189620396 case-studies-pos-office
-
Upload
homeworkping2 -
Category
Education
-
view
98 -
download
0
Transcript of 189620396 case-studies-pos-office
Get Homework/Assignment Done
Homeworkping.com
Homework Help
https://www.homeworkping.com/
Research Paper help
https://www.homeworkping.com/
Online Tutoring
https://www.homeworkping.com/
click here for freelancing tutoring sites
Case studies: PejabatPos Lama, Ipoh, Perak
Picture of PejabatPos Lama in the early 90’s and before the conservation work
Background
The PejabatPos Lama, Ipoh, was originally placed in the rearmost portion of Ipoh
Town Hall, at DatoSagor Road, in the middle of the government sector of the British
administrative period. Other organizational buildings, testimonials and the
commercial banks, give the area a European taste through the architectural styles
employed. This building is located in front of the majestic Ipoh Railway Station and
was constructed the same time as its neighbour the Ipoh High Court. The building
was designed by a British architect call Arthur Benison Hubback. The Construction
began in 1913 and was completed in 1916 (JabatanWarisan Negara, 2013). The
postal service in this building was operated 1083 before the building became the
Perak Tourism Centre till 1995. Since then the building was unused for a very long
time and without the maintenance the roof started to leak, the rain water downpipes
starting to break, the floorboards started to rotted and the trees grew inside the
building, plus the severe damage of the building.With that, in 2007, the Ipoh City
Council applied to the Department of National Heritage for assistance. After
cautiouslystudy, the Department agreed to carry out conservation work and in 2009,
work began and was completed in 2010(JabatanWarisan Negara, 2013).
Characteristic of the building
This is a two-storey building is surrounded by an open arched verandah on the
ground floor and an open colonnaded verandah on the first floor and these
verandahs provide shade for the main building and shelter from both the heat and
the tropical rain (JabatanWarisan Negara, 2013). The marble floors add to the sense
of freshness and the ground floor columns and walls are rusticated, and give alook of
being built from large stone blocks. This is referring to a typical Renaissance feature
and the wide protruding columns are form on the ground floor that form the base and
for the Roman Doric columns is on first floor. These are both circular and square in
plan, adding to the liveliness of the façade (JabatanWarisan Negara, 2013).The
timber floor in the existing heritage building has suffered damage caused by wear
and tear and dry rot. Other damages continued also include termite attack, cut-out
routes to enable installation of mechanical and electrical lines and exposure to the
elements not to mention time and human use factors.
Comparison of the building in 2008 and 2010
1.)
2.)
3.)
4.)
Before the building was being conserved. The floor finishers were cement render. When working on the floor, it is found that the original floor was found to have marble finishes.
the worker is been instructed to dig up and explore the whole ground By knowing what is the original floor to unearth the original finishes A few parts of the original floor
were damaged provoking the contractor to search for similar material (marble) with the same colour and texture as replacement
This is the floor after grinding and polishing.
Description Before (2008) After (2010)
5.)
6.)
8.)
9.)
The timber was originally the second floor finishes. But When it was checked last 2008, the timber was badly rotten and deemed unsafe for habitation. The timber joist was found to be in a very good condition during the conservation work.
The whole timber joist remained unchanged even though the floorboards were replaced using the exact type of wood (meranti) used for the previous floorThe floor is ready to be coated with shellac
This is the floor condition upon accomplishment of conservation works.
Appendix
This is the front view of the PejabatPos Lama, Ipoh after a 90% completion of conservation work
This is the open area
This is the view of the first floor area
This is the close up of the chamfered corner with the rusticated base and Roman Doric columns above
The damaged Meranti floors were replaced with matching timbers that was found
Reference list
(n.d.). Retrieved from http://ac.els-cdn.com/S1877705811029791/1-s2.0-S1877705811029791-main.pdf?_tid=3f421efa-4edc-11e3-9f2a-00000aacb35d&acdnat=1384619541_394a3c3e2cbc61a730fd7ee9e8c949cd
(n.d.). Retrieved fromhttp://www.heritage.gov.my/index.php/en/conservation/conservation-building/public-buildings/the-old-ipoh-post-office-building
The roof was repaired to the roof parapet , to the top of the walls