19th ANNUAL INTERNATIONAL MARITIME LAW … · Achielle Lauro Fu Giacchino & C v Total Societa...
Transcript of 19th ANNUAL INTERNATIONAL MARITIME LAW … · Achielle Lauro Fu Giacchino & C v Total Societa...
19th ANNUAL INTERNATIONAL MARITIME LAW ARBITRATION MOOT 2018
MEMORANDUM OF TEAM 27
PARTIES:
CERULEAN BEANS AND AROMAS PTY LTD CLAIMANT
-AND-
DYNAMIC SHIPPING LLC
RESPONDENT -AND-
THE SHIP ‘MADAM DRAGONFLY’
-COUNSEL FOR RESPONDENT-
MELISSA ARSOV MATTHEW JAMES MCKIERNAN CELIL SAID KARDASLAR FIONA GARTON
MEMORANDA FOR RESPONDENT TEAM 27
2
TABLE OF CONTENTS INDEX OF ABBREVIATIONS……………………………….……….….…. 3 INDEX OF AUTHORITIES………………………………………….…..…... 4
A CASES B LEGISLATION
C CONVENTIONS AND TREATIES D COMMENTARY SUMMARY………………………………………………………...……….... 7-8 PRELIMINARY ISSUES ....………………………………………………..... 9 A JURISDICTION ARGUMENT ON THE MERITS………………….......................................... 10 SUBMISSIONS ONE: THE CHARTER PARTY
I THE TRIBUNAL SHOULD FIND THAT THE RESPONDENT FIND THAT THE RESPONDENT DID NOT BREACH THE CHARTER PARTY II THE DEVIATION BY THE RESPONDENT TO THE PORT OF SPECTRE WAS JUSTIFIED UNDER CLAUSE 17 OF THE CHARTERPARTY AS A FORCE MAJEURE III IN THE ALTERNATIVE, THE DEVIATION WAS JUSTIFIED FOR THE PURPOSE OF SAVING PROPERTY
IV FURTHER, THE RESPONDENT DID NOT BREACH THE CHARTERPARTY AS THE DELAY WAS DUE TO FORCE MAJEURE
V THE RESPONDENT CANNOT BE HELD LIABLE FOR DAMAGE TO CARGO WHICH OCCURRED AFTER DELIVERY AT THE PORT OF DILLAMOND
VI IN THE ALTERNATIVE, IF ANY LIABILITY IS ATTRIBUTED TO THE RESPONDENT THEN IT IS SUBJECT TO LIMITATION UNDER INTERNATIONAL CONVENTION
SUBMISSIONS TWO: THE ISSUE OF LIEN OVER THE VESSEL I THE TRIBUNAL SHOULD DENY CLAIMANTS ASSERTION OF ENTITLEMENT OVER THE MARITIME LIEN OVER THE VESSEL
SUBMISSIONS THREE: COUNTERCLAIM
I THE TRIBUNAL SHOULD MAKE ORDERS FOR THE CLAIMANT TO BE HELD LIABLE FOR THE AMOUNT OWING UNDER THE CHARTERPARTY II THERE IS A VALID GENERAL AVERAGE CLAIM UNDER CHARTERPARTY
REQUEST FOR RELIEF
MEMORANDA FOR RESPONDENT TEAM 27
3
INDEX OF ABBREVIATIONS
& And
B/L Bill of lading
CBA Cerulean Beans and Aromas Proprietary Limited
CISG Convention on the International Sale of Goods
Cl Clause
DS Dynamic Shipping LLP
FM Force Majeure
LMMA London Maritime Arbitrators Association
MLAANZ Maritime Law Association of Australia and New Zealand
Ltd Limited
Pty Proprietary
UNCITRAL United Nations Commission on International Trade Law
USD United States Dollar
MD Madame Dragonfly
MEMORANDA FOR RESPONDENT TEAM 27
4
INDEX OF AUTHORITIES
A CASES
AUSTRALIA
Australian Coastal Shipping Case
Australian Coastal Shipping Commission v Green [1971] 1 QB 456, 483 (Lord Denning MR)
Bulk Chile Case Dry Bulk Handy Holding Inc. and another v. Fayette International Holdings Ltd and another (The Bulk Chile) [2012] EWHC 2107 (Comm)
Great China Metal Case
Hewett Case Hako Fortress Case
Sam Hawk Case
Great China Metal Industries Co Ltd v Malaysian International Shipping Corp Berhad ( 1998) 196 CLR 16 Hewett v Court (1983) 149 CLR 639 Programmed Total Marine Services Pty Ltd v The Ships Hako Fortress, Hako Endeavour, Hako Excel and Hako Esteem (2013) FCAFC 21 The Ship “Sam Hawk” v Reiter Petroleum Inc [2016] FCAFC 26
UNITED KINGDOM
Azioni Case
Halcyon Isle Case
Achielle Lauro Fu Giacchino & C v Total Societa Italiana Per Azioni [1968] 2 Lloyd's Rep 247 Bankers Trust International Ltd v Todd Shipyards Corporation [1981] AC 221 (PC), 232
Hong Kong Fir Case
Bijela Case
Trade Green Case
Hongkong Fir Shipping Co Ltd v Kawasaki Kisen Kaisha Ltd [ 1962] 2 QB 26 Marida Ltd v Oswal Steel (The Bijela) [1993] 1 Lloyd’s Rep 411 Trade Green Shipping Inc v Securitas Bremer Allgemeine Verischerungs AG [2000] 2 Lloyd’s Rep 451.
