AMENDED ENVIRONMENTAL ASSESSMENT REPORT FOR THE PHASE 1 NEW TRANSMISSION LINE TO PICKLE LAKE PROJECT SECTION 8.0: ABORIGINAL AND TREATY RIGHTS AND INTERESTS
August 2018 Project No. 1535751
APPENDIX 8.0A Community Researcher Guide
February 29, 2016
PHASE 1 NEW TRANSMISSION LINE TO PICKLE LAKE
Traditional Land and Resource Study Community Researcher Guide
REP
OR
T
Report Number: 1535751-001-R-RevB
Distribution:
Wataynikaneyap L.P. (email copy) Community Researchers
Submitted to:Wataynikaneyap Power L.P.
COMMUNITY RESEARCHER GUIDE
February 29, 2016 Report No. 1535751-001-R-RevB I
Table of Contents
GLOSSARY/DEFINITIONS ....................................................................................................................................................... II
1.0 INTRODUCTION ............................................................................................................................................................... 1
1.1 The Purpose of This Guide .................................................................................................................................. 1
2.0 WATAYNIKANEYAP POWER ......................................................................................................................................... 3
3.0 PROJECT OVERVIEW ..................................................................................................................................................... 4
3.1 Project Schedule.................................................................................................................................................. 5
4.0 ROLES AND RESPONSIBILITIES ................................................................................................................................... 6
4.1 Community Researchers (CR) ............................................................................................................................. 6
4.2 Wataynikaneyap .................................................................................................................................................. 7
4.3 Golder .................................................................................................................................................................. 7
5.0 THE ENVIRONMENTAL ASSESSMENT ......................................................................................................................... 8
6.0 THE TRADITIONAL LAND AND RESOURCE USE STUDY ........................................................................................... 9
6.1 Working with Land Users ..................................................................................................................................... 9
6.2 Preparing Interviewees ...................................................................................................................................... 10
6.3 Deliverables ....................................................................................................................................................... 11
7.0 CONTACTS .................................................................................................................................................................... 12
8.0 MY QUESTIONS ............................................................................................................................................................. 13
FIGURES
Figure 1: Project Location ......................................................................................................................................................... 2
APPENDICES
APPENDIX A Wataynikaneyap Power Project Environmental Assessment for the Phase 1 New Transmission Line to Pickle Lake Environmental Assessment Workshop 2015
APPENDIX B Consent Form
COMMUNITY RESEARCHER GUIDE
February 29, 2016 Report No. 1535751-001-R-RevB II
GLOSSARY/DEFINITIONS
Alternating Current (AC)
An Alternating Current is an electrical current in which charge changes direction periodically. Alternating Current is used to provide electricity to homes and businesses. Alternating Current voltage is increased or decreased with a transformer.
CCEG A former company that was a grouping of 20 First Nation communities, formerly known as the Central Corridor Energy Group (CCEG) that was formed to initiate the Wataynikaneyap Project.
Connection Facility
A Connection Facility is a part of the electricity distribution system that connects the main distribution system with the customer. It is typically a small building with facilities to interconnect the transmission line and distribution lines.
FortisOntario (Fortis) FortisOntario is a subsidiary of Fortis, an electric and gas utility business with approximately $28 billion in assets, including significant transmission and distribution facilities in Ontario.
Golder Associates Ltd. (Golder)
Golder is global organization providing consulting, design, and construction services in earth, environment, and related areas of energy. Golder is providing consulting services to Wataynikaneyap Power L.P for the environmental assessment.
OEAA Ontario Environmental Assessment Act is provincial regulatory document that provides the authority for a process for reviewing the environmental impact of proposed activities prior to the granting the permits required for construction.
Renewable Energy Systems (RES)
RES provides development, engineering, construction, and operations services to the utility-scale wind, solar, transmission, and energy storage markets across the Americas, and had built over 500MW of renewable energy projects and associated transmission facilities in Ontario.
ROW Right of Way is the area within which the transmission line will be built.
Traditional Land and Resource Use Study
A traditional land and resource use study looks at the way First Nations people use their lands and resources to understand how they may be affected by a Project or development. This is typically done by interviewing users and mapping their land and resource uses.
Transformer Station
A transformer station is a part of an electrical generation, transmission, and distribution system. Transformer stations change voltage from high to low, or the reverse, or perform any of several other important functions. Typically, transformer stations change voltage between the transmission system and the distribution system.
Wataynikaneyap Power L.P.
A grouping of First Nation communities, the Central Corridor Energy Group (CCEG), in partnership with FortisOntario and Renewable Energy Systems (RES) Canada (Fortis-RES), a joint venture, have formed a transmission company, Wataynikaneyap Power L.P. (Wataynikaneyap) to develop, construct, and operate the Wataynikaneyap Power Project.
