Scenario 4 Demolition and Redevelopment
Proposed Scheme & Review
Concorde Close, Hounslow
November 2019January 2020
Contents ................................................................................................................................................. 3
Introduction .......................................................................................................................................... 5
1. Existing Estate ............................................................................................................................... 7
1.1 Ground Floor Plan - Existing ........................................................................................................... 8
1.2 First Floor Plan - Existing ................................................................................................................ 9
1.3 Second Floor Plan - Existing ........................................................................................................... 10
1.4 Existing Estate Provision & Housing Need ..................................................................................... 11
2. Thought process.......................................................................................................................... 13
2.1 Site Context ................................................................................................................................. 14
2.2 Design Development - Access and Amenity Space ........................................................................ 15
2.3 Elevation Design Development ..................................................................................................... 16
2.4 Brick Building Techniques found in Hounslow ................................................................................ 17
2.5 Workshop with Young Customers .................................................................................................. 18
2.6 Modern Brick Precedent 1& 2 ......................................................................................................... 19
2.7 Modern Brick Precedent 3 & 4 ........................................................................................................ 20
2.8 Modern Terrace Precedent 5 .......................................................................................................... 21
2.9 Modern Brick Precedent 6 .............................................................................................................. 22
2.10 Modern Brick Precedent 7 ............................................................................................................ 23
2.11 Elevation Type 1 - The Traditional Terrace Bays ........................................................................... 24
2.12 Elevation Type 2 - The Entrance Bay ............................................................................................ 25
2.13 Elevation Type 3 - The Patchwork Bay .......................................................................................... 26
2.14 Elevation Type 4 - The Recessed Bays .......................................................................................... 27
2.15 Block A & BC Front Elevations - Materiality .................................................................................. 28
2.16 Block A West Elevations to Lampton Road ................................................................................. 29
2.17 Tenure Split ................................................................................................................................ 30
2.18 Dual Aspect Units and Private Amenity ....................................................................................... 31
2.19 Wheelchair User Dwellings ......................................................................................................... 32
2.20 Massing ...................................................................................................................................... 33
2.21 3D Sketch ................................................................................................................................... 34
3. Proposed Plans & Unit Schedule ...................................................................................... 36
3.1 Ground Floor Plan ........................................................................................................................ 37
3.2 First Floor Plan .............................................................................................................................. 38
3.2 Second Floor Plan ......................................................................................................................... 39
3.2 Third Floor Plan............................................................................................................................. 40
3.3 Roof Plan ...................................................................................................................................... 41
3.4 Front Building Elevations .............................................................................................................. 42
3.5 Rear Building Elevations ............................................................................................................... 43
3.6 Site Sections ................................................................................................................................ 44
4. Required and Achieved Unit Mix ...................................................................................... 46
4. Unit Mix Summary .......................................................................................................................... 47
5. Adopted Highways .................................................................................................................... 49
5.1 Proposal vs Adopted Highway - diagram ....................................................................................... 50
6. Proposal Summary Review .................................................................................................. 52
6.1 Scheme Achievements & Limitations Summary ........................................................................... 53
Contents
This document has been prepared on behalf of our client, Home Group.
Apart from two refurbishment scenarios 2 & 3 for Concorde Close, Farrells have been instructed to develop an additional scenario that incudes full demolition of the existing estate and new redevelopment for the Concorde Close site. This scenario has been prepared to enable testing of the different estate regeneration schemes.
The key areas of discussion that this document covers are:
- Design development of the layouts and the buildings facade
- Updated fl oor plans and elevations
- Area schedules and unit mix.