AQASIA Case
Makis Case
Vinnlustodin HF and another v Sea Tank Shipping AS [2016] EWHC 2514 (Comm) Vlassopoulos v British and Foreign Marine Insurance Co [1929] 1 KB 187
MEMORANDA FOR RESPONDENT TEAM 27
5
UNITED STATES OF AMERICA Trojan Case
Cineraria Shipping Case
Peck & Hughes v American Smelting and Refining Co (1913) 210 Fed Rep 89 Royal Insurance Co of America v Cineraria Shipping Co 894 F Supp 1557 (1996)
B AUSTRALIAN LEGISLATION
Admirality Act 1988 (Cth) Limitation of Liability for Maritime Claims Act 1989 (Cth)
Navigation Act 1912 (Cth)
Sale of Goods (Vienna Convention) Act 1986 (NSW)
Trade Practices Act 1975 (Cth)
Carriage of Goods by Sea Act 1991 (Cth)
C CONVENTIONS AND TREATIES Convention on Limitation of Liability for Maritime Claims, opened for signature 19 November 1976, [1991] ATS 12 (entered into force 1 December 1986); see Limitation of Liability for Maritime Claims Act 1989 (Cth).
International Convention for the Safety of Life at Sea (SOLAS) 1974, Ch V Regulations; International Maritime Organisation, Annex 25 - Guidelines for Voyage Planning - IMO Resolution A.893(21) UNCITRAL Model Law on International Commercial Arbitration
United Nations Convention on Contracts for the International Sale of Goods, opened for signature 11 April 1980, 1489 UNTS 58 (entered into force I January 1988) York-Antwerp Rules 1994
MEMORANDA FOR RESPONDENT TEAM 27
6
D SECONDARY MATERIAL
Girvin Girvin S, Carriage of Goods by Sea (Oxford University Press, 2nd ed, 2011)
Hudson
Sherman
Wilson
Hudson, Geoffrey, The York-Antwerp Rules: The Principles and Practice of General Average Adjustment in Accordance with the York-Antwerp Rules 1994 (LLP, London, 2nd ed, 1996) Sherman, Charles Phineas, Roman Law in the Modern World, vol 2 (Littleton, Colo. : F.B. Rothman, 1993) Wilson, John F, Carriage of Goods by Sea (Pearson, 7th ed, 2010)
MEMORANDA FOR RESPONDENT TEAM 27
7
SUMMARY
The parties
Cerulean Beans and Aromas Pty Ltd, is an exporter of speciality coffee goods.
Dynamic Shipping LLC is a transportation and logistics company.
Voyage Charterparty Agreement
The parties entered into a Charterparty agreement (‘The Charterparty‘) for the
transportation and delivery of 35,000kg of specialty grade coffee suitable for
immediate sale. The goods were packaged in four containers, with no damage noted
by the carrier during loading. Under the initial agreement the goods were to be carried
on board the vessel, MADAME DRAGONFLY MD 737.
Jurisdiction
The agreement is governed by the law of New South Wales, Australia (Clause 28, the
Charterparty). Incorporating Clause Paramount: Owners to have benefit of Article
4(5). The lex mercatoria of both ports are UK law. Both Jurisdictions are CISG
signatories.
MEMORANDA FOR RESPONDENT TEAM 27
8
According to Clause 27 a of the Charterparty, ‘any dispute arising out of or in
connection with its contract, including any question regarding its existence, validity or
termination, shall be referred to arbitration in London by...a tribunal of 3
arbitrators...in accordance with the Arbitration Laws of the London Maritime
Arbitrators Association (LMMA)’.
Port of Loading and Discharge
The initial receipt shows the goods were loaded at the Port of Cerulean. The
agreement stated the Port of Dillamond to be the point of discharge and the final
destination of the goods.
Current Position
The RESPONDENT has fulfilled all contractual obligations and rejects the claim put
forward by the claimant for damages and rejects any allegation of an equitable
maritime lien over the vessel ‘MADAME DRAGONFLY’.
The CLAIMANT has failed to pay for the costs associated with the voyage which for
goods were delivered in a merchantable condition. This has placed RESPONDENT in
a position where payments cannot be made essential to its operation and continuation
of its transportation business.
The CLAIMANT has commenced legal proceedings. The RESPONDENT seeks to
counterclaim for damages, demurrage and unpaid costs for the voyage and delivery of
goods.
MEMORANDA FOR RESPONDENT TEAM 27
9
PRELIMINARY ISSUES
SUBMISSION ON THE ISSUE OF JURISDICTION
The RESPONDENT argues that this tribunal does not have jurisdiction to hear the
CLAIMANT’s Charterparty claim’s: (I) the tribunal has the power to rule on its own
jurisdiction; (II) the Arbitration Agreement is governed by the law of NSW, Australia;
(III) liability for damage to cargo cannot be determined at this stage.
A. Clause 28 of the Charterparty states that the law of New South Wales,
Australia shall govern the agreement. Incorporating Clause Paramount: Owners to
have benefit of Article 4(5) of the Hague-Visby Rules.
