2003 MECON_Project Review Meeting 4th Dec'13

download 2003 MECON_Project Review Meeting 4th Dec'13

of 26

Transcript of 2003 MECON_Project Review Meeting 4th Dec'13

  • 8/13/2019 2003 MECON_Project Review Meeting 4th Dec'13

    1/26

    A H o u s e o

    f E n g i n e e r i n g

    E x c e l l e n c e

    MECON LIMITED

    As on 3rd

    Dec13

    BALANCE JOBS INSMS PROJECT.

  • 8/13/2019 2003 MECON_Project Review Meeting 4th Dec'13

    2/26

    A H o u s e o

    f E n g i n e e r i n g E x c e l l e n c e

    MECON LIMITED

    Sl.No.

    System Scope AlreadyCompleted

    upto thisreview

    ProgressDuring Review

    Period

    BALANCEJOBS

    DATE OFCOMPLETION

    REMARKS

    1.LIME PLANTCIVIL

    Cabletrench

    Pre castslab for cabletrench

    Flooring.

    Drain inLime Plant

    Arealeveling

    TOTAL

    480 m3

    80m3

    388m3

    187m 3

    1135m

    3

    477m3

    73m3

    368m3

    187m 3

    1105m

    3

    NIL

    3m3

    15m3

    NIL

    18m

    3

    3m3

    7m3

    20m3

    NIL

    27m3

    By 25th

    Dec13

    Completed.

    By Dec13.

    Overallcompletion by 25

    th

    Dec13 (includingroads)

    Job has beentaken up& is inprogress.

    PROGRESS & BALANCE JOBS IN SMS PROJECT --- Review Period-27 th Nov13 to 3 rd Dec13

  • 8/13/2019 2003 MECON_Project Review Meeting 4th Dec'13

    3/26

  • 8/13/2019 2003 MECON_Project Review Meeting 4th Dec'13

    4/26

    A H o u s e o f E n g i n e e r i n g E x c e l l e n c e

    MECON LIMITED

    Sl.No.

    System Scope AlreadyCompleted

    upto thisreview

    ProgressDuring Review

    Period

    BALANCEJOBS

    DATE OFCOMPLETION

    REMARKS

    1.2

    LIME PLANT

    MECHANICAL

    REFRACTORY

    1389T

    641T

    1048.5T.

    90T.

    Piping (mixedgas) &Diathermic oilpiping(3T),Vibrating screens& chutes(1.5T),Conveyor-deck plates(2.5T), DE-3(17T)TOTAL- 24T

    NIL

    340.5T(DE system,conveyorsystem,piping/ gasnetwork)

    551T.

    Jan14.

    Jan14.

    190T is nonpriority.

    Inspection callgiven by M/sTeruzzi/ SKGrefractories.Inspection is in

    progress at Nagpur

    PROGRESS & BALANCE JOBS IN SMS PROJECT----- Review Period-27 th Nov13 to 3 rd Dec13

  • 8/13/2019 2003 MECON_Project Review Meeting 4th Dec'13

    5/26

    A H o u s e o f E n g i n e e r i n g E x c e l l e n c e

    MECON LIMITED

    Sl.No.

    System Progress since last Review BalanceJobs

    Date ofCompletion

    Remarks

    1.3 LIME PLANT ELECTRICS

    & AUTOMATION

    1 st lot of Power cable (80drums)received at site. 24 drumspending. Out of 67 km , 55 kmreceived at site & balance 12 kmprocurement is under process.

    33T Strl. Steel for cable tray fromM/s Fame Steel, Nagpur received atsite.

    Cable schedule (Instrument cable-24177mt. & control cable 72157mt.) &automation drawings approved.

    600mm ladder type cable tray (1 kmout of 3 km) dispatched on 2 nd Dec13& received at site.

    Earthing job at site started. LTSS lime plant to MCC roommain cable trench cable traysupporting structures erection started(20% completed)

    Erection ofElectricalequipments( Automationpanels, Cabletray, Cables,Lightingfixtures etc.),testing &commissioning activities.

