were misled into thinking that they were dealing with the

pawnshop owned by petitioner Sicam as all the pawnshop tickets issued to

them bear the words “Agencia de R.C. Sicam”; and that there was no

indication on the pawnshop tickets that it was the petitioner corporation that

owned the pawnshop which explained why respondents had to amend their

complaint impleading petitioner corporation.

The CA further held that the corresponding diligence required of a

pawnshop is that it should take steps to secure and protect the pledged items

and should take steps to insure itself against the loss of articles which are

entrusted to its custody as it derives earnings from the pawnshop trade which

petitioners failed to do; that Austria is not applicable to this case since the

robbery incident happened in 1961 when the criminality had not as yet

reached the levels attained in the present day; that they are at least guilty of

contributory negligence and should be held liable for the loss of jewelries;

and that robberies and hold-ups are foreseeable risks in that those engaged in

the pawnshop business are expected to foresee.

The CA concluded that both petitioners should be jointly and

severally held liable to respondents for the loss of the pawned jewelry.8

Page 6: 2007 casesROBERTO C

Petitioners’ motion for reconsideration was denied in a Resolution

dated August 8, 2003.

Hence, the instant petition for review with the following assignment

of errors:

THE COURT OF APPEALS ERRED AND WHEN IT DID, IT OPENED ITSELF TO REVERSAL, WHEN IT ADOPTED UNCRITICALLY (IN FACT IT REPRODUCED AS ITS OWN WITHOUT IN THE MEANTIME ACKNOWLEDGING IT) WHAT THE RESPONDENTS ARGUED IN THEIR BRIEF, WHICH ARGUMENT WAS PALPABLY UNSUSTAINABLE.

THE COURT OF APPEALS ERRED, AND WHEN IT DID, IT OPENED ITSELF TO REVERSAL BY THIS HONORABLE COURT, WHEN IT AGAIN ADOPTED UNCRITICALLY (BUT WITHOUT ACKNOWLEDGING IT) THE SUBMISSIONS OF THE RESPONDENTS IN THEIR BRIEF WITHOUT ADDING ANYTHING MORE THERETO DESPITE THE FACT THAT THE SAID ARGUMENT OF THE RESPONDENTS COULD NOT HAVE BEEN SUSTAINED IN VIEW OF UNREBUTTED EVIDENCE ON RECORD.9

[9]

Anent the first assigned error, petitioners point out that the CA’s

finding that petitioner Sicam is personally liable for the loss of the pawned

jewelries is “a virtual and uncritical reproduction of the arguments set out on

pp. 5-6 of the Appellants’ brief.”10[10]

Petitioners argue that the reproduced arguments of respondents in

their Appellants’ Brief suffer from infirmities, as follows:

9

10

Page 7: 2007 casesROBERTO C

(1) Respondents conclusively asserted in paragraph 2 of their Amended Complaint that Agencia de R.C. Sicam, Inc. is the present owner of Agencia de R.C. Sicam Pawnshop, and therefore, the CA cannot rule against said conclusive assertion of respondents;

(2) The issue resolved against petitioner Sicam was not among those raised and litigated in the trial court; and

(3) By reason of the above infirmities, it was error for the CA to have pierced the corporate veil since a corporation has a personality distinct and separate from its individual stockholders or members.

Anent the second error, petitioners point out that the CA finding on

their negligence is likewise an unedited reproduction of respondents’ brief

which had the following defects:

(1) There were unrebutted evidence on record that petitioners had observed the diligence required of them, i.e, they wanted to open a vault with a nearby bank for purposes of safekeeping the pawned articles but was discouraged by the Central Bank (CB) since CB rules provide that they can only store the pawned articles in a vault inside the pawnshop premises and no other place;

(2) Petitioners were adjudged negligent as they did not take insurance against the loss of the pledged jelweries, but it is judicial notice that due to high incidence of crimes, insurance companies refused to cover pawnshops and banks because of high probability of losses due to robberies;

(3) In Hernandez v. Chairman, Commission on Audit (179 SCRA 39, 45-46), the victim of robbery was exonerated from liability for the sum of money belonging to others and lost by him to robbers.

Respondents filed their Comment and petitioners filed their Reply

thereto. The parties subsequently submitted their respective Memoranda.

We find no merit in the petition.

Page 8: 2007 casesROBERTO C

To begin with, although it is true that indeed the CA findings were

exact reproductions of the arguments raised in respondents’ (appellants’)

brief filed with the CA, we find the same to be not fatally infirmed. Upon

examination of the Decision, we find that it expressed clearly and distinctly

the facts and the law on which it is based as required by Section 8, Article

VIII of the Constitution. The discretion to decide a case one way or another

is broad enough to justify the adoption of the arguments put forth by one of

the parties, as long as these are legally tenable and supported by law and the

facts on records.11[11]

Our jurisdiction under Rule 45 of the Rules of Court is limited to the

review of errors of law committed by the appellate court. Generally, the

findings of fact of the appellate court are deemed conclusive and we are not

duty-bound to analyze and calibrate all over again the evidence adduced by

the parties in the court a quo.12[12] This rule, however, is not without

exceptions, such as where the factual findings of the Court of Appeals and

the trial court are conflicting or contradictory13[13] as is obtaining in the

instant case.

However, after a careful examination of the records, we find no

justification to absolve petitioner Sicam from liability.

The CA correctly pierced the veil of the corporate fiction and

adjudged petitioner Sicam liable together with petitioner corporation. The

rule is that the veil of corporate fiction may be pierced when made as a

11

12

13

Page 9: 2007 casesROBERTO C

shield to perpetrate fraud and/or confuse legitimate issues. 14[14] The theory of

corporate entity was not meant to promote unfair objectives or otherwise to

shield them.15[15]

Notably, the evidence on record shows that at the time respondent

Lulu pawned her jewelry, the pawnshop was owned by petitioner Sicam

himself. As correctly observed by the CA, in all the pawnshop receipts

issued to respondent Lulu in September 1987, all bear the words “Agencia

de R. C. Sicam,” notwithstanding that the pawnshop was allegedly

incorporated in April 1987. The receipts issued after such alleged

incorporation were still in the name of “Agencia de R. C. Sicam,” thus

inevitably misleading, or at the very least, creating the wrong impression to

respondents and the public as well, that the pawnshop was owned solely by

petitioner Sicam and not by a corporation.

Even petitioners’ counsel, Atty. Marcial T. Balgos, in his letter16[16]

dated October 15, 1987 addressed to the Central Bank, expressly referred to

petitioner Sicam as the proprietor of the pawnshop notwithstanding the

alleged incorporation in April 1987.

We also find no merit in petitioners' argument that since respondents

had alleged in their Amended Complaint that petitioner corporation is the

present owner of the pawnshop, the CA is bound to decide the case on that

basis.

14

15

16

Page 10: 2007 casesROBERTO C

Section 4 Rule 129 of the Rules of Court provides that an admission,

verbal or written, made by a party in the course of the proceedings in the

same case, does not require proof. The admission may be contradicted only

by showing that it was made through palpable mistake or that no such

admission was made.

Thus, the general rule that a judicial admission is conclusive upon the

party making it and does not require proof, admits of two exceptions, to wit:

(1) when it is shown that such admission was made through palpable

mistake, and (2) when it is shown that no such admission was in fact made.

The latter exception allows one to contradict an admission by denying

that he made such an admission.17[17]

The Committee on the Revision of the Rules of Court explained the

second exception in this wise:

x x x if a party invokes an “admission” by an adverse party, but cites the admission “out of context,” then the one making the “admission” may show that he made no “such” admission, or that his admission was taken out of context.

x x x that the party can also show that he made no “such admission”, i.e., not in the sense in which the admission is made to appear.

That is the reason for the modifier “such” because if the rule simply states that the admission may be contradicted by showing that “no admission was made,” the rule would not really be providing for a contradiction of the admission but just a denial.18[18] (Emphasis supplied).

While it is true that respondents alleged in their Amended Complaint

that petitioner corporation is the present owner of the pawnshop, they did so

17

18

Page 11: 2007 casesROBERTO C

only because petitioner Sicam alleged in his Answer to the original

complaint filed against him that he was not the real party-in-interest as the

pawnshop was incorporated in April 1987. Moreover, a reading of the

Amended Complaint in its entirety shows that respondents referred to both

petitioner Sicam and petitioner corporation where they (respondents)

pawned their assorted pieces of jewelry and ascribed to both the failure to

observe due diligence commensurate with the business which resulted in the

loss of their pawned jewelry.

Markedly, respondents, in their Opposition to petitioners’ Motion to

Dismiss Amended Complaint, insofar as petitioner Sicam is concerned,

averred as follows:

Roberto C. Sicam was named the defendant in the original complaint because the pawnshop tickets involved in this case did not show that the R.C. Sicam Pawnshop was a corporation. In paragraph 1 of his Answer, he admitted the allegations in paragraph 1 and 2 of the Complaint. He merely added “that defendant is not now the real party in interest in this case.”

It was defendant Sicam's omission to correct the pawnshop tickets used in the subject transactions in this case which was the cause of the instant action. He cannot now ask for the dismissal of the complaint against him simply on the mere allegation that his pawnshop business is now incorporated. It is a matter of defense, the merit of which can only be reached after consideration of the evidence to be presented in due course.19

[19]

Unmistakably, the alleged admission made in respondents' Amended

Complaint was taken “out of context” by petitioner Sicam to suit his own

purpose. Ineluctably, the fact that petitioner Sicam continued to issue

pawnshop receipts under his name and not under the corporation's name

19

Page 12: 2007 casesROBERTO C

militates for the piercing of the corporate veil.

We likewise find no merit in petitioners' contention that the CA erred

in piercing the veil of corporate fiction of petitioner corporation, as it was

not an issue raised and litigated before the RTC.

Petitioner Sicam had alleged in his Answer filed with the trial court

that he was not the real party-in-interest because since April 20, 1987, the

pawnshop business initiated by him was incorporated and known as Agencia

de R.C. Sicam. In the pre-trial brief filed by petitioner Sicam, he submitted

that as far as he was concerned, the basic issue was whether he is the real

party in interest against whom the complaint should be directed.20[20] In fact,

he subsequently moved for the dismissal of the complaint as to him but was

not favorably acted upon by the trial court. Moreover, the issue was squarely

passed upon, although erroneously, by the trial court in its Decision in this

manner:

x x x The defendant Roberto Sicam, Jr likewise denies liability as far as he is concerned for the reason that he cannot be made personally liable for a claim arising from a corporate transaction.

This Court sustains the contention of the defendant Roberto C. Sicam, Jr. The amended complaint itself asserts that “plaintiff pawned assorted jewelries in defendant's pawnshop.” It has been held that “ as a consequence of the separate juridical personality of a corporation, the corporate debt or credit is not the debt or credit of the stockholder, nor is the stockholder's debt or credit that of a corporation.21[21]

Clearly, in view of the alleged incorporation of the pawnshop, the

issue of whether petitioner Sicam is personally liable is inextricably

20

21

Page 13: 2007 casesROBERTO C

connected with the determination of the question whether the doctrine of

piercing the corporate veil should or should not apply to the case.

The next question is whether petitioners are liable for the loss of the

pawned articles in their possession.

Petitioners insist that they are not liable since robbery is a fortuitous

event and they are not negligent at all.

We are not persuaded.

Article 1174 of the Civil Code provides:

Art. 1174. Except in cases expressly specified by the law, or when it is otherwise declared by stipulation, or when the nature of the obligation requires the assumption of risk, no person shall be responsible for those events which could not be foreseen or which, though foreseen, were inevitable.

Fortuitous events by definition are extraordinary events not

foreseeable or avoidable. It is therefore, not enough that the event should not

have been foreseen or anticipated, as is commonly believed but it must be

one impossible to foresee or to avoid. The mere difficulty to foresee the

happening is not impossibility to foresee the same. 22[22]

To constitute a fortuitous event, the following elements must concur:

(a) the cause of the unforeseen and unexpected occurrence or of the failure

of the debtor to comply with obligations must be independent of human will;

22

Page 14: 2007 casesROBERTO C

(b) it must be impossible to foresee the event that constitutes the caso

fortuito or, if it can be foreseen, it must be impossible to avoid; (c) the

occurrence must be such as to render it impossible for the debtor to fulfill

obligations in a normal manner; and, (d) the obligor must be free from any

participation in the aggravation of the injury or loss. 23[23]

The burden of proving that the loss was due to a fortuitous event rests

on him who invokes it.24[24] And, in order for a fortuitous event to exempt

one from liability, it is necessary that one has committed no negligence or

misconduct that may have occasioned the loss. 25[25]

It has been held that an act of God cannot be invoked to protect a

person who has failed to take steps to forestall the possible adverse

consequences of such a loss. One's negligence may have concurred with an

act of God in producing damage and injury to another; nonetheless, showing

that the immediate or proximate cause of the damage or injury was a

fortuitous event would not exempt one from liability. When the effect is

found to be partly the result of a person's participation -- whether by active

intervention, neglect or failure to act -- the whole occurrence is humanized

and removed from the rules applicable to acts of God. 26[26]

Petitioner Sicam had testified that there was a security guard in their

pawnshop at the time of the robbery. He likewise testified that when he

started the pawnshop business in 1983, he thought of opening a vault with

23

24

25

26

Page 15: 2007 casesROBERTO C

the nearby bank for the purpose of safekeeping the valuables but was

discouraged by the Central Bank since pawned articles should only be stored

in a vault inside the pawnshop. The very measures which petitioners had

allegedly adopted show that to them the possibility of robbery was not only

foreseeable, but actually foreseen and anticipated. Petitioner Sicam’s

testimony, in effect, contradicts petitioners’ defense of fortuitous event.

Moreover, petitioners failed to show that they were free from any

negligence by which the loss of the pawned jewelry may have been

occasioned.

Robbery per se, just like carnapping, is not a fortuitous event. It does

not foreclose the possibility of negligence on the part of herein petitioners.

In Co v. Court of Appeals,27[27] the Court held:

It is not a defense for a repair shop of motor vehicles to escape liability simply because the damage or loss of a thing lawfully placed in its possession was due to carnapping. Carnapping per se cannot be considered as a fortuitous event. The fact that a thing was unlawfully and forcefully taken from another's rightful possession, as in cases of carnapping, does not automatically give rise to a fortuitous event. To be considered as such, carnapping entails more than the mere forceful taking of another's property. It must be proved and established that the event was an act of God or was done solely by third parties and that neither the claimant nor the person alleged to be negligent has any participation. In accordance with the Rules of Evidence, the burden of proving that the loss was due to a fortuitous event rests on him who invokes it — which in this case is the private respondent. However, other than the police report of the alleged carnapping incident, no other evidence was presented by private respondent to the effect that the incident was not due to its fault. A police report of an alleged crime, to which only private respondent is privy, does not suffice to establish the carnapping. Neither does it prove that there was no fault on the part of private respondent notwithstanding the parties' agreement at the pre-trial that the car was carnapped. Carnapping does

27

Page 16: 2007 casesROBERTO C

not foreclose the possibility of fault or negligence on the part of private respondent.28[28]

Just like in Co, petitioners merely presented the police report of the

Parañaque Police Station on the robbery committed based on the report of

petitioners' employees which is not sufficient to establish robbery. Such

report also does not prove that petitioners were not at fault.

On the contrary, by the very evidence of petitioners, the CA did not

err in finding that petitioners are guilty of concurrent or contributory

negligence as provided in Article 1170 of the Civil Code, to wit:

Art. 1170. Those who in the performance of their obligations are guilty of fraud, negligence, or delay, and those who in any manner contravene the tenor thereof, are liable for damages.29[29]

Article 2123 of the Civil Code provides that with regard to pawnshops

and other establishments which are engaged in making loans secured by

pledges, the special laws and regulations concerning them shall be observed,

and subsidiarily, the provisions on pledge, mortgage and antichresis.

The provision on pledge, particularly Article 2099 of the Civil Code,

provides that the creditor shall take care of the thing pledged with the

diligence of a good father of a family. This means that petitioners must take

care of the pawns the way a prudent person would as to his own property.

In this connection, Article 1173 of the Civil Code further provides:

Art. 1173. The fault or negligence of the obligor consists in the

28

29

Page 17: 2007 casesROBERTO C

omission of that diligence which is required by the nature of the obligation and corresponds with the circumstances of the persons, of time and of the place. When negligence shows bad faith, the provisions of Articles 1171 and 2201, paragraph 2 shall apply.

If the law or contract does not state the diligence which is to be observed in the performance, that which is expected of a good father of a family shall be required. We expounded in Cruz v. Gangan30[30] that negligence is the omission

to do something which a reasonable man, guided by those considerations

which ordinarily regulate the conduct of human affairs, would do; or the

doing of something which a prudent and reasonable man would not do.31[31] It

is want of care required by the circumstances.

A review of the records clearly shows that petitioners failed to

exercise reasonable care and caution that an ordinarily prudent person would

have used in the same situation. Petitioners were guilty of negligence in the

operation of their pawnshop business. Petitioner Sicam testified, thus:

Court:

Q. Do you have security guards in your pawnshop?A. Yes, your honor.

Q. Then how come that the robbers were able to enter the premises when according to you there was a security guard?

A. Sir, if these robbers can rob a bank, how much more a pawnshop.

Q. I am asking you how were the robbers able to enter despite the fact that there was a security guard?

A. At the time of the incident which happened about 1:00 and 2:00 o'clock in the afternoon and it happened on a Saturday and everything was quiet in the area BF Homes Parañaque they pretended to pawn an article in the pawnshop, so one of my employees allowed him to come in and it was only when it was announced that it was a hold up.

30

31

Page 18: 2007 casesROBERTO C

Q. Did you come to know how the vault was opened?A. When the pawnshop is official (sic) open your honor the pawnshop is

partly open. The combination is off.

Q. No one open (sic) the vault for the robbers?A. No one your honor it was open at the time of the robbery.

Q. It is clear now that at the time of the robbery the vault was open the reason why the robbers were able to get all the items pawned to you inside the vault.

A. Yes sir.32[32]

revealing that there were no security measures adopted by petitioners in the

operation of the pawnshop. Evidently, no sufficient precaution and

vigilance were adopted by petitioners to protect the pawnshop from unlawful

intrusion. There was no clear showing that there was any security guard at

all. Or if there was one, that he had sufficient training in securing a

pawnshop. Further, there is no showing that the alleged security guard

exercised all that was necessary to prevent any untoward incident or to

ensure that no suspicious individuals were allowed to enter the premises. In

fact, it is even doubtful that there was a security guard, since it is quite

impossible that he would not have noticed that the robbers were armed with

caliber .45 pistols each, which were allegedly poked at the employees.33[33]

Significantly, the alleged security guard was not presented at all to

corroborate petitioner Sicam's claim; not one of petitioners' employees who

were present during the robbery incident testified in court.

Furthermore, petitioner Sicam's admission that the vault was open at

32

33

Page 19: 2007 casesROBERTO C

the time of robbery is clearly a proof of petitioners' failure to observe the

care, precaution and vigilance that the circumstances justly demanded.

Petitioner Sicam testified that once the pawnshop was open, the combination

was already off. Considering petitioner Sicam's testimony that the robbery

took place on a Saturday afternoon and the area in BF Homes Parañaque at

that time was quiet, there was more reason for petitioners to have exercised

reasonable foresight and diligence in protecting the pawned jewelries.

Instead of taking the precaution to protect them, they let open the vault,

providing no difficulty for the robbers to cart away the pawned articles.

We, however, do not agree with the CA when it found petitioners

negligent for not taking steps to insure themselves against loss of the

pawned jewelries.

Under Section 17 of Central Bank Circular No. 374, Rules and

Regulations for Pawnshops, which took effect on July 13, 1973,

and which was issued pursuant to Presidential Decree No. 114, Pawnshop

Regulation Act, it is provided that pawns pledged must be insured, to wit:

Sec. 17. Insurance of Office Building and Pawns- The place of business of a pawnshop and the pawns pledged to it must be insured against fire and against burglary as well as for the latter(sic), by an insurance company accredited by the Insurance Commissioner.

However, this Section was subsequently amended by CB Circular No.

764 which took effect on October 1, 1980, to wit:

Sec. 17 Insurance of Office Building and Pawns – The office building/premises and pawns of a pawnshop must be insured against fire. (emphasis supplied).

Page 20: 2007 casesROBERTO C

where the requirement that insurance against burglary was deleted.

Obviously, the Central Bank considered it not feasible to require insurance

of pawned articles against burglary.

The robbery in the pawnshop happened in 1987, and considering the

above-quoted amendment, there is no statutory duty imposed on petitioners

to insure the pawned jewelry in which case it was error for the CA to

consider it as a factor in concluding that petitioners were negligent.

Nevertheless, the preponderance of evidence shows that petitioners

failed to exercise the diligence required of them under the Civil Code.

The diligence with which the law requires the individual at all times to

govern his conduct varies with the nature of the situation in which he is

placed and the importance of the act which he is to perform.34[34] Thus, the

cases of Austria v. Court of Appeals,35[35] Hernandez v. Chairman,

Commission on Audit36[36] and Cruz v. Gangan37[37] cited by petitioners in

their pleadings, where the victims of robbery were exonerated from liability,

find no application to the present case.