COMMUNITY RESEARCHER GUIDE
February 29, 2016 Report No. 1535751-001-R-RevB 1
1.0 INTRODUCTION A grouping of 20 First Nation communities, formerly known as the Central Corridor Energy Group (CCEG),
in partnership with FortisOntario and Renewable Energy Systems (RES) Canada (Fortis-RES), have formed
a transmission company, the Wataynikaneyap Power Limited Partnership (Wataynikaneyap) to develop,
construct, and operate the Wataynikaneyap Transmission Project. The Wataynikaneyap Transmission Project is
being developed in two phases. Phase 1, the New Transmission Line to Pickle Lake Project, is a proposed,
approximately 300 kilometre (km) long, 230 kilovolt (kV) transmission line from the Dryden/Ignace area
to Pickle Lake. Phase 1 is currently undergoing an Individual Environmental Assessment (IEA) under the Ontario
Environmental Assessment Act. Phase 2 includes approximately 1,500 km of 115 kV and 44 kV transmission
lines for subsystems north of Pickle Lake and Red Lake that will connect 16 remote First Nation communities
(the Project), currently powered by diesel generation, to the provincial electrical grid. The proposed Phase 1
Project is located in northwestern Ontario near Dryden (Figure 1).
To complete the Environmental Assessment, Golder Associates Ltd. (Golder) has been hired by
Wataynikaneyap as the environmental assessment consultant. Golder is a consulting company that provides
engineering and environmental consulting services. As part of the environmental assessment, Golder conducts a
range of studies to determine the effects of the Project on the environment.
An important component of the environmental assessment is to characterize potential effects to the lands
and resources used by First Nations that are important to their culture and way of life. Wataynikaneyap and
Golder are initiating a traditional land and resource use study with the potentially affected First Nation
communities. Community Researchers within each community will be retained by their respective communities
and First Nation Councils to work alongside Golder to collect this information.
1.1 The Purpose of This Guide The Community Researcher Guide (the Guide) is designed to assist the CR by providing information to build an
understanding of Project, the environmental assessment process, and the study methods and documents that
will be used in the collection of traditional land and resource use information. The Guide will be supplemented by
discussion with the Golder traditional land and resource study specialist, and other technical specialists as
needed, to build an understanding of the Project and environmental assessment for the traditional land and
resource use study.
For clarification, the term “traditional land and resource use study” is being used to describe this process.
This is a common term for studies that document how First Nations people use their homelands, and the
resources that it provides. The term is typically part of the environmental assessment process. The term
“traditional” recognizes the long history that First Nations people have with the land and differentiates it from
non-Aboriginal users. The term “traditional” is not intended to imply that First Nations use of lands and resources
only occurred in the past. This study is primarily targeted at current land and resource users and stewards of
traplines and resource areas.
While this Guide is provided as background information and for reference purposes, it is important the
CR understands that he or she will be supported throughout the study primarily by the Golder study specialist but
also as needed by the Tribal Council representative, and Chief and Council to complete the work.
This page intentionally left blank
")
")
")
")
")
")
")
")
")
")
")
")
")
")
!(
!(
!(
!(
!(
!(
!(
!(
!.
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(!(
!(
!( !(
!(
!(
!(
!(
!(!(
!(
!(
EAGLE DOGTOOTHPROVINCIAL
PARK (WATERWAY CLASS)
!
EAST ENGLISH RIVERPROVINCIAL PARK
(WATERWAY CLASS)
OBONGA-OTTERTOOTHPROVINCIAL PARK
(WATERWAY CLASS)
!
KAIASHK PROVINCIALNATURE RESERVE
!
ST. RAPHAEL LAKEPROVINCIAL PARK
(WATERWAY CLASS)
!
GULL RIVER PROVINCIALPARK (WATERWAY
CLASS)
!
BRIGHTSANDRIVER
PROVINCIAL PARK
!
AARONPROVINCIAL PARK
!
MINNITAKI KAMESPROVINCIAL
NATURE RESERVE
BUTLER LAKEPROVINCIAL
NATURE RESERVE
!
ALBANYRIVER
PROVINCIAL PARK
!
LOLA LAKE PROVINCIALNATURE RESERVE
!OJIBWAYPROVINCIAL PARK
!PANTAGRUEL CREEKPROVINCIAL
NATURE RESERVE
!
PIPESTONERIVER PROVINCIAL
PARK
!
SANDBAR LAKE PROVINCIALPARK (NATURAL
ENVIRONMENT CLASS)
!
TROUT LAKE PROVINCIALNATURE
RESERVE
WABAKIMIPROVINCIAL PARK
!
WINDIGO POINTPROVINCIAL NATURE
RESERVE
KOPKA RIVER PROVINCIALPARK (WATERWAY CLASS)
UPPER ENGLISH RIVERCONSERVATION RESERVE
!
TROUT LAKECONSERVATION
RESERVE
! ADAIR LAKECONSERVATION
RESERVE
LAC SEUL ISLANDSCONSERVATION
RESERVE
!
BROKENMOUTH RIVERCONSERVATION RESERVE
!
HARTH LAKECONSERVATION
RESERVE
!
WHITEMUDCONSERVATION
RESERVE
!
TWILIGHT LAKECONSERVATION
RESERVE
!
GULL-CHRISTINACONSERVATION
RESERVE
!
WILLOW LAKECONSERVATION
RESERVE
!
WEST WABIGOON RIVERCONSERVATION RESERVE
!
BRUCE LAKECONSERVATION
RESERVE
OTTERTOOTHCONSERVATION
RESERVE
!
MELGUND LAKECONSERVATION
RESERVE
!
GARDEN PAKASHKANCONSERVATION
RESERVE
!
AIRPORT ROADCONSERVATION
RESERVE
!
EAST WABIGOONCONSERVATION
RESERVE
!
