National Institute of Fashion Technology, Gandhinagar
Summer Internship Report
at
Shahi Exports Pvt. Ltd. Faridabad
A summer Internship Report for Partial fulfilment of the Requirement for the award of Degree in
Bachelor of Fashion Technology-Apparel Production
By-
Satyam Singh
Shrey Vij
Department of Fashion Technology
Batch 2008-2012
ACKNOWLDGEMENT
We would like to thank Ms. Ameesha Mehta, Course Coordinator, UG-Technology, and
our faculty mentor Mr. Pawan Godiawala, Department of Fashion Technology for their
guidance and motivation throughout the duration of this internship.
This work is not a sole endeavour but rather an integrated effort of many individuals
directed towards the same goal. We feel very much proud at underlining the
magnanimous qualities of Mr. Raman Bhutani, Assistant Production Manager, Shahi
Exports, Faridabad for showing affection, enthusing zeal, germinating interest and
inspiring hard work.
We would like to extend my gratitude to Mr. Sunil Jasso, GM Production, Mr.Pardeep
Singh, IE Manager, Mr. Ankur Joshi, Cutting Manager and all the employees of Shahi
Exports for showing great concern & interest in our work and guided us throughout the
internship. They have been a constant source of inspiration to us throughout the duration
of the internship, constantly monitoring the work at close quarters and throwing light on
minute technicalities. It would be appropriate to say that this work would not have seen
the light of the day, but for their painstaking and unstinted cooperation.
Satyam Singh
Shrey Vij
2
SECTION- A
Company Overview
3
INTRODUCTION
SHAHI Exports Pvt. Ltd. is engaged in the manufacture and export of readymade garments in
the International market. It is one of the largest export houses in India. The company started its
operations in the form of a small fabrication unit with the help of 25 machines.
The company has grown from leaps to bounds from a simple fabrication unit to present turnover
of Rs. 2200 crore, around 55000 employees and spread over 27 locations. It has manufacturing
units in six different states of India viz. Delhi, Haryana, Uttar Pradesh, Tamil Nadu, Karnataka
and Andhra Pradesh. The group is into manufacturing of a wide range of Men’s and Ladies wear
and also home products.
SHAHI group has all the modern units equipped with state-of-the-art technology giving the best
to its buyers.
Its manufacturing facilities includes Assembly line machines, Prima Vision system print/fabric
development, Meyer fusing press, Barudan and Tajima, Multi head computerized embroidery
machine, in house washing plant, automatic cutting machines (F.K. Systems).
SHAHI has a well-equipped sampling division where latest patterns/designs/styles of high stan-
dards are developed with the assistance of experienced designers.
It has a training center for tailors at Faridabad and Bangalore each to train and develop them into
vital human resource for efficient operations.
As regards to quality, SHAHI has been ranked one of the best in Asia by J.C.Penny, the world-
renowned departmental stores.
4
COMPANY PROFILE
Name: Shahi Exports Private Limited
Established: 1974
Owner: Mrs. Sarla Ahuja
Managing Director: Mr. Harish Ahuja
Address: Industrial Plot-1, Sector 28 Faridabad, Haryana
Work Force: More than 30,000
Capacity: Over 2 million high quality garments per month
Retail House: At Last & Co. , New York
Fabric Processing: Sarla Fabrics, Ghaziabad
Annual Turnover: INR 2200 crore (Group Turnover)
COMPANY MISSION:
Exploring new dimensions of excellence. A path, where there was none. A new horizon beyond
yesterday. Excellence beyond today, touching tomorrow. It’s a world of relentless quest for
quality. Its mindset, the action, and partners of Shahi are ever reaching further, never resting on
achievements. Yes! Milestone never takes one there; it is the road that we create to reach
excellence. Ever evolving excellence. Shahi believes that its main strength is its people. The
larger investments made in the manufacturing units will give the desired results only if backed
by a committed human effort. The result will directly give us a sense of pride for being a part of
Shahi family.
CORPORATE VALUES
Guiding principles illuminate the path that leads to their destination. SHAHI emphasizes on
some guiding principles, which are indicative of the values it believes in and would like to
continue in the organization. These are the building blocks of the organizational culture. The
company believes in:
5
High level of honesty and a sense of responsibility.
Two-way communication channel for all purposes of communication.
In sharing the fruit of growth, prosperity with its partners i.e. the employees.
In giving each individual room to contribute and grow.
The company firmly believes that team spirit is the hallmark of success.
KEY STRENGTHS
Shahi Exports Private Limited (Shahi) is one of the largest vertically integrated garment manufacturer and exporter in India.
India’s second largest apparel exporter by value of exports.
Shahi is one of the most successful professionally managed companies in India.
India’s largest exporter by installed capacity.
Well qualified trained and committed professionals with a shared vision.
Highly qualified Design team, Product development skills and a Design Studio.
High degree of adoption of advanced manufacturing technology MIS and IT systems.
All factories and offices are electronically linked to facilitate all time access to informa-tion
Focus on quality and a proven track record :
Short shipment: 0.50%
On time delivery: 98%
Quality claims: Nil.
6
PRODUCT PROFILE:
The following are based and operated in NCR
1. LSD – Ladies Speciality Division
2. LBAD – Ladies branded Apparel Division
3. LFD – Ladies Fashion Division (basically caters to Wal-Mart)
4. HFD – Home Furnishing Division
MAJOR BUYERS
Tommy Hilfigher Armani Hugo Boss Liz Claiborn Abercrombie & Fitch (A &
F) J.C. Penny Kohls
Gap Target Wal-mart Calvin Klein Espirit Hennes & Mauritz (H &
M) Nautica
7
COMPANY HEIRARCHY
(Fig 1)
Departments
115
MERCHANDISING DEPARTMENT
A merchandiser is an interface between the buyer and the supplier who has to ensure the quality of
production and timely delivery. Merchandising is a process through which products are planned,
developed, executed and presented to the buyers. It includes directing and overseeing the
development of product line from start to finish.
ROLE OF THE DEPARTMENT
To look for the appropriate market
To get the samples made according to the buyer’s specification
To estimate and quote the cost of the garment to the buyer and negotiate with them
Getting orders
Constant interaction with the buyer for the approval
To get the fabric and trims in-house for bulk production
Co-ordinating with the PPC and production
OBJECTIVE OF MERCHANDISER
To create market
Understanding buyers’ requirements
Sourcing of materials, fabrics
Select the range
Creating the product
Taking buyers approvals
Negotiation with buyer
Procuring the orders
Materializing the order
Execution the order
Coordination between production and production planning department
Dispatching the shipment
116
After shipment dispatching merchandiser is also responsible for buyer claims, profit and
subsequent orders. If buyer has any problem in quality of the product then it is the
responsibility of the merchandiser to resolve the problem with the buyer.
(Fig 1.1)
HIERARCHY
117
Fig(1.2)
118
PROFIT CENTER HEAD, MARKETING
DIVISIONAL MARKETING MANAGER
MARKETING MANAGER
SENIOR MERCHANT
MERCHANT
JUNIOR MERCHANT
CO-ORDINATOR
PROCESS OF MERCHANDISING:
The first stage of merchandising is when buyer sends either spec, sketch or any garment
pieces and asks for sample with costing or only costing using different fabrics. The specs
sent by the buyer are also called Tech Packs.
The merchandiser gets the approval of all things like fabric, trims, label, costing etc. and
either buyer gives the approval or gives the vendors’ name.
-The allocation chart and FTP directory is received by the merchant from the buyer online.
-The fabric CAD is also received from the buyer which has all the details of the pantone
shade and the repeat size.
-The prints are developed from their own mill, SFL (Sarla Fabric Limited) or are
subcontracted.
-A CD is developed which has the color picture of the fabric. This is sent to the fabric
department for development.
-Sample piece is developed.
Next, costing is done on the basis of the spec, sketch and garment which are sent by the
buyer for making the sample. Merchandiser does the average costing/consumption of the
garment. The quotation is sent to the buyer/buying house and the approval is awaited. One
thing is to be noted that while giving the consumption, the cut-able width of the fabric to be
received (either mill made-developed in India or imported fabric) has to be considered
while costing. Also the marker utilization depends on the style, which may affect the
consumption greatly. The fabric characteristic also matters vis-à-vis nap etc.
The merchandiser monitors the design from sampling to production and then final dispatch.
They are a link between the buyer and the company. All correspondence that the buyer
wants to do regarding his style will be done through the merchandiser. Merchandiser
monitors the total sampling from development to the time the production sample is made
119
and goods go into actual production.
They also see that the fabric is developed on time and send it for approval to the buyer and
subsequently if all samples are made on time, send them to the buyer for approval too.
They are also in constant touch with production to know the status of their styles.
Merchandising activities include:
1. To get order : Buyer directly communicates with the merchandiser in order to place the order.
Fixed buyers are allotted to merchandisers and the communication is between the buyer an that
particular merchant.
2. Costing: Costing of the garment in bulk is calculated on the basis of quality of material and
their requirement in the garment. It is one of the most important activities of the merchandiser.
To arrive at a perfect price to be quoted to the buyer, following points are taken into
consideration:
Costing is done considering these aspects of the cost.
120
FIXED COST
1. Factory Cost - It is the fixed cost incurred for running the factory. It is different for
different floor.
2. Standard Sewing Cost
Direct Labour: Operators Salary
Indirect Material: Lubrication Oil, Needles , Cleaning Material
Indirect Labour: Staff & Maintenance Salary
Indirect Expenses: Power, Depreciation Of The Machinery
The standard sewing cost per operator per hour defined by Shahi for its Faridabad unit is
Rs 62.83
VARIABLE COST
1. YY (Yields/yards) – It is average consumption of the fabric. It is decided by preparing a
mini-marker which includes wastage of fabric due to laying, cutting, fabric defect, end cut-
ting loss, marker loss and the buffer that is maintained to avoid shortage in future.
2. Trims Cost – They are procured from local market as well as imported as per buyer’s re-
quirements.
Calculation of cost of fabric per garment
Calculation of cost of trims and threads
Cut-make cost
Poly bag cost
Cost of carton box
Calculation of consumption of fabric (yields per yard) and threads to
produce one garment
3. Sampling: Merchandiser is involved in coordinating with the sampling department. Based on
the mutual agreement between the merchant and the buyer, sampling department is involved in
121
making samples. In every step of samples, buyer sends back comments along with the tech
pack.
4. Order confirmation: After the approval of all the samples, the order is confirmed by the
buyer. Merchandiser receives the PO sheet. Merchandising department communicates with
planning and production departments and decides for the possible PCD (production cut date)
for the required quantity. Then he fixes up the PCD and delivery date with the buyer.
5. Preparing the time and action plan: This is prepared by the merchant stating that all the
different activities associated with the order should be complete by the stipulated dates. It is
like making sub goals to accomplish the ultimate goal which is shipping of the order on the
pre- decided date.
6. Preparing the bill of material: This enlists all the different materials required for making the
garment.
7. Execution: Merchandising department communicates with the buyer QA during the
production. He gets the approval of the quality or any changes in the garment.
8. Shipment of goods: According to delivery date the goods are shipped on time.
Documentation department is informed about the delivery date, the quantity etc. In case of any
delay, goods are sent through air on the company’s cost.
For each order, the merchant has to prepare a file containing all the details and relevant documents
which is passed on to the subsequent stages in the production process for reference purposes.
122
DOCUMENTATION IN MERCHANDISING
File prepared by merchant has following details:
Style Specification: contains a brief description of the style.
Style # : as mentioned by the buyer
Movex item # : Item number of the style by Movex
Buyer: Name of the buyer
PCD: Production cut date for the style
Merchant: Name of the merchant handling the style
The file contains the following:
Purchase order for the style
Garment techpack
Relevant communication with the buyer regarding proto, fit and pre production samples. All the comments from the buyer for various samples are included.
Thread consumption report
Fabric Test Report
Fabric and trim cards: Contains swatches of the fabric and trims to be used
Mini marker with costing average
FOLDER SUMMARY
It consists of the general details like brand name, buyer’s name, size range and the drawing of the
garment.
1. Color / Trim Page: It consists of the details like description, size of the trims like button
size, material of which it is made of, no. of holes that it should have.
2. Fabric Page: It consists of the details of the fabric like the count of the yarn, construction
(EPI, PPI) and color specifications. It also states the value addition finishes and
embellishments.
123
3. Packing And Labeling Details: It consists of the details like type of packing, hanger type,
polybag type, clips type of labeling.
4. Label Placement: It describes with figures where the label, hang tag, spare button is to be
attached.
5. Correct Balance : Basic and important tips for correct fit
6. How to Measure: It shows how to measure the important dimensions of the garment.
7. Technical Sketch: It is a 2-D representation of the garment showing all the stitch lines,
panes, trims etc. symbolically.
8. Development Photos: It consists of the photos of the garment.
9. Specification Sheet: It consists of all the dimensions with tolerances and increments for
bigger sizes.
10. Bill Passing Reports: This is the report used in fabric receiving. It states details like type,
quantity, receipt no, item details, amount. It also has goods receipt note attached. It contains
fabric code, width, color, quantity, rate, value etc.
11. Feedback: The feedback comes in the form of comments and photographs of the garment
on the dummy with its errors highlighted like puckering and pinching.
12. Costing Sheet: Contains details like cost of fabric, trims, washing, embroidery, sampling,
testing, freight, duty, insurance etc.
13. Style Track Sheet: It is used to track the status of the order. It consists of details like style
no., merchant’s name, floor on which it is allocated, name of the floor manager.
14. Initial Marker Planning Sheet: It consists of fabric width, total pieces, pieces placed,
efficiency and length.
124
15. Approval Form : Approvals can be for fabric, trims, slight errors which are acceptable to
the buyer
Workflow of the Merchandising Department
Fig(1.3)
125
Buyer’s enquiry / Tech-pack
Costing
Style finalization
Purchase Order received
Fit approval process 1st fit
Fabric/Material approval 2nd fit
Fabric/Material order Pre production sample
Fabric/Material follow-up Size set
Fabric/Material in-house Production
Follow-up
Regular tracking and updating buyer
Order shipping
SAMPLING DEPARTMENT
Sampling department is the most vital department of the organization. It is the department that de-
velops the samples thus enabling the Product Development. This department prepares samples on
the basis of the requirements of the buyer. The sampling department here caters to the need of all
the other units of Shahi as it was centralized.
Sampling was self sufficient as it had its own stitching. washing, trimming, spotting, and ironing
etc dedicated for the construction of samples only. The fabric and trims are sourced from the in
house warehouse depending upon the availability. The fabric which is sourced for the sampling
purpose is called yardage and is 25-30mts in length.
SAMPLING PROCESS :
The process of sampling goes through a series of sampling stages each of them are explained
below:
1. PROTO SAMPLE: It is the reflection of the first techpack received from the buyer. The
sample is sent to the buyer for the design approval. Proto sample is made in the base size. Styling
is important. The comments and second tech pack is sent back referring changes in the sample.
2. FIT SAMPLE: The comments are received regarding the shape, size and fullness. The sample
is checked for fit on body forms. It is made in exact fabric, though print maybe different,
since the drape and fit are to be checked.
3. SECOND FIT SAMPLE: It is similar to the first fit sample made with a few changes according
to comments received from the buyer. Again a third or fourth fit sample may be required to be
made. After approval of fit sample, order is confirmed along with all the specifications.
4. PRE-PRODUCTION/SEALER SAMPLE: This sample is known as the bible of production. It
is done for the base size of any one color and actual fabric and actual trims are used.
126
5. SIZE-SET SAMPLE: The sample is made in actual fabric and trims in all sizes and is sent to
the buyer for approval.
6. GPT SAMPLE: These samples are made for garment testing for seam-slippage, tearing
strength, button pulling etc. it is the garment pack sample.
7. TOP (TOP OF PRODUCTION) SAMPLE: It is the best sample from first of bulk production.
8. SALESMAN SAMPLE: It is made for the buyer to find out the opinion of the store owners
whether the style would sell in the market or not, and the demand of that product.
WORKFLOW OF THE SAMPLING DEPARTMENT
Fig(1.4)
127Alteration (if any)
B/A, Riveting
Thread Trimming
Merchandiser orders for fabric Requisition
Patterns are made as per the PO
Raw material is issued on PO
Cutting
Embroidery (if any)
Sewing
Bar-tacking, B/H
Washing
MACHINERY DETAILS
The sampling department has 9 lines with different machines. For details refer (Appendix 1.1 and
Appendix 1.2)
128
Ironing
Initial Checking
Spotting
Final Checking (according to PO)
Packing
Measurement Checking
Erudition:
The average FOB is $8-$10 .
The most complex stage is getting the approval from the buyer on fabric, shades, print and fit.
Since the lead time is less, therefore any delay at any stage can delay the entire order.
The operators in the sampling department are very experienced and highly skilled. They are explained the construction of any new sample by the pattern master and the supervisor.
IT plays a crucial role in the merchandising department. All information regarding the order status are fed into the ERP. This facilitates smooth flow in the department.
129
ORDER ANALYSIS DEPARTMENT
The Order Analysis Department (OAD) acts as the bridge between the merchandising and the
production functions of the unit. This department gives technical support to the production team.
They do a complete analysis of the style from all possible perspectives. A research or analysis
plays an important role before manufacturing any product. The role of this department starts when
the all the fit and sealer samples for the style have been approved and the order is ready for bulk
production.
OAD receives two complete files containing all the details and documents from the concerned
merchant. Once the files are received by the department, they are checked for the following details:
Purchase Order (PO) – contains order quantity, colour and size ratio, destination,
delivery date etc
Product Style Details (PSD) – contains details about the fabric (count,
construction, colour), thread, labels, accessories, buttons, fusing etc.
Final mini marker (for interlinings as well if applicable)
Tech Pack (updated) – containing garment measurements with all the fit
comments by the buyer.
Sealed sample (buyer approved)
Embroidery design – with the placement and type of thread to be used
Swatches of fabric, fusing, threads etc
Operational breakdown of the style
Thread consumption report
Base patterns
Washing, ironing and packing instructions
130
The department checks if all the documents are present in the files and are complete. Once this is
established, one file is sent to the Industrial Engineering Department and the other is kept in OAD
and worked upon.
FUNCTIONS
The following functions are carried out by the Order Analysis Department:
All the base patterns and the sealer sample are checked and the measurements are matched
with the specifications given by the buyer. It is also checked whether all the latest
comments related to the fit of the garment have been incorporated and the necessary
alterations are made to the patterns with the involvement of the merchant.
Size set patterns are developed according to the final corrected patterns. Size set samples
(two per size) are checked by OAD for measurements and construction.
OAD analyzes the fabric and what it demands while being used in manufacturing. The
impact of dyeing, processing and finishing on the fabric is considered, its shrinkage along
warp and weft is determined. Also it is determined if any special test should be done on the
fabric.
Complete analysis of the trims is carried out. Their compatibility with each other and more
importantly with the fabric is checked through tests.
A thorough study of seams and stitches of the sample is done. This helps in maintaining the
quality of the garment and in reduction of unwanted operations.
OAD determines the spreading and cutting details like mode of spreading, grain on which
patterns are to be cut etc
All the stitching details like the different stitches and seams to be used, SPI to be used are
determined.
Based on the size set development, all the critical quality points and instructions to the
operator and checkers are determined.
131
Style Analysis Report
OAD prepares a report called the Style Analysis Report based on the studies carried out by them.
This is a 3-4 page report containing all the details which would be required by the subsequent
departments in a concise form so that they can be retrieved quickly and easily by anyone. This
report consists of details about the fabric, trims, spreading and cutting instructions, construction
details such as stitches and seams along with all seam diagrams, washing, ironing and packing
instructions and critical instructions to the sewing operators and quality checkers.
(Sample report attached in the appendix (Report 1)
132
COMPUTER AIDED DESIGN DEPARTMENT
This department is centralized for all the NCR units of Shahi. Based on the nature of work, this
department is divided into four sections:
SECTIONS
Embroidery section: It makes the punch cards according to the design of embroidery. This
punch card is fed into a floppy which is inserted into the embroidery machine for it to un-
derstand the design.
In the remaining three sections, the software being used is OPTITEX
Pattern making section : Making the patterns using specification sheets and then checking
their fit on virtual dummies.
Grading section: Generally medium size patterns are developed and they are graded up to
the required number of sizes up and down.
