18 Autumn in Colorado. Economic Evaluation and Sensitivity-Risk Analysis of Zarshuran Gold Mine...

35
18 Autumn in Colorado

Transcript of 18 Autumn in Colorado. Economic Evaluation and Sensitivity-Risk Analysis of Zarshuran Gold Mine...

Page 1: 18 Autumn in Colorado. Economic Evaluation and Sensitivity-Risk Analysis of Zarshuran Gold Mine Project Authors: Kazem Oraee; University of Stirling,

18

Autumn in Colorado

Page 2: 18 Autumn in Colorado. Economic Evaluation and Sensitivity-Risk Analysis of Zarshuran Gold Mine Project Authors: Kazem Oraee; University of Stirling,

Economic Evaluation and Sensitivity-Risk Analysis of Zarshuran Gold Mine ProjectEconomic Evaluation and Sensitivity-Risk Analysis of Zarshuran Gold Mine Project

Authors:Authors:

Kazem Oraee; University of Stirling, UK

Ahmad Sayadi; Tarbiat Modares University, Iran

Mahdi Tavassoli; Tarbiat Modares University, Iran

2011 SME Annual MeetingFeb. 27-Mar. 2, 2011, Denver, Colorado, US

Page 3: 18 Autumn in Colorado. Economic Evaluation and Sensitivity-Risk Analysis of Zarshuran Gold Mine Project Authors: Kazem Oraee; University of Stirling,

Outline

2011 SME Annual Meeting, Feb. 27-Mar. 2, 2011, Denver, Colorado, US 3

Introduction Methodology Case Study Cost and Income Estimation Discounted Cash Flow (DCF) Analysis Sensitivity Analysis Risk Analysis Conclusions

Page 4: 18 Autumn in Colorado. Economic Evaluation and Sensitivity-Risk Analysis of Zarshuran Gold Mine Project Authors: Kazem Oraee; University of Stirling,

Economic Evaluation of Mining Projects

Case StudyIntroduction Conclusion

Discounted Cash Flow- the most suitable method

Constraints

Uncertainty of internal data

Uncertainty of external data

Methodology Cost & Income Estimation DCF Sensitivity Analysis Risk Analysis

2011 SME Annual Meeting, Feb. 27-Mar. 2, 2011, Denver, Colorado, US 4

Page 5: 18 Autumn in Colorado. Economic Evaluation and Sensitivity-Risk Analysis of Zarshuran Gold Mine Project Authors: Kazem Oraee; University of Stirling,

Risk Analysis of Mining Projects

Case StudyIntroduction ConclusionMethodology Cost & Income Estimation DCF Sensitivity Analysis Risk Analysis

2011 SME Annual Meeting, Feb. 27-Mar. 2, 2011, Denver, Colorado, US 5

Sensitivity Analysis

Scenario Analysis

Decision Tree

Root Sum of Squares (RSS)

Mont Carlo Method

Page 6: 18 Autumn in Colorado. Economic Evaluation and Sensitivity-Risk Analysis of Zarshuran Gold Mine Project Authors: Kazem Oraee; University of Stirling,

Methodology

Case StudyIntroduction ConclusionMethodology Cost & Income Estimation DCF Sensitivity Analysis Risk Analysis

2011 SME Annual Meeting, Feb. 27-Mar. 2, 2011, Denver, Colorado, US 6

Develop an economic model by COMFAR software- DCF table construction. NPV, IRR and Payback are calculated

Sensitivity Analysis

Finding the most effective parameters on variations of NPV

To determine the probability distribution of the most effective parameters

To perform the probability analysis of NPV with the help of Mont Carlo simulation by @Risk software

Page 7: 18 Autumn in Colorado. Economic Evaluation and Sensitivity-Risk Analysis of Zarshuran Gold Mine Project Authors: Kazem Oraee; University of Stirling,

Zarshuran Gold Mine Project

Case StudyIntroduction ConclusionMethodology Cost & Income Estimation DCF Sensitivity Analysis Risk Analysis

2011 SME Annual Meeting, Feb. 27-Mar. 2, 2011, Denver, Colorado, US 7

The most important gold deposit in Iran

Discovered by: Anglo American Company in 1995

Owned by: IMIDRO, a state-owned company

Page 8: 18 Autumn in Colorado. Economic Evaluation and Sensitivity-Risk Analysis of Zarshuran Gold Mine Project Authors: Kazem Oraee; University of Stirling,