EAGLE LAKE ISLANDSCONSERVATION
RESERVE
LAC SEUL ISLANDSCONSERVATION
RESERVE
Musselwhite Mine Approximate Distance 150 km from Node G
HWY 516
HWY 17
HWY 72
HWY 642
HWY 599
HWY 17
HWY 105
HWY 5
99
VERMILION RIVER ROAD
SLATE FALLS ROAD
E1CTRANSMISSION LINE
M1MTRANSMISSION LINE
E4DTRANSMISSION LINE
PICKLE LAKE
SUPERIORJUNCTION
!
OSNABURGH HOUSE
Cat Lake
NungesserLake
FawcettLake
BirchLake
LittleVermilion
LakeTroutLake
BamajiLake
Lake St.Joseph
Red Lake
PashkokoganLakeGullrock
Lake
ChurchillLake Miniss
Lake
WhitewaterLake
PakwashLake Wabakimi
Lake
Lac Seul
SavantLake
SmoothrockLake
Lake ofthe Woods
LakeNipigon
SturgeonLakeMinnitaki
Lake
SeseganagaLake
WapikaimaskiLakeLake of
BaysVermilionLake
EagleLake
BellLake
ShikagLake
DryberryLake
SowdenLake
AtikwaLake
Rowan Lake
!
NEW OSNABURGH
WABIGOON
AMESDALE
CAMP ROBINSON
CASUMMITLAKE
COLLINS
GOLDPINES
TRAPPER'SLANDING
UCHILAKE
DRYDEN
SIOUXLOOKOUT
ARMSTRONG STATION
BALMERTOWN
IGNACE
RED LAKE
DINORWIC
HUDSON
MCINTOSH
SNAKE FALLS
ALLANWATERBRIDGE
COCHENOUR
EAR FALLS
REDLAKE ROAD
CAT LAKE
FRENCHMAN'SHEAD
SIX MILE CORNER
CENTRAL PATRICIAPICKLE CROW
SWAINPOST
EAGLE RIVERMINNITAKI
QUIBELL
VERMILIONBAY
GULL BAY
SAMLAKE
MIGISISAHGAIGAN
PERRAULTFALLS
NARROWLAKE
SLATEFALLS
MANITOU FALLS
SOUTHBAY
Slate FallsNation
Savant Lake
Ojibway Nationof Saugeen
Lac Seul First Nation
Cat LakeFirst Nation
Eagle Lake First Nation
Kiashke Zaaging Anishinaabek
MishkeegogamangFirst Nation
WabauskangFirst Nation
Wabigoon LakeOjibway Nation
Whitesand First Nation
500000
500000
600000
600000
700000
700000
5500
000
5500
000
5600
000
5600
000
5700
000
5700
000
G:\P
rojec
ts\20
11\11
-1151
-0456
_Dryd
en_T
o_Pic
kleLa
ke_T
ransm
ission
Line\G
IS\M
XDs\W
orking
\Stak
ehold
erCon
sulta
tion_
Abori
ginalE
ngag
emen
t\Work
Plan\C
ommu
nityR
esea
rcherG
uide\P
rojec
tLoca
tion.m
xd
³LEGEND
Base Data - MNRF LIO, obtained 2015, NTDBCorridor Alternatives - Provided by GENIVAR Mar-Aug 2012Preliminary Proposed 40-m-wide Alignment ROW - Produced by Golder AssociatesLtd. October 24, 2013First Nation Communities from Indian and Northern Affairs Canada ( www.ainc-inac.gc.ca)Produced by Golder Associates Ltd under licence from Ontario Ministry of Natural Resources, © Queens Printer 2008Projection: Transverse Mercator Datum: NAD 83 Coordinate System: UTM Zone 15
Mississauga, Ontario
DESIGN
PROJECT LOCATION
FIGURE: 1PROJECT NO. 11-1151-0456
PROJECT
TITLE
GIS
REVIEW
JMC 10 Oct. 2015
CHECK
WATAYNIKANEYAP POWER PROJECTPHASE 1 NEW TRANSMISSION LINE TO PICKLE LAKE
JMC 26 Jan. 2016SWAE
26 Jan. 201626 Jan. 2016
REFERENCE
SCALE 1:1,100,000
0 10 20 30 40 50 605
Kilometres
") Connection Facility") Transformer Station
Preliminary Proposed CorridorPreliminary Proposed 2-km-wide CorridorPreliminary Proposed Corridor OptionPreliminary Proposed 2-km-wide Corridor OptionCorridor Alternatives Proposed Corridor Alternatives 2-km-wide Corridor
!. City!( Town") First Nation Community
RailwayRoadHighwayWaterbodyProvincial ParkConservation ReserveFirst Nations ReserveMunicipal Boundary
Utility LinesExisting Electrical Transmission LineNatural Gas Pipeline
This page intentionally left blank
COMMUNITY RESEARCHER GUIDE
February 29, 2016 Report No. 1535751-001-R-RevB 3
2.0 WATAYNIKANEYAP POWER The Wataynikaneyap Transmission Project is being developed in two phases. Phase 1, the New Transmission
Line to Pickle Lake Project, is a proposed, approximately 300 kilometre (km) long, 230 kilovolt (kV)
transmission line from the Dryden/Ignace area to Pickle Lake. Phase 1 is currently undergoing an Individual
Environmental Assessment (IEA) under the Ontario Environmental Assessment Act. Phase 2 includes
approximately 1,500 km of 115 kV and 44 kV transmission lines for subsystems north of Pickle Lake and
Red Lake that will connect 16 remote First Nation communities (the Project), currently powered by diesel
generation, to the provincial electrical grid. Wataynikaneyap means “line that brings light” in Anishiniiniimowin,
named by the Elders who provided guidance to the partners. The company’s vision is to provide accessible and
affordable power to residents, businesses, and industry in the region, realizing opportunities for First Nations.