Marker making section : Markers are made keeping in mind the following factors:
Mode of spreading
Width of the fabric available
Matching if required
Shrinkage along warp and weft
Size ratio required
The marker made is first taken out on the printer (miniature version markers). The
full size markers are printed through on the plotter. The computer aided design
department is also responsible for making mini for merchandiser for estimating the
costing average.
The usual marker efficiency achieved is 75%-85%
133
Machinery details
Number of computer systems = 12
One digitizing screen for transferring manually made patterns into the system
One digital printing machine for printing prints on fabric for sampling purposes
Workforce
20 pattern masters
4 graders
2 digitizers
10 marker makers
6 staff members
134
WORK PROCESS FLOW OF CAD
(Fig: 1.5)
135
Receive spec sheets from merchant
Make pattern
Digitize pattern
Pattern correction
Pattern grading
Cut ratio planning
Output marker to plotter Output mini marker to printer
Send to cutting dept. for cutting Send to merchandiser for costing
Marker planning according to the cut ratio plan
Output to graphic plotter
Patterns sent to merchant for sampling
PRODUCTION PLANNING AND CONTROL DEPARTMENT
This department has two parts: production planning and production control.
PRODUCTION PLANNING
The production planning department at Shahi Exports, Faridabad is a centralized planning
department for all the units in the NCR. So, primarily the planning of the following six units takes
place here:
Faridabad
Faridabad 2
Sarai
Okhla
A-5
E-10
The number of lines and number of machines per line in each of the six units are as follows:
(Table 1.1)
Unit Number of lines Machines/Line
Faridabad
LSD& HFD (all H&M and
Target orders executed here
only)
21 40
Faridabad 2 (LFD) 22 40
Sarai 9 33
Okhla 12 40
A-5 8 45
136
The planning is done for all the lines of all the above units. While planning, they consider a
planned efficiency slab for the purpose of estimating output. This efficiency slab is based on the
order quantity and is as follows:
Style wise order quantity Efficiency to be considered:
(Table 1.2)
Style wise order quantity Efficiency to be considered
1500-3000 30%
3001-10000 40%
10001-20000 51%
20001-30000 58%
30001-50000 63%
More than 50000 65%
Based on this, they book the capacity for fulfilling the upcoming orders on time. The roles and responsibilities of the production planning people include:
Analyzing the available capacity and communicating to the merchandiser whether it will be
possible to complete a particular order on the delivery date quoted by the buyer.
To ensure that the lines are continuously fed and in case of sliding of orders, the orders
must be reshuffled so that the lines are never idle. In short, they are responsible for opti-
mum utilization of the available capacity.
137
PRODUCTION CONTROL
For the purpose of production control, there are five teams in this department segregated buyer
wise. These people are responsible for the execution of order in the unit. The roles and
responsibilities of production control people are:
To supervise smooth execution of the order in the unit.
Organizing a pre-production meeting prior to production to discuss critical issues.
Complete fabric follow up with merchant and the fabric store.
Complete accessory follow up with merchant and sub store.
Supervising the entire production process to ensure timely execution of the order.
WORKING OF PPC-
A style sheet is received which has a style no., pictures, order quantity, and ex factory. This
is received by the product development department.
Next, unit is allocated i.e. it is determined in which factory unit, the particular style is going
to be made on basis of the order quantity. Also, the ex factory dates are decided.
A final chart is prepared and the PD team then divides the order quantity to the production
team.
A style number is decided upon. This number is used by the merchant to communicate with
buyer.
Production team specifies the item number and then the production structure is developed.
Final sample received from the buyer and PDS is updated.
Next, production team and the merchandiser prepares details about the item. i.e. trims,
thread etc.
Through movex, any item can be checked by the other department but cannot be altered.
Industrial engineering specifies the costing through the run through time. Thus the total
cost is achieved.
After the cost sheet is signed, ordering is done.
138
The PCD (Planned Cut Date) is decided and 40% of all the materials should be enclosed by this
date. If the order quantity is less than 5000 pcs, the 100% of the materials should be enclosed.
7- 10 days before the planned cut date, 2 samples and 2 files are received sealed from the buyer.
Production File (It has details about the marker, tech pack, color of thread, trims, hanger,
specification sheets etc.) is given to the OAD (Order analysis department). The OAD checks the
patterns and other techniques. If it is approved, the garment is sealed and sent to the I.E.D.
DOCUMENTS MAINTAINED-
Daily production reports
Production File
Internal Movex reports
Conversion costs for units
Planned vs. HO reports
Production Variance Reports (PVR)
Erudition:
Proper feeding in the lines must be done
Follow up of the processes is very important
Regular flow of materials in a line must be maintained
No line must stay idle
Urgent orders can be given priority over others
All the raw material must arrive on time to meet the delivery dates
FABRIC SOURCING DEPARTMENT
Sourcing of the fabric is the responsibility of this department. They source fabric for sampling as
well, except for Target and Walmart which have a separate sampling sourcing division. Unlike in
other industries, this department is segregated according to the areas from which the fabric is
purchased rather than being segregated buyer wise.
139
DIVISIONS
CENTRAL SOURCING DIVISION: It is responsible for sourcing of greige fabric like
cambric, voile, poplin etc.
PROCESSING DIVISION: It is responsible for getting the greige fabric processed. It
works in coordination with the central sourcing division.
SALEM DIVISION: It is responsible for sourcing of yarn dyed fabrics. The checking of
yarn dyed fabrics is done at Salem only by an office of Shahi set up there before it is dis -
patched.
IMPORTS AND MILL MADE DIVISION: It is responsible for sourcing of imported
and mill made fabric (from Surat). Only finished fabric is imported. 90% of the fabric im-
ported is from China and 5% each from Korea and Pakistan. About 20-25% of the total fab-
ric is imported and for 60-70% of outhouse production, imported fabric is used. Outhouse
production facilities are available at Bangladesh and Sri Lanka. Fabrics that are imported
include:
Stretch fabrics
Linen and its blends
Silk and its blends
Bottom weight fabrics
Cotton, poly-spandex
Fine quality polyester etc.
Shahi has its own fabric dyeing and processing unit in Ghaziabad by the name of Sarla Fabric
Limited (earlier known by the name of Palm Prints). It is a vertically integrated unit with facilities
of weaving, dyeing, printing and finishing.
Approximately 40000 meter fabric is procured from here. However there are certain constraints:
Limited capacity.
Limitation on the colors and prints that Sarla Fabrics can do.
Fabrics like georgette etc. cannot be processed here as they do not have jet dyeing ma-
chines.
140
Sometimes, greige fabric is purchased and then it is processed at Sarla Fabrics.
Shahi is renowned for making all shipments on time. One of the significant reasons for this is that
it has its own fabric unit where it can prioritize its work according to the need. Most of the
exporters face this problem of receiving the fabric late and hence facing delayed shipments.
(Fig 1.6)
Other sources
Automatic and power looms
Salem
Coimbatore
Erode
Mill made fabric
Vardhman
Arvind
Nahar
Shyam Tex
Ashima
SUPPLIERS
The main markets for fabric supply for Shahi are Delhi, Panipat, Amritsar, Salem, Mumbai.
Some of the fabric suppliers of Shahi ( for both sampling & Production) are:
141
Muthu Corp, Erode
Picanova fabrics pvt ltd, Mumbai
New Diamond Woollen mills, Amritsar
Mafatlal Industries Ltd, Nadia
Ramkumar Mills Pvt Ltd, Bangalore
Netflex India Pvt Ltd, Mumbai
Priyanka Fabrics, Salem
Bhuvana Fabrics, Erode
Vincord Textiles, Delhi
Vijai Fabric Connection, Erode
L.K Woollen & Silk Mills, Amritsar
A.P Khanna & Sons Pvt Ltd, New Delhi
Himgiri Textiles, Faridabad
Rajindra Handloom Pvt Ltd, Panipat
Shiv Shakti Furnishing Pvt Ltd
KCS Fabrics Pvt Ltd (handloom, jacquard upholstery & curtains)
Maurya’s, Delhi
Parkash textile Mills, New Delhi
Charu Enterprises, New Delhi
R.G Jindal & sons pvt Ltd.
The thread suppliers are:
Coats
Vardhaman
Pashupati
Oswal
Shahi has an in-house testing lab for measuring GSM, color fastness, rubbing fastness, Dimensional Stability, stretchability and testing others properties of fabrics
For labdips, strikeoffs and other approvals, fabrics are sent to testing laboratories like:
142
MTL
ITS-International Testing service
PROCESS FLOW FOR ORDERING OF FABRIC
(Fig 1.7)
Before placing an order, the sourcing department analyses all the vendors and selects the best one.
All the fabric purchases need an approval from the Managing Director before placing of the
order.
(Fig 1.8)
143
Development
- Buyer specifies fabric quality and specifications
- Requirements of designers
Quality selected
Approval of quality
(count, construction, look, hand feel) through lab dips, strike offs and desk looms
Fabric ordered
Take quotation and delivery from all vendors
Check past records for quality of vendors in case of similar prices
being offered
Price negotiations with selected vendor
Approval from MD
Order placed
LEAD TIMES
Based on the lead times for procurement of fabrics, it is decided whether it is feasible to complete
the order on time or not.
(Fig 1.9)
Greige fabric: If it is of regular quality like 60’s cambric or voile, it can directly be picked
from the market otherwise the average lead time in India is 40-45 days.
Processing of fabric: It takes around 10-20 days. So after purchase of greige fabric and its
processing, fabric is in house after about 50 days.
Yarn dyed fabrics: Yarn dyed fabrics have a lead time of about 30-40 days.
Mill made fabrics: Lead times are from 35-60 days.
Imported fabrics: If greige fabric is available then it takes 10-15 days (for processing) + 20
days (for clearances shipping etc.) and if greige fabric is unavailable, it takes 30-35 days +
20 days.
PURCHASE & LOGISTICS DEPARTMENT
The Purchase & Logistics Department is responsible for the sourcing of all the accessories
required by the company. This ranges from trims that go into the making of a garment to items
required for the general functioning of the unit.
144
Merchant places order to fabric sourcing
Production cut date (PCD) asked
According to PCD (on PCD, 40% fabric should be in house) and lead times, feasibility is decided
Divisions
Purchase : responsible for sourcing of the following accessories from domestic markets:
– Cartons
– Carton tapes
– Stationary
– Chemicals
– Fusing
– Elastics
– Thread
– Labels (domestic)
– Other daily requirement items
Logistics : responsible for the sourcing of the following:
– Buttons (both domestic and imported)
– Laces
– Tapes
– Sequins, beads etc from local markets
– Polybags
– All imported trims (hangers, labels, zippers etc)
145
WORKFLOW OF THE PURCHASE AND LOGISTICS
DEPARTMENT:
(Fig 1.10)
PROCESS :
All the requirements related to production department are taken into consideration. These
requirements are forwarded to the Purchase & Logistics department through MOVEX.
With the help of MOVEX it comes to know the requirements of the production department
and the order is placed accordingly.
The codes are generated against each order in MOVEX and according to these codes
requirements are generated.
Purchase & Logistics department checks the quantity of accessories in its previous record
to see if there is any balance. It then orders the remaining quantity.
The items are received by the Accessories Store.
146
Requirements sent by merchandiser
Requisition sent by the system
Items counter sourced, options submitted with prices
Items are approved by the merchandiser or by the buyer
Once the order is confirmed, options are chosen
buyerSourcing
buyerQuality, price and lead time play an important role in sourcing
buyer
The discounts received on the purchase are
Cash discounts
Bulk discounts
NON FABRIC STORE
Accessory Store of Shahi is centralized, for all fabrication units.
They have their main accessory store at the Faridabad Unit, from where accessories are
issued to all other units (substores).
Purchasing of Accessories is also centralized.
The accessory store is sometimes referred as Non-Fabric Store because it does not only
store accessories, but also various requirements like stationary, machines, spare parts,
grains, sugar, etc.
Basic procedure for receipt of goods at the accessories store is as follows:
(Fig 1.11)
147
Marketing prepares BOM (Bill of Materials) when order is finalized
The entries are fed in Movex
These entries are reflected in purchase
Sourcing is done on the basis of costing given by marketing
According to the delivery date material is sought (Average lead time is 45 day before PCD i.e. planned cut date)
Accessories are received at central accessory store.
PCT
Likewise, when need of other items arises, it is communicated to the purchase department which
places the order and the goods are then received at the non fabric store.
The central accessories store (non fabric store) has direct contact only with the sampling
department otherwise individual departments contact the sub-stores only and are not allowed any
direct contact with the central store.
Any of the accessories which fails to pass the quality checking is returned to the supplier. Also in
case excess trims are accessories are left over after their requirement is fulfilled, they are disposed
to suppliers or are sold at discounted prices.
148
PROCESS FLOW OF AT THE NON FABRIC STORE
(Fig 1.12)
149
Requirement of material arises
PCT
Challan issued
PCT
Supplier invoice received with the goods (bill +PO)
Random checking (visual) at gate by physical receiver and security
Checking of trims by quality checkers (Checked according to specification. Min 5% checked, 10%,
15%......100%)
System entry done in movex
Observations of quality checking maintained in material receipt cum
inspection report
Accessories stored in particular bin (location so that they are easy to track)
Material issued to substore
PCT
TESTING LABORATORY DEPARTMENT
Shahi has an in house testing laboratory where the following equipments are available for the
testing to be carried out:
Paramount Digi strength
Purpose: Finding the tensile strength of fabric. Also it is used for testing seam strength and
seam slippage.
Suitable for: Wovens only (Minimum sample size = 6” X 4”)
Capacity: 250 kg
UBIQUE Bursting strength tester
Purpose: Finding the tensile strength of fabric
Suitable for: Knits only
Capacity: 250 kg
FB push-pull scale
Purpose: It is a pull strength tester for determining the pulling strength of trims attached to
the garment
Suitable for: Trims like buttons, hooks, loops, snaps etc. Different types of grippers are
available for different purposes.
For example: The buttons must be able to withstand the recommended strength of pull for
about 10 seconds which is 15 pounds for garments meant for adults and 17 pounds for kids
wear.
Paramount tearing strength tester (as per ASTM D1424)
Purpose: It is used for determining the strength a fabric can withstand before tearing after
an initial cut has been introduced
Paramount Crockmeter
Purpose: It is used for determining the rubbing fastness of fabric.
150
Process: Bleached white fabric is mounted on the machine which is rubbed against the
darkest area of fabric for about ten cycles and the staining on the white fabric is measure
with the help of grayscale.
Digital Balance
Purpose: It is used to measure small amount of weights with precision for eg: yarn count,
gsm etc. It has a sensitivity of 0.0001g.
GSM sample cutter – Paramount
Purpose: It is used to cut a fabric sample with a fixed diameter i.e. 11.56 cm which is used
for measuring the gsm of the fabric. The sample cut (represents 0.01 metre square) is
weighed on the digital balance and the reading observed is multiplied by 100 to get the gsm
of the fabric.
Projection balance
Purpose: It is for finding the fibre content of the fabric. Different fibers have a particular
structure by which they can be identified.
PHAN pH meter
Purpose: It is used to find the pH of the fabric. Acceptable range of pH is 5-8. However the
acceptable range varies from buyer to buyer.
Process: 250 ml of water is boiled and 10 g sample is put in it. Boiling is further continued
for 10 minutes. The water is cooled to room temperature and sample is removed. pH meter
is dipped in this water and pH button is pressed. It then displays the pH. Wet processing is
redone in case pH is not within the prescribed range.
Hotplate
Purpose: It is for heating purposes.
IFB front loading washing machine
Purpose: It is for determining the response to washing for garments or fabrics. It helps in
testing the dimensional stability (shrinkage, extension).
151
Process: Washing cycles are introduced for garments for 45 minutes as per wash care
instructions and after that the sample is viewed for physical changes of color, size and
appearance. Multifiber cloth is attached to determine color fastness.
Paramount Launderometer
Purpose: It is used for washcare development. It is a stronger machine and is five times
more effective as compared to the IFB washing machine which is milder.
Paramount Digilight
Purpose: It is used for testing the light fastness property of the fabric/garment.
Hot air oven
Purpose: It is used for drying or calculating moisture regain etc
Lexus steam line steam iron
Purpose: It is used for pressing the fabrics swatches when calculating shrinkage.
A TRF form is to be filled and the sample is to be sent for testing to the lab. Fiber content,
GSM, Color fastness etc can be teated in-house only.
152
FABRIC STORE AND INSPECTION DEPARTMENT
Fabric store at Shahi, Faridabad is a centralized store for all units in the NCR.
When the fabric is sourced and brought to the company, they are stored in the factory’s
fabric storage area and it is the responsibility of fabric stores department.
From here, the fabric is taken for inspection and then stored in specific locations from
where it is issued for cutting.
The fabric is stored lot-wise.
Rolls of fabric that are of similar shade are kept together.
After the fabric sourcing department places order for fabric, the production fabric is
received by the fabric stores.
When the goods come in, supplier invoice is received. It has the following details: -
1. PO number
2. Number of rolls, color, length, width
3. Dispatch quantity
The goods are then offloaded and stored in receiving location.
The fabrics are then sent for inspection after which they are stored in separate racks
according to whether the fabric is accepted or rejected.
The rejected fabric is returned back to the supplier.
The accepted fabric is also stored in specific locations.
They are allotted a bin number and are stored accordingly so that they can be easily located
whenever required.
Also a bin card is maintained which has details of the fabric received, where it has been
issued, how much is issued and how much is left with the store.
After receiving, the fabric inspection is carried out. The fabric is checked 100% barring the
following situations in case of which it is checked only 10%:
1. If it is from some buyer nominated vendor.
2. If it is imported.
3. If it is from SFL. In this case, only 10% of fabric is checked because the fabric is
checked at Sarla Fabrics before it is dispatched.
153
DOCUMENTATION DONE DURING RECEIVING
ICR – Incoming Receiving
GRN – Goods Reeceiving Number
Bin no. – Place of storage like racks
Bin Card – It tells us about the detail of the fabric received, to whom which has been
issued, how much is issued and how much is left with the store.
Once the fabric is received, the quality department inspect the fabric for defects.
The fabric is checked 100% barring the following situations in case of which it is checked only
10%.
1. If it is from some buyer nominated vendor.
2. If it is imported.
3. If it comes from SFL.
(The fabric procured from SFL is checked 100% before it is dispatched.
On reaching Shahi, only 10% of it is checked.)
Erudition:
Fabric Inspection is very crucial.
Proper Lot separation must be done.
Center to selvedge is a major constraint for cutting.
The operators who do shade sorting undergo a hue eye-test.
WORKFLOW OF THE FABRIC STORE AND INSPECTION DEPARTMENT(Fig 1.13)
154
155
No
Yes
Fabric in-house in store
Uploaded in system by floor incharge
Goods Received Note provided by store incharge
Physical and technical counter check by goods received note
Report to DMM/Fabric sourcing department
Test by lab
Is fabric imported/mill made?
100% lotting 100% lotting
100% audit of each lots
10% random audit of each lot
Report consolidation
Report to DMM
Report accepted?
Uploaded in system
Report to fabric store
Uploaded in system
Return fabric to party
Ready to cut
Rejected
AcceptedYes
No
End
Start
YesNo
Report to fabric store
If acceptable
FABRIC INSPECTION
For the purpose of inspection of fabric, four point system is followed which allots different points
for different lengths of defects. The defects are marked by different stickers as shown in the
following table:
Table 1.3
Points Defect Sticker
1 0 to 3” Green
2 3 to 6” Yellow
3 6 to 9” Blue
4 9” to above (Full Width) Arrow sticker
Total points per 100 square yard are calculated. Different types of fabrics have different passing
points. They are as follows:
1 Grey fabric – 20 points/100 m
2 Powerloom fabric – 44 points/100 m
3 Imported/millmade fabric – 25 points/100 m
MACHINERIES:
The inspection is carried out manually as well as by machines. They have the following machines
for inspection:
12 tables to check the fabric manually with the provision of 4 tube-lights horizontal to the
table
2 automatic machines (RAMSONS) which had a provision of light at the base of surface
and on the top.
