2 MW Power Project- IM (Gujarat)
-
Upload
anoop-jain -
Category
Documents
-
view
222 -
download
0
Transcript of 2 MW Power Project- IM (Gujarat)
-
8/8/2019 2 MW Power Project- IM (Gujarat)
1/9
2 MW Solar Power based
Power Project
1.0 Power Scenario in India
India is one of the fastest growing economies
amongst the emerging markets and has seen adecade with a CAGR of more than 7%. Even
after the global slowdown, India is expected to
record almost 8% growth in the current year
(2009-10) and go back to pre-slowdown levelsof 9%+ from next year.
One of the key ingredients for growth on an
economy is Energy and there is a positive
correlation between per capita income and percapita power consumption. Per capita
consumption of power in India is 700 units per
annum, which is far below the world averageand almost 400 million people in the country
do not yet have access to power. India, thus,
has a peak deficit of over 13% and averagedeficit of over 9% in its energy requirements,
at current levels, without counting the
additional requirements for growth as well as
the needs for sections of society which are stilldeprived of this basic necessity. To meet the
growing demand of energy, Government of
India has worked out a plan for enhancement ofgeneration capacity by 78,000 MW by the end
of 2011-12 and another 100,000 -110,000 MW
by 2017. Some studies have indicated thatIndia would need 950,000 MW against
availability of 450,000 MW by the end of
2030.
1.1 Power Generation
Like everywhere else, India also uses almost allsources of energy, including Thermal Power,
Hydro Power, Fossil fuel based Power, Nuclear
Power and Power from Renewable Sources i.e.Wind, Biogas, Solar. Thermal power, however,
remainsthe core of power generation, though
newer fuels are finding their way into this
industry. The table below shows the sources of
power generation as they stack-up in the total
power generation capacity in India:
1.2 Renewable Sources of Energy
In India, Power from renewable sourcesaccounts only 10% of the total power
generation. Out of 15,225 MW generated from
renewable sources, 10,890 MW is producedfrom Wind Power and only 8 MW is produced
from Solar Power sources as on 31st October,2009.
2.0 Solar Power in India
India is blessed with approximately 300 sunnydays with about 2,3003,200 clear sunshine
hours per year. Indias theoretical power
reception is on the land area is 5,000 trillionkWh/year. The daily average solar energy
incident over India ranges from 4 to 7 kWh/m2,
depending upon geographic location. Withsuch high potential of solar energy,
government of India has taken several
measures to promote the generation & use of
Solar energy. Government announced manyschemes in the 11th five year plan (2007-2011),
out of which NSM, National Solar Mission-
2022, is the most ambitious plan which targets
Prepared By:
Cascade Solar Pvt Ltd
New Delhi, India
Source Power
Generat-
ion (MW)
%
Thermal Power:
- Coal 81,606 52
- Gas 17,056 11
- Oil 1,200 01
Hydro Power 36,885 23
Nuclear Power 4,120 03
Renewable Energy
Source
15,225 10
Total 1,56,092 100
-
8/8/2019 2 MW Power Project- IM (Gujarat)
2/9
to make India as a global leader in the solar
energy.
2.1 National Solar Mission
The NSM is a major initiative of theGovernment of India and State Governments to
promote & encourage ecologically sustainable
growth while addressing Indias energy
security challenge. This mission targets toproduce 20,000 MW by 2022 and thus making
India a global leader in Solar Power.
2.1.1 Installed Capacity Targets under
NSM
2.1.2 Key Points of NSM
a) To ramp up capacity of Grid-
Connected Solar Power generation to
1,000 MW by 2013 and an additional3,000 by the 2017 through themandatory use of renewable purchase
obligation by utilities backed with a
preferential tariff. b) To promote programmes for off grid
applications, reaching 1,000 MW by
2017 and 2,000 MW by 2022.c) To achieve 15 million sq. meters solar
thermal collector area by 2017 and 20
million by 2022.
d) To deploy 20 million solar lightingsystems for rural areas by 2022.
e) To create favorable conditions for solar
manufacturing capability, particularlysolar thermal for indigenous production
and market leadership.