    By Feb14 M/s Teruzzihas to expeditesupply of cabletray (13kmapprox.) &Illuminationmaterial onurgent basis.

    Cable datasheet(instrument &control)to beapproved &

    pending withM/s Vulcan. &PO to beplacedimmediately.

    AC ducting job to beexpedited.

    PROGRESS & BALANCE JOBS IN SMS PROJECT--- Review Period-27 th Nov13 to 3 rd Dec13

  • 8/13/2019 2003 MECON_Project Review Meeting 4th Dec'13

    6/26

    A H o u s e o f E n g i n e e r i n g E x c e l l e n c e

    MECON LIMITED

    Sl.No.

    System Scope AlreadyCompleted

    upto thisreview

    Progress DuringReview Period

    BALANCEJOBS

    DATE OFCOMPLETION

    REMARKS

    2.LADDLEFURNACE CIVILLHF Proper.

    Compensator Buildingwith CableTrench.

    AHUbuilding.

    TOTAL

    2108m3

    340m3

    35m3

    2483m3

    2108m3

    340m3

    35m3

    2483m3

    False flooringfalse ceiling work isin progress.

    NIL

    Brick workcompleted.

    NIL

    Falseflooring falseceiling work .

    NIL

    Plastering,painting etc.

    NIL

    Balance job tobe completedalong with

    electrical cablingwork.

    Completed.

    Completed.

    Completed.

    PROGRESS & BALANCE JOBS IN SMS PROJECT -- Review Period-27 th Nov13 to 3 rd Dec13

  • 8/13/2019 2003 MECON_Project Review Meeting 4th Dec'13

    7/26

    A H o u s e o f E n g i n e e r i n g E x c e l l e n c e

    MECON LIMITED

    Sl.No.

    System Scope AlreadyCompleted

    upto thisreview

    ProgressDuring

    ReviewPeriod

    BALANCEJOBS

    DATE OFCOMPLETION

    REMARKS

    2.1

    LADDLE

    FURNACE

    MECHANICAL

    a) PIPING

    b) Fittings

    c) Valves

    d) Filter Cageswith Ventury

    e) ID Fan

    f) Hopper &

    Casing

    89T

    9T

    10T

    9T

    11T

    41T

    88T

    8.5T

    9.5T

    2T

    3T

    41T

    NIL

    0.5T

    0.5T

    NIL

    NIL

    8T

    1T

    0.5T

    0.5T

    7T

    8T

    NIL

    10th

    Dec13.

    10th

    Dec13.

    10th

    Dec13.

    15th

    Dec 13

    15th

    Dec13

    Completed.

    After civil handover forcompressor room & FTProom.

    PROGRESS & BALANCE JOBS IN SMS PROJECT----- Review Period-27 th Nov13 to 3 rd Dec13

  • 8/13/2019 2003 MECON_Project Review Meeting 4th Dec'13

    8/26

    A H o u s e o f E n g i n e e r i n g E x c e l l e n c e

    MECON LIMITED

    Sl.No.

    System Scope AlreadyCompleted

    upto thisreview

    ProgressDuring

    ReviewPeriod

    BALANCEJOBS

    DATE OFCOMPLETION

    REMARKS

    2.2

    LADDLEFURNACE MECHANICAL g)Soft waterpump.

    h) Uncooledduct from LF

    i) Water cooledcable

    j) SecondaryCircuit.

    k) Wire feeder

    TOTAL (INCL.PIPING)

    3T

    42T

    3.6T

    3T

    10T

    472T

    2T

    38T

    NIL

    NIL

    10T

    443T

    NIL

    3T

    NIL

    NIL

    NIL

    12T

    1T

    4T

    3.6T

    3T

    Completed.

    29T

    15 th Dec13.

    15 th Dec13

    25 th Dec13.

    15th

    Dec13

    Civil front to bemade ready.(FG bay-C-20)

    Modification workis under progress.SMS shut downrequired.

    Overall Completionby 25 th Dec13.