156
WORKFORCE
13 checkers
13 assistants
13 helpers
4 staff member
COMMON FABRIC DEFECTS WHICH OCCURRED IN THE FABRICS:-
Centre selvedge
Length wise color variation
Haziness
Patchiness
Stains
Color fly
Crease marks
Fold marks
Weaving defects
o Double pick
o Double end
o Broken end
o Missing end
o Slubs
o Thin place
o Thick place
o Neps
Chalk marks
Holes
Patta
157
Fabric Audit Procedure
Non denim
1. Receive the fabric from fabric store.
2. Compare the fabric with original/buyer approved swatch for design, shade etc.
3. Audit 10% Fabric in case of imported/millmade fabrics and 100% otherwise.
4. 4 points system is followed for marking of defects, which is as follows:
5. Colored stickers are used for defects of different points:
6. Mention the face & back of audited fabric with stickers on one swatch which is to be
attached to be given to cutting.
7. Prepare the shade band of printed & solid fabric.
8. Swatches of shade wise lots of every fabric that is being audited is shown to concerned
authorities.
9. If both fabric audit & lab audit reports are ok fabric will be issued to cutting.
Denim
1. 50 X 50 cm. Swatches are received by Q.A.D. through fabric store.
2. Marking is done by fabric store person with the help of templates.
3. After this marking, 10% to 15% swatches are cross checked for correct marking.
4. These swatches are sent for over locking & after that to washing dept.
5. On receiving swatches (which had been cross-checked for correct marking) is done with
the help of shrinkage scale.
6. After this, ironing shrinkage is also considered for the above mentioned swatches.
7. Acceptable shrinkage value are from 0/0 to –3/-3% (warp/weft)
8. No positive shrinkage value is acceptable in both warp/weft.
9. Swatches, which do not have shrinkage value between 0/0 to –3/-3 is sent for re-washing.
10. Re-washed swatches are again marked & rest of procedure as mentioned above is followed.
11. Finally those swatches which do not have shrinkage between 0/0 to –3/-3 even after re-
washing are rejected & reports carrying these roll numbers (rejected swatches) are
forwarded to concerned authorities.
158
FABRIC QUALITY CONTROL INSPECTION REPORT
It is the inspection report of the fabric when it is received in Shahi.
It consists of supplier name, fabric code, meterage received, meterage inspected,
construction etc. it has the following details:
1) Bale no.
2) Meterage in stickers.
3) Actual meterage
4) Actual width (min, max)
5) E.P.I
6) P.P.I
7) Penalty points in Weaving faults
8) Penalty points in dyeing and printing faults
9) Penalty points in weft bars/ shade defects
10) Penalty points in stubs/stains/holes.
With this information it is decided whether the fabric it to be accepted or rejected, or if some
compensation is to be taken.
159
FABRIC A UDIT SOP
Received fabric from store with p.o no and grn no.
Cut 1 meter fabric from each lot/color for lab testing.
Cut 6” pieces across the width and fabric shading checked side to side and end to end.
Fabric checked as per 4 point system basis:
Points system:-
0” to 3” ------------------- 1 point – green sticker
3” to 6” ------------------- 2 point – yellow sticker
6” to 9” ------------------- 3 point – blue sticker
9” to above ---------- 4 point – arrow sticker any hole
-------------- 4 point – arrow sticker
Pass point per 100 meter:-
For greige fabric --------------------------- 20 point
For power loom fabric ----------------- 44 point
For mill made fabric --------------------- 25 point
Make the audit report and issue to cutting if audit and lab report are pass
Keep fabric swatches for reference.
Lot no. 100 shows rejection and red sticker put on reject fabric.
White sticker put on pass fabric and item no, roll qty,
Width, lot/shade no, roll no are marked on each sticker.
CUTTING DEPARTMENT
160
The cutting department at SHAHI , Faridabad is a centralized cutting department for
all the units in the NCR.
Automating spreading and cutting facilities are available here.
After the confirmation of the order, merchant send two reference files containing all
details of the order to the order analysis department.
The OAD department, after studying the styles and making the style analysis report,
hands over one file to IED and other to cutting for production.
The Cutting floor of SHAHI Exports is one of the largest in India.
The Cutting floor is in the lower basement and includes the following departments:
The Fabric Store
Central Accessory Store
The Spreading & Cutting Area
The Fusing Area
The Bundling and Ticketing Area
The Computer Embroidery Department
Thread Cutting Area (for Embroidery)
Total Area: 16878sq ft.
161
WORKFLOW OF THE CUTTING DEPARTMENT:
(Fig 1.14)
162
Sample cutting
Fabric receiving from stores
Recording of fabric as per lot/shrinkage/width
File, sample received from OAD
Cutting approval
Cut order issue
Receiving of marker
Layering
Cutting (CAM/manual)
Checking
Numbering
Pass
Bundling
Quality audit
Dispatch to stitching unit
Embroidery (if required)
Fusing (if required)
Re-cutting (if required)
Technical Specifications (Appendix 1.3)
Machine Details (Appendix 1.4)
Workforce Details (Appendix 1.5)
Infrastructure Details (Appendix 1.6)
Marker making
The markers for the purpose of cutting are made by the CAD department. This marker is made
keeping in view the costing average quoted by the merchant to the buyer. In case patterns have
been made manually, the patterns are digitized to transfer them to the system and then a marker is
made.
In case of CAM cutting, marker is sent to the cutting floor in floppy and in case of manual cutting, actual
size marker is obtained through the plotter available. The specifications of the plotter available are:
Machine Model Make Number
Wind Jet Plotter Windjet/ Plo/ 180 Algotex 1
SPREADING
163
The spreading of the fabric was being done manually as well as using an automatic
spreader.
Brown paper was laid and taped before spreading for all fabrics in both types of spreading.
This was to protect the fabric from rough spots on the table surface. It also enabled the
spread to be moved as required (due to low friction) and also it prevented the lower plies
from distortion by straight knife while cutting.
Only one operator could carry out the spreading using the automatic spreader whereas three
operators were involved in manual spreading.
In manual spreading, one operator pulled the fabric from roll and the two others took this
fabric to the required length (of spread). On reaching the required length, they aligned the
edges and placed a weight on it. Both these operators return back and while balancing the
fabric and the third operator balance the fabric near the roll and in the end he cuts the fabric
with scissors or end cutter.
In automatic spreading, the spreader fixed the ply of fabric with the help of movable
catcher. Laying then started with the spreader smoothening the layer with the help of a stick
as he traveled on the traveler attached to the machine. The end cutter cut the fabric and
fixed end catcher caught the ends of the ply at the other end
During the spreading process, a layer chart was maintained which kept a track of meterage
consumed and end bits left. The spreading process is followed by placement of the marker
on the top ply.
To secure the marker on the lay, it was torn at different places and a tape was put there.
ERUDITION: Quality considerations for spreading
There were check points for inspection of spreading quality for the QCs where they check
spreading defects such as leaning, uneven tension, and misalignment of plies, bowing,
skewness, & fabric defects.
Fabric where stripe or check matching has to be done is done along the lines of the thread
which are tied exactly perpendicular to the table length.
For napped fabrics like corduroy, twill weave, denim, velvet, some prints & plaid, the
spreaders were instructed to take extra care while spreading and were spread manually.
164
In case of fabric defects, the fabrics were sent marked with stickers in colors contrasting to
the fabric color. If the defect was minor it was ignored. However in case of major defect
they remove the flaw.
In case shade variation within the roll, part with the varied shade was removed.
In case of narrow width fabrics, if the defect was within the roll, they aligned the selvedges
of one side while the other end across the width was left as it was. For too many inconsis-
tencies, the QC in charge was informed & according to the severity of the problem, CAD
marker of the shorter width was ordered.
CUTTING
Before the starting of the cutting process the marker setting was done.
The cutting of fabric was done manually as well as by machine (Computer Aided Manufac-
turing.
Manual cutting was done with a straight knife for all fabrics. For smaller parts like collars,
pockets, collar bands etc. blocks were cut which were then recut using a band knife. Two
cutters were involved in cutting a lay.
There was helper alongside who collected the waste bits of fabric in a bin in order to
prevent the floor from getting dirty and to create enough free movable space for the cutting
knife.
The cut parts were shifted & tied by a helper. The tied parts then collected in a polybag ,
and then they were sent for ticketing. These were later dispatched to the production floor
upstairs through a lift specially meant for carrying cut parts.
Drill machine is also used if marking like pocket marking on front is required.
In case of CAM cutting, since there is no marker on the cut parts, marking of parts prior to
cutting becomes essential to have a reference after cutting. Each part on the CAD marker
was torn off neatly from the centre to accommodate pasting of small stickers which had
info such as:
Job order Style Number No. Of plies Lot number Size Layer number
165
Emb number No. Of parts
2 air channels on the bottom side of the table surface along on the bottom side of the table
surface along with 112 air nozzles per square meter.
Five blow motors per table, each supplying air to a particular zone of the table
ERUDITION: Quality considerations for cutting
The QC compared the hard pattern to marker paper to ensure the accuracy of the marker. The
tolerance for this was nil.
The cut parts from top ply & the bottom ply were matched in order to see whether they had
been cut properly. The bottom ply sometimes got distorted due to constrained movement of the
knife. In such cases the plies were later cut with hand shears.
There was also a check for ragged or uneven cutting. The QC instructed the cutter to correct it
there & then.
The notch location was supposed to be checked by placing patterns over top ply. The tolerance
for this was +/- 1/8 of inch.
166
(Table 1.4)
Lot Size or Quality Being Audited1.5 A.Q.L.
Inspect Accept
Less than 151 8 0
151 – 280 8 0
281 – 500 32 1
501 – 1200 32 1
1201 – 3200 50 2
3201 – 10000 80 3
10001 – 35000 125 5
35001 – 150000 200 7
150001 – 500000 315 10
500001 and Above 500 14
DOCUMENTS USED
Requisition Slip: This was issued by the cutting Dept to the fabric stores specifying the
quantity of fabric they required for the Dept. It specified info such as:
Quantity in pieces
Ratio required
PO/Style.
Cutting Order : This document contained information about cutting order for a particular
style. It has information about item number, country, style number, delivery date, size,
color, and order quantity and fabric width.
167
CUTTING AUDIT PROCEDURE
Auditing procedure in cutting starts from the stage when the sample is given by production for
auditing.
Sample Audit
Following are the documents required for the sample audit.
Pattern
Original sample
Spec sheet
Style analysis
Lab test report of fabric
Fabric audit report
Patterns are checked as per the spec sheet and style analysis. Fabric audit report & lab test report
are analysed to foresee the problems that can come in any of the garment manufacturing process.
Cutting is checked as per the patterns. Pattern of all the sizes is checked to counter any errors in
grading.
Online auditing
When the layer is being layed fabric is inspected for any possible fabric defect that can af -
fect the appearance of the garment. Lab test report & fabric audit report is checked.
Parts of fabric with major defects are removed
While spreading check that there are no creases.
Check that layer length is 2 cms more than marker length
Check that fabric cuttable width is ½” more than marker width and lay height is as requires
layer height, width of layer & the marker width.
Marker is checked for missing part, direction of part, marker width as per the fabric width
& any other possible discrepancy.
Cutting quality is checked for the following defects.
168
o Measurements
o Miscut
o Check plies
o Check matching
o Rugged edges
o Weaving defects
o Selvedges
o Notches
Final auditing
First step in final auditing is to verify the bundle & the layer chart details compati -
bility.
Layer numbering is cross-checked & po, style is confirmed.
Cutting quality audit is done with the help of patterns, specs & original sample.
Checking of fabric flaws.
SYSTEMS FOLLOWED IN CUTTING
Marker checking before cutting.
Part changing of fabric flaw pieces during numbering.
Checking of cutting by production after numbering for bundling.
Cross- checking of weight variation by auditors.
Putting of main sticker on the layer before cutting.
Send product file to units along with first cutting.
Sending of fabric audit & lab test report to unit.
Sending of shade band to units.
BUNDLING AND TICKETING
169
Ticketing is done with the help of ticketing guns.
Tickets carry information regarding the lot no, layer no, ply no etc.
Ticketing is done manually.
Every bundle has a tag which contains the entire description of the garment.
In case of fabric when the ticket can not be stuck to the parts, extra space is left in the
pattern for ticketing purposes.
In case of cut parts going for embroidery or re-cutting, which require excessive hand-
ling, ticketing is done in with ink in empty area of the block.
The color of the sticker is according to the fabric shrinkage %, which is as follows:
(Table 1.5)
Shrinkage Percentage Sticker Color
0.5 White
1.0 Yellow
1.5 Blue
2.0 Pink
2.5 Green
3.0 Orange
3.5 Grey
4.0 Red
After ticketing is complete, cut parts go through an audit and finally are tied into
bundles of 20 pieces each
170
FUSING:
MACHINE DETAILS:
No. of Machines : 2
Make : Fiblon, Hashima
Voltage: 449 V, 3P 50/60 Hz
E/Power: 15 KwH
Pressure: 1-5 kg/cm³
FUSING USED:
Thick
KF- 36
KF- 79
KF- 546
KF-246
Light
FX-1008
NX-100 and FX-100 are available in different colors – black, charcoal, white and off white.
171
FLOW PROCESS FOR FUSING
(Fig 1.15)
172
Style Information as Production File
Mock Preparation of Fusing Sample
Mock Washing of Fusing Sample
Make Internal Test Report
Internal Test OK
Production Starts
Check Machine Parameters
If Correct
Continue Production
Audit Fused Parts
Is Audit Pass?
Issue to Dispatch
Reset Machine
Call Maintenance
Inform QA Executive
Inform All Concerned
100% Checking of Lot Again
Parts Replacement for Rejects
Yes
No
Yes
No
COMPUTERIZED EMBROIDERY DEPARTMENT
The computer embroidery department is centralized. Shahi has largest embroidery facility in ASIA.
The manual embroidery is mainly outsourced.
The merchandiser takes the art work from the buyer
Pieces to be embroidered are first cut and ticketed and then they come for embroidery.
The cut pieces bear the lot number, size and serial number of that style so that after
embroidery it can be rearranged to avoid shade variation problems in the garment.
In case the panel to be embroidered is too small to fit into the frame, strips of fabric are
stitched around it to make it fit into the frame. This is done before the pieces are sent to
the CED.
The design is punched into a floppy by the CAD department which is the loaded on the
computerized embroidery machine. This is done using the WINGS software.
Stitching as well as embroidery threads are used which come from reputed
manufacturers like Vardhman and Coats.
For different types of patterns and different sizes of cut pieces, different sizes of frames
are used
Rough fabric is attached with the main fabric and some buffer is taken to save fabric
and to avoid puckering due to looseness.
173
COSTING-
It is done on the basis of the number of stitches. (approx 1Re per 1000 stitches)
For small logos the costing is done frame wise.
STITCHES-
E Stitch
Zig Zag
Lockstitch
Satin
Chain
Cross
Run
Depending on the style the stitches are done.
174
WORKFLOW OF THE EMBROIDERY DEPARTMENT:
(Fig 1.16)
175
Machine room planning of machines
Design analysis
Bulk cutting receiving
Received embroidery swatch/ thread shade card & placement
Receiving trims and cutting
Sample making and OAD approval
Layer numbering
Parts sewing and patch cutting (if required)
Machine room loading
Framing
Machine running
Inline checking
MACHINERY DETAILS
176
Sorting
Thread cutting
Checking and alteration
Bundling
Quality audit Recheck
Dispatch
Pass
Fail
Make Model No. of m/c
machines
No. of heads Area
Barudan BENSH-YN18 20 20 30x60 cm2
Barudan BENSH-YN18 6 18 40x80 cm2
Multi head machine specifications
Number of needles per head = 9 (Therefore it can process 9 colors)
Distance b/w heads: 30 cm
Speed of machine = 750 rpm (average), 900 rpm (maximum)
Capacity: 5200 million stitches/ month
Stitches/hour: 20000-25000
Software used: WINGS
Some of the features of the machinery are listed below:
Top thread sensors Split pressure foot for easy threading Individual thread clamping system to hold thread in place to prevent pull outs Automatic thread/needle break detector Under head light Automatic colour change Automatic thread trimmer Built – in 3.5” disk drive Automatic speed control ensure optimum stitch quantity
Miscellaneous
Frames are used for holding the garment from all sides firmly so as to prevent the fabric
from going down with the needle or accumulating into folds. They are of different sizes and
shapes. They may be:
-Circular or
-Rectangular
Maximum Dimensions of design frame: 59cm x 25cm
Minimum dimensions of design frame: 7cm x 7cm
177
Bobbin used: IIGM, a franchisee of Barudan
Thread: Polyester trilobal, sometimes rayon, spun polyester (Vardhman, Madura Coats)
Backing: This is a non-woven layer to support the fabric so that it is able to bear the stress of em-
broidery.
Water soluble: It dissolves while ironing and steaming
Paper foam: It dissolves in a single wash.
Needles used: DBK X 5
Manufacturer: Groz Beckert, Bissel, Schmitz
Size: 8, 9 - for voile, cotton and poplin fabric
Size: 11- for corduroy fabric
Size: 14, 16- for denims
Sequence sizes: 3mm, 4mm, 5mm, 7mm, 9mm. Most production feasible are 4mm and 5mm.
One advantage of the machine is its individual head controlling. If embroidery has left at some place then the embroidery program at a particular head can be rewound and executed until it reaches the state of other head. Then embroidery is recommended for all the heads together at the end of the embroidery the panels are passed through needle detector, as there is a high risk of needle breakage in embroidery machines.
WORKFORCE
One operator and framer each for one machine
1 supervisor for every 6 machines
EMBROIDERY AUDIT PROCEDURE
178
Online auditing
Following cross checks are performed by the quality auditor on the machines in computerized
embroidery.
-Cross-checking of blunt needle on the framing table
-Presence of embroidery design on the framing table.
-Cross-checking of the framing needle distance on the framing table.
-Cross-checking of the starting point of embroidery on machine for the conformance of the
placement correctness.
-Visual inspection of pieces on the machine for the detection & rectification of alteration thread
shade.
-Checking of the final pieces.
Final auditing
At this stage auditor inspects the units not only for all the defects, which were audited in online
audit, but also cross checks.
-Embroidery thread shades with approved shade card.
-Audit 10% of production pieces with reference to the approved swatch for the design &
placement.
-Audit of the pass pieces of the checkers for analyzing percentage of defects passed by the
checkers.
-Auditing of the numbering in the layer for any discrepancy. Fortnightly, audit of thread cutting in
embroidery is checked. At this stage auditor checks for numbering on the embroidery panels also.
179
Lot Size or Quality Being Audited1.5 A.Q.L.
Inspect Accept
Less than 151 8 0
151 – 280 8 0
281 – 500 32 1
501 – 1200 32 1
1201 – 3200 50 2
3201 – 10000 80 3
10001 – 35000 125 5
35001 – 150000 200 7
150001 – 500000 315 10
500001 and Above 500 14
DOCUMENTS MAINTAINED
Production charts that detail about time, style and the stitches.
Broken needle Report
WINGS software
It gives
Average thread Stitches Y/Y Physical check
180
INDUSTRIAL ENGINEERING DEPARTMENT
Industrial engineering department is considered the backbone of any garment factory. It plays a
vital role in production of the garment. It involves all other production departments and is
responsible for monitoring performance of the same. It gives technical solutions to the
problems faced during the garment production. It is responsible for improving productivity and
efficiency of different departments
The Industrial Engineering Department, has been divided into two levels according to the functions performed. First is the PDS department which deals with product development stage. The other one is Floor I.E. which is concerned with production stage of the garment.
Functions of the PDS department are:
Calculating SAM from tech-pack
Calculating SAM from the sample
Preparing an operation bulletin by using oracle
PDS updating in ERP software
Making layout according to the OB
Suggesting changes to make the production of the garment easier
i.e. performing R&D
Deciding machines and manpower
Suggesting attachments and folders
Making Pitch diagrams
Functions of the Floor I.E. department are:
Planning review
Arrangement of folders and attachments
Arrangement of machine and manpower a/c to the style i.e. line setting and line balancing
Calculating manpower, efficiency
Setting production targets by helping the PPC Department
181
Carrying out regular time studies to check whether the planned SAM is being achieved or not.
Undertaking Motion studies & method
Monitoring production & providing solutions
Checking the hourly production
The formulae used in calculation are:
Productivity (per operator) Output / No. of operators used
Efficiency (SAM * Production / No. of operators used*480)*10
ERUDITION:
Line Balancing is very crucial to attain on time delivery.