Wataynikaneyap is working with FortisOntario and RES Canada (Fortis-RES) to develop the project.
The objectives of Wataynikaneyapinclude the following:
Establish a First Nation led Transmission Company to improve transmission service to Pickle Lake and
connect 16 remote First Nation communities to the provincial electricity grid.
Provide clean and accessible power for residents, businesses, and industry in the region.
Realize economic opportunities for First Nations in the construction and operation of the Transmission Line.
Provide a market for First Nation power generation initiatives.
COMMUNITY RESEARCHER GUIDE
February 29, 2016 Report No. 1535751-001-R-RevB 4
In December 2014, Wataynikaneyap initiated a process to select a qualified transmission partner. Through a
competitive review of qualified proposals, Wataynikaneyap selected the Fortis-RES Partnership for exclusive
negotiation, and entered into a Partnership Agreement for the purpose of developing and operating the
transmission facilities.
The Fortis-RES Partnership will work with Wataynikaneyap to manage the Partnership and invest in the project,
while the 20 First Nations of Wataynikaneyap will remain majority owners and have the option to become
100% owners over time.
3.0 PROJECT OVERVIEW It is important that the CR have an understanding of the need for the Project, the basic elements of the Project,
and the Project location. The CR is not expected to have a detailed understanding of the Project and its
components. Detailed questions can be referred back, firstly, to the Golder study specialist or, subsequently,
the Tribal Council representatives or Wataynikaneyap..
The CR will be provided with local small scale and regional large scale maps to assist them with an
understanding of the Project location and illustrate the location of the transmission line and associated
components (e.g. temporary construction camps, connection facilities) to prospective interviewees. The CR is
encouraged to learn as much as possible about the Project and resources will be provided for further reading.
The proposed Project includes the construction, operation and maintenance, and retirement1 of a proposed
alternating current (AC) electricity transmission system in northwestern Ontario. The proposed Project includes
the following main components (see slides 8-11 in Appendix A).
The corridor for considering where the transmission line will be built is approximately 2 km wide.
The studies for routing the line and the environmental assessment will be conducted on the 2 km wide
corridor and the line will be placed within it. However, the actual area that will be cleared, and where the
transmission line will be built and operated, will be 40 metres (120 feet) wide (See slides 8 and 9
Appendix A).
An overhead alternating current transmission line will be built within the 40 metre-wide cleared area
(see slide 9 Appendix A). Associated components will be located within a 2 km-wide corridor approximately
300 km in length (from near Dinorwic or Ignace to Pickle Lake). Based on the outcome of a preliminary
corridor routing analysis and results of engagement, three corridors where the transmission line could be
placed have been identified. The three corridors are identified in Figure 1. They are as follows:
a preliminary proposed corridor originating in Dinorwic (east of Dryden), and extending north to
terminate at Pickle Lake;
and two corridor alternatives originating in the Ignace area, as follows:
1 Retirement as applicable to the Project components (e.g., poles).
COMMUNITY RESEARCHER GUIDE
February 29, 2016 Report No. 1535751-001-R-RevB 5
Corridor Alternative A – a corridor alternative that travels west around Mishkeegogamang
First Nation extending north to terminate at Pickle Lake, and
Corridor Alternative B – a corridor alternative that travels east through Mishkeegogamang
First Nation and also terminates at Pickle Lake.
a connection facility to serve as a connection between the Project transmission line and an existing 230 kV
line owned and operated by Hydro One. The connection facility for the preliminary proposed corridor is
proposed to be located at Dinorwic, and the connection facility for the two Ignace to Pickle Lake corridor
alternatives is proposed to be located approximately 20 km west of Ignace (see slide 10; Other Project
Components in Appendix A);
a transformer station and ancillary components are proposed at Pickle Lake to provide for connection and switching of the new 230 kV AC transmission line to the existing Hydro One (E1C) and the Musselwhite Mine (M1M) transmission lines (see slide 10; Other Project Components in Appendix A); and
temporary structures (see slides 11; Project Construction in Appendix A) associated with construction, including but not limited to construction camps, access roads, laydown areas, water crossings, waste management and staging areas.
The connection facility for the preliminary proposed corridor will be constructed at Dinorwic, east of Dryden, and the connection facility for the two Ignace Area corridor alternatives would be constructed approximately 20 km west of Ignace. From there, the corridors will travel north approximately 300 km to a transformer station to be constructed at Pickle Lake. The majority of the Project traverses Ontario’s Crown forest, which is divided into four (4) forest management units. From south to north, the preliminary proposed corridor (Dinorwic-Pickle Lake) crosses the Dryden, Wabigoon, English River and Lac Seul Forest Management Units. From south to north, the corridor alternatives (Ignace-Pickle Lake) cross the Wabigoon, East English River and Caribou Forest Management Units.