Introduction
1. Existing Estate
1.1 Ground Floor Plan - Existing
Concorde Close | Demolition and Redevelopment Scheme | Proposal & Commentary8
9
1.2 First Floor Plan - Existing
January 2020 |
1.3 Second Floor Plan - Existing
Concorde Close | Demolition and Redevelopment Scheme | Proposal & Commentary10
11
Housing Need provided by Home Group
Existing Unit Mix & Area Schedule
1.4 Existing Estate Provision & Housing Need
Existing Estate Unit Mix
Affordable Rent
Social Rent
Total
Bedsits 2B 2B Maisonettes Total
2 18 11 311 8 3 12
3 26 14 43
Housing Need Mix 1b2p 2b3p 2b4p 3b5p 4b5p 4b6p
Affordable Rent 0 3 3 3 0 1Social Rent 9 5 5 6 2 1London Affordable Rent 5 0 0 0 0 0
Total 14 8 8 9 2 2 43
28
Total
10
5
Parking 23 spacesRequirement
Existing Estate Areas sqm sqft sqm sqft sqm sqft
Affordable (Social Rent) 2,319 24,963 2,055 22,115 1,875 20,183
Affordable (Affordable Rent) 994 10,698 881 9,478 705 7,589
Total 3,313 35,661 2,935 31,592 2,580 27,771
GEA NIAGIA
January 2020 |
2. Thought process
CONCORDE CLOSE
KEY:
Concorde Close Boundary
Site Access
HOUNSLOW CENTRALSTATION
LA
MPTO
N R
OA
D
ALEXANDRA ROAD
LA
MP
TO
N P
AR
K R
OA
DRAILWAY
2.1 Site Context
N
Concorde Close | Demolition and Redevelopment Scheme | Proposal & Commentary14
15
Access and core location:
The site shape alows for two blocks to be allocated - a shorter (Block A) and longer block (Block B/C). The long building has been split further into two building with their own cores and access. This approach optimises the internal space usage and corridor distances
Communal and Private Amenity Space:
The space between Block A and B is allocated to communal child playspace.
The green spaces at the rear of both blocks B and C north of Block A are turned into private garden space for the ground fl oor fl ats.
Defensible space and private patios run along the front elevations of Block A and Blocks B and C facing the child playspace.
EntranceChild PlayspacePrivate gardenDefensible SpacePrivate Patios
KEY:
EntranceLobby corridorBuilding Core
KEY: KEY:
Bicycle StoreStandard Car Parking SpaceWheelchair Car Parking spaceVehicle Route
Car and Cycle Space:
Bicycle stores are positioned.to the rear of all building cores. An additional bicycle store is located in Block B to meet the cycle requirement. There are fi ve accessible Shefi eld stands, located next to the child play space.
In addition, the proposal includes 17 standard car parking spaces and 5 wheelchair car parking spaces. along Concorde Close.
B
A
C B
A
C B
A
C
2.2 Design Development - Access and Amenity Space
N NN
January 2020 |
Vertical Recessed Break
Vertical Recessed BreakVertical
RecessedBay
ProjectingBay
Projecting Bay
2.3 Elevation Design Development
1. Current layout results in a simple elevation with only one central recessed bay.
Primary Massing
Articulation of Blocks
Horizontal Bonding and Texture
3. Ground fl oor will be emphasized by the use of horizontal brick features to balance the proposed vertical articulation.
This is in the form of soldier bricks and running brick bond.
The recessed strips will be in dark bricks, while all projecting blocks will be in red, white or yellow brick
2. The facade is articulated into seven bays. Vertical recessed break strips are allocated to rows of single windows.
Groups of bays project in plan to add additional level of facade articulation and diff erentiate the main entrances to the building.
Concorde Close | Demolition and Redevelopment Scheme | Proposal & Commentary16
17
2.4 Brick Building Techniques found in Hounslow
Corner brick features provide identity to some of the local traditional architecture
Brick ground fl oor separated to the render fi rst fl oor via a soldier brick course. The last is reiterated in the window sill.
Contunuous brick soldier course runs above window level and contributes to the horizontal articulation of the building.
January 2020 |
2.5 Workshop with Young Customers
A workshop with the young customers was held in April 2018. Participants had the opportunity to explore a series of samples from varieous materials, textures and colours.
The most interactive activity was a more hands on experiece on how brick patterns could develop. The children were given a pack of fi ve diff erent colour styles of bricks and examples of 10 diff erent bonds. They were asked to pick their preferred pattern and try to create it with any bricks they prefer.
Concorde Close | Demolition and Redevelopment Scheme | Proposal & Commentary18
19
Silchester Road, Notting Dale
• Hoziontal brick soldier feature is used in the design of the window top and sill
• Yellow brick corbelling runs horizontally across ground and fi rst fl oor and this in combination with a standard brick bond adds a level of complexity. to the building design.
Buccleuch House, Hackney
• Vertical articulation has been achieved through the merge of single and double windows and the use of aluminium panel betwee the two.
• Articulation between bottom and upper fl oor through the use of diff erent type of brick. Two rows of brick soldier run horizontally to diff erentiat the boundary between the two types of brick.
2.6 Modern Brick Precedent 1 & 2
January 2020 |
Camden Courtyards, Camden Town
• Windows across two storeys have been coupled via the use of aluminium panel with vertical pattern that looks like a continuation of the balustrade
• The inset balconies contribute to the articulaton of the building and mark the boundary between the building blocks,
Trafalgar Place, Elephant and Castle
• Various brick colour blends vertically.
