19 MountainRisks IntensiveCourse-Barcelona-08 Labiouse ... · EPFL -LMR Protective measures at the...
Transcript of 19 MountainRisks IntensiveCourse-Barcelona-08 Labiouse ... · EPFL -LMR Protective measures at the...
ÉCOLE POLY TECHNIQUEFÉDÉRALE DE LAUSANNE
L M RSeptember 3rd, 2008Mountain Risks Intensive Course
LABORATOIRE DEMÉCANIQUE DES ROCHES
V. Labiouse
Mitigation measuresProtective works
2
EPFL - LMR
Steps for Rock Fall Risk Management
Mitigation measures
Evaluation of rock fall propagation
Risk analysis and evaluation
Hazard mappingand land-use planning
Identification and characterisation of the departure zone
EPFL - LMR
Delineation of rock falls hazard zones according to an intensity-probability diagram
Return period (Probability)
Inte
nsity
[kJ]
30 years
100 years
300 years
High Medium Low
Hig
hM
ediu
mLo
w
High Danger
Medium D
anger
Low Dan
ger
⇒ 1. Constraints on land-use planning (built-up restrictions)2. Stabilisation and/or protection measures (if existing buildings)
EPFL - LMR
Constraints on land-use planning
g First priority is given to land-use planning, which includes the delineation of areas suitable for construction or zones where additional protection is required
No restrictionsLocal protection recommended.Protection required for sensitive
buildingsLow
Modifications only with increased safety measures (local
protection)
No new residential area permitted.In existing housings lots, construction
permitted with conditions (local protection)
Medium
Normal maintenance of building permitted.
Modifications only when Nb of persons is not increased
Construction of new buildings prohibitedHigh
Existing buildingsNew buildingsDegree of hazard
EPFL - LMR
Stabilisation and/or protection measures
g Only second priority is afforded to structural protection measures.g The protection requirements are defined on the basis of the following questions:
n What level of protection is required, for whom and why ?n What level of residual risk can be tolerated ?n What level of protection can we afford ?
Lateltin & al. 2005
Cost-benefit analysis
necessary
PLANAT, 2007
EPFL - LMR
Mitigation measures
Fearing the sky may fall on our
head…
EPFL - LMR
Protective measures at the source (cliff face)
g Removal of unstable rock elementsn clearing (manually or by explosives)n Slope reshaping
g Stabilization / reinforcement of unstable rock massesn Shallow and deep-site drainagesn Steel wire mesh or wire rope netsn Use of vegetationn Anchors or boltsn Shotcreten Retaining walls (buttress)
See the presentation« Mitigation measures- Protective works »by Eduardo Alonso
EPFL - LMR
Protective measures in the slope (propagation)
g Natural barriersn Protection forestsn Boulder-gathering ditches
g Protective engineering worksn Wire mesh or cable net drapesn Rigid barriers (wood, metal, concrete)n Low energy barrier fencesn High energies barrier fencesn Galleries n Embankments and reinforced dams
EPFL - LMR
Protective measures in the slope (propagation)
g Natural barriersn Protection forestsn Boulder-gathering ditches
g Protective engineering worksn Wire mesh or cable net drapesn Rigid barriers (wood, metal, concrete)n Low energy barrier fencesn High energies barrier fencesn Galleries n Embankments and reinforced dams
EPFL - LMR
Protection forests
g Danger significantly reduced (low and medium blocks), but not completely eliminated (large blocks)
g Natural protection to promote, before resorting to engineering works
g Preserving measures needed (forest maintenance)
Document WSL
Cemagreffilm
EPFL - LMR
Probable Residual Rockfall Hazard under a forested slopehttp://www.ecorisq.com/en/rockfornet.php
g Rock characteristicsn Dimensions, type, shape
g Slope characteristicsn Mean gradient of the slopen Height of the cliffn Length of the forestn Distance before the forest
g Forest characteristicsn Mean stand densityn Stand basal area
Rockfor.NET is a program developed by the Cemagref (Grenoble) to calculate the Probable Residual Rockfall Hazard (PRH)
under a forested slope, which is the percentage of rocks that surpasses the forested area of a slope.
PRH depends on:
EPFL - LMR
Boulder-gathering ditches
Vallorbe - Le PontRoad
ditch and dam(Visinand quarry)
2.5 m
Document Bonnard & Gardel
3 m
EPFL - LMR
Guidelines for bouders-gathering ditches
rollingbouncingfalling
Prevalent mode of rockfall motion (Ritchie, 1963)
Design chart for rock traps as suggested by Whiteside (1986) from work by Fookes and Sweeney (1976) based on Ritchie’s experiments (hundreds of full-scale rockfall tests)
Summary by Richards (1986) of main findings from Hong Kong rockfall tests by Mak and Blomfield(1986). Release of 1000 boulders (10-30 cm) on each of 13 different pre-split slopes.