In Austria, Maria Abad received from Guillermo Austria a pendant

with diamonds to be sold on commission basis, but which Abad failed to

subsequently return because of a robbery committed upon her in 1961. The

incident became the subject of a criminal case filed against several persons. 34

35

36

37

Page 21: 2007 casesROBERTO C

Austria filed an action against Abad and her husband (Abads) for recovery

of the pendant or its value, but the Abads set up the defense that the robbery

extinguished their obligation. The RTC ruled in favor of Austria, as the

Abads failed to prove robbery; or, if committed, that Maria Abad was guilty

of negligence. The CA, however, reversed the RTC decision holding that the

fact of robbery was duly established and declared the Abads not responsible

for the loss of the jewelry on account of a fortuitous event. We held that for

the Abads to be relieved from the civil liability of returning the pendant

under Art. 1174 of the Civil Code, it would only be sufficient that the

unforeseen event, the robbery, took place without any concurrent fault on the

debtor’s part, and this can be done by preponderance of evidence; that to be

free from liability for reason of fortuitous event, the debtor must, in addition

to the casus itself, be free of any concurrent or contributory fault or

negligence.38[38]

We found in Austria that under the circumstances prevailing at the

time the Decision was promulgated in 1971, the City of Manila and its

suburbs had a high incidence of crimes against persons and property that

rendered travel after nightfall a matter to be sedulously avoided without

suitable precaution and protection; that the conduct of Maria Abad in

returning alone to her house in the evening carrying jewelry of considerable

value would have been negligence per se and would not exempt her from

responsibility in the case of robbery. However we did not hold Abad liable

for negligence since, the robbery happened ten years previously; i.e., 1961,

when criminality had not reached the level of incidence obtaining in 1971.

38

Page 22: 2007 casesROBERTO C

In contrast, the robbery in this case took place in 1987 when robbery

was already prevalent and petitioners in fact had already foreseen it as they

wanted to deposit the pawn with a nearby bank for safekeeping. Moreover,

unlike in Austria, where no negligence was committed, we found petitioners

negligent in securing their pawnshop as earlier discussed.

In Hernandez, Teodoro Hernandez was the OIC and special

disbursing officer of the Ternate Beach Project of the Philippine Tourism in

Cavite. In the morning of July 1, 1983, a Friday, he went to Manila to

encash two checks covering the wages of the employees and the operating

expenses of the project. However for some reason, the processing of the

check was delayed and was completed at about 3 p.m. Nevertheless, he

decided to encash the check because the project employees would be waiting

for their pay the following day; otherwise, the workers would have to wait

until July 5, the earliest time, when the main office would open. At that time,

he had two choices: (1) return to Ternate, Cavite that same afternoon and

arrive early evening; or (2) take the money with him to his house in Marilao,

Bulacan, spend the night there, and leave for Ternate the following day. He

chose the second option, thinking it was the safer one. Thus, a little past 3

p.m., he took a passenger jeep bound for Bulacan. While the jeep was on

Epifanio de los Santos Avenue, the jeep was held up and the money kept by

Hernandez was taken, and the robbers jumped out of the jeep and ran.

Hernandez chased the robbers and caught up with one robber who was

subsequently charged with robbery and pleaded guilty. The other robber who

held the stolen money escaped. The Commission on Audit found Hernandez

negligent because he had not brought the cash proceeds of the checks to his

office in Ternate, Cavite for safekeeping, which is the normal procedure in

Page 23: 2007 casesROBERTO C

the handling of funds. We held that Hernandez was not negligent in deciding

to encash the check and bringing it home to Marilao, Bulacan instead of

Ternate, Cavite due to the lateness of the hour for the following reasons: (1)

he was moved by unselfish motive for his co-employees to collect their

wages and salaries the following day, a Saturday, a non-working, because to

encash the check on July 5, the next working day after July 1, would have

caused discomfort to laborers who were dependent on their wages for

sustenance; and (2) that choosing Marilao as a safer destination, being

nearer, and in view of the comparative hazards in the trips to the two places,

said decision seemed logical at that time. We further held that the fact that

two robbers attacked him in broad daylight in the jeep while it was on a busy

highway and in the presence of other passengers could not be said to be a

result of his imprudence and negligence.

Unlike in Hernandez where the robbery happened in a public utility,

the robbery in this case took place in the pawnshop which is under the

control of petitioners. Petitioners had the means to screen the persons who

were allowed entrance to the premises and to protect itself from unlawful

intrusion. Petitioners had failed to exercise precautionary measures in

ensuring that the robbers were prevented from entering the pawnshop and

for keeping the vault open for the day, which paved the way for the robbers

to easily cart away the pawned articles.

In Cruz, Dr. Filonila O. Cruz, Camanava District Director of

Technological Education and Skills Development Authority (TESDA),

boarded the Light Rail Transit (LRT) from Sen. Puyat Avenue to

Monumento when her handbag was slashed and the contents were stolen by

Page 24: 2007 casesROBERTO C

an unidentified person. Among those stolen were her wallet and the

government-issued cellular phone. She then reported the incident to the

police authorities; however, the thief was not located, and the cellphone

was not recovered. She also reported the loss to the Regional Director of

TESDA, and she requested that she be freed from accountability for the

cellphone. The Resident Auditor denied her request on the ground that she

lacked the diligence required in the custody of government property and was

ordered to pay the purchase value in the total amount of P4,238.00. The

COA found no sufficient justification to grant the request for relief from

accountability. We reversed the ruling and found that riding the LRT cannot

per se be denounced as a negligent act more so because Cruz’s mode of

transit was influenced by time and money considerations; that she boarded

the LRT to be able to arrive in Caloocan in time for her 3 pm meeting; that

any prudent and rational person under similar circumstance can reasonably

be expected to do the same; that possession of a cellphone should not hinder

one from boarding the LRT coach as Cruz did considering that whether she

rode a jeep or bus, the risk of theft would have also been present; that

because of her relatively low position and pay, she was not expected to have

her own vehicle or to ride a taxicab; she did not have a government assigned

vehicle; that placing the cellphone in a bag away from covetous eyes and

holding on to that bag as she did is ordinarily sufficient care of a cellphone

while traveling on board the LRT; that the records did not show any specific

act of negligence on her part and negligence can never be presumed.

Unlike in the Cruz case, the robbery in this case happened in

petitioners' pawnshop and they were negligent in not exercising the

precautions justly demanded of a pawnshop.

Page 25: 2007 casesROBERTO C

WHEREFORE, except for the insurance aspect, the Decision of the

Court of Appeals dated March 31, 2003 and its Resolution dated August 8,

2003, are AFFIRMED.

Costs against petitioners.

SO ORDERED.

SPOUSES ELVIRA AND CESAR DUMLAO,

Petitioners,

-versus-

MARLON REALTY CORPORATION, Respondent.

G.R. No. 131491

Present:

PUNO, C.J., Chairperson,SANDOVAL-GUTIERREZ, CORONA, AZCUNA, andGARCIA, JJ.

Promulgated:

August 17, 2007

x-----------------------------------------------------------------------------------------x

DECISION

SANDOVAL-GUTIERREZ, J.:

For our resolution is the instant Petition for Review on Certiorari

under Rule 45 of the 1997 Rules of Civil Procedure, as amended, assailing

Page 26: 2007 casesROBERTO C

the Decision39[1] dated August 25, 1997 and Resolution40[2] dated November

13, 1997 rendered by the Court of Appeals in CA-G.R. SP No. 43366,

entitled “MARLON REALTY CORPORATION, petitioner, v. HON. JUDGE

REGIONAL TRIAL COURT OF PARAÑAQUE, BRANCH 258 and ELVIRA

D. DUMLAO, ET AL., respondents.”

The following facts are undisputed:

On November 26, 1991, spouses Elvira and Cesar Dumlao,

petitioners, and Marlon Realty Corporation, respondent, entered into a

Contract to Sell41[3] involving a 109 square meter lot in Welcome Village,

Parañaque City. The terms of payment are:

1. Petitioners shall pay respondent P218,000.00 as cost of the lot;

2. The sum of P61,000.00 shall be paid upon the signing of the contract; and

3. The balance of P157,000.00 shall be paid with interest at 24% per annum within six (6) months.

Petitioners paid P61,000.00 as downpayment upon the signing of the

contract. In the meantime, interest began to accrue on the P157,000.00

balance of the purchase price.

39

40

41

Page 27: 2007 casesROBERTO C

On November 4, 1992, the Urban Bank informed respondent

corporation that petitioners’ loan of P148,000.00, intended as payment for

their obligation, was approved. However, the bank imposed the following

conditions: the amount shall be released only after its mortgage lien shall

have been registered in the Registry of Deeds and annotated on petitioners’

land title; and that respondent must first execute a deed of absolute sale in

favor of petitioners.

On November 26, 1992, the parties entered into a Compromise

Agreement42[4] whereby petitioners agreed to pay respondent, on or before

March 26, 1993, the amount of P38,203.33 representing the accrued interest

as of that date on the P157,000.00 balance of the purchase price; and that

respondent shall execute a Deed of Sale to facilitate the transfer of title to

petitioners. On the same day, petitioners paid the buyer’s equity of

P9,000.00.

On December 1, 1992, respondent, pursuant to the Compromise

Agreement, executed a Deed of Sale43[5] in favor of petitioners. But they

refused to pay the interest agreed upon despite respondent’s repeated

demand.

On January 26, 1995, respondent filed with the Metropolitan Trial

Court (MTC), Branch 78, Parañaque City a complaint for a sum of money

against petitioners. The MTC, in its Decision44[6] dated June 17, 1996,

42

43

44

Page 28: 2007 casesROBERTO C

dismissed the complaint, holding that it is for specific performance

cognizable by the Regional Trial Court (RTC).

On appeal by respondent, the RTC, Branch 258, Parañaque City

rendered its Decision dated November 19, 1996 affirming the MTC

judgment dismissing the complaint “not on the ground of lack of

jurisdiction, but for lack of cause of action.” 45[7]

Petitioners filed a motion for reconsideration but it was denied by the

RTC in its Order of February 04, 1997.

On February 28, 1997, respondent filed with the Court of Appeals a

petition for review. In its Decision dated August 25, 1997, the appellate

court held that respondent’s complaint is for a sum of money, the Contract

to Sell being a “unilateral acknowledgment of an existing debt” on

petitioners’ part. The dispositive portion of the Decision reads:

WHEREFORE, premises considered, the petition is hereby given DUE COURSE and the assailed Decision dated November 19, 1996 of the RTC of Parañaque, Branch 258, and its Order dated February 4, 1997 denying therein plaintiff’s Motion for Reconsideration, as well as the Decision dated June 17, 1996 of the Metropolitan Trial Court of Parañaque, Branch 78, are REVERSED and SET ASIDE.

A new judgment is hereby entered ordering defendant spouses Cesar and Elvira Dumlao to pay the sum of P109,929.79 representing the accumulated interests as of January 6, 1995 with interest at 2% per month computed from January 6, 1995.

SO ORDERED.46[8]

45

46

Page 29: 2007 casesROBERTO C

Petitioners filed a motion for reconsideration but it was denied by the

Court of Appeals in its Resolution dated November 13, 1997.

Hence, this petition.

The issue for our resolution is whether petitioners are liable to pay

interest on the balance of the purchase price.

Petitioners insist that they are not liable to pay interest since the loan

proceeds were released, not to petitioners, but directly to respondent; and

that pending the release, no interest should accrue.

Petitioners’ arguments are misplaced.

Obligations arising from contracts have the force of law between the

contracting parties and should be complied with in good faith.47[9] We must

look into the terms of the contract to determine the respective obligations of

the parties thereto. If the terms of a contract are clear and leave no doubt

upon the contracting parties’ intention, then such terms should be applied in

their literal meaning.48[10]

47

48

Page 30: 2007 casesROBERTO C

In this case, there is no question that the parties voluntarily entered

into a Contract to Sell a parcel of land. The terms of payment of the

purchase price are clear and unambiguous, thus:

SECOND – That in consideration of the agreement to sell the above described property, the VENDEE obligates himself/herself to pay the VENDOR the sum of TWO HUNDRED EIGHTEEN THOUSAND ( P 218,000.00) PESOS, Philippine Currency from the date of execution of this contract until paid as follows:

a) The amount of SIXTY ONE THOUSAND xxx ( P 61,000.00) PESOS when this contract is signed, and

b) The balance of ONE HUNDRED FIFTY SEVEN THOUSAND ( P 157,000.00) PESOS shall be paid with interest at 24% per annum to be computed based on the outstanding and payable balance, as of the date of downpayment, within a period of SIX (6) MONTHS x x x. Any installment not paid on or before the due date, or within the grace period of five (5) days thereafter, shall bear a penalty of 2% per month based on the remaining unpaid monthly installments. Note: As per agreement, the amount of P148,000.00 is receivable thru an URBAN BANK Letter of Guaranty (Pag-ibig Loan)

THIRD – That demand for payment by the VENDOR is not necessary to make the VENDEE incur delay (default). Note: Buyer’s equity is P 9,000.00 .

Pursuant to the above agreement, it is clear that a 24% interest per

annum on the balance of P157,000.00 shall be paid to respondent by

petitioners. Having signed the contract, petitioners are bound to comply

with its terms and conditions in good faith. We reiterate that the contract is

the law between them.

We observe that respondent, faithful to its part of the bargain,

executed a deed of sale in favor of petitioners. In fact, a Transfer Certificate

Page 31: 2007 casesROBERTO C

of Title was already issued in their names. Fairness demands that petitioners

also fulfill their obligation to pay interest on the balance of the purchase

price.

WHEREFORE, we DENY the petition. The assailed Decision and

Resolution of the Court of Appeals in CA-G.R. SP No. 43366 are

AFFIRMED.

Costs against petitioners.

SO ORDERED.

UNITED COCONUT PLANTERS BANK,

Petitioner,

- versus -

SPOUSES SAMUEL and ODETTE BELUSO,

Respondents.

G.R. No. 159912

Present:

YNARES-SANTIAGO, J., Chairperson,AUSTRIA-MARTINEZ, CHICO-NAZARIO,NACHURA, and REYES, JJ.

Promulgated:

August 17, 2007x- - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - -x

Page 32: 2007 casesROBERTO C

D E C I S I O N

CHICO-NAZARIO, J.:

This is a Petition for Review on Certiorari under Rule 45 of the Rules

of Court, which seeks to annul the Court of Appeals Decision49[1] dated 21

January 2003 and its Resolution50[2] dated 9 September 2003 in CA-G.R. CV

No. 67318. The assailed Court of Appeals Decision and Resolution

affirmed in turn the Decision51[3] dated 23 March 2000 and Order52[4] dated 8

May 2000 of the Regional Trial Court (RTC), Branch 65 of Makati City, in

Civil Case No. 99-314, declaring void the interest rate provided in the

promissory notes executed by the respondents Spouses Samuel and Odette

Beluso (spouses Beluso) in favor of petitioner United Coconut Planters Bank

(UCPB).

The procedural and factual antecedents of this case are as follows:

On 16 April 1996, UCPB granted the spouses Beluso a Promissory

Notes Line under a Credit Agreement whereby the latter could avail from

the former credit of up to a maximum amount of P1.2 Million pesos for a

term ending on 30 April 1997. The spouses Beluso constituted, other than

their promissory notes, a real estate mortgage over parcels of land in Roxas

City, covered by Transfer Certificates of Title No. T-31539 and T-27828, as 49

50

51

52

Page 33: 2007 casesROBERTO C

additional security for the obligation. The Credit Agreement was

subsequently amended to increase the amount of the Promissory Notes Line

to a maximum of P2.35 Million pesos and to extend the term thereof to 28

February 1998.

The spouses Beluso availed themselves of the credit line under the

following Promissory Notes:

PN # Date of PN Maturity Date Amount Secured

8314-96-00083-3 29 April 1996 27 August 1996 P 700,000

8314-96-00085-0 2 May 1996 30 August 1996 P 500,000

8314-96-000292-2 20 November 1996 20 March 1997 P 800,000

The three promissory notes were renewed several times. On 30 April

1997, the payment of the principal and interest of the latter two promissory

notes were debited from the spouses Beluso’s account with UCPB; yet, a

consolidated loan for P1.3 Million was again released to the spouses Beluso

under one promissory note with a due date of 28 February 1998.

To completely avail themselves of the P2.35 Million credit line

extended to them by UCPB, the spouses Beluso executed two more

promissory notes for a total of P350,000.00:

PN # Date of PN Maturity Date Amount Secured

97-00363-1 11 December 1997 28 February 1998 P 200,000

98-00002-4 2 January 1998 28 February 1998 P 150,000

Page 34: 2007 casesROBERTO C

However, the spouses Beluso alleged that the amounts covered by these last

two promissory notes were never released or credited to their account and,

thus, claimed that the principal indebtedness was only P2 Million.

In any case, UCPB applied interest rates on the different promissory

notes ranging from 18% to 34%. From 1996 to February 1998 the spouses

Beluso were able to pay the total sum of P763,692.03.

From 28 February 1998 to 10 June 1998, UCPB continued to charge

interest and penalty on the obligations of the spouses Beluso, as follows:

PN # Amount Secured Interest Penalty Total

97-00363-1 P 200,000 31% 36% P 225,313.24

97-00366-6 P 700,000 30.17% (7 days)

32.786% (102 days)

P 795,294.72

97-00368-2 P 1,300,000 28%(2 days)

30.41% (102 days)

P 1,462,124.54

98-00002-4 P 150,000 33% (102 days)

36% P 170,034.71

The spouses Beluso, however, failed to make any payment of the

foregoing amounts.

On 2 September 1998, UCPB demanded that the spouses Beluso pay

their total obligation of P2,932,543.00 plus 25% attorney’s fees, but the

spouses Beluso failed to comply therewith. On 28 December 1998, UCPB

foreclosed the properties mortgaged by the spouses Beluso to secure their

credit line, which, by that time, already ballooned to P3,784,603.00.

Page 35: 2007 casesROBERTO C

On 9 February 1999, the spouses Beluso filed a Petition for

Annulment, Accounting and Damages against UCPB with the RTC of

Makati City.

On 23 March 2000, the RTC ruled in favor of the spouses Beluso,

disposing of the case as follows:

PREMISES CONSIDERED, judgment is hereby rendered declaring the interest rate used by [UCPB] void and the foreclosure and Sheriff’s Certificate of Sale void. [UCPB] is hereby ordered to return to [the spouses Beluso] the properties subject of the foreclosure; to pay [the spouses Beluso] the amount of P50,000.00 by way of attorney’s fees; and to pay the costs of suit. [The spouses Beluso] are hereby ordered to pay [UCPB] the sum of P1,560,308.00.53[5]

On 8 May 2000, the RTC denied UCPB’s Motion for

Reconsideration,54[6] prompting UCPB to appeal the RTC Decision with the

Court of Appeals. The Court of Appeals affirmed the RTC Decision, to wit:

WHEREFORE, premises considered, the decision dated March 23, 2000 of the Regional Trial Court, Branch 65, Makati City in Civil Case No. 99-314 is hereby AFFIRMED subject to the modification that defendant-appellant UCPB is not liable for attorney’s fees or the costs of suit.55[7]

On 9 September 2003, the Court of Appeals denied UCPB’s Motion

for Reconsideration for lack of merit. UCPB thus filed the present petition,

submitting the following issues for our resolution:

53

54

55

Page 36: 2007 casesROBERTO C

I

WHETHER OR NOT THE HONORABLE COURT OF APPEALS COMMITTED SERIOUS AND REVERSIBLE ERROR WHEN IT AFFIRMED THE DECISION OF THE TRIAL COURT WHICH DECLARED VOID THE PROVISION ON INTEREST RATE AGREED UPON BETWEEN PETITIONER AND RESPONDENTS

II

WHETHER OR NOT THE HONORABLE COURT OF APPEALS COMMITTED SERIOUS AND REVERSIBLE ERROR WHEN IT AFFIRMED THE COMPUTATION BY THE TRIAL COURT OF RESPONDENTS’ INDEBTEDNESS AND ORDERED RESPONDENTS TO PAY PETITIONER THE AMOUNT OF ONLY ONE MILLION FIVE HUNDRED SIXTY THOUSAND THREE HUNDRED EIGHT PESOS (P1,560,308.00)

III

WHETHER OR NOT THE HONORABLE COURT OF APPEALS COMMITTED SERIOUS AND REVERSIBLE ERROR WHEN IT AFFIRMED THE DECISION OF THE TRIAL COURT WHICH ANNULLED THE FORECLOSURE BY PETITIONER OF THE SUBJECT PROPERTIES DUE TO AN ALLEGED “INCORRECT COMPUTATION” OF RESPONDENTS’ INDEBTEDNESS

IV

WHETHER OR NOT THE HONORABLE COURT OF APPEALS COMMITTED SERIOUS AND REVERSIBLE ERROR WHEN IT AFFIRMED THE DECISION OF THE TRIAL COURT WHICH FOUND PETITIONER LIABLE FOR VIOLATION OF THE TRUTH IN LENDING ACT

V

WHETHER OR NOT THE HONORABLE COURT OF APPEALS COMMITTED SERIOUS AND REVERSIBLE ERROR WHEN IT FAILED TO ORDER THE DISMISSAL OF THE CASE BECAUSE THE RESPONDENTS ARE GUILTY OF FORUM SHOPPING56[8]

Validity of the Interest Rates

56

Page 37: 2007 casesROBERTO C

The Court of Appeals held that the imposition of interest in the

following provision found in the promissory notes of the spouses Beluso is

void, as the interest rates and the bases therefor were determined solely by

petitioner UCPB:

FOR VALUE RECEIVED, I, and/or We, on or before due date, SPS. SAMUEL AND ODETTE BELUSO (BORROWER), jointly and severally promise to pay to UNITED COCONUT PLANTERS BANK (LENDER) or order at UCPB Bldg., Makati Avenue, Makati City, Philippines, the sum of ______________ PESOS, (P_____), Philippine Currency, with interest thereon at the rate indicative of DBD retail rate or as determined by the Branch Head.57[9]

UCPB asserts that this is a reversible error, and claims that while the

interest rate was not numerically quantified in the face of the promissory

notes, it was nonetheless categorically fixed, at the time of execution

thereof, at the “rate indicative of the DBD retail rate.” UCPB contends that

said provision must be read with another stipulation in the promissory notes

subjecting to review the interest rate as fixed:

The interest rate shall be subject to review and may be increased or decreased by the LENDER considering among others the prevailing financial and monetary conditions; or the rate of interest and charges which other banks or financial institutions charge or offer to charge for similar accommodations; and/or the resulting profitability to the LENDER after due consideration of all dealings with the BORROWER.58[10]

In this regard, UCPB avers that these are valid reference rates akin to

a “prevailing rate” or “prime rate” allowed by this Court in Polotan v. Court

57

58

Page 38: 2007 casesROBERTO C

of Appeals.59[11] Furthermore, UCPB argues that even if the proviso “as

determined by the branch head” is considered void, such a declaration would

not ipso facto render the connecting clause “indicative of DBD retail rate”

void in view of the separability clause of the Credit Agreement, which reads:

Section 9.08 Separability Clause. If any one or more of the provisions contained in this AGREEMENT, or documents executed in connection herewith shall be declared invalid, illegal or unenforceable in any respect, the validity, legality and enforceability of the remaining provisions hereof shall not in any way be affected or impaired.60[12]

According to UCPB, the imposition of the questioned interest rates

did not infringe on the principle of mutuality of contracts, because the

spouses Beluso had the liberty to choose whether or not to renew their credit

line at the new interest rates pegged by petitioner.61[13] UCPB also claims

that assuming there was any defect in the mutuality of the contract at the

time of its inception, such defect was cured by the subsequent conduct of the

spouses Beluso in availing themselves of the credit line from April 1996 to

February 1998 without airing any protest with respect to the interest rates

imposed by UCPB. According to UCPB, therefore, the spouses Beluso are

in estoppel.62[14]

We agree with the Court of Appeals, and find no merit in the

contentions of UCPB.