    PROGRESS & BALANCE JOBS IN SMS PROJECT---- Review Period-27 th Nov13 to 3 rd Dec13

  • 8/13/2019 2003 MECON_Project Review Meeting 4th Dec'13

    9/26

    A H o u s e o f E n g i n e e r i n g E x c e l l e n c e

    MECON LIMITED

    Sl.No.

    System Scope AlreadyCompleted

    upto thisreview

    ProgressDuring

    ReviewPeriod

    BALANCEJOBS

    DATE OFCOMPLETION

    REMARKS

    2.3

    LADDLE

    FURNACE

    STRUCTURA L

    Chimney

    erection.

    FAFA

    structure.

    Spark

    Arrestor

    Structure

    Misc.

    Structures.

    398T

    110T

    65T

    12T

    14T

    388T

    110T

    65T

    11T

    12T

    7T

    NIL

    NIL

    NIL

    NIL

    10 T

    NIL

    NIL

    1T

    2T

    20th

    Dec13 (By

    10th

    Dec 13)

    Completed.

    Completed.

    20th

    Dec13 (5th

    Dec13)

    20th

    Dec13 (10th

    Dec13)

    Welding & nutbolt tightening workis in progress.

    Gratingsavailable at site.

    PROGRESS & BALANCE JOBS IN SMS PROJECT- Review Period-27 th Nov13 to 3 rd Dec13

  • 8/13/2019 2003 MECON_Project Review Meeting 4th Dec'13

    10/26

    A H o u s e o f E n g i n e e r i n g E x c e l l e n c e

    MECON LIMITED

    Sl.No.

    System Scope AlreadyCompleted

    upto thisreview.

    ProgressDuringReviewPeriod

    BALANCEJOBS

    DATE OFCOMPLETION

    REMARKS

    2.4

    LADDLE

    FURNACE

    BAG Filter &

    Silo supportStructure.

    REFRACTORY

    (Scope-105T)

    137T

    105T

    (1200 nosfor ladle carprotection &7480 nosfor encasingof columnnear

    equipments)

    130T

    NIL

    7T

    NIL

    7T

    105T

    20 th Dec1330 th Nov13

    Starting ofob will be by20 th Dec13.

    Aftercompletion ofmechanicalob.

    DC issuedfor bricks &communicatedto MECON,

    Ranchi.

    PROGRESS & BALANCE JOBS IN SMS PROJECT----- Review Period-27 th Nov13 to 3 rd Dec13

  • 8/13/2019 2003 MECON_Project Review Meeting 4th Dec'13

    11/26

    A H o u s e o f E n g i n e e r i n g E x c e l l e n c e

    MECON LIMITED

    Sl.No.

    System AlreadyCompleted upto

    this review.

    Progress DuringReview Period

    BalanceJobs

    Date ofCompletion

    REMARKS

    2.5 ELECTRICAL MCC room &Control roompanels, desk, VFlocal control ,VFPDB Hydraulic

    room RIO panel,lubrication panel,HT Panel erectiondone, DCDB,Battery Charger,Furnace switch,WTP MCCerection,transformerinstallation checkup, bushinginstallation done.

    Trafo. roombusbar fixing workin progress.

    LF proper power

    & control Cablelaying in progress.

    LTSS#4 to MCC-1 ,2 & LTSS#5 toWTP MCC LT cablelaying completed.

    WTP MCCPanel erectionwork completed.

    FTP MCC , PFcompensator roomcable tray erectionstarted.

    Balanceelectrical &instrumentation equipmenterection in LF

    proper, ID Fancabling, FTP,Compensatorroom, cablelaying ,termination,testing &commissioning.

    By Dec13,Testing &Commissioning by Jan14.

    LCS -11/28nos.RIO -1/3nos.FIELDJB (Electrical )-9/23nos.INSTRUMENT

    JB -8nos.

    Testing groupto be deployedby DANIELI forprecommissioningchecks.

    Calibration ofinstruments to bedone.

    PROGRESS & BALANCE JOBS IN SMS PROJECT - -- Review Period-27 th Nov13 to 3 rd Dec13

  • 8/13/2019 2003 MECON_Project Review Meeting 4th Dec'13

    12/26

    A H o u s e o f E n g i n e e r i n g E x c e l l e n c e

    MECON LIMITED

    Sl.No.