Zarshuran Gold Mine Project

Case StudyIntroduction ConclusionMethodology Cost & Income Estimation DCF Sensitivity Analysis Risk Analysis

2011 SME Annual Meeting, Feb. 27-Mar. 2, 2011, Denver, Colorado, US 8

Tonnage of inferred ore: 55 tons of Gold

Page 9: 18 Autumn in Colorado. Economic Evaluation and Sensitivity-Risk Analysis of Zarshuran Gold Mine Project Authors: Kazem Oraee; University of Stirling,

Zarshuran Gold Mine Project

Case StudyIntroduction ConclusionMethodology Cost & Income Estimation DCF Sensitivity Analysis Risk Analysis

2011 SME Annual Meeting, Feb. 27-Mar. 2, 2011, Denver, Colorado, US 9

The mine is in construction phase/ planning stage

Planned ore production:

750,000 tons/year

Ultimate stripping ratio: 13.6

Page 10: 18 Autumn in Colorado. Economic Evaluation and Sensitivity-Risk Analysis of Zarshuran Gold Mine Project Authors: Kazem Oraee; University of Stirling,

Zarshuran Gold Mine Project

Case StudyIntroduction ConclusionMethodology Cost & Income Estimation DCF Sensitivity Analysis Risk Analysis

2011 SME Annual Meeting, Feb. 27-Mar. 2, 2011, Denver, Colorado, US 10

Planned mill plant production:

3,060 kg of gold

1,270 kg of silver

Project’s lifetime: 18 years including 3 years as construction phase

Page 11: 18 Autumn in Colorado. Economic Evaluation and Sensitivity-Risk Analysis of Zarshuran Gold Mine Project Authors: Kazem Oraee; University of Stirling,

Initial investment for the mine

Case StudyIntroduction ConclusionMethodology Cost & Income Estimation DCF Sensitivity Analysis Risk Analysis

2011 SME Annual Meeting, Feb. 27-Mar. 2, 2011, Denver, Colorado, US 11

Cost items $ Million Share (%)

Buildings 0.46 1.92

Infrastructure 0.55 2.25

Trucks 6.89 28.42

Loaders 4.13 17.04

Auxiliary machinery 3.14 12.96

Administration costs 0.50 2.07

Development costs 5.5 22.68

Other costs 1.06 4.37

Working capital 2.01 8.29

Total 24.25 100

Page 12: 18 Autumn in Colorado. Economic Evaluation and Sensitivity-Risk Analysis of Zarshuran Gold Mine Project Authors: Kazem Oraee; University of Stirling,

Initial investment for the mill plant

Case StudyIntroduction ConclusionMethodology Cost & Income Estimation DCF Sensitivity Analysis Risk Analysis

2011 SME Annual Meeting, Feb. 27-Mar. 2, 2011, Denver, Colorado, US 12

Cost items $ Million Share (%)

Land 0.42 0.63

Infrastructure 4.16 6.21

Civil works 17.28 25.78

Equipment and machinery 33.51 51.00

Erection costs 3.67 5.48

Reclamation costs 0.21 0.32

Administration costs 0.32 0.47

Other costs 2.98 4.44

Working capital 4.48 6.68

Total 67.04 100

Page 13: 18 Autumn in Colorado. Economic Evaluation and Sensitivity-Risk Analysis of Zarshuran Gold Mine Project Authors: Kazem Oraee; University of Stirling,

Operating annual costs for the mine

Case StudyIntroduction ConclusionMethodology Cost & Income Estimation DCF Sensitivity Analysis Risk Analysis

2011 SME Annual Meeting, Feb. 27-Mar. 2, 2011, Denver, Colorado, US 13

Cost items $ Thousand Share (%)Drilling 50 0.58Blasting 330 4.13

Spare parts 540 6.65Maintenance 910 11.27Wear parts 300 3.76

Engineering and consultancy 50 0.59

Tires 1,300 16.12Ramp maintenance 10 0.17

Fuel 940 11.64Lubricants 770 9.61

Communication 4 0.05Labor 2,310 28.77

Royalties 100 1.23

Administration costs 50 0.66

Other costs 380 4.76Total 8,050 100

Page 14: 18 Autumn in Colorado. Economic Evaluation and Sensitivity-Risk Analysis of Zarshuran Gold Mine Project Authors: Kazem Oraee; University of Stirling,

