12 Feb 2020 Unlocking Facility Value Through Life Cycle Thinking Presenters: Prof. Rodney Stewart, Dr. Sherif Mostafa and Dr. Emiliya Suprun Griffith University

Transcript of 12 Feb 2020 Unlocking Facility Value Through Life Cycle ... · functions including remote visual...

Page 1: 12 Feb 2020 Unlocking Facility Value Through Life Cycle ... · functions including remote visual checking, safety training, asset identification, model creation for later refurbishments,

12 Feb 2020

Unlocking Facility Value Through Life Cycle Thinking

Presenters: Prof. Rodney Stewart, Dr. Sherif Mostafa and Dr. Emiliya Suprun

Griffith University

Page 2: 12 Feb 2020 Unlocking Facility Value Through Life Cycle ... · functions including remote visual checking, safety training, asset identification, model creation for later refurbishments,

Agenda• Part 1 - BIM (Digital Twin) Transition Documentation and

Planning – Case of Seqwater Journey – Rodney Stewart (5 mins)

• Part 2 - Case Study 1: Seqwater Canungra Water Treatment Plant - Back-building digital twins of water assets – Getting the LOD-LOI business case right – Sherif Mostafa (5 mins)

• Part 3 - Case Study 2: QLD Government Department of Housing and Public Works – Evaluating the Benefits of BIM for life cycle asset maintenance of remote government housing – Emiliya Suprun (5 mins)

• Questions (5 mins)

2

Page 3: 12 Feb 2020 Unlocking Facility Value Through Life Cycle ... · functions including remote visual checking, safety training, asset identification, model creation for later refurbishments,

Part 1: BIM (Digital Twin) Transition Documentation and Planning

Not terribly novel stuff – But worth mentioning that knowing what you want from BIM to meet your organisational goals and specifying it to your supply chain is essential before embarking on this BIM journey – else business value may be destroyed by the technological disruption

3

Page 4: 12 Feb 2020 Unlocking Facility Value Through Life Cycle ... · functions including remote visual checking, safety training, asset identification, model creation for later refurbishments,

4

BIM and Digital Asset Management Strategy

The Lifecycle of the Digital and Physical Asset

Making BIM Level 2 ‘Business As Usual’

Drawings and models are always going to be important. However, for asset management that goes beyond the design and construction period, it is the data that is important

Page 5: 12 Feb 2020 Unlocking Facility Value Through Life Cycle ... · functions including remote visual checking, safety training, asset identification, model creation for later refurbishments,

BIM (Digital Twin) Roadmap Workshop and Report for Seqwater

5

Workshop Facilitators:

Brian Smith (Director, Optimised Maintenance, optimisedmaintenance.com)Brian leads Optimised Maintenance to work with businesses in improving the understanding and execution of their assets by optimising the asset management practices.

Richard Simpson (Director, Meta Moto, metamoto.com.au)Richard leads Meta Moto leveraging over 25 years’ international experience advising in the development, implementation, and delivery of strategic assignments including geo-spatial and BIM projects.

Rodney Stewart, Emiliya Suprun and Sherif Mostafa (Research Team, Griffith University, https://www.griffith.edu.au/cities-research-institute/)The GU team are researchers in digital transformation research. Conduct industry collaborative research projects on the technical and management aspects of digital transformation with a specific focus on the utility sector.

Page 6: 12 Feb 2020 Unlocking Facility Value Through Life Cycle ... · functions including remote visual checking, safety training, asset identification, model creation for later refurbishments,

6

Roadmap WorkshopBusiness UnitsAsset ManagementAsset Systems and Information GovernanceAsset Lifecycle PlanningEngineering Standards and AssuranceAsset PlanningOperations - Supply SystemAsset MaintenanceMaintenance PlanningPlanning, Operations, DeliveryProcess EngineeringWater QualityProject SupportProgram DeliveryOTE Assurance and PerformanceOTE Strategy and PlanningOTE DeliverySpatial ServicesArchitecture and SecurityProperty ServicesCommercial ServicesStrategic SourcingWork Health and SafetyCustomer, Strategy & PlanningIntegrated Master PlanningProject DevelopmentMore!!!!