Article 1308 of the Civil Code provides:

59

60

61

62

Page 39: 2007 casesROBERTO C

Art. 1308. The contract must bind both contracting parties; its validity or compliance cannot be left to the will of one of them.

We applied this provision in Philippine National Bank v. Court of

Appeals,63[15] where we held:

In order that obligations arising from contracts may have the force of law between the parties, there must be mutuality between the parties based on their essential equality. A contract containing a condition which makes its fulfillment dependent exclusively upon the uncontrolled will of one of the contracting parties, is void (Garcia vs. Rita Legarda, Inc., 21 SCRA 555). Hence, even assuming that the P1.8 million loan agreement between the PNB and the private respondent gave the PNB a license (although in fact there was none) to increase the interest rate at will during the term of the loan, that license would have been null and void for being violative of the principle of mutuality essential in contracts. It would have invested the loan agreement with the character of a contract of adhesion, where the parties do not bargain on equal footing, the weaker party's (the debtor) participation being reduced to the alternative "to take it or leave it" (Qua vs. Law Union & Rock Insurance Co., 95 Phil. 85). Such a contract is a veritable trap for the weaker party whom the courts of justice must protect against abuse and imposition.

The provision stating that the interest shall be at the “rate indicative of

DBD retail rate or as determined by the Branch Head” is indeed dependent

solely on the will of petitioner UCPB. Under such provision, petitioner

UCPB has two choices on what the interest rate shall be: (1) a rate indicative

of the DBD retail rate; or (2) a rate as determined by the Branch Head. As

UCPB is given this choice, the rate should be categorically determinable in

both choices. If either of these two choices presents an opportunity for

UCPB to fix the rate at will, the bank can easily choose such an option, thus

63

Page 40: 2007 casesROBERTO C

making the entire interest rate provision violative of the principle of

mutuality of contracts.

Not just one, but rather both, of these choices are dependent solely on

the will of UCPB. Clearly, a rate “as determined by the Branch Head” gives

the latter unfettered discretion on what the rate may be. The Branch Head

may choose any rate he or she desires. As regards the rate “indicative of the

DBD retail rate,” the same cannot be considered as valid for being akin to a

“prevailing rate” or “prime rate” allowed by this Court in Polotan. The

interest rate in Polotan reads:

The Cardholder agrees to pay interest per annum at 3% plus the prime rate of Security Bank and Trust Company. x x x.64[16]

In this provision in Polotan, there is a fixed margin over the reference rate:

3%. Thus, the parties can easily determine the interest rate by applying

simple arithmetic. On the other hand, the provision in the case at bar does

not specify any margin above or below the DBD retail rate. UCPB can peg

the interest at any percentage above or below the DBD retail rate, again

giving it unfettered discretion in determining the interest rate.

The stipulation in the promissory notes subjecting the interest rate to

review does not render the imposition by UCPB of interest rates on the

obligations of the spouses Beluso valid. According to said stipulation:

The interest rate shall be subject to review and may be increased or decreased by the LENDER considering among others the prevailing financial and monetary conditions; or the rate of interest and charges

64

Page 41: 2007 casesROBERTO C

which other banks or financial institutions charge or offer to charge for similar accommodations; and/or the resulting profitability to the LENDER after due consideration of all dealings with the BORROWER.65[17]

It should be pointed out that the authority to review the interest rate was

given UCPB alone as the lender. Moreover, UCPB may apply the

considerations enumerated in this provision as it wishes. As worded in the

above provision, UCPB may give as much weight as it desires to each of the

following considerations: (1) the prevailing financial and monetary

condition; (2) the rate of interest and charges which other banks or financial

institutions charge or offer to charge for similar accommodations; and/or (3)

the resulting profitability to the LENDER (UCPB) after due consideration of

all dealings with the BORROWER (the spouses Beluso). Again, as in the

case of the interest rate provision, there is no fixed margin above or below

these considerations.

In view of the foregoing, the Separability Clause cannot save either of

the two options of UCPB as to the interest to be imposed, as both options

violate the principle of mutuality of contracts.

UCPB likewise failed to convince us that the spouses Beluso were in

estoppel.

Estoppel cannot be predicated on an illegal act. As between the

parties to a contract, validity cannot be given to it by estoppel if it is

prohibited by law or is against public policy.66[18]

65

66

Page 42: 2007 casesROBERTO C

The interest rate provisions in the case at bar are illegal not only

because of the provisions of the Civil Code on mutuality of contracts, but

also, as shall be discussed later, because they violate the Truth in Lending

Act. Not disclosing the true finance charges in connection with the

extensions of credit is, furthermore, a form of deception which we cannot

countenance. It is against the policy of the State as stated in the Truth in

Lending Act:

Sec. 2. Declaration of Policy. – It is hereby declared to be the policy of the State to protect its citizens from a lack of awareness of the true cost of credit to the user by assuring a full disclosure of such cost with a view of preventing the uninformed use of credit to the detriment of the national economy.67[19]

Moreover, while the spouses Beluso indeed agreed to renew the credit

line, the offending provisions are found in the promissory notes themselves,

not in the credit line. In fixing the interest rates in the promissory notes to

cover the renewed credit line, UCPB still reserved to itself the same two

options – (1) a rate indicative of the DBD retail rate; or (2) a rate as

determined by the Branch Head.

Error in Computation

UCPB asserts that while both the RTC and the Court of Appeals

voided the interest rates imposed by UCPB, both failed to include in their

computation of the outstanding obligation of the spouses Beluso the legal

rate of interest of 12% per annum. Furthermore, the penalty charges were

67

Page 43: 2007 casesROBERTO C

also deleted in the decisions of the RTC and the Court of Appeals. Section

2.04, Article II on “Interest and other Bank Charges” of the subject Credit

Agreement, provides:

Section 2.04 Penalty Charges. In addition to the interest provided for in Section 2.01 of this ARTICLE, any principal obligation of the CLIENT hereunder which is not paid when due shall be subject to a penalty charge of one percent (1%) of the amount of such obligation per month computed from due date until the obligation is paid in full. If the bank accelerates teh (sic) payment of availments hereunder pursuant to ARTICLE VIII hereof, the penalty charge shall be used on the total principal amount outstanding and unpaid computed from the date of acceleration until the obligation is paid in full.68[20]

Paragraph 4 of the promissory notes also states:

In case of non-payment of this Promissory Note (Note) at maturity, I/We, jointly and severally, agree to pay an additional sum equivalent to twenty-five percent (25%) of the total due on the Note as attorney’s fee, aside from the expenses and costs of collection whether actually incurred or not, and a penalty charge of one percent (1%) per month on the total amount due and unpaid from date of default until fully paid.69[21]

Petitioner further claims that it is likewise entitled to attorney’s fees,

pursuant to Section 9.06 of the Credit Agreement, thus:

If the BANK shall require the services of counsel for the enforcement of its rights under this AGREEMENT, the Note(s), the collaterals and other related documents, the BANK shall be entitled to recover attorney’s fees equivalent to not less than twenty-five percent (25%) of the total amounts due and outstanding exclusive of costs and other expenses.70[22]

68

69

70

Page 44: 2007 casesROBERTO C

Another alleged computational error pointed out by UCPB is the

negation of the Compounding Interest agreed upon by the parties under

Section 2.02 of the Credit Agreement:

Section 2.02 Compounding Interest. Interest not paid when due shall form part of the principal and shall be subject to the same interest rate as herein stipulated.71[23]

and paragraph 3 of the subject promissory notes:

Interest not paid when due shall be added to, and become part of the principal and shall likewise bear interest at the same rate.72[24]

UCPB lastly avers that the application of the spouses Beluso’s

payments in the disputed computation does not reflect the parties’

agreement. The RTC deducted the payment made by the spouses Beluso

amounting to P763,693.00 from the principal of P2,350,000.00. This was

allegedly inconsistent with the Credit Agreement, as well as with the

agreement of the parties as to the facts of the case. In paragraph 7 of the

spouses Beluso’s Manifestation and Motion on Proposed Stipulation of

Facts and Issues vis-à-vis UCPB’s Manifestation, the parties agreed that the

amount of P763,693.00 was applied to the interest and not to the principal,

in accord with Section 3.03, Article II of the Credit Agreement on “Order of

the Application of Payments,” which provides:

Section 3.03 Application of Payment. Payments made by the CLIENT shall be applied in accordance with the following order of preference:

71

72

Page 45: 2007 casesROBERTO C

1. Accounts receivable and other out-of-pocket expenses2. Front-end Fee, Origination Fee, Attorney’s Fee and other

expenses of collection;3. Penalty charges;4. Past due interest;5. Principal amortization/Payment in arrears;6. Advance interest;7. Outstanding balance; and8. All other obligations of CLIENT to the BANK, if any.73[25]

Thus, according to UCPB, the interest charges, penalty charges, and

attorney’s fees had been erroneously excluded by the RTC and the Court of

Appeals from the computation of the total amount due and demandable from

spouses Beluso.

The spouses Beluso’s defense as to all these issues is that the demand

made by UCPB is for a considerably bigger amount and, therefore, the

demand should be considered void. There being no valid demand, according

to the spouses Beluso, there would be no default, and therefore the interests

and penalties would not commence to run. As it was likewise improper to

foreclose the mortgaged properties or file a case against the spouses Beluso,

attorney’s fees were not warranted.

We agree with UCPB on this score. Default commences upon

judicial or extrajudicial demand.74[26] The excess amount in such a demand

does not nullify the demand itself, which is valid with respect to the proper

amount. A contrary ruling would put commercial transactions in disarray, as

validity of demands would be dependent on the exactness of the

computations thereof, which are too often contested.

73

74

Page 46: 2007 casesROBERTO C

There being a valid demand on the part of UCPB, albeit excessive, the

spouses Beluso are considered in default with respect to the proper amount

and, therefore, the interests and the penalties began to run at that point.

As regards the award of 12% legal interest in favor of petitioner, the

RTC actually recognized that said legal interest should be imposed, thus:

“There being no valid stipulation as to interest, the legal rate of interest shall

be charged.”75[27] It seems that the RTC inadvertently overlooked its non-

inclusion in its computation.

The spouses Beluso had even originally asked for the RTC to impose

this legal rate of interest in both the body and the prayer of its petition with

the RTC:

12. Since the provision on the fixing of the rate of interest by the sole will of the respondent Bank is null and void, only the legal rate of interest which is 12% per annum can be legally charged and imposed by the bank, which would amount to only about P599,000.00 since 1996 up to August 31, 1998.

x x x x

WHEREFORE, in view of the foregoing, petiitoners pray for judgment or order:

x x x x

2. By way of example for the public good against the Bank’s taking unfair advantage of the weaker party to their contract, declaring the legal rate of 12% per annum, as the imposable rate of interest up to February 28, 1999 on the loan of 2.350 million.76[28]

75

76

Page 47: 2007 casesROBERTO C

All these show that the spouses Beluso had acknowledged before the RTC

their obligation to pay a 12% legal interest on their loans. When the RTC

failed to include the 12% legal interest in its computation, however, the

spouses Beluso merely defended in the appellate courts this non-inclusion,

as the same was beneficial to them. We see, however, sufficient basis to

impose a 12% legal interest in favor of petitioner in the case at bar, as what

we have voided is merely the stipulated rate of interest and not the

stipulation that the loan shall earn interest.

We must likewise uphold the contract stipulation providing the

compounding of interest. The provisions in the Credit Agreement and in the

promissory notes providing for the compounding of interest were neither

nullified by the RTC or the Court of Appeals, nor assailed by the spouses

Beluso in their petition with the RTC. The compounding of interests has

furthermore been declared by this Court to be legal. We have held in Tan v.

Court of Appeals,77[29] that:

Without prejudice to the provisions of Article 2212, interest due and unpaid shall not earn interest. However, the contracting parties may by stipulation capitalize the interest due and unpaid, which as added principal, shall earn new interest.

As regards the imposition of penalties, however, although we are

likewise upholding the imposition thereof in the contract, we find the rate

iniquitous. Like in the case of grossly excessive interests, the penalty

77

Page 48: 2007 casesROBERTO C

stipulated in the contract may also be reduced by the courts if it is iniquitous

or unconscionable.78[30]

We find the penalty imposed by UCPB, ranging from 30.41% to 36%,

to be iniquitous considering the fact that this penalty is already over and

above the compounded interest likewise imposed in the contract. If a 36%

interest in itself has been declared unconscionable by this Court,79[31] what

more a 30.41% to 36% penalty, over and above the payment of compounded

interest? UCPB itself must have realized this, as it gave us a sample

computation of the spouses Beluso’s obligation if both the interest and the

penalty charge are reduced to 12%.

As regards the attorney’s fees, the spouses Beluso can actually be

liable therefor even if there had been no demand. Filing a case in court is

the judicial demand referred to in Article 116980[32] of the Civil Code, which

would put the obligor in delay.

The RTC, however, also held UCPB liable for attorney’s fees in this

case, as the spouses Beluso were forced to litigate the issue on the illegality

of the interest rate provision of the promissory notes. The award of

attorney’s fees, it must be recalled, falls under the sound discretion of the

court.81[33] Since both parties were forced to litigate to protect their

respective rights, and both are entitled to the award of attorney’s fees from

the other, practical reasons dictate that we set off or compensate both

78

79

80

81

Page 49: 2007 casesROBERTO C

parties’ liabilities for attorney’s fees. Therefore, instead of awarding

attorney’s fees in favor of petitioner, we shall merely affirm the deletion of

the award of attorney’s fees to the spouses Beluso.

In sum, we hold that spouses Beluso should still be held liable for a

compounded legal interest of 12% per annum and a penalty charge of 12%

per annum. We also hold that, instead of awarding attorney’s fees in favor

of petitioner, we shall merely affirm the deletion of the award of attorney’s

fees to the spouses Beluso.

Annulment of the Foreclosure Sale

Properties of spouses Beluso had been foreclosed, titles to which had

already been consolidated on 19 February 2001 and 20 March 2001 in the

name of UCPB, as the spouses Beluso failed to exercise their right of

redemption which expired on 25 March 2000. The RTC, however, annulled

the foreclosure of mortgage based on an alleged incorrect computation of the

spouses Beluso’s indebtedness.

UCPB alleges that none of the grounds for the annulment of a

foreclosure sale are present in the case at bar. Furthermore, the annulment of

the foreclosure proceedings and the certificates of sale were mooted by the

subsequent issuance of new certificates of title in the name of said bank.

UCPB claims that the spouses Beluso’s action for annulment of foreclosure

constitutes a collateral attack on its certificates of title, an act proscribed by

Section 48 of Presidential Decree No. 1529, otherwise known as the Property

Registration Decree, which provides:

Page 50: 2007 casesROBERTO C

Section 48. Certificate not subject to collateral attack. – A certificate of title shall not be subject to collateral attack. It cannot be altered, modified or cancelled except in a direct proceeding in accordance with law.

The spouses Beluso retort that since they had the right to refuse

payment of an excessive demand on their account, they cannot be said to be

in default for refusing to pay the same. Consequently, according to the

spouses Beluso, the “enforcement of such illegal and overcharged demand

through foreclosure of mortgage” should be voided.

We agree with UCPB and affirm the validity of the foreclosure

proceedings. Since we already found that a valid demand was made by

UCPB upon the spouses Beluso, despite being excessive, the spouses Beluso

are considered in default with respect to the proper amount of their

obligation to UCPB and, thus, the property they mortgaged to secure such

amounts may be foreclosed. Consequently, proceeds of the foreclosure sale

should be applied to the extent of the amounts to which UCPB is rightfully

entitled.

As argued by UCPB, none of the grounds for the annulment of a

foreclosure sale are present in this case. The grounds for the proper

annulment of the foreclosure sale are the following: (1) that there was fraud,

collusion, accident, mutual mistake, breach of trust or misconduct by the

purchaser; (2) that the sale had not been fairly and regularly conducted; or

Page 51: 2007 casesROBERTO C

(3) that the price was inadequate and the inadequacy was so great as to

shock the conscience of the court.82[34]

Liability for Violation of Truth in Lending Act

The RTC, affirmed by the Court of Appeals, imposed a fine of

P26,000.00 for UCPB’s alleged violation of Republic Act No. 3765,

otherwise known as the Truth in Lending Act.

UCPB challenges this imposition, on the argument that Section 6(a) of

the Truth in Lending Act which mandates the filing of an action to recover

such penalty must be made under the following circumstances:

Section 6. (a) Any creditor who in connection with any credit transaction fails to disclose to any person any information in violation of this Act or any regulation issued thereunder shall be liable to such person in the amount of P100 or in an amount equal to twice the finance charge required by such creditor in connection with such transaction, whichever is greater, except that such liability shall not exceed P2,000 on any credit transaction. Action to recover such penalty may be brought by such person within one year from the date of the occurrence of the violation, in any court of competent jurisdiction. x x x (Emphasis ours.)

According to UCPB, the Court of Appeals even stated that

“[a]dmittedly the original complaint did not explicitly allege a violation of

the ‘Truth in Lending Act’ and no action to formally admit the amended

petition [which expressly alleges violation of the Truth in Lending Act] was

82

Page 52: 2007 casesROBERTO C

made either by [respondents] spouses Beluso and the lower court. x x

x.”83[35]

UCPB further claims that the action to recover the penalty for the

violation of the Truth in Lending Act had been barred by the one-year

prescriptive period provided for in the Act. UCPB asserts that per the

records of the case, the latest of the subject promissory notes had been

executed on 2 January 1998, but the original petition of the spouses Beluso

was filed before the RTC on 9 February 1999, which was after the expiration

of the period to file the same on 2 January 1999.

On the matter of allegation of the violation of the Truth in Lending

Act, the Court of Appeals ruled:

Admittedly the original complaint did not explicitly allege a violation of the ‘Truth in Lending Act’ and no action to formally admit the amended petition was made either by [respondents] spouses Beluso and the lower court. In such transactions, the debtor and the lending institutions do not deal on an equal footing and this law was intended to protect the public from hidden or undisclosed charges on their loan obligations, requiring a full disclosure thereof by the lender. We find that its infringement may be inferred or implied from allegations that when [respondents] spouses Beluso executed the promissory notes, the interest rate chargeable thereon were left blank. Thus, [petitioner] UCPB failed to discharge its duty to disclose in full to [respondents] Spouses Beluso the charges applicable on their loans.84[36]

We agree with the Court of Appeals. The allegations in the

complaint, much more than the title thereof, are controlling. Other than that

stated by the Court of Appeals, we find that the allegation of violation of the

83

84

Page 53: 2007 casesROBERTO C

Truth in Lending Act can also be inferred from the same allegation in the

complaint we discussed earlier:

b.) In unilaterally imposing an increased interest rates (sic) respondent bank has relied on the provision of their promissory note granting respondent bank the power to unilaterally fix the interest rates, which rate was not determined in the promissory note but was left solely to the will of the Branch Head of the respondent Bank, x x x.85[37]

The allegation that the promissory notes grant UCPB the power to

unilaterally fix the interest rates certainly also means that the promissory

notes do not contain a “clear statement in writing” of “(6) the finance charge

expressed in terms of pesos and centavos; and (7) the percentage that the

finance charge bears to the amount to be financed expressed as a simple

annual rate on the outstanding unpaid balance of the obligation.”86[38]

Furthermore, the spouses Beluso’s prayer “for such other reliefs just and

equitable in the premises” should be deemed to include the civil penalty

provided for in Section 6(a) of the Truth in Lending Act.

UCPB’s contention that this action to recover the penalty for the

violation of the Truth in Lending Act has already prescribed is likewise

without merit. The penalty for the violation of the act is P100 or an amount

equal to twice the finance charge required by such creditor in connection

with such transaction, whichever is greater, except that such liability shall

not exceed P2,000.00 on any credit transaction.87[39] As this penalty depends

on the finance charge required of the borrower, the borrower’s cause of

action would only accrue when such finance charge is required. In the case

85

86

87

Page 54: 2007 casesROBERTO C

at bar, the date of the demand for payment of the finance charge is 2

September 1998, while the foreclosure was made on 28 December 1998.

The filing of the case on 9 February 1999 is therefore within the one-year

prescriptive period.