WIP management is very important.
Folders and attachments must be used to increase efficiency
SAM calculation at PDS stage is crucial as it directly affects the costing.
DEPARTMENT WORKFLOW (Fig 1.17):
182
Revised O.B. prepared
Requirement of the machines & attachments is provided to maintenance department 5
days before loading
Line setting according to layoutLoading
Additional operations added
Merchandiser gives samples
Total SAM for costing purpose
Order approval
Sample arrives again to make O.B. & changes recommended
Target production is projected for next 5 days @ 12.5%, 25%, 35%, 45%, 55%
efficiencies respectively
3 days after loading the line, time study is performed
As per the time study, line balancing is done again
Method study is done simultaneously Critical operations are sorted out
183
SEWING DEPARTMENT
Sewing department can be termed as the heart and soul of any garment manufacturing unit. This
department is responsible for the conversion of cut panels into actual garments.
Shahi Exports, Faridabad has a floor set up comprising of 21 lines of around 40 machines
each.
The whole floor is divided into two sub floors, namely; floor A and floor B. The production
capacity of the floors is 2,50,000 units of garment per month.
When a new style comes over; the various information like operation breakdown, sewing details,
critical operations etc is put up on the display board. A sample of the garment is also put up in
front of the sewing line for any type of reference.
Line is set as per line layout plan.
Operations are assigned to the operators according to their skill set.
Required SPI, thread tension and needle no. is set by supervisors and mechanic as per
requirement.
Line in charge & supervisor give the direction to the operators about their respective jobs.
In line checkers and QC’s ensure that the quality coming out of each operation is as per the
quality specification.
Industrial Engineer do the study of operators and their respective operations again. If any
change is needed in the layout and working method for maintaining the quality and
production, immediate action is taken.
184
WORK FLOW OF THE SEWNG DEPARTMENT(Fig 1.18)
185
186
Pre Production Meeting
Size Set Approval
Pilot Run
Bulk Cutting
Lot Bundling in 20 Pieces
Production & QA Meeting
Operation Breakdown
Line Setting
Line Layout
Line Feeding
QUALITY ASSURANCE FOLLOWED ON THE STITCHING FLOOR
The bundles of 20 garment pieces each comes from the cutting department along with the
pattern, product file, product sample and fit sample.
Patterns are checked by a roaming QC ,QA or production technician
3 inline checkers (at each critical operation)
1 final checkers (checks for basic measurements, stitching faults, balancing problems-
100% checking)
Lots are made
Sent for auditing(2.5 AQL system followed by the auditor)
If defects found, sent back for 100% checking and alteration
187
Manual Operation
Sewing Process Machine Operation
Ironing Operation
Checking Process
Inline Checking 100%
Audit as per AQL 2.5
Finishing
Auditing
Final Checking 100%
(Table 1.6)
MEASUREMENT AUDIT AQL 2.5
LOT SIZE SAMPLE SIZE PASS FAIL
1 COLOR 20 1 2
2 COLOR 32 2 3
3 COLOR 50 3 4
4 COLOR 80 5 6
5 COLOR 80 5 6
>5 COLOR 125 7 8
Workforce Details (Appendix 1.7)
Machine details (Appendix 1.8)
188
DOCUMENTATION DONE DURING STITCHING
BROKEN NEEDLE MAINTENANCE RECORD
Replacement of broken needles is done by the feeder only. If any needle gets broken during the
sewing process and the tip of needle is not found, the garment is taken away from the line for
careful metal detection and the broken needle is submitted to maintenance department where one
person is specifically employed to maintain this record.
NEEDLE DISPOSAL LOG
It is used to keep the record of the no. of needle broken by a particular operator, on a particular
machine. The signature of the operator is taken against any such entry.
The idea of returning the deformed needle to get a new one from maintenance is really helpful in
ensuring the needle is not left in any of the garments. If the broken part is not detected by the
needle detector as well, that piece is discarded.
Date Time Order
No.
Operator Needle Found
(broken)
Reject ND/F ND/R Sign
Found : all needle parts are found and registered.
Rejected : all needle parts not found, product rejected.
ND/F : product checked by needle detector, all parts found and registered.
ND/R : product checked by needle detector, all parts not found, product discarded
189
MACHINE MAINTENANCE RECORD
Machine Maintenance card is put up on each and every machine. The machines are maintained
properly on weekly and monthly basis. An immediate corrective action is taken by maintenance
department in case of any type of breakdown. Every machine is cleaned and checked by the
operators before starting the work on machine.
On an average, each line has:
40 machines
8 tables
41 operators
10 helpers
2 supervisors
1 line charge
4 inline checkers
1 line QC
STYLE WISE SAM UTILIZED PER FLOOR
This report tells us the total SAM utilized per line, per style. It utilizes the following format.
Date: __/__/__ FLOOR:
S. NO. STYLE OUTPUT M/C SAM M/N SAM TOT SAM
1.
2.
3.
TOTAL
190
LINE FEED FORM
The feeder of the line maintains a regular record of the no. of pieces loaded per hour. It also
includes the batch no, size and grand total per day.This gives an idea of the no. of pieces of a
particular style fed per hour in a line. If we compare it with the hourly output of the line we can get
WIP of that line per hour or per day. It also helps us in identifying bottlenecks based on the
comparison of no. of pieces as input and that as of output.
PRODUCTION REPORT
This report tells us the no. of pieces from cutting, input pieces in the line, output from the line and
dispatched pieces.
Line
No.
Styl
e
No.
Order
Qty
Cutting Input Output Line
WIP
Dispatch
18 8899 6786 Today Cumm Today Cumm Today Cumm 967 Today Cumm
234 400 56 450 65 312 100 213
INLINE CHECK POINT REPORT
The format given to the inline quality checkers consisted of defects like stain, pencil mark, color
variation, wrong stitch, damage, bowing, weaving, puckering, wrong sized panels, improper
tension, run off, imbalance, joint out, center out, uneven stitch etc. To report any other defect
appropriate space is provided.
191
OPERATOR RECRUITMENT
Operator And Helper Recruitment Procedure
Operator Sewing Test
Operator and Helper Skill Test
Marks Allotment System
Format
Operator Sewing Test Standards
a. High Skill Operator: Should have knowledge of all the machines and should be
working @ 85% efficiency.
b. Senior Operator: Should know at least 2 machines and can perform four operations
@ 85% efficiency.
c. Operator: Should know 1 machine and can perform @ 75% efficiency.
SECTION CATEOGARY GRADE OPERATION
SEWING TAILORS A Attach collar and neck band
Should know all sewing machines and each operation should be done at
85% efficiency
Attach and top stitch sleeve
placket
Collar attach
Collar finish
Top stitch armhole
Kansai front placket attach
Pocket attach
Bottom hem
Feed of arm
192
SEWING TAILORS B Top stitch side seam
Should know at least 2 machines and 4 operations of each @ 85%
efficiency
Top stitch pocket flap
Back yoke attach
Join front and back
Side seam over lock
Hem sleeve
Hem left and right front
placket
Attach label on 4 sides
Run collar/cuff stitch
SEWING TAILORS C Top stitch yoke and back
Should know at least 1 machine and all operations of that machine @ 85%
efficiency
Top stitch shoulder
Hem pocket
Hem cuff
Make pleats
SEWING TAILORS D Attach loop label to body
Should know 1 machine and 1 operation @ 75% efficiency Make loops
Make pleats on sleeves
Bottom stay stitch
All parts stay stitch
193
Incentive Scheme
Incentives are an important part of any labor based organization. It helps boost the morale of
operators and gives them a reason to work. A fair incentive scheme can work wonders for the
organization.
In the following manner incentive was calculated:
The planned and actual efficiency for each style and each line is compared and the incentive
earned per line is calculated as per below:
For Actual Eff > Planned Eff
Up to 5% 20% of the gross saving
5%-10% 25% of the gross saving
10%-15% 30% of the gross saving
Above 15% 35% of the gross saving
Appropriate parameter is selected from the table and incentive amount is calculated using the
following formula:
194
(Rate of Incentive) x (Actual Runtime) x (Manpower Used)
WASHING DEPARTMENT
Shahi's washing department is capable of imparting different finishes such as: hard/caustic
wash, enzyme wash, acid wash, stone wash, bleaching, and softener wash.
The washing machines used are equipped for garment dyeing as well as normal washing. Thus
garment dyeing is also done when required. Dip-dyeing, tie-and-dye is also done here.
An Intranet challan is issued to the washing department by the dispatch department while
sending the pieces for washing.
The washing department issues a hand written challan upon returning the goods after washing.
The recipes for washing and dyeing etc are developed by the testing lab during the testing of the
fabric and then handed to the washing department.
The capacity of the washing department is 1800 kg/day.
RECIPES OF MOST COMMONLY USED WASHING TECHNIQUES:
Normal Wash:
Wetting, 20-20 mins, 40-45 C
Hydro
Tumble dry, 40-45 mins, 60 –70C
195
Enzyme Wash:
Desizing, 20mins, 50C, Desizing agent – 2.5% OWF
Rinse (2 cycles)
Maintain pH (4.5 – 5.5) by acetic acid
Enzyme wash, 30mins, 55-60 C, enzyme – 3.5% OWF
Bleach using hypo (if required to strip the color)
Rinse (2 cycles)
Neutralize with hypo crystal (sodium thio-sulphate) – 1% OWF, 10mins
Rinse (2 cycles)
Softener (silicon 0.7% + cationic 1.0%), 5mins running, 15 mins dip, 45-50 C
Hydro
196
Tumble dry, 60-70 C, 40-45mins
Softener, silicones, enzymes, anti-satin agents, neutralizers, lubricating agents, de-aerating agents,
water softener etc are other chemicals used in washing.
TYPES OF WASHING:
PERC or Dry Cleaning (DC) :
Every product is not subjected to PERC or DC process. Only those products which have stubborn
stains like that of oil and rust undergo this process. Mostly white or light coloured products that are
more vulnerable to staining are dry –cleaned. PERC gives them whiteness as well as shiny
appearance also.
Stone Wash:
This wash uses volcanic rock or pumice stones added during the washing of products to act as an
abradant. A more or less uniform and prominent fading is seen in this wash. The degree of fading
depends upon the product to stone ratio, washing time, size of stones and load of product. Rotary
type of drum is used for about 1-2 hrs. Generally, 1-2 kgs. of stones is used for 1kg of product. It is
usually carried out with enzyme wash.
Acid Wash:
Acid wash is done in a large rotating wooden cylinder filled with thermacol balls that are coated
with solution of HYPO, Zinc and Calcium. These balls rub against the fabric to give it an overall
grainy which is characteristic of denim. Size of ball depends upon the degree of required effect &
type of fabric (for e.g. for knit small size of ball is used while for denim large ones are added.) For
a mixed designer effect, different sizes of balls are used together. The process takes about 10-
15mins and is done at 35-40 oC. This process is also known by names like Moon Wash, Blat Wash,
and Ice Wash.
197
Spray Wash:
This wash is used to fade put the color randomly in from the garment which is hung over vertical
Penequins or pneumatic brushing robo balloons. Spray gun is used to spray KMnO4 to make out
the required design. KMnO4 oxidizes the dye from the applied area hence fading of color takes
place.
Hand Sanding (Scrapping):
It is done with the help of an abrader which scrap of the surface indigo dye from the fabric. This
process is used to create the different sharp line faded effects on the denim products using a mould.
The mould made according to design is put inside he product oh an inflated penequin (horizontal
or vertical). This raises the fabric surface such that it takes the shape engraved in the mould, which
can now be precisely rubbed with aluminum oxide paper manually. During this the fiber loss of
upper surface takes place and hence the required worn out design is created.
Grinder
Grinder is an innovative technique to give the denim a very prominent worn n torn out look by
carefully cutting away either the warp as the weft threads as per the need of the design.
Machinery Details (Appendix 1.9)
Capacity: 2000 kg/day
Shifts : 2 shifts /day
Types of Washes: Hard/Caustic wash, Enzyme wash, Acid wash, Stone wash, Bleaching Softener
washes etc.
198
An internal challan is issued by the dispatch department to the washing department when garments
are sent for washing. Garments after wash are returned along with a hand written challan.
WASHING WORK FLOW
Fig 1.19
QUALITY ASSURANCE
199
Enzyme Wash
Desizing
Detergent Wash
Bleaching
Neutralization
Softening
100% inspection of the washed garments takes place. Once the garments have been dried, they are
checked on the following aspects:
Color
Hand/feel
Measurements (to determine shrinkage)
Stains, etc
Since some variation in the shades is inevitable due to batch processing of garments, the garments
are separated into 3-4 shade lots during the inspection process according to recurring shade. If a
garment has a drastic change in shade, or shrinkage is outside expected range, it is not accepted
and may be reprocessed if possible.
200
FINISHING DEPARTMENT
The finishing floor at Shahi has been divided into five sections: floors A, B, C and D and HFD
(Home Furnishing Department finishing). These floors were almost similar in layout.
Capacity: 1200 pcs/day/floor
Shift : 8 hours
Manpower Status (Appendix 1.10)
Details per Floor (Appendix 1.11)
201
WORKFLOW OF THE FINISHING DEPARTMENT (Fig 1.20)
202
Kaj / Button marking (manually)
Receive goods from sewing
Bartacking
Button hole stitching
Washing
Button attaching
Thread Cutting
Thread suctioning
Ironing
Initial Checking
Alteration (if any)
Quality Audit
Measurement check (10%)
Final checking
Re-pressing
Shade matching
Folding and putting in poly bags
Tagging
Dispatching to packing section
PROCESSES
Size Sorting
Button and buttonhole position in a ladies top can be same for different sizes or different for
different sizes. So, if the button and buttonhole position is different for different sizes, then it is
necessary that the lot should be sorted as per the specified sizes. At this stage the bundles are done
away with and all the garments of a particular style are made into a single lot which may or may
not be sorted size wise. There are separate sorting tables for this purpose.
Buttonhole Marking
After the size sorting has been done, the garment pieces are brought to the Kaj marking tables. The
kaj marking is done with a white colored pencil using a cardboard template. A template has been
stuck near the edges of the marking tables with the help of a cello tape. This template helps in
marking the button hole position. Templates may be different for different sizes.
Buttonholing
The pieces on which kaj marking has been made are put in a plastic basket and brought in the
buttonholing section and buttonholes are made at the marked kaja position. An hourly production
record is maintained for each of these operators and to check the production and backlog.
Button Position Marking
Garment pieces are sent for button position marking after the buttonholing. There are separate
tables allocated for this purpose. The button position-marking worker picks up a garment and
aligns the two front plackets. The worker then places the shirt on the table and lifts the kaj placket
and taking kajs made as reference points, marks the position for button attaching. The position of
button is marked with the help of a white pencil.
Button Attaching
203
The button position has been marked and now the button are attached. Pieces from the button
position marking tables are brought to button attaching section and separated as per the kind of
button attaching stitch to be made. These separated pieces are sent to the respective machines.
Button attaching stitch is of two types namely lockstitch and chain stitch. Each of these stitches
could be further of two types namely cross and straight button stitch. The kind of stitch to be
provided is specified by the buyer.
An hourly production check is kept for the button-attaching operators. As soon as a particular P.O.
is received for button attaching, the machines are allocated for the purpose taking into
consideration the type of stitch required.
Thread Cutting
Uncut threads affect the presentation of finished and packed garments. Therefore, it is necessary to
cut and trim the loose and uncut threads. As soon as button is attached the garments pieces are
brought to tables meant for the purpose of thread cutting.
Thread Suction
Loose thread hampers the presentation of the final packed garments. Hence, to remove these loose
threads the garments are fed into the thread suction machine. To operate this machine one person
holds the garment in the suction area and the loose cut threads are sucked in.
Ironing
Garments are sent for initial ironing after thread cutting. Seam ironing takes place.
Rough Checking
This section plays a very crucial role in ensuring the quality of end garment. Each quality checker
is provided stickers for marking defects, thread clippers etc. Each checker is instructed to check the
garments thoroughly, mark the defects with arrow stickers and also to cut the uncut threads if
found. Every checker puts the pass piece in the plastic basket below the inspection table. It is the
responsibility of the quality checker to take the defective pieces for correction and after correction
put it in the pass pieces basket. The defects found at this stage could be broadly of the following
types
204
a) Stitching defects
b) Stains
c) Weaving defects
d) Button/buttonholing defects
Checker puts his allotted number on each of the garment piece passed by him. Each checker is
monitored for performance. Every time a defective piece is found at a later stage, it is traced back
to the checker who passed it. This checker is then shown his mistake and taught the correct method
so that this is not repeated again. . All these checkers are given regular on-the-job training.
Finishing in charge or supervisors teach checkers the correct method of garment checking.
Alterations and Stain Removal
As soon as the quality checkers comes across a defect, he brings the defective piece to the
operators meant for the purpose of trouble shooting.
An hourly and daily record of the number of pieces altered is maintained. This helps in keeping a
track on the quality of garments being sent to finishing by the production floor. 20-30% is
normally the alteration and stain removal rate. In case of defects like button/buttonhole and
embroidery the pieces are taken back to the respective department.
The stain removal section has facility to remove the following type of stains: oil, yellow, black and
paint spots, stains due to color bleeding, ink, rust, tracing marks, yellow stains, and hard stains.
Final Checking
In this section the overall look of the garment is seen. For the purpose of removal of stains detected
during this stage, each table is provided with a spot washing stain removal gun. Also, each table is
provided with thread clipper to cut the uncut threads. All the defective pieces are sent for alteration
and necessary corrections.
205
Final Ironing
The ironing supervisors analyze the style as per the critical instructions given in the OAD folder.
Based on the ironing instructions, instructions are given to the ironing operators about the correct
way of ironing the garments of a particular style. The hanging trolleys from where the garments
were retrieved for ironing and placed after ironing are ergonomically designed, keeping in mind
the ironing operator’s movement.
Tagging and Packing
The passed pieces are brought to the tagging and packing section on the hanging wheeled trolleys.
It is the responsibility of the packing supervisors to provide the tagging operators with the
appropriate price and brand ticket or tags. As soon as a new style arrives in the tagging section, the
packing supervisor places the necessary tags in the racks provided for this purpose. The tagging
operator is instructed as to where and how the tag has to be placed. The most important thing to be
kept in mind while placing the tag is to match the size mentioned on the main label and the size on
tag or ticket.
Quality Audit
A quality audit is done after the garment is finished. This is one of the most important steps. AQL
of 4 is followed.
206
AUDIT PROCEDURES
Pre Final Audit
After the garment is ironed and checked by the production checkers the lot is then offered to the
auditor for prefinal audit. Auditor picks up random units from the given lot as per AQL sample lot
size. If it is with in the acceptable limits of AQL then the lot is sent for packing and if the defected
pieces exceed the acceptable limit then the lot is sent for rework along with the defect
classification.
Visual audit chart
Table
Lot size Sample size 2.5 Accept0-280 13 0
281-500 20 1501-1200 32 21201-3200 50 33201-10000 80 510001-35000 125 735001-150000 200 10150001-500000 315 14
>500001 500 21
Fit audit
Fit audit is done at the finishing audit stage. In this audit auditor has to measure pieces of each size
of an order. The measurement going beyond the tolerance limit is then highlighted and corrective
action is taken on the same. (Refer format 13 of annexure)
Measurement audit chart
Lot size Sample size Pass Fail1 color 20 1 22 colors 32 2 33 colors 50 3 44 colors 80 5 65 colors 80 5 6
207
>5 colors 125 7 8
Packing audit
Packing audit is done based on the following chart:
Lot size Sample size Pass Fail3-15 3 0 116-25 5 0 126-50 8 0 151-90 13 0 191-150 20 0 1151-280 32 0 1281-500 50 0 1501-1200 80 0 1
>1201 125 0 1
SYSTEM FOLLOWED IN FINISHING
Audit at various stages of ironing, finishing, kaj-button, packing.
For new style initial pieces are studied in all respects along with product file.
All critical points are mentioned on QAD auditing table related to running style.
Feedback/communication to production on regular basis regarding problems in style.
Audit of packing quality.
FINAL AUDIT PROCEDURE
Final statistical audit is performed on a given number of randomly selected boxes from an
identifiable lot.