I THE ARBITRAL PANEL DOES NOT HAVE JURISDICTION TO HEAR
THE MATTER AS IT WAS NOT PROPERLY CONSTITUTED IN
ACCORDANCE WITH THE CHARTERPARTY
A. A determination on this matter by the tribunal would be inconsistent with
Clause 27 of the Agreement relating to Arbitration.1
[1] Clause 27 (d) of the Charterparty requires that any dispute related to ‘technical
matters’ arising out of or in connection with the contract to be referred to expert
determination by an independent Master Mariner.
1 The Record, p 12: Clause 27.
MEMORANDA FOR RESPONDENT TEAM 27
10
[2] Clause 27 (g) identifies ‘technical matters’ as inclusive of the vessel’s route, loading
and unloading of cargo, storage conditions, and other matters which could be
reasonably considered within the expert technical knowledge of a Master Mariner.
[3] Clause 27 (e) states that arbitral proceeding cannot commence prior to the satisfaction
of Clause 27 (d).
[4] The expert opinion of Simon Webster, maritime engineer, does not satisfy the
requirements of Clause 27 (d) of the Charterparty and as such the arbitral panel has
not been properly constituted in accordance with the charter party requirements.
ARGUMENT ON THE MERITS
SUBMISSION ONE: THE RESPONDENT DID NOT BREACH THE
CHARTERPARTY.
[5] The RESPONDENT is not liable to pay damages because: (I) the deviation was
justified under Clause 17 of the Charterparty as a Force Majeure event; (II) the delay
in delivery was due to a Force Majeure event; Alternatively, if the Tribunal finds that
the RESPONDENT is liable: (IV) the RESPONDENT can rely on the Force Majeure
(FM) clause. Further, the RESPONDENT argues that it is not liable for damage to
cargo because: (V) the damage occurred after delivery and was due to the delayed
collection of the cargo by CLAIMANT. (IV) Any liability on the part of
RESPONDENT is limited under international convention.
MEMORANDA FOR RESPONDENT TEAM 27
11
I THE DEVIATION BY THE RESPONDENT TO THE PORT OF SPECTRE WAS
JUSTIFIED UNDER CLAUSE 17 OF THE CHARTERPARTY AS A FORCE
MAJEURE EVENT
[6] The RESPONDENT agrees that stopping at the Port of Spectre was a deviation. This
deviation was permitted under Clause 17(b) and (c) of the Charterparty.
[7] The deviation by the RESPONDENT was justified under Clause 17 of the
Charterparty as a Force Majeure event.
[8] The RESPONDENT will be excused from liability for its deviation if it can show
that: Clause 17 of the Chaterparty was engaged; and the RESPONDENT followed the
procedure required during a Force Majeure event.
[9] A Force Majeure event can be established for the purpose of engaging Clause 17 of
the Charterparty if there was:
(i) ‘unforeseen weather events, acts of God, accidents, fire, explosions flood,
land slips, ice, frost or snow’;
(ii) ‘inability to obtain or delays in securing transportation facilities, stoppages
of the Shipper’s fuel supply, hindrances of whatsoever nature in mining,
processing, loading, shipping or discharging products occurring without
negligence of the Charterer’.
[10] The RESPONDENT followed the procedure required in the event of a Force Majeure
event. Access to the Port of Dillamond was suspended by Port Authorities, the
deviation of the vessel was justifiable and necessary.
MEMORANDA FOR RESPONDENT TEAM 27
12
II IN THE ALTERNATIVE, THE DEVIATION WAS JUSTIFIED FOR THE
PURPOSE OF PROPERTY
[11] The RESPONDENT is entitled to deviate for the purpose of saving property,
including the ship, and will not be liable for such deviation under Clause 17 of the
Charterparty relating to Force Majeure.
[12] The Vessel was at liberty to deviate in order to ensure the safety of the vessel and its
cargo. Dangers to the vessel may result from natural causes, such as severe storms.
Where the dangers arise from natural causes they must be reasonably permanent, and
not merely inconvenient or occasional interruptions.
[13] At the time of the deviation it was unclear how long the severe weather would
continue, indeed any presumption of customary knowledge by the Master would have
been negated by the sudden occurrence of the weather.
[14] It was not viable for the Vessel to wait at sea, in dangerous weather conditions. The
RESPONDENT submits it would be dangerous to the ship for it to remain on its
chartered course, where severe wet weather conditions persisted and without
permission of the Port Authority to proceed to the Port of Dillamond. Therefore, the
RESPONDENT was permitted to avoid this danger to the property by deviating from
the usual course.
III FURTHER, THE RESPONDENT DID NOT BREACH THE CHARTERPARTY
AS THE DELAY TO DELIVERY WAS DUE TO A FORCE MAJEURE EVENT
[15] The RESPONDENT is not liable to pay damages because: (I) the deviation was
justified under Clause 17 of the Charterparty as a Force Majeure event; (II) the delay
MEMORANDA FOR RESPONDENT TEAM 27
13
[15] in delivery was due to a Force Majeure event ; Alternatively, if the Tribunal finds
that the RESPONDENT is liable: (IV) the RESPONDENT can rely on the Force
Majeure clause. Further, the RESPONDENT argues that it is not liable for damage to
cargo because: (V) the damage occurred after delivery and was due to the heavy rain
during the period delayed collection of the cargo by CLAIMANT.
