WARA PRESSURE MAINTENANCE PROJECT
COMMISSIONING PROCEDURE
Class 1 Doc. No. : 11050146-CM-PRO-000-5017 Rev.A Page 2of 63
REVISION SUMMARY
REV. DATE DESCRIPTION PAGE
A 22 Nov. 2013 Issued for Approval
WARA PRESSURE MAINTENANCE PROJECT
COMMISSIONING PROCEDURE
Class 1 Doc. No. : 11050146-CM-PRO-000-5017 Rev.A Page 3of 63
TABLE OF CONTENTS
1. COMMISSIONING PHILOSOPHY .................................................................................................. 4
1.1 EXECUTION PLAN FOR THE COMMISSIONING PROGRAM ............................................................... 4
2. COMMISSIONING ORGANIZATION............................................................................................... 5
3. COMMISSIONING SCHEDULES ................................................................................................... 5
3.1 COMPLETION PROGRAM ............................................................................................................ 5
3.2 COMMISSIONING ....................................................................................................................... 7
3.3 COMMISSIONING EXECUTION ..................................................................................................... 8
3.4 TESTING OF ROTATING EQUIPMENT ............................................................................................ 9
3.5 TIGHTNESS TESTS .................................................................................................................. 13
3.6 INSTRUMENTS AND SAFETY CONTROL ...................................................................................... 14
3.7 OPERATIONAL FUNCTION TEST ................................................................................................ 14
3.8 PREPARATION FOR START-UP .................................................................................................. 16
3.9 CONSTRUCTION COMPLETION (CC) AND READY FOR COMMISSIONING (RFC)................................ 20
3.10 AFTER CONSTRUCTION COMPLETION (CC) ................................................................................ 20
4. SYSTEM COMPLETION PRIORITIES .......................................................................................... 22
4.1 EARLY ACCEPTANCE UTILITIES ................................................................................................ 22
4.2 SUPPORTING FACILITIES (TANKAGE & UTILITIES) ...................................................................... 22
4.3 PROCESS FACILITIES .............................................................................................................. 22
5. EXECUTION PLAN ....................................................................................................................... 22
5.1 HOME OFFICE PLANNING & PREPARATION PHASE ..................................................................... 22
5.2 SITE COMMISSIONING PHASE ................................................................................................... 26
5.3 SYSTEM TURNOVER ................................................................................................................ 27
5.4 COORDINATION ...................................................................................................................... 29
6. HEALTH SAFETY & ENVIRONMENT (HSE) ................................................................................ 29
6.1 HOME OFFICE PREPARATION ................................................................................................... 29
6.2 COMMISSIONING SITE SAFETY ................................................................................................. 29
6.3 ENVIRONMENT & HARMFUL EMISSIONS .................................................................................... 30
7. ATTACHMENTS............................................................................................................................ 31
ATTACHMENT 1: TABLE–SPLIT OF WORK FOR CONSTRUCTION, PRE-COMM. & COMMISSIONING ............. 32
ATTACHMENT 2: PRE-COMMISSIONING/COMMISSIONING ORGANIZATION .............................................. 63
WARA PRESSURE MAINTENANCE PROJECT
COMMISSIONING PROCEDURE
Class 1 Doc. No. : 11050146-CM-PRO-000-5017 Rev.A Page 4of 63
1. COMMISSIONING PHILOSOPHY
A successful Commissioning for WARA PRESSURE MAINTENANCE PROJECT will require attention to
detail and close coordination between COMPANY and CONTRACTOR to successfully produce a safe
and reliable operating facility on schedule.
CONTRACTOR’s approach to a successful Commissioning for WARA PRESSURE MAINTENANCE
PROJECT is based on the fully integrated involvement of all concerned parties in all aspects, and in
each phase, of the project as described below.
This assures that all parties are fully familiar with their respective duties, are fully informed and trained
to safely carry out their duties and fully supported by the Team for the successful Start-up and operation
of WARA PRESSURE MAINTENANCE PROJECT.
CONTRACTOR will make use of the most experienced and specialized personnel in the execution of
the Commissioning.
Key members of this Team will be assigned as early as possible during the Engineering Stage and
preparations for the following work.
Establish an Organization.
Develop schedules and progress measurement tools for commissioning phases of the works.
Be responsible for the management and direction of all vendor representatives, specialists and
technical service providers
Manage, supervise, direct and control the Commissioning activities for the safe and assist
operation and test activities of the facility for successful turnover to COMPANY
1.1 Execution Plan for the Commissioning Program
The Commissioning program plan is a two distinct-phased approach to Commissioning – the Initial
Home Office Planning & Preparation phase and the Site execution phase which is defined as follows:
Phase-1 of the Commissioning program plan will be conducted / developed in CONTRACTOR’s home
office and will include, but not be limited to, the following activities:
Coordination with Engineering and Precommissioning on Commissioning requirement
Development of site specific Commissioning administrative and technical procedures
Incorporation of COMPANY procedures and testing requirements
Preliminary Operations and Maintenance Manuals of the area not provided by Licensor will be
prepared by process design team for review by COMPANY.
Preparation of "Scoped" drawings / databases for turnover package development
Development of Commissioning schedule with input from COMPANY’s project management
Development of the budget for all Commissioning activities.
Phase -2 of the Commissioning program plan will be conducted on-site and will include, but not be
limited to, the following activities:
Mobilization of the Commissioning Team
Administration system turnovers from Precommissioning to Commissioning Team.
Coordinate with precommissioning the completion of system punch lists in preparation for
turnover to the Commissioning Team.
Coordinate and conduct the equipment and systems Commissioning testing program.
Administration systems turnover to COMPANY’s Commissioning Team.
WARA PRESSURE MAINTENANCE PROJECT
COMMISSIONING PROCEDURE
Class 1 Doc. No. : 11050146-CM-PRO-000-5017 Rev.A Page 5of 63
2. COMMISSIONING ORGANIZATION
CONTRACTOR will provide Commissioning personnel in the applicable disciplines as needed with
extensive experience to complete specified / identified Commissioning activities.
Commissioning Manager will have overall responsibility for coordination of all project Commissioning
activities. Commissioning Manager reports directly to the Site Manager and to the Project Manager.
The discipline test engineers, equipment vendor representatives, precommissioning craft, contract
support and Contractor’s Commissioning personnel assisting in the Commissioning effort will work
under the direction of the Commissioning Manager as a single Team.
Every effort will be made to maintain the continuity of all Commissioning Team members including
assigned support craft and COMPANY’s personnel throughout the duration of all Commissioning
activities. This continuity of personnel will aid greatly in the effectiveness and efficiency of the
Commissioning Team.
Refer to detailed Commissioning Organization.
3. COMMISSIONING SCHEDULES
The schedules for all Commissioning activities will be developed as early as possible at detail
engineering stage. This will include an overview of the sequencing of system preparations and the
critical path for these activities.
3.1 Completion Program
The completion of the facility, the preparation of the facility for operation, the Start-up of the facility
and the operation of the facility for proof of performance involves several steps or specific sets of
activities which are typically referred to as:
Facility Construction Completion (End of Pre-commissioning)
System Commissioning
Facility Initial Start Up
Facility Turnover (End of Commissioning)
Performance Test
Provisional Acceptance
Final Acceptance
These various steps, and the sequence of execution, are represented below:
WARA PRESSURE MAINTENANCE PROJECT
COMMISSIONING PROCEDURE
Class 1 Doc. No. : 11050146-CM-PRO-000-5017 Rev.A Page 6of 63
CONTRACTOR is responsible for Construction, Pre-commissioning and Commissioning of the Facility
including test run. However, COMPANY’s operation team will work hand to hand, gaining experience
in plant Commissioning and Start up and ensure seamless transfer of responsibilities during take over
of the new facilities on completion of test run.
3.1.1 End of Pre-commissioning and Handover to Commissioning
End of Pre-commissioning is the 2nd
key step in the process of overall completion.
This is the stage where the basic pre-commissioning work has been completed and the pre-
commissioning quality control inspections and tests have been completed (and duly recorded) for all
the elements that make up a particular system within a unit or plant area.
This is attested by the various QA/QC Reports associated with each discipline and item of equipment.
These Tests and Records represent volumes of records and, in order to readily determine the status of
completion; these records shall be collated on a system- by -system or unit basis.
Pre-commissioning is achieved when the pre-commissioning work for a defined scope of piping,
electrical, instrumentation, civil/structural facilities buildings, underground, structural steelwork, and
miscellaneous items have been completed.
CONTRACTOR remedy or resolve to the satisfaction of COMPANY all pre-commissioning punch list
items classified as needed before starting Commissioning.
WARA PRESSURE MAINTENANCE PROJECT
COMMISSIONING PROCEDURE
Class 1 Doc. No. : 11050146-CM-PRO-000-5017 Rev.A Page 7of 63
3.2 Commissioning
As soon as a System has been pre-commissioned and completed in accordance with the Contract and
is in compliance with the Scope of Work (excluding such minor items as finishing of insulation and
painting, and other items not materially affecting the operation or safety of the System) and has
passed any tests required on that System, the system is on ready for Commissioning.
Commissioning is the term used for the final tests, inspections and checks carried out by the
commissioning team to confirm that the equipment and systems within the unit and plant are
precommissioned in accordance with the approved design and specifications and will function to
specified operational requirements.
It is at this stage that the final preparations, checks and line out of the equipment and plant
(commissioning of the particular items or systems) can be carried out in preparation for introduction of
hydrocarbons and start-up of the facilities.
CONTRACTOR will confirm to COMPANY that all commissioning activities have been successfully
carried out. This is reflected by the Commissioning Checklists and “Test Record” Sheets, which record
the action taken by the Commissioning Team in the preparation of the systems for Turn-over.
It is typically at this stage, having confirmed for COMPANY that all End of Commissioning activities
have been successfully completed, that Turnover Certification for the plant will be issued for
performance test..
3.2.1 Scope
Commissioning involves the preparation of systems to achieve ready for Performance test status. In
this phase between system end of commissioning and the commencement of Performance test, a
considerable amount of operation work is required. This Commissioning work is be carefully planned
and executed by CONTRACTOR in close consultation with COMPANY and Manufacturer
representatives.
Throughout the Commissioning phase the CONTRACTOR maintain and update the formalized system
punch list. At this time the punch list will record any material items which remain outstanding for
Turnover (Commissioning Completion) status, and any corrective work which has become evident
during commissioning.
On successful completion of all of the required Commissioning work, CONTRACTOR will notify
COMPANY a system is Turnover (Commissioning Completion).
Upon successful completion of Commissioning, CONTRACTOR will apply for Turnover Certificate,
signifies the end of the commissioning phase.
WARA PRESSURE MAINTENANCE PROJECT
COMMISSIONING PROCEDURE
Class 1 Doc. No. : 11050146-CM-PRO-000-5017 Rev.A Page 8of 63
3.2.2 Commissioning Responsibilities
All tools and equipment, all consumable materials, fuels and all services necessary to complete
Commissioning shall be planned and furnished by CONTRACTOR.
Certain utilities, such as water and power may be sourced from COMPANY’s utility distribution system.
