16030-ElectricalTests
-
Upload
engnadeem-uddin -
Category
Documents
-
view
214 -
download
0
Transcript of 16030-ElectricalTests
-
7/29/2019 16030-ElectricalTests
1/8
City of Ceres 16030-1 Electrical TestsWell No. 19R July 2009
SECTION 16030
ELECTRICAL TESTS
PART 1. -GENERAL1.01 DESCRIPTION
A. This section specifies the work necessary to test, commission and demonstrate thatthe electrical work satisfies the criteria of this specification and functions as required
by the Contract Documents.
B. The work of this Section includes furnishing the labor, equipment, and powerrequired to support the testing of equipment specified in other sections of the
specification. Electrical testing specified in Division 16 functional testing of all power
and controls shall be completed before commencement of start-up. This scope of
work may require the Contractor to activate circuits, shutdown circuits, and runequipment, make electrical measurements, replace blown fuses, install temporary
jumpers, etc.
C. Contractor is responsible for all work, equipment damage, power interruptions andschedule delays caused by the testing agency.
1.02 SUBMITTALSA. Results of all testing shall be submitted prior to final project acceptance, per
Specification 01300. Three copies are required to be included as part of final
Operations and Maintenance Manuals. Submittal shall describe test conditions,
weather including temperature and humidity, test date, plant flows, duration of test,
test equipment, tested equipment, testing technician, as found and as-left results,
expected results, actual results, pass/fail status Report based on listed testing
standards and NETA (latest edition) and a registered Professional Engineers stamp
and signature; registered in Electrical Engineering in the State of California. A
Professional Engineer, providing Pass or Fail equipment and system status, as
well as recommendation to allow energizing equipment, shall author Report.
B. Specific data relative to insulation resistance, voltage levels, load currents, relaysettings, dial settings, etc., shall be provided for all equipment and material required
to be tested.
C. Test result shall be submitted in one submittalD. Test reports shall be based on NETAs latest Acceptance Testing Specifications
having a sign-off, pass/fail data filed for each line item covered by NETAs
Acceptance Testing Specifications latest edition.
-
7/29/2019 16030-ElectricalTests
2/8
City of Ceres 16030-2 Electrical TestsWell No. 19R July 2009
1.03 OPERATION AND MAINTENANCE MANUALSA. Include the Electrical Test Result Study and Engineers Report within the Operation
and Maintenance Manuals.
1.04 TESTING ORGANIZATION QUALIFICATIONSA. Testing organization shall be corporately and financially independent of the supplier,
producer and installer of the equipment, who has been regularly engaged in the testing
of equipment for a period of at least 10 years. All testing shall be conducted under the
direct supervision of an electrical Engineer, registered in the State of California. This
registered electrical Engineer will prepare and sign test Reports with values,
recommendations, and comments.
B. Testing equipment required to conduct the specified tests shall be furnished by thetesting organization. Testing equipment shall be in good working condition and
comply with the requirements of this Specification and applicable industry standards.
C. Testing shall be done in accordance with the manufacturer's instructions, theseSpecifications, and applicable NETA Acceptance Testing Specifications, NEMA,
ANSI, NFPA, and ASTM Standards. All testing shall be done in the presence of the
Engineer, and forms shall include space for Engineer sign off at time of test. Testing
organization shall meet Federal OSHA criteria for accreditation of testing
laboratories, Title 29, Part 1907, 1910 and 1936. Membership in the National
Electrical Testing Association constitutes proof of meeting such criteria.
D. The testing organization shall cooperate with any manufacturer's representative thatmay be retained by the Contractor. Testing organization shall be Cutler-Hammer;
Electro-test; Power Systems; General Electric; or equal.
1.05 APPLICABLE CODES, STANDARDS AND REFERENCESA. All inspections and tests shall be in accordance with the following codes and latest
standards as provided otherwise herein:
1. National Electrical Manufacturer's Association - NEMA2. American Society for Testing and Materials - ASTM3. Institute of Electrical and Electronic Engineers - IEEE4. InterNational Electrical Testing Association - NETA Acceptance Testing
Specifications5. American National Standards Institute - ANSI C2: National Electrical Safety
Code
6. State and local codes and ordinances7. Insulated Cable Engineers Association - ICEA
-
7/29/2019 16030-ElectricalTests
3/8
City of Ceres 16030-3 Electrical TestsWell No. 19R July 2009
8. Association of Edison Illuminating Companies - AEIC9. Occupational Safety and Health Administration - OSHA10.National Fire Protection Association - NFPA
B. Inspections and tests shall utilize the following references:1. Project Specifications2. Project Drawings3. Manufacturer's instruction manuals applicable to each particular apparatus
1.06 SAFETY AND PRECAUTIONSA. Safety practices shall include, but are not limited to, the following requirements:
1. Occupational Safety and Health Act Accident Prevention Manual for IndustrialOperations, National Safety Council
2. Applicable state and local safety operating procedures3. Owner's safety practices4. National Fire Protection Association - NFPA 70E5. American National Standards for Personnel Protection
B. All tests shall be performed with apparatus de-energized. Exceptions must be
thoroughly reviewed to identify safety hazards and devise adequate safeguards.