    System Progress sincelast Review

    BALANCE JOBS DATE OFCOMPLETION

    REMARKS

    3. GAS HOLDER Alignment ofupper horizontalpiston girdercompleted.

    Closing of shellis under progress.

    Alignment of 48nos piston fendercolumncompleted.

    Spiral Plateerection.

    Surfacepreparation from10m to 22m forseal erection.

    New sealopening door fixing.& 01 no additionalmaintenance doorfixing.

    Painting work.

    Expected date ofcompletion oferection by Dec13.

    Expected date ofcommissioning is 31 st Jan14.

    BHEL will mobilizemanpower from 16 th Dec13 instead of20

    th Nov13.

    Expected date ofseal to reach at site

    10th

    Dec13.

    PROGRESS & BALANCE JOBS IN SMS PROJECT - -- Review Period-27 th Nov13 to 3 rd Dec13

  • 8/13/2019 2003 MECON_Project Review Meeting 4th Dec'13

    13/26

    A H o u s e o f E n g i n e e r i n g E x c e l l e n c e

    MECON LIMITED

    Sl.No.

    System Progress sincelast Review

    BALANCE JOBS DATE OFCOMPLETION

    REMARKS

    4. Hot Metal Mixer

    (1300T)

    Mixer

    Commissioning

    (M/s HEC)

    Charging hole

    cover erection.

    Testing of

    motor & power

    cables.

    UPS

    installation done,

    commissioning in

    progress.

    Blower made

    ready for idle run.

    Fixing of limit

    switches.

    Testing of

    individual

    equipments & trial

    run.

    PLC I/O

    testing, HMI

    installation &

    commissioning.

    Pre heating to

    start by 16th

    Dec13 &

    commissioning by

    26 th Dec13.

    Jupiter Hi Tech

    commissioning

    engineers are at site.

    Forbes Marshall

    commissioning team to

    arrive on 9 th Dec13.

    PROGRESS & BALANCE JOBS IN SMS PROJECT----- Review Period-27 th Nov13 to 3 rd Dec13

  • 8/13/2019 2003 MECON_Project Review Meeting 4th Dec'13

    14/26

    A H o u s e o f E n g i n e e r i n g E x c e l l e n c e

    MECON LIMITED

    Sl.No.

    System Alreadycompleted

    upto thisreview

    Progress duringreview period

    Balance Jobs Date ofCompletion

    Remarks

    5. Water System

    Soft Water

    Plant (M/s Ion

    Exchange).

    Fire FightingFacility (M/s

    Safety Control).

    Filter mediafilling workcompleted.

    3400Mtr.completed outof 4000Mtr.

    In-shopoverheadpiping of SMS1700mcompleted.

    Main IncomerCable laying fromLTSS#3 to MCC inprogress.

    Pump Housecivil work is inprogress.

    Electricalerection andpiping, testing&commissioning.

    Undergroundpiping of

    RMHS.

    300m out of2000m.

    By 20th

    Dec13(Nov13)

    By Jan14.

    Supply ofinstrumentation cable& hoist is pending.

    As per M/s IEILTesting group will beavailable at site on

    7th

    Dec13 for MCCpanel testing &charging.

    Manpower is lowdue to paymentrelated problems.

    Work held up dueto stored structuralitems of RMHS (M/sRukmani).

    PROGRESS & BALANCE JOBS IN SMS PROJECT -- Review Period-27 th Nov13 to 3 rd Dec13

  • 8/13/2019 2003 MECON_Project Review Meeting 4th Dec'13

    15/26

    A H o u s e o f E n g i n e e r i n g E x c e l l e n c e

    MECON LIMITED

    Sl.No.

    System Progress since lastReview

    BALANCE JOBS DATE OFCOMPLETION

    REMARKS

    6. Water

    System

    Circulation

    Water

    System-KBL

    Dosing pipe lines &under flow pumpspipeline erection in

    progress. 01 no Knife discharge

    filter , thickener is inoperation.

    Electrical connectionin scrapper & testing.Flexible cables & JBs

    are to be supplied byM/s Triveni.