UCPB argues that a violation of the Truth in Lending Act, being a

criminal offense, cannot be inferred nor implied from the allegations made

in the complaint.88[40] Pertinent provisions of the Act read:

Sec. 6. (a) Any creditor who in connection with any credit transaction fails to disclose to any person any information in violation of this Act or any regulation issued thereunder shall be liable to such person in the amount of P100 or in an amount equal to twice the finance charge required by such creditor in connection with such transaction, whichever is the greater, except that such liability shall not exceed P2,000 on any credit transaction. Action to recover such penalty may be brought by such person within one year from the date of the occurrence of the violation, in any court of competent jurisdiction. In any action under this subsection in which any person is entitled to a recovery, the creditor shall be liable for reasonable attorney’s fees and court costs as determined by the court.

x x x x

(c) Any person who willfully violates any provision of this Act or any regulation issued thereunder shall be fined by not less than P1,000 or more than P5,000 or imprisonment for not less than 6 months, nor more than one year or both.

As can be gleaned from Section 6(a) and (c) of the Truth in Lending Act, the

violation of the said Act gives rise to both criminal and civil liabilities.

Section 6(c) considers a criminal offense the willful violation of the Act,

imposing the penalty therefor of fine, imprisonment or both. Section 6(a),

on the other hand, clearly provides for a civil cause of action for failure to

88

Page 55: 2007 casesROBERTO C

disclose any information of the required information to any person in

violation of the Act. The penalty therefor is an amount of P100 or in an

amount equal to twice the finance charge required by the creditor in

connection with such transaction, whichever is greater, except that the

liability shall not exceed P2,000.00 on any credit transaction. The action to

recover such penalty may be instituted by the aggrieved private person

separately and independently from the criminal case for the same offense.

In the case at bar, therefore, the civil action to recover the penalty

under Section 6(a) of the Truth in Lending Act had been jointly instituted

with (1) the action to declare the interests in the promissory notes void, and

(2) the action to declare the foreclosure void. This joinder is allowed under

Rule 2, Section 5 of the Rules of Court, which provides:

SEC. 5. Joinder of causes of action.—A party may in one pleading assert, in the alternative or otherwise, as many causes of action as he may have against an opposing party, subject to the following conditions:

(a) The party joining the causes of action shall comply with the rules on joinder of parties;

(b) The joinder shall not include special civil actions or actions governed by special rules;

(c) Where the causes of action are between the same parties but pertain to different venues or jurisdictions, the joinder may be allowed in the Regional Trial Court provided one of the causes of action falls within the jurisdiction of said court and the venue lies therein; and

(d) Where the claims in all the causes of action are principally for recovery of money, the aggregate amount claimed shall be the test of jurisdiction.

In attacking the RTC’s disposition on the violation of the Truth in

Lending Act since the same was not alleged in the complaint, UCPB is

Page 56: 2007 casesROBERTO C

actually asserting a violation of due process. Indeed, due process mandates

that a defendant should be sufficiently apprised of the matters he or she

would be defending himself or herself against. However, in the 1 July 1999

pre-trial brief filed by the spouses Beluso before the RTC, the claim for civil

sanctions for violation of the Truth in Lending Act was expressly alleged,

thus:

Moreover, since from the start, respondent bank violated the Truth in Lending Act in not informing the borrower in writing before the execution of the Promissory Notes of the interest rate expressed as a percentage of the total loan, the respondent bank instead is liable to pay petitioners double the amount the bank is charging petitioners by way of sanction for its violation.89[41]

In the same pre-trial brief, the spouses Beluso also expressly raised

the following issue:

b.) Does the expression indicative rate of DBD retail (sic) comply with the Truth in Lending Act provision to express the interest rate as a simple annual percentage of the loan?90[42]

These assertions are so clear and unequivocal that any attempt of

UCPB to feign ignorance of the assertion of this issue in this case as to

prevent it from putting up a defense thereto is plainly hogwash.

Petitioner further posits that it is the Metropolitan Trial Court which

has jurisdiction to try and adjudicate the alleged violation of the Truth in

Lending Act, considering that the present action allegedly involved a single

credit transaction as there was only one Promissory Note Line.

89

90

Page 57: 2007 casesROBERTO C

We disagree. We have already ruled that the action to recover the

penalty under Section 6(a) of the Truth in Lending Act had been jointly

instituted with (1) the action to declare the interests in the promissory notes

void, and (2) the action to declare the foreclosure void. There had been no

question that the above actions belong to the jurisdiction of the RTC.

Subsection (c) of the above-quoted Section 5 of the Rules of Court on

Joinder of Causes of Action provides:

(c) Where the causes of action are between the same parties but pertain to different venues or jurisdictions, the joinder may be allowed in the Regional Trial Court provided one of the causes of action falls within the jurisdiction of said court and the venue lies therein.

Furthermore, opening a credit line does not create a credit transaction

of loan or mutuum, since the former is merely a preparatory contract to the

contract of loan or mutuum. Under such credit line, the bank is merely

obliged, for the considerations specified therefor, to lend to the other party

amounts not exceeding the limit provided. The credit transaction thus

occurred not when the credit line was opened, but rather when the credit line

was availed of. In the case at bar, the violation of the Truth in Lending Act

allegedly occurred not when the parties executed the Credit Agreement,

where no interest rate was mentioned, but when the parties executed the

promissory notes, where the allegedly offending interest rate was stipulated.

UCPB further argues that since the spouses Beluso were duly given

copies of the subject promissory notes after their execution, then they were

Page 58: 2007 casesROBERTO C

duly notified of the terms thereof, in substantial compliance with the Truth

in Lending Act.

Once more, we disagree. Section 4 of the Truth in Lending Act

clearly provides that the disclosure statement must be furnished prior to the

consummation of the transaction:

SEC. 4. Any creditor shall furnish to each person to whom credit is extended, prior to the consummation of the transaction, a clear statement in writing setting forth, to the extent applicable and in accordance with rules and regulations prescribed by the Board, the following information:

(1) the cash price or delivered price of the property or service to be acquired;

(2) the amounts, if any, to be credited as down payment and/or trade-in;

(3) the difference between the amounts set forth under clauses (1) and (2)

(4) the charges, individually itemized, which are paid or to be paid by such person in connection with the transaction but which are not incident to the extension of credit;

(5) the total amount to be financed;

(6) the finance charge expressed in terms of pesos and centavos; and

(7) the percentage that the finance bears to the total amount to be financed expressed as a simple annual rate on the outstanding unpaid balance of the obligation.

The rationale of this provision is to protect users of credit from a lack

of awareness of the true cost thereof, proceeding from the experience that

banks are able to conceal such true cost by hidden charges, uncertainty of

Page 59: 2007 casesROBERTO C

interest rates, deduction of interests from the loaned amount, and the like.

The law thereby seeks to protect debtors by permitting them to fully

appreciate the true cost of their loan, to enable them to give full consent to

the contract, and to properly evaluate their options in arriving at business

decisions. Upholding UCPB’s claim of substantial compliance would defeat

these purposes of the Truth in Lending Act. The belated discovery of the

true cost of credit will too often not be able to reverse the ill effects of an

already consummated business decision.

In addition, the promissory notes, the copies of which were presented

to the spouses Beluso after execution, are not sufficient notification from

UCPB. As earlier discussed, the interest rate provision therein does not

sufficiently indicate with particularity the interest rate to be applied to the

loan covered by said promissory notes.

Forum Shopping

UCPB had earlier moved to dismiss the petition (originally Case No.

99-314 in RTC, Makati City) on the ground that the spouses Beluso

instituted another case (Civil Case No. V-7227) before the RTC of Roxas

City, involving the same parties and issues. UCPB claims that while Civil

Case No. V-7227 initially appears to be a different action, as it prayed for

the issuance of a temporary restraining order and/or injunction to stop

foreclosure of spouses Beluso’s properties, it poses issues which are similar

to those of the present case.91[43] To prove its point, UCPB cited the spouses

Beluso’s Amended Petition in Civil Case No. V-7227, which contains

91

Page 60: 2007 casesROBERTO C

similar allegations as those in the present case. The RTC of Makati denied

UCPB’s Motion to Dismiss Case No. 99-314 for lack of merit. Petitioner

UCPB raised the same issue with the Court of Appeals, and is raising the

same issue with us now.

The spouses Beluso claim that the issue in Civil Case No. V-7227

before the RTC of Roxas City, a Petition for Injunction Against Foreclosure,

is the propriety of the foreclosure before the true account of spouses Beluso

is determined. On the other hand, the issue in Case No. 99-314 before the

RTC of Makati City is the validity of the interest rate provision. The

spouses Beluso claim that Civil Case No. V-7227 has become moot because,

before the RTC of Roxas City could act on the restraining order, UCPB

proceeded with the foreclosure and auction sale. As the act sought to be

restrained by Civil Case No. V-7227 has already been accomplished, the

spouses Beluso had to file a different action, that of Annulment of the

Foreclosure Sale, Case No. 99-314 with the RTC, Makati City.

Even if we assume for the sake of argument, however, that only one

cause of action is involved in the two civil actions, namely, the violation of

the right of the spouses Beluso not to have their property foreclosed for an

amount they do not owe, the Rules of Court nevertheless allows the filing of

the second action. Civil Case No. V-7227 was dismissed by the RTC of

Roxas City before the filing of Case No. 99-314 with the RTC of Makati

City, since the venue of litigation as provided for in the Credit Agreement is

in Makati City.

Page 61: 2007 casesROBERTO C

Rule 16, Section 5 bars the refiling of an action previously dismissed

only in the following instances:

SEC. 5. Effect of dismissal.—Subject to the right of appeal, an order granting a motion to dismiss based on paragraphs (f), (h) and (i) of section 1 hereof shall bar the refiling of the same action or claim. (n)

Improper venue as a ground for the dismissal of an action is found in

paragraph (c) of Section 1, not in paragraphs (f), (h) and (i):

SECTION 1. Grounds.—Within the time for but before filing the answer to the complaint or pleading asserting a claim, a motion to dismiss may be made on any of the following grounds:

(a) That the court has no jurisdiction over the person of the defending party;

(b) That the court has no jurisdiction over the subject matter of the claim;

(c) That venue is improperly laid;

(d) That the plaintiff has no legal capacity to sue;

(e) That there is another action pending between the same parties for the same cause;

(f) That the cause of action is barred by a prior judgment or by the statute of limitations;

(g) That the pleading asserting the claim states no cause of action;

(h) That the claim or demand set forth in the plaintiff’s pleading has been paid, waived, abandoned, or otherwise extinguished;

(i) That the claim on which the action is founded is unenforceable under the provisions of the statute of frauds; and

(j) That a condition precedent for filing the claim has not been

Page 62: 2007 casesROBERTO C

complied with.92[44] (Emphases supplied.)

When an action is dismissed on the motion of the other party, it is

only when the ground for the dismissal of an action is found in paragraphs

(f), (h) and (i) that the action cannot be refiled. As regards all the other

grounds, the complainant is allowed to file same action, but should take care

that, this time, it is filed with the proper court or after the accomplishment of

the erstwhile absent condition precedent, as the case may be.

UCPB, however, brings to the attention of this Court a Motion for

Reconsideration filed by the spouses Beluso on 15 January 1999 with the

RTC of Roxas City, which Motion had not yet been ruled upon when the

spouses Beluso filed Civil Case No. 99-314 with the RTC of Makati.

Hence, there were allegedly two pending actions between the same parties

on the same issue at the time of the filing of Civil Case No. 99-314 on 9

February 1999 with the RTC of Makati. This will still not change our

findings. It is indeed the general rule that in cases where there are two

pending actions between the same parties on the same issue, it should be the

later case that should be dismissed. However, this rule is not absolute.

According to this Court in Allied Banking Corporation v. Court of

Appeals93[45]:

In these cases, it is evident that the first action was filed in anticipation of the filing of the later action and the purpose is to preempt the later suit or provide a basis for seeking the dismissal of the second action.

92

93

Page 63: 2007 casesROBERTO C

Even if this is not the purpose for the filing of the first action, it may nevertheless be dismissed if the later action is the more appropriate vehicle for the ventilation of the issues between the parties. Thus, in Ramos v. Peralta, it was held:

[T]he rule on litis pendentia does not require that the later case should yield to the earlier case. What is required merely is that there be another pending action, not a prior pending action. Considering the broader scope of inquiry involved in Civil Case No. 4102 and the location of the property involved, no error was committed by the lower court in deferring to the Bataan court's jurisdiction.

Given, therefore, the pendency of two actions, the following are the relevant considerations in determining which action should be dismissed: (1) the date of filing, with preference generally given to the first action filed to be retained; (2) whether the action sought to be dismissed was filed merely to preempt the later action or to anticipate its filing and lay the basis for its dismissal; and (3) whether the action is the appropriate vehicle for litigating the issues between the parties.

In the case at bar, Civil Case No. V-7227 before the RTC of Roxas

City was an action for injunction against a foreclosure sale that has already

been held, while Civil Case No. 99-314 before the RTC of Makati City

includes an action for the annulment of said foreclosure, an action certainly

more proper in view of the execution of the foreclosure sale. The former

case was improperly filed in Roxas City, while the latter was filed in Makati

City, the proper venue of the action as mandated by the Credit Agreement.

It is evident, therefore, that Civil Case No. 99-314 is the more appropriate

vehicle for litigating the issues between the parties, as compared to Civil

Case No. V-7227. Thus, we rule that the RTC of Makati City was not in

error in not dismissing Civil Case No. 99-314.

WHEREFORE, the Decision of the Court of Appeals is hereby

AFFIRMED with the following MODIFICATIONS:

Page 64: 2007 casesROBERTO C

1. In addition to the sum of P2,350,000.00 as determined by the

courts a quo, respondent spouses Samuel and Odette Beluso are

also liable for the following amounts:

a. Penalty of 12% per annum on the amount due94[46] from the

date of demand; and

b. Compounded legal interest of 12% per annum on the amount

due95[47] from date of demand;

2. The following amounts shall be deducted from the liability of

the spouses Samuel and Odette Beluso:

a. Payments made by the spouses in the amount of

P763,692.00. These payments shall be applied to the date

of actual payment of the following in the order that they

are listed, to wit:

i. penalty charges due and demandable as of the time of

payment;

ii. interest due and demandable as of the time of

payment;

iii. principal amortization/payment in arrears as of the

time of payment;

iv. outstanding balance.

b. Penalty under Republic Act No. 3765 in the amount of

P26,000.00. This amount shall be deducted from the

liability of the spouses Samuel and Odette Beluso on 9

94

95

Page 65: 2007 casesROBERTO C

February 1999 to the following in the order that they are

listed, to wit:

i. penalty charges due and demandable as of time of

payment;

ii. interest due and demandable as of the time of

payment;

iii. principal amortization/payment in arrears as of the

time of payment;

iv. outstanding balance.

2. The foreclosure of mortgage is hereby declared VALID.

Consequently, the amounts which the Regional Trial Court and

the Court of Appeals ordered respondents to pay, as modified in

this Decision, shall be deducted from the proceeds of the

foreclosure sale.

SO ORDERED.

DIVISION

FIL-ESTATE PROPERTIES, INC.,Petitioner, G.R. No. 165164

Present:

QUISUMBING, J., Chairperson,CARPIO,

Page 66: 2007 casesROBERTO C

- versus - CARPIO MORALES, TINGA, andVELASCO, JR., JJ.

SPOUSES GONZALO and CONSUELO GO,

Respondents.

Promulgated:

August 17, 2007x- - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - -x

RESOLUTION

QUISUMBING, J.:

For review on certiorari are the Decision96[1] dated June 9, 2004 of the

Court of Appeals in CA-G.R. SP No. 79624, and its Resolution97[2] dated

August 3, 2004, denying the motion for reconsideration.

The basic facts in this case are undisputed.

On December 29, 1995, petitioner Fil-Estate Properties, Inc. (Fil-Estate)

entered into a contract to sell a condominium unit to respondent spouses

Gonzalo and Consuelo Go at “Eight Sto. Domingo Place,” a condominium

project of petitioner located on Sto. Domingo Avenue, Quezon City. The

spouses paid a total of P3,439,000.07 of the full contract price set at

P3,620,000.00.

Because petitioner failed to develop the condominium project, on

August 4, 1999, the spouses demanded the refund of the amount they paid,

plus interest. When petitioner did not refund the spouses, the latter filed a

complaint against petitioner for reimbursement of P3,620,000 representing 96

97

Page 67: 2007 casesROBERTO C

the lump sum price of the condominium unit, plus interest, P100,000

attorney’s fees, and expenses of litigation before the Housing and Land Use

Regulatory Board (HLURB).

In answer, petitioner claimed that respondents had no cause of action

since the delay in the construction of the condominium was caused by the

financial crisis that hit the Asian region, a fortuitous event over which

petitioner had no control.

On July 18, 2000, the HLURB Regional Director approved the

decision of the Housing and Land Use Arbiter in favor of the spouses Go.

The HLURB ratiocinated that the Asian financial crisis that resulted in the

depreciation of the peso is not a fortuitous event as any fluctuation in the

value of the peso is a daily occurrence which is foreseeable and its

deleterious effects avoided by economic measures. The HLURB went on to

say that when petitioner discontinued the development of its condominium

project, it failed to fulfill its contractual obligations to the spouses. And

following Article 147598[3] of the Civil Code, upon perfection of the contract,

the parties, here the spouses Go, may demand performance. And under

Article 119199[4] of the same code, should one of the parties, in this instance

Fil-Estate, fail to comply with the obligation, the aggrieved party may

choose between fulfillment or rescission of the obligation, with damages in

either case. Inasmuch as Fil-Estate could no longer fulfill its obligation, the

spouses Go may ask for rescission of the contract with damages. The

dispositive portion of the decision reads:

98

99

Page 68: 2007 casesROBERTO C

WHEREFORE, the foregoing considered, judgment is hereby rendered as follows:

1. Ordering the respondent, Fil-Estate Properties, Inc., to refund to the complainants, P3,439,000.07 (the amount proved) plus 12% interest thereon reckoned from 09 August 1999 (the date the respondent received the demand letter) until the same is fully paid.

2. Ordering the respondent to pay to the complainants P25,000.00 attorney’s fees as and by way of damages.

All other claims and counterclaims are dismissed.

IT IS SO ORDERED.100[5]

The Board of Commissioners of the HLURB denied petitioner’s

petition for review and consequent motion for reconsideration.101[6] The

Office of the President dismissed petitioner’s appeal and denied its motion

for reconsideration.102[7]

On appeal, asserting that both the HLURB and the Office of the

President committed reversible errors, Fil-Estate asked the Court of Appeals

to set aside the orders it is appealing.

The Court of Appeals affirmed the actions taken by the HLURB and

the Office of the President and declared that the Asian financial crisis could

not be considered a fortuitous event and that respondents’ right is provided

for in Section 23103[8] of Presidential Decree (P.D.) No. 957, otherwise

known as “The Subdivision and Condominium Buyers’ Protective Decree.”

The appellate court also noted that there was yet no crisis in 1995 and 1996

when the project should have been started, and petitioner cannot blame the

100

101

102

103

Page 69: 2007 casesROBERTO C

1997 crisis for failure of the project, nor for even not starting it, because the

project should have been completed by 1997.

The appellate court denied petitioner’s motion for reconsideration.

Hence, this petition raising two issues for our resolution as follows:

I.

THE HONORABLE COURT OF APPEALS ERRED IN HOLDING THAT THE ASIAN FINANCIAL CRISIS IS NOT A FORTUITOUS EVENT THAT WOULD EXCUSE THE DELIVERY BY PETITIONER OF THE SUBJECT CONDOMINIUM UNIT TO RESPONDENTS.

II.

THE HONORABLE COURT OF APPEALS ERRED IN HOLDING PETITIONER LIABLE FOR THE PAYMENT OF ATTORNEY’S FEES.104[9]

On the first issue, did the Court of Appeals err in ruling that the Asian

financial crisis was not a fortuitous event?

Petitioner, citing Article 1174105[10] of the Civil Code, argues that the

Asian financial crisis was a fortuitous event being unforeseen or inevitable.

Petitioner likewise cites Servando v. Philippine Steam Navigation Co.,106[11]

to bolster its case. Petitioner explains that the extreme economic exigency

and extraordinary currency fluctuations could not have been reasonably

foreseen and were beyond the contemplation of both parties when they

entered the contract. Petitioner further asserts that the resultant economic

collapse of the real estate industry was unforeseen by the whole Asia and if

104

105

106

Page 70: 2007 casesROBERTO C

it was indeed foreseeable, then all those engaged in the real estate business

should have foreseen the impending fiasco. Petitioner adds that it had not

committed any fraud; that it had all the required government permits; and

that it had not abandoned the project but only suspended the work. It also

admits its obligation to complete the project. It says that it had in fact asked

the HLURB for extension to complete it.107[12]

In their Comment, respondents submit that the instant petition be

rejected outright for the reason that petitioner has not raised any question of

law in the instant petition. The questions of whether or not the Asian

financial crisis is a fortuitous event, and whether or not attorney’s fees

should be granted, are questions of facts which the Court of Appeals

recognized as such.

Respondent spouses reiterate that contrary to what petitioner avers,

the delay in the construction of the building was not attributable to the Asian

financial crisis which happened in 1997108[13] because petitioner did not even

start the project in 1995 when it should have done, so that it could have

finished it in 1997, as stipulated in the contract.

Preliminarily, respondents bring to the attention of this Court the

strange discrepancy in the dates of notarization of the Certification of Non-

Forum Shopping and the Affidavit of Service both notarized on September

24, 2004, while the Secretary’s Certification was notarized a day earlier on

September 23, 2004. However, we shall not delve into technicalities, but we

shall proceed with the resolution of the issues raised on the merits.

107

108

Page 71: 2007 casesROBERTO C

Indeed, the question of whether or not an event is fortuitous is a

question of fact. As a general rule, questions of fact may not be raised in a

petition for review for as long as there is no variance between the findings of

the lower court and the appellate court, as in this case where the HLURB,

the Office of the President, and the Court of Appeals were agreed on the

fact.

Worthy of note, in a previous case, Asian Construction and

Development Corporation v. Philippine Commercial International Bank,109

[14] the Court had said that the 1997 financial crisis that ensued in Asia did

not constitute a valid justification to renege on obligations. We emphatically

stressed the same view in Mondragon Leisure and Resorts Corporation v.