Demineralized(or potable) water for Commissioning flushing and dynamic testing shall be provided by
CONTRACTOR.
CONTRACTOR will organize testing and water use to minimize waste of water.
CONTRACTOR will provide the plant air and instrument air used during the Commissioning of
instruments.
3.3 Commissioning Execution
Detail and specific commissioning procedures will be prepared for the project and presented for
COMPANY’s review and approval.
The following Basic Guidelines are provided only as a “typical” guide to the commissioning activities
which are normally involved in the preparation of a plant for operation.
It is important to note that fixed procedures for the execution of every commissioning activity cannot
always be applied in the same manner in each and every case. This is due to the nature of the work
and conditions of the facility that can vary from case to case.
It is not practical to cover all possible contingencies or emergencies conditions. Therefore, some of
the procedures and operating conditions stated herein may be require modification to meet unusual or
emergency conditions.
The intent is to ensure that the quality and integrity of plant preparations is maintained; regardless of
procedural methods.
The purpose of the Commissioning Guidelines will be to familiarize COMPANY’s operation group with
some of the basic aspects of Commissioning activities.
Detail procedures specific to the individual systems and equipment items on this project will be
prepared prior to the beginning of commissioning for the project.
All COMPANY’s operating and operations maintenance personnel will become familiar with all details
of the Commissioning activities, and the function of all operating equipment, during the course of the
On-The-Job training that will be given as they participate in each of the following activities.
3.3.1 P&ID Checks
The following Check List Procedure is intended as a guide to operators to assist in P&ID checking.
However, it does not in anyway suggest that the P&ID check is limited to the following list.
It is essential when carrying out the P&ID check the very latest revisions of the P&ID are checked. It is
important that items on the Check List are clearly defined and the item number entered on the P&ID.
3.3.2 Check Procedure
When P&ID checks are being carried out, and the persons checking are unsure of the validity of any
WARA PRESSURE MAINTENANCE PROJECT
COMMISSIONING PROCEDURE
Class 1 Doc. No. : 11050146-CM-PRO-000-5017 Rev.A Page 9of 63
item, they should immediately contact a member of the site engineering team. This will save future
confusion and help to speed up the P&ID check.
(a) List all items, e.g. temperature indicators, pressure indicators, etc. are not installed or
incomplete.
(b) Check instrument tag numbers to ensue the correct instrument is mounted in the correct
location, note any deviation.
(c) Note whether vents at high point or drains at low point are omitted.
(d) Note dead legs and question drainage, purging etc.
(e) Note any obvious materials faults, e.g. carbon steel bolts on stainless steel flanges.
(f) Check (note deviation) of orifice plate orientation and tag number.
(g) Note tapping point orientation.
(h) Note if in line strainers are in place, check tag numbers.
(i) Visually check (note deviation) piping runs for abnormality. Ensure exchangers, vessels etc.
process/utility piping is routed to the correct nozzle.
(j) Note installation of relief valves, check seals, bolts, gaskets and tag numbers.
(k) Note all safety items, trip hazards, head room hazards, missing gratings, manholes, fire
hazards, poor access to emergency equipment etc.
3.3.3 P&ID Check List Control
To ensure that P&ID check results are properly recorded and subsequently acted on the following
method is suggested;
(a) P&ID check teams to mark up the P&ID with a highlighter, line by line, to reflect which
portions of the system have been checked,
(b) Faulty items are given a check number, this number is marked on the P&ID and
corresponding number entered on the Check List with a description of the fault.
(c) Make two photocopies of the Check List.
(d) Make two copies of marked up P&ID.
(e) Attach Check List to P&ID.
(f) One copy of Check List and P&ID is used as the operations work copy.
(g) One copy of Check List and marked up P&ID is the operating master copy and is kept in the
central work area.
(h) The work copy is used for rechecking purposes. The status of all items is noted on the work
copy and find out entered into the master copy.
(i) One copy of Check List and marked up P&ID is transmitted to COMPANY’s team who will
inform Contractor of any further defective / missing items noted by the COMPANY’s team.
(j) Operations will recheck the items to ascertain whether or not the item has been corrected. If
not, a note is made in the Check List.
(k) When Contractor has acted on the items he will inform COMPANY that the work is complete.
3.3.4 Check completion of Pre-commissioning Activities
Please refer to the Pre-commissioning Procedures.
3.4 Testing of Rotating Equipment
Before start of test runs on rotating equipment, the following personnel should be informed.
(a) Commissioning and start-up team.
WARA PRESSURE MAINTENANCE PROJECT
COMMISSIONING PROCEDURE
Class 1 Doc. No. : 11050146-CM-PRO-000-5017 Rev.A Page 10of 63
(b) COMPANY’s start-up rotating equipment engineers.
(c) COMPANY’s operation group.
(d) Vendor service engineer for package items
Contractor maintenance specialists will instruct COMPANY’s team on how to carry out the testing of
rotating equipment. They will keep a continuous watch on the rotating equipment and monitor
performance.
Where practical, machinery will be operated, performance tested and systems operated prior to start-
up of the Plant.
For package systems, Operational performance of instruments and systems will be carried out.
Instrument inspection and calibration must be completed prior to this run-in-period.
Before the actual test is carried out, all inspection requirements and preparations, inclusive of
manufacturer's vendor representative requirements must be completed.
Inspection on any item of running equipment that could involve personnel coming into contact with
moving parts requires the power supply to be isolated and locked off.
Any internal inspection of running equipment, which involves opening of parts, which may contain
pressure, requires the suction and discharge to be isolated and the casing vent to be opened.
The casing must be at atmospheric pressure before any attempt is made to open the equipment.
If there is any doubt as to the security of the isolation, then blind flanges should be installed on the
equipment side of the suction and discharge valves.
Equipment should be isolated using blinds if hydrocarbons are present in the system during the test
run.
3.4.1 Electric Motors
Electric motors will be subject to a no-load testing i.e.: the motor is uncoupled from the driven
equipment. During the no-load test, the following items should be recorded:
(a) Check direction of rotation.
(b) Motor vibration levels.
(c) Bearing temperatures.
(d) Abnormal noises
Using the subsequent test with the driven equipment connected to the electric motor the following
items are to be measured and recorded:
(a) Electric motor current.
(b) Motor vibration levels.
(c) Bearing temperatures.
(d) The start-up current, and time for fin fan motors.
3.4.2 Pump Test Run Preparation
WARA PRESSURE MAINTENANCE PROJECT
COMMISSIONING PROCEDURE
Class 1 Doc. No. : 11050146-CM-PRO-000-5017 Rev.A Page 11of 63
The following steps will be taken for the Pump Test Run Preparation:
Pump suction line should be fully flushed before Test Run
(a) The pump should still be uncoupled from the driver.
(b) Install strainers with (20~40) mesh size temporary start-up screens before aligning pumps.
Mark all strainers and keep a list similar to the blind list, so as to prevent a 'lost' screen.
Connect the suction and discharge flanges to the pumps and simultaneously
(c) Remove pipe stresses.
(d) Connect the pump to the driver and check alignments (cold alignment check).
(e) Rotate the shaft manually to check for freedom of movement.
(f) When a test run with water has been planned, carefully isolate the loop system from the rest
of the sections. The water should be sufficient to fill the whole loop and provide sufficient
head available to the pumps.
(g) A final check should be carried out that correct lubricating oil and grease have been put into
the pump, and that the oil glass shows proper level.
(h) Open the suction valve.
(i) Check that the seal does not leak and that seal flushing and cooling water connections are
correctly made.
(j) Rotate the centrifugal pump shaft by hand to test for free rotation.
(k) Flush water from the pump drain and the suction drain to remove scale (if possible).
(l) Check that the coupling guard is secure.
(m) Start lube oil system (if applicable).
(n) Switch the pump on and off as a final check for correct shaft rotation.
(o) Ensure that the pump is liquid full.
3.4.3 Centrifugal Pump Test Run
During the pump test the following items should be checked:
(a) Bearing temperatures.
(b) Vibrations.
(c) Abnormal noises, noise levels.
(d) Pump discharge pressure at shut off head and normal flow (if possible).
(e) Leaks identified and listed for repair if not pulled up.
(f) A test sheet is to be completed.
(g) The test duration is for a minimum of 30 minutes (if applicable).
3.4.4 Positive Displacement Pump Test Run
During the Initial run, the following items must be confirmed or checked:
(a) Confirm the liquid has sufficient lubricating properties.
(b) Supply cooling water where necessary.
(c) Start the pump with open suction and discharge valve. Check the mechanical performance of
the pump and watch bearing temperature, if applicable.
(d) Check flushing supply to seals, if applicable.
(e) When discharge pressure drops, stop the pump, inspect and clean the strainer in the suction
line.
(f) Check for excessive vibration.
(g) Check motor amperage, if applicable.
(h) Check for noise levels in excess of specifications.
WARA PRESSURE MAINTENANCE PROJECT
COMMISSIONING PROCEDURE
Class 1 Doc. No. : 11050146-CM-PRO-000-5017 Rev.A Page 12of 63
(i) Check pump for leaks.
(j) A test sheet is to be completed.
(k) The test duration should be for a minimum of 2 hours.
3.4.5 Centrifugal Compressor Test Run
Before test runs on Centrifugal Compressors are carried out, a detail plan of action must be reviewed
with the Vendor specialists to confirm readiness. The plan of action should consist of the following
elements, as a minimum:
(a) Vendor’s commissioning instructions for review
(b) Detailed schedule of action with actual dates and milestones reached.
(c) All individual equipment tests, lube oil pumps, motors, filters, etc. should be specified
separately. In general the criteria for testing and inspection to be described individually for
such equipment items.
(d) Tests of all auxiliary systems lube oil, seal oil and cooling water etc. should be included and
scheduled well in advance of compressor test run.
(e) Anti surge control system to be tested and line up checked.
(f) In case the test run is carried out with a medium different than the design process gas,
restrictions on speed, discharge temperatures, pressures, etc. should be clearly specified.
(g) The compressor test run should be scheduled at the end of the test run series of the driver
(steam/gas turbine): however, it is to be carried out as a separate activity.
(h) All test results should be recorded on specified test sheets that are part of the test program.
As a minimum, the following parameters should be included:
(a) Oil pressures, temperatures, flows.
(b) Gas pressures, temperatures, flows.
(c) Vibration signals (during start-up and at operating speed).
(d) Noise levels.
(e) Speeds.
(f) Driver operating data.
3.4.6 Reciprocating Compressor Start-Up Preparations
The following steps will be taken for the Compressor Start-Up Preparations:
(a) Check that the inlet filter and fine mesh screen element is installed and that there is no space
between the filter element and the filter casing.
(b) Check that correct lubricating oil has been put in the compressor and oil glass is full.
(c) Check that all lines are connected properly to the machine.
(d) Bar the crankshaft over for at least one revolution to make sure that all-moving parts of the
compressor run freely.
(e) Check that the shaft guard is installed.
(f) The lubricator settings should be in excess of normal operating settings. Remove suction and
discharge compression valves, if required.
