2002 Furnace Tutorial
-
Upload
scongiundi -
Category
Documents
-
view
15 -
download
0
description
Transcript of 2002 Furnace Tutorial
Furnace OperationsTutorial
Ken BeasleyConsultant
Ethylene Global Consulting Services
Introduction to Ethylene Cracking Furnace Operation Fundamentals
The modern cracking furnace is the heart and soul of any ethylene plant.When operated and maintained properly it can have a long life and provide consistent production of product. Conversely improperly operated and/or maintained, it can be unreliable and very expensive to keep running.Today we will offer some fundamentals in the proper operation of modern cracking furnaces.
DisclaimerAlways follow your licensor design recommendations for your furnace.Since all modern furnace designs are tailor made for each application, the best general guidelines will not work for every furnace, even ones that are the most typical. Any values provided today, while they may be typical of many furnaces, are only used to illustrate general trends and tendencies and are not to be used without consulting your operations manual.If anything presented here conflicts with your furnaces design and operation manual, follow your manual.
Parameters for Controlling the Pyrolysis Reaction
Conversion/Severity – disappearance of feed-stock on a once through basisSelectivity – a measure of olefins production at a set conversion/severity Coil geometry - fixed by designCoil pressure - limited by design
Maintaining Proper Furnace Balance
Dilution steam rate well controlledHomogenous feed composition and steady composition will result in best operation Balanced Feed Flow to each pass • Adjust Feed flow +/- five percent maximum to
balance Coil Outlet Temperatures• Critical Flow Elements to divide flows equally
Adequate and Controlled DraftSufficient Excess Air - 2 to 3% oxygen minimum leaving the radiant sectionBalanced Coil Outlet Temperatures: for equalseverities (assuming equal feed and dilution steam flows and even heat flux) +/- 2 degrees C (~4 deg F)
Coking
A naturally occurring byproduct of steam cracking that results inHeater radiant coil inlet or outlet pressure increaseCoil tube wall temperature increaseIncrease in arch (bridgewall) temperatureTransfer Line Exchanger fouling – gradual increase in outlet temperature and/or increase in pressure drop
Sulfur Content in Feed
Sulfur reduces catalytic effect of the metals in the radiant coils, producing less CO/CO2Gaseous feedstock: 80 to 100 PPM (typical)Liquid feedstock: 100 PPM + (typical)
Typical Conversion LevelsEthane: 65 to 68 percent (majority of ethane
furnaces)Up to 75 percent & higher for some
Propane: 80 to 95 percent
Butane: 80 to 95 percent
Liquid Feed: Composition and desired distribution of products often measured by the ratio of Ethylene to Propylene or Methane to Propylene
Dilution SteamControls the partial pressure for reacting hydrocarbonsIncreases yield of olefinic product components and reduces coking at the same severityTypical dilution steam mass ratio to feed:• Ethane 0.30-0.35• Propane 0.30-0.40• Butane 0.40-0.45
Dilution steam is also used for final vaporization of liquid feedsMinimize contaminants such as Sodium
• Naphtha 0.50-0.80• Gas oil 0.60-1.2• HGO;HVGO 0.75-1.2
Typical Operating Temperature Limitations for Radiant Coils
Knowing your specific design metallurgical limits is the key
HK-40: 1040 degrees C (1905 degrees F)
HP-40 modified:1125 degrees C (2055 degrees F)
XTM: 1150 degrees C (2100 degrees F)
These are only typical examples of radiant coil metallurgy
Typical Operating Temperature Limitations (Cont‘d)
Typicals for many modern designs:• Crossover process: 815 deg C (1500 deg F)
[decoking maximum]• Radiant coil process: 900 deg C (1650 deg F)
[decoking maximum]• TLE (Carbon Steel): less than 343 deg C
(650 deg F) • TLE(Carbon Steel with ½ MO): less than 400 deg C
(750 deg F)
Typical Operating Temperature Limitations (Cont‘d)
Typicals for many modern designs (Continued):
• Convection section tube support: 1155 deg C (2110 deg F) (maximum)