Operating annual costs for the mill plant

Case StudyIntroduction ConclusionMethodology Cost & Income Estimation DCF Sensitivity Analysis Risk Analysis

2011 SME Annual Meeting, Feb. 27-Mar. 2, 2011, Denver, Colorado, US 14

Cost items $ Million Share (%)

Consumable materials 10.6 59.19

Energy 3.5 19.55

Spare parts 0.97 5.4

Maintenance 0.72 4

Administration costs 0.05 0.3

Labor 1.22 6.81

Other costs 0.85 4.76

Total 17.91 100

Page 15: 18 Autumn in Colorado. Economic Evaluation and Sensitivity-Risk Analysis of Zarshuran Gold Mine Project Authors: Kazem Oraee; University of Stirling,

Annual income

Case StudyIntroduction ConclusionMethodology Cost & Income Estimation DCF Sensitivity Analysis Risk Analysis

2011 SME Annual Meeting, Feb. 27-Mar. 2, 2011, Denver, Colorado, US 15

Average gold price (2003-2009): 621.17 $/oz

0

200

400

600

800

1000

1200

200720052004 2006 200920082003

$/oz

2010

Page 16: 18 Autumn in Colorado. Economic Evaluation and Sensitivity-Risk Analysis of Zarshuran Gold Mine Project Authors: Kazem Oraee; University of Stirling,

Annual income

Case StudyIntroduction ConclusionMethodology Cost & Income Estimation DCF Sensitivity Analysis Risk Analysis

2011 SME Annual Meeting, Feb. 27-Mar. 2, 2011, Denver, Colorado, US 16

Average silver price (2003-2009): 10.34 $/oz

0

4

8

12

16

20

200720052004 2006 200920082003

$/oz

2010

Page 17: 18 Autumn in Colorado. Economic Evaluation and Sensitivity-Risk Analysis of Zarshuran Gold Mine Project Authors: Kazem Oraee; University of Stirling,

Annual income

Case StudyIntroduction ConclusionMethodology Cost & Income Estimation DCF Sensitivity Analysis Risk Analysis

2011 SME Annual Meeting, Feb. 27-Mar. 2, 2011, Denver, Colorado, US 17

Total Annual Income

=3,060 (kg/year) × 621.17 ($/oz) × 32.15 (oz/kg)

+1,270 (kg/year) × 10.34 ($/oz) × 32.15 (oz/kg)

=

$ 61.5 Million

Page 18: 18 Autumn in Colorado. Economic Evaluation and Sensitivity-Risk Analysis of Zarshuran Gold Mine Project Authors: Kazem Oraee; University of Stirling,

Net Present Value of the Project

Case StudyIntroduction ConclusionMethodology Cost & Income Estimation DCF Sensitivity Analysis Risk Analysis

2011 SME Annual Meeting, Feb. 27-Mar. 2, 2011, Denver, Colorado, US 18

NPV = + $ 36.6 Million

Discount rate = % 15.4 (The average inflation rate for the last 7 years)

Page 19: 18 Autumn in Colorado. Economic Evaluation and Sensitivity-Risk Analysis of Zarshuran Gold Mine Project Authors: Kazem Oraee; University of Stirling,

Net Present Value and Internal Rate of Return

Case StudyIntroduction ConclusionMethodology Cost & Income Estimation DCF Sensitivity Analysis Risk Analysis

2011 SME Annual Meeting, Feb. 27-Mar. 2, 2011, Denver, Colorado, US 19

IRR = 22.5%

($ Million)

Page 20: 18 Autumn in Colorado. Economic Evaluation and Sensitivity-Risk Analysis of Zarshuran Gold Mine Project Authors: Kazem Oraee; University of Stirling,

Cumulative Value of the Project(Payback Period)

Case StudyIntroduction ConclusionMethodology Cost & Income Estimation DCF Sensitivity Analysis Risk Analysis

2011 SME Annual Meeting, Feb. 27-Mar. 2, 2011, Denver, Colorado, US 20

Year $ Million

1 - 45.45

2 - 79.69

3 - 109.64

4 - 74.06

5 - 38.48

6 - 2.90

7 32.67

8 52.53

9 88.11

Year $ Million

10 123.69

11 159.27

12 194.85

13 214.71

14 243.14

15 271.57

16 300.00

17 328.43

18 348.98

Page 21: 18 Autumn in Colorado. Economic Evaluation and Sensitivity-Risk Analysis of Zarshuran Gold Mine Project Authors: Kazem Oraee; University of Stirling,