A preferred corridor for the transmission system will be identified based on the results of the environmental studies, technical criteria and construction cost. The corridor for considering where the transmission line will be built is 2 km wide. The studies for the environmental report will be conducted on the 2 km wide corridor and the transmission line will be placed within it. However, the actual area that will be cleared and where the transmission line will be built and operated will only be 40 metres wide.
3.1 Project Schedule The presentation provided in Appendix A was presented to communities over the summer of 2015. The schedule
has evolved since that time. A new Project schedule has been added for reference.
A number of things can influence the schedule and it is subject to change. Please speak with the Study
Specialist if you have further questions.
COMMUNITY RESEARCHER GUIDE
February 29, 2016 Report No. 1535751-001-R-RevB 6
4.0 ROLES AND RESPONSIBILITIES The following section provides a description of the roles and responsibilities for the Traditional Land and Resource Use Study for each of Wataynikaneyap, Golder and the CRs. The roles and responsibilities were developed to provide clarity to Chief and Council. The information provided to Chief and Council is listed below. There may be some differences in the responsibilities once discussions with community leadership have taken place, or the contracting relationship for the CR has been established. The studies will be tailored according to each community’s interests and preferences.
4.1 Community Researchers (CR) The role of the CRs is to facilitate the information gathering process with community members. In this role,
each CR will do the following:
With support from the Golder study specialist, develop an understanding of the Project, the environmental
assessment and the need for data collection;
Communicate regularly (by either phone or email) with the Golder study specialist on progress and
communicating challenges with data collection;
Liaising and reporting with Chief and Council and Band Office staff as required;
Identify existing information in the community that may have been already collected and arrange for access
for Golder;
Identify and contact participants, individuals or families who may be land users, trappers or harvesters;
Provide input on methodology for data collection and the appropriate questions to ask in data collection;
Meet with participants to explain the study and verify their knowledge or use of the area;
Explain consent prior to the data collection interview with Golder;
Arrange a venue and time in the community for interviews to be held with participants and the CR within a
two day period;
Arrange for translation services if needed;
Arrange for Elder care if needed (assistance to Elders to allow them to participate);
Facilitate interviews with participants (introduce Golder study specialist, assist with interview when needed);
Verify information with participants once digitized and mapped;
Provide hard copy maps to Golder with any proposed revisions, if required.
COMMUNITY RESEARCHER GUIDE
February 29, 2016 Report No. 1535751-001-R-RevB 7
4.2 Wataynikaneyap Wataynikaneyap, through its member First Nation Councils, will be responsible for working with the communities
to develop a contracting and hiring process for the CRs to assist with data collection, which will include the
following tasks:
First Nation Council representatives will maintain oversight of CR, Golder, and the data collection process
and deliverables;
Arrange contract with sufficient liability protection for hiring of CRs;
Provide a job description for the community researcher;
Manage the hiring process with the community for the CRs;
Manage the invoicing process with the community;
Explain Golder’s role in the data collection;
Coordinate with Golder and the community if needed to manage any issues with the CRs;
Provide contact information for the CRs to Golder;
Work with communities to identify translation services during interviews; and
Administering honoraria if required.
4.3 Golder For this study, Golder will be communicating with the CRs, providing information about the Project and the
environmental assessment, and providing guidance in the data and information collection process. In this role,
Golder will be responsible for the following tasks:
Providing and explaining information to the community and the CR’s on the Project and requirements for
data collection for the EA;
Discuss methodology with the CRs, and seek input on proposed methodology;
Provide consent forms for study participants and review with the CRs;
Work with the CRs to identify land users and provide advice on engagement strategies as needed;
Develop questionnaire to use with the participants to collect relevant data and information;
Travel to eight communities to conduct interviews at sessions arranged by the CRs;
Review consent to participate in the study and obtain consent to collect data and information;
Document information on maps with participants in accordance with standard methodologies;
Provide supplies for interviews (e.g., maps, pens, recording device, consent forms);
Provide information once digitized and mapped to the CRs to review and verify with participants;
COMMUNITY RESEARCHER GUIDE
February 29, 2016 Report No. 1535751-001-R-RevB 8
Discuss concerns about the Project and how it may affect participants’ land and resource use;
Digitize information and provide to Wataynikaneyap for discussion in Project design;
In discussion with Wataynikaneyap, identify mitigations for land and resource use;
Identify outstanding concerns to Wataynikaneyap for further consideration; and
Provide information once digitized and mapped to the CRs to review and verify with participants;
Provide information, including process and results, for the EA Report. The details of specific traditional use
data and information to be included in the EA Report will be dependent on consent by the participants;
and a review by the First Nation Councils.
5.0 THE ENVIRONMENTAL ASSESSMENT The traditional land and resource use study is being conducted as part of the environmental assessment for the
Phase 1 New Transmission Line to Pickle Lake. The environmental assessment is a requirement under
the OEAA, and it is a project planning tool that is used to:
Predict and minimize or avoid environmental effects before they happen
Incorporate environmental factors and public feedback into project design and decision-making
The environmental assessment includes:
A description of the proposed Project
A description of the existing environment (Baseline studies)
Aboriginal and stakeholder engagement to discuss and receive input on issues and concerns
Consideration of Project alternatives, including advantages and disadvantages
Identification of potential environmental effects
Identification of impact management measures to mitigate and manage identified potential environmental
effects
Recommendations for follow-up monitoring
Wataynikaneyap has completed the Terms of Reference stage of the EA process; and has commenced the EA
stage. The Terms of Reference can be found at the Wataynikaneyap website at
http://www.wataypower.ca/node/28.