Court of Appeals,110[15] that the Asian financial crisis in 1997 is not among

the fortuitous events contemplated under Article 1174 of the Civil Code.

Also, we cannot generalize that the Asian financial crisis in 1997 was

unforeseeable and beyond the control of a business corporation. It is

unfortunate that petitioner apparently met with considerable difficulty e.g.

increase cost of materials and labor, even before the scheduled

commencement of its real estate project as early as 1995. However, a real

estate enterprise engaged in the pre-selling of condominium units is

concededly a master in projections on commodities and currency movements

and business risks. The fluctuating movement of the Philippine peso in the

foreign exchange market is an everyday occurrence, and fluctuations in

currency exchange rates happen everyday, thus, not an instance of caso

fortuito.

109

110

Page 72: 2007 casesROBERTO C

Are respondents entitled to reimbursement of the amount paid, plus

interest and attorney’s fees?

Yes. Section 23 of P.D. No. 957 is clear on this point.

It will be noted that respondents sent a demand letter dated August 4,

1999 to Fil-Estate asking for the return of “the total amount paid including

amortization interests” and “legal interest due thereon.”111[16] The latter did

not respond favorably, and so the spouses filed a complaint demanding the

reimbursement of P3,620,000 representing the lump sum price of the

condominium unit with interest at the legal rate, and P100,000 attorney’s

fees. But the respondents actually sought the refund of P3,620,000.00, the

lump sum cost of the condominium, more than their actual payment of

P3,439,000.07. We are thus constrained to award only P3,439,000.07,

representing the sum of their actual payments plus amortization interests and

interest at legal rate which is 6% per annum from the date of demand on

August 4, 1999. We are not unaware that the appellate court pegged the

interest rate at 12% on the basis of Resolution No. R-421, Series of 1988 of

the HLURB. But, conformably with our ruling in Eastern Shipping Lines,

Inc. v. Court of Appeals,112[17] the award of 12% interest on the amount of

refund must be reduced to 6%.

Moreover, we are constrained to modify the Court of Appeals’ grant

of attorney’s fees from P25,000 to P100,000 as just and equitable since

respondents were compelled to secure the services of counsel over eight

111

112

Page 73: 2007 casesROBERTO C

years to protect their interest due to petitioner’s delay in the performance of

their clear obligation.

WHEREFORE, the petition is DENIED for lack of merit. Petitioner

is hereby ordered (1) to reimburse respondents P3,439,000.07 at 6% interest

starting August 4, 1999 until full payment, and (2) to pay respondents

P100,000.00 attorney’s fees. Costs against petitioner.

SO ORDERED.

UNIWIDE SALES, INC., Petitioner,

-versus-

MIRAFUENTE & NG, INC., Respondent.

G.R. No. 172454

Present:

QUISUMBING, J., Chairperson, CARPIO,CARPIO MORALES, TINGA, andVELASCO, JR., JJ.

Promulgated:

August 17, 2007

x - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - -- - - - - - - - - - x

D E C I S I O N

CARPIO MORALES, J.:

Page 74: 2007 casesROBERTO C

Uniwide Sales, Inc. (petitioner) and Mirafuente and Ng, Inc.

(respondent), represented by Architect Robert Mirafuente, forged on

December 13, 1993 a “DESIGN SERVICES: ARCHITECTURAL

SERVICES AGREEMENT”113[1] (the agreement) whereby petitioner

engaged respondent “to plan and design the proposed UNIWIDE SALES

MALL” located at a 10-hectare lot along Roxas Boulevard, Parañaque for a

consideration of Two Million Five Hundred Thousand (P2,500,000) Pesos

“for Architectural Design Service only.” The pertinent portions of the

agreement read:

ARTICLE 1 SCOPE OF WORK

That the scope of work to be done by the Architect, as herein authorized by the Owner, for the subject Project herein referred to consist of professional services for the preparation, planning, design and documentation for architectural drawings of the project. The work is deemed ninety five percent (95%) complete upon submission of complete working drawings and documents for construction. The last five percent (5%) consist of task required during the construction phase as stipulated in this contract.

x x x x

ARTICLE 2 ARCHITECT FEES AND MANNER OF PAYMENTS

The Owner shall pay the Architect TWO MILLION FIVE HUNDRED THOUSAND PESOS (P2,500,000.00) as compensation for the Architectural Design Service only.

x x x x

Payments of the Architectural Design Fee shall be made in accordance with the following schedule:

113

Page 75: 2007 casesROBERTO C

Signing of this Agreement Ten percent (10%)

Schematic Design Phase Fifteen percent (15%)Pro-rata to completed phase

Design Development Phase Thirty Five Percent (35%)Pro-rata to completed phase

Construction Document Phase Thirty Five Percent (35%)Pro-rata to completed phase

Construction Phase Five Percent (5%)Pro-rata to contractor’s payment

_____________________________________________________TOTAL One Hundred Percent 100%

The Owner agrees to make partial payments during each of the various stages of the Design Architect’s work upon his request, provided it is within the framework of the schedule of payments outlined above.

x x x x

x x x x

ARTICLE 5 OTHER EXPENSES CHARGEABLE TO OWNER

x x x x

Work Suspended or abandoned: If the work of the Architect is abandoned or suspended, in whole or in part, due to causes not attributable to the Architect, the Architect is to be paid by the Owner for services rendered corresponding to the fees due on the stage of suspension or abandonment of work.

Change Order by Owner: If changes occur after the final design has been approved and confirmed, or changes and additions during construction, then the Architect is to be paid by the Owner for additional services rendered equivalent to six (6) percent of revised construction cost of the affected design submitted by the Contractor concerned.

x x x x114[2] (Emphasis in the original; italics and underscoring supplied)

114

Page 76: 2007 casesROBERTO C

The agreement contained no provision within which respondent was

to accomplish its services.

By letter of August 16, 1995 signed by respondent’s Production

Manager Architect Leo Villamor and noted by Architect Mirafuente,

respondent submitted to petitioner, “Attn. Mr. Jimmy Gow, Chairman,”

x x x x

. . . copies of the Master Plans (e.g. Ground, Second and Third) of the latest plans of above project showing all the changes we have agreed including the changes made from last meeting with your interior design group at City Garden Restaurants.115[3]

In the same letter, respondent informed that it had “submitted the

same plans together with the complete package of all Architectural plans (1

set) to Arch. Rene De Guzman on August 9, 1995 (TR# BS 00183) to cover

our Change Order.”

Petitioner, however, through its consultant Asian Technicon Managers

& Consultants, Inc., by letter of August 22, 1995 which was received on

August 23, 1995 by respondent, terminated the latter’s services. The notice

of termination reads:

Subject: THE COASTAL MALL PROJECT NOTICE OF CONTRACT TERMINATION

1. Further to our verbal instruction given to you on 08 August 1995 that all your works be put on-hold, the Owner has finally decided to stop

115

Page 77: 2007 casesROBERTO C

all the works immediately and terminate your Consultancy Services for the preparation, planning, design and documentation for Architectural drawings of the Project.

2. We hereby serve this Notice of Termination with immediate effect and the Owner will be very grateful to receive from you (if any) all documents and data that have been developed for this project.

3. To properly close the contract, you are requested to submit your final statement of account relative to this project . Your usual cooperation is appreciated.116[4] (Emphasis and underscoring supplied )

Respondent thereafter sent petitioner a letter of September 18, 1995

following up its “billing amounting to FOUR HUNDRED THOUSAND

PESOS (P400,000.00) representing full payment for the Change Order

requested by Owner.” It also sent another letter of even date following up its

“billing amounting to FOUR HUNDRED THIRTY SEVEN THOUSAND

FIVE HUNDRED PESOS (P437,500.00) representing full payment for the

Construction Document Phase-Architectural Design Fee.”117[5] These letters

were telefaxed to petitioner on October 19, 1995.

As respondent’s demands were not acted upon by petitioner,

respondent, by letter of December 15, 1995, again demanded payment for its

services, particularly for the “Construction Document Phase” and for the

“Change Order,” in the amounts of P437,500 and P400,000, respectively.

Through its Chairman of the Board Jimmy Gow, petitioner replied by letter

of December 20, 1995 reading:

Dear Arch. Mirafuente:

116

117

Page 78: 2007 casesROBERTO C

I refer to your letter of December 15, 1995 demanding payment from our firm of the amount of Eight Hundred Thirty Seven Thousand Five Hundred Pesos (Php 837,500.00) for the Uniwide Coastal Mall Project.

Please be advised that we are still in the process of reconciling our records. We would, therefore, appreciate it if you can provide us with the supporting documents for said amount.

We will revert to you as soon as we receive your inputs and our records have been reconciled.

Thank you and may you have a Merry Christmas!118[6] (Emphasis and underscoring supplied)

Its demands for the payment of its services having remained

unheeded, respondent filed on February 27, 1996 with the Regional Trial

Court (RTC) of Pasig a complaint for sum of money – P437,500

representing payment due on the “Construction Document Phase” of the

project, and P400,000 representing payment due on the “Change Order,”

plus interest thereon at the rate of 24% per annum from August 9, 1995 until

petitioner pays its obligation; attorney’s fees equivalent to 25% of the

amounts due and demandable; and costs of suit.119[7]

Branch 155 of the Pasig RTC found for respondent by Decision of

June 19, 2001, ordering petitioner to pay it the following:

1. PhP837,500.00 representing the total amount of unpaid architectural fees owing to the plaintiff, plus legal interest of 6% per annum from the date of extra-judicial demand until the finality of the herein Decision;

2. Peso equivalent of 25% of the amount due and collectible as and by way of attorney’s fees; and,

118

119

Page 79: 2007 casesROBERTO C

3. The costs of suit.120[8]

On appeal, the Court of Appeals, by Decision of November 14,

2005,121[9] affirmed the trial court’s decision.

In affirming the trial court’s decision, the appellate court found that

respondent submitted to petitioner the complete and final set of architectural

designs, plans and specifications prior to the termination of its services,122[10]

but the termination appeared to be a mere ploy of petitioner to avoid its

obligation to pay respondent’s fees.123[11]

The appellate court went on to note that petitioner never presented any

proof showing that it was dissatisfied with respondent’s services,124[12] for if

it was, it could have, early on, terminated the same without waiting for

respondent to complete its undertakings under the agreement.

The appellate court even noted that at the time petitioner terminated

respondent’s services, the construction of the mall had already begun.125[13]

Hence, the present petition, petitioner faulting the appellate court:

120

121

122

123

124

125

Page 80: 2007 casesROBERTO C

1. . . . IN HOLDING THAT THE PETITIONER WAS NOT ABLE TO SUFFICIENTLY PROVE ITS DEFENSE AGAINST THE CLAIM OF THE RESPONDENT.

2. . . . IN HOLDING THAT THE RESPONDENT WAS ABLE TO SUBMIT TO THE PETITIONER THE COMPLETE AND FINAL SET OF ARCHITECTURAL DESIGNS, PLANS AND SPECIFICATIONS PRIOR TO THE TERMINATION OF ITS SERVICES BY THE PETITIONER.

3. . . . [IN] DECID[ING] THE CASE IN A WAY NOT IN ACCORD WITH LAW AND THE APPLICABLE DECISIONS OF THE SUPREME COURT.126[14]

Petitioner urges this Court to take exception to the rule that in a

petition filed under Rule 45, such as the one at bar, only questions of law are

allowed for, so petitioner contends, the inference made by the Court of

Appeals from its findings of fact is manifestly erroneous or absurd.127[15]

Petitioner insists that respondent failed to fulfill its obligations under

the agreement, hence, it is justified in refusing to heed respondent’s

monetary claims.128[16]

Specifically, petitioner alleges that despite its verbal agreement with

respondent that the plans should be submitted within six (6) months from the

signing of the agreement,129[17] respondent complied with it only after a year

and a half. And petitioner emphasizes that when respondent transmitted the

architectural design and plans on August 9, 1995 (to petitioner’s Architect

de Guzman) and August 16, 1995 (to petitioner’s Chairman Jimmy Gow), its

126

127

128

129

Page 81: 2007 casesROBERTO C

Chairman Jimmy Gow had in June 1995 verbally terminated respondent’s

services.

The petition fails.

The resolution of the petition hinges on a determination of whether

the termination of the agreement by petitioner was made prior to

respondent’s compliance with its undertakings thereunder.

By petitioner’s own admission, the petition raises a factual issue

which is beyond the ambit of the present petition under Rule 45.

Both the trial and appellate courts found that the architectural design

prepared by respondent was delivered to petitioner before the termination of

the agreement. Absent any sufficient and convincing evidence to the

contrary, such finding binds this Court as it is supported by sufficient

evidence.

Albeit this Court entertains factual determination of a case brought to

it via Rule 45 under certain circumstances, e.g. (a) where there is grave

abuse of discretion; (b) when the finding is grounded entirely on

speculations, surmises or conjectures; (c) when the inference made is

manifestly mistaken, absurd or impossible; (d) when the judgment of the

Court of Appeals was based on a misapprehension of facts; (e) when the

factual findings are themselves conflicting; (f) when the Court of Appeals, in

making its findings, went beyond the issues of the case and the same are

contrary to the admissions of both appellant and appellee; (g) when the

Court of Appeals manifestly overlooked certain relevant facts not disputed

Page 82: 2007 casesROBERTO C

by the parties and which, if properly considered, would justify a different

conclusion; (h) where the findings of fact of the Court of Appeals are

contrary to those of the trial court; (i) where the findings of fact are mere

conclusions without citation of specific evidence on which they are based;

and (j) where the findings of fact of the Court of Appeals are premised on

the absence of evidence and are contradicted by the evidence on record,130[18]

the petition at bar does not present any similar or analogous circumstance.

As noted earlier, the agreement forged by the parties does not provide

for a period within which respondent has to accomplish its undertakings

thereunder. Petitioner claims, however, that there was a verbal agreement

with respondent that the architectural design should be finalized and

approved by petitioner within six (6) months from signing of their written

agreement. Why the parties did not incorporate in the agreement this

alleged period within which respondent had to accomplish its services

escapes comprehension.

At any rate, if indeed the parties verbally agreed to a period of six

months for respondent to comply with its undertakings, why did not

petitioner immediately seek the enforcement of such alleged verbal

agreement when the period expired on June 13, 1994 or, in the alternative,

terminate respondent’s services? Why did not petitioner reject the

documents sent by respondent on August 9, 1995? Why did not petitioner,

in its earlier-quoted December 20, 1995 reply-letter to respondent, complain

of respondent’s alleged delay in complying with its undertakings within the

alleged verbally agreed six-month period? Such glaring omissions negate

130

Page 83: 2007 casesROBERTO C

petitioner’s claim of having verbally agreed with respondent delimiting the

latter’s period of compliance with its undertakings to six months.

But even assuming that there was indeed such verbal agreement,

petitioner is estopped from enforcing the same, it having continued to deal

with petitioner on the project even after the expiration of the six-month

period by, inter alia, recommending revisions of the design and paying

respondent’s services for the first two phases of the project schedule.131[19]

As for petitioner’s claim that it had, in June 1995, verbally ordered

respondent to stop and cease all its activities relating to the design132[20] of the

mall, albeit it sent the formal notice of termination on August 22, 1995

which was received by respondent the following day, August 23, 1995, the

same fails. The notice of termination does not refer to a verbal advice of

termination in June 1995. Instead, it refers to an August 8, 1995 advice to

respondent for it to “put on hold [respondent’s] works.” “[P]ut[ting] on

hold” is not equivalent to termination.

In fact, the August 22, 1995 notice of termination of services did not

specify the ground behind such termination.

Petitioner was to later claim that it terminated the services of

respondent due to “material deficiencies in the architectural design

proposals” submitted on August 9, 1995. But did it not earlier claim that it

had priorly terminated respondent’s services in June 1995 or on August 8,

1995?

131

132

Page 84: 2007 casesROBERTO C

Additionally, if indeed petitioner verbally terminated the agreement as

early as June 1995, why did it still send a representative to attend the

meeting with respondent’s representatives on July 18, 1995 at City Garden

Restaurant to discuss revisions of the design, which revisions were

subsequently incorporated in the architectural drawing package transmitted

to petitioner on August 9, 1995?133[21]

Even petitioner’s witness Jaime Rioflorido of Asian Technicon, the

project manager for the mall, admitted that at the time said company took

over as project manager in July 1995, “[he] saw that the substructure works,

meaning the bored piles [sic], were substantially completed.”134[22] Such

admission shows that the mall project had been started by petitioner using

the plan prepared by respondent for, as said witness declared, the new

architect was appointed only in November 1995.135[23]

Without doubt, respondent had discharged its obligation under the

agreement prior to the termination of its services by petitioner on August 22,

1995.

For petitioner to terminate the agreement after respondent had

complied with its obligation under the agreement violates Article 1159 of

the New Civil Code which provides that “[o]bligations arising from

contracts have the force of law between the contracting parties and should be

complied with in good faith.”

133

134

135

Page 85: 2007 casesROBERTO C

WHEREFORE, the Court of Appeals Decision of November 14,

2005 is AFFIRMED.

Costs against petitioner.

SO ORDERED.

LICOMCEN INCORPORATED,Petitioner,

- versus -

FOUNDATION SPECIALISTS, INC.,Respondent.

x ------------------------------------------xFOUNDATION SPECIALISTS, INC.,

Petitioner,

- versus -

LICOMCEN INCORPORATED and COURT OF APPEALS,

Respondents.

G.R. No. 167022

G.R. No. 169678

Present:

YNARES-SANTIAGO, J., Chairperson,AUSTRIA-MARTINEZ,CHICO-NAZARIO, NACHURA, andREYES, JJ.

Promulgated:

August 31, 2007

Page 86: 2007 casesROBERTO C

x------------------------------------------------------------------------------------x

DECISION

NACHURA, J.:

For review in these consolidated petitions is the November 23, 2004

Decision136[1] of the Court of Appeals (CA) in CA-G.R. SP. No. 78218, as

well as the Resolutions dated February 4, 2005137[2] and September 13,

2005,138[3] denying the motions for its reconsideration.

Liberty Commercial Center, Inc. (LICOMCEN) is a corporation

engaged in the business of operating shopping malls. In March 1997, the

City Government of Legaspi leased its lot in the Central District of Legaspi

to LICOMCEN. The Lease Contract was based on the Build-Operate-

Transfer Scheme under which LICOMCEN will finance, develop and

construct the LCC City Mall (CITIMALL). LICOMCEN engaged E.S. De

Castro and Associates (ESCA) as its engineering consultant for the project.

On September 1, 1997, LICOMCEN and Foundation Specialist, Inc.

(FSI) signed a Construction Agreement for the bored pile foundation of

CITIMALL.139[4] Forming part of the agreement were the Bid Documents

and the General Conditions of Contract (GCC)140[5] prepared by ESCA. A

salient provision of the GCC is the authority granted the engineering

consultant to suspend the work, wholly or partly. LICOMCEN was also

136

137

138

139

140

Page 87: 2007 casesROBERTO C

given the right to suspend the work or terminate the contract. Among other

caveats, GC-05 provided that questions arising out or in connection with the

contract or its breach should be litigated in the courts of Legaspi, except

where otherwise stated, or when such question is submitted for settlement

through arbitration. GC-61 also provided that disputes arising out of the

execution of the work should first be submitted to LICOMCEN for

resolution, whose decision shall be final and binding, if not contested within

thirty (30) days from receipt. Otherwise, the dispute shall be submitted to

the Construction Industry Arbitration Commission (CIAC) for arbitration.

Upon receipt of the notice to proceed, FSI commenced work and

undertook to complete it within ninety (90) days, all in accordance with the

approved drawing, plans, and specifications.

In the course of the construction, LICOMCEN revised the design for

the CITIMALL involving changes in the bored piles and substantial

reduction in number and length of the piles. ESCA, thus, informed FSI of

the major revision on December 16, 1997141[6] and ordered the non-delivery

of the steel bars, pending approval of the new design. FSI, however,

responded that the steel bars had already been loaded and shipped out of

Manila. ESCA then suggested the delivery of 50% of the steel bars to the

jobsite and the return of the other 50% to Manila, where storage and security

were better.142[7]

141

142

Page 88: 2007 casesROBERTO C

On January 15, 1998, LICOMCEN sent another letter to FSI ordering

all the construction activities suspended, because Albay Accredited

Constructions Association (AACA) had contested the award of the Contract

of Lease to LICOMCEN and filed criminal complaints with the Office of the

Ombudsman for violation of the Anti-Graft and Corrupt Practices Act

against LICOMCEN and the City Government of Legaspi. Thus, pending a

clear resolution of the case, LICOMCEN decided to suspend all construction

activities. It also requested FSI not to unload the steel bars.143[8]

On January 17, 1998, the steel bars for the CITIMALL arrived at the

Legaspi port, and despite LICOMCEN’s previous request, these were

unloaded and delivered to the jobsite and some to Tuanzon compound,144[9]

FSI’s batching site. Then, on January 19, 1998, LICOMCEN reiterated its

decision to suspend construction, and ordered demobilization of the

materials and equipment for the project.145[10] Finally, on February 17, 1998,

LICOMCEN indefinitely suspended the project, due to the pending cases in

the Ombudsman.146[11]

FSI demanded payment for its work accomplishments, material costs,

and standby off equipment, as well as other expenses amounting to

P22,667,026.97,147[12] but LICOMCEN took no heed.

On October 12, 1998, the Ombudsman dismissed the cases filed

against the City Government and LICOMCEN. The dismissal was affirmed 143

144

145

146

147

Page 89: 2007 casesROBERTO C

by this Court148[13] and attained finality on September 20, 2000.149[14] This

notwithstanding, LICOMCEN did not lift the suspension of the construction

that it previously ordered. It then hired Designtech Consultants and

Management System (Designtech) as its new project consultant, which, in

turn, invited contractors, including FSI, to bid for the bored piling works for

CITIMALL.150[15]

FSI reiterated its demand for payment from LICOMCEN, but the

latter failed and refused to pay, prompting FSI to file a petition for

arbitration with the CIAC, docketed as CIAC Case No. 37-2002.