C. The testing firm shall have a designated safety representative on the project to
supervise the testing operations with respect to safety.
1.07 SCHEDULINGA. Perform Electrical Tests after electrical installation is 100% completed.
1.08 LIST OF ITEMS TO BE TESTEDA. Switchboard/Motor Control CenterB. RTU PanelC. PanelboardD. CablesE. System GroundF. Miscellaneous Testing
-
7/29/2019 16030-ElectricalTests
4/8
City of Ceres 16030-4 Electrical TestsWell No. 19R July 2009
PART 2. -MATERIALSNOT USED
PART 3. -EXECUTION3.01 TESTING
A. The following test requirements are intended to supplement test and acceptancecriteria that may be stated elsewhere.
B. Switchboard: Clean equipment prior to testing. Verify lubrication on moving andsliding surfaces.
1. Inspect all devices installed such as breakers, fuses, insulators, barriers, doors,panels, hardware, etc. for physical damage, sizing, and compare equipment
nameplate information with latest one line diagram and report discrepancies.
Inspect and verify anchorage, area clearance and correct alignment. Verify current
and potential transformer ratios, and inspect installation.
2. Test insulation on each bus, phase-to-phase and phase-to-ground with a suitablemegohmmeter.
3. Test insulation of all control and relay field wiring circuits to ground with asuitable megohmmeter.
4. Functional test of all devices, such as circuit breakers, space heaters, relays,switches and alarm points. Confirm correct operation and sequencing of electrical
and mechanical interlock system.
5. Check for proper grounding connections at both ends of assembly. Check forexternal, visible ground lug connections. Check ground bus continuity. Performground resistance tests.
6. Perform current injection tests on entire current circuit in each section ofswitchboard.
7. Check for proper torquing of all bolted connections.8. Calibrate and test all circuit breakers and relays in the switchboard. Test circuit
breakers according to Miscellaneous Testing, this specification. Determine
accuracy of all meters and calibrate as required.
C. Motor Control Center1. Clean equipment prior to testing.2. Inspect for nameplate compliance, physical damage, and proper operation of
alarm and control devices. Inspect and verify anchorage, area clearance, and
proper connections. Verify correct mounting of circuit breakers.
3. Functional test of all devices, such as contactors, relays, switches, solid state
-
7/29/2019 16030-ElectricalTests
5/8
City of Ceres 16030-5 Electrical TestsWell No. 19R July 2009
overloads, protective relays, breakers, indicating lights and meters. Perform
adjustments for final settings in accordance with coordination study.
4. Test insulation of the bus phase-to-phase and phase-to-ground for power busesand phase-to-ground for all control circuits with a suitable megohmmeter.
5.
Test operation of each switch or breaker in each starter assembly. Test doorinterlocking. Test Circuit Breakers according to Miscellaneous Testing, this
specification.
6. Energize space heaters and check operation.7. Check for proper torquing of all bolted connections.8. Verify grounding of lugs, conduit hubs and MCC.9. Contractor shall tabulate the following data for all three-phase motors. Tabulation
shall be submitted to the Engineer at least two weeks prior to performing the
testing specified in this section. Tabulation to include:
a. Motor identification including tag number.b. Motor nameplate full load amps, horsepower, voltages and phase.c. Recommended Motor Circuit Protector (MCP) setting.
10.The work of this section requires that the Contractor record the following data tothe tabulation specified in paragraph above.
a. Measurable amperes when motor is drawing normal process load.b. Changes required to MCP setting.c. Date of test.d. Remarks (i.e. difficulty in motor attaining full speed, abnormal process
conditions, and abnormal line voltage).
D. Remote Terminal Unit (RTU) Panel1. Clean equipment prior to testing.2. Inspect for physical damage, grounding, proper connections, and anchorage.3. Owner shall witness energizing.4. Functional Loop Testing
1) General: The Contractor shall provide the services of factory-trained andexperienced field personnel to perform verification and functional loop testingas described below. The purpose of functional loop testing is to (1) verify field
cabling and wiring; (2) to verify circuits are performing their intended function
by testing individual instrument loops; and (3) to verify radio telemetry
communication. These functional loops consist of the following types; analog,
discrete, and control and logic system. The Contractor shall notify the
-
7/29/2019 16030-ElectricalTests
6/8
City of Ceres 16030-6 Electrical TestsWell No. 19R July 2009
Engineer in writing a minimum of two (2) weeks prior to the proposed date for
commencing functional loop testing. The Resident Engineer and City O&M
personnel will witness all functional loop testing. Each functional loop must
be complete before testing. Partial loops will not be tested.
2) One month prior to testing the Contractor shall submit a functional loop testplan. The plan shall include the list loops to be tested and the type of test foreach loop listed. A loop may have multiple type tests. List all tests
individually.