2.1.3 Types of Solar Power Projects
under NSM
The mission envisages the setting up of the
following demonstration projects in the Phase
I:
a) 50-100 MW solar thermal Plant with 4-
6 hours storage.
b) A 100 MW capacity parabolic trough
technology based solar thermal plant.c) A 100-150 MW solar hybrid plant with
coal, gas or bio-masses to address
variability and space-constraints.d) 20-50 MW solar plants with or without
storage, based on central receiver
technology with molten salt / steam asthe working fluid and other emerging
technologies.
e) Grid-Connected rooftops PV systems.
f) Solar-based space-cooling and
refrigeration systems to meet day timeand summer season peak load.
2.1.4 Incentives / Subsidies under NSM
To promote private investment in this sector,Government has planned to offer following
incentives for power generation units:
a) Excise duties and custom duties
concessions / exemptions are made
available on specific equipments,critical materials, components and
project imports.b) Capital / interest subsidy.
c) Accelerated Depreciation.
d) Preferential tariff for grid interactive
renewable power (in potential states).e) Financing the project upto 70% of the
total project cost.
f) Loan at low interest rate.
2.1.5 Proposed Time Frame & Process
Prepared By:
Goldbird Advisors Pvt LtdNew Delhi, India
Phase Year Capacity
Target (MW)I Upto 2013 1,100
II Upto 2017 4,000
III Upto 2022 20,000
Particular Date
Invitation of EOI 31/03/2010
Last date of submission of
application with documentsfor registration
30/06/2010
Selection of developers by theCentral Empowered
Committee
15/09/2010
Signing of MOU with SPD 30/09/2010
Readiness for signing of PPA& PSA 31/10/2010
-
8/8/2019 2 MW Power Project- IM (Gujarat)
3/9
2.1.6 Proposed Guidelines for
Registration under NSM
I. Expression of Interest (EOI):
a) Invitation of EOI for registration of the new
Solar Power Developers (SPDs) with NVVN.
b) SPDs meeting the eligibility requirements
will be registered with NVVN.
c) The final selection will be made out of
registered SPDs.
II. Eligibility Requirements
a) Net worth of Rs. 3-5 Crore/MW for the pastthree years.
b) Land in possession of at least 1 hectare/MW.
c) Water allocation for Solar Thermal.
d) Confirmation from STU regarding
evacuation of power at 33kv & above.
e) Technical requirement as approved by
MNRE.
f) Undertaking for domestic content to be
submitted as under-
For Solar PV - Use of both Cells &
Modules.
For Solar Thermal 30% local content.
2.1.7 Conditions Precedents for Signing
of MOU
a) Statutory and other clearances as applicable.
b) Complete DPR.
c) Letter of Comfort (LOC) for Equity / Debt
from Promoter(s) / Financial Institution(s).
d) Submission of performance bank guarantee Rs. 50 lakh/MW
Rs. 25 lakh/MW before signing of
MOU.
Rs. 25 lakh/MW before signing of PPA.
e) No change in controlling share holding in
the company permitted from MOU signing till
PPA execution.
2.1.8 Key Elements of PPA
a) PPA will remain valid for 25 years from thedate of commencement of supply from the
solar power project.
b) The solar power tariff will be applicable forthe year of commissioning as determined by
the CERC.
c) Transmission charges, losses, RLDC/SLDC
charges, scheduling charges or any othercharges for supply of solar power beyond
delivery point to be borne by the respective
distribution utility.
d)
Billing & Payment cycle will be as per Energy
Accounts issued by RPC/SLDC.
Prepared By:
Goldbird Advisors Pvt LtdNew Delhi, India
Source Power
Generation
(MW)
Thermal Power 9,498
Hydro Power 772
Nuclear Power 825Renewable Energy
Source
1,398
Total 12,493
-
8/8/2019 2 MW Power Project- IM (Gujarat)
4/9
e) Scheduling of power will be as per Indian
Electricity Grid Code (IEGC).
f) NVVN will establish irrevocable revolvingletter of credit (LCs) in favour of the Solar
Power Developers prior to commencement of
electricity supply from the proposed Solar
Power Plant.
g) Distribution Utilities will ensure Payment
Security Mechanism (PSM) as per Escrow / Tri
Partite Agreement and open irrevocable
revolving letter of credit.
h) After execution of PPA, controlling share
holding in the company will be maintained
upto 3 years after commencement of supply ofpower.
3.0 Power Scenario in Gujarat
Gujarat is one of the most progressive states in
the country. It has been in the forefront of
industrial development of India and has shownsignificant leadership in other spheres of
economics and social development too.