IV THE RESPONDENT CANNOT BE HELD LIABLE FOR DAMAGE TO
CARGO WHICH OCCURRED AFTER DELIVERY AT THE PORT OF
DILLAMOND
[16] The cargo was delivered to CLAIMANT at 8.42pm on 29 July 2017. The
RESPONDENT at this time had discharge its obligations, and liability for the cargo
was passed to the CLAIMANT.
[17] In reliance of the expert evidence of Simon Webster, the cargo was damaged during
the 24 hour period AFTER 4.30am on 30 July.
[18] Any damage that occurred to the cargo after delivery is not attributable to the
RESPONDENT as the liability had passed to the CLAIMANT and as such the
CLAIMANT bears the liability.
[19] The CLAIMANT may not rely on an event of Force Majeure to limit liability due to
the unprecedented rainfall. The failure to collect cargo after receiving notification of
delivery and failure to mitigate losses by collecting the cargo in a timely manner for
immediate use will prevent access to limitation of liability under the contract.
MEMORANDA FOR RESPONDENT TEAM 27
14
VI IN THE ALTERNATIVE, IF ANY LIABILITY IS ATTRIBUTED TO THE
RESPONDENT THEN IT IS SUBJECT TO LIMITATION UNDER
INTERNATIONAL CONVENTION
[20] A If the RESPONDENT is liable for breach of contract then it will be entitled to limit
liability. Clause 28 of the Chaterparty will apply as ‘incorporating clause paramount:
owners to have benefit of Article 4(5) of the Hague-Visby Rules which provides:
‘(a) Unless the nature and value of such goods have been declared by the
shipper before shipment and inserted in the bill of lading, neither the carrier
nor the ship shall in any event be or become liable for any loss or damage to or
in connection with the goods in an amount exceeding 666.67 units of account
per package or unit or 2 units of account per kilogramme of gross weight of
the goods lost or damaged, whichever is the higher.
(b) The total amount recoverable shall be calculated by reference to the value
of such goods at the place and time at which the goods are discharged from the
ship in accordance with the contract or should have been so discharged.
The value of the goods shall be fixed according to the commodity exchange
price, or, if there be no such price, according to the current market price, or, if
there be no commodity exchange price or current market price, by reference to
the normal value of goods of the same kind and quality.
MEMORANDA FOR RESPONDENT TEAM 27
15
(c) Where a container, pallet or similar article of transport is used to
consolidate goods, the number of packages or units enumerated in the bill of
lading as packed in such article of transport shall be deemed the number of
packages or units for the purpose of this paragraph as far as these packages or
units are concerned. Except as aforesaid such article of transport shall be
considered the package or unit.
(e) Neither the carrier nor the ship shall be entitled to the benefit of the
limitation of liability provided for in this paragraph if it is proved that the
damage resulted from an act or omission of the carrier done with intent to
cause damage, or recklessly and with knowledge that damage would probably
result.
(h) Neither the carrier nor the ship shall be responsible in any event for loss or
damage to, or in connection with, goods if the nature or value thereof has been
knowingly mis-stated by the shipper in the bill of lading.’
[21] In the alternative, if the RESPONDENT is liable in negligence to the CLAIMANT, it
may limit its liability pursuant to the Convention on the Limitation of Liability for
Maritime Claims.
[22] Art 2.1(b), the cost of transporting cargo falls within the Limitation Convention where
there is a ‘loss resulting from delay in the carriage by sea of cargo’. Due to the closure
of the port, delivery of the Claimant’s cargo was impossible until the port was open
sometime after delivery fell due. Consequently, the CLAIMANT incurred loss
resulting from delay.
MEMORANDA FOR RESPONDENT TEAM 27
16
SUBMISSION TWO: LIEN OVER THE VESSEL
I THE TRIBUNAL SHOULD DENY CLAIMANTS ASSERTION OF
ENTITLEMENT TO MARITIME LIEN OVER THE VESSEL
A The tribunal does not have the jurisdiction to determine this matter
[23] The jurisdiction of Australia (and by default New South Wales) and England only
recognises four liens that are capable of conferring a maritime lien:
a. claims for damage done by the ship;
b. salvage claims;
c. bottomary and respondentia bonds (Masters dispersments); and
d. seaman’s wage claims.
[24] This unique maritime lien will be commenced as an action in rem against the ship or
property.2 This action in rem will amount to the arrest of the ship and the vessel
potentially being liquidated. This action is the exclusive jurisdiction of the Admiralty
Court.
[25] As this tribunal is not an Admiralty Court, as such it will not have the power to decide
or enforce the arrest of any vessel regarding any actions in rem. This tribunal
therefore lacks the jurisdiction to decide the alleged maritime lien over the
MADAME DRAGONFLY.
[26] Alternatively, if the tribunal decides has the jurisdiction to decide this issue, the
tribunal must find that the CLAIMANT has no claim of maritime lien over the
2 Admiralty Act 1988 (Cth) s 15(1).
MEMORANDA FOR RESPONDENT TEAM 27
17
MADAM DARGONFLY in relation to a sum of $100,000 for wages it has paid to the
crew.
[27] The maritime lien for seaman’s wages is ‘a privileged claim’3 and a ‘personal right’4.
A proceeding of this maritime lien may be commenced in an action in reim against
the ship.5 This privileged and personal right is a unique right afforded to the master
and members of the crew alone. It cannot be transferred or subrogated. Once it is
extinguished it cannot be revived.