Additional Information is provided in the presentation in Appendix A. A similar presentation was used in the last
round of engagement with communities on the environmental assessment process and it introduced the
collection of information about land and resource use for traditional purposes.
COMMUNITY RESEARCHER GUIDE
February 29, 2016 Report No. 1535751-001-R-RevB 9
6.0 THE TRADITIONAL LAND AND RESOURCE USE STUDY This section will present information on the traditional land and resource use study and the proposed study
methods.
The purpose of the traditional land and resource use study is to build an understanding of how community
members are using the land and its resources for hunting, fishing, trapping and harvesting. It also aims to
identify any other concerns about resources such as cultural resources (e.g. hunting cabins, sacred sites,
archaeological sites). If study participants have specific knowledge of these resources that they are willing to
share, we will consider this information in the studies being prepared for the environmental assessment.
For example, if a community member has specific knowledge about moose migration patterns, we will consider it
in the studies.
While we recognize that community members may have a deep and broad knowledge of their homelands, for the
purposes of this study the focus will be on the area that may be affected by the construction, operation and
maintenance of the Phase 1 transmission system. It is of utmost importance that we communicate respect to
community members who may share their knowledge and experience.
The CR has a key role in the collection of the information. The CR should communicate with band lands and
resources staff to determine if land and resource use information has been previously collected in the vicinity of
the Project. This information is often collected as part of land use planning processes or because other projects
(such as a mine or dam project) has been built nearby. Accessing this information, if it is available, is a critical
step as it will help focus interviews with land users.
The CR will be responsible for identifying land users, explaining the location of the project, and making a request
that they participate in the interview process.
6.1 Working with Land Users There are a number of ways to identify potential land users that may need to be interviewed with respect to the
Project area. As the CR it is assumed that you will have a good knowledge of the individuals and families within
your community and whether they may be using the land or have knowledge about resources that could be
affected by the construction, operation and maintenance of the Phase 1 transmission line. There are other ways
that you may identify community members to interview and the Golder specialist will discuss these with you
through the course of the study. Some suggestions are:
Speaking with leadership, Elders, and lands and resource staff
Putting up notices with maps in the band office, community centre, or post office
Making radio announcements if available in your community
Making announcements at community meetings and functions, particularly where elders meet
Once you have identified potential users, it is important that you set up a time to meet with them to explain more
about the project and the study. The Golder study specialist will help you to prepare with what to say to potential
interviewees. You will need to explain some information about the Project and show them a map of the location
of the transmission lines. You will need to explain why the information is important and that they will be
COMMUNITY RESEARCHER GUIDE
February 29, 2016 Report No. 1535751-001-R-RevB 10
interviewed. It is important that you communicate that the interview is by their consent, and also that their name
and any land and resource information that they choose to share will be kept confidential if they wish. A sample
of the consent form is in Appendix B.
The CR is responsible for arranging a place and time to meet with the potential interviewee (or their family) if they have information to share about their land use. If possible, it is best to arrange all the interviews on a single day at a single location such as a room in the band office or community centre (If there are a larger number of interviewees, the interviews can be arranged over a two day period). The Golder study specialist will meet with them and conduct the interview. The Golder study specialist, with permission from the interviewee, may record the interview. The Golder study specialist will review the Project and discuss consent for the study. The Golder study specialist will ask a series of questions to better understand land and resource use and the individual’s knowledge of the area. They will ask the interviewee to mark areas of use on a map and will record all of the information.
The Golder study specialist will speak with the CR by phone and/ communicate by email on a regular (weekly basis) to support the study and timing of the interviews. The Golder specialist will answer any questions the CR may have and will request information on how contacting community members is proceeding. They will develop a schedule with the CR for the interviews based on the number of interviewees, their availability, and a schedule that is workable for the Golder study specialist.
The CR is also responsible for arranging Elder care if needed (so that Elders can travel to the interview). The CR will attend the interviews and provide assistance to the interviewees as needed. Interviews will be conducted in English. The CR will provide translation or arrange for translation if needed, during the interview.
Honoraria will be provided to interviewees if agreed upon by Chief and Council.
6.2 Preparing Interviewees The Golder study specialist will be asking questions of interviewees. The CR should help prepare the interviewee by explaining the types of questions that may be asked. Each person interviewed will be asked some questions about their birthdate and family to understand who they are related to and who they may be harvesting resources with. The study specialist will ask questions that are specific to their land and resource use. For example, if the study specialist is interviewing a trapper, she will be asking questions specific to that activity such as:
What animals are you trapping?
What time of year do you go trapping in the
area?
Do you trap every year?
What do you do with the animals you trap?
There will be additional questions but this list provides examples only.
The information that the interviewee supplies will guide the questions asked in the interview. Additionally, the study specialist will want to know about other subjects such as:
Archaeological Sites;
Spiritual or cultural sites;
Any specific knowledge of plants or animals in
the area (such as migration patterns or fish
spawning);
Plants of importance; and
Other important landscape features:
Are there other people we should speak
with about this area?
COMMUNITY RESEARCHER GUIDE
February 29, 2016 Report No. 1535751-001-R-RevB 11
The CR should prepare the interviewee by letting him or her know that we will be asking about these subjects.
The interviewee may wish to speak with others prior to the interview to prepare, although this is not necessary.