• Horizontal brick corbel iterates above windows and contributes to the coherence of the project langugage.
• Balcony zig zag shift to create a playfull feature.
• Horizonal brick corbel on ground fl oor provides a diff erent texture and adds a level of complexity.
2.7 Modern Brick Precedents 3 & 4
Concorde Close | Demolition and Redevelopment Scheme | Proposal & Commentary20
21
2.8 Modern Terrace Precedent 5
Highmead Estate, Enfi eld
• The versatility in this project has been achived through the introduction of various brick collour and diff erent window size
January 2020 |
2.9 Modern Terrace Precedent 6
Residence, Russia
Block massing stepps up and down. Brick blocks built in diff erent colours and the introduction of vertical brick pattern contributes to the unique character of each block.
Concorde Close | Demolition and Redevelopment Scheme | Proposal & Commentary22
23
2.10 Modern Terrace Precedent 7
St Josephhof Residences, Netherlands
The versitility of the building language is achieved through the use of diff erent brick colour and the consistent playful shift of window openings.
January 2020 |
A B
Bay A
2.11 Elevation Type 1 - The Traditional Terrace Bays4. Within the overall facade there are
four types of bays, which are scaled to match traditional residential terraces at the surrounding context.
The end corner bays are the simplest and lowest in height, stepping down to the perimeter of the site.
Concorde Close | Demolition and Redevelopment Scheme | Proposal & Commentary24
25
Entrance Entrance
CONCORDE CLOSE
Soldier brick and running brick bond
C D
Bay C
2.12 Elevation Type 2 - The Entrance Bay
5 Main entrance bay represents typical modern terrace, which steps forward in plan to mark the front doors. It is covered in identical red brick. The ground fl oor brick soldier is extended above the entrance to create a grand feature.
January 2020 |
E F
Bay E
2.13 Elevation Type 3 - The Patchwork Bay
6. The two inner bays between the central recessed bay follow the same language as the traditional modern terrace but alternates window and door positions to create a patchwork eff ect that create interest and diversity in the facade.
Concorde Close | Demolition and Redevelopment Scheme | Proposal & Commentary26
27
2.14 Elevation Type 4 - The Recessed Bays
7. The central block and the couple of facade strips step back. They are covered in dark brick, arranged as soldier course and running bonds.
G H I
Bay HBay GJanuary 2020 |
2.15 Block A & BC Front Elevations - Materiality
Yellow brick - running bond and soldier course
Red brick -running bond and soldier course
Dark (black) brick -soldier course
White brick -running bond and soldier course
Block BC - West Elevation
Block A - South Elevation
Concorde Close | Demolition and Redevelopment Scheme | Proposal & Commentary28
29
2.16 Block A - West Elevation to Lampton Road
January 2020 |
2.17 Tenure Split
Tenure Split: The total scheme includes 65 market units, 43 aff ordable/social rent units.
Block C accommodates 36 aff ordable/social rent units, The remaining 7 units are located on the ground fl oors of Block A and B. The market units are positioned on the remaing space of Block A and B.
KEY:
Entrances to L00 Aff ordable/Social Rent Unit in Block A & BAff ordable/Social Rent UnitsMarket Units
Typical Floor
Block A
Block B Block C
Block A
Block B Block C
Ground Floor
Refuse Store
NN
Concorde Close | Demolition and Redevelopment Scheme | Proposal & Commentary30
31
2.18 Dual Aspect Units and Private Amenity
Dual Aspect Units:
The buildings layouts have been optimised to accommodate maximum number of dual aspect units. Of 28 units on a typical fl oorplan, there are 14 dual aspect and through units. This forms 50% dual aspect units.
Dual Aspect Units
KEY:
Block A
Block B Block C
Block A
Block B Block C
KEY:
Balcony
Building footprint line, where all balconies are inset into the building to further increase separation distance with neighbours
Private Amenity Space - Balconies:
Balconies are strategically located in response to the surrounding context. Most of them are projecting from the building footprint.
However, balconies on the northern and eastern elevations have been inset to maximise separation distance and limit overlooking with 69 Lampton Road and the neighbours on Lampton Park Road.