Page 7: 12 Feb 2020 Unlocking Facility Value Through Life Cycle ... · functions including remote visual checking, safety training, asset identification, model creation for later refurbishments,

7

BIM Roadmap Workshop – Process Structure

Identify Define the Business Case•What is our Current State?•What is our Required State?•How are these measure?•What is the gap?

How do we get from our current state to our required state?•Define the change performance

measures (KPIs). Use business risk terms.

•Define how to measure risk assessment inputs.

•Ensure all risks to the business are documented and performance gap defined.

AssessDefine the Change Requirement•Why is our current state the way it

is?•What needs to change?

Define the Gap Assessment•The difference between the

current state and the required state.

Road Map•How do we get there?•What are the steps?

ImproveMake the change

•Execute the Road Map•Apply structured Management of

Change•Ensure the changes are

documented, risk assessed and approved before they are executed.

ReviewBusiness Case•Are the risks managed?•Have we met KPIs?

Additional Work•Has the change been successful?•Are any further works required?

Risks•Have the risks identified in the

business case been effectively managed?

•Have any new risks been introduced?

•Are they effectively managed? How do we measure and control this?

Conducting Activities for Each Step

Page 8: 12 Feb 2020 Unlocking Facility Value Through Life Cycle ... · functions including remote visual checking, safety training, asset identification, model creation for later refurbishments,

8

BIM Implementation – Key Lessons Learned (Critical Success Factors)

• Unnecessary modelling of data to the nth degree (Organisation has a good understanding of theright LOD-LOI requirements that will add value to business functions)

• Lack of integration of systems and failure to update models (Strategy and requirements mustconsider all of the organisations’ information systems and seamless transfer between them)

• Failure to implement a proper change management program for the technological improvementopportunity (Strategy adequately considers people, constraints, organisational structure, etc.)

• Don’t try to change everything at once (Strategy stages transition sensibly and targets best valueopportunities first, and measured benefits are used to further enhance buy-in from employees)

• Not fully knowing and/or failing to properly communicate to the entire supply chain how theorganisation wants information provided to it (Comprehensive digital strategy with EIR, etc.)

• Not sufficiently considering software data compatibility, standards and ownership (Strategy ensuresthat new and old systems can talk to other and that data is owned by the organisation and not aprovider).

• Particular software solution driving the strategic planning of the organisation (Organisationconsiders the opportunities, constraints and gaps first and then selects software solutions fittingtheir strategy)

Page 9: 12 Feb 2020 Unlocking Facility Value Through Life Cycle ... · functions including remote visual checking, safety training, asset identification, model creation for later refurbishments,

9

Canungra WTP A showcase of Laser Scan Integrated BIM

Part 2: Case Study 1: Seqwater Canungra Water Treatment Plant

Dr Sherif Mostafa

Back-building digital twins of water assets –Getting the LOD-LOI business case right

Page 10: 12 Feb 2020 Unlocking Facility Value Through Life Cycle ... · functions including remote visual checking, safety training, asset identification, model creation for later refurbishments,

10

Step 1: LiDAR Scanning

Page 11: 12 Feb 2020 Unlocking Facility Value Through Life Cycle ... · functions including remote visual checking, safety training, asset identification, model creation for later refurbishments,

Step 2: Object Recognition and Validation

11

Page 12: 12 Feb 2020 Unlocking Facility Value Through Life Cycle ... · functions including remote visual checking, safety training, asset identification, model creation for later refurbishments,

Step 3: Asset Data Using Different LOD & LOI

SCENE Webshare Plant 3D Revit12

Page 13: 12 Feb 2020 Unlocking Facility Value Through Life Cycle ... · functions including remote visual checking, safety training, asset identification, model creation for later refurbishments,