3.4.7 Reciprocating Compressor Test Run
In case a test run on a gas that is different from the design process gas is carried out, specific
WARA PRESSURE MAINTENANCE PROJECT
COMMISSIONING PROCEDURE
Class 1 Doc. No. : 11050146-CM-PRO-000-5017 Rev.A Page 13of 63
attention should be paid to restrictions on power demand and discharge temperatures. Restrictions
should be clearly specified in the procedure.
The plan of action should consist of the following elements,
(a) Operate the compressor on a start-up procedure while the lube oil pump operates for about
five minutes.
(b) After bringing the unit to a standstill, check all bearings and other friction parts for
temperature rise. If no excessive temperature is observed and once all items have been
verified on tightness, start the compressor again and let it run for available hours.
(c) Regular observations should be made during available hours.
(d) After the mechanical run-in period, the suction and discharge compression valves should be
refitted in their respective places and the compressor started again on no-load e.g.: by means
of the application of valve unloaders.
(e) Increase to full load gradually and run for specified period, unless observations indicate the
presence of a defect.
(f) Check the oil pressures and temperatures of all bearings and seals and check proper
functioning of lubricator regularly.
(g) Check the gas pressures and temperatures regularly.
(h) Check for any gas leakage, vibration of machine and piping.
(i) Check the automatic loading and unloading device, if installed, for smooth operation.
(j) Check for noise levels in excess of specified requirements.
(k) A test sheet is to be completed.
3.4.8 Air Cooler/Condenser Fan Test Run
A test run to be carried out with preferably all fans of the particular bank section simultaneously in
operation. The following checks will be made:
(a) Check for vibration levels on electric motor and one point of the structure.
(b) Record electric motor amperage.
(c) Check for abnormal noises.
(d) Check whether belt/pulley engagement is over the full width during operation.
(e) Check for abnormal structural vibrations or loose bolts during operation.
3.5 Tightness Tests
This is normally the final stage before inerting the Plant prior to the introduction of hydrocarbons.
Although the various items of equipment will be “boxed-up” and the piping system lined up for start-up
a final “tightness” or leak test must be carried out.
A tightness test is a final check for leaks before the inert/purging step and the introduction of
hazardous materials into the plant. It is essential when preplanning this stage that particular attention
is paid to pressure breaks in the various sections of the plant, in order to prevent damage to
equipment by over pressurizing.
A leak of hydrocarbons during start-up poses a safety risk. It can also prove costly. The opening of
equipment after the introduction of hydrocarbons will require gas freeing and will also cause delays.
The equipment has to be isolated, drained, depressurized and purged with nitrogen to remove the
WARA PRESSURE MAINTENANCE PROJECT
COMMISSIONING PROCEDURE
Class 1 Doc. No. : 11050146-CM-PRO-000-5017 Rev.A Page 14of 63
contents. Then, after repairs are completed, the system is again tightness tested and purged with
nitrogen to remove the air. These delays can be costly.
The following procedure is recommended to ensure that the unit is absolutely tight. When correctly
done, the chances of equipment having to be opened for leak repairs later will be minimal.
Mark-up the system to be tested on the P&ID, highlighting any pressure breaks within the system and
the isolation points for the system. Isolate the system being tested at its extremities by block valves or
blinds, closing all vents and drains. Line up valves within system ready for test.
Where block valves are used for isolation, open a vent, drain, or instrument connection to atmosphere
downstream of block valve. This will allow checks to be made as to whether block valves are passing
and also prevent pressuring of downstream systems.
Tape flanges in the system if required and make a pinhole on the tape at the top, mark clearly the
location of the pinhole.
During the test, the system must be protected against over pressuring by putting in service safety relief
valves, which have been calibrated and set. In the event that the flare system is operational, the relief
valves should be installed with the exhaust turned to atmosphere.
Identify the instruments which will be used to monitor the pressure. Use of control room instruments to
monitor the pressure is encouraged at this time, as it proves the output of instrument systems.
Pressure should be monitored and ambient temperatures taken into account for reasonable pressure
losses due to ambient temperature reductions. It is useful to set the relevant DCS instruments
on ’trend’ to record pressure variations.
Pressurize the system in stages up to the defined pressure by using of plant/instrument air or nitrogen.
Ensure soap solution being used is compatible with all metal and gasket materials etc.
As each desired pressure step is reached, spray a small amount of soap solution on the point of the
joints. Formation of soap bubbles will indicate a leak.
When the required pressure is reached, shut off the main air/nitrogen supply and monitor the pressure
over a fixed period of time. The standard set depends on the process being tested.
3.6 Instruments And Safety Control
The objectives of the instrument section of the Start-Up Team are as follows:
(a) To confirm that the instruments and safeguarding systems function as designed.
(b) To confirm that the instruments installation is according to design standards.
(c) To confirm that the instrument documentation reflects the as built status of the Plant.
(d) To advise and assist Production on a smooth transition of Plant from Precommissioning to
Operational status.
3.7 Operational Function Test
Operational Function Testing is to be developed in conjunction with and COMPANY’s commissioning
team to prove the instrument and safety control systems and the associated operability of equipment.
WARA PRESSURE MAINTENANCE PROJECT
COMMISSIONING PROCEDURE
Class 1 Doc. No. : 11050146-CM-PRO-000-5017 Rev.A Page 15of 63
Operational Function Testing is to include the following requirements:
(a) To prove the operation and calibration of each instrument loop from its process connection to
final element.
(b) To prove that for all input conditions, the corresponding output actions occur as designed.
(c) To ensure the integrity of all safeguarding of equipment.
(d) To ensure that all systems are fully commissioned and ready for Start-Up.
Operational Function Testing Documentation is to be developed as follows:
(a) Standard calibration sheets for all instruments incorporating an in-situ calibration procedure.
(b) Supporting documents such as loop diagrams, and/or, marked-up logic diagrams.
(c) A cover sheet for documentation approval.
In addition to the above, complex procedures shall include the following:
(a) A planning sheet showing test equipment and manpower required and involvement from
other disciplines.
(b) A summary sheet showing a list of all instrument tag numbers involved, supported with
drawing numbers.
(c) A functional description of the system.
(d) A detailed step-by-step test procedure typically in the form of an input test condition versus
output action matrix.
(e) A diagram showing any independent relationships between test procedures.
The Operational Function Testing is to be witnessed by the COMPANY to ensure that all testing is
correctly executed and report sheets made and signed by both parties. If necessary,
recommendations are to be made to improve or remedy problems discovered during testing. Testing is
to be conducted so as to demonstrate to Operations that the systems operate as designed.
WARA PRESSURE MAINTENANCE PROJECT
COMMISSIONING PROCEDURE
Class 1 Doc. No. : 11050146-CM-PRO-000-5017 Rev.A Page 16of 63
SAFETY: During the commissioning phase, the instrument system and operation teams will work very
closely, as part of the plant may be under pressure, people will be working in different areas, etc. It is
important to stress that function testing of instruments may only be carried out under a Work Permit
System, in order to prevent accidental discharge of air, etc.
3.8 Preparation For Start-Up
3.8.1 Introduction
The final activities to make the unit ready for initial start-up are described in this section. These
activities include:
(a) Filter media in filters.
(b) Loading of chemicals.
(c) Installation of orifice plates.
(d) Removal of blinds.
(e) Nitrogen purge.
(f) Dry-out of lines and equipment.(if required)
3.8.2 Packing (Air Dryer)
Confirm that the correct height of packing is installed, that the different layers of stacked packing are
crossed in order that the joints are not in line, but there is an overlapping.
Support grids and retaining grids should also be checked.
3.8.3 Filter Media Filling
Before filter medias are loaded in filters, they must have been thoroughly cleaned. They should be free
of debris. No excessive rust should be present.
General guidelines for loading include:
(a) Check that all nozzles and supports in and outside are as specification (vessel drawing).
(b) Ensure that clearances between screen layers and screen and vessel walls have been
checked and adjusted to prevent filter media falling below the support grid.
(c) Inspect the filter media before loading to ensure that drums have not sustained damage in
shipping or storage at site.
(d) Do not load filter media or dryer desiccant in rainy or humid weather.
(e) Only break filter media drum shipping seals as required to steadily supply the loading
operation.
(f) Provide loading personnel working inside a vessel with suitable protective equipment, such
as dust or mesh air masks. Refer to supplier’s safety recommendations.
(g) Mark in the same way the specified height of the filter media layer.
(h) Use a hopper with flexible height for loading.
(i) The sock attachment should be long enough to distribute the material without free fall
Otherwise, filter media breakage could occur and too many fines will be produced.
(j) Fill up with specified supporting material until the first mark.
(k) Check the layer in the middle with a dipstick and ensure level is uniform
WARA PRESSURE MAINTENANCE PROJECT
COMMISSIONING PROCEDURE
Class 1 Doc. No. : 11050146-CM-PRO-000-5017 Rev.A Page 17of 63
(l) Fill up with filter media until the second mark from the screen.
3.8.4 Loading Of Chemicals
Prior to loading of any chemicals, vessels and lines should have been thoroughly cleaned and all
equipment and upstream piping work should be free of rust and debris.
If any chemicals are prone to oxidation, the applicable vessel should be inert and isolated as soon as
possible after loading is complete.
Safety precautions and procedures must be strictly adhered to (safety equipment used) during all
handling and all loading of chemicals.
3.8.5 Installation Of Orifice Plates
Install instrument orifice plates and restriction orifices (R.O's) in accordance with data sheets and
P&ID.
(a) Instrument orifice plates and R.O's must not be installed before piping runs have been
thoroughly cleaned.
(b) Consult orifice data sheets to determine bore size, use P&ID to determine the direction of
flow and plate O.D. size.
(c) Maintain an installation record of orifice plates and restriction orifices, to facilitate control over
the installation of the plates and to serve as a reference should problems occur later.
(d) Record the following information in the documentation pack for hand-over to COMPANY:
• Date of installation.
• Plate tag number.
• Bore size.
• Line number.
• Signatures of witnesses for correct installation.
(e) All orifice plate to be installed with the inscription stamp on the upstream side of the tab.
(f) Flow orifice plates to have the counter sunk side facing downstream, except conical orifices
which have the counter sunk side facing upstream
(g) If vent holes in the orifice plate are specified, locate during installation top or bottom of the
pipe dependant on liquid or gas service.
3.8.6 Plant Blinds Check
Inspect all plant equipment and piping for the removal of test blinds. Make a Blind Control list of all
operational blinds and spectacle blinds that should be installed. Indicate their operational position
clearly.
Check that blinds and spectacle blinds are installed in correct positions ready for plant start-up. The
Blind Control list shall be checked and confirmed by the field operators or each shift.
WARA PRESSURE MAINTENANCE PROJECT
COMMISSIONING PROCEDURE
Class 1 Doc. No. : 11050146-CM-PRO-000-5017 Rev.A Page 18of 63
3.8.7 O2 Freeing
Before hydrocarbons are introduced into the unit, the O2 content must be reduced to avoid an
explosive mixture being created. Nitrogen can be introduced by hose connections or with fixed
injection points, hoses are better connected at low points.
• Pressure up unit being purged with nitrogen to utility service pressure.