Typical Floor Typical FloorN N
January 2020 |
2.19 Wheelchair User Dwellings
Wheelchair Adaptable Units M4(3)
KEY:
Wheelchair User Dwellings:
As part of the planning requirement, Scenario 4 provides 10% wheelchair adaptable dwellings M4(3), which are primarily located on ground fl oor to allow for ease of access.. This requirement is applied to all unit types and tenures as following:
2x1B2P - Social rent1x 2B3P - Social rent1 x 3B5P- Aff ordable rent 4 x 1B2p - Market2 x 2B3P - Market
1B2P SR
1B2PSR
3B5PAR
2B3PM
2B3PSR
2B3PM
2B3PM
1B2PM
1B2PM
Typical FloorGround FloorN N
Concorde Close | Demolition and Redevelopment Scheme | Proposal & Commentary32
33
2.20 Massing
Front building.
4 Floors
4 Floors
A
B
C
Rear building.
Front building. West elevation Rear building. West elevation Section through Lampton Road and the child play area
Lampton Road Child play
Front building Rear building
January 2020 |
2.21 3D Sketch
Concorde Close | Demolition and Redevelopment Scheme | Proposal & Commentary34
3. Proposed Plans & Unit Schedule
37
3.1 Ground Floor Plan
CO
NCO
RD
E CLO
SE
LAMPTON ROAD
963 ft²89 m²
A.00.073B5P
725 ft²67 m²
A.00.052B3P
652 ft²61 m²
A.00.031B2P
548 ft²51 m²
A.00.021B2P
539 ft²50 m²
A.00.011B2P
767 ft²71 m²
A.00.061B2P
834 ft²77 m²
A.00.042B4P
712 ft²66 m²
C.00.082B3P
996 ft²93 m²
C.00.073B5P
1,101 ft²102 m²
C.00.064B6P
804 ft²75 m²
C.00.052B4P
547 ft²51 m²
C.00.091B2P
1,044 ft²97 m²
C.00.033B5P
804 ft²75 m²
C.00.042B4P
559 ft²52 m²
C.00.021B2P
547 ft²51 m²
C.00.011B2P
679 ft²63 m²
B.00.071B2P
827 ft²77 m²
B.00.012B3P
841 ft²78 m²
B.00.082B3P
546 ft²51 m²
B.00.021B2P
785 ft²73 m²
B.00.032B3P
785 ft²73 m²
B.00.042B3P
604 ft²56 m²
B.00.051B2P
547 ft²51 m²
B.00.061B2P
1B2P
2B3P
2B4P
3B5P
4B6PNote: Draft plan awaiting landscape input
January 2020 |
3.2 First Floor Plan
652 ft²61 m²
A.00.102B3P
550 ft²51 m²
A.00.161B2P
548 ft²51 m²
A.00.151B2P
668 ft²62 m²
A.00.142B3P
539 ft²50 m²
A.00.081B2P
545 ft²51 m²
A.00.121B2P
548 ft²51 m²
A.00.091B2P
765 ft²71 m²
A.00.112B4P
692 ft²64 m²
A.00.132B3P
679 ft²63 m²
B.00.161B2P
541 ft²50 m²
B.00.131B2P
724 ft²67 m²
C.00.192B3P
712 ft²66 m²
C.00.172B3P
547 ft²51 m²
B.00.091B2P
815 ft²76 m²
B.00.182B4P
559 ft²52 m²
B.00.171B2P
547 ft²51 m²
B.00.151B2P
546 ft²51 m²
B.00.101B2P784 ft²
73 m²
B.00.112B4P
784 ft²73 m²
B.00.122B4P
1,044 ft²97 m²
C.00.123B5P
804 ft²75 m²
C.00.132B4P
559 ft²52 m²
C.00.111B2P
547 ft²51 m²
C.00.101B2P
996 ft²93 m²
C.00.163B5P
1,101 ft²102 m²
C.00.154B6P
804 ft²75 m²
C.00.142B4P
547 ft²51 m²
B.00.141B2P
1B2P
2B3P
2B4P
3B5P
4B6P
Concorde Close | Demolition and Redevelopment Scheme | Proposal & Commentary38
39
3.3 Second Floor Plan
548 ft²51 m²
A.00.241B2P
550 ft²51 m²
A.00.251B2P
539 ft²50 m²
A.00.171B2P
548 ft²51 m²
A.00.181B2P
652 ft²61 m²
A.00.192B3P
545 ft²51 m²
A.00.211B2P
765 ft²71 m²
A.00.202B4P
692 ft²64 m²
A.00.222B3P
668 ft²62 m²
A.00.232B3P
1B2P
2B3P
2B4P
3B5P
4B6P
804 ft²75 m²
C.00.232B4P
804 ft²75 m²
C.00.242B4P
712 ft²66 m²
C.00.272B3P
724 ft²67 m²
C.00.282B3P
547 ft²51 m²
C.00.201B2P
559 ft²52 m²
C.00.211B2P
1,044 ft²97 m²
C.00.223B5P