LICOMCEN denied the claim of FSI, arguing that it lacks factual and

legal basis. It also assailed the jurisdiction of the CIAC to take cognizance

of the suit, claiming that jurisdiction over the controversy was vested in the

regular courts, and that arbitration under the GC-61 of the GCC may only be

resorted to if the dispute concerns the execution of works, not if it concerns

breach of contract.

During the preliminary conference, the parties agreed to submit the

controversy to the Arbitral Tribunal and signed the Terms of Reference

(TOR).151[16] But on February 4, 2003, LICOMCEN, through a collaborating

counsel, filed an Ex Abundati Ad Cautela Omnibus Motion.152[17] It

reiterated the claim that the arbitration clause in the contract does not cover

claims for payment of unrealized profits and damages, and FSI did not 148

149

150

151

152

Page 90: 2007 casesROBERTO C

comply with the condition precedent for the filing of the suit, thus, the CIAC

cannot take cognizance of the suit. LICOMCEN further averred that FSI has

no cause of action against it because the claim for material costs has no

factual basis and because the contract is clear that FSI cannot claim damages

beyond the actual work accomplishments, but only reasonable expenses for

the suspension or termination of the contract. LICOMCEN also alleged that

the expenses incurred by FSI, if there be any, cannot be considered

reasonable, because there was no showing that the materials were ordered

and actually delivered to the job site. Finally, it prayed for the suspension of

the proceedings, pending the resolution of its omnibus motion.

On February 20, 2003, the CIAC issued an Order153[18] denying

LICOMCEN’s omnibus motion on the ground that it runs counter to the

stipulations in the TOR. Trial, thereafter, ensued. FSI and LICOMCEN

presented witnesses in support of their respective claims.

After due proceedings, the CIAC rendered a Decision154[19] in favor of

FSI, the dispositive portion of which reads:

WHEREFORE, premises considered, judgment is hereby rendered in favor of Claimant FOUNDATION SPECIALIST, INC. and against Respondent LICOMCEN, INCORPORATED, ordering the latter to pay to the former the following amounts:

1. P14,643,638. 51 representing material costs at site;2. P2,957,989.94 representing payment for equipment and labor

standby costs;3. P5,120,000.00 representing unrealized profit; and4. P1,264,404.12 representing the unpaid balance of FSI's billing.

153

154

Page 91: 2007 casesROBERTO C

FURTHER, the said Respondent is ordered to solely and exclusively bear the entire cost of arbitration proceedings in the total amount of P474,407.95 as indicated in the TOR, and to reimburse the herein Claimant of any amount thereof which it had advanced and paid pursuant to TOR.

All the above-awarded amounts shall bear interest of 6% per annum from the date of the formal demand on February 3, 1998 (Par. 10, Admitted Facts, TOR) until the date this Decision/Award becomes final and executory and 12% per annum from the date this Decision/Award becomes final and executory until fully paid.

SO ORDERED.155[20]

LICOMCEN elevated the CIAC Decision to the CA. It faulted the

CIAC for taking cognizance of the case, arguing that it has no jurisdiction

over the suit. It also assailed the award and the ruling that the contract had

been terminated, allegedly for lack of factual and legal basis.

On November 23, 2004, the CA rendered the assailed Decision,

modifying the CIAC Decision, viz.:

WHEREFORE, the foregoing considered, the assailed Decision is hereby MODIFIED to the extent that paragraph 1 of the dispositive portion is amended and accordingly, petitioner is ordered to pay only the amount of P5,694,939.865 representing the material costs at site; and paragraphs 2 and 3 on equipment and labor standby costs and unrealized profit of the same dispositive portion are deleted. The rest is AFFIRMED in all respects. No costs.

SO ORDERED.156[21]

155

156

Page 92: 2007 casesROBERTO C

Both LICOMCEN and FSI filed motions for partial reconsideration, but

these were denied by the CA in its Resolutions dated February 4, 2005157[22]

and September 13, 2005.158[23]

LICOMCEN and FSI reacted with the instant petitions. Considering

that the cases involve the same parties, issues and assailed decision, this

Court ordered the consolidation of G.R. No. 167022 and G.R. No. 169678 in

its Resolution dated November 20, 2006.

LICOMCEN raised the following issues:

1.

WHETHER OR NOT THE PROJECT WAS MERELY SUSPENDED AND NOT TERMINATED.

2.

WHETHER OR NOT THE TRIBUNAL HAD JURISDICTION OVER THE DISPUTE.

3.

WHETHER OR NOT FSI IS ENTITLED TO CLAIM ANY AMOUNT OF DAMAGES.

4.

WHETHER OR NOT LICOMCEN IS THE PARTY AT FAULT.159[24]

157

158

159

Page 93: 2007 casesROBERTO C

FSI, on the other hand, interposes the following:

1. THE COURT OF APPEALS ERRED IN NOT AWARDING TO PETITIONER THE FULL AMOUNT OF MATERIAL COSTS AT THE SITE.

2. THE COURT OF APPEALS ERRED IN DENYING PETITIONER'S CLAIM FOR EQUIPMENT AND LABOR STANDBY COSTS.

3. THE COURT OF APPEALS ERRED IN DENYING PETITIONER'S CLAIM FOR UNREALIZED PROFIT.

4. THE COURT OF APPEALS ERRED IN RENDERING A MERE MINUTE RESOLUTION IN RESOLVING PETITIONER'S MOTION FOR PARTIAL RECONSIDERATION.160[25]

First, we resolve the issue of the CIAC’s jurisdiction.

LICOMCEN insists that the CIAC had no jurisdiction over the suit.

Citing GC-05 and GC-61 of the GCC, it posits that jurisdiction over the

dispute rests with the regular courts of Legaspi City.

The argument is misplaced.

The power and authority of a court to hear, try, and decide a case is

defined as jurisdiction. Elementary is the distinction between jurisdiction

over the subject matter and jurisdiction over the person. The former is

conferred by the Constitution or by law, while the latter is acquired by virtue

of the party's voluntary submission to the authority of the court through the

exercise of its coercive process.161[26]

160

161

Page 94: 2007 casesROBERTO C

Section 4 of Executive Order (E.O.) No. 1008, or the Construction

Industry Arbitration Law, provides:

SECTION 4. Jurisdiction. — The CIAC shall have original and exclusive jurisdiction over disputes arising from, or connected with, contracts entered into by parties involved in construction in the Philippines, whether the dispute arises before or after the completion of the contract, or after the abandonment or breach thereof. These disputes may involve government or private contracts. For the Board to acquire jurisdiction, the parties to a dispute must agree to submit the same to voluntary arbitration.

The jurisdiction of the CIAC may include but is not limited to violation of specifications for materials and workmanship; violation of the terms of agreement; interpretation and/or application of contractual provisions; amount of damages and penalties; commencement time and delays; maintenance and defects; payment default of employer or contractor and changes in contract cost.

Excluded from the coverage of this law are disputes arising from employer-employee relationships which shall continue to be covered by the Labor Code of the Philippines. (Emphasis supplied)

Corollarily, Section 1, Article III of the Rules of Procedure Governing

Construction Arbitration provides that recourse to the CIAC may be availed

of whenever a contract contains a clause for the submission of a future

controversy to arbitration, thus:

SECTION 1. Submission to CIAC Jurisdiction. — An arbitration clause in a construction contract or a submission to arbitration of a construction dispute shall be deemed an agreement to submit an existing or future controversy to CIAC jurisdiction, notwithstanding the reference to a different arbitration institution or arbitral body in such contract or submission. When a contract contains a clause for the submission of a future controversy to arbitration, it is not necessary for the parties to enter into a submission agreement before the claimant may invoke the jurisdiction of CIAC.

Page 95: 2007 casesROBERTO C

Clearly then, the CIAC has original and exclusive jurisdiction over disputes

arising from or connected with construction contracts entered into by parties

that have agreed to submit their dispute to voluntary arbitration.162[27]

The GCC signed by LICOMCEN and FSI had the following arbitral

clause:

GC-61 DISPUTES AND ARBITRATION

Should any dispute of any kind arise between the LICOMCEN, INCORPORATED and the Contractor or the Engineer and the Contractor in connection with, or arising out of the execution of the Works, such dispute shall first be referred to and settled by the LICOMCEN, INCORPORATED who shall within a period of thirty (30) days after being formally requested by either party to resolve the dispute, issue a written decision to the Engineer and Contractor.Such decision shall be final and binding upon the parties and the Contractor shall proceed with the execution of the Works with due diligence notwithstanding any Contractor’s objection to the decision of the Engineer. If within a period of thirty (30) days from receipt of the LICOMCEN, INCORPORATED’s decision on the dispute, either party does not officially give notice to contest such decision through arbitration, the said decision shall remain final and binding. However, should any party within thirty (30) days from receipt of the LICOMCEN, INCORPORATED’s decision contest said decision, the dispute shall be submitted for arbitration under the Construction Industry Arbitration Law, Executive Order 1008. The arbitrators appointed under said rules and regulations shall have full power to open up, revise and review any decision, opinion, direction, certificate or valuation of the LICOMCEN, INCORPORATED. Neither party shall be limited to the evidence or arguments put before the LICOMCEN, INCORPORATED for the purpose of obtaining his said decision. No decision given by the LICOMCEN, INCORPORATED shall disqualify him from being called as a witness and giving evidence in the arbitration. It is understood that the obligations of the LICOMCEN, INCORPORATED, the Engineer and the Contractor shall not be altered by reason of the arbitration being conducted during the progress of the Works.163[28]

162

163

Page 96: 2007 casesROBERTO C

LICOMCEN theorizes that this arbitration clause cannot vest

jurisdiction in the CIAC, because it covers only disputes arising out of or in

connection with the execution of works, whether permanent or temporary. It

argues that since the claim of FSI was not connected to or did not arise out

of the execution of the works as contemplated in GC-61, but is based

Page 97: 2007 casesROBERTO C

on alleged breach of contract, under GC-05164[29] of the GCC, the dispute can

only be taken cognizance of by the regular courts. Furthermore, FSI failed

to comply with the condition precedent for arbitration. Thus, according to

LICOMCEN, the CIAC erred in assuming jurisdiction over the case.

Contrary to what LICOMCEN wants to portray, the CIAC validly

acquired jurisdiction over the dispute. Firstly, LICOMCEN submitted itself

to the jurisdiction of the CIAC when its president Antonio S. Tan signed the

TOR165[30] during the preliminary conference. The TOR states:

V. MODE OF ARBITRATION

The parties agree that their differences be settled by an Arbitral Tribunal who were appointed in accordance with the provision of Article V, Section 2 of the CIAC Rules of Procedure Governing Construction Arbitration, as follows:

SALVADOR C. CEGUERAChairman

FELISBERTO G.L. REYESMember

SALVADOR P. CASTRO, JR.Member

The case shall be decided in accordance with the Contract of the parties and the Construction Industry Arbitration Law (Executive Order No. 1008) and on the basis of evidence submitted, applicable laws, and industry practices where applicable under the law.166[31]

Secondly, we agree with the CA that the suit arose from the execution of

works defined in the contract. As it aptly ratiocinated:

164

165

166

Page 98: 2007 casesROBERTO C

[T]he dispute between [FSI] and [LICOMCEN] arose out of or in connection with the execution of works. [LICOMCEN] has gone quite far in interpreting “disputes arising out of or in connection with the execution of work” as separate and distinct from “disputes arising out of or in connection with the contract” citing the various provisions of the Construction Agreement and Bid Documents to preclude CIAC from taking cognizance of the case. To the mind of this Court, such differentiation is immaterial. Article 1374 of the Civil Code on the interpretation of contracts ordains that “the various stipulations of a contract shall be interpreted together, attributing to the doubtful ones that sense which may result from all of them taken jointly.” Essentially, while we agree that [FSI’s] money claims against [LICOMCEN] arose out of or in connection with the contract, the same necessarily arose from the work it accomplished or sought to accomplish pursuant thereto. Thus, said monetary claims can be categorized as a dispute arising out of or in connection with the execution of work.167[32]

Thirdly, FSI complied with the condition precedent provided in GC-

61. Record shows that FSI referred the claim to ESCA on February 3, 1998,

and then to LICOMCEN on March 3, 1998,168[33] but it was disallowed on

March 24, 1998.169[34] Then, on April 15, 1998, FSI rejected the evaluation

of the billings made by ESCA and LICOMCEN and further informed the

latter of its intention to turn over the project.170[35] FSI exerted efforts to

have the claim settled amicably, but no settlement was arrived at. Hence, on

March 14, 2001, FSI through counsel made a final demand to pay.171[36]

LICOMCEN, however, adamantly refused to pay, prompting FSI to file suit

with the CIAC. Clearly, FSI substantially complied with the condition

precedent laid down in GC-61. Finally, the arbitral clause in the agreement,

considering that the requisites for its application are present, is a

167

168

169

170

171

Page 99: 2007 casesROBERTO C

commitment by the parties to submit to arbitration the disputes covered

therein. Because that clause is binding, they are expected to abide by it in

good faith.172[37]

Just as meaningful, the issue of jurisdiction was rendered moot by

LICOMCEN's active participation in the proceedings before the CIAC. It is

true that LICOMCEN initially assailed the jurisdiction of the CIAC. But

when the CIAC asserted its jurisdiction in its February 20, 2003 Order,173[38]

LICOMCEN did not seek relief from the CIAC ruling. Instead, LICOMCEN

took part in the discussion on the merits of the case, even going to the extent

of seeking affirmative relief. The active involvement of a party in the

proceedings is tantamount to an invocation of, or at least an acquiescence to,

the court's jurisdiction. Such participation indicates a willingness to abide

by the resolution of the case, and will bar said party from later on impugning

the court or body's jurisdiction.174[39] The Court will not countenance the

effort of any party to subvert or defeat the objective of voluntary arbitration

for its own private motives.175[40] After submitting itself to arbitration

proceedings and actively participating therein, LICOMCEN is estopped

from assailing the jurisdiction of the CIAC, merely because the latter

rendered an adverse decision.

Having resolved the issue of jurisdiction, we proceed to the merits of

the case.

172

173

174

175

Page 100: 2007 casesROBERTO C

LICOMCEN faults the CIAC and the CA for ruling that the contract

had been terminated, insisting that it was merely indefinitely suspended. To

bolster its position, LICOMCEN cited GC-41 of the GCC which reads:

GC-41 LICOMCEN, INCORPORATED’S RIGHT TO SUSPEND WORK OR TERMINATE THE CONTRACT

x x x x

2. For Convenience of LICOMCEN, INCORPORATED

If any time before completion of work under the Contract it shall be found by the LICOMCEN, INCORPORATED that reasons beyond the control of the parties render it impossible or against the interest of LICOMCEN, INCORPORATED to complete the work, the LICOMCEN, INCORPORATED at any time, by written notice to the Contractor, may discontinue the work and terminate the Contract in whole or in part. Upon issuance of such notice of termination, the Contractor shall discontinue the work in such manner, sequence and at such time as the LICOMCEN, INCORPORATED/Engineer may direct, continuing and doing after said notice only such work and only until such time or times as the LICOMCEN, INCORPORATED/Engineer may direct. x x x176[41]

(Emphasis supplied)

Unfortunately for LICOMCEN, this provision does not support but

enervates its theory of indefinite suspension. The cited provision may be

invoked only in cases of termination of contract, as clearly inferred from the

phrase “discontinue the work and terminate the contract.” And in statutory

construction implies conjunction, joinder or union.177[42] Thus, by invoking

GC-41, LICOMCEN, in effect, admitted that the contract had already been

terminated.

176

177

Page 101: 2007 casesROBERTO C

The termination of the contract was made obvious and unmistakable

when LICOMCEN’s new project consultant rebidded the contract for the

bored piling works for the CITIMALL.178[43] The claim that the rebidding

was conducted for purposes of getting cost estimates for a possible new

design179[44] taxes our credulity. It impresses us as nothing more than a lame

attempt of LICOMCEN to avoid liability under the contract. As the CIAC

had taken pains to demonstrate:

Suspension of work is ordinarily understood to mean a temporary work stoppage or a cessation of work for the time being. It may be assumed that, at least initially, LCC had a valid reason to suspend the Works on December 16, 1997 pursuant to GC-38 above-quoted. The evidence show, however, that it has not ordered a resumption of work up to the present despite the lapse of more than four years, and despite the dismissal of the case filed with the Office of the Ombudsman which it gave as reason for the suspension in the first place. As such, LCC’s suspension of the Works had already lost its essential characteristic of being merely temporary or only for the time being. To still consider it a “suspension” at this point is to do violence to reason and logic.

Perhaps because of this LCC came up with the assertion that what we have is an “indefinite suspension.” There is no such term in the Construction Agreement or the Contract Documents. In fact, it is unknown in the construction industry. Construction work may either be suspended or terminated, but never indefinitely suspended. Since it is not sanctioned by practice and not mentioned in the herein Construction Agreement and the Contract Documents, “indefinite suspension” is irregular and invalid. Due to the apparent incongruity of an “indefinite suspension,” LCC changed the term to “continued suspension” in its Memorandum. Unfortunately for it, the factual situation remains unchanged. The Works stay suspended for an indefinite period of time.180

[45]

Accordingly, the CA did not err in affirming the CIAC ruling that the

contract had already been terminated.

178

179

180

Page 102: 2007 casesROBERTO C

Neither can LICOMCEN find refuge in the principle of laches to steer

clear of liability. It is not just the lapse of time or delay that constitutes

laches. The essence of laches is the failure or neglect, for an unreasonable

and unexplained length of time, to do that which, through due diligence,

could or should have been done earlier, thus giving rise to a presumption

that the party entitled to assert it had either abandoned or declined to assert

it. 181[46]

Indeed, FSI filed its petition for arbitration only on October 8, 2002,

or after the lapse of more than four years since the project was “indefinitely

suspended.” But we agree with the CIAC and the CA that such delay can

hardly be considered unreasonable to give rise to the conclusion that FSI

already abandoned its claim. On the contrary, the delay was due to the fact

that FSI exerted efforts to have the claim settled extra-judicially which

LICOMCEN rebuffed. Besides, except for LICOMCEN’s allegation that the

filing of the suit is already barred by laches, no proof was offered to show

that the filing of the suit was iniquitous or unfair to LICOMCEN. We

reiterate that, unless reasons of inequitable proportions are adduced, a delay

within the prescriptive period is sanctioned by law and is not to be

considered delay that would bar relief.182[47] In the instant case, FSI filed its

claim well within the ten-year prescriptive period provided for in Article

1144 of the Civil Code.183[48] Therefore, laches cannot be invoked to bar FSI

from instituting this suit.

181

182

183

Page 103: 2007 casesROBERTO C

The doctrine of laches is based upon grounds of public policy which

require, for the peace of society, discouraging stale claims. It is principally a

question of the inequity or unfairness of permitting a right or claim to be

enforced or asserted. There is no absolute rule as to what constitutes laches;

each case is to be determined according to its particular circumstances. The

question of laches is addressed to the sound discretion of the court, and since

it is an equitable doctrine, its application is controlled by equitable

considerations. It cannot be worked to defeat justice or to perpetrate fraud

and injustice. 184[49]

We now come to the monetary awards granted to FSI. LICOMCEN

avers that the award lacked factual and legal basis. FSI, on the other hand,

posits otherwise, and cries foul on the modification made by the CA. It

asserts that the CA erred in disregarding the pieces of evidence that it

submitted in support of the claim despite the lack of objection and

opposition from LICOMCEN. It insists entitlement to the full amount of

material costs at site, for equipment and labor standard costs, as well as

unrealized profits.

In this connection, we must emphasize the distinction between

admissibility of evidence and its probative value. Just because a piece of

evidence is not objected to does not ipso facto mean that it conclusively

proves the fact in dispute. The admissibility of evidence should not be

confused with its probative value. Admissibility refers to the question of

whether certain pieces of evidence are to be considered at all, while

probative value refers to the question of whether the admitted evidence

184

Page 104: 2007 casesROBERTO C

proves an issue. Thus, a particular item of evidence may be admissible, but

its evidentiary weight depends on judicial evaluation within the guidelines

provided by the rules of evidence.185[50]

We have carefully gone over the records and are satisfied that the

findings of the CA are well supported by evidence. As mentioned above, the

contract between LICOMCEN and FSI had already been terminated and, in

such case, the GCC expressly provides that:

GC-42 PAYMENT FOR TERMINATED CONTRACT

If the Contract is terminated as aforesaid, the Contractor will be paid for all items of work executed, and satisfactorily completed and accepted by the LICOMCEN, INCORPORATED up to the date of termination, at the rates and prices provided for in the contract and in addition:

1. The cost of partially accomplished items of additional or extra work agreed upon by the LICOMCEN, INCORPORATED and the Contractor.

2. The cost of materials or goods reasonably ordered for the Permanent or Temporary Works which have been delivered to the Contractor but not yet used and which delivery has been certified by the Engineer.

3. The reasonable cost of demobilization

For any payment due the Contractor under the above conditions, the LICOMCEN, INCORPORATED, however, shall deduct any outstanding balance due from the Contractor for advances in respect to mobilization and materials, and any other sum the LICOMCEN, INCORPORATED is entitled to be credited.186[51]

We agree with the Court of Appeals that the liability of LICOMCEN

for the cost of materials on site is only P5,694,939.85. The said award

represents the materials reasonably ordered for the project and which were 185

186

Page 105: 2007 casesROBERTO C

delivered to the job site. FSI cannot demand full payment of the steel bars

under Purchase Order No. 6035.187[52] As shown by the records, the steel

bars were loaded at M/V Alberto only on January 12, 1998188[53] and reached

Legaspi City on January 16, 1998.189[54] But as early as December 16, 1997,

LICOMCEN already informed FSI of the major revision of the design and

ordered the non-delivery to the jobsite of the 50% of the steel bars.