    Testing &commissioning ofmotorized valves(NINL CLEARANCEREQUIRED) calibrationof balance 4 nos. flowmeters.

    ETP area Underslung crane electricalconnection, testing &commissioning.

    Laying of opticalfiber communicationcable to BOF & CCParea.

    By 15th

    Dec13Nov13

    By 15th

    Dec13Nov13

    Work is going slowdue to shortage ofmanpower.

    PLC personnel isrequired forcommissioning thewhole system.

    M/s KBL has to takeaction for cable surveywork inside tunnel &clearance will be givenaccordingly.

    PROGRESS & BALANCE JOBS IN SMS PROJECT -- Review Period-27 th Nov13 to 3 rd Dec13

  • 8/13/2019 2003 MECON_Project Review Meeting 4th Dec'13

    16/26

    A H o u s e o f E n g i n e e r i n g E x c e l l e n c e

    MECON LIMITED

    Sl.No.

    System Progress sincelast Review

    BALANCE JOBS DATE OFCOMPLETION

    REMARKS

    7. CRANES

    CD-Bay

    (150T)- Mixer

    Charging

    Crane.

    FG-Bay

    (100T Crane-II )

    All drives tested.

    Rope reeving ofboth hoists tested.

    Auxiliary hoist(50T) drive testing

    done.

    Commissioning

    work is being takenup parallely with CDbay crane.

    Load test.

    Testing &

    commissioning &rope reeving.

    By 7th

    Dec13,

    30th

    Nov13.

    By 15th

    Dec13,

    10 th Dec13.

    Trial run of all mechanismsbeing taken.

    Load shifting started. Few materials found

    defective during testing & tobe replaced.

    Drive testing by 10th

    Dec13.

    Rope reeving will be doneafter drive testing .

    Few materials founddefective during testing & tobe replaced.

    PROGRESS & BALANCE JOBS IN SMS PROJECT----- Review Period-27 th Nov13 to 3 rd Dec13

  • 8/13/2019 2003 MECON_Project Review Meeting 4th Dec'13

    17/26

    A H o u s e o f E n g i n e e r i n g E x c e l l e n c e

    MECON LIMITED

    Sl.No.

    System Progress since lastReview

    BALANCEJOBS

    DATE OFCOMPLETION

    REMARKS

    7.1 FG-Bay-5T

    capacity

    Cantilever

    Crane

    Scrap

    Handling

    Crane (15T)-

    DE Bay

    Rotating

    Trolley

    Cranes (25T

    Crane-II) in LM

    & MN-Bay.

    Electrical panel

    manufacturing in

    progress by Unitech,

    Blore. Internal items

    procurement done.

    Revised drawing

    prepared & submitted

    to MECON, Ranchi for

    approval.

    NIL

    Supply &

    erection of crane.

    Magnet

    connection &

    Commissioning

    activity.

    By 22nd

    Dec13,

    5th

    Dec13

    By 10th

    Dec13,

    25th

    Nov13

    Strl design drg. (Crane

    support) received for construction.

    LTE will be done.

    Magnet & auxiliaries to bedispatched by 15.12.13.

    Cabling job 90% completed atsite.

    Dismantling of trolleyscompleted by M/s Pawanconstruction under HEC.

    Awaiting trailers at site fordispatch of trolleys .

    PROGRESS & BALANCE JOBS IN SMS PROJECT----- Review Period-27 th Nov13 to 3 rd Dec13

  • 8/13/2019 2003 MECON_Project Review Meeting 4th Dec'13

    18/26

    A H o u s e o f E n g i n e e r i n g E x c e l l e n c e

    MECON LIMITED

    Sl.No.

    System Progress sincelast Review

    BALANCE JOBS DATE OFCOMPLETION

    REMARKS

    7.2 BMFA CRANES

    15TGrab &

    20T EOT Crane.

    Electrical

    panels, cables

    are ready to be

    dispatched.

    IWC issued by

    MECON.

    Panels under

    dispatch to HEC

    Ranchi.

    Electrical erection of

    panels, cabling.

