Page 2: 2 RNC System Commissioning

Page2Copyright © 2007 Huawei Technologies Co., Ltd. All rights reserved.

Foreword The commissioning is performed after the hardware installation

The commissioning ensures the RNC works properly as

designed

RNC commissioning procedure

Commissioning RNC hardware

Commissioning software loading

Verifying all interfaces

Verifying RNC services

Integrating the RNC into M2000

Page 3: 2 RNC System Commissioning

Page3Copyright © 2007 Huawei Technologies Co., Ltd. All rights reserved.

References

《 RNC Commissioning Guide 》

Page 4: 2 RNC System Commissioning

Page4Copyright © 2007 Huawei Technologies Co., Ltd. All rights reserved.

Objectives Upon completion of this course, you will be able to:

Describe the procedure of RNC commissioning

Perform the steps in RNC commissioning

Page 5: 2 RNC System Commissioning

Page5Copyright © 2007 Huawei Technologies Co., Ltd. All rights reserved.

Contents

1. Introduction to RNC Commissioning

2. Procedure of RNC Commissioning

Page 6: 2 RNC System Commissioning

Page6Copyright © 2007 Huawei Technologies Co., Ltd. All rights reserved.

Introduction to RNC Commissioning Definition of RNC Commissioning

The commissioning of equipment, RNC loading, interfaces, and services after hardware installation

To ensures that the RNC works as designed

RNC Commissioning Prerequisites Passing hardware installation acceptance and powering-o

n test At least one NodeB and one set of CN equipment available

Page 7: 2 RNC System Commissioning

Page7Copyright © 2007 Huawei Technologies Co., Ltd. All rights reserved.

Introduction to RNC Commissioning RNC Commissioning Preparations

BAM and LMT application software are ready

License file is ready

MML command script for initial configuration is ready

Page 8: 2 RNC System Commissioning

Page8Copyright © 2007 Huawei Technologies Co., Ltd. All rights reserved.

Contents

1. Introduction to RNC commissioning

2. Procedure of RNC commissioning

Page 9: 2 RNC System Commissioning

Page9Copyright © 2007 Huawei Technologies Co., Ltd. All rights reserved.

Contents

2. Procedure of RNC commissioning

2.1 Commissioning RNC Equipment

2.2 Verifying interfaces (Iub, Iu-CS, Iu-PS, Iur)

2.3 Handling Alarms During RNC Commissioning

2.4 Verifying RNC Services

2.5 Integrating the RNC into the M2000

2.6 Creating RNC Scheduled Tasks

2.7 Checking RNC Commissioning Results

Page 10: 2 RNC System Commissioning

Page10Copyright © 2007 Huawei Technologies Co., Ltd. All rights reserved.

Procedure of RNC commissioning Commissioning RNC Equipment

Step 1 Commissioning BAM

Install the BAM application in the active workspace

Check the operation of the BAM application

Step 2 Commissioning LMT

Install LMT application

Connect LMT to the BAM

Start the local maintenance terminal

Page 11: 2 RNC System Commissioning

Page11Copyright © 2007 Huawei Technologies Co., Ltd. All rights reserved.

Procedure of RNC commissioning Commissioning RNC Equipment

Step 3 Loading RNC software and data file

Generating RNC data file

– Clear the data in the BAM database (RST DATA)

– Generate the data file in offline state (SET OFFLINE & FMT DATA)

DB

BAM

FormatFAM board

Resetto load

ConfigurationManagement

module

MMLConfiguration

command

*.dat

Configuration console

Page 12: 2 RNC System Commissioning

Page12Copyright © 2007 Huawei Technologies Co., Ltd. All rights reserved.

Procedure of RNC commissioning Commissioning RNC Equipment

Step 3 Loading RNC software and data file

Setting RNC loading parameter (SET LODCTRL )

Loading RNC

– Reset RNC (RST SYS)

– The boards automatically load software and data file from the

BAM

– Start the loading progress window to monitor the loading

process

Page 13: 2 RNC System Commissioning

Page13Copyright © 2007 Huawei Technologies Co., Ltd. All rights reserved.

Procedure of RNC Commissioning Commissioning RNC Equipment

Step 4 Verifying the license

Save the license in BAM Active Workspace Installation Directory\

FTP\License

Activate the license (ACT LICENSE)

Check the license consistency between host and BAM (CMP

LICENSE)

Display the configuration of license (DSP LICENSE)

Step 5 Verifying Switchover Between Active and Standby

Boards (SWP BRD)

Page 14: 2 RNC System Commissioning

Page14Copyright © 2007 Huawei Technologies Co., Ltd. All rights reserved.

Procedure of RNC Commissioning Verifying interfaces (Iub, Iu-CS, Iu-PS, Iur)

The protocol structure of terrestrial interfaces

TransportNetwork

Layer

Transport NetworkUser Plane

Control Plane User Plane

Transport NetworkUser Plane

Transport NetworkControl Plane

RadioNetwork

Layer

SignalingBearer

Physical Layer

SignalingBearer

DataBearer

Application Protocol

User Data

ALCAP

Page 15: 2 RNC System Commissioning

Page15Copyright © 2007 Huawei Technologies Co., Ltd. All rights reserved.

Procedure of RNC Commissioning Verifying interfaces (Iub, Iu-CS, Iu-PS, Iur)

Check the status of different objects Verifying Iub interface

Checking physical link (DSP E1T1, DSP ETHPORT) Checking control plane (DSP SAALLNK, DSP SCTPLNK, DSP IUB

CP) Checking user plane (DSP AAL2PATH, DSP IPPATH)

Page 16: 2 RNC System Commissioning

Page16Copyright © 2007 Huawei Technologies Co., Ltd. All rights reserved.

Procedure of RNC Commissioning Verifying interfaces

Verifying Iub interface Checking management plane

– To be sure NodeB can be operated at remote end

Checking cell status (DSP CELL)

Verifying Iu-CS, Iu-PS and Iur interfaces The procedures and commands are similar with those in Iu

b interface

Page 17: 2 RNC System Commissioning

Page17Copyright © 2007 Huawei Technologies Co., Ltd. All rights reserved.

Procedure of RNC Commissioning Handling Alarms During RNC Commissioning

Clearing the alarms if something wrong happen

Verifying RNC Services

To be sure RNC can provide services defined in license

file

Basic services

– Voice service, CS stream service, PS service, mobility

management, and OM management

Feature services

– Inter-system handover, HSDPA service, HSUPA service, MBMS

service, and location service

Page 18: 2 RNC System Commissioning

Page18Copyright © 2007 Huawei Technologies Co., Ltd. All rights reserved.

Procedure of RNC Commissioning Integrating the RNC into the M2000 Creating RNC Scheduled Tasks (back up tasks) Checking RNC Commissioning Results

iManagerTM M2000

DCN

Page 19: 2 RNC System Commissioning