In final audit auditor selects number of boxes from identifiable lot to inspect. This selection
is based on the square root of the total lot offered for the inspection.
208
Auditor checks for accessories in a garment with the help of product file of that specified
style i.e. hang tag, main lable, wash care lable, button, hanger, sizers, polybag etc.
Auditor also checks carton marking, weight, dimensions, ratio & packing instruction.
All the final audits are done on AQL 4.0 if auditor finds the lot size with in the acceptable
limits of AQL then the complete lot is passed, otherwise in case of defect more than the
acceptable limits, the lot is sent for rework
Erudition:
Finishing is one of the most important departments where the final appearance of the
garment is achieved.
Loose threads are deterrent to business
It is better to remove as many unwanted threads at the sewing stage as possible
Proper carton packing needs to be done for avoiding problems in shipping
209
PACKAGING AND DISPATCH DEPARTMENT
As Shahi Faridabad is the corporate office, it plans and controls all the shipments of it styles in
NCR as well as its Bangalore and Hyderabad branches. The goods from Delhi – NCR Region are
sent from the Mumbai and Kolkata Port and of Bangalore Branch are sent from Chennai port.
PACKAGING
Packaging is the most crucial department product. The packaging has to be very good as it attracts
the customer. Thus the presentation to the customer is very crucial. Also the packaging department
is in a separate area so that there is no common access to it. The records maintained by this
department are essential as the loss of even one piece can cause a major problem.
Records of pieces received from various units which are issued to packaging include the following.
Fabric codes
Swatch codes
Delivery schedules
Records of number of pieces received from finishing department along with their style
number, ratio etc.
Records of pieces shipped along with date, quantity, ratio, mode of shipment, style no, PO
etc.
Each of the carton shipped is labeled with the following information printed on each:
Carton no. Buyer’s logo Company name Style no. Customer code PO No. Measurement of the carton Address of the buyer Date of Delivery
210
Weight Size ratio chart Country of origin
Every country has a different type of sticker. Thus stickers are put on the cartons depending on to
which country the order is going to. Packages containing the first sample, salesman sample, fabric
swatches etc are dispatched to buyers almost every alternate day.
DISPATCH
The responsibility of this department is to monitor the inflow and the outflow of the material to
and from the company. It does the work of receiving and issuing of the material.
Some of the records maintained by this department on the on line system are:
Checklist
Finishing pending
Records
Dispatch receipt
Dispatch issue
Documents which need to be carried by the driver of vehicle carrying company’s goods are:
Form – 31: It is required while crossing state borders. It carries driver’s name, description of
goods, quantity, issuing company’s name and date.
Challan: It carries the PO number, style number and number of pieces.
Stickers Put on the Cartons
Information regarding the carton are printed on a sticker which is then stuck on the carton so that it
can be identified. The information on the stickers was mentioned earlier.
211
DOCUMENTATION
Documentation department of Shahi is centralized for all the units in Delhi and NCR. This
department is divided in two parts namely export and import. The entire data relating to this
department is stored and backed up in a computer system. This department arranges document for
shipping the order on the date of shipment.
This department helps in custom clearance from the custom office following the rules made by
ministries of commerce and finance respectively.
Documents required for the shipment/export:
212
Shipping Bill
Custom Clearance
Certificate of
Origin of Goods
Marine Institute
Certificate of FOB
Invoice, duly
signed
Test Certificate of
Goods
Air Way Bill, if by
Air
Packing List
Purchase Order
Certificate
IEC Certificate
Letter of Credit
GR Form
AR4Form
213
Since Shahi is basically an export oriented unit, its responsibility grows manifold. Sometimes on
buyers’ demand company has to import fabric or trims.
Documents required for import:
Bill of Landing
Bill of Entry
Duty Exemption Certificate, if goods are duty free
Invoice, duly signed
Packing List, duly signed
IGM Certificate, if by air
Import License
Certificate of Origin of Goods
Marine Insurance Certificate, if FOB
Custom Clearance Certificate
Importer Declaration, duly signed
Letter of Credit
Goods Test Certificate
HUMAN RESOURCE
PERSONNEL
The Personnel department is centralized for all the units in Delhi and NCR. This department is
responsible for recruitment, training and deciding the organizational HR policies. It also takes care
of wages and salaries of all the employees.
The main functions of Personnel department are:
Manpower Planning
Recruitment
Induction
Training
Discipline
Sourcing
Salary
Administration
Motivation
Welfare Activities
Company gives the salary to its employees as follows:
Basic Salary + HRA + Annual Increment (announced every April) + ESI (employee state
insurance) + Conveyance Allowances + LTA + PF etc.
Crèche Facility
Shahi, looking at the need of its’ large women workforce has started crèche facility for their small
children. Crèche takes care of children’s food, learning and health.
Medicine Box
In Shahi Faridabad there are various medical boxes (first aid boxes), which are placed at different
locations in the unit, it is very useful as there are various small accidents happening in the industry
every now and then. These boxes are properly maintained and if some medicine is utilized it is
quickly replaced. A person who is responsible and whose work station is near the medical box is
made the incharge of the box, and the key to the box always lies with that person, he/she is
responsible to inform the concerned authorities if some medicine is used fully or expired. That
persons name, phone no and photograph is put on the medical box so that in the case of emergency
he/she could be immediately contacted.
List of the medicines in the box
1. Soframycin
2. Burnol
3. Moov
4. Disposable gloves
5. Eye wash cup
6. Gentamycin eye drops
7. Band-aid
8. Tape roll
9. Bandage
10. Cotton
11. Amrutanjan
12. Forceps
13. Scissors
14. Kidney tray
15. Savlon
TRAINING
Shahi has a very well designed training and recruitment programme designed by KSA
Technopak. Shahi believes in the policy of training their operators in house.
The training programme is for 15-25 days. After the completion the worker is sent to shop
floor in a line especially for trainees or newly trained operators. A full line of 21 machines is
dedicated for training in the sewing department
RECRUITMENT
For recruitment of the operators Shahi takes four tests (3 dexterity tests and 1 vision test). The
tests are:
Dexterity Test:
a. In this test the skill and concentration of the operator is tested. The test happens on a
pencil board. There are 96 pencils in four lines i.e. 24 in each line. The board is divided
into two sections. The applicant has to take out the pencils from the first section and
has to put them into second. The time limit for this test is 2.15 minutes.
b. Another dexterity test is also taken on the same board. Here the applicant has to take
the pencil out, turn it upside down and put it in another hole. The time limit for this
activity is 2.5 minutes.
c. The next test is ball test. A tray is divided into two sections along a small barrel. 25
marbles are placed on one section of the tray. The candidate needs to pick up the ball
one by one from a section, put it in the barrel top, catch it at the bottom and put it in
another section of tray. The time limit for this test is 2.0 minutes.
Vision Test:
This test is also called maze test. It comprise of two parts having 10 lines each. The ap -
plicant has to trace the numbered lines from one end of the maze to the other. The al -
lowed time for one part is 2.0 minutes.
If an applicant does 8 lines out of 10 successfully, he is selected.
217
SHAH I EXPORTS PVT. LTD., FARIDABAD
TRAINING
After the applicant is selected, he or she undergoes an operator training programme that is for
15-25 days. It varies from person to person.
Training Process
a. On the first day the trainee is told about the sewing machine and its parts. Next
5-6 days are for paper exercise.
b. There are six paper exercises that the trainee has to do. These exercises are
mainly to help the trainees develop machine control and handling.
c. For the consecutive 3 days trainees undergo 19 fabric exercises.
d. These exercises involved 9 SNLS, 6 DNLS and 4 O/L machines. It aimed at
giving the trainee better control over fabric and operations like back tack and
bar tack.
e. After these exercises the operators are asked to stitch one complete shirt. Then
they are asked to sit on any machine according to task they can perform. They
are observed by the training supervisor. The time taken by the operators is
noted down
f. A form is filled for each of the operator, which tells about the operator’s skill
in different operations he or she can perform.
g. A graph (no. of days vs. different operations) is plotted for each operator and a
file is prepared which includes the detail of different exercises he has
performed, his skills in various operations and his performance evaluation
details etc.
h. The operator is then sent to the sewing floor in a line, specially designed for
new comers. The supervisor and the line in charge keenly observe the
performance of the operator.
i. The operator remains in this line for 30-45 days and then is made to sit in the
production line for the operations he can perform.
218
SHAH I EXPORTS PVT. LTD., FARIDABAD
COMPLIANCES
There is a separate team which looked after the compliances requirement of various buyers,
they informed the buyer about the various practices, policies of the company and its
infrastructure. They used to supply buyer with relevant compliances related documents like
fire drill record, broken needle maintenance record, policy of child labor etc. They coordinated
with buyer on any query regarding the compliance fulfillment.
Certain rules of some buyers that compliance has to deal with and fulfill:
H&M HENNES & MAU RITZ AB Code of Conduct
It states its rules and compliances of H&M HENNES & MAURITZ AB, which includes
219
SHAH I EXPORTS PVT. LTD., FARIDABAD
1) Ch
ild
lab
our
2) Saf
ety
(bu
ildi
ng,
fir
e,
firs
t
aid
eq
uip
me
nt)
3) W
ork
ers
rig
ht
4) W
ag
es
an
d
wo
rki
ng
ho
urs
5) Fa
SHAH I EXPORTS PVT. LTD., FARIDABAD
- 220
cto
ry
co
ndi
tio
ns(
te
mp
era
tur
e,
hy
gie
ne,
ve
ntil
ati
on)
6) Ho
usi
ng
co
ndi
tio
ns(
i.e.
Th
e
fac
tor
y
pro
vid
ed
SHAH I EXPORTS PVT. LTD., FARIDABAD
- 221
acc
om
mo
dat
ion
)
7) En
vir
on
me
nt
SHAH I EXPORTS PVT. LTD., FARIDABAD
- 222
KOHL’S Safety
Requirements
for Men’s,
Women’s, &
Children’s
Wear
This brand has
some general rules
like
SHAH I EXPORTS PVT. LTD., FARIDABAD
- 223
1) Fastener applications
2) General wearing apparel
flammability
3) Attachment strength
4) Nickel ( metal hardware should not
have any trace of nickel)
5) No sharp points or edges.
6) Zipper safety
224
SHAH I EXPORTS PVT. LTD., FARIDABAD
This brand has defined rules for the entire above like, metal claw top/bottom stop zippers are not
allowed in garments were the claw is exposed.
LI & FUNG Factory Evaluation Guide Book
It includes LI & FUNG compliances like social compliances, technical compliances, country of origin
compliances, machine list, factory photo list, broken needle policy, broken needle record, sharp tools
control record etc.
225
SHAH I EXPORTS PVT. LTD., FARIDABAD
ENTERPRISE RESOURCE PLANNING
The enterprise resource planning software used in Shahi Exports Private Limited is Movex. Earlier
Shahi used oracle based ERP software system to update and circulate the information. Now seeing the
increasing demand for quick management of information and data Shahi updated itself with the JAVA
based application MOVEX.
APPLICATION OF MOVEX
Resource and material planning: combines traditional resource planning solution for scope ,
terminology and theoretical benefits with innovative organizational solutions.
Product data management: stores and reuses information needed by various administrative
processes in manufacturing and distribution companies.
Project management: improves the project management in terms of dates, plan and different
other industries.
Financial control: handles all aspects of the controlling requirements so that one can analyze,
plan and display detailed management views of key business processes.
Manufacturing: combines flexibility and deep functionality with an ability to support a wide
range of different manufacturing environments and strategies.
Maintenance: provides an advanced maintenance application with extensive functionality
designed to support wide ranging business needs.
Financial management: is a flexible, internet enabled system that handles all aspects of
financial management and enables you to utilize the crucial information that drives today’s
business decisions.
BENEFITS OF MOVEX
It manages machines and financial assets for current and future business efficiencies.
Movex ERP contains a number of powerful tools for managing enterprise resources such as
human skill, machinery and equipment, financial status etc. It includes dynamic solution for
integrating global multi unit organizations using different currencies, languages, business
principles and legal aspects.
226
SHAH I EXPORTS PVT. LTD., FARIDABAD
Movex is seamlessly integrated with Movex Customer Relationship Management and Movex
Supply Chain Planning & Execution and thereby provides the ability to boost revenues through
increased timely sales and an efficient supply chain. In addition Movex provides an online way
of controlling financial situations which is a must in the economy prevailing.
Movex provides with a foundation to efficiently manage and control internal resources and
finances, thus allowing focusing on maximizing revenues and customer satisfaction. For
instance Movex Maintenance manages machinery and equipment assets to ensure that proactive
maintenance is carried out, which minimizes downtime cost and low product quality.
Another application, Financial Controlling and Management, enables to plan and follow up on
financial resources to support future business growth or change. Product Data Management
enables to share valuable information about products in processes such as sales, manufacturing
and planning.
INFRASTRUCTURE & PLANT LAY OUT
Shahi has 4 floors including the basement area.
There is an electronic lift (of OTIS) for mobility purpose.
227
SHAH I EXPORTS PVT. LTD., FARIDABAD
The floors are categorized as :
-1 for basement
0 for ground floor
1 for 1st floor
While exit from the lift at basement first comes-
Sampling department
Then CAD
OAD
Cutting, Spreading, fusing & Computer Embroidery Department
Fabric & Accessory stores
At ground floor level comes-
Main reception & Lobby
Merchandising department (I)
Fabric, Accessory purchase department & Industrial Engineering department
Finishing & packing department.
Crèche
Finishing floor is categorized as Floor A, B, C & D.
Outside there is the Testing lab, ATM of citi bank.
At 1st floor comes-
Design cell
Showroom
Merchandising department (II)
Reception ( for telephone operators)
Personnel department, accounts, EDI, transport & all administration units
Canteen
Waiting rooms
228
SHAH I EXPORTS PVT. LTD., FARIDABAD
At the top most floor is the production unit- Floor F1 & F2.From entry through the main gate, first
comes a temple maintained by Shahi, then, comes the parking areas for employees. There is a good
pollution free environment maintained at Shahi with lush green lawns, fountains etc maintained by the
Horticulture department.
Ladies & gents toilet are provided at every floor.
LAYOUT
FLOOR DEPARTMENT
BASEMENT
Sampling Department(Pattern Making,
Cutting, Stitching,Embroidery &Finishing),Sampling Fabric Store,
Sampling Accessories Store,Cad & Cam Department,
Quality Department,Multi Head Embroidery Machine,
Production Cutting & Spreading Machines,Fusing Machines, Stitching Department,Production Fabric Store & Trim Store.
GROUND FLOOR
Merchandising DepartmentHome Furnishing Showroom,
Design Room,Fabric Department,Trims Department,
Purchase Department,Planning Department,
Production Finishing & Packaging,Washing Department,
Dyeing Unit, Laboratory,Workers Canteen,
MOVEX Study Center,Conference Room.
1st FLOOR accounts department, billing department,design room,
documentation department,employees canteen.
HR department,IT department,
229
SHAH I EXPORTS PVT. LTD., FARIDABAD
merchandising department,Owner’s room,
R&D department, call center,conference rooms,
showroom,
230
SHAH I EXPORTS PVT. LTD., FARIDABAD
Fig 1.21
231
SHAH I EXPORTS PVT. LTD., FARIDABAD
Fig 1.22
232
SHAH I EXPORTS PVT. LTD., FARIDABAD
LAYOUT OF SECOND FLOOR(Fig 1.23):
233
SHAH I EXPORTS PVT. LTD., FARIDABAD
LAYOUT OF THE CUTTING SECTION
Fig 1.24
234
SHAH I EXPORTS PVT. LTD., FARIDABAD
235
SHAH I EXPORTS PVT. LTD., FARIDABAD
LAYOUT OF THE FABRIC STORE AND INSPECTION SECTION (Fig 1.25)
LAYOUT OF FINISHING SECTION (Fig. 1.26):
236
SHAH I EXPORTS PVT. LTD., FARIDABAD
Fig. 1.27
237
SHAH I EXPORTS PVT. LTD., FARIDABAD
SWOT ANALYSIS
Strength
Vertical Integration
Specialized units
Quality adherence
Introduction of ERP
Efficient planning Department
Weakness
Centralized cutting
Technological Advancement
Centralized Merchandising
Inefficient use of ERP
Opportunity
Infrastructure
Flexible Manufacturing
H R Department
Threat
International Competition
1. STRENGTH :
VERTICAL INTEGRATION: Shahi Export House Company started its operation way back in
1973. Earlier established in Delhi ( Okhla), now in Faridabad, Shahi stands vertically integrated
as one of the largest manufacturer/exporters in India offering ready-to-wear garments for ladies,
men and children. It
consists of units including the areas of Noida, Ranjitnagar, Gaziabad and in Bangalore. Though
all the units are in different areas of Delhi & surrounding areas, there is a smooth flow of work
between all the units. In total there are 18 integrated state-of-the art garment production centers
of Shahi. It has its own integrated unit of fabric mills, processing units, printing & dyeing,
embroidery, wash & finishes.
SHAH I EXPORTS PVT. LTD., FARIDABAD
In the case of fabric capability Shahi has:
Integrated fabric base for both wovens and knits.
Both facilities equipped with German and Swiss state of the art processing Machines
which ensures a high level quality output
Sourcing office in China providing access to diverse fabric bases in the Far East
Sourcing relationship with all leading mills in India like Arvind, Morarjee, Ashima,
Vardhman and several independents in auto-loom sector.
Sarla Fabrics (Earlier called as Palmprint Textiles), the fabric process house is one of India’s
foremost wet processing plant. All kinds of woven fabrics like poplin, twill, canvas, gauge,
corduroy, chiffon, moss crepe, Rayon, Georgettes, Nets, Velvets, Cambric, satin, Bosky, lycra
etc are processed to international standards.
Prints like reactive, vat colour discharge on reactive grounds & pigments apart from some
special printing techniques like burnt out effects on polyester-cotton blends are achieved here. In
all, the unit produces about 90,000 mtrs of processed fabric per day.
This puts Shahi at the top compared to the other export house. It cuts down the lead-time &
prices.
Consistency: when a company is vertically integrated there is a lot of consistency in the
fabric. As from the yarn stage to the weaving stage medium remains one. Therefore there
is no involvement from outside. It eliminates the mediators, excluding the provisions of
wastages, transportation costs etc.
Lead times: when every procedure is done under one roof, it abolishes the time required
to transport the material from one place to another.
Reduced transportation cost: transporting a product from one place to another consumes
time & money. For any value added service like washes, sequins a company send the
fabric or garment to other locations but this is not a case with Shahi every thing is done in
house thus reducing transportation cost.
SHAH I EXPORTS PVT. LTD., FARIDABAD
Specialized units: Shahi has divided the Faridabad & Bangalore as woven & knits unit
respectively. By making the units specialized it has help the company in achieving better &
faster production. As the same work is repeated again, it helps staff to understand faster & better
which has lead to efficient utilization of resources & quality shipments.
QUALITY ADHERENCE: Shahi relates itself with quality. Quality department places checks
at all the required areas in all the production departments like, fabric department, cutting
department, sewing department, finishing & packaging department. Other than this Q.A’s are
also allotted for each specific brand within the organization. The Q.A department also takes
active part in the sampling as it is the base on which order comes.
Focus on quality and a proven track record
↔ Short shipment : 0.50%
↔ On time delivery : 98%
↔ Quality claims: Nil.
INTRODUCTION OF ERP – M3
The whole computerization system helps keep all the departments in link with each other. The
software used is used for almost every function & process-
Sampling
Costing
Order capturing (job order details, fabric, trims requirements)
Production (Cutting, stitching, finishing, packing, consignment delivery)
Shipment (boxes, box no., place)
Buyer’s PO entry (Invoicing & Billing)
Accounts/Finance (interlinking of bills, vouchers, payments, salary management, various
allowances)
Time Management (leave records, calculation of bonus, reimbursement amount etc)
SHAH I EXPORTS PVT. LTD., FARIDABAD
The top management people can keep track of the status of production just by a single click. All
departments can keep in touch with each other and can know the status of orders.
Without this whole computerization system it would had been difficult for various departments
to interlink with each other.
EFFECIENT PLANNING DEPARTMENT - the planning department of the company has a
very good team of members which very carefully studies each garment. After the complete
analytical study of each garment the team makes different combinations of folders & attachments
in such a manner that it helps in faster & efficient production that too with minimal wastage of
time.