1 and 1.5 m high barriers at 1.5 m from the slope toe will trap 95% and 100%
respectively of all boulders
EPFL - LMR
Protective measures in the slope (propagation)
g Natural barriersn Protection forestsn Boulder-gathering ditches
g Protective engineering worksn Wire mesh or cable net drapesn Rigid barriers (wood, metal, concrete)n Low energy barrier fencesn High energies barrier fencesn Galleries n Embankments and reinforced dams
EPFL - LMR
Defensive works
Energy absorption
capacity[kJ]
RIGID BARRIERS
LOW ENERGY FENCES
FENCES+CABLE
GALLERIES
EMBANKMENTS
REINFORCED DAMS
Compiled by Prof. Descoeudres in 1997
CAN
EPFL - LMR
Cable net drapery
EPFL - LMR
Rigid barriers
Safe at a first glance...
very low energy absorption capacity!(from 30 to 50 kJ)
but...
Leissigen
EPFL - LMR
Mitigation measuresFlexible barriers
Photos BEG, Valais
g Natural barriersn Protection forestsn Boulder-gathering ditches
g Protective engineering worksn Wire mesh or cable net drapesn Rigid barriersn Low energy barrier fencesn High energies barrier fencesn Galleries n Embankments and reinforced dams
EPFL - LMR
Barrier fences
g Low energy4 up to 200 kJ
g Medium energy4 between 200 et 1000 kJ
g High energy4 over 1000 kJ
Swiss guideline
Barrier classes depending on the energy absorption capacity
June 2001
European guideline 9 classes of falling rock protection kits depending on their
energy absorption capacityFebruary 2008
SEL [kJ]
MEL [kJ]
EPFL - LMR
Barrier fences – low energy
EPFL - LMR
Barrier fences – medium and high energies
1. By the net4 Elastic deformation4 No maintenance required
2. By the energy dissipators4 Concentrated plastic deformation4 Replacement of the dissipators
3. By other parts of the structure4 Damages to the structure (e.g. posts)
10 m
4 to 7 m
Energy dissipation
2
1
EPFL - LMR
Geobrugg nets
Before
After
Barrier fences – medium and high energies
EPFL - LMR
Isofer nets
Before
After
Barrier fences – medium and high energies
EPFL - LMR
European Technical Approval for barrier fencesETAG 027 on Falling Rock Protection Kits
g 2 testsite-geometries consideredn inclined or vertical
g Standardised test set up and executionn Three functional modulesn Block: form, weight, impact speedn Impact point defined for 1 + 2 SEL, MEL
EPFL - LMR
European Technical Approval for barrier fenceshttp://www.eota.eu/ETAGs/ETAG 027
g Service energy level (SEL)n objective : to check if the kit is able to accept successive impacts and
the reduction of the useful height is limited within an acceptable valuen 2 successive impacts in net fence without maintenance between testsn Residual height hR after 1 SEL-test: Threshold value of 70 % of
nominal height
2.
1.
block removed after the first launch
EPFL - LMR
European Technical Approval for barrier fenceshttp://www.eota.eu/ETAGs/ETAG 027
g Maximum energy level (MEL)n objective : to characterize the maximum capacity of the kitn 1 impact with three times the energy of the SEL-testn Residual height classes after MEL-test
4 A (≥50%), B (31-49 %), C (≤30 %) (% of nominal height)
SEL [kJ]
MEL [kJ]
carried out in the same kit used for SEL testingafter being repaired or in a new kit
EPFL - LMR
Mitigation measuresGalleries
Photo J. Jacquemoud
Photo Journal 24Heures
g Natural barriersn Protection forestsn Boulder-gathering ditches
g Protective engineering worksn Wire mesh or cable net drapesn Rigid barriersn Low energy barrier fencesn High energies barrier fencesn Galleries n Embankments and reinforced dams
EPFL - LMR
Protection galleries
g Mainly reinforced concrete rigid structures (eventually prestressed)
g (usually) with a soil cushion above the slab to assure energy dissipation
Protection of linear infrastructures (roads, railways)
Structures used in the same way as a protection against snow
avalanches
EPFL - LMR
Traditional-design protection galleries
EPFL - LMR
Traditional design of the Swiss galleriesMost of the Swiss galleries are cast-in-place reinforced concrete structures
with a soil cushion above the slab to ensure energy dissipation
129
74
25
52
78
13
197
190
246
157
212
83
139
56
119
0% 20% 40% 60% 80% 100%
With cushionlayer
Precast
Prestressed
Arch
Adjacent totunnel
Yes No No data
Data base of Swiss galleries compiled by K. Schellenberg (ETHZ – IBK)
EPFL - LMR
Maximum impulsive force on the soil cushionPh.D. thesis of Sara Montani (LMR-EPFL, 1997)
g Similarities with Hertz’ law for elastic shocks:
g Influence of the friction angle not inferred from experiments, but deduced from FE computations
g Influence of the thickness of the soil cushion eg Penetration of the block d into the soil cushion:
Slab
e
mR
ME ϕ
H
M
Facc
( )F RR
eM Eacc E pot= ⋅ ⋅
⋅⎛⎝⎜
⎞⎠⎟ ⋅ ⋅ ⋅135
30 2 0 4 0 2 0 6. exp tan. . . .ϕ
53
53
525
1HWMR765.1P Emax ⋅⋅⋅⋅=
dF d Eacc pot⋅ = ⋅16.
