18 - 1 ©2003 Prentice Hall Business Publishing, Cost Accounting 11/e, Horngren/Datar/Foster...

60
18 - 1 ©2003 Prentice Hall Business Publishing, Cost Accounting 11/e, Horngren/Datar/F Spoilage, Rework, and Scrap Chapter 18

Transcript of 18 - 1 ©2003 Prentice Hall Business Publishing, Cost Accounting 11/e, Horngren/Datar/Foster...

18 - 1©2003 Prentice Hall Business Publishing, Cost Accounting 11/e, Horngren/Datar/Foster

Spoilage, Rework,and Scrap

Spoilage, Rework,and Scrap

Chapter 18

18 - 2©2003 Prentice Hall Business Publishing, Cost Accounting 11/e, Horngren/Datar/Foster

Learning Objective 1

Distinguish among spoilage,rework, and scrap.

18 - 3©2003 Prentice Hall Business Publishing, Cost Accounting 11/e, Horngren/Datar/Foster

TerminologyTerminology

Spoilage refers to unacceptable unitsdiscarded or sold for reduced prices.

Rework is units that are repaired.

Scrap is material left over.

18 - 4©2003 Prentice Hall Business Publishing, Cost Accounting 11/e, Horngren/Datar/Foster

Learning Objective 2

Describe the accountingprocedures for normal and

abnormal spoilage.

18 - 5©2003 Prentice Hall Business Publishing, Cost Accounting 11/e, Horngren/Datar/Foster

Normal SpoilageNormal Spoilage

Normal spoilage is spoilage that is an inherentresult of the particular production process and

arises even under efficient operating conditions.

Normal spoilage rates should be computed usingtotal good units completed as the base, not total

actual units started in production.

18 - 6©2003 Prentice Hall Business Publishing, Cost Accounting 11/e, Horngren/Datar/Foster

Abnormal SpoilageAbnormal Spoilage

Abnormal spoilage is spoilage that should notarise under efficient operating conditions.

Companies record the units of abnormalspoilage and keep a separate Loss from

Abnormal Spoilage account.

18 - 7©2003 Prentice Hall Business Publishing, Cost Accounting 11/e, Horngren/Datar/Foster

Process Costing andSpoilage Example

Process Costing andSpoilage Example

Big Mountain, Inc., manufactures skiing accessories.

All direct materials are added at the beginning ofthe production process.

In October, $95,200 in direct materials wereintroduced into production.

Assume that 35,000 units were started, 30,000good units were completed, and 1,000 units

were spoiled (all normal spoilage).

18 - 8©2003 Prentice Hall Business Publishing, Cost Accounting 11/e, Horngren/Datar/Foster

Process Costing andSpoilage Example

Process Costing andSpoilage Example

Ending work in process was 4,000 units(each 100% complete as to direct material costs).

Spoilage is detected upon completion of the process.

Spoilage is typically assumed to occur at the stageof completion where inspection takes place.

18 - 9©2003 Prentice Hall Business Publishing, Cost Accounting 11/e, Horngren/Datar/Foster

Process Costing andSpoilage Example

Process Costing andSpoilage Example

Approach A recognizes spoiled units whencomputing output in equivalent units.

Approach B does not count spoiled units when computing output in equivalent units.

18 - 10©2003 Prentice Hall Business Publishing, Cost Accounting 11/e, Horngren/Datar/Foster

Approach A ExampleApproach A Example

Costs to account for $95,200Divide by equivalent units 35,000Cost per equivalent unit $ 2.72Good units completed: 30,000 × $2.72 $81,600Add normal spoilage: 1,000 × $2.72 2,720Costs of good units transferred out $84,320Work in process: 4,000 × $2.72 10,880Costs accounted for $95,200

18 - 11©2003 Prentice Hall Business Publishing, Cost Accounting 11/e, Horngren/Datar/Foster

Approach B ExampleApproach B Example

Costs to account for $95,200Divide by equivalent units 34,000Cost per equivalent unit $ 2.80Good units completed: 30,000 × $2.80 $84,000Costs of good units transferred out $84,000Work in process, ending: 4,000 × $2.80 11,200Costs accounted for $95,200

18 - 12©2003 Prentice Hall Business Publishing, Cost Accounting 11/e, Horngren/Datar/Foster

Learning Objective 3

Account for spoilage inprocess costing using the

weighted-average method.