2. WEAKNESS
CENTRALIZED CUTTING : there is a centralized cutting in the head unit. Cutting for Delhi
NCR production units is done at the head unit. At times priority is given more to some orders
than that to the others. So, the cutting of the other orders is put to halt. At times when the
production units are short of cut pieces they have to wait for the cutting department to work on
their order, in turn wasting the time and delay in the production.
TECHNOLOGY: machines that are being used in the organization in the sewing department
even in the cutting department automatic spreader and cutting machines are very old and need
updation. Investment in the machinery is less.
TIME CONSUMPTION IN THE FINISHING DEPARTMENT
(SAMPLING) :
The sampling in Shahi has to go within 3 days of receiving the tech pack. The pattern making,
cutting & stitching is done within 2 days but the finishing department takes more than 1 day to
finish a garment. This at times becomes a messy situation. As the sampling department is too big
SHAH I EXPORTS PVT. LTD., FARIDABAD
the finishing department & the workers are less compared thus a merchant has to always be
present when his/her garment is in finishing department. This affects the efficiency of the
company.
CENTRALISED MERCAHNDISING:
The production units are lacking of merchants to follow an order, all the work is handled and
taken care by the merchants in the Faridabad unit. At times it becomes too messy to track one
order as the merchant is sitting in Faridabad and giving instructions at Bangalore. This creates
confusion as the merchant in Faridabad is not aware of what is going in Bangalore. This
eventually increases the lead time as everything has to be sent to Faridabad merchants for
approval and then sent back. As the lot approval has to be sent to Faridabad after the approval it
is again sent to the production unit, this activity is very time consuming. Even the P.O. is made
by the merchant in Faridabad so if there is some shortage of fabric it has to be informed in
Faridabad after which again a P.O is raised after which only the fabric is generated.
INEFFICIENT USE OF ERP:
The merchants & DMMs are not using the ERP system MOVEX efficiently. The system is
capable of doing lots of things which can reduce the lead time and increase efficiency of an
order, but this is not done. The system is used just to generate the P.O which is a part of the ERP.
The merchandisers have not taken any classes for the same, they are working on hit & trial
method or learnt something from their seniors.
3. OPPORTUNITY
1) Developing excellent infrastructure on design to capture business from Domestic Importer &
China.
Active involvement of design with buyer’s design department.
CAD facilities to make new prints & yarn dye patterns.
SHAH I EXPORTS PVT. LTD., FARIDABAD
Digital printing to print directly from CAD
2) Worldwide sourcing of Fabric.
Product Development & Price Competitiveness on Imported Piece Goods.
3) Manufacturing more complicated garments
Focus on high fashion garments
More embellished & sequin work
Attract more European buyers
4) The HR department is efficient enough, it makes an effort to motivate its employees by
celebrating different festivals & days. It makes the working environment very comfortable &
light in such tremendous pressure. They also organize for training of its employees in different
fields as- self defense, fabrics etc. still the HR Department gives a lot of freedom to the workers
due to which the older operators sometimes neglect their work due to which it becomes difficult
for the production managers to handle them.
4. THREATS
1) International competition
China, which is the largest exporter, has substantially increased its market share. Countries
like Bangladesh and turkey are very cost effective. China excels in the industry because of
cheap labor, efficient management, higher productivity, government policies, strong research
and development and industrial base.
SHAH I EXPORTS PVT. LTD., FARIDABAD
SECTION- B
PROJECT
SHAH I EXPORTS PVT. LTD., FARIDABAD
Project 1 : Reducing fabric wastage in the cutting Department
Cutting Department
Objective:
To reduce fabric wastage by implementing 100 percent width segregation. Make different markers for each width received.
Problems:
Although the width inspection was done 100 percent for the rolls but if in the middle of the roll the width changed further segregation was not been done.
Markers were being made only if the width varied by 2 inches which caused lot of fabric wastage.
Full use of the fabric widths to decrease the actual average was not being made.
End-cutters are not being used which causes the plies to be of varying lengths. This causes fabric wastage.
The actual average being calculated was a representation of all the widths therefore the profit or loss because of the width variation being received could not be tracked.
The slip on the rolls had the fabric width information and not the cuttable width.
At some places in layer charts roll numbers are not been mentioned.
When a roll is left over and is being used again the new metrage does not match with the left over metrage so we do not have any record of the difference.
The name of the left over roll should be updated in such a way so that it can be easily rec-ognized when being reused.
The calculation for the lay metrage, the difference and the balance is done manually by the operators who are finding difficulty in doing calculations.
SHAH I EXPORTS PVT. LTD., FARIDABAD
Suggestions:
100 percent width segregation.
Different markers for each width.
End cutters to be used which would reduce fabric wastage and also save time.
We have suggested a system of modifying the roll number if it is being reused. For eg. if the roll is of 200 meters and there is width variation in that roll so when its spread for the first time u upgrade the roll no as 75A and when its spread for the second time it is up-graded as 75B and so on.
It thus providing calculators would not only provide errors but will also save lot of time.
These suggestions were implemented in two styles.
M-409M-537
Methodology:
1)Measuring the width of each lay being spread.
2)Checking the lay length being written in lay slip is correct.
3)Developing a format for recording the following data:
Roll no
Roll metrage
Lay metrage
End bits
Left over
Difference
System Average
Actual average
SHAH I EXPORTS PVT. LTD., FARIDABAD
Can cut
Actual cut
Difference
Total cut
Variance
Summarizing the actual average width
Findings:
Item no: M-409
Order quantity: 36032
Fabric type: Nylon mesh
Fiber content: 100 percent polyester
Cost per meter: 135
System average: 0.98
Widths Received: 52”, 54”, 56”, 57”.
Summary
WIDTHNO. OF ROLLS
LAY METERAGE QUANTITY
SYSTEM YY
ACTUAL YY VARIANCE%
52 3 263.69 258 0.98 1.02 4.0854 28 2454.95 2425 0.98 1.01 3.0656 251 31267.98 32594 0.98 0.96 -2.0457 2.5 270.75 300 0.98 0.90 0 Total 284.5 34257.37 35577 0.98 0.96 -2.04
Width 52”
System YY: 0.98
SHAH I EXPORTS PVT. LTD., FARIDABAD
Actual YY: 1.02
Difference: 0.98-1.02 = -0.04
Total meters: -0.04*258=- 10.32 meters
Total Amount: -10.32*95.85= Rs-989
Width 54”
System YY: 0.98
Actual YY: 1.01
Difference: 0.98-1.01 =- 0.03
Total meters: -0.03*2425 =- 72.75 meters
Total Amount: -72.75*95.85 = Rs- 6973
Width 56”
System YY: 0.98
Actual YY: 0.96
Difference: 0.98-0.96 = 0.02
Total meters: 0.02*32594 = 651.88 Meters
Total Amount: 651.88*95.85 = Rs62482
Width 57”
System YY: 0.98
Actual YY: 0.90
Difference: 0.98-0.90 = 0.08
Total meters: 0.08*300 = 24 meters
Total Amount: 24*95.85 = Rs2300
Total savings for width 52”, 54”, 56”, 57”.
SHAH I EXPORTS PVT. LTD., FARIDABAD
= 62482-989-6973+2300
Total savings = Rs. 56820
Findings:
Item no: M-537
Order quantity: 33325
Fabric type:
Fiber content:
Cost per meter: 84.6
System average: 1.85
Widths Received: 54”, 56”, 56.25”, 56.5”,57”.
SummaryWIDTH NO. OF ROLLS LAY METERAGE QUANTITY SYSTEM YY ACTUAL YY VARIANCE%
SHAH I EXPORTS PVT. LTD., FARIDABAD
54 1 6190.89 3499 1.85 1.77 -4.8656 294.5 38253.05 20475 1.85 1.87 1.0856.25 50 6190.89 3499 1.85 1.77 -3.7856.5 70 9209.29 5252 1.85 1.75 -5.457 11 1051.64 600 1.85 1.75 -5.4 Total 426.5 60895.763 33325 1.85 1.83 -1.08
Width 54”
System YY: 1.85
Actual YY: 1.78
Difference: 1.85-1.78 = 0.07
Total meters: 0.08*78=- 6.24 meters
Total Amount: 6.24*84.6=Rs 527
Width 56”
System YY: 1.85
Actual YY: 1.87
Difference: 1.85-1.87 = -0.02
Total meters: -0.02*20475=-409 meters
Total Amount: -409*84.6=Rs-34601.
Width 56.25”
System YY: 1.85
Actual YY: 1.77
Difference: 1.85-1.77 = 0.08
Total meters: 0.08*3499= 279.92 meters
Total Amount: 279.92*84.6=Rs 23681
SHAH I EXPORTS PVT. LTD., FARIDABAD
Width 56.5”
System YY: 1.85
Actual YY: 1.75
Difference: 1.85-1.75 = 0.10
Total meters: 0.10*5252= 525.2 meters
Total Amount: 525.2*84.6=Rs 44431
Width 57”
System YY: 1.85
Actual YY: 1.75
Difference: 1.85-1.75 = 0.10
Total meters: 0.10*600= 60 meters
Total Amount: 60*84.6=Rs 5076
Total Savings: = (527+23681+44431+5076)-(34601) = Rs. 39114
SHAH I EXPORTS PVT. LTD., FARIDABAD
Project 2 - In-house Audit in Cutting Section
Methodology
The workflow of the cutting section was observed over a period of 15 days. The actions
of the operators and managers, as well as the working conditions were noted. Previous reports
and records of the cutting department were studied. It was only then that these observations
and suggestions could be made.
Observations
Absence of floor level cutting plan:
Presently for daily cutting of approximately 20,000 - 25,000 pieces, no formal planning is
available with cutting section and whole process is running with verbal planning.
Table-wise Cutting Plan:
1. Day to day table wise working is not through planning, but as per situation & decided
on the spot i.e. man-dependent.
SHAH I EXPORTS PVT. LTD., FARIDABAD
2. Based on monthly sewing plan received from central planning, cutting is performed but no document is available for day’s table-wise cutting plan.
3. Based on the requirement of stitching, cutting masters are informed about the pieces
to be cut for the day.
In the absence of floor level planning, masters start layering and cutting, wherever they find
vacant cutting table. Instances have been noted, wherein due to lack of planning, wastage of
man-hour and capacity were observed. This happens as teams of three are grouped in an
informal way. After every layering teams have to revert to the master for what to do next.
Need for supervisory control in layering for wastage reduction:
It was observed that there is absence of cross checking for the layer length actually laid by
layer man while layering, so that any mistake can be corrected at early stage. For laying
fabric layers, the concerned cutting master notes the layer length and other detail over the
layer chart. The layer man lays the fabric as per the length mentioned in the layer chart and
no supervisor/master checks the length, width and no of layers while layering.
Need for proper accountability - Unit-wise cutting control after clear table
authorization and capacity allocation :
For better control and fixing accountability of masters, it is required to have unit-wise
division of cutting capacity (Tables) and masters. Planning & control responsibilities of
cutting & cutting tables should also be divided unit wise.
Need for de-centralization of CAD:
Presently, CAD is responsible for preparation of costing, fabric, final and production markers.
Production/Cutting markers are prepared on the information provided by Cutting Section(i.e.
SHAH I EXPORTS PVT. LTD., FARIDABAD
Cutting master). The CAD prepares the Marker without confirming whether the
cutting master's requirement would lead to wastage or saving. This type of uncertainity can be
avoided by:
o Decentralization of CAD by shifting preparation of Production/Cutting marker
section under Cutting Section.
o Benchmark for Production Marker (Under Cutting Section) can be set based
on the average of the final marker prepared by CAD.
This system would be helpful in fixing the responsibility/accountability of deviations in
actual fabric average vis-a-vis average initially recommended for fabric procurement.
Need for more Auto End Cutter machines - Avoiding Avoidable Daily Fabric
Wastage (500 m per day ):
It has been observed that while cutting the fabric by pulling it by hand or by scissors, on an
average 4-6 cm of fabric is wasted per layer. If calculated for 20,000 pieces daily cutting
with 2 piece marker, i.e for 10,000 layers, daily avoidable wastage of fabric comes to a
whooping 500 m. (approx. 13,000 m in a month or 1,56,000 m in a year)
The reduction in wastage of 4-6cm can be achieved by installing Fabric End Cutters at each
table, which are currently installed only on Fusing cutting tables.
Improper storage of end pieces - Wastage of man hours/productivity:
Storage of various sized end pieces is improperly done. Most of the time, cutting
personnel are observed to be searching the end pieces bale, whenever required.
Proper storage of stock & its availability in system will enable proper planning.
With the result, fresh fabric would be issued only after the efficient utililization of end pieces.
SHAH I EXPORTS PVT. LTD., FARIDABAD
Loss of Production Hours Due to Poor Maintenance:
As confirmed by Cutting Section, due to poor maintenance, most of the time, CAM,
Spreader and Fusing machines are on break-down. Out of 30 days, CAM is normally on
break-down for 10 days also the machine can not be used for more than 8 hours. Each
month CAM cuts around 10,000 pieces only and rest of the cutting is done by manual
cutting machine. Cutting capacity can be increased by properly repairing CAM and replacing
damaged parts.
There is a problem of spares for Hand Cutting machines.
Loss of man-hour:
The embroidery thread cutting section lies in between the numbering section and small
bundling section. So there is wastage of man hours to shift pieces from one place to another.
For material (cut pcs & cutting wastages) transfer on floor, movable light weight trolleys and
roller dustbins can be used as these are easy to handle. Dragging pieces in polythene on floor
and easy to handle heavy trolleys for trash & kattran are also used.
There is lot of movement in bundling section for ticketing and small bundle making.
Suggestions
Cutting & layer chart preparation – These two activities should be under one person.
Cutting section is in need of mechanization (two way spreading machine) and computerization.
Need for computerization of layer chart layer wise.
Need for fabric inspection data with fabric layering
This will ensure setting of standard number of plies for particular type of fabric and
its compliance. Actual fabric width, marker width and any mismatch will be revealed.
SHAH I EXPORTS PVT. LTD., FARIDABAD
SHAH I EXPORTS PVT. LTD., FARIDABAD
Section C
Appendix
SHAH I EXPORTS PVT. LTD., FARIDABAD
APPENDIX-1
(Machine and workforce details)
SHAH I EXPORTS PVT. LTD., FARIDABAD
Appendix 1.1 : MACHINERY DETAILS(SAMPLING)
Operation Machine type Total number
Pattern making Tables 4
Cutting Tables 11
Sewing Lockstitch machines 172
Sewing Feed off the arm 2
Sewing Kansai 1
Sewing Kansai designing 1
Sewing Pickstitch 1
Sewing Flatlock 3
Sewing DNLS 1
Sewing Chainstitch machines 1 single needle + 1 double needle
Sewing Overlock machines 11
Sewing Picotting 1
Sewing Blind stitch 1
Sewing Snap button 2
Sewing Fagotting 2
Sewing Embroidery 21
Sewing Baby overlock 1
Sewing Keyhole machine 1
Sewing Bartack machine 1
Sewing Buttonhole machine 2
Sewing Button attaching machine 2
Sewing Zig zag embroidery 1
Sewing Fusing machine 1
Sewing Riveting 1
Sewing Blanket stitching 1
Handwork Table 4
Finishing Ironing table 6
Finishing Thread trimming table 1
Quality Checking Tables 6
Packing Table 1
SHAH I EXPORTS PVT. LTD., FARIDABAD
Appendix 1.2 : LINE-WISE MACHINERY DETAILS(SAMPLING)
Line Machinery
Line 1
1 Chainstitch button attach + 2 Lockstitch button attach
+ 1 Bartack + 1 Normal buttonhole + 1 Riveting
+ 1 Eyelet buttonhole + 2 SNLS (alterations)
+ 1 Snap button attach
Line 2 19 SNLS + 2 5-T O/L
Line 3 18 SNLS + 1 5-T O/L + 1 SNCS + 1 DNLS
Line 4 19 SNLS + 1 5-T O/L
Line 5 14 SNLS + 1 5-T O/L + 1 Flatlock + 1 6-T Picoting
Line 6 14 SNLS + 1 5-T O/L + 1 DNCS + 1 SNCS + 1 2-T O/L
Line 7 15 SNLS + 2 Smocking + 1 5-T O/L
Line 8 14 SNLS + 1 5-T O/L
Pattern Making
Line A – 8 table
Line B – 7 table
1 Transfer table (White pattern paper to brown pattern paper)
Dimensions: 72” X 48” X 41”
Cutting
8 Sample table + 1 Mock table
SHAH I EXPORTS PVT. LTD., FARIDABAD
Dimensions: 94.5” X 49” X 37”
Hand work 4 table
Embroidery 23 Hand embroidery + 1 Blind hemming + 1 DNLS
Thread
trimming1 table
Quality
checking6 table
Finishing 6 Ironing table + 1 Spot cleaning table
Packing 1 table
SHAH I EXPORTS PVT. LTD., FARIDABAD
Appendix 1.3 TECHNICAL SPECIFICATIONS(CUTTING DPT.)
DRILLER
Current – 1.3 amp
Volts – 220
Cycle – 50 per second
Motor Phase – I
STRAIGHT KNIFE
Blade - 8” long & 1.25” wide
Current – 4.2 amp
Volts – 220
Cycle – 50 per second
RPM – 2850 (Strokes per minute)
Motor Phase – I
CAM CUTTER
Actual cutting area 2m/2m
Actual suction area 2.1m/2.1m
Actual vacuum strength 150 milibar (maximum)
Single bristle diameter 1.3 mm
Bristle length 40 mm
SHAH I EXPORTS PVT. LTD., FARIDABAD
No. Of bristle in one replaceable unit 17 * 17=289
Area of bristle unit that can be replaced 51.3 mm X 50.64 mm
Maximum layer width after compression 7.5 cm
Cutting speed 0 – 40 m/min
Blade sharpening frequency 2.5 – 3 m (of cutting)
Blade Single edge
Drilling Yes
Hot drill Yes
Hot notch No
Bristle conveyor movement while cutting Yes
Bristle conveyor speed 19 m /min
3 phase power unit 380 volt , 50 hz
Current with a full load 62.5 A
Current of maximum load 35 A
Installed power (including suction fans) 25 kw
Pneumatic feed 150 l min at 8 bar
Cooling unit 540 l min at 8 bar
In board computer 4 MB RAM, 66 MHz
Hard disk memory 850 MB
Working temperature 10 - 30°
RS 232 online connection with cad system Yes
SHAH I EXPORTS PVT. LTD., FARIDABAD
Optional network connection Yes
Maximum speed of unloading conveyor 48 m/ min
Notch depth 2 – 6 mm
AUTOMATIC SPREADER
Length of the spreading table 40 m
Width of the spreading table 72”
Height of the spreading table 36”
Table top type Smooth, card board type
Number of clamps 14
2 air channels on the bottom side of the table surface along on the bottom side of the table
surface along with 112 air nozzles per square meter.
Five blow motors per table, each supplying air to a particular zone of the table.