BIM 360 Ops for Common Data Environment

13

Page 14: 12 Feb 2020 Unlocking Facility Value Through Life Cycle ... · functions including remote visual checking, safety training, asset identification, model creation for later refurbishments,

Step 4: Costs of BIM integration

14

Page 15: 12 Feb 2020 Unlocking Facility Value Through Life Cycle ... · functions including remote visual checking, safety training, asset identification, model creation for later refurbishments,

Step 5: Benefits of BIM Integration to the BAU

Most valuable benefits

15

Page 16: 12 Feb 2020 Unlocking Facility Value Through Life Cycle ... · functions including remote visual checking, safety training, asset identification, model creation for later refurbishments,

Stakeholders’ BIM Life Cycle Stage Relevance

16

Page 17: 12 Feb 2020 Unlocking Facility Value Through Life Cycle ... · functions including remote visual checking, safety training, asset identification, model creation for later refurbishments,

Laser Scan Integrated BIM Cost-benefit Data Map

17

Page 18: 12 Feb 2020 Unlocking Facility Value Through Life Cycle ... · functions including remote visual checking, safety training, asset identification, model creation for later refurbishments,

Laser Scan Integrated BIM

Websharedataset

and/or and/or

and/or

Point Cloud

18

Page 19: 12 Feb 2020 Unlocking Facility Value Through Life Cycle ... · functions including remote visual checking, safety training, asset identification, model creation for later refurbishments,

Comparison of Different LOD Models Capability

WebShare

LOD 300

Revit

LOD 350

Plant 3D

LOD 400

Plant 3D + Revit

LOD 500

Live interaction ✔ ✔ ✔

All asset data & info ✔ ✔ ✔ ✔

Manufacturer & supply data ✔ ✔ ✔ ✔

AEC design ✔ ✔

External link attachment ✔ ✔ ✔ ✔

Pipe & plant creation ✔ ✔ ✔

Simulation ✔ ✔ ✔

"Smart" P&ID ✔ ✔

Clash detection ✔ ✔ ✔

GIS data ✔ ✔ ✔ ✔

Single mode assembly ✔ ✔

Phone access ✔ ✔

O&M manuals & other data ✔ ✔ ✔ ✔

Reduces construction costs & duration ✔ ✔ ✔

Life cycle & maintenance data ✔ ✔ ✔

Quality reports ✔ ✔ ✔

Bill of materials ✔ ✔ ✔

19

Page 20: 12 Feb 2020 Unlocking Facility Value Through Life Cycle ... · functions including remote visual checking, safety training, asset identification, model creation for later refurbishments,

The SCENE WebShare model – LOD 300 can beimplemented as a temporary solution for O&Mpurposes.

Plant 3D model – LOD 400 for the design andprocess engineering and the amount of possibleinput provided

BIM 360 – LOD 500 is recommended when a WTPor a new section of an existing one has to beconstructed.

Create 3D digital scans of all of built assets (i.e.point cloud digital twins) by employing a smallsurvey team and purchase LiDAR scanningequipment which would be useful for a range offunctions including remote visual checking, safetytraining, asset identification, model creation forlater refurbishments, etc.

Having well defined software use anddata/model exchange workflows. A clear plan ofsoftware available and processes needs to beoutlined before 3D modelling can proceed.

LOD 500

LOD 400

Webshare model LOD 300

Recommendations

20

Page 21: 12 Feb 2020 Unlocking Facility Value Through Life Cycle ... · functions including remote visual checking, safety training, asset identification, model creation for later refurbishments,

21

Evaluating the Benefits of BIM for life cycle asset maintenance of remote

government housing

Part 3: Case Study 2: QLD Government Department of Housing and Public Works

Dr Emiliya Suprun

Page 22: 12 Feb 2020 Unlocking Facility Value Through Life Cycle ... · functions including remote visual checking, safety training, asset identification, model creation for later refurbishments,

22

O&M Challenges

Queensland remote regions (Adapted from QDHPW, 2016)