18 - 13©2003 Prentice Hall Business Publishing, Cost Accounting 11/e, Horngren/Datar/Foster

Weighted-Average: SpoilageWeighted-Average: Spoilage

The following example is for the month ofNovember and relates to Big Mountain, Inc.

Direct materials are introduced at the beginningof the production cycle.

Conversion costs are added evenly during the cycle.

18 - 14©2003 Prentice Hall Business Publishing, Cost Accounting 11/e, Horngren/Datar/Foster

Weighted-Average: SpoilageWeighted-Average: Spoilage

Normally the spoiled units are 2% of the output.

Assume that Big Mountain, Inc., had 1,000 unitsin the beginning work in process inventory,

100% complete for materials ($9,700), and 60%complete for conversion ($10,000).

18 - 15©2003 Prentice Hall Business Publishing, Cost Accounting 11/e, Horngren/Datar/Foster

Weighted-Average: SpoilageWeighted-Average: Spoilage

Ending work in process inventory was 4,000 units(100% materials and 20% conversion).

Costs added during the month were $87,500 formaterials and $72,000 for conversion.

What are the costs assigned to the units completed,spoiled, and in ending work in process inventory?

18 - 16©2003 Prentice Hall Business Publishing, Cost Accounting 11/e, Horngren/Datar/Foster

Physical Units (Step 1)Physical Units (Step 1)

Work in process, beginning (November 1)100% material, 60% conversion costs 1,000Started during November: 35,000

36,000

Good units completed and transferred out: 31,000Work in process, ending inventory:100% material 20% conversion costs 4,000

35,000

18 - 17©2003 Prentice Hall Business Publishing, Cost Accounting 11/e, Horngren/Datar/Foster

Physical Units (Step 1)Physical Units (Step 1)

What is the number of spoiled units?

36,000 – 35,000 = 1,000

What is the normal spoilage?

31,000 × 2% = 620

What is the abnormal spoilage?

1,000 – 620 = 380

18 - 18©2003 Prentice Hall Business Publishing, Cost Accounting 11/e, Horngren/Datar/Foster

Compute EquivalentUnits (Step 2)

Compute EquivalentUnits (Step 2)

Materials ConversionCompleted and transferred 31,000 31,000Normal spoilage 620 620Abnormal spoilage 380 380Ending inventory 4,000 800Equivalent units 36,000 32,800

100%100% 20%20%

18 - 19©2003 Prentice Hall Business Publishing, Cost Accounting 11/e, Horngren/Datar/Foster

Compute EquivalentUnit Costs (Step 3)

Compute EquivalentUnit Costs (Step 3)

Materials Conversion Beginning inventory $ 9,700 $10,000 Current costs 87,500 72,000 Total $97,200 $82,000 Equivalent units 36,000 32,800 Cost per unit $2.70 $2.50

18 - 20©2003 Prentice Hall Business Publishing, Cost Accounting 11/e, Horngren/Datar/Foster

Summarize Total Costs (Step 4)Summarize Total Costs (Step 4)

Work in process beginning inventory:Materials $ 9,700Conversion 10,000Total beginning inventory $ 19,700

+ Current costs:Materials $87,500Conversion 72,000

= Costs to account for $179,200

18 - 21©2003 Prentice Hall Business Publishing, Cost Accounting 11/e, Horngren/Datar/Foster

Assign Total Costs (Step 5)Assign Total Costs (Step 5)

Good units completed and transferred out(31,000 units):Costs before adding normal spoilage:31,000 × ($2.70 + $2.50) $161,200Normal spoilage: 620 × ($2.70 + $2.50) 3,224Total $164,424

18 - 22©2003 Prentice Hall Business Publishing, Cost Accounting 11/e, Horngren/Datar/Foster

Assign Total Costs (Step 5)Assign Total Costs (Step 5)

Abnormal spoilage: 380 × ($2.70 + $2.50) $ 1,976Work in process, ending (4,000 units):Direct materials (4,000 × $2.70) $10,800Conversion (800 × $2.50) 2,000Total $12,800

18 - 23©2003 Prentice Hall Business Publishing, Cost Accounting 11/e, Horngren/Datar/Foster

Assign Total Costs (Step 5)Assign Total Costs (Step 5)

Costs of units completed and transferred out (including normal spoilage) $164,424Cost of abnormal spoilage 1,976Costs in ending inventory 12,800Total costs accounted for $179,200

The $1,976 cost of abnormal spoilageis assigned to the Loss fromAbnormal Spoilage account.