Cumulative Net Present Value of the Project (Discounted Payback Period)

Case StudyIntroduction ConclusionMethodology Cost & Income Estimation DCF Sensitivity Analysis Risk Analysis

2011 SME Annual Meeting, Feb. 27-Mar. 2, 2011, Denver, Colorado, US 21

Year $ Million

1 - 39.38

2 - 65.10

3 - 84.59

4 - 64.52

5 -47.14

6 - 32.07

7 - 19.02

8 - 12.71

9 - 2.90

Year $ Million

10 5.59

11 12.95

12 19.33

13 22.42

14 26.24

15 29.56

16 32.43

17 34.92

18 36.60

Page 22: 18 Autumn in Colorado. Economic Evaluation and Sensitivity-Risk Analysis of Zarshuran Gold Mine Project Authors: Kazem Oraee; University of Stirling,

Case StudyIntroduction ConclusionMethodology Cost & Income Estimation DCF Sensitivity Analysis Risk Analysis

2011 SME Annual Meeting, Feb. 27-Mar. 2, 2011, Denver, Colorado, US 22

($ Million)

Cumulative Net Present Value of the Project (Discounted Payback Period)

Page 23: 18 Autumn in Colorado. Economic Evaluation and Sensitivity-Risk Analysis of Zarshuran Gold Mine Project Authors: Kazem Oraee; University of Stirling,

Sensitivity Analysis

Case StudyIntroduction ConclusionMethodology Cost & Income Estimation DCF Sensitivity Analysis Risk Analysis

2011 SME Annual Meeting, Feb. 27-Mar. 2, 2011, Denver, Colorado, US 23

DescriptionMinus

($ Million)Base Case($ Million)

Plus($ Million)

Gold and Silver Price ±10% 14.58 36.60 58.62

Operating Costs ± 10% 47.23 36.60 25.97

Purchase Price ± 10% 44.45 36.60 28.75

Discount Rate ± 10% 48.81 36.60 26.23

Page 24: 18 Autumn in Colorado. Economic Evaluation and Sensitivity-Risk Analysis of Zarshuran Gold Mine Project Authors: Kazem Oraee; University of Stirling,

Sensitivity Analysis

Case StudyIntroduction ConclusionMethodology Cost & Income Estimation DCF Sensitivity Analysis Risk Analysis

2011 SME Annual Meeting, Feb. 27-Mar. 2, 2011, Denver, Colorado, US 24

Therefore, instead of absolute numbers for most

effective parameters:

Gold Price, Silver Price and Discount Rate

probability distributions are used

Page 25: 18 Autumn in Colorado. Economic Evaluation and Sensitivity-Risk Analysis of Zarshuran Gold Mine Project Authors: Kazem Oraee; University of Stirling,

Probability distribution of gold price($/oz Thousand)

Case StudyIntroduction ConclusionMethodology Cost & Income Estimation DCF Sensitivity Analysis Risk Analysis

2011 SME Annual Meeting, Feb. 27-Mar. 2, 2011, Denver, Colorado, US 25

Page 26: 18 Autumn in Colorado. Economic Evaluation and Sensitivity-Risk Analysis of Zarshuran Gold Mine Project Authors: Kazem Oraee; University of Stirling,

Probability distribution of silver price($/oz)

Case StudyIntroduction ConclusionMethodology Cost & Income Estimation DCF Sensitivity Analysis Risk Analysis

2011 SME Annual Meeting, Feb. 27-Mar. 2, 2011, Denver, Colorado, US 26

Page 27: 18 Autumn in Colorado. Economic Evaluation and Sensitivity-Risk Analysis of Zarshuran Gold Mine Project Authors: Kazem Oraee; University of Stirling,

Probability distribution of inflation rate

Case StudyIntroduction ConclusionMethodology Cost & Income Estimation DCF Sensitivity Analysis Risk Analysis

2011 SME Annual Meeting, Feb. 27-Mar. 2, 2011, Denver, Colorado, US 27

Page 28: 18 Autumn in Colorado. Economic Evaluation and Sensitivity-Risk Analysis of Zarshuran Gold Mine Project Authors: Kazem Oraee; University of Stirling,