• Remote locations are often located many kilometers from service centers

• OH&S challenges• Expensive contractor

services• Travel times rapidly blow-

out a housing repairs and maintenance budget

• Maintenance scheduling• Performance

measurement • Traceability of specific

materials or components

Page 23: 12 Feb 2020 Unlocking Facility Value Through Life Cycle ... · functions including remote visual checking, safety training, asset identification, model creation for later refurbishments,

23

Remote Housing: O&M

724(7%)

423(4.1%)

613(5.9%) 197

(1.9%)14

(0.1%)

6,476(62.4%)

32(0.3%)

169(1.6%)

903(8.7%)

830(8%)

0

1,000

2,000

3,000

4,000

5,000

6,000

7,000

Recorded Cases: Defects by Nature of Impact

447(4.3%)

2,431(23.4%)

37(0.4%)

568(5.5%)

772(7.4%) 620

(6%)

27(0.3%)

606(5.8%)

29(0.3%)

482(4.6%)

511(4.9%)

1,266(12.2%)

38(0.4%)

5(0.01%)

384(3.7%)

2,158(20.8%)

0

500

1,000

1,500

2,000

2,500

3,000

Recorded Cases: Asset Groups

Page 24: 12 Feb 2020 Unlocking Facility Value Through Life Cycle ... · functions including remote visual checking, safety training, asset identification, model creation for later refurbishments,

24

Remote Housing: Critical Assets

Air-conditioning

Building Structure• Roofs• Windows• External & Internal stairs• Walls• Stumps & Posts

Internal and External Finishes• Internal & External wall finishes• Internal & External floor finishes • Internal & External structure finishes

Site Upgrades• Internal & External structure

components• Boundary walls, fences and

gates• Driveways & Footpaths• Foundation & Slabs• Plumbing upgrades• Hard surfaced & Paved areas• Landscaping & Gardening• Retaining walls • Drainage

Page 25: 12 Feb 2020 Unlocking Facility Value Through Life Cycle ... · functions including remote visual checking, safety training, asset identification, model creation for later refurbishments,

25

BIM for Remote Housing Maintenance

Object oriented asset information and maintenance actions repository as an accessible single source of truth for maintenance workers

Page 26: 12 Feb 2020 Unlocking Facility Value Through Life Cycle ... · functions including remote visual checking, safety training, asset identification, model creation for later refurbishments,

26

BAU vs BIM-enabled Operation and Maintenance for regional and remote government housing

0

500

1,000

1,500

2,000

2,500

3,000

3,500

$/Dwelling/Year

BIM-enabled O&M BAU

0

200

400

600

800

1,000

1,200

1,400

1,600

$/Incident/Year

BIM-enabled O&M BAU

Modelling the life cycle asset maintenance business case for BIM

Page 27: 12 Feb 2020 Unlocking Facility Value Through Life Cycle ... · functions including remote visual checking, safety training, asset identification, model creation for later refurbishments,

27

Benefits of BIM Implementation for Asset Management in Remote Regions • Resource saving within the Department of Housing and Public Works

• Resource saving by contractors

• Close control and monitoring of critical assets

• Improved statistical data collection and evaluation

• Rework cost savings up to 25% for individual assets

• Easy-to-use unite “eco-system”

• Better understanding of assets

• Enhanced quality of maintenance services for public houses

Source: Department of Housing and Public Works

Page 28: 12 Feb 2020 Unlocking Facility Value Through Life Cycle ... · functions including remote visual checking, safety training, asset identification, model creation for later refurbishments,

Acknowledgements• Sustainable Built Environment National Research Centre

(SBEnrc) and its partners for funding Projects 2.64: UnlockingFacility Value Through Life Cycle Thinking

• Seqwater for funding the Project titled Developing a DigitalAsset Information Model Framework

• Personnel from Queensland Government Department of Housing& Public Works and Seqwater that participated in a number ofmeetings, site visits and workshops

Thank you! Any questions? 28