• Then depress as rapidly as possible. Carry out this procedure three more times
• Ensuring that you purge out all high point vents and low point drains.
• Commence checking O2 content at several points to ensure the whole unit is virtually O2 free.
• Continue pressure purging with nitrogen until O2 content of less than 2 % vol. is achieved.
• The unit should be left under a slight positive pressure of nitrogen until the introduction of
hydrocarbons during normal startup.
NOTE: No entry into equipment permitted after introduction of nitrogen. After this step the flare header
and stack can be commissioned, if not already in operation.
3.8.8 Dry-out Of Lines And Equipment
Dry-out is necessary in Nitrogen Package units to avoid blocking lines and equipment by ice formation.
Drying out is finished when the water content measured with portable moisture analysis is at the levels
determined by vendor’s specification. Drying out of systems can be speeded up by using dry air during
commissioning and the use of nitrogen during the purging phase.
The early Commissioning work focus on a sequence of activities performed on individual systems.
Activities such as followings; these activities may be carried out in a simultaneous manner by
individual disciplines.
Air blowing
Water flushing
Leak test
Filter Media Loading
Piping reinstatement
Final instrumentation and electrical hook up
Vessel inspection and closure
Instrument loop / function tests
Preservation
During the stages of Commissioning, systems are combined to enable wider functionality checks to be
carried out, such as trial dynamic operation of pumps and compressors, containment / tightness
testing, flow route and flow rate testing, control sequence testing, process initiated trip tests, and
others.
The stages of Commissioning therefore require that several interfacing systems are brought to an
equivalent status to allow such testing to be carried out. At an appropriate point in the progress of
Commissioning, systems shall therefore be combined and integrated to enable multidiscipline dynamic
test activities to commence.
WARA PRESSURE MAINTENANCE PROJECT
COMMISSIONING PROCEDURE
Class 1 Doc. No. : 11050146-CM-PRO-000-5017 Rev.A Page 19of 63
The tests may simultaneously involve many systems and supporting utility distribution systems.
Dynamic testing work is multidiscipline and sequential in nature, and CONTRACTOR will carefully plan
and prepare for the activities to ensure all systems, personnel and material are made available when
required.
After dynamic testing, all systems within a part of the Plant it is brought to an equivalent state of
readiness for commissioning operations to commence. CONTRACTOR will include for Manufacturer
specialists if required at site for Commissioning work and advice. This will include, but not limited to
the following:
Nut-shell Filter Package
Media Filter Package
Horizontal Induced Gas Floating Vessel(HIGF Vessel) Package
Air Compressors Package including operations
Chemical Dosing Package
Large multistage pumps
Critical Metering Systems
Safety Systems
High Voltage Switchgear
Uninterruptible Power Supply (UPS) system
Online Analyzers/Sampling system
Fire and gas monitoring system
Distributed Control System (DCS) and Safety Instrumented System (SIS)
Emergency Vent Systems
Critical HVAC
Vibration monitoring of rotating equipment
Flare
Throughout the Commissioning phase, CONTRACTOR provides evidence of the following:
Test, witness, and certification documentation.
Systems Package records.
All appropriate procedures and method statements.
All safety plans/permit to work/safety procedures.
Check sheets, record sheets and certificates or documents to support ready for Commissioning are
signed as complete by CONTRACTOR and witnessed by COMPANY. They also are recorded in the
System Manual.
3.8.9 Equipment and Process Dynamic Testing
Process and equipment dynamic testing have to be carried out during Commissioning in this Project.
These activities are to confirm, as much as possible, that equipment will be capable of safe and
secure operation when committed to the Start up sequence leading to operational service. Tests will
be conducted using relatively safe fluids (e.g. air, water, inert gas) to allow run-in and functionality
testing of individual equipment items and parts of the process. This functionality testing involves
activities such as followings;
Water circulation at pressure
Air circulation
Control system serviceability
Containment and valve integrity testing
WARA PRESSURE MAINTENANCE PROJECT
COMMISSIONING PROCEDURE
Class 1 Doc. No. : 11050146-CM-PRO-000-5017 Rev.A Page 20of 63
Blow down and depressurization tests
CONTRACTOR will develop specific method statements for these activities and address issues of
area access and control, and the safety at interfaces. A safety risk analysis will be carried out prior to
commencing each activity. CONTRACTOR will arrange for Manufacturer specialists as appropriate to
direct, conduct or witness this dynamic testing, if required. CONTRACTOR will notify to COMPANY in
writing to start the dynamic testing in advance.
During this phase the Commissioning Team will confirm that the equipment and systems within the
unit and facility are pre-commissioned in accordance with the approved design and specifications and
will function to specified operational requirements. The Commissioning will be carried out in a system
base methodology.
At this stage the final preparations, checks and line out of the equipment and facility (Commissioning
of the particular items or systems) will be carried out in preparation for introduction of hydrocarbons
and start-up of the facilities.
3.9 Construction Completion (CC) and Ready For Commissioning (RFC)
Once the Pre-commissioning has been completed in accordance with the Contract and has passed
any tests required on that System, CONTRACTOR will notify the COMPANY in writing to issue the
certificate for “Construction Completion” (CC).
When CONTRACTOR submits a notice of system Construction Completion, There is a COMPANY
check of the following before agreement that the system is Construction Completion and then
COMPANY signs an accepted Construction Completion certificate for the system:
a) The resolved punch list for the system with all items required for Pre-commissioning is completed.
b) Check list of all pre-commissioning items for the system completed
c) Non-destructive Testing (NDT) records and QA/QC documentation for all Materials to confirm
checked/inspected/tested/calibrated to the requirements of the Project Standard and the
Subcontractor’s instructions and Standards for each separate System.
d) Confirmation of flow direction for all elements including control valves and flow elements.
e) Isolation and/or blinding are correct
f) Line by line check of system P&IDs
g) Rotational, alignment and other mechanical consideration are completed
Ready for Commissioning for a system is upon satisfactory completion of pre-commissioning activities,
Construction Completion Certificate, a system pre-commissioning review and a Certification of
Construction.
COMPANY’s approval of CC status will be governed by the effective administration, resolution of
outstanding punch list items, a system Commissioning plan and joint CONTRACTOR / COMPANY
safety review. All inspection instructions, witness and documentation for the system will be completed
and signed by COMPANY and CONTRACTOR as Construction Completion.
Commissioning safety review for a system (or joint CONTRACTOR / COMPANY safety review) will be
carried out based on PSSR (Pre Start up Safety Review) procedure.
Following Completion of Commissioning safety review, CONTRACTOR will commence the
Commissioning of the System.
3.10 After Construction Completion (CC)
After the Pre-commissioning Completion of a system/sub-system, the preparation of the facility for
WARA PRESSURE MAINTENANCE PROJECT
COMMISSIONING PROCEDURE
Class 1 Doc. No. : 11050146-CM-PRO-000-5017 Rev.A Page 21of 63
operation, the Start-up of the facility and the operation of the facility for proof of performance involves
several steps or specific sets of activities which are typically referred to as:
System Commissioning
Facility Initial Start Up
Performance Test
Provisional Acceptance
3.10.1 System Base Commissioning Methodology
The tests to be carried out during Commissioning activities will be exhaustive, according to the
methodology described below. No equipment or part of the installation will be accepted without
associated check and tests prior to energization and Start-Up.
3.10.2 System Base Completion Approach
The checking and testing phase of a new facility is by necessity a relatively detailed and sophisticated
process. Not all parts of the facility reach the same degree of completion at the same time, hence
some areas or units may be mechanically completed while others are not. It would therefore be a
waste of time to wait for the whole facility to reach End of Pre-commissioning before starting
Commissioning activities.
The Commissioning activities can start even if all the Pre-commissioning activities are not completed,
provided that the system or subsystem concerned is in safe condition for doing the Commissioning
activities As examples, the Commissioning activities, such as Mechanical running test for the each
rotating equipment can start even if the Pre-commissioning of other piping or instrument portion in the
same system or subsystem are not completed, provided that the system or subsystem concerned is in
the safe condition for doing the Commissioning activities.
Since HVAC systems and Firefighting equipment inside/outside buildings are independent from the
process systems, these systems will be Pre-commissioned and Commissioned separately from the
process systems.
3.10.3 System / Subsystem definition
This specific partition of a facility into systems and subsystems for completions activities takes place
as early as possible, at Basic Engineering phase and will always be submitted for approval to the
COMPANY.
The partition of a facility is a key preparation activity that has a major impact on all aspects of
completion operation. The subsystems must be defined so as to be as independent as possible, not
too small, but of manageable size, and exactly adapted to the Start-Up sequence.
Refer to “11050146-CM-PRO-000-5013 System Definition Procedure” for system list.
3.10.4 Hand-Over Tool.
A software application tool, called, UNICCS (Unified Construction to Commissioning System),
CONTRACTOR In-house system, will be used as hand-over tool in order to cover the aspects of
project completion activities and to obtain a smooth transfer of the facilities from CONTRACTOR to
COMPANY, as quickly as possible and with the required safety.
The UNICCS functions are follows;
WARA PRESSURE MAINTENANCE PROJECT
COMMISSIONING PROCEDURE
Class 1 Doc. No. : 11050146-CM-PRO-000-5017 Rev.A Page 22of 63
UNICCS is a database that tracks the completion progress of all tagged item, marked on the P&ID,
installed on the project.
Within UNICCS are links to the item which is fundamental to the requirements of inspection, test and
commissioning at each stage of the project.
Manage QC document
Manage Commissioning job check / Test sheet
Manage punch list
Handle output progress reports and the status
Import / Export data by using MS Excel.
4. SYSTEM COMPLETION PRIORITIES
In general, except Early Acceptance Utilities, the facilities will be commissioned and completed to the
following priorities to accommodate the staged Commissioning of the plant.
Testing and handover will be completed “system–by–system” (service-by service) basis.
4.1 Early Acceptance Utilities
Some specific facilities, requested by COMPANY, such as Utility Water, Site office complex,
interconnecting piping, interconnecting pipe racks will be available to run in advance until fixed
schedule.
4.2 Supporting Facilities (Tankage & Utilities)
The Utilities Systems will be commissioned and put onto service first and used for the Commissioning
and preparation of the rest of the plant. This generally applies to the water, air, nitrogen etc. services
required to prepare the other plants for operation.
The Commissioning of the Tankage Systems involves the final line up of the systems for introduction
of feedstock for start-up.
4.3 Process Facilities
The Commissioning and Start-up of the Process facilities involves a number of process steps, with the
primary operations/process procedures being outlined in the Operations Manuals.
A system comprises the equipment, piping and all support facilities within defined battery limit,
required for carrying out a specific function or service. The objective of defining systems and
subsystems is to facilitate sequential End of Precommissioning, Commissioning and Turnover to
COMPANY for Initial Start-up and Performance Test. System may comprise a verity of subsystems
such as mechanical items, piping, electrical and control systems.
5. EXECUTION PLAN
5.1 Home Office Planning & Preparation Phase
CONTRACTOR will commence the detail planning for the Commissioning of the facility.