679 ft²63 m²
B.00.261B2P
547 ft²51 m²
B.00.251B2P541 ft²
50 m²
B.00.231B2P
784 ft²73 m²
B.00.222B4P
784 ft²73 m²
B.00.212B4P
546 ft²51 m²
B.00.201B2P
547 ft²51 m²
B.00.191B2P
815 ft²76 m²
B.00.282B4P
559 ft²52 m²
B.00.271B2P
996 ft²93 m²
C.00.263B5P
1,101 ft²102 m²
C.00.254B6P
547 ft²51 m²
B.00.241B2P
January 2020 |
765 ft²71 m²
A.00.292B4P
545 ft²51 m²
A.00.301B2P
652 ft²61 m²
A.00.282B3P
548 ft²51 m²
A.00.271B2P
539 ft²50 m²
A.00.261B2P
550 ft²51 m²
A.00.341B2P
548 ft²51 m²
A.00.331B2P
668 ft²62 m²
A.00.322B3P
692 ft²64 m²
A.00.312B3P
804 ft²75 m²
C.00.332B4P
804 ft²75 m²
C.00.342B4P
712 ft²66 m²
C.00.372B3P
724 ft²67 m²
C.00.382B3P
547 ft²51 m²
C.00.301B2P
559 ft²52 m²
C.00.311B2P
996 ft²93 m²
C.00.363B5P
1,101 ft²102 m²
C.00.354B6P
1,044 ft²97 m²
C.00.323B5P
679 ft²63 m²
B.00.361B2P
547 ft²51 m²
B.00.351B2P
559 ft²52 m²
B.00.371B2P
815 ft²76 m²
B.00.382B4P
547 ft²51 m²
B.00.291B2P
546 ft²51 m²
B.00.301B2P784 ft²
73 m²
B.00.312B4P
784 ft²73 m²
B.00.322B4P
541 ft²50 m²
B.00.331B2P
547 ft²51 m²
B.00.341B2P
1B2P
2B3P
2B4P
3B5P
4B6P
3.4 Third Floor Plan
Concorde Close | Demolition and Redevelopment Scheme | Proposal & Commentary40
41
3.3 Roof Plan
January 2020 |
+20.700
+20.700
A
N
S
W EB
C
A
N
S
W EB
C
A
N
S
W EB
C
A
N
S
W EB
C
3.4 Front Building Elevations
Concorde Close | Demolition and Redevelopment Scheme | Proposal & Commentary42
43
+20.385+20.400
+20.400
3.5 Rear Building Elevations
A
N
S
W EB
C
A
N
S
W EB
C
January 2020 |
3.6 Site Sections
Proposed Concorde Close 69 Lampton Road61 Lampton Road 63 Lampton Road Proposed sub-station
BA
N
S
W EB
C
D
63 Lampton Road Concorde Close Block B
A
N
S
W EB
C
A
N
S
W EB
C
Section through Block C
8.1m
6m
Concorde Close | Demolition and Redevelopment Scheme | Proposal & Commentary44
4. Required and Achieved Unit Mix
47
4.1 Unit Mix Summary
Sitewide areas sqm sqft sqm sqft sqm sqft
Affordable (Social Rent) 2,319 24,963 2,055 22,115 1,875 20,183
Affordable (Affordable Rent) 994 10,698 881 9,478 705 7,589
Total 3,313 35,661 2,935 31,592 2,580 27,771
GEA GIA NIA
1b2p 2b3p 2b4p 3b5p Total0 3 3 3 100% 30% 30% 30% 100%
9 5 5 6 2832% 18% 18% 21% 100%
5 0 0 0 5100% 0% 0% 0% 100%
39 13 13 0 6560% 20% 20% 0% 100%
53 21 21 9 10849% 19% 19% 8% 100%4%
4b6p1
10%
3
4
11%
00%
00%
1b2p 2b3p 2b4p 3b5p 4b5p 4b6p Total0 3 3 3 0 1 100% 30% 30% 30% 0% 10% 100%
9 5 5 6 2 1 2832% 18% 18% 21% 7% 4% 100%
9 8 8 9 2 2 3824% 21% 21% 24% 5% 5% 100%
Redevelopment Sitewide areas sqm sqft sqm sqft sqm sqft
Social Rent 3,039 32,712 2,818 30,333 2,339 25,177
Affordable Rent 1,028 10,698 941 9,478 807 8,687
Market 5,308 57,135 5,025 54,089 3,845 41,388
Total 9,375 100,913 8,784 94,551 6,991 75,251
GEA GIA NIA
Achieved MixAffordable RentMix
Social RentMix
London Affordable Rent - Social RentMix
MarketMix
TotalMix
Housing NeedAffordable RentMix
Social RentMix
TotalMix
Demolition and Redevelopment Scheme
Housing Need Unit Mix by Home Group
Achieved Unit Mix of Demolition and Redevelopment
January 2020 |
5. Adopted Highways
963 ft²89 m²3B5P
725 ft²67 m²2B3P
652 ft²61 m²1B2P
548 ft²51 m²1B2P