The per capita consumption of power in
Gujarat is more than 1,300 units, which is the
second highest in the country. The totalgeneration is expected to be about 10,984 MW(installed capacity is expected to be increased
to 14,645 MW and T&D losses around 25%)
against the expected peak demand of more than14,031 MW by the end of 2011-12.
3.1 Power Generation in Gujarat
The Gujarat state is pre-dominantly dependent
on thermal power. The table below shows thebreak up of various source of power generation
in the state of Gujarat.
With the sole aim of making Gujarat a power
leader in future, the provincial Government has
been taking many steps to promote &encourage the private players to set up power
plants in the state.
The graph below shows the governments
efforts to promote the private players to set upmore and more power plants in the state of
Gujarat. In Gujarat private players produces
more than 34% of the total power generation.
3.2 Power Consumption:
The table and graph below show the peak
power shortage in the state of Gujarat.
(In MW)
06-07 07-08 08-09
Availability 8,110 8,885 9,830
Requirements 11,619 12,119 12975
Shortage 30% 27% 24%
Prepared By:
Goldbird Advisors Pvt LtdNew Delhi, India
3,509
3,234
3,145
2,900
3,000
3,100
3,200
3,300
3,400
3,500
3,600
2006-07 2007-08 2008-09
State
45%
Central
21%
Private
34%
-
8/8/2019 2 MW Power Project- IM (Gujarat)
5/9
4.0Solar Power Policy of Gujarat State
Gujarat state government has introduced the
Solar Power Policy-2009 on 6th January, 2009
with the following resolution.
1. Operative Period: This policy will remainin operation up to 31st March, 2014. SolarPower Generators (SPGS) installed and
commissioned during the operative period will
become eligible for the incentives declared
under this policy, for the period of 25 yearsfrom the date of commissioning or for the life
span of the SPGS, whichever is earlier.
2. Installed Capacity: A maximum of 500
MW will be allowed for installation during theoperative period of the policy.
3. Capacity Cap: The minimum project
capacity of a SPG, in case of SPV and SolarThermal will be 5 MW each.
4. Eligible Unit: any company or bodycorporate or association or body of individuals,
whether incorporated or not, or artificial
juridical person will be eligible for setting up
of SPGS, either for the purpose of captive useand / or for selling of electricity, in accordance
with the amended Electricity Act-2003. The
entity will submit a proposal, with requisitedetails, as may be specified to the Nodal
Agency, for qualifying for setting up of the
project.
5. Exemption from Payment of Electricity
Duty: Electricity generated from the SPGS and
used for the self consumption / sale to the third
party / sale to licensees will be exempted formpayment of Electricity Duty.
6. Exemption from Demand Cut: Exemption
from demand cut to the extent of 50% of the
installed capacity of SPGs, assigned for captiveuse purpose, will be allowed.
7. Security Deposit: The developer will be
required to provide Bank Guarantee (BG) of
Rs. 50 Lacs / MW at the time of signing ofPPA with GUVNL and / or distribution
licensee.
If the developer fails to achieve commercialoperation within time period mentioned in
PPA, the BG will be forfeited. BG will berefunded, if the developer achieves commercialoperation within time period as per PPA.
8. Open Access (OA) for third party sale: If
any developer or beneficiary is granted OA,they will have to pay the applicable OA
charges and losses as approved by GERC from
time to time. The Cross Subsidy Surchargewill not be applicable for OA obtained for third
party sale within the state.
9. Sale of Energy: The energy generated from
a solar power project, will be sold to the
distribution licensees in the state at levelised
fixed tariff per unit as mentioned in the tablebelow for the period of 25 years, under a PPA,
to be specified by the GUVNL and / or
distribution licensee.
Benefits of this policy will not be available to projects set up under the MNRE incentivescheme for solar power generation. Further,
any subsidy / incentive received by SPG
developer from any source will be reducedfrom above mentioned rate for purchase of
power from SPG developers except the benefit
of Accelerated Depreciation under income taxact.