[28] As was found in the Hako Fortress6 decision, the court found that a third party was
not entitled to claim a maritime wages lien over the vessel for funds that were paid to
crew members. The court found that only persons entitled to arrest a ship for a
maritime lien for unpaid wages were the master and the crew where their wages
remained unpaid.
[29] This case indicates why the tribunal should find that no maritime lien for wages is
possible to be found for the CLAIMANT. As demonstrated in the Hako Fortress
decision, only the crew is able to enforce any possible maritime lien for wages against
MADAME DRAGONFLY. The CLAIMANT is without any grounds to claim such a
right as it is clearly not the master or member of the crew of the MADAME
DRAGONFLY.
B This Tribunal has no jurisdiction to decide on any equitable maritime lien
over the vessel MADAME DRAGONFLY.
3 Bankers Trust International Ltd v Todd Shipyards Corporation (The ‘Halcyon Isle”) [1981] AC 221 (PC), 232. 4 Programmed Total Marine Services Pty Ltd v The Ships Hako Fortress, Hako Endeavour, Hako Excel and Hako Esteem (2013) FCAFC 21. 5 Admiralty Act 1988 (Cth) s 15. 6 Ibid.
MEMORANDA FOR RESPONDENT TEAM 27
18
[30] An equitable lien confers a power of sale and an appointment of a receiver through an
order of the court.7 A court must be the authority that decides if any equitable lien
exists over property and how that lien should be enforced.8
[31] This tribunal does not convey the powers of a court and as such it lacks the
jurisdiction to decide any alleged claim for an equitable lien of the MADAME
DRAGONFLY.
SUBMISSIONS THREE: COUNTERCLAIM
I THE TRIBUNAL SHOULD MAKE ORDERS FOR THE CLAIMANT TO BE
HELD LIABLE FOR THE AMOUNTS OWING UNDER THE CHARTER PARTY.
A The composition of the amount pleaded are as follows:
a. Freight;
[32] The parties have agreed that freight be paid by telegraphic transfer in United States
Dollars to the RESPONDENT’s account within two days of delivery of the cargo.9
[33] The parties have agreed that the freight for the voyage be in the amount of
$500,000.10
[34] Delivery of the cargo occurred 29 July 2017,11 as such payment of freight as agreed
by the parties was required to occur two after this date, that being 1 August 2017.
7 Charles Phineas Sherman, Roman Law in the Modern World (1917) vol 2, § 616. 8 Hewett v Court (1983) 149 CLR 639. 9 Voyage Charterparty Clause 22. 10 Voyage Charterparty Box 11. 11 The Record, p 24.
MEMORANDA FOR RESPONDENT TEAM 27
19
[35] A follow up invoice was sent by the RESPONDENT along with an email regarding
the late payment of the freight for the voyage, 7 August 2017. The CLAIMANT
responded by refusing to pay the invoice the freight costs.12
[36] The CLAIMANT has claimed this refusal to pay is due to a breach of the Charterparty
as a result of delayed arrival of the MADAME DRAGONFLY at the Port of
Dillamond. As discussed above the delayed arrival of the MADAME DRAGONFLY
to the Port of Dillamond was a direct result of Force Majeure event.13
[37] This Force Majeure event Clause clearly states ‘The shipper…shall not be liable on
any basis whatsoever, without limitation, whether it be in contract, tort, or otherwise,
in damages or otherwise responsible for the failure or delay...in discharging if
prevented, delayed or obstructed by any Force Majeure Event.’14
[38] Due to this clause in the Charterparty, the CLAIMANT is without any basis for
refusing payment of freight to the RESPONDENT. It is clear the RESPONDENT has
delivered the cargo and the tribunal must find that the CLAIMANT is liable for the
freight as agreed upon by the parties in the Charterparty.
b. agency fees at the Port of Spectre, to which the Madame Dragonfly was
required to deviate during the voyage;
[39] The RESPONDENT is able to call upon the principle of General Agency. According
to Rule A of the York-Antwerp Rules 1994, there is a ‘General Average act when,
[40] and only when, any extraordinary sacrifice or expenditure is intentionally and
reasonably made or incurred for the common safety for the purpose of preserving 12 The Record, p 33. 13 Voyage Charterparty Clause 17(b). 14 Voyage Charterparty Clause 17 [4].
MEMORANDA FOR RESPONDENT TEAM 27
20
from peril the property involved in a common maritime adventure’.15 The
RESPONDENT has satisfied the four conditions set out in Rule A, as such the
RESPONDENT is entitled to rely on the General Average adjustment.
