1H 2016 data center outlook: Phoenix, Colliers TSG

2

Click here to load reader

Transcript of 1H 2016 data center outlook: Phoenix, Colliers TSG

Page 1: 1H 2016 data center outlook: Phoenix, Colliers TSG

Colliers InternationalTechnology Solutions GroupGREATER PHOENIX | Q4 2015

COLLIERS INTERNATIONAL2390 E. Camelback Rd, Suite 100Phoenix, AZ 85016www.colliers.com/greaterphoenix

Why Phoenix is the Silicon Valley of the DesertPRO-BUSINESS

CLIMATEABUNDANT ACCESS TO

F I B E R

COMPUTER DATA CENTER

TAX EXEMPTION2ND FASTINGGROWING TECH FOCUSED WORKFORCE

M O R E T H A N 1 1 0

C O M P A N I E S

ONE OF THE MOSTPROGRESSIVED ATA C E N T E R INCENTIVE PROGRAMS

Diversified Economy HEALTHCARE & BIOMEDICAL

ADVANCED BUSINESS SERVICES SOFTWARE

MISSION CRITICAL AEROSPACE & AVIATION

EMERGING TECHNOLOGIES

MANUFACTURING & LOGISTICS

LOW COST OF POWER

$.065/kWhARIZONA IS THE ONLY

NET EXPORTERI N T H E S O U T H W E S T

TOP DESTINATION FOR THE

TO RELOCATE THEIR DATA CENTER FROM BOTH COASTS

MICHAEL ORTIZAVP - Technology Solutions Practice Group Direct: 602-222-5069 | Cell: [email protected]

Page 2: 1H 2016 data center outlook: Phoenix, Colliers TSG

Colliers InternationalTechnology Solutions GroupGREATER PHOENIX | Q4 2015

This document/email has been prepared by Colliers International for advertising and general information only. Colliers International makes no guarantees, representations or warranties of any kind, expressed or implied, regarding the information including, but not limited to, warranties of content, accuracy and reliability. Any interested party should undertake their own inquiries as to the accuracy of the information. Colliers International excludes unequivocally all inferred or implied terms, conditions and warranties arising out of this document and excludes all liability for loss and damages arising there from. This publication is the copyrighted property of Colliers International and /or its licensor(s). © 2015. All rights reserved.

Base Rent + Utility + PUE UpliftCOMPETING MARKETS IN THE SOUTH | WESTERN REGIONS

Dallas

TOTAL RENT

TOTAL PWR COST

TOTAL PUE COST

$24,814,365

80%

15%5%

$17,144,531

$207 kw/Mo

Phoenix

TOTAL RENT

TOTAL PWR COST

TOTAL PUE COST $25,169,506

77%

17%

6%

$17,389,902

$210 kw/Mo

Silicon V

TOTAL RENT

TOTAL PWR COST

TOTAL PUE COST

$30,195,583

68%

23%

8%

$20,862,477

$252 kw/Mo

LA

TOTAL RENT

TOTAL PWR COST

TOTAL PUE COST

$33,056,279

65%

26%

9%

$22,838,965

$275 kw/Mo

COLLIERS INTERNATIONAL2390 E. Camelback Rd, Suite 100Phoenix, AZ 85016www.colliers.com/greaterphoenix

MICHAEL ORTIZAVP - Technology Solutions Practice Group Direct: 602-222-5069 | Cell: [email protected]

AZ TCO IS EXCLUSIVE HB2009 DATA CENTER INCENTIVES PROGRAM WHICH

CAN PROVIDE ~$4.5 M IN ADDITIONAL SAVINGS OVER 10 YEAR PERIOD. * TCO NPV @ 8%

* *

* *