• Insulating Fire Brick: >1370 deg C (2500 deg F)
• Ceramic Fiber Blanket/Modules: >1370 deg C (2500 deg F)
• Castable Refractory: 1100 to 1370 deg C (2010 to 2500 deg F)
Coil Movement
All furnace coils but particularly the radiant coils must be able to move freely.Radiant coils have a short life if not allowed to move freely due to high stresses and deformation that results in• bowed tubes• uneven heat flux
Preoperational InspectionSpring hanger/counterweight• Proper setting• Proper weight• No interference
Coil guides and anchors• Proper clearance• Seal installed• Proper anchor installed
Preoperational Inspection (Cont‘d)Coil (inside heater)• Free to move as they expand or contract• All clearances meet tolerance• No tubes bowed
Coil (outside heater)• Proper crossover pipe support with sufficient
clearance• Crossover insulation installed• Proper spring hanger/counterweight installed
Preoperational Inspection (Cont‘d)Burner and piping• Burner properly installed and clean• Fuel gas piping cleaned (Initial Commissioning)• Check if all burner block valves are accessible from
platform (Initial Commissioning)
Instrumentation• Thermocouple/thermowell properly installed in the
Coil outlet, crossover, firebox, TLE outlet• Verify calibration
Preoperational Inspection (Cont‘d)Structure• Casing stiffening installed (Initial Commissioning)• Convection section tube support bolting tightened
(Initial Commissioning)• No bolts/nuts missing (Initial Commissioning)
Refractory/expansion joints• Check if all brick, castable, and ceramic fiber
insulation are in place• Check setting drawings for expansion joint size and
location (Initial Commissioning)• Make sure all debris has been removed
Preoperational Inspection (Cont‘d)Platform and ladders (Initial Commissioning)• Check accessibility to instruments• No interference with piping or instruments/electrical• Unobstructed emergency exit available in two
directions
Peep and access doors • Can be opened easily and closed tightly• Internal insulation installed fills peep door• Access openings closed with brick/ceramic fiber
blocks
Preoperational Inspection (Cont‘d)Convection section tubes (Initial Commissioning)• Check for cleanliness• Check for damaged fins• Check crossover piping for proper setting and
guides• Check manifold/jumpover anchor points
Preoperational Inspection (Cont‘d)
TLEs and steam drum (Initial Commissioning)• Check TLE support beams for level and square• Check top guides for proper length and
clearance• Check risers/downcomers are free to expand
vertically and laterally• Check if steam drum supports have clearance
to expand
Preoperational Inspection (Cont‘d)Stack damper/induce draft fan• Check for construction materials left (Initial
Commissioning)• Check insulation for damage• Expansion clearance between damper plate and
insulation (Initial Commissioning)• Damper shaft alignment• Check linkage, minimum stop, and air failure
position• Check instruments for proper location• Verify ID fan rotation (Initial Commissioning)
Furnace OperationFurnace Strategy (Startup)• Check instrumentation and interlocks• Check blind installation• Decoking air is blinded or disconnected• Check stack damper for proper operation• Open steam drum and super heater vent valve• Check all fuel gas block valves are closed• Check transfer line valves in proper position• Open decoking valve• Fill steam drum to 50 percent, open blowdown to
keep flow through Boiler Feed Water coil
Furnace Operation (Cont‘d)Furnace Strategy (Startup) (Cont’d)• Adjust burner dampers for start• Start I.D. fan, check draft, and purge box for fifteen
minutes• Check combustibles with portable analyzer• Light pilots with portable torch or igniters• When permissives are satisfied, begin to light
burners• Use an even pattern to keep firebox uniform
temperature• Follow furnace vendor recommendation
Furnace Operation (Cont‘d)Hydrocarbon injection• Coil outlet temperature should be below target
temperature - 15 to 20 deg C (60 to 70 deg F) typical