WARA PRESSURE MAINTENANCE PROJECT
COMMISSIONING PROCEDURE
Class 1 Doc. No. : 11050146-CM-PRO-000-5017 Rev.A Page 23of 63
This will include participation in the Process Safety Reviews, HAZOP Study and Constructability
Reviews to ensure that operational issues are fully anticipated in the design, construction and pre-
commissioning of the facility.
This involvement in the early basic design and engineering stage will assure the facility’s ability to be
properly commissioned and assist the Team in the development of the Commissioning Execution Plan.
During this initial stage, CONTRACTOR’s Commissioning Manager and his planning team will work
with COMPANY’s Commissioning Manager and Operating representative to commence basic planning
and development of the key execution tools. These Key Execution Tools include;
The basic Start-up Plan defining the sequential preparation and commissioning plan for the
primary processes, units and systems. This sets the overall priorities for Engineering,
Procurement and Commissioning.
The outline of the System Packages that will be used to define and record the completion and
readiness of the facilities for commencement of operations. These packages (or System
Dossiers) commence with the definition of the basic “systems” and “sub-systems” that will be
required for detailed planning for End of Pre-commissioning of the facilities.
Commencement of preparation of the Commissioning Procedures to be used for the specific
facility; in preparation for receipt of specific vendor and licensor data for the specific equipment
items and processes.
WARA PRESSURE MAINTENANCE PROJECT
COMMISSIONING PROCEDURE
Class 1 Doc. No. : 11050146-CM-PRO-000-5017 Rev.A Page 24of 63
Commencement of preparation of the Operations Manuals that will include all data and
procedures necessary for the safe and efficient start-up and operation of the facility.
Detailed planning and preparation for Commissioning activities will start in CONTRACTOR’s Home
Office as early as possible at the Engineering stage.
5.1.1 Participation in Project Meeting & Design Input
CONTRACTOR's Commissioning Manager or his designee will attend daily / weekly engineering
meetings, as well as, regular project review meetings held by the Project Team during the home office
engineering phase of the project.
The Home Office phase will begin early in the design period of the project when key members of the
Commissioning Team will be on hand to input specific requirements for Commissioning and Start-up
procedures into the design phase.
CONTRACTOR's Commissioning Manager or his designee will participate in the Constructability,
Process Safety and HAZOP reviews if required with the other multi-discipline review Teams to ensure
that all operability and operations safety issues are addressed.
As the information becomes available, they will begin to review the basic process and utility system
designs with engineering and the design operating parameters for major equipment items and
packages.
5.1.2 Review of Project Drawing and Scope
During the engineering phase, the Commissioning Manager or his designee will review project
drawings for issues such as; system operability, lessons learned from previous projects to ensure
better productivity and system reliability, incorporation of Commissioning flushing connections (If
flushing is required), adequate system vents / drains and instrument taps for system Performance
Testing.
Electrical single lines and P&ID's will be used to "scope" the systems for development of turnover
packages. These scoped drawings will specifically define the system turnover boundaries for pre-
commissioning as bulk pre-commissioning finishes and the emphasis turns to system completion.
Once the system boundaries are finalized, the scoping boundaries will be included as a development
level in each electronically created drawing and maintained as the drawings are revised.
A turnover package numbering system will be developed during the scoping effort. The scoped
drawings will be assigned specific turnover package numbers for ease of identification. Engineering
databases, which are developed, will incorporate these specific turnover package numbers by adding
a turnover package number field to the database list.
These databases include the project's major equipment list, valve list, motor load list, instrument list,
cable and I/O lists. These lists will be sorted by turnover package number for inclusion into the
individual turnover packages. The combination of scoped drawings and the scoped databases will give
a detailed description of each system.
5.1.3 Development of Commissioning Documents
A detailed Commissioning strategy document will be developed for the COMPANY, which includes
execution plan for work at the project site with the first objective of optimizing the activities and
schedule of the Commissioning phase.
WARA PRESSURE MAINTENANCE PROJECT
COMMISSIONING PROCEDURE
Class 1 Doc. No. : 11050146-CM-PRO-000-5017 Rev.A Page 25of 63
It will define the safe working practices, project site organization, responsibilities for the facilities and
the interfaces within the CONTRACTOR’s team, the phased MC and RFSU completion objectives by
system and Unit, the detailed method statements to be generated, and the completion documentation
to be prepared by CONTRACTOR.
The strategy document will also address the sequence and objectives of the Commissioning phase,
including outline manpower plans for operations, supervisory, safety, and maintenance functions and
technical support until the plant is released to COMPANY. CONTRACTOR will work closely with
COMPANY on these items.
Each system turnover from Pre-commissioning to Commissioning will be noted as a turnover
milestone activity to begin major testing for the specific system.
CONTRACTOR’s Commissioning Manager, in conjunction with COMPANY Operations, will develop,
revise and maintain the Commissioning schedule and will coordinate / schedule activities with
CONTRACTOR’s Project Scheduling Group to ensure timely Commissioning updates.
The Commissioning Schedule will identify, by system, the preferred sequence in which commissioning
should prepare and complete the scoped project systems. It will also identify walk-down dates for each
system, commissioning release dates by system, and specific Commissioning activities required to
test and pre-commission individual systems.
The schedule will include, and be used to track system turnover dates and Completion Plan showing,
individual commissioning target dates, Commissioning and RFSU targets and activities.
CONTRACTOR will develop a commissioning plan and performance test plan in close consultation
with COMPANY and ensure the commissioning and RFSU sequence for the Plant is consistent with
the Commissioning plan
The sequence and duration for commissioning work leading to RFSU of each system shall be
prepared in a system Completion Plan showing, individual commissioning target dates,
Commissioning and RFSU targets and activities. CONTRACTOR shall ensure the commissioning and
RFSU sequence for the Plant is consistent with the Commissioning plan.
5.1.4 Development of System Manuals
The Commissioning of the facilities will be carried out on a “system-by- system”.
Each operating facility, and the specific units involved, is divided into logical process and/or piping and
equipment “systems”.
A System Manual will be prepared for each system. COMPANY shall be furnished updated copy.
System Manual “CONTENTS” page will show the following minimum sections:
a.) System Name
b.) Contents Sheet (Index)
c.) System and Sub-system identification
d.) System summary sheet
The documentation in each System Manual record the inspection, checking and testing activities
required to achieve RFC and RFSU status.
The System Manual will only be complete when all the records of inspections, checks and tests
acceptance have been appropriately signed off as approved and summary certifications completed in
the System Manual.
WARA PRESSURE MAINTENANCE PROJECT
COMMISSIONING PROCEDURE
Class 1 Doc. No. : 11050146-CM-PRO-000-5017 Rev.A Page 26of 63
5.1.5 System/Sub-System Division
CONTRACTOR will divide the Facility into system as a basic approach to Facility Commissioning
activities. Systems will be developed such that the individual systems can provide a practical, safe and
secure subdivision of the facilities on which to base completion.
The subdivision of the Facility into system provides a workable method to Schedule Commissioning
work according to a logical sequence of Commissioning and/or Commissioning activities;
Conduct Commissioning and/or Commissioning activities of some Facility systems while others
are still under pre-commissioning;
Complete the part on a system-by-system basis and in a systematic and controlled manner.
The approach takes full advantage of the fact that any given moment in the Facility, some areas (i.e.
systems) are already under Commissioning, while others are under construction or still under pre-
commissioning. The overall result of this approach is the earliest start-up date of the Facility as a
whole.
A defined subdivision of the Facility into system shall also be used by pre-commissioning staff as the
basis of its pressure test program (hydraulic, pneumatic).
Systems are first defined on the Facility P&I Diagrams; these are marked up using a clear
identification method to show each system and boundaries between systems and ensure that any
requirements for additional isolation for systems and operational areas will be included in the design.
5.2 Site Commissioning Phase
5.2.1 Site Mobilization Plan
Site mobilization of the Commissioning Team will occur to support system turnovers from pre-
commissioning and to ensure that subsequent testing will coincide with project schedule requirements.
Additional Commissioning Test Personnel will be scheduled onsite, as needed, until full staffing levels
are obtained.
The Commissioning Manager will relocate to site after completion of the home office planning and
preparations.
This plan will be developed at the beginning of site mobilization for Commissioning team considering
the actual progress of Commissioning activities and be reviewed with COMPANY’s Commissioning
Team.
5.2.2 Equipment Vendor Support Plan
Contractor will provide Vendor representatives for installation, Commissioning, and Commissioning
services. CONTRACTOR will advise the COMPANY Representative when Vendor representatives are
ready to mobilize to the Commissioning Site.
For all Vendor representatives providing Commissioning assistance and Training for Company
Employee before/after Mechanical Completion, CONTRACTOR will keep a daily time sheet for each
Vendor representative.
5.2.3 Punch Control Plan
WARA PRESSURE MAINTENANCE PROJECT
COMMISSIONING PROCEDURE
Class 1 Doc. No. : 11050146-CM-PRO-000-5017 Rev.A Page 27of 63
Punch items are tasks not yet completed or tasks that do not meet project design and specifications
and can be related but not limited to
Equipment that is damaged, defective, inoperable, incomplete or not yet installed.
Any part of work, including documentation, which does not conform to project scope,
specifications, documentation, recognized engineering practices, relevant codes or statutory
requirements.
Any situation that can have HSE impact.
This Punch will not include any approved facility modification which has been implemented but not
reported on the master document, but incomplete facility modifications will be included on the Punch.
Punch list items will be categorized by priority as shown below.
A. Must be completed prior to Mechanical Completion
B. Must be completed prior to Start-up and Commissioning
C. Can be completed after Start-up but prior to Turnover
5.3 System Turnover
CONTRACTOR’s Commissioning Personnel will work with “COMPANY” prior to turnover of system to
assist Performance Test in the identification and correction of deficiencies that require resolution prior
to turnover.
Prior to the system turnover process will consist of system walk-downs by COMPANY’s
Commissioning personnel. The walk-down will result in the generation of a "System punch list". The
items on this list will be addressed by CONTRACTOR’s Commissioning Team and prior to system
turnover and acceptance by COMPANY’s Commissioning Team.
CONTRACTOR’s Commissioning Group will identify components or system activities / tests that will
be completed by commissioning prior to turnover.
As pre-commissioning progresses to the point of 65% ~ 70% of End of Precommissioning, where
various systems begin to reach mechanical, as well as, electrical completion, precommissioning
begins to switch over from a bulk pre-commissioning mode to a systems completion mode.
Turnover packages that define system boundaries using drawings and databases are developed and
issued to commissioning well in advance of the first scheduled system turnover dates.
The aim of the turnover packages is to provide commissioning with the necessary information to
complete systems or portions of systems (subsystems) in the required sequence for successful project
Commissioning.
Each turnover package will contain mechanical, electrical, and instrumentation components that
represent a usable part of a system or the entire system depending on system size.
As each of the system / subsystem packages near mechanical and electrical completion, the
Commissioning Team will coordinate with pre-commissioning to identify any deficiencies or incomplete
items that would prevent the orderly and systematic testing for the turnover package equipment.