Prepared By:
Goldbird Advisors Pvt LtdNew Delhi, India
Particulars Tariff for
Photovoltaic
(Rs./KWh)
Tariff for
Thermal
(Rs./KWh)ProjectsCommissio-
ned before
31/12/2010
a) 13.00 forfirst 12 years
b) 3.00 for
next 13 years
a) 10.00 forfirst 12 years
b) 3.00 for
next 13 years
Projects
Commissio-
ned before31/03/2014
a) 12.00 for
first 12 years
b) 3.00 for next 13 years
a) 9.00 for
first 12 years
b) 3.00 for next 13 years
-
8/8/2019 2 MW Power Project- IM (Gujarat)
6/9
10. Plant & Machinery: Only new Plant &
Machinery will be eligible for installationunder this policy.
11. Sharing of CDM benefit: The developerwill pass on 50% of the gross CDM benefits to
the distribution licensee with whom PPA issigned.
12. Reactive Power Charges: The drawl of
reactive power will be charged as per the
GERC order, as amended from time to time.
13. State Government Facilitation and Nodal
Agency: GEDA & GPCL will be the stategovernment nodal agencies for facilitation and
implementation of the solar power policy
2009.
14. Forecasting & Scheduling: The SPG
based generation will not be covered under
scheduling procedure for intra state ABT.However, the actual energy injected in the grid
during particular time block of 15 minutes will
be post-facto considered in drawl schedule forsale of power to licensee / third party for giving
set-off against the consumption of recipient
unit in case of wheeling.
15. Metering of Electricity: The electricity
generated from the SPGs, will be metered on amonthly basis jointly by GEDA and GETCO at
the sending sub-station of 66 KV or above
located at site.
16. Grid Connectivity & Evacuation facility
up to GETCO sub-station: The evacuation
facility form the solar sub-station/switch yardto the GETCO sub-station will be initially
approved by GETCO after carrying out thesystem study. The power by the SPG will beinjected at 66 KV. The transmission line from
the switch yard of the solar sub-station to the
GETCO sub-station will be laid by GETCO.
17. Renewable Purchase Obligation: The
quantum of power that can be injected in the
grid from all renewable resources i.e. purchase
by distribution licensees plus captive
consumption plus third party sale should berestricted to 10% of the total consumption. This
will be subject to the further detailed
regulations pronounced by GERC from time totime.
18. Restriction for use of fossil fuel: fossilfuel will not be used in a Solar Thermal Power
Project.
19. Wheeling Charges: The wheeling ofelectricity generated form the SPGs, to the
desired locations/s for self use within the state,
will be allowed at a wheeling charges of 2% ofthe energy fed to the grid, till the wheeling
charge is decided by the GERC and thereafter
at the wheeling charge as per GERC, asamended from time to time.
20. Penalty for non fulfilling power purchase
obligation: Distribution licensee failing tomeet the minimum solar power purchase as
specified by the commission is liable to pay
penalty at a rate of Rs. 12/KWh to GEDA,which will be passed on the to the distribution
licensee who procure in the ratio of their solar
power purchase during the year.
21. Mid Term Review: State government may
undertake a mid term review of this policy aftera period of 3 years or as and when need arises
in view of technological breakthrough or to
remove any inconsistency with Electricity Act
2003, rules and regulations made there under orany government of Indian policy.
22. Power to remove difficulties: If anydifficulty arises in giving effect to this policy,
the Project Approval Committee is authorizedto issue clarification as well as interpretation tosuch provisions, as may appear to be necessary
for removing the difficulties.
4.1 Eligibility Criteria as per Solar
Power Policy of Gujarat State:
Prepared By:
Goldbird Advisors Pvt LtdNew Delhi, India
-
8/8/2019 2 MW Power Project- IM (Gujarat)
7/9
The entity desiring to set up the solar power
plant for selling electricity to distribution
licensee in the state of Gujarat is required tofulfill the below following financial and
technical eligibility criteria.
I. Financial Criteria
a) Internal Resource Generation (IRG):
Rs. 1.2 Crore/MW of the capacity,computed as five times the maximum
internal resources generated during any
of the last five years businessoperations.
b) Net Worth (NW): Rs. 2 Crore/MW of
the capacity which will be derived from
any of the past three years annualaccounts.
c) Annual Turnover (AT): Rs. 4.8
Crore/MW of the capacity which willbe derived from any of the past three
years annual accounts.
