Basics of Capital Budgeting. An Overview of Capital Budgeting.
2. capital budgeting review
-
Upload
sudarshan-kadariya -
Category
Economy & Finance
-
view
247 -
download
7
Transcript of 2. capital budgeting review
Capital Budgeting
By
Sudarshan Kadariya
IBM
The Position of Capital Budgeting
Capital Budgeting
L o n g T e rm A sse ts S h o rt T e rm A sse ts
Investm ent D ecison
D e b t/E qu ity M ix
Financing D ecis ion
D iv id en d P a yo u t R a tio
D ividend D ecision
Financial Goa l of the F irm :W ealth Maxim isation
1. Average Rate of Return
2. Payback Period
3. Discounted Payback Period
4. Net Present Value
5. Internal Rate of Return
6. Modified IRR
7. Profitability index
Capital Budgeting - Methods
Non-discounted Cash Flow Methods Discounted Cash Flow Methods
i) ARR: Calculate & compare with cutoff rate /required rate of return/hurdle rate (Decision rule: if ARR>Cutoff = Accept, otherwise reject )
i) DPBP: Same except cash flow are discounted by project’s COC
ii) PBP: Years to recover initial investment. Shorter the PBP, the better.
ii) NPV: Find the discounted net cash flow of the project at 0 year. Higher NPV, the better
iii) IRR: The discount rate that yield zero NPV. If IRR>hurdle rate = accept the project
iv) MIRR: When the case of non-normal cash flow. Discount rate that equates PV of costs and PV of terminal value
v) PI: Also known as benefit-cost ratio, PV of benefits/PV of costs. Acceptable of PI>1
ARR = Avg. Net Income Per Year Avg. Investment
Average Rate of Return
Example:Year Net Income Cost1 6,000 100,000
Initial2 8,000 0 Salvage
Value3 11,0004 13,0005 16,0006 18,000
ARR
Avg. Net Income 72,000 6
Avg. Investment 100,000 2
AROI 12,000 50,000
ARR
= 12,000
= 24%
= 50,000
Advantages◦ Simplicity◦ Use the readily available accounting information
Disadvantages◦ It is based on accounting information rather
than cash flows◦ Fails to take account of the timing of the cash
inflows and outflows◦ Time value of money is ignored
ARR
Years required to recover the original investment
Example:Year Net Income Cash Flow Cumulative CF1 6,000 26,000 26,0002 8,000 28,000 54,0003 11,000 31,000 85,0004 13,000 33,000
118,0005 16,000 36,000
154,0006 18,000 18,000
172,000
Payback = 3 + 100,000 - 85,000 118,000 - 85,000
Payback Method
= 3.45 Years
PBP The amount of time needed to recover the
initial investment
The number of years it takes including a fraction of the year to recover initial investment is called payback period
To compute payback period, keep adding the cash flows till the sum equals initial investment
Simplicity is the main benefit, but suffers from drawbacks
Technique is not consistent with wealth maximization—Why? (lack of reinvestment)
Advantages◦ Simplicity in use and a popular method
Disadvantages◦ Fails to consider cash flows after the payback
period◦ It provides limited insight into risk and liquidity◦ Ignore time value of money and cost of capital
(curved by DPBP)◦ Ignore the risk of the project while evaluation
PBP
FV = PV (1 + r)n
Compounding: Finding FV
Discounting:Finding PV:PV = FV/(1 + r) n
Internal Rate of Return:Finding r
Time Value of Money
Discounted Payback Period
Similar to payback period approach with one difference that it considers time value of money
The amount of time needed to recover initial investment given the present value of cash inflows
Keep adding the discounted cash flows till the sum equals initial investment
All other drawbacks of the payback period remains in this approach
Not consistent with wealth maximization
NPV = Present Value of All Future Cash Flows less Inital Cost
= CF1 + CF2 + CF3 +.......CFn - Io 1+r (1+r)2 (1+r)3 (1+r)n
Net Present Value
Year CF Disc. Factor PV
0 -100000 1 -100000
1 26000 1/1.1 = .9091 23637
2 28000 1/(1.1)2 = .8264 23139
3 31000 1/(1.1)3 = .7573 23290
4 33000 1/(1.1)4 = .6830 22539
5 36000 1/(1.1)5 = .6209 22352
6 18000 1/(1.1)6 = .5645 10161
NPV = 25121
NPV - Example
NPV Based on the amount of cash flows
NPV equals the present value of cash inflows minus initial investment
Technique is consistent with the principle of wealth maximization—Why?