EPFL - LMR
Maximum equivalent static force acting on the slabPh.D. thesis of Sara Montani (LMR-EPFL, 1997)
g Similarities with Hertz’ law for elastic shocks:E0.4 and (m g H)0.6
g Factor accounting for the slab stiffness k similar to a formula derived by Tonello (1988) based on momentum conservation considerations.
( ) 5.0HgmmM1
k2P ⋅⋅⋅+⋅
=
( )F R e Mk
m M gEE potint
. . . ..= ⋅ ⋅ ⋅ ⋅+ ⋅
⋅−0 13 0 8 0 1 0 4 0 6
Slab
e
mR
ME ϕ
H
FintM
Mk
m
Mk
m
P
EPFL - LMR
Design of protection galleries in Switzerland ??
Swiss FederalRoads AuthoritiesCFF
F Re
M EE potint. . .. tan= ⋅ ⋅ ⋅ ⋅ ⋅2 8
10 7 0 4 0 6ϕ
( )F R e Mk
m M gEE potint
. . . ..= ⋅ ⋅ ⋅ ⋅+ ⋅
⋅−0 13 0 8 0 1 0 4 0 6
g ASTRA and CFF guideline for the design of rock fall protection galleries (October 1997)
g Ph.D. thesis of Sara Montani (December 1998)
g Revised version of the ASTRA guideline (2008)Same formula to assess the equivalent static force acting on the slab
g Verification of existing rock fall protection galleries (ASTRA, 2004)Assessment of the robustness of galleries by means of 3 factors:
structure ductility, absorbing cushion, magnitude of the design action
EPFL - LMR
Innovative conceptPare-Pierre Structurellement Dissipant PSD
(Tonello Engineering)
Highly reinforced concreteslabs of high thickness (≈ 1 m)with stirrups against punching+ energy dissipators at each
column-slab contactNo soil cushion !
Recent-design protection galleries in FranceDesigned for an energy absorption capacity of 10´000 kJ at ULS
EPFL - LMR
Mitigation measuresEmbankments and reinforced dams
Photo Tissières
g Natural barriersn Protection forestsn Boulder-gathering ditches
g Protective engineering worksn Wire mesh or cable net drapesn Rigid barriersn Low energy barrier fencesn High energies barrier fencesn Galleries n Embankments and reinforced dams
EPFL - LMR
Embankments and reinforced dams
JapaneseexperimentsProf. Yoshida
Impact of2700 kJ
EPFL - LMR
Embankments and reinforced dams
Embankments with pneusolelements
Dam reinforced by geotextiles and steel meshes (TENAX)
Capacity of 4500 kJ
EPFL - LMR
Dam in Saleudan (Valais)after rockfalls in July 1996
800 m3 of material retained by the dam
Block of 50 m3Document Tissières
Embankments and reinforced dams
EPFL - LMR
Simulations of rockfall impacts on embankments using a Discrete Element Model
F.-V. Donzé, Laboratoire 3S-R, Grenoble
g Calibration and validation on triaxial tests & impacts on granular cushionsg Parametrical study
n Influence of the translational kinetic energy4 the block gets over for an impact energy of 4000 kJ.
n Influence of the impact height4 a height of safety (about 1/4 of the dam height) is needed to contain the block.
n Influence of the rotational kinetic energy4 block’s rotation plays a major role. It is getting over for a ratio Erot/Etrans larger than 10%.
EPFL - LMR
The capacity of structural protective measures against rock falls is increasing…
Energy absorption
capacity[kJ]
RIGID BARRIERS
LOW ENERGY FENCES
FENCES+CABLE
GALLERIES
EMBANKMENTS
REINFORCED DAMS
Compiled by Prof. Descoeudres in 1997
CAN
EPFL - LMR
Bases for a correct risk management (FOWG):g An adequate assessment of hazards and risks is
essential. It requires knowledge about the nature of the governing processes and about the possibility of their control.
g Protection requirements depend on the potential consequences (damages). Protection of human life has the outmost priority.
g First priority applies to land use planning, which includes the delineation of areas suitable for construction or zones where additional protection is required.
g Only second priority is afforded to structural protection measures, in cases where they can be cost-effective.
g Maintenance of protection structures is imperative
… but sufficient emphasis should be put on preventive measures …
… and more than1000 trajectory runswere performed todesign adequatelythe rockfall barriers
EPFL - LMR
Residual risk reduction by detecting nets