[41] First, as the RESPONDENT was transporting the CLAIMANT’s cargo by sea, the
parties were clearly engaged in a joint enterprise appropriately required as a
‘common maritime adventure’.16 The MADAME DRAGONFLY, and by extension,
the CLAIMANT’s cargo on board, constituted the common property involved in
this maritime adventure.17
[42] Secondly, the expenditure incurred in relation to the MADAME DRAGONFLY
seeking an emergency berth at the Port of Spectre was extraordinary. It is out of the
ordinary for a ship’s guidance system to sustain damage during a voyage as a result of
solar flares damaging Global Positioning Satellites and consequently the need for the
emergency berth was ‘out of the ordinary’. The emergency berth therefore constitutes
expenditure beyond what was envisaged under the Charterparty and consequently the
CLAIMANT cannot expect the RESPONDENT to bear these extraordinary expenses
alone.18
[42] Thirdly, the expenditure was intentionally and reasonably incurred by the
RESPONDENT. The RESPONDENT deliberately deviated from the Charterparty
agreed course to seek and emergency berth in the Port of Spectre. Moreover,
[42] there was no ‘practicable alternative’19 available other than to deviate from the
agreed course to seek the emergency berth because the ship was unable to
continue on that voyage after the solar flares had damaged the navigation
15 York-‐Antwerp Rules 1994, Rule A. 16 Trade Green Shipping Inc v Securitas Bremer Allgemeine Verischerungs AG (The Trade Green) [2000] 2 Lloyd’s Rep 451. 17 Peck & Hughes v American Smelting and Refining Co (The Trojan) (1913) 210 Fed Rep 89. 18 Marida Ltd v Oswal Steel (The Bijela) [1993] 1 Lloyd’s Rep 411. 19 Australian Coastal Shipping Commission v Green [1971] 1 QB 456, 483 (Lord Denning MR).
MEMORANDA FOR RESPONDENT TEAM 27
21
equipment on the MADAME DRAGONFLY.20 In the circumstances, the General
Average act was reasonable.
[43] Fourthly, by seeking the emergency ‘port of refuge’,21 the RESPONDENT not only
ensured the safety and viability of the vessel, but also, by extension, the safety of
the CLAIMANT’s cargo. Damage to the navigation equipment by the solar flares
removed the ability of the MADAME DRAGONFLY to complete the voyage safely22
and imperilled the vessel’s operations, which necessarily placed the cargo at risk.
The RESPONDENT’s actions were therefore vital to maintain common safety and
prevent harm not only to the ship itself, but also to the CLAIMANT’s cargo.
Agency berthing costs were therefore incurred ‘for the purpose of preserving
from peril’23 the property involved in the common maritime adventure.
[44] Specifically, the RESPONDENT is entitled to a contribution for agency berthing
costs pursuant to Rule X ‘Expenses at Port of Refuge’,24 which enabled the
‘adventure to be completed’. 25
[45] The claim for contribution in General Average is not precluded even if the
expenditure was incurred negligently. If the Tribunal finds that the event
which gave rise to the expenditure may have been ‘due to the fault of one of the
parties to the adventure’,26 rights to ‘contribution in General Average shall not be
affected’.27 Rule D of the York-‐Antwerp Rules 1994 states clearly that when a
General Average situation exists, the expenditure incurred shall be the subject of
20 The Record, p 17: Email dated 26 July 2017 at 2:32pm 21 York-Antwerp Rules 1994, Rule X. 22 Royal Insurance Co of America v Cineraria Shipping Co 894 FSupp 1557 (1996). 23 York-Antwerp Rules 1994, Rule A. 24 York-Antwerp Rules 1994, Rule X. 25 York-Antwerp Rules 1994, Rule XIV. 26 York-Antwerp Rules 1994, Rule D. 27 York-Antwerp Rules 1994, Rule D.
MEMORANDA FOR RESPONDENT TEAM 27
22
an adjustment even though the General Average situation would not have arisen
but for the fault of the Respondent.28
[46] Where the tribunal applies the laws of New South Wales29 in determining the
General Average claim, the adjustment will be made in ‘accordance with the law
and practice of the United States of America’.30 RESPONDENT is able to rely on
the New Jason Clause in Clause 19 of the Charterparty, to claim the General
Average contribution ‘losses or expenses of a General Average nature’ resulting
from ‘any cause whatsoever, whether due to negligence or not’.31
[47] Therefore, if the tribunal finds that the reason for seeking the emergency berth
at the Port of Spectre was as a result of negligence or the RESPONDENT’s fault, it
will not result in the RESPONDENT’s inability to rely on the General Average
adjustment.
c. the cost of repairs to damage caused to the Madame Dragonfly when
avoiding dangerous weather conditions;
II THERE IS A VALID GENERAL AVERAGE CLAIM UNDER THE
CHARTERPARTY.
[48] The RESPONDENT is able to rely on Clause 19 of the Charterparty to claim a
contribution in General Average.
[49] As discussed above the RESPONDENT is able to rely on a claim of General Average
regarding the damage to the hull from actions taken by the crew that occurred during
the unexpected dangerous weather conditions.
28 Geoffrey Hudson, The York-Antwerp Rules: The Principles and Practice of General Average Adjustment in Accordance with the York-Antwerp Rules 1994 (LLP, 2nd ed, 1996) 58. 29 The Record, p 12: Clause 28. 30 The Record, p 10: Clause 19. 31 The Record, p 10: Clause 19 [2].
MEMORANDA FOR RESPONDENT TEAM 27
23
[50] As mentioned above Rule A of the York-‐Antwerp Rules 1994 states, there is a
‘General Average act when, and only when, any extraordinary sacrifice or
expenditure is intentionally and reasonably made or incurred for the common
safety for the purpose of preserving from peril the property involved in a
common maritime adventure’.32 The four conditions set out in Rule A are
satisfied and thus, the Respondent is entitled to a General Average adjustment.