18 - 24©2003 Prentice Hall Business Publishing, Cost Accounting 11/e, Horngren/Datar/Foster

Learning Objective 4

Account for spoilage inprocess costing usingthe first-in, first-out

(FIFO) method.

18 - 25©2003 Prentice Hall Business Publishing, Cost Accounting 11/e, Horngren/Datar/Foster

Physical Units (Step 1)Physical Units (Step 1)

Work in process, beginning (November 1):100% material, 60% conversion costs 1,000Started during November 35,000

36,000

Good units completed and transferred out:From beginning inventory 1,000Started and completed 30,000

31,000

18 - 26©2003 Prentice Hall Business Publishing, Cost Accounting 11/e, Horngren/Datar/Foster

Physical Units (Step 1)Physical Units (Step 1)

Work in process, ending inventory:100% material, 20% conversion costs 4,000Normal spoilage 620Abnormal spoilage 380

18 - 27©2003 Prentice Hall Business Publishing, Cost Accounting 11/e, Horngren/Datar/Foster

Compute EquivalentUnits (Step 2)

Compute EquivalentUnits (Step 2)

Materials ConversionGood units completed and transferred out:From beginning inventory 0 400Started and completed 30,000 30,000Normal spoilage 620 620Abnormal spoilage 380 380Ending inventory 4,000 800Equivalent units 35,000 32,200

18 - 28©2003 Prentice Hall Business Publishing, Cost Accounting 11/e, Horngren/Datar/Foster

Compute EquivalentUnit Costs (Step 3)

Compute EquivalentUnit Costs (Step 3)

Materials ConversionCurrent costs $87,500 $72,000Divided by equivalent units 35,000 32,200Cost per unit $2.50 $2.236**$2.236 (rounded)

18 - 29©2003 Prentice Hall Business Publishing, Cost Accounting 11/e, Horngren/Datar/Foster

Summarize Total Costs (Step 4)Summarize Total Costs (Step 4)

Work in process beginning inventory:Materials $ 9,700Conversion 10,000Total beginning inventory $ 19,700

+ Current costs: Materials $ 87,500 Conversion 72,000= Costs to account for: $179,200

18 - 30©2003 Prentice Hall Business Publishing, Cost Accounting 11/e, Horngren/Datar/Foster

Assign Total Costs (Step 5)Assign Total Costs (Step 5)

Good units completed and transferred out:

From beginning inventory:Work in process $ 19,700.00Conversion costs added incurrent period (400 × $2.236) 894.40Total $ 20,594.40

Started and completed:30,000 × ($2.50 + $2.236) $142,080.00

18 - 31©2003 Prentice Hall Business Publishing, Cost Accounting 11/e, Horngren/Datar/Foster

Assign Total Costs (Step 5)Assign Total Costs (Step 5)

Costs before adding normal spoilage:($20,594.40 + $142,080.00) $162,674.40

Normal spoilage:620 × ($2.50 + $2.236) 2,936.32Total $165,610.72

18 - 32©2003 Prentice Hall Business Publishing, Cost Accounting 11/e, Horngren/Datar/Foster

Assign Total Costs (Step 5)Assign Total Costs (Step 5)

Abnormal spoilage:380 × ($2.50 + $2.236) $1,799.68

Work in process, ending (4,000 units):Direct materials (4,000 × $2.50) $10,000Conversion (800 × $2.236) 1,789Total $11,789

18 - 33©2003 Prentice Hall Business Publishing, Cost Accounting 11/e, Horngren/Datar/Foster

Assign Total Costs (Step 5)Assign Total Costs (Step 5)

Costs of units completed and transferred out (including normal spoilage) $165,610.72Cost of abnormal spoilage 1,799.68Costs in ending inventory 11,789.00Total costs accounted for $179,200.00

The $1,799.68 costs of abnormal spoilage areassigned to the Loss from Abnormal Spoilage

account.

18 - 34©2003 Prentice Hall Business Publishing, Cost Accounting 11/e, Horngren/Datar/Foster

Learning Objective 5

Account for spoilage inprocess costing using thestandard-costing method.

18 - 35©2003 Prentice Hall Business Publishing, Cost Accounting 11/e, Horngren/Datar/Foster

Standard-Costing: SpoilageStandard-Costing: Spoilage

The standard-costing method makescalculating equivalent unit costsunnecessary and so simplifies

process costing.