    DSL erection.

    Testing &

    commissioning.

    Execution by

    Dec13 (Nov13)

    Cables & DSL system

    ordered on M/s M R

    Trading, Kolkata. & M/s

    IEP, Kolkata.

    Inspection awaiting for

    DSL cable.

    PROGRESS & BALANCE JOBS IN SMS PROJECT---- Review Period-27 th Nov13 to 3 rd Dec13

  • 8/13/2019 2003 MECON_Project Review Meeting 4th Dec'13

    19/26

    A H o u s e o f E n g i n e e r i n g E x c e l l e n c e

    MECON LIMITED

    Sl.No.

    System Progress sincelast Review

    BALANCE JOBS DATE OFCOMPLETION

    REMARKS

    7.3 CRANES

    10 T Maintenance

    Crane for New

    Compressor House .-

    TECHNOINDUSTRIES,

    AHMEDABAD.

    Manufacturing

    completed.

    Crane is ready at

    supplier works.

    Erection &

    commissioning.

    Crane is ready at

    supplier works,

    Ahmadabad & is

    awaiting inspection.

    NINL Engr. To bedeputed for inspection.

    PROGRESS & BALANCE JOBS IN SMS PROJECT--- Review Period-27 th Nov13 to 3 rd Dec13

  • 8/13/2019 2003 MECON_Project Review Meeting 4th Dec'13

    20/26

    A H o u s e o f E n g i n e e r i n g E x c e l l e n c e

    MECON LIMITED

    Sl.No.

    System Progress sincelast Review

    BALANCE JOBS DATE OFCOMPLETION

    REMARKS

    8

    AC System(M/s FrickIndia)

    Ventilation

    System (M/sEFE, Kolkata)

    NIL

    NIL

    Supply of PUFinsulation.

    Testing &

    Commissioning ofpanels , fans &motors.

    By Dec13 (30 th

    Nov13).

    Commissionedand running as perrequirement.

    01 no. electroniccard for chiller unit-

    01 is to be replaced. Operation to takehandover for 24 hrs.running.

    All electrical

    drawings has beencleared fromMECON, Ranchi.

    EFE has to takeimmediate action forsupply of panels.

    PROGRESS & BALANCE JOBS IN SMS PROJECT--- Review Period-27 th Nov13 to 3 rd Dec13

  • 8/13/2019 2003 MECON_Project Review Meeting 4th Dec'13

    21/26

    A H o u s e o f E n g i n e e r i n g E x c e l l e n c e

    MECON LIMITED

    Sl.No.

    System Progress since lastReview

    Balance Jobs Date ofCompletion

    Remarks

    9. CCTV (M/sNELCO )

    LSTB (M/sPhi Audiocom,Pune)

    NELCO Engr.present at site.Power, Data, Video,Control Cabling BOFarea completed for 4nos cameras out of 6.

    Camera JB,

    mounting standerection & water tankerection completedfor 4 nos cameras atBOF.

    BOF & CCP areatesting activities inprogress.

    Fixing of Cameras-08nosin CCP & 06 nos. in BOF,water cooled jackets, UPS,Video & Control Cables,Remote controlled pan & tiltunits, Video distributionamplifier /equalizers, Control

    Console with control units,19 TFT monitors.

    CCP area -fixing of 03 nosdesktop stations.

    BOF area- fixing of 02 nosdesktop stations.

    Outside plant area &inside office interconnection--3 km cabling to be done.

    Total system testing &commissioning.

    By Dec13. AIR & WATERPIPELINES TO BEMADE READY.

    FollowingShortfall cables tobe supplied:

    3Cx2.5-1250mtrs7Cx1.5-1250mtrs2Px2.5-1250mtrsRG-11-1250mtrs.

    PROGRESS & BALANCE JOBS IN SMS PROJECT----- Review Period-27 th Nov13 to 3 rd Dec13

  • 8/13/2019 2003 MECON_Project Review Meeting 4th Dec'13

    22/26

    A H o u s e o f E n g i n e e r i n g E x c e l l e n c e

    MECON LIMITED

    Sl.No.