Accept a project if NPV ≥ 0
Advantages◦ Consider time value of money◦ Maximize shareholders wealth (reinvestment)◦ Use all cash flow during the project life◦ Based on estimated cash flow rather than
accounting information of the project
Disadvantages◦ The estimation of cash flows is difficult due to
uncertainty◦ Difficult to determine the appropriate discount rate◦ In case of projects with unequal life, proper
consideration has to be given while applying NPV rules
NPV
Discount rate that makes NPV Zero (i.e., that equates PV of benefits with the cost).
IRR: Io = CF1 + CF2 + ..... + CFn
1+r (1+r)2 (1+r)n
Solve for r.
Example: 100,000 = 26000 + 28000 + 31000 + ... +18000
1+r (1+r)2 (1+r)3
(1+r)6
r = 18.2%
Internal Rate of Return
IRR
)(0LH
HL
LL RRx
PVPV
CFPVRIRR
Advantages◦ Consider time value of money◦ Maximize shareholders wealth (reinvestment)◦ Use all cash flow during the project life◦ Based on estimated cash flow rather than
accounting information of the project◦ Easy to understand
Disadvantages◦ IRR has problem when non-normal cash flow,
multiple IRR arise◦ The estimation of cash flows is difficult due to
uncertainty◦ In case of mutually exclusive projects (that does not
occur at the same time) IRR may give the conflicting results because of its assumption.
IRR
Internal Rate of Return
The rate at which the net present value of cash flows of a project is zero, I.e., the rate at which the present value of cash inflows equals initial investment
Project’s promised rate of return given initial investment and cash flows
Consistent with wealth maximization
Accept a project if IRR ≥ Cost of Capital
Modified IRR
nCIF
O MIRR
TVPV
)1(
MIRR is the discount rate at which present value of project’s cost is equal to the present value of its terminal value
Cross over rate is that discount rate where NPVs of two projects are equal
NPV profile is a graph that plots a project’s NPV against the COC rates
NPV versus IRR Usually, NPV and IRR are consistent with
each other. If IRR says accept the project, NPV will also say accept the project
IRR can be in conflict with NPV if ◦ Investing or Financing Decisions◦ Projects are mutually exclusive
Projects differ in scale of investment Cash flow patterns of projects is different
◦ If cash flows alternate in sign—problem of multiple IRR
If IRR and NPV conflict, use NPV approach
Profitability IndexPI = PV of all Benefits
PV of all Cost
Example:PV (Benefits) = 26000 + 28000 +..+18000
1.1 (1.1)2 (1.1)6
= 125121
PV (Cost) = 100000
PI = 125121 = 1.25 100000
NPV = CF1 + CF2 +.............. + CFn - Io
l+r (l+r)2 (l+r)n
Cash Flows IncrementalAfter TaxNet Working Capital
Estimating cash flow is more qualitative approach and base on the knowledge of the projects and the capability of the management
Estimating Cash Flows
1. Initial Costs: New cost of assetsAdditional WC
requirementSale of Old Assets
2. Annual Costs: Revenue Less CostsAfter Tax
3. Terminal Cash Flows: Salvage ValueRecovery of NWC
Procedure
Sale of Existing PlantCF= Selling Price + T (B.V. - S.P.)
Annual Cash FlowsOCF= (Sales-Cost)(1-T) + T, DEPREC
orOCF= Net Inc + Depreciation
Cash Flow Estimates
Evaluating Capital Projects1) Focus on Cash Flow, Not Profits.
– Cash Flow = Economic Reality.– Profits can be managed/manipulated.
2) Carefully Estimate Expected Future Cash Flows.
3) Select a Discount Rate Consistent with the Risk of Those Future Cash Flows.
4) Account for the Time Value of Money.5) Compute NPV
6) Net Present Value = Value Created or Destroyed by the Project.
NPV is the amount by which the value of the firm will change if you undertake the project.
7)Identify Risks and Uncertainties. Run a Sensitivity Analysis.
8) Identify Qualitative Issues.– Flexibility, Quality, Know-How, Learning, etc
9) Decide
Which technique is superior? Although our decision should be based on NPV,
but each technique contributes in its own way.
Payback period is a rough measure of riskiness. The longer the payback period, more risky a project is.
IRR is a measure of safety margin in a project. Higher IRR means more safety margin in the project’s estimated cash flows.
PI is a measure of cost-benefit analysis. How much NPV for every rupee of initial investment.
Thank you.