18 - 36©2003 Prentice Hall Business Publishing, Cost Accounting 11/e, Horngren/Datar/Foster

Journal EntriesJournal Entries

Assume that the completed units are transferredto Finished Goods.

What are the journal entries?

Finished Goods XXXWork in Process XXX

To transfer good units completed in November

18 - 37©2003 Prentice Hall Business Publishing, Cost Accounting 11/e, Horngren/Datar/Foster

Journal EntriesJournal Entries

Loss from Abnormal Spoilage XXXWork in Process XXX

To recognize abnormal spoilage detected inNovember

18 - 38©2003 Prentice Hall Business Publishing, Cost Accounting 11/e, Horngren/Datar/Foster

Learning Objective 6

Account for spoilage in job costing.

18 - 39©2003 Prentice Hall Business Publishing, Cost Accounting 11/e, Horngren/Datar/Foster

Job Costing: SpoilageJob Costing: Spoilage

With a job-costing system, companies candecide to assign normal spoilage to specific jobs.

Alternatively, they can allocate normal spoilageto all jobs as part of manufacturing overhead.

Loss from abnormal spoilage is recorded asa cost of the period.

18 - 40©2003 Prentice Hall Business Publishing, Cost Accounting 11/e, Horngren/Datar/Foster

Job Costing: SpoilageJob Costing: Spoilage

Assume that 5 parts out of 40 parts of WhitefishMachine Shop’s Job #10 are spoiled (normal).

Costs assigned prior to the inspection pointare $1,000 per part.

The current disposal price of the spoiled partsis $200 per part.

When the spoilage is detected, the spoiled goodsare inventoried at $200 per part.

18 - 41©2003 Prentice Hall Business Publishing, Cost Accounting 11/e, Horngren/Datar/Foster

Job Costing: SpoilageJob Costing: Spoilage

Normal spoilage attributable to a specific job:

When normal spoilage occurs because of thespecifications of a particular job, that jobbears the cost of the spoilage reduced by

the current disposal value of that spoilage.

What is the journal entry?

18 - 42©2003 Prentice Hall Business Publishing, Cost Accounting 11/e, Horngren/Datar/Foster

Job Costing: SpoilageJob Costing: Spoilage

Materials Control(spoiled goods at currentdisposal value): 5 × $200 1,000

Work in Process Control (Job #10) 1,000To recognize disposal value of spoiled parts

18 - 43©2003 Prentice Hall Business Publishing, Cost Accounting 11/e, Horngren/Datar/Foster

Job Costing: SpoilageJob Costing: Spoilage

Work in Process (Job # 10)Parts 40,000 Parts 1,000(40 × $1,000) (5 × $200)Balance 39,000

What is the total cost of the 35 good units?

(35 × $1,000) + (5 × $800) = $39,000

18 - 44©2003 Prentice Hall Business Publishing, Cost Accounting 11/e, Horngren/Datar/Foster

Job Costing: SpoilageJob Costing: Spoilage

Normal spoilage common to all jobs:

In some cases, spoilage may be considered anormal characteristic of a given production cycle.

The spoilage is not charged to a specific job.

What is the journal entry?

18 - 45©2003 Prentice Hall Business Publishing, Cost Accounting 11/e, Horngren/Datar/Foster

Job Costing: SpoilageJob Costing: Spoilage

Materials Control(spoiled goods at currentdisposal value): 5 × $200 1,000Manufacturing OverheadControl (normal spoilage) 4,000

Work in Process Control (Job #10) 5,000To recognize spoiled parts

18 - 46©2003 Prentice Hall Business Publishing, Cost Accounting 11/e, Horngren/Datar/Foster

Job Costing: SpoilageJob Costing: Spoilage

Abnormal spoilage:

If the spoilage is abnormal, the net loss ishighlighted and always charged to an

abnormal loss account.

Assume that the 5 parts of Whitefish MachineShop’s Job #10 are considered abnormal spoilage.

What is the journal entry?

18 - 47©2003 Prentice Hall Business Publishing, Cost Accounting 11/e, Horngren/Datar/Foster

Job Costing: SpoilageJob Costing: Spoilage

Materials Control(spoiled goods at currentdisposal value): 5 × $200 1,000Loss from Abnormal Spoilage 4,000

Work in Process Control (Job #10) 5,000To recognize spoiled parts

18 - 48©2003 Prentice Hall Business Publishing, Cost Accounting 11/e, Horngren/Datar/Foster

Learning Objective 7

Account for rework in job costing.