Inexplicably, FSI continued the delivery. Worse, it unloaded all the steel

bars and delivered them to the jobsite and some to the Tuanzon batching

plant on January 17, 1998,190[55] despite LICOMCEN’s order not to do so.

FSI cannot now claim payment of the cost of all these materials.

LICOMCEN, however, cannot deny liability for 50% of the steel bars

because, as mentioned, it ordered their delivery to the jobsite. The steel bars

had in fact been delivered to the jobsite and inventoried by Cesar Cortez of

ESCA,191[56] contrary to LICOMCEN’s claim. The payment of these

materials is, therefore, in order, pursuant to GC-41:

The Contractor shall receive compensation for reasonable expenses incurred in good faith for the performance of the Contract and for reasonable expenses associated with the termination of the Contract. x x x.192[57]

We also uphold the denial of FSI’s claim for equipment and labor

standard costs, as no convincing evidence was presented to prove it. The list

187

188

189

190

191

192

Page 106: 2007 casesROBERTO C

of rented equipment193[58] and the list of workers194[59] offered by FSI and

which were admitted by CIAC, are far from being clear and convincing

proof that FSI actually incurred the expenses stated therein.

As aptly said by the CA, FSI should have presented convincing pieces

of documentary evidence, such as the lease contract or the receipts of

payment issued by the owners of the rented equipment, to establish the

claim. As to its claimed labor expenses, the list of employees does not

categorically prove that these listed employees were actually employed at

the construction site during the suspension. Hence, even assuming that

LICOMCEN failed to submit evidence to rebut these lists, they do not ipso

facto translate into duly proven facts. FSI still had the burden of proving its

cause of action, because it is the one asserting entitlement to an affirmative

relief.195[60] On this score, FSI failed. The CA, therefore, committed no

reversible error in denying the claim.

FSI’s claim for unrealized profit has to be rejected too. GC-41

specifically provided that:

x x x The Contractor shall have no claim for anticipated profits on the work thus terminated, nor any other claim, except for work actually performed at the time of complete discontinuance, including any variations authorized by the LICOMCEN, INCORPORATED/Engineer to be done under the section dealing with variation, after the date of said order, and for any claims for variations accruing up to the date of said notice of termination.196[61] (Emphasis supplied)

193

194

195

196

Page 107: 2007 casesROBERTO C

The provision was agreed upon by the parties freely, and significantly, FSI

did not question this. It is not for the Court to change the stipulations in the

contract when they are not illegal. Article 1306 of the Civil Code provides

that the contracting parties may establish such stipulations, clauses, terms

and conditions as they may deem convenient, provided they are not contrary

to law, morals, good customs, public order, or public policy.197[62] Besides,

no convincing proof was offered to prove the claim. In light of the

foregoing, the CA, therefore, correctly denied the claim for unrealized profit.

Similarly, we agree with the CIAC and the CA that LICOMCEN

should bear the cost of arbitration as it adamantly refused to pay FSI’s just

and valid claim, prompting the latter to institute a petition for arbitration.

In sum, we find no reason to disturb the decision of the CA. It cannot

be faulted for denying FSI’s motion for reconsideration through a mere

Minute Resolution, for as we held in Ortigas and Company Limited

Partnership v. Velasco:198[63]

The filing of a motion for reconsideration, authorized by Rule 52 of the Rules of Court, does not impose on the Court the obligation to deal individually and specifically with the grounds relied upon therefor, in much the same way that the Court does in its judgment or final order as regards the issues raised and submitted for decision. This would be a useless formality or ritual invariably involving merely a reiteration of the reasons already set forth in the judgment or final order for rejecting the arguments advanced by the movant; and it would be a needless act, too, with respect to issues raised for the first time, these being, x x x deemed waived because not asserted at the first opportunity. It suffices for the Court to deal generally and summarily with the motion for reconsideration, and merely state a legal ground for its denial (Sec. 14, Art. VIII, Constitution); i.e., the motion contains merely a reiteration or

197

198

Page 108: 2007 casesROBERTO C

rehash of arguments already submitted to and pronounced without merit by the Court in its judgment, or the basic issues have already been passed upon, or the motion discloses no substantial argument or cogent reason to warrant reconsideration or modification of the judgment or final order; or the arguments in the motion are too unsubstantial to require consideration, etc.

WHEREFORE, the herein petitions for review are DENIED, and the

assailed Decision and Resolutions of the Court of Appeals are AFFIRMED.

SO ORDERED.

ANTONIO CHIENG, substituted by WILLIAM CHIENG,

Petitioner,

-versus –

SPOUSES EULOGIO and TERESITA SANTOS,

Respondents.

G.R. No. 169647

Present:

YNARES-SANTIAGO, Chairperson,AUSTRIA-MARTINEZ, CHICO-NAZARIO, NACHURA,* and REYES, JJ.

Promulgated:

August 31, 2007

x - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - -x

*

Page 109: 2007 casesROBERTO C

D E C I S I O N

CHICO-NAZARIO, J.:

Before this Court is a Petition for Review on Certiorari under Rule 45

of the Rules of Court,199[1] praying that the Decision, dated 13 September

2005 of the Court of Appeals in CA-G.R. CV No. 79971200[2] be set aside and

the Decision201[3] and Order202[4] of the Olongapo City Regional Trial Court

(RTC), Branch 74, in Civil Case No. 239-0-93, dated 23 October 2001 and

11 January 2002, respectively, which were reversed by the appellate court,

be reinstated.

Stripped of the non-essentials, the facts are as follows:

On 17 August 1989, petitioner Antonio Chieng203[5] extended a loan in

favor of respondent spouses Eulogio and Teresita Santos. As security for

such loan, the respondents executed in favor of petitioner a Deed of Real

Estate Mortgage over a piece of land, consisting of 613 square meters,

situated at West Bajac-Bajac, Olongapo City, and covered by Transfer

Certificate of Title (TCT) No. T-2570 issued by the Registry of Deeds of

Olongapo City in the name of respondents. On even date, the Deed of Real

Estate Mortgage was registered with the Registry of Deeds of Olongapo City

and was duly annotated on TCT No. T-2570.

199

200

201

202

203

Page 110: 2007 casesROBERTO C

Thereafter, respondent Eulogio issued several checks in favor of

petitioner as payment for the loan. Some of these checks were dishonored,

prompting the petitioner to file a criminal case against respondent Eulogio

for violation of Batas Pambansa Blg. 22 before the Olongapo City RTC,

Branch 72, docketed as Criminal Cases No. 612-90 to No. 615-90. During

the pre-trial conference of these cases, petitioner and respondent Eulogio

entered into a compromise agreement, which was contained in the Order of

the court, to wit:

ORDER

When this case was called for pre-trial conference in the presence of the Honorable Prosecutor, accused Eulogio Santos and private complainant Antonio Chieng came to an agreement that the total indebtedness of Mr. Santos as of today, July 15, 1991 amounts to Two Hundred Thousand (P200,000.00) Pesos including interest since the beginning and excluding those already paid for. It is understood that at a payment of P20,000.00 each month starting on or before July 31, 1991 and upon the completion of the amount of P200,000.00 without any interest, the indebtedness of Mr. Santos shall/have been discharged and upon payment of P20,000.00 on or before July 31 1991, the next payment on or before August 31 1991, these cases will be considered terminated.

Prosecutor Martinez, Accused Eulogio Santos and complainant Antonio Chieng are notified of this assignment.204[6]

Respondent Eulogio failed to comply with his obligation in the

compromise agreement.

On 17 June 1993, petitioner filed with the Olongapo City RTC,

Branch 74, an action for foreclosure of mortgage constituted on respondents’

204

Page 111: 2007 casesROBERTO C

real property docketed as Civil Case No. 239-0-93. Petitioner alleged that

he extended a loan of P600,000.00 in favor of respondents for which

respondents executed the Deed of Real Estate Mortgage dated 17 August

1987 in his favor. Despite his repeated demands, respondents failed to pay

the loan.

Respondents sought the dismissal of the case on the ground of lack of

cause of action claiming that the Deed of Real Estate Mortgage did not

reflect the parties’ true intention or agreement because the total amount of

their indebtedness was only around P200,000.00, not P600,000.00 as stated

in the Deed. Respondents and petitioner supposedly agreed to make it

appear that respondents’ loan amounted to P600,000.00 to protect the latter

from the claims of their other creditors who were trying to attach or levy

their property. Respondents further averred that they had partly paid their

loan but petitioner refused to issue them receipts and to render an accounting

of their remaining obligation.

On 10 February 1994, petitioner made his formal offer of evidence.

Upon submission by respondents of their Comment/Objections to

petitioner’s formal offer of evidence, the court issued an Order dated 1

September 1994, admitting petitioner’s offer of evidence, and set the hearing

for the reception of respondents’ evidence on 28 September 1994. However,

hearings were successively postponed upon the motions of respondents. On

14 January 1997, the court issued an Order declaring that (1) the respondents

were deemed to have waived their right to present evidence; and (2) the case

was considered submitted for decision. Respondents filed a Motion for

Page 112: 2007 casesROBERTO C

Reconsideration of the said RTC Order dated 14 January 1997, but this was

denied.205[7]

On 9 July 1997, the Olongapo City RTC, Branch 74, rendered a

Decision206[8] ordering the respondents to pay petitioner their loan obligation

amounting to P600,000.00, plus interests and attorney’s fees, thus:

WHEREFORE, judgment is hereby rendered ordering the [ herein respondents] to pay [herein petitioner] within 90 days from receipt of this Decision the sum of P600,000.00 with legal rate of interest of 12% per annum from August 13, 1992 until the amount is fully paid; to pay [petitioner] the amount of P60,000.00 as attorney’s fees; and the costs of this suit.

In default of such payment, the Sheriff of this Court is ordered to sell at public auction the property described in the Deed of Real Estate Mortgage x x x together with the improvements thereon and apply the proceeds thereof to the principal obligation, interests, attorney’s fees and the costs of this suit.

Respondents filed a Motion for Reconsideration207[9] arguing:

[C]onsidering that another branch of this Honorable Court, particularly Branch 72 through Judge Esther Nobles Bans had issued an order fixing the actual obligation of the [herein respondents] to [herein petitioner] in the sum of P200,000.00 with the conformity of both the herein parties, a copy of the said order is hereto attached as Annex “I” of this motion for the ready reference and guidance of this Honorable Court.

In effect, the said order is in the nature of a judicial compromise or judgment that should be strictly complied with and/or honored by the herein parties, unless the same was entered into through palpable mistake.

Besides, it would be the height of injustice to compel the herein [respondents] to pay more than P200,000.00 when the herein parties had

205

206

207

Page 113: 2007 casesROBERTO C

already pegged the obligation of the herein [respondents] to the said [petitioner] in the sum of P200,000.00.

On 6 October 1997, the court issued an Order setting aside its earlier

Decision dated 9 July 1997.208[10]

Respondent Eulogio explained that he issued several checks

amounting to P107,000.00 in favor of petitioner as partial payment of the

loan as evidenced by a memorandum. He added that some of the checks he

issued bounced; thus, he and his wife failed to fully discharge their loan.

Instead of foreclosing the mortgage on their property, petitioner chose to

institute criminal cases against respondent Eulogio for issuing bouncing

checks in violation of Batas Pambansa Blg. 22, docketed as Criminal Cases

No. 612-90 to No. 615-90 before the Olongapo City RTC, Branch 72. He

bared that the P200,000.00 which he was directed to pay petitioner by the

Olongapo City RTC, Branch 72 in its Order dated 15 July 1991 in Criminal

Cases No. 612-90 to No. 615-90 was the same subject of Civil Case No.

239-0-93 pending with the Olongapo City RTC, Branch 74.

On 23 September 1998, petitioner passed away.209[11] Thereafter, his

heirs filed a motion to substitute him in Civil Case No. 239-0-93.210[12] In its

Order dated 12 January 1999, the Olongapo City RTC, Branch 74 granted

the motion and directed the substitution of petitioner by his son, William

Chieng.211[13]

208

209

210

211

Page 114: 2007 casesROBERTO C

On 23 October 2001, the Olongapo City RTC, Branch 74 rendered a

Decision in Civil Case No. 239-0-93 directing the respondents to pay

petitioner the amount of P377,000.00 with interest, plus attorney’s fees and

costs.212[14] The decretal portion of the decision reads:

WHEREFORE, finding [herein respondents] Eulogio Santos and Teresita Santos liable to [herein petitioner] Antonio Chieng (substituted herein by William Cheng) in the sum of P377,000,00 including interest;

- judgment is hereby rendered directing Eulogio Santos and Teresita Santos, to jointly and severally pay to the Court:

1. the sum of Three Hundred Seventy Seven Thousand Pesos (P377,000.00) within a period of not less than ninety (90) days from notice of this judgment;

2. the sum of P25,000.00 to pay for the attorney’s fees of [petitioner’s] counsel;

3. the sum of P3,210.00 costs/filing fees.

In default of such payment, the property to be sold by the Court’s Deputy Sheriff, to realize the mortgage debt and costs.213[15]

It agreed with respondents that the Deed of Real Estate Mortgage was

simulated and that the loan obligation was only P200,000.00. It also found

that respondents made payments amounting to P107,000.00. Respondent’s

liability was arrived at in this manner:

Since the mortgage debt of P200,000.00 was contracted on August 17, 1989, when judicially demanded on June 23, 1993, the mortgage debt of P200,000.00 at 12% per annum (without compounding since there is no written agreement to that effect) earned an interest of P92,000.00 on June 17, 1993. From 1993 up to the present, a total of P192,000,00 in interest

212

213

Page 115: 2007 casesROBERTO C

again accrued and adding the same to the interest due from August 17, 1989, an overall total interest of P284,000.00 at 12% per annum without compounding, is due from the [herein respondents].

Accordingly, [respondents] have paid a total of P107,000.00 to [herein petitioner], hence, deducting that amount from the total interest due, would leave an unpaid interest of P177,000,00. Adding this to the uncontroverted principal debt of P200,000.00, the [respondents] owe [petitioner] the total sum of P377,000.00.214[16]

Respondents filed a Motion for Reconsideration asserting that the

charging of interest on the loan obligation was unwarranted because no

payment of interest was agreed upon.215[17] In its Order dated 11 January

2002, the court denied the Motion for Reconsideration, reasoning that

respondents were the ones who presented as evidence the supposed

compromise agreement between petitioner and respondent Eulogio, as stated

in the Order dated 15 July 1991 of the Olongapo City RTC, Branch 72, in

Criminal Cases No. 612-90 to No. 615-90.216[18] According to the court, it

used the very same compromise agreement as its basis for imposing the 12%

per annum interest rate, and that respondents were precluded from

disclaiming the said agreement.

Unsatisfied, respondents filed an appeal with the Court of Appeals,

docketed as CA-G.R. CV No. 79971. In a decision dated 13 September

2005, the appellate court reversed the Decision dated 23 October 2001 and

Order dated 11 January 2002 of the Olongapo City RTC, Branch 74, and

dismissed Civil Case No. 239-0-93.217[19] Citing our ruling in Bank of

214

215

216

217

Page 116: 2007 casesROBERTO C

America v. American Realty Corporation,218[20] it held that a mortgagor-

creditor has two choices of action: he may either file an ordinary action to

recover the indebtedness or foreclose the mortgage. In short, once a

collection suit is filed, the action to foreclose the mortgage is barred.

It ratiocinated that although Criminal Cases No. 612-90 to No. 615-90

for Violation of Batas Pambansa Blg. 22 before the Olongapo City RTC,

Branch 72, were not strictly in the nature of ordinary actions for

collection/payment of debts or loans, the resulting compromise agreement in

the said cases between petitioner and respondent Eulogio, on the matter of

payment of the loan, had the effect of settling respondents’ indebtedness to

petitioner. This is pursuant to Section 1, Rule 111 of the 1985 Rules on

Criminal Procedure which provides that the civil action for the recovery of

civil liability is impliedly instituted in the criminal actions. Having been

impliedly instituted in the criminal cases, any separate civil action for the

collection or payment of the loan, like the action for foreclosure of real

estate mortgage, can no longer be availed of by petitioner. Thus, it

pronounced that the issue of the payment of the loan, having been the

subject of the Order dated 15 July 1991 of the Olongapo City RTC, Branch

72, in Criminal Cases No. 612-90 to No. 615-90, cannot be re-litigated and

that the proper course of action for petitioner was to seek the execution of

the said order. In closing, the Court of Appeals decreed:

Having made the foregoing pronouncement, the Court finds no necessity to discuss the second assignment of error because there being no loan obligation which can be enforced, no interest could be likewise granted in favor of [herein petitioner].

218

Page 117: 2007 casesROBERTO C

WHEREFORE, in view of the foregoing, the Decision of the Regional Trial Court of Olangapo, Branch 74, in Civil Case No. 239-0-93 is hereby REVERSED and a new one entered DISMISSING the complaint.219[21]

Petitioner thus filed the instant Petition before us challenging the

Decision dated 13 September 2005 of the Court of Appeals. In our

Resolution dated 5 December 2005, we denied the Petition due to

petitioner’s failure to submit the duplicate original or certified true copy of

the assailed decision pursuant to Sections 4(d) and 5, Rule 45 in relation to

Section 5(d), Rule 56 of the Rules of Court.220[22] Petitioner filed a Motion

for Reconsideration praying that his submission of one certified true copy of

the questioned decision be considered as substantial compliance with the

Rules.221[23] Finding the Motion meritorious, we issued a Resolution dated

19 April 2006 reinstating the present Petition.222[24]

The sole issue to be resolved is: whether petitioner, by filing Criminal

Cases No. 612-90 to No. 615-90 for violation of Batas Pambansa Blg. 22

against respondent Eulogio, was already barred or precluded from availing

himself of the other civil remedy of the foreclosure of the real estate

mortgage.223[25]

Petitioner maintains that, in filing Criminal Cases No. 612-90 to No.

615-90 for violation of Batas Pambansa Blg. 22 against respondent Eulogio,

he should not be deemed to have impliedly instituted therein an ordinary

219

220

221

222

223

Page 118: 2007 casesROBERTO C

action for collection of the loan which will preclude him from pursuing the

remedy of foreclosure of real estate mortgage.224[26] He asserts that no

evidence was adduced proving that the obligation for which the checks were

issued in Criminal Cases No. 612-90 to No. 615-90 was the same loan

obligation secured by the Deed of Real Estate Mortgage in Civil Case No.

239-0-93. Petitioner’s complaint-affidavit and the informations filed against

respondent Eulogio in the said criminal cases, which could have shed light

on the rights of the parties therein, were not presented during the trial before

the Olongapo City RTC, Branch 74 in Civil Case No. 239-0-93. Petitioner

argues that, if indeed the obligation for which the checks were issued in said

criminal cases is the same as the obligation secured by the Deed of Real

Estate Mortgage, the Olongapo City RTC, Branch 72 would have mentioned

in its Order dated 15 July 1991 in Criminal Cases No. 612-90 to No. 615-90

that the consideration in the Deed of Real Estate Mortgage was being

reduced to only P200,000.00.225[27]

Moreover, petitioner claims that respondents did not pay a single

centavo under the compromise agreement in Criminal Cases No. 612-90 to

No. 615-90. The compromise agreement was thus deemed abandoned, with

no more force and effect. Petitioner further asseverates that 14 years had

already lapsed from the time the Order dated 15 July 1991 of the Olongapo

City RTC, Branch 72 in Criminal Cases No. 612-90 to No. 615-90 became

final, so that he can no longer file a Motion for Execution thereof or an

Action to Revive Judgment. It was for this very reason why petitioner was

constrained to file an action for judicial foreclosure of mortgage. To enjoin

224

225

Page 119: 2007 casesROBERTO C

his action to foreclose the real estate mortgage would be an injustice since he

would be left with no other recourse in recovering the loan balance from

respondents.226[28]

For reasons of justice and equity, we rule in favor of petitioner.

At the threshold, the following discussion merits equal attention. A

mortgage-creditor may, in the recovery of a debt secured by a real estate

mortgage, institute against the mortgage-debtor either a personal action for

debt or a real action to foreclose the mortgage. These remedies available to

the mortgage-creditor are deemed alternative and not cumulative. An

election of one remedy operates as a waiver of the other. In sustaining the

rule that prohibits a mortgage-creditor from pursuing both remedies of a

personal action for debt or a real action to foreclose the mortgage, we held in

Bachrach Motor Co., Inc. v. Icarangal,227[29] that a rule which would

authorize the mortgage-creditor to bring a personal action against the

mortgage-debtor and simultaneously or successively another action against

the mortgaged property, would result not only in multiplicity of suits so

offensive to justice and obnoxious to law and equity, but would also subject

the mortgage-debtor to the vexation of being sued in the place of his

residence or of the residence of the mortgage-creditor, and then again in the

place where the property lies. Hence, a remedy is deemed chosen upon the

filing by the mortgage-creditor of the suit for collection or upon his filing of

the complaint in an action for foreclosure of mortgage, pursuant to the

provisions of Rule 68 of the Rules of Court.228[30]

226

227

228

Page 120: 2007 casesROBERTO C

Proceeding therefrom, we shall now determine whether petitioner’s

filing of Criminal Cases No. 612-90 to 615-90 is equivalent to the filing of a

collection suit for the recovery of the mortgage-loan which, pursuant to the

aforesaid rule on the alternative remedies of collection and foreclosure,

precludes the petitioner from subsequently availing himself of the action to

foreclose the mortgaged property.