[51] Once again, firstly on the same voyage, the RESPONDENT was transporting the
CLAIMANT’s goods by sea, the parties were clearly engaged in a joint enterprise
appropriately described as a ‘common maritime adventure’.33 The MADAME
DRAGONFLY and by extension, the CLAIMANT’s cargo on board, constituted the
common property involved in this maritime adventure.34
[52] Secondly, the damage to the hull of the MADAME DRAGONFLY was
extraordinary.35 It is ‘out of the ordinary’ for a ship to have such extreme and
violent weather arrive so quickly and without warning.36 There is nothing to
indicate that the Respondent failed to fulfil its obligation to provide a seaworthy
ship at the commencement of the voyage, and consequently the damage to hull
from extreme sudden weather was ‘out of the ordinary’. Repair costs to the hull
therefore constitute expenditure beyond what was envisaged under the
Charterparty and consequently the CLAIMANT cannot expect the RESPONDENT
to bear these extraordinary expenses alone.37
32 York-‐Antwerp Rules 1994, Rule A. 33 Trade Green Shipping Inc v Securitas Bremer Allgemeine Verischerungs AG (The Trade Green) [2000] 2 Lloyd’s Rep 451. 34 York-Antwerp Rules 1994, Rule A. 35 Above, n 32. 36 The Record, p 20: Email dated 29 July 2017 a7 8:58 am; p 21: News report dated 29 July 2017. 37 Marida Ltd v Oswal Steel (The Bijela) [1993] 1 Lloyd’s Rep 411.
MEMORANDA FOR RESPONDENT TEAM 27
24
[53] Thirdly, the decision to cut the anchor chain was intentionally and reasonably
incurred by the RESPONDENT. The RESPONDENT deliberately cut the anchor
chain, which caused the damage to the hull. Moreover, there was no ‘practicable
alternative’38 available other than to cut the anchor chain the caused the damage
to the hull because the ship would otherwise have suffered catastrophic damage
at the hands of the sudden, unexpected and extreme weather. In the
circumstances, the General Average act was reasonable.
[54] Fourthly, by cutting the anchor chain which caused the damage to the MADAME
DRAGONFLY’s hull, the RESPONDENT not only ensured the safety and viability of
the vessel, but also, by extension, the safety of the CLAIMANT’s cargo. Remaining
at anchor during such a violent storm could have left the vessel at the mercy of
the sea and imperilled the not only the vessel’s operations, which would
necessarily placed the cargo at risk, and resulted in even greater damage to the
vessel’s hull. It could also prevent the MADAME DRAGONFLY from having the
ability to complete the voyage.39 The RESPONDENT’s actions were therefore vital
to maintain common safety and prevent harm not only to the ship itself, but also
to the CLAIMANT’s cargo. Repair costs were therefore incurred ‘for the purpose
of preserving from peril’40 the property involved in the common maritime
adventure.41
38 Australian Coastal Shipping Commission v Green [1971] 1 QB 456, 483 (Lord Denning MR). 39 Royal Insurance Co of America v Cineraria Shipping Co 894 FSupp 1557 (1996). 40 York-‐Antwerp Rules 1994, Rule A. 41 Vlassopoulos v British and Foreign Marine Insurance Co (Makis) [1929] 1 KB 187.
MEMORANDA FOR RESPONDENT TEAM 27
25
[55] Specifically, the RESPONDENT is entitled to the actual reasonable cost of
repairing or replacing such damage or loss, subject to deductions in accordance
with Rule XIII.42
[56] As previously discussed above, where the tribunal applies the laws of New South
Wales43 in determining the General Average claim, the adjustment will be made
in ‘accordance with the law and practice of the United States of America’.44
RESPONDENT is able to rely on the New Jason Clause in Clause 19 of the
Charterparty, to claim the General Average contribution ‘losses or expenses of a
General Average nature’ resulting from ‘any cause whatsoever, whether due to
negligence or not’.45
[57] Therefore, if the tribunal finds that the reason for damage to the vessel’s hull was
as a result of negligence or the RESPONDENT’s fault, it will not result in the
RESPONDENT’s inability to rely on the General Average adjustment.
d. Agency fees at the Port of Dillamond;
[58] The party’s have agreed that the any charges relating to wharfage ‘at load or
discharge port to be for Charters’ account.46 The party’s have also agreed that the
‘ship shall be consigned to the Charterer’s Agents at the port of discharge (Port of
Dillamond), paying all customary fees at each port, for attending to matters
concerning the cargo of the vessel.’47
42 York-‐Antwerp Rules 1994, Rule XVIII 43 The Record, p 12: Clause 28. 44 The Record, p 10: Clause 19. 45 The Record, p 10: Clause 19 [2]. 46 The Record, p 11: Clause 23. 47 The Record, p 7: Clause 12(a).
MEMORANDA FOR RESPONDENT TEAM 27
26
[59] According to the Charterparty Clause 12(a), the CLAIMANT is responsible for the
payment of the Agency fees at the discharge port in accordance with the
RESPONDENTS guarantee to deliver always afloat as customary to nominated
discharge port.48 The Respondent has delivered the cargo in accordance with the
Charterparty agreement.
[60] The CLAIMANT is responsible under the Charterparty agreement for the payment of
the Agency fees at the Port of Dillamond.
e. Demurrage;
[61] The RESPONDENT advised the CLAIMANT of the arrival time as soon as it was
reasonably aware of such information in a series of emails over a period of twelve
hours.49 These emails detail the delivery of the CLAMAINT’s cargo in the Port of
Dillamond as per the Charterparty agreement of the party’s.