SHAH I EXPORTS PVT. LTD., FARIDABAD
S.NO MACHINE MODEL MAKE NO
1. Fusing machine HP-450 MS Hashima 1
2 Cam machine TP3002, FTR 200/200 F.K.Systema (Tukatech) 1
3 Straight Knife Machine 620 X, 2YK119-5 Blue Streak II (Eastman) 12
4 Spreading table Locally made -- 18
5 Spreading Machine Automatic CO SX F.K.Arna, TukaTech 2
6 Recutting table Locally made -- 2
7 Band Knife Machine 11636, STV Wastema International 1
8 Fusing Machine (Flat
Continuous)
HP 1000 ED Hashima 1
9 Die Cutting MF 9.5 Ngaishing 1
10 End cutters - - 2
11 Driller - Eastman 1
12 Sticker Gun - - 30
Appendix 1.4: MACHINERY DETAILS(CUTTING DPT)
SHAH I EXPORTS PVT. LTD., FARIDABAD
Appendix 1.5: WORKFORCE OF THE CUTTING DEPARTMENT:
Cutting manager 1
Cutting senior executive 1
Industrial engineer 3
Cutting junior executive 3
Quality controller 4
Computer operator 2
Cutting incharge 1
Cutting masters 1
Supervisors 7
Cutters 10
Fusing cutters 2
Helpers 10
CAM operators 2
Pattern sampling incharge 1
Pattern sampling master 1
Sampling manual cutter 2
Fusing incharge 1
Re-cutting incharge 2
Fabric 10
Layerman 33
SHAH I EXPORTS PVT. LTD., FARIDABAD
Re-cutting 15
Dispatch 10
Numbering in-charge 1
Numbering 35
Fusing 39
Bundling 11
Marker & sticker 5
Sampling helper 2
Peon 2
Feeder 2
SHAH I EXPORTS PVT. LTD., FARIDABAD
Appendix 1.6: INFRASTRUCTURE DETAILS OF THE CUTTING DEPARTMENT:
Table No. Details
1,2 Width: 64”
Length: 462”
Height: 34”
3,4,5 Width: 60”
Length: 714”
Height: 34”
6 Width: 59”
Length: 836”
Height: 34”
7,8,9 Width: 59”
Length: 187”
Height: 34”
10,11 Width: 62”
Length: 418”
Height: 34”
14 Width: 54”
Length: 242”
Height: 34”
15,16 Width: 72.5”
Length: 1562”
Height: 34”
17,18 Width: 72.5”
SHAH I EXPORTS PVT. LTD., FARIDABAD
Extendable width (28” on both sides( i.e. 56”))
Length: 1232”
Height: 34”
19 Width: 62”
Length: 418”
Height: 34”
Re-cutting tables (12,13) Width: 62”
Length: 836”
Height: 34”
HFD Cutting Tables
(4 tables)
Width: 72.5”
Length: 1562”
Height: 34”
SHAH I EXPORTS PVT. LTD., FARIDABAD
Appendix 1.7 WORKFORCE(SEWING DPT)
S. NO. WORK TYPE PRESENT
1 Manager 2
2 Executive 4
3 Operator 882
4 Hand Operator 252
5 Inline Checker 63
6 Final Checker 42
7 SPI Checker 2
8 QC 21
9 Dispatcher 16
10 Production Writer (IE) 11
11 Computer Operator 4
12 Junior Engineer 4
13 Supervisor 21
14 Line In charge 21
15 Floor In charge 4
16 Writer 2
17 Feeder 21
18 Needle Stock 2
19 Mechanic 3
SHAH I EXPORTS PVT. LTD., FARIDABAD
20 Electrician 2
21 Medical 1
TOTAL 1380
Appendix 1.8 MACHINE DETAILS(SEWING FLOOR)
S.
NO.
TYPE OF MACHINE MAKE MODEL NO. QUANTITY
1. Snls Brother Db2b101cm 72
2. Snls (ubt) Brother Db2b201ebten 16
3. Snls Brother Db2b736cn 72
4. Snls (edge cutter) Brother Db2b777eccn 2
5. Snls (with thread trim) Brother Sl73740330md602 96
6. Snls (with thread trim) Brother Sl737md602f401 3
7. Snls (needle feed) Brother Sn-7210-3 23
8. Snls Juki Ddn5530ncn 214
9. Snls Juki Ddn5550-3ubt 119
10. Snls Juki Ddn5550-ubtemc3 8
11. Snls Juki Dlm5200cm 54
12. Snls Juki Dln5410ubtem 32
13. Snls Siruba L818f-m1 53
SHAH I EXPORTS PVT. LTD., FARIDABAD
14. Sncs Juki Mh481 5
15. Dnls Brother Lt2-b842scm ¼” 1
16. Dnls Brother Lt2-b845-3scm 1
17. Dnls Juki Lh3168sf 3
18. Dnls Juki Lh3128cm- ¼” 5
19. Dnls Juki Lh3168cm- ¼” 26
20. Dnls Juki Lh3168ubtem- ¼” 22
21. Bartack Brother Ke51430c-01-s 2
22. Bartack Brother Lk1850 1
23. Bartack Brother Lk3b430bd 2
24. Bartack Brother Ke-430c-01 1
25. Bartack Juki Lk1900mc590sn 2
26. Bartack Juki Lk1900 hs 1
27. Button hole Amf reece S 100mech 1
28. Button hole Brother Lh4-b814-2 6
29. Button hole Juki Lvh780cm 4
30. Button hole Juki Lvh781ucm 7
31. Button hole Juki Lbh 781 6
32. Button attach (chain stitch) Brother Cv3-b916cm 1
33. Button attach (lock stitch) Juki Lk1903ass/301/10 3
34. Button attach (lock stitch) Juki Lk1903mcsm 2
SHAH I EXPORTS PVT. LTD., FARIDABAD
35. Button attach Brother Be-438c 1
36. Button attach (chain stitch) Juki Mb372cm 5
37. Overlock Brother Ma4b551cm 2
38. Overlock Juki Mo3616cm 21
39. Overlock Juki Mo3916cn 16
40. Overlock Juki Mo6716s-de4-40h 4
41. Overlock (4 thd) Pegasus M3652-13 2
42. Overlock (5 thd) Pegasus M732-38-3x4 1
43. Overlock (6 thd) Pegasus M732-355 18
44. Overlock Siruba 757f-516m 28
45. Overlock (5 thd, ls) Siruba 757f-516m2-35 13
46. Snap button attach Gold stitch 55 9
47. Snap button attach Hang gang Zn-90 3
48. Snap button attach Zzihi No model 2
49. Shank button attach Juki Mb 372 3
50. DNCS Juki Mh380- ¼” cm 5
51. Bone pocket machine Darkapp adler 1970-991005-100 2
52. Blind stitch Juki Cv641cm 5
53. FOA Juki Ms1190cm- ¼” 1
54. FOA Juki Ms1261cm- ¼” 13
SHAH I EXPORTS PVT. LTD., FARIDABAD
55. FOA Juki Ms1261vocm- ¼” 4
56. Pin tucking Kansai Dfb1412ptv 1
57. Smocking Kansai 1404cm ¼” ¾” 1
58. Smocking Kansai 1412pqcm ¼” 17
59. Smocking Kansai Dfb1012pssm 4
60. Digital puller Muyngjin Mp1116b 8
61. Digital puller Muyngjin Mp1116ss 10
62. Collar turning Ngaishing Ns45 1
63. Collar heat notcher Ngaishing Ns91clrtur 2
64. Collar contour trimmer Ngaishing Ns92 2
65. Pocket creasing Ngaishing Ns84pktcrs 1
66. Cuff blocking Ngaishing Ns85cufblc 2
67. Flat lock Revo Rs-900
68. Flat lock Siruba C007h/w812-356/crl/csa 2
69. Flat lock Union special U-s-flatlock 1
70. Embroidery Paff Emb 7
71. Sleeve attaching Paff 337g-734/02-2 1
72. Sewing lifting trolley Ramsons Sewlifttrolley 1
73. Zig zag cs picoting Siruba Z008-248q 2
74. Fagotting Singer 72w19 2
SHAH I EXPORTS PVT. LTD., FARIDABAD
75. Zig zag Sunstar Dpk-3 10
76. Hook & eye Ykk Gn5 2
77. Snap button attach Ngaishing Ns45 1
78. Automatic shank b/a w/wrap Ascolite Mms mark 10 3
Appendix 1.9: Washing Department Machinery Details
SHAH I EXPORTS PVT. LTD., FARIDABAD
S.no Machine Type Make Capacity Qty
1 Drying thumbler Ramsons 100kg 5
2 Sampling washing machine Stalwart 10kg 1
3 Washing machine Ramsons 110kg 2
4 Sampling washing machine Fabcare 12kg 2
5 Hydro extractor Fabcare 15kg 1
6 Sampling washing machine Ramsons 15kg 2
7 Sampling washing machine Stalwart 15kg 1
8 Drying thumbler Steafab 15kg 1
9 Hydro extractor 15kg 1
10 Washing machine Ramsons 200kg 5
11 Hydro extractor Fabcare 25kg 2
12 Drying thumbler ( local ) not in use 25kg 1
13 Drying thumbler Ramsons 25kg 1
14 Drying thumbler ( electrical ) Steafab 25kg 1
15 Hydro extractor Steafab 25kg 1
16 Washing machine Steafab 25kg 1
17 Drying thumbler Fabcare 50kg 2
18 Drycleaning machines Steafab 50kg 2
19 Drying thumbler Fabcare 60kg 1
20 Washing machine Ramsons 60kg 1
21 Washing machine Steafab 60kg 2
22 Cracle washing machine (local ) Wooden 1
SHAH I EXPORTS PVT. LTD., FARIDABAD
23 Steam conical cylinder with press (local ) 1
24 Steamer 1
Appendix 1.10: Manpower Status of Finishing Floor
SHAH I EXPORTS PVT. LTD., FARIDABAD
FLOOR MANPOWER
A 105
B 102
C 105
D 105
Appendix 1.11: Infrastructure Details of Finishing Floor
PURPOSENO. OF M/C,
TABLE USEDEQUIPMENT USED MANPOWER/TABLE
Thread cutting 5 Thread cutter/clipper 4
Initial
checking10 Stickers 2
Ironing 15 Steam iron, flat bed, bucks 1
Shade
matching1 2
Alteration 13Sewing machine, thread
clipper1
Measurement 1 Measuring tape 2
Spotting 2 Spotting gun, chemicals 2
Final checking 4 Stickers 2
Packaging 3 Packaging material, 2
SHAH I EXPORTS PVT. LTD., FARIDABAD
polythene bags
Qc 1 2
SHAH I EXPORTS PVT. LTD., FARIDABAD
APPENDIX-2
(ANNEXURES)
SHAH I EXPORTS PVT. LTD., FARIDABAD
COMPANY
MACHINE DETAILS (Sampling floor machinery excluded)
Year of Estd. 1974 SEWING M/C
Make Qty. Make Qty. Make No.of M/C
Make Qty. Make Qty.
Annual Turnover (Rs.crore)
2200 crore
SNLS Ordinary
Juki 214 Brother 70 Sunstar 51 Siruba 53
Proprietory/Partner./Pvt. Ltd.
Pvt. Lytd.
SNLS With UBT
Juki 135 Brother 115 Sunstar 4 Siruba 147
Export/Doms/Both./100%EOU
100% EOU
DNLS Ordinary
Juki 35 Brother 3 Sunstar 14
In house /Fabrication/Both
Both ZIGZAG Sunstar 36
No. of units 32 SNCS Juki 4
Total Workforce
55000 DNCS Juki 3
Feed Off the Arm
Juki 22 Siruba 66
Organisation Pattern
Single Needle edge cutter
Juki 54 Brother 1 Siruba 3
Owner Ms. Sarla Ahuja
D/N UBT Juki 22
Vice President
3 Picotting Kansai 25
Senior Executives
6 O/L(total) Juki 42 Pegasus 16
Junior Executives
6 5TH. O/L
Production 1 Flat Lock Siruba 6
SHAH I EXPORTS PVT. LTD., FARIDABAD
manager Collar
turning machine
Ngaishing 2
Cuff turning machine
Ngaishing 2
CUTTING Dept.
Bartack Juki 1 Brother 4
Production Manager
1 Button sew C/S L/S
Juki 9
Cam operator
2 Button hole Juki 11 Brother 6 Siruba 10
Cutting Master/Asst.
3 Welt pocket m/c
Durkopp Adlerq
2
Workers / Helpers
61.00 Blindstitch Juki 4
Cutting excutive
1 CUTTING M/C
Make Qty. FINISHING M/C
Qty. No.of M/C
Qty. Qty.
STRAIGHT KNIFE
Bluestreak/2Yk119-5
12 Ironing table
63
SEWING Dept.
BAND KNIFE
Wastema International/11636 STV
1 STAIN REMOVING GUN
20
Production manager
3 Driller Eastman 1 STAIN REMOVING W/S
1
Floor incharge
4 DIE CUTTING
Ngaishing/MF 9.5
1 WASHING M/C
Fabcare 3 Ramson 8 Stefab
3
Line incharge 21 Spreading machine
F.K.Arna/Automatic CO SX
2 HYDRO EXTRACTOR
Fabcare 3 Stefab 2
SHAH I EXPORTS PVT. LTD., FARIDABAD
Operators 882 CAM F.K. Systema/TP3002
1 TUMBLE DRYER
Ramson 6 Fabcare 3 Stefab
2
Supervisor 21 Fusing machine(Flat contiuons)
Hashima/HP100ED
1 DRY CLEANING
Stefab 2
Inline checker
63
Finising Dept
Production manager
1
Operators 472
Helpers 85
QA 5
SHAH I EXPORTS PVT. LTD., FARIDABAD
SPREADING DEPARTMENT
Style M543Fabric Width 39.5" Solid/YarnDyed/Print
Fabric DetailLining fabricFabric Poplin
Fibre Content 100% cotton Nap
One Way
Manual Spreading Yes Splicing ? No Model n/a Make n/aNo.of Weights Used
1
Spreading M/c Type n/aLay Length
6.21mFabric Package Type
BaleHow Old
n/a Use of pins no
Spreading Mode NOW/FOWTable Width
64"Table top type
plyTable Lth
18m Table Ht 3ft
No.of Clamp Used 0 Lights per table 34Use of papers between layers
noHeight of light from cutting table
2.5 m
Lay No. 1 Lay Ht 2" No. of Fab Layers 100 MarkerType Paper / Fabric / CAD / On lineTime Duration in min.
10m 47s 8m 33s 8m 16s 9m 49s 8m 20s 9 m 25s12m 21s
14m 19s 13m 12s8m 48s
No. of Layers 10 10 10 10 10 10 10 10 10 10Total fabric handled*
62.1 67.1 67.3 63.6 63.6 65.1 64.1 63.6 65.1 63.4
Spreading operators 3 3 3 3 3 3 2 2 2 3* (No. of layers x Lay length)+ End bits Lay No. 1 Lay Ht 2" No. of Fab Layers 100 MarkerType Paper / Fabric / CAD / On lineTime Duration in min.
10m 32s 8m 43s 8m 29 s 8m 11s 12m 27s 12m 50s9m 31s
8m 19s 8m 57s8m 10s
No. of Layers 10 10 10 10 10 10 10 10 10 10Total fabric handled*
63.5 66.1 64.3 65.2 64 63.6 65.6 63.1 65.1 64.3
Spreading operators 3 3 3 3 2 2 3 3 3 3Operator Name Age Sex Education Height How long working in the deptt. Salaried/Hourly wageNagendra 35 M 10th pass 5'7" 4 salariedVishwanath 33 M 4th pass 5'11" 4 salaried
Akhilesh 40 M 8th pass 5'5" 12 salaried
SPREADING DEPARTMENT
SHAH I EXPORTS PVT. LTD., FARIDABAD
Style M398 Fabric Width 50" Solid/YarnDyed/PrintFabric Detail
Shell fabricFabric Polyester Fibre Content 100% polyester Nap One way
Manual Spreading
Yes Machine Spreading No Splicing ? No Table Lth 18m Table Width 64"
Spreading M/c Type
n/a Make n/a Model n/a How Old n/a Table Ht 3ft
Spreading Mode
NOW/FOW Lay Length 6.21m Fabric Package Type Roll Table top type
ply
No.of Clamp Used
0 No.of Weights Used 1 Use of pins no Use of papers between layers no
Lights per table
34 Height of light from cutting table 2.5 m
Lay No. 1Lay Ht
2" No. of Fab Layers 100 MarkerType Paper / Fabric / CAD / On line
Time Duration in min.
15m 40s16m 15s
15m 40s 14m 39s 14m 20s15m 15s
17m 3s16m 19s
14m 13s 14m 48s
No. of Layers
10 10 10 10 10 10 10 10 10 10
Total fabric handled*
62.5 63.2 65.4 62.1 3.1 64.8 65.1 62.9 63.6 64.1
Spreading operators
3 3 3 3 2 3 2 3 3 3
* (No. of layers x Lay length)+ End bits
Lay No. 1Lay Ht
2" No. of Fab Layers 100 MarkerType Paper / Fabric / CAD / On line
Time Duration in min.
15m 43s18m 43s
14m 59s 16m 12s 15m 27s 14m 6s 16m 9s 17m 2s 15m 3s 14m 16s
No. of Layers
10 10 10 10 10 10 10 10 10 10
Total fabric handled*
65 66.1 67.2 65.2 65.1 63.1 62.1 63.6 65.6 63.1
Spreading operators
3 3 3 3 2 2 3 3 3 3
SHAH I EXPORTS PVT. LTD., FARIDABAD
Name Age Sex Education Height How long working in the deptt. Salaried/Hourly wageAnupam 56 M 7th pass 5'9" 14 salariedShailesh 23 M 9th pass 5'8" 3 salariedMahesh 40 M 8th pass 5'5" 7 salaried
SPREADING DEPARTMENT
Style M514 Fabric Width 60" Solid/YarnDyed/Print Fabric Detail
Shell fabric
Fabric cotton Fibre Content100% cotton
Nap One way
Manual Spreading Yes Machine Spreading ? No Splicing ? No Use of pins no
SHAH I EXPORTS PVT. LTD., FARIDABAD
Spreading Mode NOW/FOW Lay Length 5.02m Fabric Package Type Roll Table Ht 3ft
No.of Clamp Used 6 No.of Weights Used 1Table Lth
18mUse of papers between layers
no
Height of light from cutting table
2.5 mTable Width
64" Table top type ply
Lay No. 1 Lay Ht 2"No. of Fab Layers
100 MarkerType Paper / Fabric / CAD / On line
Time Duration in min.
31m 44s 30m 25s 31m 44s31m 12s
29m 23s
30m 55s 31m 43s31m 29s
30m 23s
29m 28s
No. of Layers 10 10 10 10 10 10 10 10 10 10Total fabric handled*
52.4 51.6 53.6 55.3 51.4 51.1 52.5 53.1 53.8 54.2
Spreading operators
4 4 4 4 4 4 4 4 4 4
Lay No. 1 Lay Ht 2"No. of Fab Layers
100 MarkerType Paper / Fabric / CAD / On line
Time Duration in min.
30m 32s 33m 45s 32m 14s32m 32s
33m 13s
30m 35s 31m 54s31 m 19s
31m 12s
32m 8s
No. of Layers 10 10 10 10 10 10 10 10 10 10Total fabric handled*
51.8 53.5 53.1 54.2 53.8 52.4 53.6 54.9 53.6 55.2
Spreading operators
4 4 4 4 4 3 3 4 4 4
Name Age Sex Education Height How long working in the deptt. Salaried/Hourly wageSunil 37 M 10th pass 5'10" 20 salariedGiriraj 39 M 8th pass 5'9" 17 salariedHarinder 32 M 7th pass 5'8" 13 salariedRaj 29 M 8th pass 5'9" 12 salaried
CUTTING DEPARTMENT
STYLE H - 980 FABRIC WIDTH 46"FABRIC 100% Cotton FABRIC CODE S983 RedSOLID/YARN DYED/PRINT Solid FABRIC DETAIL Symmetric Solid CottonFABRIC CONTENT Cotton NAP Either WayMARKER MODE NEW MARKER LENGTH 6 meters MARKER WAY NEW TOTAL PIECES / LAY 400 pcs.