When petitioner filed Criminal Cases No. 612-90 to No. 615-90 for

violation of Batas Pambansa Blg. 22 against respondent Eulogio, petitioner’s

civil action for the recovery of the amount of the dishonored checks was

impliedly instituted therein pursuant to Section 1(b) of Rule 111 of the 2000

Rules on Criminal Procedure. In the case of Hyatt Industrial Manufacturing

Corporation v. Asia Dynamic Electrix Corporation,229[31] we elucidated thus:

We agree with the ruling of the Court of Appeals that upon filing of the criminal cases for violation of B.P. 22, the civil action for the recovery of the amount of the checks was also impliedly instituted under Section 1(b) of Rule 111 of the 2000 Rules on Criminal Procedure. Under the present revised Rules, the criminal action for violation of B.P. 22 shall be deemed to include the corresponding civil action. The reservation to file a separate civil action is no longer needed. The Rules provide:

Section 1. Institution of criminal and civil actions. –

(a) x x x x

(b) The criminal action for violation of Batas Pambansa Blg. 22 shall be deemed to include the corresponding civil action. No reservation to file such civil action separately shall be allowed.

229

Page 121: 2007 casesROBERTO C

Upon filing of the aforesaid joint criminal and civil actions, the offended party shall pay in full the filing fees based on the amount of the check involved, which shall be considered as the actual damages claimed. Where the complaint or information also seeks to recover liquidated, moral, nominal, temperate or exemplary damages, the offended party shall pay additional filing fees based on the amounts alleged therein. If the amounts are not so alleged but any of these damages are subsequently awarded by the court, the filing fees based on the amount awarded shall constitute a first lien on the judgment.

Where the civil action has been filed separately and trial thereof has not yet commenced, it may be consolidated with the criminal action upon application with the court trying the latter case. If the application is granted, the trial of both actions shall proceed in accordance with section 2 of this Rule governing consolidation of the civil and criminal actions.

The foregoing rule was adopted from Circular No. 57-97 of this Court. It specifically states that the criminal action for violation of B.P. 22 shall be deemed to include the corresponding civil action. It also requires the complainant to pay in full the filing fees based on the amount of the check involved. Generally, no filing fees are required for criminal cases, but because of the inclusion of the civil action in complaints for violation of B.P. 22, the Rules require the payment of docket fees upon the filing of the complaint. This rule was enacted to help declog court dockets which are filled with B.P. 22 cases as creditors actually use the courts as collectors. Because ordinarily no filing fee is charged in criminal cases for actual damages, the payee uses the intimidating effect of a criminal charge to collect his credit gratis and sometimes, upon being paid, the trial court is not even informed thereof. The inclusion of the civil action in the criminal case is expected to significantly lower the number of cases filed before the courts for collection based on dishonored checks. It is also expected to expedite the disposition of these cases. Instead of instituting two separate cases, one for criminal and another for civil, only a single suit shall be filed and tried. It should be stressed that the policy laid down by the Rules is to discourage the separate filing of the civil action. The Rules even prohibit the reservation of a separate civil action, which means that one can no longer file a separate civil case after the criminal complaint is filed in court. The only instance when separate proceedings are allowed is when the civil action is filed ahead of the criminal case. Even then, the Rules encourage the consolidation of the civil and criminal cases. We have previously observed that a separate civil action for the purpose of recovering the amount of the dishonored checks would only prove to be costly, burdensome and time-consuming for both parties and would further delay the final disposition of the case. This multiplicity of suits must be avoided. Where petitioners’ rights may be fully adjudicated

Page 122: 2007 casesROBERTO C

in the proceedings before the trial court, resort to a separate action to recover civil liability is clearly unwarranted. x x x.

The impliedly instituted civil action in Criminal Cases No. 612-90 to

No. 615-90 for violation of Batas Pambansa Blg. 22 was, in effect, a

collection suit or suit for the recovery of the mortgage-debt since the

dishonored checks involved in the said criminal cases were issued by

respondent Eulogio to petitioner for the payment of the same loan secured

by the Deed of Real Estate Mortgage. As correctly found by the Olongapo

City RTC, Branch 74, in its Decision dated 23 October 2001 in Civil Case

No. 239-0-93:

After a careful scrutiny of the evidence adduced by the parties, this Court will not hesitate to state that –

- it is convinced that the parties had one and only transaction, the one constituted on August 17, 1989;

x x x x

- the bouncing checks for which defendant was criminally charged with, were part of the checks issued to plaintiff in consideration of the mortgage debt secured on August 17, 1989;

- defendant’s payment for those checks should appropriately be considered as payment of the mortgage debt, defendant’s only obligation in favor of the plaintiff;

x x x x

The Court has likewise taken note of the fact that plaintiff is a businessman by his admission, and the fact that the purpose of the defendants’ seeing him on August 17, 1989 is in order to borrow money. The testimony of plaintiff that defendants are known to him cannot be related to any special occasion or event of meeting and later becoming friends, otherwise plaintiff could have stated so. His having known the defendants refer to only one occasion, that is, when the defendants came to his business office to obtain a loan. Anyone can do that. That person

Page 123: 2007 casesROBERTO C

would then be his debtor. And so, defendants on August 17, 1989 became debtors of the plaintiff.

Why would defendants come to plaintiff if not for that purpose? Plaintiff is known in Olongapo City as a money lender. His business at 1670 Rizal Avenue, West Bajac-bajac is a money lending business.

As a lender, plaintiff’s prime concern is profit. In order to attain this, he has to impose double measures to protect his interest. First, to ask the borrower to produce the title to the property intended as collateral. On this, the lender asks the borrower to execute a deed of mortgage. Plaintiff does not operate as a commercial bank neither as a rural bank, hence, he belongs to the group that allows a borrower to repay within a shorter period. Secondly, to facilitate collection of the monthly repayments, the lender requires the borrower to issue checks for each month ensuing all in equal amounts. Usually, the checks so issued would also include the interest due each month, but in this case, there is no testimony to that effect. However, it can be assumed considering the subsequent acts of the parties.

As soon as the borrower is able to satisfy the two conditions, he gets the desired loan. The lender then has the borrower’s head, as well as his tail, in his hands, and that is the predicament where the defendants found themselves in. Defendants were, however, confronted with a problem. Someone else is after their property, a third person in whose favor they owe a demandable obligation. This person is hot on pursuing the property to satisfy what defendants owe her. And defendants opened up and relayed their predicament to the plaintiff and the latter agreed.

Anxious that the defendants’ property will eventually be attached or levied, leaving the loan he will give without any collateral, plaintiff agreed to simulate the amount in the Deed, to an amount higher that the third persons claim against the defendants but at the same time he required from the defendants checks to cover the P200,000.00 loan. Defendant Eulogio testified that he issued the checks for the amount of P200,000.00 and plaintiff did not deny this. x x x.230[32]

Consequently, when petitioner filed Criminal Cases No. 612-90 to No.

615-90, he was deemed to have already availed himself of the remedy of

collection suit. Following the rule on the alternative remedies of a mortgage-

230

Page 124: 2007 casesROBERTO C

creditor, petitioner is barred from subsequently resorting to an action for

foreclosure.

However, it should be stressed that respondents have not yet fully

paid the loan. In fact, respondents themselves admitted that they still

owe petitioner the balance of the loan.231[33]

To allow respondents to benefit from the loan without paying its

whole amount to petitioner, and to preclude the petitioner from recovering

the remaining balance of the loan, would constitute unjust enrichment at the

expense of petitioner. The principle that no person may unjustly enrich

himself at the expense of another (Nemo cum alterius detrimento locupletari

potest) is embodied in Article 22 of the New Civil Code, to wit:

ART. 22. Every person who through an act of performance by another, or any other means, acquires or comes into possession of something at the expense of the latter without just or legal ground, shall return the same to him.

As can be gleaned from the foregoing, there is unjust enrichment

when (1) a person is unjustly benefited, and (2) such benefit is derived at the

expense of or with damages to another.232[34] The main objective of the

principle of unjust enrichment is to prevent one from enriching oneself at the

expense of another.233[35] It is commonly accepted that this doctrine simply

means that a person shall not be allowed to profit or enrich himself

inequitably at another’s expense.234[36] One condition for invoking this

231

232

233

234

Page 125: 2007 casesROBERTO C

principle is that the aggrieved party has no other action based on contract,

quasi-contract, crime, quasi-delict or any other provision of law.235[37]

The principle of unjust enrichment obliges the respondents to pay the

remaining balance of the loan plus interest. Relieving the respondents of

their obligation to pay the balance of the loan would, indeed, be to sanction

unjust enrichment in favor of respondents and cause unjust poverty to

petitioner.

In the exercise of our mandate as a court of justice and equity,236[38] we

hold, pro hac vice, that respondents are still liable to pay the remaining

balance of the loan.

We, nonetheless, do not subscribe to the computations made by the

RTC. In Eastern Shipping Lines, Inc. v. Court of Appeals,237[39] we ruled that

when the obligation is breached and it consists in the payment of a sum of

money such as a loan, the interest due should be that which may have been

stipulated in writing. We also held that the interest due shall itself earn legal

interest from the time it is demanded, and that in the absence of stipulation

as to the payment of interest, the rate of interest shall be 12% per annum to

be computed from default, i.e., from judicial or extra-judicial demand.

We further declared that when the judgment of the court awarding a sum of

money becomes final and executory, the rate of legal interest, regardless of

whether it is a loan/forbearance of money case or not, shall be 12% per

235

236

237

Page 126: 2007 casesROBERTO C

annum from such finality until its satisfaction, this interim period being

deemed to be then equivalent to a forbearance of credit.

In the instant case, there was no written agreement as to the payment

of interest on the mortgage-loan between petitioner and respondents. The

rate of interest, therefore, is 12% per annum, to be computed from the time

an extra-judicial demand was made by the petitioner on 30 July 1992.238[40]

We also found that an amount of P107,000.00 out of the total loan of

P200,000.00 was already paid by the respondents. Thus, only the balance of

P93,000.00 should earn a legal interest of 12% per annum from the time of

the extra-judicial demand on 30 July 1992. In addition, a legal interest of

12% per annum should also be imposed to be computed from the finality of

this Decision up to its satisfaction.

WHEREFORE, the instant Petition is hereby GRANTED. The

Decision of the Court of Appeals dated 13 September 2005 in CA-G.R. CV

No. 79971 is hereby REVERSED and SET ASIDE. Respondents Eulogio

and Teresita Santos are hereby ORDERED to pay petitioner Antonio

Chieng, substituted by William Chieng, the balance of the loan amounting to

P93,000.00, plus legal interest of 12% per annum from 30 July 1992 up to

the finality of this Decision, and an additional legal interest of 12% per

annum from the finality of this Decision up to its satisfaction. No costs.

SO ORDERED.

238

Page 127: 2007 casesROBERTO C

REMINGTON INDUSTRIAL G.R. No. 171858SALES CORPORATION,

Petitioner, Present:

Ynares-Santiago, J. (Chairperson), - versus - Austria-Martinez,

Chico-Nazario, Nachura, and Reyes, JJ.

CHINESE YOUNG MEN’S CHRISTIAN ASSOCIATION OF THE PHIL. ISLANDS, doing Promulgated: business under the name MANILA DOWNTOWN YMCA,

Respondent. August 31, 2007

x ---------------------------------------------------------------------------------------- x

RESOLUTION

YNARES-SANTIAGO, J.:

For resolution is the motion for reconsideration filed by respondent

Chinese Young Men’s Christian Association of the Philippine Islands

(YMCA) of the Decision dated January 22, 2007, the dispositive portion of

which states:

WHEREFORE, the instant petition is GRANTED. The Decision and Resolution of the Court of Appeals in CA-G.R. SP No. 88599 are SET ASIDE. The Decision of the Regional Trial Court of Manila, Branch 25, in Civil Case No. 03-107655, dismissing the unlawful detainer case for lack of merit, is hereby REINSTATED and AFFIRMED.

Page 128: 2007 casesROBERTO C

SO ORDERED.239[1]

Respondent YMCA owns a two storey-building in Binondo, Manila.

It leased Unit No. 963 located at the second floor to petitioner RISC from

December 1, 1993 to November 30, 1995. It also leased to petitioner RISC

Unit No. 966 located at the ground floor from December 1, 1995 to

November 30, 1997, while the adjoining unit or Unit 964 was leased to

petitioner’s sister company RSC. Petitioner removed the partition between

Units 964 and 966 and used the combined areas as its office, hardware store

and display shop for steel products. It was also used as a passageway to

Unit 963, which was utilized by petitioner as its staff room.

On February 27, 1997, respondent formally terminated the lease over

the second floor unit and gave RISC until March 31, 1997 to vacate the

premises. Before the said period ended, RISC filed an action for the Fixing

of Lease Period over the said unit.240[2] Subsequently, YMCA filed an action

for Ejectment241[3] against petitioner. The two cases were consolidated before

Branch 26 of the Metropolitan Trial Court of Manila (MeTC-Manila).

Meanwhile, petitioner filed a Petition for Consignation of Rentals242[4]

alleging that respondent refused to receive payments of the rentals for the

ground floor units without just cause. During the hearing, petitioner filed a

Formal Surrender of the Leased Premises243[5] to which respondent

manifested that it does not object to the turn over or the surrender of the

239

240

241

242

243

Page 129: 2007 casesROBERTO C

leased premises.244[6] On July 9, 1998, after petitioner delivered two checks

covering the rents for the ground floor units, the trial court issued an Order

declaring the consignation case closed. However, petitioner continued to

use the premises as passageway since it is the only means of ingress and

egress to the second floor unit it occupies. RISC kept the premises

padlocked allegedly as a security measure and failed to give YMCA the keys

to the premises.

On August 11, 1998, the trial court hearing the consolidated cases

rendered a Decision extending the lease period for three years from finality

of the Decision and dismissed YMCA’s complaint for ejectment. Petitioner

filed a Motion to Constitute Passageway alleging that it has no means of

ingress or egress to its second floor Unit. An ocular inspection was

conducted on February 5, 1999. The Commissioner’s Report revealed that

petitioner is still in possession of the keys to the two ground floor units

because YMCA failed to provide an adequate passageway to the second

floor.245[7] Thereafter, YMCA manifested its willingness to constitute a

passageway provided Remington will surrender possession of the ground

floor unit.246[8]

Since respondent was never in actual possession of the premises at the

ground floor, it demanded payment from the respective lessees rentals in

arrears. Respondent sent Statements of Account dated September 7, 1999

and December 31, 1999 which petitioner repudiated. Finally, on January 18,

2000, respondent sent petitioner a Notice of Termination of Lease with

244

245

246

Page 130: 2007 casesROBERTO C

demand to vacate and pay rents from July 1998 to December 1999. This

was followed by Statements of Account dated July 28, 2000 and August 7,

2000 according to which the rental arrears amounted to P571,153.85.

On October 26, 2000, respondent filed two ejectment cases against

petitioner before the MeTC of Manila. The ejectment case against RSC over

ground floor Unit No. 964 was raffled to Branch 20 of the MeTC-Manila

which rendered its Decision on November 5, 2001 ordering RSC to vacate

the premises and to pay back rents. However, upon appeal, the RTC

reversed the Decision of the MeTC and dismissed the complaint. YMCA

appealed to the Court of Appeals which dismissed the case on technical

grounds and is now pending appeal before this Court.

The ejectment case against petitioner RSIC over ground floor Unit

No. 966, the subject matter of the case at bar, was raffled to Branch 17 of the

MeTC-Manila.247[9] In its Decision dated June 20, 2003, it ordered petitioner

RSIC to vacate the premises and to pay back rents.248[10] Consequently,

petitioner appealed to the RTC which ruled in its favor dismissing the

complaint for ejectment for lack of cause of action.249[11] Thereafter, YMCA

appealed to the Court of Appeals which reversed the RTC and reinstated the

Decision of the MeTC.

The Court of Appeals decided in favor of respondent YMCA ruling

that it was effectively deprived of possession of the subject units since RISC

failed to surrender possession despite manifesting its willingness to do so, by

247

248

249

Page 131: 2007 casesROBERTO C

padlocking the subject premises. It did not lend credence to petitioner’s

claim that the padlocking of the premises was for self-preservation and that

it is the only means of ingress and egress to its second floor unit since RISC

continued to exercise control over the subject premises. The appellate court

also rejected the RTC’s observation that YMCA was not prevented from

taking control of the disputed units for it could have easily forced open the

padlocks. It maintained that ejectment is the legal alternative as against the

use of force and breaches of the peace.

RISC thus filed the instant petition for review on certiorari assailing

the Decision of the Court of Appeals. In the assailed Decision, we ruled

that petitioner has effectively surrendered possession of Units 964 and 966;

that the filing of petitioner’s Formal Surrender of the Leased Premises

constitute constructive delivery of the said premises effective July 1, 1998 as

it thereafter emptied and vacated the premises; and that respondent could

have easily removed the padlock and take legal and actual possession of the

premises.

In the instant motion for reconsideration, respondent argues that

petitioner has not constructively delivered the possession of the ground floor

units despite the filing in the consignation case of the Formal Surrender of

the Leased Premises and after it has emptied and vacated the leased

premises on July 1, 1998. Respondent contends that petitioner’s use of the

premises as passageway, the continued padlocking of the gates and non-

turnover of keys constitute unlawful withholding of the possession of the

subject premises for which petitioner should be liable.

Page 132: 2007 casesROBERTO C

We grant the motion.

A case for Unlawful Detainer is an action against one who unlawfully

withholds possession after the expiration or termination of his right to hold

possession by virtue of any contract, express or implied, brought within one

year from the date of the last demand.250[12] From the allegations of the

respondent, the case for unlawful detainer is grounded on three acts of

petitioner, i.e., using the premises as passageway, the continued padlocking

of the premises and non-turnover of keys.

In a contract of lease, the lessor binds himself to give the enjoyment

or use of a thing to the lessee for a price certain, and for a period which may

be definite or indefinite.251[13] The lessor is obliged to deliver the thing which

is the object of the contract in such condition as to render it fit for the use

intended252[14] and upon its termination, the lessee shall return the thing just

as he received it, save what has been lost or impaired by the lapse of time, or

by ordinary wear and tear, or from an inevitable cause.253[15]

The filing of the Formal Surrender of Leased Premises and the actual

emptying of the premises constitute constructive delivery of possession.

Hence, the contract of lease was terminated on July 1, 1998 and it is

incumbent upon petitioner, as lessee, to comply with its obligation to return

the thing leased to the lessor and vacate the premises.

250

251

252

253

Page 133: 2007 casesROBERTO C

However, petitioner failed to comply with its obligation to return the

premises to respondent. In order to return the thing leased to the lessor, it is

not enough that the lessee vacates it. It is necessary that he places the thing

at the disposal of the lessor, so that the latter can receive it without any

obstacle. He must return the keys and leave no sub-lessees or other persons

in the property; otherwise he shall continue to be liable for rents.254[16]

Petitioner’s constructive delivery of the premises did not produce the

effect of actual delivery to the respondent. To be effective, it is necessary

that the person to whom the delivery is made must be able to take control of

it without impediment especially from the person who supposedly made

such delivery.255[17] In the case at bar, records show that despite the

termination of the lease, respondent was never in possession of the premises

because it was padlocked. Respondent was not given the key to the

premises hence it was deprived to use the same as it pleases.

Although the use of the premises as passageway was justified,

petitioner cannot deprive respondent the use of the said premises by having

it padlocked. Other than simply repudiating the demand for back rentals,

petitioner should have given respondent a set of keys so it can enter the

premises without exposing the property to security risks. Prudence dictates

the delivery of the keys to respondent to dispel any doubt that petitioner is

using the premises other than as a mere passageway and that it has never

withheld possession of the same to the respondent. Petitioner had several

opportunities to give respondent access to the premises starting from the

254

255

Page 134: 2007 casesROBERTO C

time it sent its first demand to pay back rentals until the complaint for

ejectment was filed but it never availed of these opportunities.

From the foregoing, it is apparent that petitioner’s constructive

delivery did not effectively transfer possession of the leased premises to

respondent. From the time the lease was terminated, petitioner unlawfully

withheld possession of the leased premises from respondent.256[18] However,

it appears that petitioner had moved out from respondent’s building on

March 12, 2004, as stated in its Manifestation257[19] before Branch 25 of the

RTC-Manila. Respondent is entitled to a reasonable compensation for

petitioner’s continued occupancy of the premises despite termination of the

lease from July 1, 1998 to March 12, 2004.

Under Section 17, Rule 70 of the Rules of Court, the trial court may

award reasonable compensation for the use and occupation of the leased

premises after the same is duly proved. In Asian Transmission Corporation

v. Canlubang Sugar Estates,258[20] the Court ruled that the reasonable

compensation contemplated under said Rule partakes of the nature of actual

damages based on the evidence adduced by the parties.  The Court also ruled

that “fair rental value is defined as the amount at which a willing lessee

would pay and a willing lessor would receive for the use of a certain

property, neither being under compulsion and both parties having a

reasonable knowledge of all facts, such as the extent, character and utility of

256

257

258

Page 135: 2007 casesROBERTO C

the property, sales and holding prices of similar land and the highest and

best use of the property.”259[21] 

The reasonable compensation for the leased premises fixed by the trial

court based on the stipulated rent under the lease contract which is

P22,531.00, must be equitably reduced in view of the circumstances

attendant in the case at bar. First, it should be noted that the premises was

used only as a means of passageway caused by respondent’s failure to

provide sufficient passageway towards the second floor unit it also occupies.

Second, respondent was negligent because it waited for more than a year

before it actually demanded payment for back rentals as reflected in its

Statement of Accounts dated September 7, 1999. When both parties to a

transaction are mutually negligent in the performance of their obligations,

the fault of one cancels the negligence of the other and, as in this case, their

rights and obligations may be determined equitably under the law

proscribing unjust enrichment.260[22] From the foregoing, we find the amount

of P11,000.00 a month equitable and reasonable compensation for

petitioner’s continued use of the premises.

WHEREFORE, the motion for reconsideration is GRANTED. The

Decision dated January 22, 2007 is VACATED and a new judgment is

entered REINSTATING and AFFIRMING the Decision of the

Metropolitan Trial Court of Manila in Civil Case No. 168628-CV with the

MODIFICATION that petitioner is ordered to PAY respondent

259

260

Page 136: 2007 casesROBERTO C

P11,000.00 a month from July 1, 1998 until March 12, 2004 as reasonable

compensation for the use of the premises.

SO ORDERED.