The format, content, and detail of the Turnover Packages is usually defined through contract
WARA PRESSURE MAINTENANCE PROJECT
COMMISSIONING PROCEDURE
Class 1 Doc. No. : 11050146-CM-PRO-000-5017 Rev.A Page 28of 63
definitions and requirements or can be discussed and agreed to in meetings during the EPC portion of
the project.
5.3.1 Turnover Documentation & Records
The following Commissioning documentation and records will be maintained by CONTRACTOR to
enable all parties to review the scope of the Commissioning works, the status of that work and the
confirmation that each element of the work has been satisfactorily completed.
5.3.2 System Manuals
The Commissioning of the facilities will be carried out on a “system-by-system” basis. Each operating
facility, and the specific units involved, is divided into logical process and /or piping and equipment
“systems”. These systems are generally defined by and incorporate equipment required for, a
particular service or portion of the operation.
5.3.3 Documentation for Commissioning
The following document related with Commissioning activities will be included in the system packages
(dossier) for each system.
Notification of Readiness for Commissioning
Commissioning “Punch” Status Report
Check Lists & Reports
Turnover Certificate Request
5.3.4 Commissioning QA/QC Records
The confirmation of completion of commissioning works suitable for Commissioning to commence is
represented by QA/QC Inspection Test Reports for the various elements of the facility. The records
are collated on a discipline basis for each area of the facility.
A QA/QC Status Register will be prepared that reflects the status of commissioning QA/QC
documentation relating to specific facility (by Unit) and systems (by Service).
CONTRACTOR’s QA/QC representatives will sign this Register as certification that the required items
have been completed and registered with COMPANY.
The QA/QC Status Register will be kept current and available for COMPANY and CONTRACTOR’s
Commissioning Team to confirm that all commissioning QA/QC releases have been made for a
particular facility or system prior to Start-up.
This Register will also reflect the issue status of all such QA/QC records such that COMPANY can
confirm readiness for Start-up.
5.3.5 Operating Manual
CONTRACTOR will prepare plant specific draft-operating manual of the unit. The Operating Manual
include procedure related with package items if any and will be submitted to COMPANY for review at
least 90 days prior to Commissioning.
Review of operating manuals shall be done by COMPANY within 30 days after receipt of draft
operating manuals. All the changes, additions, deletion required by the COMPANY will be discussed
WARA PRESSURE MAINTENANCE PROJECT
COMMISSIONING PROCEDURE
Class 1 Doc. No. : 11050146-CM-PRO-000-5017 Rev.A Page 29of 63
with the CONTRACTOR and will be incorporated in the final operating manuals by the CONTRACTOR.
The 10(Ten) copies of final operating manual in English, (along with 1 CD of the same) will be
submitted to COMPANY. The manuals shall be submitted to COMPANY at least 60 days prior to
Commissioning.
5.4 Coordination
5.4.1 Correspondence with COMPANY
The Commissioning of the facilities will be carried out on a “system-by-system” basis.
As soon as a System has been pre-commissioned and completed for each Commissioning activities in
accordance with the Contract and has passed any tests required on that System, CONTRACTOR will
issue “Request for inspection” to notify the COMPANY in writing.
Company shall witness, finish his inspection and complete the Commissioning activities by sign off on
the relevant check sheet/test record sheet.
6. HEALTH SAFETY & ENVIRONMENT (HSE)
6.1 Home Office Preparation
All Commissioning activities are planned and implemented in accordance with the COMPANY and
Contractor’s HSE Guide Lines Procedure. Any accident or impairment to the health of personnel is
avoidable. Commissioning team shall maintain a safe working environment and ensure that injury and
harm to the health of personnel is mitigated.
6.2 Commissioning Site Safety
To meet the schedule & target, End of Pre-commissioning, Commissioning activities will have
schedule overlaps. Commissioning activities will begin early and will take place parallel with pre-
commissioning activities.
The management of hazards shall identify the possibilities of commissioning personnel being exposed
to hazards associated with the activities of the other. The potential for exposure to hazardous
situations increases with the large number of site personnel overlapping independent multiple work
phases.
Commissioning works is essentially the bridge activity between pre-commissioning and start-up. It
must directly interface with Facility Completion. Therefore, toolbox talks will have to be conducted prior
to starting any activity and will be repeated at each shift that will continue with the same activity to
ensure that the work force is familiar with the hazards involved:
Work scheduled to be carried out
Health, Safety, and Environmental requirements related to those activities
Familiar with the Incident Reporting System
6.2.1 Effective Communication
Effective communications is essential in conveying vital information to commissioning and operation
WARA PRESSURE MAINTENANCE PROJECT
COMMISSIONING PROCEDURE
Class 1 Doc. No. : 11050146-CM-PRO-000-5017 Rev.A Page 30of 63
personnel for ensuring their safety and the efficiency of the project. All communication should be clear,
accurate, concise, and well planned to avoid ambiguities, confusion and/or misunderstandings.
Following methods for conveying the information should be utilized as applicable:
Commissioning meetings
Project site notices and placards
Banners and warning signs
Regular tool box talks
Handover log books and shift reports
Project daily progress reports
6.2.2 Isolations
During Commissioning activities, it is necessary to protect personnel from sources of energy
associated with the works by following a safe isolation procedure. Isolation procedures are designed to
protect the crew from unexpected energization, start-up, or release of energy, while working on
equipment or a unit.
Contractor will clear all equipment that will be affected by the equipment isolation. Cleaning of
equipment will be performed as outlines in unit/area specific procedure. Any chemicals or chemical
residual expected to be remaining in the equipment must be documented for each affected work
group.
6.2.3 Safe Use of Nitrogen
Nitrogen is used during Commissioning for leak check and inerting purposes. Nitrogen is an inert gas
that causes asphyxiation, if it is released in a space where it can lower the oxygen levels below
required to sustain life. The nitrogen hazards, consequences on uncontrolled release, protective
measures to be taken, shall be clearly specified in the procedures where nitrogen is used and shall be
discussed with working team prior to start using nitrogen at site.
6.3 Environment & Harmful Emissions
6.3.1 Piping Dewatering
Water used to test pipe work and the pipeline may contain chemical additives to prevent corrosion and
microbiological growth, if required, and where applicable a marker for leak detection. These fluids shall
be discharged in compliance with the Local Environmental Regulations and the Environmental
Management Plan. The medium selection shall take into consideration the environment and
compatibility with the final process fluids without compromising other testing criteria and requirements.
6.3.2 Venting and Flaring
Start-up procedures shall include provisions to minimize flaring and venting; however, flaring and
venting may occur as a result of testing and while bringing the facility up to specifications.
6.3.3 Waste Disposal
Waste disposal shall be in accordance with the COMPANY’s Waste Management guidelines and
wherever it is possible, the re-use or recycling of any solid or liquid waste shall be considered. The
commissioning manager, jointly with the COMPANY, will make a plan for the control of waste
WARA PRESSURE MAINTENANCE PROJECT
COMMISSIONING PROCEDURE
Class 1 Doc. No. : 11050146-CM-PRO-000-5017 Rev.A Page 31of 63
generated during water flushing. The plan shall include permitting, means for storing and disposing
contaminated fluids and material.
6.3.4 Noise Management
Although every effort has been made in the design to minimize noise, the design still has to be tested
to ensure noise levels are within the acceptable range. The Commissioning Team shall make possible
recommendations for improvements, where noise levels do not meet the acceptance criteria. Potential
for excessive noise increases during Commissioning activities.
Therefore, Commissioning strategy shall be evaluated to minimize noise; e.g., consider the use of
water versus air blowing, or reducing the noise level by using silencers or other means. To minimize
the exposure against noise, air blowing will be considered to be done during night time or shift change
as possible.
The personal Noise Dose (a function of noise level and exposure time) shall not exceed 85 dB on a
continuous basis over an eight-hour day. Proper ear protection shall be worn in areas where the noise
level exceeds 85 dB.
7. ATTACHMENTS
Attachment 1: Table – Split of Work for Construction, Pre-commissioning and Commissioning
Attachment 2: Pre-Commissioning/Commissioning Organization
WARA PRESSURE MAINTENANCE PROJECT
COMMISSIONING PROCEDURE
Class 1 Doc. No. : 11050146-CM-PRO-000-5017 Rev.A Page 32of 63
[텍스트 입력]
Attachment 1: Table–Split of Work for Construction, Pre-Comm. & Commissioning
Section Description
1. General
2. Electrical
3. Instrumentation
4. Buildings
5. Air Conditioning
6. Communications Equipment
7. Tie-ins to Existing Facilities
8. Safety & Fire Protection Equipment
9. Civil/Structural
10. Piping and Accessories
11. Flare System
12. Vessels
13. Columns
14. Tanks
15. Exchangers
16. Pumps
17. Compressors
18. Gas Turbines
19. Heaters
20. Miscellaneous
21. Chemicals
22. Package Units
WARA PRESSURE MAINTENANCE PROJECT
COMMISSIONING PROCEDURE
Class 1 Doc. No. : 11050146-CM-PRO-000-5017 Rev.A Page 33of 63
[텍스트 입력]
LEGEND:
Cy = Company, Ctr = Contractor,
X = Perform the work, A = Assist as required, W = Witness and sign off, R = Review and Approve, I =
Inspect and Approve.
1.0 GENERAL Construction
Phase
Pre-
commissioning
Phase
Commissioning
Phase
Ctr Cy Ctr Cy Ctr Cy
a) Obtain vendor assistance where necessary for
Mechanical Completion, Pre-commissioning and
Commissioning.
X X X
b) Obtain any permits and approvals from government and
regulatory agencies required in the name of the
Contractor.
X A X A
c) Make application to the Company for all necessary
permits issued in the Company’s name that are required
for the Work.
X R X R
d) Maintain an adequate vendor instruction file so that
information may be readily reviewed through the Work. X R X R X R
e) Transmit to the Company all ’As Built’ Records,
Operation and Maintenance Manuals, spare parts lists
and all other documentation required to obtain
Turnover.
X R
f) Remove all rust preventatives, oils, greases and paints
used to preserve equipment during transportation and
construction whenever these protective materials will be
detrimental to operation.
X W/I
g) Provide a list and the lubricants of Approved
Manufacturer recommended for use in the Facility.
X R
h) Prepare detailed flushing and testing procedures for the
specific systems.
X R
i) Flush systems and perform initial charge of all
lubricants. Dispose of all flushing oil in accordance with
the Company’s instructions.
X W/I
j) Maintain lubrication after initial charge to achieve Pre-
commissioning.
X
WARA PRESSURE MAINTENANCE PROJECT
COMMISSIONING PROCEDURE
Class 1 Doc. No. : 11050146-CM-PRO-000-5017 Rev.A Page 34of 63
[텍스트 입력]
1.0 GENERAL (Contd.) Construction
Phase
Pre-
commissionin
g
Phase
Commissioning
Phase
k) Remove all temporary supports, bracing or other foreign
objects that were installed in vessels, ducts, piping,
transformers, machinery, or other equipment to prevent
damage during shipment, storage, and erection and
repair any damage sustained.
X
l) Inspect and check Work during construction stage and
perform such non-operational test as are necessary to
assure the integrity of the installation in accordance with
the Issued for Construction drawings and specifications.