6.3 Deliverables Please note that the timeline provided is an estimate only and will depend on scheduling by the CR, study
specialist, and interviewees. The study must be completed by March 31, 2016.
Table 1: Deliverables
Deliverable Tasks Timeline
Deliverable 1 Initiation
Develop an understanding of the Project, the
environmental assessment and the need for data
collection;
Identify existing information in the community that may
have been already collected and arrange for access for
Golder;
Identify and contact participants, individuals or families
who may be land users, trappers or harvesters;
Provide input on methodology for data collection and the
questionnaire;
First Nation to hire a qualified Community Researcher
(CR) to complete the work.
Deliverables:
Identification of participants
Existing information relevant to the study
Host one radio show and visit 10 people to discuss the
project.
Administer Community Researcher wages.
February 15
Deliverable 2 Interviews
Meet with participants to explain the study and verify their
knowledge or use of the area;
Explain consent prior to the data collection interview with
Golder;
Arrange a venue and time in the community for interviews
within a two-day period, if possible;
Arrange for translation services if needed;
Arrange for Elder care if needed (i.e., assistance to Elders
to allow them to participate);
Facilitate interviews with participants (i.e., introduce
Golder, assist with interview when needed);
Conduct 10 interviews, if required to collect additional
information.
February 29, 2016
COMMUNITY RESEARCHER GUIDE
February 29, 2016 Report No. 1535751-001-R-RevB 12
Table 1: Deliverables
Deliverable Tasks Timeline
Deliverable 3 Information Verification
Verify information with participants once digitized and
mapped
Provide hard copy maps to Golder with any proposed
revisions to information collected, if necessary
Deliverable (if necessary):
Hard copy of maps with any proposed revisions resulting
from verification.
March 11, 2016
Deliverable 4
Communicate regularly (by either phone or email) with a representative of Golder on progress and communicating challenges with data collection; Liaising and reporting with Chief and Council and Band Office staff as required
Deliverable: Feedback from Chief and Council and / or Band Office with respect to the study to Wataynikaneyap Power L.P.
Initiation to March 31, 2016
Deliverable 5 Invoicing
Submit activity reports and invoices to supervisor & [insert First Nations Council name] upon completion of deliverables.
March 31, 2016
7.0 CONTACTS
Wataynikaneyap/First Nations Council Leads: Golder Contacts:
Independent First Nations Alliance Mary Bea Kenny 807-626-7735
Windigo First Nations Council Breann Brunton 807-737-1585
Shibogama First Nations Council Donna Brunton 807-737-2662
Sandra Witt Study Specialist 604-679-3020 (Note Sandra is based in Vancouver so it is best to call in the afternoons)
Allen Eade Environmental Assessment Project Manager 905-567 6100 Ext 1295
COMMUNITY RESEARCHER GUIDE
February 29, 2016 Report No. 1535751-001-R-RevB 13
8.0 MY QUESTIONS
_________________________________________________________________________________________
_________________________________________________________________________________________
_________________________________________________________________________________________
_________________________________________________________________________________________
_________________________________________________________________________________________
_________________________________________________________________________________________
_________________________________________________________________________________________
_________________________________________________________________________________________
_________________________________________________________________________________________
_________________________________________________________________________________________
_________________________________________________________________________________________
_________________________________________________________________________________________
_________________________________________________________________________________________
_________________________________________________________________________________________
_________________________________________________________________________________________
_________________________________________________________________________________________
_________________________________________________________________________________________
_________________________________________________________________________________________
_________________________________________________________________________________________
_________________________________________________________________________________________
_________________________________________________________________________________________
_________________________________________________________________________________________
_________________________________________________________________________________________
_________________________________________________________________________________________
_________________________________________________________________________________________
_________________________________________________________________________________________
_________________________________________________________________________________________
_________________________________________________________________________________________
_________________________________________________________________________________________
_________________________________________________________________________________________
_________________________________________________________________________________________
c:\users\hpeters\documents\other work\11-1151-0456_goldcorp_nw transmission pickle lake\watay power\phase 1 community researcher guide\1535751-001-r-revb-community researcher
guide 29feb16.docx
This page intentionally left blank
COMMUNITY RESEARCHER GUIDE
February 29, 2016 Report No. 1535751-001-R-RevB
APPENDIX A Wataynikaneyap Power Project Environmental Assessment for the Phase 1 New Transmission Line to Pickle Lake Environmental Assessment Workshop 2015
Wataynikaneyap Power ProjectEnvironmental Assessment for the
Phase 1 New Transmission Line to Pickle Lake 2015
Purpose of the Requested Community Workshop/Information Session
To share information about the Environmental Assessment process with First Nations
To listen to your concerns about the Project
To collect information for the Environmental Assessment and to help design the Project
What is an Environmental Assessment?
Requirement under the Ontario Environmental Assessment Act
Important planning tool and process:
Identifies potential effects and positive benefits of the Project on the environment
Identifies direct, indirect and cumulative effects
Identifies how to reduce or remove potential effects or enhance positive benefits (e.g., through the Project design)
Contributes to a responsible environmental decision-making process
Provides opportunity to comment on how the Project may affect you and your use of the land
What is Considered in an Environmental Assessment?