3) Analog Functional Loop Testing: Verify that each analog loop is operating bysimulating the primary elements output at the instrument using a loop
calibrator. Simulate signals at 0%, 25%, 50%, 75%, and 100% of span.
Record the readings of the loop receiver device(s) (i.e. recorder, indicator,
alarm, PLC point, etc.) on an analog loop test form. For analog output loops
the PLC will be used to force output signals to verify proper function of final
control elements. The test documentation for each analog loop shall consist of
(1) analog test form, (2) Contractor submitted loop drawing, (3) individualinstrument calibration sheets.
4) Discrete Loop Testing: Verify that each discrete instrument loop is operatingby simulating discrete outputs from the primary element of each loop to mimic
device operational function. Verify correct operation of loop receiver
instruments or indicators. The test documentation for each discreet loop shall
consist of (1) discrete loop test form, (2) Contractors submitted loop drawing,
(3) individual instrument calibration sheets.
5) Control & Logic Testing: Verify that each control and logic system isoperating correctly by verifying the operation of each device within that
system. An example would be a pump control circuit as shown on a Contractcontrol wiring diagram. The system being tested must be operational, e.g. a
pump must be ready to run and pump water. Verification of each component
in the system will be documented by circling the component on the
Contractors submitted control and wiring diagram. The test documentation
for each control and logic system test shall consist of (1) control and logic
system test form, (2) Contractors submitted control wiring diagram, (3)
Contract control wiring diagram, (4) individual instrument calibration sheets.
6) All defects and malfunctions disclosed by tests must be corrected and loopretested before final sign-off.
7) Documentation completed during testing will include:a) Instrument Field Calibration Sheetsb) Analog Loop Test Formc) Discrete Loop Test Formd) Control and Logic System Test Form
-
7/29/2019 16030-ElectricalTests
7/8
City of Ceres 16030-7 Electrical TestsWell No. 19R July 2009
8) The Contractor is to bid two days of field service time to accomplish thefunctional loop testing as defined by this Section.
E. Panelboard1. Clean equipment prior to testing.2. Inspect for physical damage, grounding, proper connections, and anchorage.3. Test insulation of the bus phase to phase and phase to ground. Record data.4. Test operation of each circuit breaker.5. Verify nameplate data, panelboard schedule information.6. Check for proper torquing of all bolted connections.7. Verify proper grounding of lugs, conduit hubs, and panelboard.
F. Cables1. Refer to Section 16120 - Wires and Cables, for the testing requirements.2. Perform a shield continuity test by ohmmeter method for instrumentation cables.
Ohmic value shall be recorded.
3. Check for proper termination of cables.G. System Ground
1. Verify each ground system, is installed in compliance with Drawings andSpecifications.
2. Provide ground-resistance tests with a ground-resistance megger at each facility,transformer and motor control center. Use appropriate method (fall of potential,
three-terminal method) to measure ohmic value of ground system to earth(maximum 5 ohms). Verify all equipment ground terminations with respect to
prime point used to establish ohmic value stated above.
H. Miscellaneous Testing1. Insulation Resistance, Continuity, Rotation: Perform routine insulation resistance,
continuity and rotation tests for all distribution and utilization equipment
including all motors horsepower and larger. All testing shall be performed in
the presence of the Engineer. The testing laboratory shall be responsible for
implementing all final settings and adjustments on protective devices and tap
changes. Any system material or workmanship, which is found defective on the
basis of acceptance tests, shall be reported directly to the Engineer. The testinglaboratory shall maintain a written record of all tests and upon completion of the
project, assemble and certify a final test report.
2. Demonstrate that light fixture outlets are switched as indicated on the ContractDrawings. Test photocell and lighting timer switch. Demonstrate that circuitry is
in accordance with panel schedules. Test Ground Fault Interrupter (GFI)
-
7/29/2019 16030-ElectricalTests
8/8
City of Ceres 16030-8 Electrical TestsWell No. 19R July 2009
receptacles.
3. Perform overall system function tests upon completion of equipment tests. Verifycorrect operation of all interlock devices, alarms, sensing devices and indicating
devices. Demonstrate the proper functioning of circuits in all modes of operation,
including alarm conditions and demonstrate satisfactory interfacing with the data
acquisition and alarms system.
3.02 TESTING SEQUENCEA. Setting the breakers and PFR relays is required prior to functional testing and
checking of the electrical components specified in this section.
B. After initial settings have been completed, each system shall be operated in themanual mode and it shall be demonstrated that operation is in compliance with the
Contract. Once the manual mode of operation has been proven, automatic operation
shall be demonstrated to verify such items as proper start and stop sequence of pumps,
etc.
3.03 WITNESS REQUIREMENTSA. All testing shall be witnessed and signed-off by the Owner and Engineer. Each test
sheet must be signed-off prior to submittal.
**END OF SECTION**