X W/I
m) Complete all necessary insulation, painting, grating,
fencing, paving, touch-up concrete and grouting, and
items of like nature.
X I X I
n) Make initial charge of non-production materials, such as
desiccants and transformer oil.
X W
o) Make check of lighting intensities in buildings and plant
areas in accordance with Project Specifications.
X W
p) Verify that the Work, or portion thereof, is complete and
that all required inspections, tests, reviews and
approvals are complete and recorded.
X R/I
q) Document all inspections, test and other
Precommissioning activities. Document all deficiencies
discovered during the course of the activities along with
corrective actions taken.
X R
r) Prepare punchlists, by system, of deficiencies between
as-built plant and latest P&ID, specifications and vendor
instructions. Correct deficiencies.
X R/I X R/I X R/I
s) Check all items of equipment for adequate, safe and
functional access per Project specifications.
X I
t) Provide, install, slip and/or remove all temporary and
permanent blinds and spectacle plates required to isolate new systems from existing systems.
X I X I
u) Thirty (30) days prior to expected Mechanical
Completion, the Contractor is to send a notification of impending Mechanical Completion to the Company.
X R
v) Completion of fire-proofing and insulation to limit heat
loss during Commissioning and for protection of personnel.
X I
w) Removal of scaffolding and other temporary works,
debris, tools, and extraneous material from areas to be turned over.
X I X I
WARA PRESSURE MAINTENANCE PROJECT
COMMISSIONING PROCEDURE
Class 1 Doc. No. : 11050146-CM-PRO-000-5017 Rev.A Page 35of 63
[텍스트 입력]
1.0 GENERAL (Contd.) Construction
Phase
Pre-
commissioning
Phase
Commissioning
Phase
x) Ten (10) days prior to expected Mechanical
Completion, the Contractor is to send request for the Company punchlist, with copy of master punchlist status.
X R/I
y) Prepare and submit notification of Mechanical
Completion when all Work items identified by the Contractor and the Company as required for Commissioning are completed. Each notification shall identify plant system(s) submitted for acceptance, copy of master punchlist for those system(s), list of uncompleted (“exception”) items with the reason for their late completion and estimated completion date, inspection and test and check-out reports, and copies of marked-up `As Built’ P&ID’s and one line diagrams and logic diagrams and list of start-up spare parts on site.
X W
z) Verify all instruments and electrical panels and local
instruments and valves are accessible for operation and maintenance.
X I
aa) Conduct all flushing, blowing and
chemical/mechanical cleaning operations where such operations can be accomplished without using permanent installed equipment.
X W
ab) Conduct all flushing and blowing operations where
permanently installed equipment must be used to obtain proper line velocities.
X W
ac) Provide any special media for flushing and/or
cleaning purposes.
X R
ad) Maintain flushing and/or blowing records as required. X I
ae) Conduct all operational tightness tests. X W/I
af) Prepare detailed purge procedure for specific
system.
X R X R
ag) Maintain tightness test records, as required. X I
ah) Install inerting connections. X W
ai) Provide inerting materials and introduce where
specified.
X W/I
aj) Submit application for Turnover Certificate when all
activities identified by the Contractor and the Company are completed. Each notification shall identify plant system(s) submitted for acceptance and copy of signed-off report forms for Commissioning activities.
X R
WARA PRESSURE MAINTENANCE PROJECT
COMMISSIONING PROCEDURE
Class 1 Doc. No. : 11050146-CM-PRO-000-5017 Rev.A Page 36of 63
[텍스트 입력]
1.0 GENERAL (Contd.) Construction
Phase
Pre-
commissioning
Phase
Commissioning
Phase
ak) Provide raw materials, such as reservoir crude Feed,
brackish water, utilities etc.
X
al) Check the integrity of system shutdown and prove
the reliability before Commissioning.
X W
am) Proceed to Commissioning as per operating manual
instructions.
A X
an) Conduct individual equipment noise surveys, as
required by the Company’s specifications documents results.
A X
ao) Prepare and submit Performance Testing
procedures.
X A
ap) Notify when the system(s) are on stream, at design
conditions and steady for the Performance Tests.
A X
WARA PRESSURE MAINTENANCE PROJECT
COMMISSIONING PROCEDURE
Class 1 Doc. No. : 11050146-CM-PRO-000-5017 Rev.A Page 37of 63
[텍스트 입력]
2.0 ELECTRICAL
Construction
Phase
Pre-
commissioning
Phase
Commissioning
Phase
Ctr Cy Ctr Cy Ctr Cy
2.1 TRANSFORMERS
a) Check physically for damage, oil leaks, etc. X W
b) Check insulation resistance between primary to
earth, secondary to earth and primary to
secondary.
X W
c) Perform oil dielectric strength tests. Provide
samples to Company for independent check.
Perform oil filtration, if required.
X W
d) Perform operation of Buchholz relay. X W
e) Check alarm and trip contacts for actuation. X W
f) Check off-load changer for proper mechanical
operation.
X W
g) Check polarity of terminals and the phase
sequence.
X W
h) Perform High Voltage DC Test in accordance with
the Project specification.
X W
2.2 H.V. SWITCHBOARDS
a) Check physically for damage, missing parts,
moving parts, clearance, etc.
X W
b) Measure the insulation resistance of each bus
from phase to phase and phase to earth with all
circuit breakers in service position, but with the
circuit breakers open.
X W
c) Draw out each circuit breaker and starter out of
the panel and push it back to ensure that the
operation is smooth.
X W
d) Draw out each circuit breaker and starter to the
isolated position, close them manually and
measure the insulation resistance from phase to
earth.
X W
e) Draw out each potential transformer to the
isolated position and measure the insulation
resistance from phase to earth.
X W
f) Check all current transformers by Primary
injection testing.
X W/R
WARA PRESSURE MAINTENANCE PROJECT
COMMISSIONING PROCEDURE
Class 1 Doc. No. : 11050146-CM-PRO-000-5017 Rev.A Page 38of 63
[텍스트 입력]
2.0 ELECTRICAL (Contd.)
Construction
Phase
Pre-
commissioning
Phase
Commissioning
Phase
Ctr Cy Ctr Cy Ctr Cy
g) Close and open each circuit breaker and starter in
test position, electrically using the control
switch/push buttons at the H.V. switchboard.
Check tripping of the circuit breaker and starter with
its emergency mechanical trip device at the H.V.
switchboard.
X W
h) Check all interlocking between earthing switches
and circuit breakers/starters. Close and open the
earthing switches and check for correct operation.
X W
i) Check the control circuit of each circuit breaker and
starter with all the interlocks and check for correct
operation. Check remote start/stop controls for
starters.
X W
j) Check castell key interlocking between the circuit
breaker and other devices as applicable.
X W
k) Check the phase sequence. X W/R
l) Check the characteristics and operation of each
relay by secondary injection testing.
X W/R
m) Simulate the operation of each of the protective
relays, trip receive and auxiliary relays, and ensure
energising of the lock-out relays and tripping of the
respective circuit breakers.
X W/R
n) Simulate and ensure correct operation of pilot wire
feeder protective relay.
X W/R
o) Check the automatic change over from mains
supply to stand-by supply and vice versa and
ensure correct operation. Check the manual
change over scheme mode.
X W/R
p) Set all protective relays to their correct setting. X W/R
q) The Contractor shall establish a Tag and Lock-out
Procedure, including a Work Permit Procedure for
the construction, Precommissioning and
Commissioning (The Company Work Permit
Procedure shall be followed to energize circuits for
powered checks/tests and start-ups).
X R X R X R
r) Energize all circuits required for the Contractor’s
Work responsibilities.
X W/I
WARA PRESSURE MAINTENANCE PROJECT
COMMISSIONING PROCEDURE
Class 1 Doc. No. : 11050146-CM-PRO-000-5017 Rev.A Page 39of 63
[텍스트 입력]
2.0 ELECTRICAL (Contd.)
Construction
Phase
Pre-
commissioning
Phase
Commissioning
Phase
Ctr Cy Ctr Cy Ctr Cy
s) Check High Voltage DC Test as per Project
Specifications
X W
2.3 440V SWITCHBOARDS
a) Check physically for damage, missing parts,
moving parts clearance.
X W
b) Measure the insulation resistance of each bus from
phase to phase and phase to earth with all circuit
breakers, starters, and switchfuse feeders in
service position but open.
X W
c) Draw out each circuit breaker, starter and
switchfuse feeder, and push it back to ensure that
the operation is smooth.
X W
d) Draw out each circuit breaker and switchfuse
feeder to the isolated position, close them manually
and measure the resistance from phase to phase
and phase to earth.
X W
e) Close and open each breaker is test position and
service position electrically. Check tripping of the
circuit breaker with its emergency mechanical trip
device.
X W
f) Check the control circuit of each circuit breaker with
all interlocks and check for correct operation.
X W
g) Draw out each starter feeder to isolated position
and check the insulation resistance from phase to
phase and phase to earth on the load side with the
starter open, for power and control circuits.
X W
h) Draw out each starter feeder to the test position,
use the test control supply and check the starter for
correct operation with all the interlocks from remote
start and local/remote stop.
X W
i) Close and open switchfuse feeders and ensure
correct operation.
X W
j) Check the current transformers by Primary Injection
Testing.
X W/R
k) Check the characteristics and operation of each
relay by secondary injection.
X W/R
WARA PRESSURE MAINTENANCE PROJECT
COMMISSIONING PROCEDURE
Class 1 Doc. No. : 11050146-CM-PRO-000-5017 Rev.A Page 40of 63
[텍스트 입력]
2.0 ELECTRICAL (Contd.) Construction
Phase
Pre-
commissioning
Phase
Commissioning
Phase
Ctr Cy Ctr Cy Ctr Cy
l) Simulate the operation of each of the protective relays
and auxiliary relays and ensure energizing of the
lockout relays and tripping of the respective circuit
breakers.
X W/R
m) Set all the protective relays to their correct setting. X W/R
n) Set all the thermal overload relays to their correct
setting.
X W/R
o) The Contractor shall establish a Tag and Lock-out
Procedure including a Work Permit Procedure for the
construction, Precommissioning and Commissioning
(Company Work Permit Procedure shall be followed to
energize circuits for powered checks/tests and start-
ups).
X R X R X R
p) Energise all circuits required for the Contractors’ Work
responsibilities.
X W/I
2.4 MOTORS
a) Check physically for damage, free rotation of fan and
movement of parts.
b) Check the insulation resistance value and dry out the
machine if the value is:
- less than 50 megohms for 3.3KV motors
- less than 5 megohms for 440V motors.
The method of drying out and retesting shall be in
accordance with Approved Manufacturers’ instructions
c) Check condition of grease in grease lubricated motor
bearings and lubricate the bearings if necessary.
X W
d) Check and ensure that all electrical connections are
tight.
X W
e) Check the direction of rotation running the motor
momentarily. Run the motor uncoupled for four (4)
hours and check for any abnormalities. The
temperature rise of motor shall be recorded at the end
of this period.
X W
2.5 BATTERIES AND CHARGERS
a) Check physically for damage.