539 ft²50 m²1B2P
767 ft²71 m²1B2P
834 ft²77 m²2B4P
713 ft²66 m²2B3P
996 ft²93 m²3B5P
1,102 ft²102 m²4B6P
804 ft²75 m²2B4P
547 ft²51 m²1B2P
1,044 ft²97 m²3B5P
804 ft²75 m²2B4P
559 ft²52 m²1B2P
547 ft²51 m²1B2P679 ft²
63 m²1B2P
827 ft²77 m²2B3P
841 ft²78 m²2B3P
547 ft²51 m²1B2P
785 ft²73 m²2B3P
785 ft²73 m²2B3P
604 ft²56 m²1B2P
547 ft²51 m²1B2P
KEY
Adopted Footway
Adopted Carriageway
Adopted Amenity
5.1 Proposal vs Adopted Highway - Diagram
Overview
• Scenario 4 will require an agreement with London Borough of Hounslow as to the ability to remove the green area and provide of a road in its place as well as to remove the footway to accommodate the proposed substation and car parking spaces.
Concorde Close | Demolition and Redevelopment Scheme | Proposal & Commentary50
6. Proposal Summary Review
53
6.1 Scheme Achievements & Limitations Summary
What the scheme achieves• The new units meet the Internal Space Standards in line with NDSS as
set out in the Draft New London Plan (Deember 2019) Table 3.3
• Minimum ceiling heights in line with NDSS as set out in the Draft New London Plan (December 2019).
• Private amenity space provision in line with the Mayor’s Housing SPG - standard 26, and LB Hounslow Policy SC5 minimum requirement is met. 738 sqm of private gardens, 501sqm of balconies and 114sqm private patios are provided in the scheme leading to a total private amenity provision of 1,353sqm.
• The Child Play Space requirement includes the provision of the total child yield to be 564sqm of which 248 sqm Doorstep Play for under 5’s. Current proposal provides 284 sqm child playspace, which leads to a shortage of 280sqm.
• 17 Standard car parking spaces and 5 wheelchair car parking spaces are provided along Concorde Close access road.
• 193 cycle spaces are provided in line with the policy requirement,of which 189 long stay, 4 short stay and 5 accessible Sheffi eld stands.
• All families occupying the existing estate have the opportunity to remain at Concorde Close.
What the scheme cannot achieve
• Communal amenity space provision in line with LB Hounslow Policy SC5 cannot be met in full due to the limited availability of open area on the site. The achieved 108 unit mix leads to the requirement of 2,805sqm communal amenity. Of this, only 1,956 sqm are provided as ground fl oor child play space (284sqm) and shared communal roof terraces (1672sqm). This leads to a shortage of 849sqm.
• The Child Play Space requirement includes the provision of the total child yield to be 564sqm of which 248 sqm Doorstep Play for under 5’s. Current proposal provides 284 sqm child playspace, which leads to a shortage of 280sqm.
January 2020 |
London
7 Hatton StreetNW8 8PL, LondonTel: +44 (0)20 7258 [email protected]
Hong Kong
Suites 1301-02, 625 King’s RoadNorth Point, Hong KongTel: +852 2523 [email protected]
Shanghai
Unit 1603, Shanghai Time Square Offi ce Tower,93 Huai Hai Zhong Road, Shanghai, PRC, 200021Tel: +86 (21) 5302 [email protected]
www.farrells.com
Concorde Close | Demolition and Redevelopment Scheme | Proposal & Commentary54