Results of Mont Carlo simulation

Case StudyIntroduction ConclusionMethodology Cost & Income Estimation DCF Sensitivity Analysis Risk Analysis

2011 SME Annual Meeting, Feb. 27-Mar. 2, 2011, Denver, Colorado, US 28

DescriptionNPV

($ Million)

Minimum -67.35

Maximum 16,253.96

Mean 49.65

Standard Deviation

122.40

Variance 141,259,016

Skewness 0.003

Mode -65.88

NPV = $ 49.65 Million

This is the most probable NPV and

not $ 36.6 Million

Page 29: 18 Autumn in Colorado. Economic Evaluation and Sensitivity-Risk Analysis of Zarshuran Gold Mine Project Authors: Kazem Oraee; University of Stirling,

Sensitivity ranking by Mont Carlo Method

Case StudyIntroduction ConclusionMethodology Cost & Income Estimation DCF Sensitivity Analysis Risk Analysis

2011 SME Annual Meeting, Feb. 27-Mar. 2, 2011, Denver, Colorado, US 29

Description Correlation

Gold Price 0.91

Discount Rate - 0.37

Silver Price 0.01

Page 30: 18 Autumn in Colorado. Economic Evaluation and Sensitivity-Risk Analysis of Zarshuran Gold Mine Project Authors: Kazem Oraee; University of Stirling,

Case StudyIntroduction ConclusionMethodology Cost & Income Estimation DCF Sensitivity Analysis Risk Analysis

2011 SME Annual Meeting, Feb. 27-Mar. 2, 2011, Denver, Colorado, US 30

NPV is most sensitive to Gold Price

Future price estimation:

Average price taken here to be 621.17 $/oz

World Bank forecasts that gold price will be 1,000 $/oz in

2020. This corresponds to growth in gold price of 5.4 % per year

Risk Analysis Based on Forecast Data

Page 31: 18 Autumn in Colorado. Economic Evaluation and Sensitivity-Risk Analysis of Zarshuran Gold Mine Project Authors: Kazem Oraee; University of Stirling,

Case StudyIntroduction ConclusionMethodology Cost & Income Estimation DCF Sensitivity Analysis Risk Analysis

2011 SME Annual Meeting, Feb. 27-Mar. 2, 2011, Denver, Colorado, US 31

If total costs increase by less than 5.4 % per year,

NPV will increase

Therefore:

Risk Analysis Based on Forecast Data

Page 32: 18 Autumn in Colorado. Economic Evaluation and Sensitivity-Risk Analysis of Zarshuran Gold Mine Project Authors: Kazem Oraee; University of Stirling,

Conclusion

Case StudyIntroduction ConclusionMethodology Cost & Income Estimation DCF Sensitivity Analysis Risk Analysis

2011 SME Annual Meeting, Feb. 27-Mar. 2, 2011, Denver, Colorado, US 32

Sensitivity Analysis showed that the selling price of

gold and silver; and discount rate are the most

important parameters. This is often the case in

mining projects.

Page 33: 18 Autumn in Colorado. Economic Evaluation and Sensitivity-Risk Analysis of Zarshuran Gold Mine Project Authors: Kazem Oraee; University of Stirling,

Conclusion

Case StudyIntroduction ConclusionMethodology Cost & Income Estimation DCF Sensitivity Analysis Risk Analysis

2011 SME Annual Meeting, Feb. 27-Mar. 2, 2011, Denver, Colorado, US 33

The NPV and IRR of the project are calculated to be

+ $ 36.6 Million and %22.5 respectively. This is an

attractive project for most investors. Based on the

results of risk analysis, the average value for NPV is

+ $ 49.65 Million. We call this expected NPV.

Page 34: 18 Autumn in Colorado. Economic Evaluation and Sensitivity-Risk Analysis of Zarshuran Gold Mine Project Authors: Kazem Oraee; University of Stirling,

Conclusion

Case StudyIntroduction ConclusionMethodology Cost & Income Estimation DCF Sensitivity Analysis Risk Analysis

2011 SME Annual Meeting, Feb. 27-Mar. 2, 2011, Denver, Colorado, US 34

Mont Carlo simulation also ranks the importance of

important parameters to be:

Gold Price

Discount Rate

Silver Price

Page 35: 18 Autumn in Colorado. Economic Evaluation and Sensitivity-Risk Analysis of Zarshuran Gold Mine Project Authors: Kazem Oraee; University of Stirling,

Thank youfor your attention