AT = Annual Gross Revenue Earned
II. Technical Criteria
a) Any entity in order to qualify will
essentially be required to have
collaboration with proven technologysupplier of solar power projects.
b) The entity mush have experience of
developing any projects in the last 10
years whose aggregate capital costs
must not be less than the amount
equivalent to Rs. 3 Crore/MW of thecapacity. Out of these projects, the
capital cost of at least one project
should be equivalent or more than Rs.50 Lacs/MW of the capacity. For this
purpose, capital expenditure on projectsthat have been completed at least 7 daysbefore the submission date of proposal
will be considered.
c) Developing Projects means successful
commissioning of a project in whichentity has not less than 26% equity
stake at the time of commissioning the
project.d) Entity will furnish documentary
evidence duly certified by qualified
auditors in support of their technicalexperience.
e) The entity will submit the proposal for
obtaining approval for setting up Solar
Power Project for selling electricity todistribution licensee in the state of
Gujarat to the Technical Committee.
5.0 The Project
It is proposed to set up a 2 MW solar power
plant in the state of Gujarat. The project wouldbe set up by the Cascade Solar Pvt. Ltd. The
project will sell power to the grid.
5.1 Location
Gujarat (complete location need to know)
5.2 Project Execution & Management
Cascade Solar / Belliss, (complete
information need to know)
Prepared By:
Goldbird Advisors Pvt LtdNew Delhi, India
IRG = PAT + Depreciation &
Amortization+ Decrease in net CA
(excluding cash) + Non-Cash
expenditure (including deferred tax) Scheduled Loan repayment
Increase in net CA (excluding cash)
NW = Equity Share Capital +
Reserves Revaluation Reserves Intangible Assets Miscellaneous
expenditures to the extent not written
off and carry forward losses
-
8/8/2019 2 MW Power Project- IM (Gujarat)
8/9
5.3 Cost of Project & its Financing
Cost of the project is estimated as under:
It is proposed to finance the project through
equity (30%) and debt (70%). A number ofspecialized lending institutions exist in India
which focus on the power sector and offer
concessional debt financing at around 10% forthe sector. Debt can be sourced from overseas
if cheaper, provide hedging costs are
reasonable.
5.4 Project Economics
In addition to the Government owned gridwhich offers a lower realization, power
produced by private projects can also be
traded / sold through power tradingcorporations set up in the public and the private
sector. Long-
term agreements can be signed with suchtrading corporation at a per unit realization of
INR 18 (USD 0.39), while actual realization,incase pre-contracted can be higher. Our
calculations are based on assured realization asstated above and the viability and payback
should improve with better realization through
the auction process.
Indicative calculation of pay-back for the
project is as under:
Prepared By:
Goldbird Advisors Pvt LtdNew Delhi, India
Sr.
No.
Particulars USD/
Millions1. Land - 0.88
2. Civil Works 0.33
3. Plant & Machinery 5.70
4. Total Works Cost 6.91
5. Detailed Design Engineering
& Project Management
0.29
6. Interest during construction
and pre-operatives
0.31
7. TOTAL PROJECT COST 7.51
Sr.
No.
Description Unit of
Measurement
1. Installed Capacity KW 2,000.00
2. Total Cost of the Project USD Millions 7.51
3. Operating Hours in a Year Hour 2,100.00
4. Annual Generation Million KwH 4.20
5. Auxiliary Power Requirement % of Total
Generation
0.025%
6. Auxiliary Consumption Million KwH 0.001
7. Net Units Available for Sale Million KwH 4.19
8. Fixed Charges:
a) - O & M Charges (1% of Total Capital Expenditure) USD Millions 0.06b) - Employee Cost USD Millions 0.07
c) - Interest @ 10% P.A. USD Millions 0.51
d) - Miscellaneous Expenses USD Millions 0.05
e) - Depreciation (on WDV) USD Millions 0.34
Sub-Total (a +b +c +d +e) USD Millions 1.03
9. Fixed Charges Per KwH USD/KwH 0.25
10. Sale Price To Grid USD/KwH 0.39
11. Savings Per Unit USD/KwH 0.14
12. Annual Savings USD Millions 0.5913. Annual Savings + Depreciation USD Millions 0.93
14. CDM Benefits (Carbon Credits) USD Millions 0.059
15. Pay-Back Period with CDM Benefits Years 6.04
-
8/8/2019 2 MW Power Project- IM (Gujarat)
9/9
Prepared By:
Goldbird Advisors Pvt LtdNew Delhi India