18 - 49©2003 Prentice Hall Business Publishing, Cost Accounting 11/e, Horngren/Datar/Foster

Rework Units ExampleRework Units Example

Normal rework attributable to a specific job:

Assume that the 5 parts of Whitefish Machine Shop’sJob #10 can be reworked for a total cost of $1,800.

$5,000 of costs associated with these parts havealready been assigned to Job #10 before rework.

What is the journal entry?

18 - 50©2003 Prentice Hall Business Publishing, Cost Accounting 11/e, Horngren/Datar/Foster

Rework Units ExampleRework Units Example

Work in Process (Job #10) 1,800Various Accounts 1,800

To charge rework costs to the job

Normal rework common to all jobs:Debit Manufacturing Overhead Control

(rework costs).

Abnormal rework:Debit Loss from Abnormal Rework.

18 - 51©2003 Prentice Hall Business Publishing, Cost Accounting 11/e, Horngren/Datar/Foster

Learning Objective 8

Account for scrap.

18 - 52©2003 Prentice Hall Business Publishing, Cost Accounting 11/e, Horngren/Datar/Foster

Recognizing ScrapRecognizing Scrap

Scrap is recognized in the accountingrecords either at the time of its sale or

at the time of its production.

Sale of scrap, if immaterial, is oftenrecognized as other revenues.

18 - 53©2003 Prentice Hall Business Publishing, Cost Accounting 11/e, Horngren/Datar/Foster

Recognizing Scrap ExampleRecognizing Scrap Example

Assume that Job #10 of Whitefish MachineShop generates normal scrap with a totalsales value of $300 (it is assumed that the

scrap returned to the storeroom is sold quickly).

Recognizing scrap at the time of its sale:

What is the journal entry?

18 - 54©2003 Prentice Hall Business Publishing, Cost Accounting 11/e, Horngren/Datar/Foster

Recognizing Scrap ExampleRecognizing Scrap Example

Cash or Accounts Receivable 300Sales of Scrap 300

To record other revenue sale of scrap

Scrap attributable to a specific job:

Job-costing systems sometimes trace the saleof scrap to the jobs that yielded the scrap.

Assume that the scrap can be tracedspecifically to Job #10.

18 - 55©2003 Prentice Hall Business Publishing, Cost Accounting 11/e, Horngren/Datar/Foster

Recognizing Scrap ExampleRecognizing Scrap Example

What is the journal entry?

Cash or Accounts Receivable 300Work in Process (Job #10) 300

To record sale of scrap

Scrap common to all jobs:

Cash or Accounts Receivable 300Manufacturing Overhead Control 300

To record other revenue sale of scrap

18 - 56©2003 Prentice Hall Business Publishing, Cost Accounting 11/e, Horngren/Datar/Foster

Recognizing Scrap ExampleRecognizing Scrap Example

Assume that the scrap is inventoriable.

What is the journal entry when scrap is attributableto Job #10 and it is returned to the storeroom?

Materials Control 300Work in Process (Job #10) 300

To record scrap returned to stores

18 - 57©2003 Prentice Hall Business Publishing, Cost Accounting 11/e, Horngren/Datar/Foster

Recognizing Scrap ExampleRecognizing Scrap Example

What is the journal entry when scrap is commonto all jobs and it is returned to the storeroom?

Materials Control 300Manufacturing Overhead Control 300

To record scrap returned to stores

18 - 58©2003 Prentice Hall Business Publishing, Cost Accounting 11/e, Horngren/Datar/Foster

Recognizing Scrap ExampleRecognizing Scrap Example

What is the journal entry when scrap is sold?

Cash or Accounts Receivable 300Materials Control 300

To record other revenue sale of scrap

18 - 59©2003 Prentice Hall Business Publishing, Cost Accounting 11/e, Horngren/Datar/Foster

Recognizing Scrap ExampleRecognizing Scrap Example

What is the journal entry when scrap is reused?

Work in Process Control 300Materials Control 300

To record use of scrap

18 - 60©2003 Prentice Hall Business Publishing, Cost Accounting 11/e, Horngren/Datar/Foster

End of Chapter 18End of Chapter 18