189620396 case-studies-pos-office

10
Get Homework/Assignment Done Homeworkping.com Homework Help https://www.homeworkping.com/ Research Paper help https://www.homeworkping.com/ Online Tutoring https://www.homeworkping.com/ click here for freelancing tutoring sites Case studies: PejabatPos Lama, Ipoh, Perak

Transcript of 189620396 case-studies-pos-office

Page 1: 189620396 case-studies-pos-office

Get Homework/Assignment Done

Homeworkping.com

Homework Help

https://www.homeworkping.com/

Research Paper help

https://www.homeworkping.com/

Online Tutoring

https://www.homeworkping.com/

click here for freelancing tutoring sites

Case studies: PejabatPos Lama, Ipoh, Perak

Picture of PejabatPos Lama in the early 90’s and before the conservation work

Page 2: 189620396 case-studies-pos-office

Background

The PejabatPos Lama, Ipoh, was originally placed in the rearmost portion of Ipoh

Town Hall, at DatoSagor Road, in the middle of the government sector of the British

administrative period. Other organizational buildings, testimonials and the

commercial banks, give the area a European taste through the architectural styles

employed. This building is located in front of the majestic Ipoh Railway Station and

was constructed the same time as its neighbour the Ipoh High Court. The building

was designed by a British architect call Arthur Benison Hubback. The Construction

began in 1913 and was completed in 1916 (JabatanWarisan Negara, 2013). The

postal service in this building was operated 1083 before the building became the

Perak Tourism Centre till 1995. Since then the building was unused for a very long

time and without the maintenance the roof started to leak, the rain water downpipes

starting to break, the floorboards started to rotted and the trees grew inside the

building, plus the severe damage of the building.With that, in 2007, the Ipoh City

Council applied to the Department of National Heritage for assistance. After

cautiouslystudy, the Department agreed to carry out conservation work and in 2009,

work began and was completed in 2010(JabatanWarisan Negara, 2013).

 Characteristic of the building

This is a two-storey building is surrounded by an open arched verandah on the

ground floor and an open colonnaded verandah on the first floor and these

verandahs provide shade for the main building and shelter from both the heat and

the tropical rain (JabatanWarisan Negara, 2013). The marble floors add to the sense

of freshness and the ground floor columns and walls are rusticated, and give alook of

being built from large stone blocks. This is referring to a typical Renaissance feature

and the wide protruding columns are form on the ground floor that form the base and

for the Roman Doric columns is on first floor. These are both circular and square in

plan, adding to the liveliness of the façade (JabatanWarisan Negara, 2013).The

timber floor in the existing heritage building has suffered damage caused by wear

Page 3: 189620396 case-studies-pos-office

and tear and dry rot. Other damages continued also include termite attack, cut-out

routes to enable installation of mechanical and electrical lines and exposure to the

elements not to mention time and human use factors.

Comparison of the building in 2008 and 2010

1.)

2.)

3.)

4.)

Before the building was being conserved. The floor finishers were cement render. When working on the floor, it is found that the original floor was found to have marble finishes.

the worker is been instructed to dig up and explore the whole ground By knowing what is the original floor to unearth the original finishes A few parts of the original floor

were damaged provoking the contractor to search for similar material (marble) with the same colour and texture as replacement

This is the floor after grinding and polishing.

Description Before (2008) After (2010)

Page 4: 189620396 case-studies-pos-office

5.)

6.)

8.)

9.)

The timber was originally the second floor finishes. But When it was checked last 2008, the timber was badly rotten and deemed unsafe for habitation. The timber joist was found to be in a very good condition during the conservation work.

The whole timber joist remained unchanged even though the floorboards were replaced using the exact type of wood (meranti) used for the previous floorThe floor is ready to be coated with shellac

This is the floor condition upon accomplishment of conservation works.

Page 5: 189620396 case-studies-pos-office

Appendix

This is the front view of the PejabatPos Lama, Ipoh after a 90% completion of conservation work

Page 6: 189620396 case-studies-pos-office

This is the open area

This is the view of the first floor area

Page 7: 189620396 case-studies-pos-office

This is the close up of the chamfered corner with the rusticated base and Roman Doric columns above

The damaged Meranti floors were replaced with matching timbers that was found