SHAH I EXPORTS PVT. LTD., FARIDABAD
SIZES IN ONE MARKER M (1)- L(1)-X L(1)- XXL(1)NO. OF PIECES IN MARKER 4TOTAL NO. OF PATTERN PARTS IN A MARKER 120NO. OF PATTERNS PER GARMENT 30TYPE OF CUTTING CNC MAKE F.K.Systema (Tukatech)
CUTTING M/C TYPEStraight Knife (block cutting) MODEL TP3002, FTR 200/200
Band Knife (recutting) BLADE TYPE Single Edge
TABLE WIDTH (CUTTABLE) 2 metresTABLE LENGTH (CUTTABLE)
2 metres
FREQUENCY OF BLADE SHARPENING WHILE CUTTING 2.5-3 metres of cuttingWORKING CONDITIONSLIGHTS PER SQ.MT. N/AFANS PER SQ. MT. No fan over the table (to prevent the movement of marker while cutting)MARKER TYPE Fed into the machine through a floppyLAY HEIGHT (max) 7.5 cm NO. OF FABRIC LAYERS 92CUTTING START TIME 11:10a.m. CUTTING END TIME 11:50a.m.TIME DURATION 40 mins CUTTING MASTERS N/ANO. OF PATTERNS CUT 120 NO. OF NOTCHES 92
Operation : Side seam overlock
Element Breakdown M/c Details : 3 Thread overlock
Sheet No. 16
Pick and position piece
Overlock one side
RepositionOverlock other side
Discard piece
Make/Model Siruba/KX10
Style M506 With/Without UBT
Fabric
Garment Ladies top Foreign Elements
(Raglan) Description
SHAH I EXPORTS PVT. LTD., FARIDABAD
NOTES S.NO T R T R T R T R T R T R T R R T
1 10.64 10.25 7.69 9.39 1.23 A 14.3 Thread breakage
2 9.12 10.80 8.87 11.04 2.23 B
3 9.25 9.29 8.54 11.25 1.67 C
4 9.14 8.97 7.48 9.51 1.54 D
5 8.32 10.08 8.34 10.62 1.46 E
6 8.61 9.15 7.42 10.16 1.83 F
7 10.73 9.22 10.87 11.01 1.98 G
8 9.43 10.99 9.32 9.18 1.59 H
9 10.55 9.17 8.75 9.99 1.32 I
10 10.62 10.04 7.70 10.14 2.34 J
K
L
M
SUMMARY
TOTAL 'T' 96.41 97.96 84.98 102.29 17.19 Seam Diagram
AVG T 9.64 9.80 8.50 10.23 1.72
RATING 0.65 0.65 0.65 0.65 0.65
Normal T 6.27 6.37 5.52 6.65 1.12 Attachment Used
P F & D 0.15 0.15 0.15 0.15 0.15
Standard T 7.21 7.32 6.35 7.65 1.28 M/c Delay* 0.07 0.07 0.07 0.07 0.07 Total op. time SAM
SHAH I EXPORTS PVT. LTD., FARIDABAD
S.A. TIME 7.71 7.84 6.80 8.18 1.37 30.52 0.51
SNLS=9% DNLS=14% O/L 3T=7% 4T=9% 5T=11%
APPENDIX VII – CAD EVALUATION FORMAT
SECTION A
QUESTIONNARE
SEGMENT – I (ORGANIZATION)
i. Which Cad system is being used in your organization?OPTITEX VERSION 10.0
ii. When was the CAD system being implemented in your organization?Before 5 years (12 – 13 YRS)
iii. How many times has the organization upgraded the CAD software or installed / changed to a new one ? ALMOST EVERY YEAR
SHAH I EXPORTS PVT. LTD., FARIDABAD
SEGMENT – II (PURPOSE)
i. Is CAD easier than traditional methods?(a) User’s point of view YES
(b) Your point of view YES
ii. For what purpose/s is the CAD system being used? (Can be more than one) FOR PATTERN MAKING FOR DIGITIZING THE PATTERNS PROVIDED BY BUYER’S MARKER PLANNING ALTERATIONS IN PATTERNS GRADING
iii. Does CAD result in greater productivity, is it more lucrative?(a) If yes, then how?
1. TIME SAVED2. QUALITY OF PATTERNS3. ALMOST 85% EFFECIENCY
SEGMENT – III (GENERAL)
i. Do you feel that CAD is affordable?YES ($5000 = RS. 180000 PER KEY)
SHAH I EXPORTS PVT. LTD., FARIDABAD
ii. Are traditional skills required to work on CAD?
Please Comment
YES TOOLS ARE THERE TO HELP OUT
iii. Are experienced pattern makers (who manually developed patterns and markers) easily accepting the extensive use of CAD / CAM?SOMETIMES
iv. Is the combination of an individual readily available who is an expert in CAD / CAM and pattern making?NO, SOMETIMES
SEGMENT- IV (TRAINING)
i. Was any training imparted to the operator when the new soft-ware was installed?YES
If yes, then for how many days?
7-15 DAYS
ii. Are you satisfied with the training given?YES
SHAH I EXPORTS PVT. LTD., FARIDABAD
iii. Do you think that training is only required when a new software is installed or do you recommend an in-house training otherwise as-well?ONLY WHEN SOFTWARE IS INSTALLED
iv. Do you think that the person working on CAD / CAM should be well versed in Pattern and Marker development or should he have fair knowledge about textile and styling as-well?YES
SEGMENT – V (PEOPLE INVOLVED)
i. How many people are working in the pattern development and marker making department?Please specify, (approx.)
CAD USERS- 18
MANUAL PATTERN MASTERS – 12
ii. Has the number changed (increased / decreased) with the usage of CAD?CANT SAY
iii. What is the age of person working on CAD?30 – 35 YRS
iv. Does he have any prior work experience on CAD?
SHAH I EXPORTS PVT. LTD., FARIDABAD
YES IF YES, THEN HOW MANY YEARS?
3-4 YRS
Section B
The following factors have been identified to have an influence on adoption of CAD / CAM.
(Kindly select the most appropriate option)
Factors influencing adoption of IT Strongly positive
Moderately positive
Indifferent Moderately negative
Strongly negative
Can’t say
High Price
Reduces dependence on people
Failed installation in other organization
Collaborative working between various employees, supplier and buyer is easier
Ability of supplier to train the users in our organization
SHAH I EXPORTS PVT. LTD., FARIDABAD
Saves fabric
The supplier does not have an office in the location where my organization is situated
Improves first pass quality product
Reduces throughput time for product assemble
Requirement of constant training
Ready availability of literate professionals
Constant up gradation of system required
Others please specify----------- -
SHAH I EXPORTS PVT. LTD., FARIDABAD
Section C
This sheet will help you decide which system is best for your pattern development department and organization. ( Even if you have one. )
Note: Simple instructions to fill in the form.
Mention the various CAD / CAM systems you are aware of in (*) columns In the row below, mention how each of these systems came your knowledge, whether through your institute, buyer’s, pattern maker, the respective
company, fairs and exhibitions or some journals etc. Mention the CAD system under the evaluating points of 1-7.evaluate by giving score of 1-7 where 1 stands for best and 7 for the least. Same number maybe given for more than one company if the features are felt to be the same. The company scoring the minimum score as per your
requirements should be your choice for buying the CAD system. In the last column, kindly mention the basis of your evaluating criteria. For ex., if you have give 1 to a particular system and 3 to the other, kindly mention
who / why you made the decision.
Criteria TUKA TECH
PAD OPTITEX LECTRA GERBER ASTOR(RED TREE)
How you found out about them
Pattern maker
industry Respective company
institute Industry Agency/journals
Communications-digitizers and file import
2 2 1 3 1 3
Piece geometry identifications(points, lines, notches, orientations lines, piece rotation line for marker making)
3 3 2 2 2 2
Pattern design functions- 2 4 1 3 1 2
SHAH I EXPORTS PVT. LTD., FARIDABAD
measurement capabilities
Pattern design functions-darts, pleats, trace, cut, combine, shrink, stretch, flip, rotate patterns.
4 2 1 3 2 3
Pattern design functions- seam allowance definition, corners, corner insert
3 2 1 2 1 2
Removing and adding of patterns from present files, printing and redo and undo functions & keyboard and mouse hot keys- shortcut keys
1 2 2 2 1 3
Pattern grading functions 2 3 2 3 2 2
Maker making functions 1 3 1 2 1 2
Automatic marker making functions
2 3 1 2 2
Software platforms 3 3 2 4 2
Outputs and consumables availability
2 2 2 2 1
SHAH I EXPORTS PVT. LTD., FARIDABAD
Manuals 4 3 1 3 3
Communications access with respect internet compatibility
2 2 3 2 2 2
Warranty and after sales service
3 3 1 3 3 3
CAM and CAS interface 2 3 2 3 1 2
Customizing features 2 2 2 3 1 2
Cost implications 2 3 1 3 1 2
Interface capabilities with other design software
2 2 1 3 1 3
Plotting facility 3 1 1 1 1 2
TOTAL
45 48 28 49 29 46
SHAH I EXPORTS PVT. LTD., FARIDABAD
Any remarks: OPTITEX COMES OUT TO BE THE BEST CAD SOFTWARE CLOSELY FOLLOWED BY GERBER
Section D
Analyzing usage of various functions in the CAD / CAM systems.
Note: Kindly tick mark in the relevant column and pen down any remark / comment related to the point in the last column.
S.No. Criteria Always Sometimes/
Occasionally
Rarely Never Additional Comment
1. Digitization
2. On screen pattern construction
3. Notches option
4. Dart manipulation
5. Grading tools
6. Size correspondence
SHAH I EXPORTS PVT. LTD., FARIDABAD
7. Specification sheet development
8. Piece assembly
9. Variant tools
10. Marker planning
11. Plotting
12. Piece rotation
13. Measurement capabilities
14. Pattern Design functions- Darts, pleats, trace, cut, combine, shrink, stretch, flip, Rotate pattern.
15. Removing and adding
SHAH I EXPORTS PVT. LTD., FARIDABAD
patterns
SHAH I EXPORTS PVT. LTD., FARIDABAD
Section E
Technical specifications
Note: Simple instructions to fill in the form.
Mention the various CAD / CAM systems you are aware of in (*) columns Mention the CAD system under the evaluating points of 1-7, evaluate by giving score of 1-7 where 1 stands for simplest and 7 for the complicated. Then compare the following system on the basis of the criteria mentioned with respect to the manual pattern making methods also (Mention the rating in
the appropriate column.) If a particular facility is not available in manual pattern making / CAD, mention NIL. In the remarks column, kindly mention the basis of your evaluating criteria (If possible). For ex., if you have given 1 to a particular system and 3 to manual
pattern development, kindly mention why you made the decision.
Criteria OPTITEX GERBER LECTRA Manual Pattern Making Remarks
Communications-digitizers and file import
1 1 4
Pattern design functions-measurement capabilities
1 1 3
Pattern design functions-darts, pleats, trace, cut, combine, shrink, stretch, flip and rotate patterns.
1 2 3
Pattern design functions- seam allowance definition, corners, corner insert
1 2 4
Removing and adding of patterns from present files, printing and redo and undo functions & keyboard and mouse hot keys- shortcut keys /
2 1 2
SHAH I EXPORTS PVT. LTD., FARIDABAD
Pattern alterations
Pattern grading functions
2 1 2
Changes in Maker plans 1 2 3
Automatic marker making functions 1 1 2
Software platforms 2 1 3
Outputs and consumables availability
2 1 2
Manuals / Books 1 2 2
Communications access with respect internet compatibility
3 1 2
Warranty and after sales service 1 1 1
CAM 2 1 2
SHAH I EXPORTS PVT. LTD., FARIDABAD
Customizing features 2 2 2
Cost implications 1
2 3
Interface capabilities with other design software
1 3 3
Plotting facility 1 3 2
Marker Planning Options (Piece rotation, Ply and edges, direction of pieces, quantity of pieces and piece adjustment command, marker efficiency, fabric width, etc.)
2 1 2
TOTAL
28 29 45
Any remarks: OPTITEX IS A SOFTWARE WHICH ADAPTS TO THE ENVIRONMET VERY EASILY AND IT IS VERY USER FRIENDLY THEREBY INCREASING THE PRODUCTIVITY OF THE USERS WHICH LEADS TO HIGHLY EFFICIENT PATTERN MAKING DEPARTMENT.
Section 2 - Administration and Security Name of the software
SHAH I EXPORTS PVT. LTD., FARIDABAD
Ref.Administration and security Assessments
Your W/F ScoreTotal (your W/F * Score )
3.1 Ease of use 4 4 16
3.2 Tabular selection 3 3 9
3.3 Password 4 4 16
3.4 Individuals and group settings 4 4 16
3.5 Audit trial 3 3 9
3.6 Customisation 4 3 12
3.7 Your Data
3.8 Your Data
3.9 Your Data
3.1 Your Data
Section 3 Total 22 21 78
Effeciency = C/(A*4)*100 88.63
Section 3 - Reports Name of the software
SHAH I EXPORTS PVT. LTD., FARIDABAD
Ref. Reports and statistical output Your W/F ScoreTotal (your W/F * Score )
4.1 Ease to access to reports 4 4 16
4.2 Data export capability 4 4 16
4.3 Customisable reports 4 4 16
4.4 Format of reports (graphical/text) 3 3 9
4.6 Your Data Re
4.7 Your Data
4.8 Your Data
Section 4 Total 1515
57
Effeciency = C/(A*4)*100 95%
Section 4 - Web Based Software Name of the software
SHAH I EXPORTS PVT. LTD., FARIDABAD
Ref. Web based Assessments Your W/F ScoreTotal (your W/F * Score )
5.1 Purchase of rent
5.2 Data ownership 4 4 16
5.3 Functionality 3 3 9
5.4 Response Speed 4 3 12
5.5 Company stability 4 3 12
5.6 Cost analysis
5.7 Internet access 4 4 16
5.8 Customisation 4 3 12
5.9 Spare
5.10 Spare
5.11 Spare
5.12 Spare
Section 5 Total 23 20 77
Effeciency = C/(A*4)*100 83.69
SHAH I EXPORTS PVT. LTD., FARIDABAD
Section 5 - Vendor and Vendor Support
Name of the software
Ref.Vendor assessment and support provision
Your W/F ScoreTotal (your W/F * Score )
6.1 Stability 3 3 96.2 Professionalism 3 3 96.3 Service level agreement 3 4 126.4 Provision of customisation 4 4 166.5 Upgrade path 4 3 126.6 Customer base 6.7 Support for add-ons 6.8 Your Data 6.9 Your Data 6.11 Your Data
Section 6 Total 1717
58
Effeciency = C/(A*4)*100 85.29
Section 6 - Software and other Costs Name of the software
SHAH I EXPORTS PVT. LTD., FARIDABAD
Ref.Cost of the software and associated costs
Your W/F ScoreTotal (your W/F * Score )
7.1 Cost of software 4 3 127.2 Cost of hardware 4 3 127.3 Potential future cost 1 2 27.4 Implementation cost 3 3 97.5 Training cost 2 3 67.6 Cost of customisation 4 3 127.7 Spare 7.8 Spare 7.9 Spare 7.10 Spare
Section 7 Total 18 17 53
Effeciency = C/(A*4)*100 73.61
Final Scores
Section Description Effeciencies
1 Overall Software Requirements 86.41
SHAH I EXPORTS PVT. LTD., FARIDABAD
2 Administration and Security 88.63
3 Reports 95
4 Web Based Software 83.69
5 Vendor and Vendor Support 85.29
6 Software and Associated Costs 73.61
7 FINAL EFFECIENCY AVERAGE OF ALL THE ABOVE
85.43833333
Time N' Action Calendar for Solids and Prints in Regular Qualities.
Time N' Action Calendar for YD Fabrics.
Time N' Action Calendar for Longer Lead Time and Speciality Fabrics.
30 Days Development Cycle 45 Days Development Cycle 60 Days Development Cycle
SHAH I EXPORTS PVT. LTD., FARIDABAD
Thresholds Timeline NO OF DAYS Timeline NO OF DAYS Timeline NO OF DAYS
In Store 11/1/2011 11/1/2011 11/1/2011
EX FCTY 9/9/201153 days prior to I/S
9/9/2011 53 days prior to I/S 9/9/2011 53 days prior to I/S
Bulk PCD 8/5/201135 days prior to Ex fcty
8/5/201135 days prior to Ex fcty
7/31/201140 days prior to Ex fcty
Bulk Fabric Flow Start (In House)
7/31/2011
40 days post the order Confirmation Date
7/31/201150 days post the order Confirmation Date
7/26/201160 days post the order Confirmation Date
Pre-Production Samples Due 7/26/201110 Days prior to PCD
7/26/201110 Days prior to PCD
7/21/2011 10 Days prior to PCD
GPT Closure 7/31/20115 Days prior to PCD
7/31/20115 Days prior to PCD
7/26/2011 5 Days prior to PCD
FOB Due 7/21/201110 Days prior to Bulk Flow Start (In House)
7/21/201110 Days prior to Bulk Flow Start (In House)
7/11/201115 Days prior to Bulk Flow Start (In House)
Size Set Approval Due 7/21/201115 Days prior to PCD
7/21/201115 Days prior to PCD
7/16/2011 15 Days prior to PCD
TRIM(S) ORDER DATE 7/6/201130 Days prior to PCD
7/6/201130 Days prior to PCD
7/1/2011 30 Days prior to PCD
Formal FPT & Internal GPT Closure
6/28/20117 Days post order confirmation
6/18/20117 Days post order confirmation
6/3/20117 Days post order confirmation
COLORWISE B/UP TO MILLS
6/22/20111 Day post order confirmation
6/12/20111 Day post order confirmation
5/28/20111 Day post order confirmation
SHAH I EXPORTS PVT. LTD., FARIDABAD
ORDER CONFIRMATION/FABRIC ORDER DATE
6/21/201145 Days prior to PCD
6/11/201155 Days prior to PCD
5/27/2011 65 Days prior to PCD
Labdips/strike offs/DESKLOOM comments (Round 2)
6/22/20113 days (transit) 4 days Buyer's approval
6/8/20113 days (transit) 4 days Buyer's approval
5/24/20113 days (transit) 4 days Buyer's approval
Labdips/strike offs/DESKLOOM Submission (Round 2)
6/15/20117 Days from comments recvd
6/1/201114 Days from comments recvd
5/17/201114 Days from comments recvd
Labdips/strike offs/DESKLOOM comments(Round 1)
6/8/20113 days (transit) 4 days Buyer's approval
5/18/20113 days (transit) 4 days Buyer's approval
5/3/20113 days (transit) 4 days Buyer's approval
Labdips/strike offs/DESKLOOM Submission (Round 1)
6/1/201110 Days from 1st TP recvd
5/11/201114 Days from 1st TP recvd
4/26/201114 Days from 1st TP recvd
LABDIP/STRIKE OFF/DESKLOOM DEVELOPMENT
5/22/2011Same day as 1st TP recvd
4/27/2011Same day as 1st TP recvd
4/12/2011Same day as 1st TP recvd
TRIM APPROVAL/CLOSURE
6/20/20111 Day prior to the order confirmation
6/10/20111 Day prior to the order confirmation
5/26/20111 Day prior to the order confirmation
TRIMS Submission 6/5/201114 Days from 1st TP Received
5/18/201121 Days from 1st TP Received
5/3/201121 Days from 1st TP Received
TRIM DEVELOPMENT 5/22/2011Same day as 1st TP recvd
4/27/2011Same day as 1st TP recvd
4/12/2011Same day as 1st TP recvd
FIT APPROVAL/Production Tech Pack
7/6/201130 Days prior to PCD
7/6/201130 Days prior to PCD
7/1/2011 30 Days prior to PCD
SAMPLE STAGE 2 (APPROVALS/COMMENTS)
6/28/20113 days (transit) 7 days Buyer's approval
6/4/20113 days (transit) 7 days Buyer's approval
6/13/20113 days (transit) 7 days Buyer's approval
SAMPLE STAGE 2 (SUBMISSION)
6/18/201110 days from rect of comments on 1st Fit Sample
5/25/201110 days from rect of comments on 1st Fit Sample
6/3/201121 days from rect of comments on 1st Fit Sample
SHAH I EXPORTS PVT. LTD., FARIDABAD
SAMPLE STAGE 2 (TP ROUTING)
6/8/2011 5/14/2011 5/13/2011
SAMPLE STAGE 1 (APPROVALS/COMMENTS)
6/8/20113 days (transit) 7 days Buyer's approval
5/14/20113 days (transit) 7 days Buyer's approval
5/13/20113 days (transit) 7 days Buyer's approval
SAMPLE STAGE 1 (SUBMISSION)
5/29/20117 days from rect of TP
5/4/20117 days from rect of TP
5/3/201121 days from rect of TP
SAMPLE STAGE 1 (TP ROUTING)
5/22/201130 Days prior to the order confirmation
4/27/201145 Days prior to the order confirmation
4/12/201145 Days prior to the order confirmation
FABRIC APPROVAL 6/19/20111 Wk from Submission
5/25/20111 Wk from Submission
5/2/20111 Wk from Submission
FABRIC QUALITY SUBMISSION TO BUYER (AFTER DOING INTERNAL FPT)
6/12/201121 Days from inspiration swatch rect
5/18/201121 Days from inspiration swatch rect
4/25/201128 Days from inspiration swatch rect
FABRIC INSPIRATION RECVD FOR DEVELOPMENT FROM BUYER
5/22/201130 Days prior to the order confirmation
4/27/201145 Days prior to the order confirmation
3/28/201160 Days prior to the order confirmation