• Dilution steam flow above normal (around 160% of design is typical)
• Make sure furnace effluent is lined up to gasoline fractionation or quench tower
• Light as many burners as possible and still have control
• The board operator observes the Coil Outlet Temperatures and as soon as they begin increasing, start feed flow to the furnace
Furnace Operation (Cont‘d)Hydrocarbon injection (Cont’d)• The feed rate can be increased at whatever rate is
required to keep Coil Outlet Temperatures reasonably uniform
• Maximum variation in Coil Outlet Temperatures in the range of 10 to 30 deg C (20 to 55 deg F)
• When feed rate reaches 50 percent of design start reducing dilution steam so when you reach design feed flow you have design steam to hydrocarbon ratio
• Place controllers on automatic• Check furnace for stable operation. If OK, increase
Coil Outlet Temperatures to target temperature
Furnace Operation (Cont‘d)Furnace alignment and adjustment• Draft and excess air• Burners firing pattern• Coil Outlet Temperature adjustment• Tube Metal Temperature pyrometer survey• Transfer Line Exchangers outlet temperature • Transfer Line Exchangers pressure drop• Check firebox oxygen, NOX, and CO
Furnace Operation (Cont‘d)
Pyrometer Survey of the radiant coils once furnace is in stable operationOnce experience with this furnace is established, the intervals and locations should be adjusted
Furnace DecokingDecoking is required:• Whenever the radiant Tube Metal
Temperatures reach their limit• Whenever there is a significant increase in the
coil inlet or outlet (10 psi typical)• When the Transfer Line Exchangers outlet
reaches the design temperature• When a furnace which has been in operation
for more than a few days and has a severe upset that has caused spalling often indicated by increased pressure differential across the coils and/or TLEs
Furnace Decoking (Cont‘d)
Methods of decoking• Steam• Steam and air
Furnace Decoking (Cont‘d)
Typical decoking limitations(follow licensor design)• COT’s 830 - 900 deg C (1525 - 1650 deg F)• Crossover processes 750 to 815 deg C (1380 to
1500 deg F)• COT’s 1000 - 1065 deg C (1830 - 1950 deg F)
(steam decoking only)• TMT’s 950 deg C (1740 deg F) (steam/air
decoking)• Transfer Line Exchangers outlet 425 deg C
(800 deg F)
Furnace Decoking (Cont‘d)Decoking parameters• COTs should be balanced at end of run temperature
to insure maximum burn and complete decoke
• Cross Over temperatures should start at the maximum allowable to insure a good start of burn at the inlet.
• Using an on-line CO2 analyzer is good measure of the burn
• Choke flow is required at all times for passes with critical flow elements.
Furnace Decoking (Cont‘d)Elements of a Good Decoke Procedure• Firing
is operated on manualis only increased
• Dilution Steam Flowis held constant or decreasedsufficient flow to ensure diffusion does not limit burning and to fluidize spalled cokenot enough to cause erosion
• Air FlowAir is only added
• Radiant tubes are visually inspected during decoke
Furnace Decoking (Cont‘d)
Characteristics of a complete decoke• Coil passes have a clean coil pressure
drop• There are no hot spots on the coils• CO2 at the end of the decoke is < 1%
Furnace Decoking (Cont‘d)Steam-air decoking – plugged tube• Restricted tube has a partial loss of flow
Will clear during decokingAdd time
• Plugged tube has no flowWill not clear during decokingIf a shutdown to replace the tube is not possible, then operate with the tube plugged, but monitor to make sure it doesn’t bow and touch adjacent tubes
Furnace Decoking (Cont‘d)Transfer Line Exchangers Cleaning• Typical experience is to have 3 to 4
decoke cycles between Transfer Line Exchanger cleaning - furnace shutdown and hydroblasting of the Transfer Line Exchanger
• Proprietary processes to steam/air decoke Transfer Line Exchangers
Glossary of Terms
TLE (TLX) - Transfer Line ExchangerCOT - Coil Outlet TemperatureTMT - Tube Metal TemperatureHC - Hydrocarbon (usually as feed to the furnace)DS - Dilution SteamHGO - Heavy Gas OilHVGO - Heavy Vacuum Gas Oil