    System Progress since lastReview

    BALANCE JOBS DATE OFCOMPLETION

    REMARKS

    10. Fire

    Detection

    System (M/s

    Agnice)

    Caster bay loop

    cable tray work &

    fixing of MCPs &

    hooter completed.

    Minor modification

    work is in progress.

    Arrangement for

    fixing of detectors

    (heat & smoke) at LF

    area is in progress.

    Hooter , MCP fixing

    in BOF area columns

    ,fixing of siren in

    BOF, LHF area,

    caster bay loop

    cabling (approx 8km

    cabling), LHS cabling

    (approx-2km from

    LTSS#3 to

    LTSS#4)total system

    testing &

    commissioning.

    By Dec13.

    PROGRESS & BALANCE JOBS IN SMS PROJECT -- Review Period-27 th Nov13 to 3 rd Dec13

  • 8/13/2019 2003 MECON_Project Review Meeting 4th Dec'13

    23/26

    A H o u s e o f E n g i n e e r i n g E x c e l l e n c e

    MECON LIMITED

    Sl.No.

    System Progress since lastReview

    BALANCEJOBS

    DATE OFCOMPLETION

    REMARKS

    11

    12.

    Roads

    Secondary

    Emission

    NIL

    Approval given toMECON, Ranchi foreligibility criteria.

    Tender documentsawaited fromMECON.

    Bitumen

    Carpeting-3300

    m 2 .

    TENDERING& ORDERING.

    Bitumen

    Carpeting by

    Dec13.

    WMM completed.

    PROGRESS & BALANCE JOBS IN SMS PROJECT- -- Review Period-27 th Nov13 to 3 rd Dec13

  • 8/13/2019 2003 MECON_Project Review Meeting 4th Dec'13

    24/26

    A H o u s e o f E n g i n e e r i n g E x c e l l e n c e

    MECON LIMITED

    Sl.No.

    System Progress sincelast Review

    BALANCE JOBS DATE OFCOMPLETION

    REMARKS

    13. CCP

    CCP/Mixer/BOF/BMFA/SMSC1

    NIL

    Roof sheetingmodification/rectification workcompleted overmixer.

    CCP area-work started.

    Commissioningof EMS system

    Part area byDec13 & balancearea by March14.

    Cards available atsite.

    M/s CONCAST hasbeen intimated to

    deploy their expertto commission thesystem.

    PROGRESS & BALANCE JOBS IN SMS PROJECT----- Review Period-27 th Nov13 to 3 rd Dec13

  • 8/13/2019 2003 MECON_Project Review Meeting 4th Dec'13

    25/26

    A H o u s e o f E n g i n e e r i n g E x c e l l e n c e

    MECON LIMITED

    Sl.No.

    System AlreadyCompleted

    upto thisreview

    Progresssince last

    Review

    BALANCEJOBS

    DATE OFCOMPLETION

    REMARKS

    14. OutgoingRail TrackConnectivity-Excavationwork by M/s

    PradeepMining.

    Laying &commissioningof 1.5km railtrackconnectingBillet StorageYard toExchangeYard by M/s

    Premco RailEngg. Ltd.

    50,500 m3

    excavation-out of totalscope54,000m

    3.

    NIL.

    1000m3

    NIL.

    1)3,500 m3

    excavation.

    1.5 km. raillaying workwill start infirst week ofDec13.

    1st

    lineexcavationcompleted.2

    nd line by

    15th

    Dec13.

    1st

    Line-By Dec13end.

    2nd

    Line-By Feb14.

    Repeat orderfor additionalquantity is underprocess.(solidified slag

    dislodging atexchange yardis in progress).

    Balance Slagremovalrequired for 2

    nd

    line excavation.Re-routing of

    overhead powerline is underprocess.

    PROGRESS & BALANCE JOBS IN SMS PROJECT----- Review Period-27 th Nov13 to 3 rd Dec13

  • 8/13/2019 2003 MECON_Project Review Meeting 4th Dec'13

    26/26

    A H o u s e o f E n g i n e e r i n g E x c e l l e n c e

    MECON LIMITED

    TH NK YOU