Slide courtesy of Nathalie Osipenko from the Ministry of Environment and Climate Change
EA Status Update
Baseline studies along preliminary proposed corridor completed in 2012
Terms of Reference (ToR) stage:
Draft and Final ToR were prepared 2012 through 2013
ToR included preliminary corridor routing analysis
In response to comments received on the Draft and Final ToR, the Final ToR was amended to include environmental assessment on preliminary proposed corridor and corridor alternatives
Amended ToR approved by the Ministry of the Environment and Climate Change (MOECC) in February 2015
Commencing EA stage
Environmental Assessment Status and Schedule
7
Overview of a Transmission Line Project
Construction and operation of a transmission line system
The system includes:
Transmission Line: towers, foundations and lines
Transformer Station
Connection Facility
Temporary access roads, construction camps, areas for equipment during construction
Land cleared for construction and operation
120 feet permanent clearing for the transmission
line within 6,562 feet corridor, which is the focus
study area for the environmental assessment
8
Transmission Line
9
Example of transmission line
Example of transmission line 120 feet right of way
clearing
Other Project Components
10
Example of Connection Facility
Example of Transformer Station
Project Construction
11
Example of construction camp Example of construction
clearing for a transmission line
Example of construction and parts of transmission
line
Discussion and Input
We need your input and feedback
We will provide transmission line maps for review and discussion
Study team members will speak to the community about:
Their concerns and issues
What land would you be able to share for the project
What is important to you for the Environmental Assessment
Your use of the land
Knowledge you can share to help the Environmental Assessment and the Project design
Traditional Knowledge and Land Use
Traditional knowledge and input from engagement will be used to understand the environment
What land would you be able to share for the Project?
Will help to determine how the Project will affect First Nations homelands and land use
Will inform the biological and social studies
Will improve the Environmental Assessment
Your input will help to design the Project
How Do We Assess The Effects?
An environmental assessment looks at potential effects of the Project from:
Construction
Air and noise from machines and equipment
Clearing of land for the Project (e.g., transmission line)
Waste
Operation and Maintenance
Routine maintenance
Vegetation management
Noise from the transmission line and other equipment
Electromagnetic fields
14
Project – Environment Effects
Predict and assess how the Project changes the environment
Identify connections between the Project and environment
Project construction activities could remove wildlife habitat
Project construction activities that create noise could affect wildlife
Wildlife and Wildlife HabitatChange to wildlife and wildlife habitat could affect hunting
More Opportunities for First Nations to Participate
Provide comments on the web site: http://www.wataypower.ca/
Participate in the requested community input workshop: provide information on maps and provide your comments.
Provide comments to Chief and Council
Provide comments to your Tribal Council
Provide information on the feedback forms at the workshop
Contact the Ministry of the Environment and Climate Change during comment periods
Dave Bell, Environmental Approvals Branch
Phone: 416-314-7232Toll free: 1-800-461-6290
Speak with the Project contacts (John Cutfeet, John Reid or Allen Eade)
A follow-up Newsletter will be provided to discuss the workshop results
There will be further community engagement (Round 3-Part 2) on the results of the environmental assessment
Contacts
John Reid Project Management Office Central Corridor Energy GroupTel: (613) [email protected]
John CutfeetCommunications Officer Wataynikaneyap PowerTel: (807) [email protected]
Allen Eade Project Manager for EA Golder Associates Ltd.Tel: (905) 567-4444 [email protected]
Questions?
COMMUNITY RESEARCHER GUIDE
February 29, 2016 Report No. 1535751-001-R-RevB
APPENDIX B Consent Form
New Transmission Line to Pickle Lake Declaration of Informed Consent and Permission to Use Information
I (name) _______________________, on this day (complete date)_________________________, give permission for Wataynikaneyap Power to interview me and record my data for the Environmental Assessment study of the New Transmission Line to Pickle Lake.
I understand that this information is being collected by Wataynikaneyap Power, and their representatives (Golder Associates Ltd.) from community members during this information session. The purpose of collecting the information is to provide Wataynikaneyap Power with information that will help them understand potential concerns with the land, water, and animals as well as concerns about cultural activities and places with respect to the proposed transmission corridors. This information will be used for the following purposes:
1) to help fulfill regulatory requirements of the environmental assessment with engagement on the project, 2) inform project design so that changes can be considered to reduce harmful effects, and 3) inform studies of species and lands of concern and how they may be affected by the project.
By signing below, I indicate my understanding that:
1) I give my consent to have my words and responses regarding my land use knowledge and my past and current traditional knowledge of the environment recorded on maps, in notes and using audio recording equipment.
2) Circle one: I agree I do not agree to have photographs taken of me and that these may be used in study materials (e.g. reports, webpage) by Wataynikaneyap Power.
3) I can remain anonymous such that my name is protected, that I will not be identified by name in any reports using information obtained from this interview, and that my confidentiality as a participant in this study will remain secure.
4) I am free to not respond to questions and to stop the interview at any time without consequences. 5) All collected information will be available to the community and may be used by them for further studies
and to help determine community member’s impacts. 6) I will retain all intellectual property rights over information and recordings collected through my
participation. 7) In the event of my death, Wataynikaneyap Power will make reasonable efforts to engage my family
members before using my information for purposes not detailed above. 8) I have read and understand the explanation provided to me in English, Oji-Cree, or Ojibway. I have
had all my questions answered to my satisfaction.
Signature of Participant
Signature of Researcher
____________________________ ____________________________