[62] The CLAIMANT chose not to respond to any communication from the
RESPONDENT in relation to the delivery time of the cargo, the CLAIMANT was
advised of the time of departure and of the Demurrage that would occur from the
time of arrival.50 This demurrage rate was known to both party’s as it was expressly
agreed upon by the party’s in the Charterparty Box 24.51
[63] The CLAIMANT accumulated five hours of Demurrage time while the
RESPONDENT awaited representatives of the CLAIMANT, totalling $100,00052
before the MADAME DRAGONFLY was required to leave the berth without the
CLAIMANT’s representatives appearing to take possession of the cargo. Any
48 The Record, p 8: Clause 14. 49 The Record, p 20: email date 29 July 2017 at 8:58 am; p 22: email dated 29 July 2017 at 4:28 pm; p 24: email date 29 July 2017 at 8:42pm. 50The Record, p 22: email dated 29 July 2017 at 4:28pm. 51 The Record, p 3: Box 24. 52 The Record, p 32: Invoice dated 29 July 2017 attached to email dated 7 August 2017.
MEMORANDA FOR RESPONDENT TEAM 27
27
additional time at berth would cost the vessel financial penalty and additional
Demurrage charges to the CLAIMANT. In so doing, the RESPONDENT has in fact
saved the CLAIMANT additional fees and charges as the CLAIMANT’s
representatives failed to collect the cargo until two days later.53
f. Use of electronic access systems at the Port of Dillamond
[64] The party’s agreed in the Charterparty Clause 23 that Wharfage, if any, at load and
discharge port be for Charterer’s account.54 This express agreement by the party’s
acknowledges that ‘any’ wharfage fees are CLAIMANT.
[65] Second to this, the RESPONDENT has delivered the cargo as required under the
Charterparty in a condition that was stipulated by the agreement. The RESPONDENT
has fulfilled their obligations.
[66] The RESPONDENT advised the CLAIMANT of the arrival time as soon as it was
reasonably aware of such information in a series of emails over a period of twelve
hours.55 These emails detail the delivery of the CLAMAINT’s cargo in the Port of
Dillamond as per the Charterparty agreement of the party’s.
[67] The CLAIMANT has chosen not to respond to the RESPONDENT to advise of any
further requirements in regards to cargo. The RESPONDENT gave notice to the
CLAIMANT that the cargo would be safely stored and secured, as is industry best
practise in such situations, at the Port of Dillamond. The RESPONDENT has then
provided the CLAIMANT with an access barcode which allowed the CLAIMANT to
collect the cargo in due course, as well as advise that due to the CLAIMANT’s failure
53 The Record, p 24: email dated 31 July 2017 at 4:21pm. 54 The Record, p 11: Clause 23. 55 The Record, p 20: email date 29 July 2017 at 8:58 am; p 22: email dated 29 July 2017 at 4:28 pm; p 24: email date 29 July 2017 at 8:42pm.
MEMORANDA FOR RESPONDENT TEAM 27
28
to take delivery of it’s cargo in the usual industry manner, the ‘delivery of the access
authority pass constitutes delivery of the cargo’.56
[68] The CLAIMANT waited two days57 before taking delivery of their cargo with the
complete knowledge of where their cargo was being stored and with the reasonable
knowledge that any company would, that the storage of and the electronic access
security protecting the cargo would be incurring cost.
[69] With the RESPONDENT’s obligations under the Charterparty completed with the
safe delivery of the cargo to the Port of Dillamond onto the dock, the liability for the
safe storage of the cargo for two days until the CLAIMANT decided to take delivery
rest completely with the CLAIMANT, and as such the cost of the electronic access
system at the Port of Dillamond. The tribunal should find that the RESPONDENT is
entitled to claim for this cost.
PRAYER FOR RELIEF For all the reasons submitted above, the RESPONDENT respectfully requests this arbitral panel to: DECLARE that this arbitral panel does not have jurisdiction to hear these proceedings; and in the alternative ADJUDGE that the RESPONDENT is not liable to the CLAIMANT for the following amounts
a) Damaged to cargo of USD15,750,00
b) Replacement of Coffee Payment of USD9,450,00
c) Settlement Payment to third party of USD5,000,000; and DECLARE that this tribunal does not have the jurisdiction to decide any alleged equitable maritime lien over the MADAME DRAGONFLY; and
56 The Record, p 23: Access authority pass delivery to the CLAIMANT. 57 The Record, p 24: email dated 31 July at 4:21pm.
MEMORANDA FOR RESPONDENT TEAM 27
29
In the alternative ADJUDGE that there is no valid equitable maritime lien over the MADAME DRAGONFLY. further ADJUDGE that the CLAIMANT is liable to the RESPONDENT for the following amounts claimed:
a) Freight in the amount of USD500,000.
b) Demurrage charges at Port of Dillamond of USD100,000.
c) CLAIMANT’s use of electronic access systems at Port of Dillamond of USD10,000.
Further, ADJUDGE that the CLAIMANT is liable to the RESPONDENT in General Average for
a) Agency fees at Port of Spectre of USD75,000.
b) Repairs to hull of USD875,000.