X W
b) Check the control circuit of charger for correct
operation. Ensure that current limiting circuits, auto-
changover circuits from float to boost mode and vice
versa are functioning correctly.
X W
WARA PRESSURE MAINTENANCE PROJECT
COMMISSIONING PROCEDURE
Class 1 Doc. No. : 11050146-CM-PRO-000-5017 Rev.A Page 41of 63
[텍스트 입력]
2.0 ELECTRICAL (Contd.) Construction
Phase
Pre-
commissioning
Phase
Commissioning
Phase
Ctr Cy Ctr Cy Ctr Cy
c) Top up the electrolyte level in the batteries as
required.
X W
d) Boost charge the batteries. X W
e) Energize the charger and keep batteries on float
charge.
X W/R
f) Perform battery acceptance tests on batteries X W/R
2.6 CABLES
a) All high voltage (above 1KV grade) cables shall be
subjected to high voltage DC test before
termination. Insulation resistance value from
phase to phase and phase to earth shall be
measured before and after H.V.D.C test.
X W
b) Before making the H.V. cable joint at each
location, the insulation resistance shall be
measured from phase to phase and phase to
earth. After completion of all joints and before
termination, the entire cable shall be subjected to
high voltage D.C. test followed by insulation
resistance check.
X W/R
c) For all low voltage cables (up to 1KV grade), the
insulation resistance value from phase to phase
and phase to earth shall be measured before
termination. Cable conductor continuity shall be
checked for each and every cable.
X W
d) For any existing control cable which requires any
joint, the insulation resistance shall be measured
between conductors to earth before and after
completion of the joint. For such cable the voltage
at which the insulation resistance check is carried
out shall be determined by the Company.
X W/R
e) Phase sequence and matching checks shall be
conducted before connection of each and every
high voltage cable.
X W/R
f) The insulation resistance checks for 11KV system
shall be done with 5KV Megger, and 3.3KV system
with 2.5KV Meggars and for LT system with 1000V
Meggar.
WARA PRESSURE MAINTENANCE PROJECT
COMMISSIONING PROCEDURE
Class 1 Doc. No. : 11050146-CM-PRO-000-5017 Rev.A Page 42of 63
[텍스트 입력]
2.0 ELECTRICAL (Contd.) Construction
Phase
Pre-
commissioning
Phase
Commissioning
Phase
Ctr Cy Ctr Cy Ctr Cy
2.7 EARTHING
a) Measure and record the earth resistance value of
each electrode.
X W
b) Check the continuity of the earthing system. X W
c) Ensure that the earth resistance value of the
complete earthing system does not exceed 4 ohms.
X W/R
2.8 LIGHTING AND SMALL POWER
a) Install lamps (incandescent, bulbs, mercury vapour
lamps, fluorescent tubes, etc.) required to fill the
fixtures, verify all lights and switches operate
properly. Test photo cells for proper operation.
X W
b) Verify that all lights are operational using normal
and emergency power.
X W/R
c) Test small power systems for correct operation. X W/R
2.9 CONTROL PANELS FOR 11KV AND 3.3KV
SWITCHBOARDS
a) Check physically for damage.
X W
b) Close and open each circuit breaker and starter
from control panel and ensure correct operation.
X W
c) Check and ensure correct operation of the Variable
Speed Drive Control Panel.
X W
d) Check and ensure correct operation of the
annunciator.
X W
2.10 UNINTERRUPTIBLE POWER SUPPLY
SYSTEM
a) Carry out checks and tests for the battery and
charger of UPS as in Clause 2.6 (a) to (f) above.
X W X W/R
b) Check circuits of inverter for correct operation.
Check the output waveforms including harmonic
distortion. Verify the current limiting circuit. X W/R
c) Check the bypass transformer and associated AVR
circuits.
X W/R
d) Check the static switch circuits. X W/R
WARA PRESSURE MAINTENANCE PROJECT
COMMISSIONING PROCEDURE
Class 1 Doc. No. : 11050146-CM-PRO-000-5017 Rev.A Page 43of 63
[텍스트 입력]
2.0 ELECTRICAL (Contd.)
Construction
Phase
Pre-
commissioning
Phase
Commissioning
Phase
Ctr Cy Ctr Cy Ctr Cy
e) Initiate transfer from one source to another, verify
the transfer timings, transient voltage dips.
recovery times, etc.
X W/R
f) Check all alarms and signalling circuits. X W/R
g) Energize all circuits required for the Contractors’
Work responsibilities.
X W/I
2.11 MISCELLANEOUS
a) Check out cathodic protection system.
X W/R
b) Paint or tag all electrical apparatus (switchboards,
breakers, push button boxes, connecting boxes,
etc.) according to the Company’s colour code or
regulation.
X W
WARA PRESSURE MAINTENANCE PROJECT
COMMISSIONING PROCEDURE
Class 1 Doc. No. : 11050146-CM-PRO-000-5017 Rev.A Page 44of 63
[텍스트 입력]
3.0 INSTRUMENTATION Construction
Phase
Pre-
commissioning
Phase
Commissioning
Phase
Ctr Cy Ctr Cy Ctr Cy
a) Check instruments and tag data supplied against
specifications sheet (type, range, material).
X I
b) Install instruments and make all specified
connections.
X W/I
c) Perform required pressure tests on instrument take-
off piping and air piping and tubing.
X W/I
d) Blow-out instrument air piping with dry air
reconnecting after pressure tests, and site
instrument air regulators.
X W/I
e) Check continuity and identification of transmission
and control system for each instrument to ensure
proper hook up and compliance with Project
specifications. This applies both to pneumatic and
electrical, analog and digital-systems. Perform
insulation test with instruments isolated or removed
for instrument electrical wiring.
X R/I
f) Check pneumatic and electrical instrument systems
for proper installation including tagging, supports,
accessibility, correct material, ratings and calibrated
fittings. Synchronise transmitter and receiver
readings for each instrument.
X R/I
g) Remove control valves, flowmeters, venturis, orifice
plates, and other in-line instruments prior to pipe
cleaning/flushing and hydrotesting.
X R/I
h) Leak-test `tight shutoff’ rates safety and control
valves at grade before installation.
X W/I
i) Install instrument after line flushing/cleaning and
hydrotesting.
X I
j) Perform all instrument calibrations at site before
installation.
X I
WARA PRESSURE MAINTENANCE PROJECT
COMMISSIONING PROCEDURE
Class 1 Doc. No. : 11050146-CM-PRO-000-5017 Rev.A Page 45of 63
[텍스트 입력]
3.0 INSTRUMENTATION (Contd.) Construction
Phase
Pre-
commissioning
Phase
Commissioning
Phase
Ctr Cy Ctr Cy Ctr Cy
k) Prepare calibration sheets for each calibration,
showing as a minimum the following:
- date of calibration
- instrument tag number
- instrument spec. sheet number
- reading before and after calibration, problems
noted and corrected
- description of calibration, method/equipment
- name of person doing calibration, and indication of
acceptance when achieved
- reference to other instruments calibrated
simultaneously.
These sheets shall be submitted as part of the loop
check data package.
X R
l) Inspect all flow elements. Micrometer check at
grade.
X W
m) Check all emergency and safety systems for
operability, by simulation, including bypass
switches/lights and resets.
X W/I
n) Perform site acceptance tests on computerised
Distributed Control System (DCS) in accordance
with Approved Manufacturers test procedures. The
DCS may not be powered up until the UPS is
completely checked out and operable. (item 2.11 &
a)
X W
o) Perform site acceptance tests on computerised
Integrated Control System/Distributed Control
System (ICS/DCS) in accordance with approved
Manufacturers test procedures. The ICS/DCS may
not be powered up until the UPS is completely
checked out and operable. (Item 2.11 & a)
X W
p) Provide sealing fluids (for example, manometers,
gauges, etc.) where required.
X I
q) Test annunciators and individual alarms by
simulating alarm conditions where possible.
X W/I
r) Stroke control valves, solenoid valves and
emergency isolation/shutdown valves, adjust the
valve movements, limit switch and air operation/air
failure actions as required.
X W
WARA PRESSURE MAINTENANCE PROJECT
COMMISSIONING PROCEDURE
Class 1 Doc. No. : 11050146-CM-PRO-000-5017 Rev.A Page 46of 63
[텍스트 입력]
3.0 INSTRUMENTATION (Contd.) Construction
Phase
Pre-
commissioning
Phase
Commissioning
Phase
Ctr Cy Ctr Cy Ctr Cy
s) Operate and adjust as necessary timers, switches,
relays, push buttons, interlocks and other
instrumentation components.
X W
t) Confirm that all elements in each instrument loop
have been checked and tested for compliance with
the drawings and specifications, after the loop
elements are all complete and correct, install sealing
compound in seals where required.
X R/I
u) Prepare and submit to the Company loop check
packages for the Company approval prior to full loop
checking by the Contractor. Data package shall
contain (as applicable to each loop) installation
check sheets, wire and tubing test sheets,
instrumentation check sheets, with copy of the
respective loop diagram and P&ID and
instrumentation specification sheets.
X R/I
v) Perform full loop checks. Identify and log any
problems for the Contractor Resolution.
X W/R
WARA PRESSURE MAINTENANCE PROJECT
COMMISSIONING PROCEDURE
Class 1 Doc. No. : 11050146-CM-PRO-000-5017 Rev.A Page 47of 63
[텍스트 입력]
Construction
Phase
Pre-
commissioning
Phase
Commissioning
Phase
Ctr Cy Ctr Cy Ctr Cy
4.0 BUILDINGS
a) Operate electrical and mechanical equipment such as
lighting, fans, and air conditioning systems to the
extent required to verify its operability. All Work
necessary to properly safeguard the equipment must
be complete.
X W
b) Install furniture, if any. X W
c) Conduct test on HVAC systems, building
pressurisation system, emergency switching system,
and safety equipment (refer to sections 3,5 and 6).
X W
d) Clean toilets, basins, sewers and water systems. X R/I
e) Operate and adjust doors, windows. Buildings shall
be tested for leak tightness and maintenance of
internal positive pressure.
X R/I
f) Perform roof leak test. X W/I
g) Commission air conditioning, building pressurisation
system, gas detection and fire control/halon systems
X R/I
h) Check the slope of roofing in order to ensure runoff of
rainwater.
X W
5.0 AIR CONDITIONING
a) Air conditioning air handling units, and individual
components thereof, appurtenances, piping and
wiring connected to the units and instrumentation
controlling the units shall be Pre-commissioned per
requirements, of the Company’s specifications and
Approved Manufacturers instructions and sections 2
& 3 of this document.
X W/I
b) Provide all Freon or other cooling medium required to
charge/recharge the air conditioning units.
X W/I
c) Charge or recharge the units as required. X W/I
6.0 COMMUNICATIONS EQUIPMENT
a) Install checkout, calibrate and test PABX, telephone
communication, internal TV system, all cabling and
associated equipment included in Work, as per
Approved Manufacturer’s instructions.
X W/I
7.0 TIE-INS TO EXISTING FACILITIES
a) The Contractor to perform all tie-in work including the X W/I
WARA PRESSURE MAINTENANCE PROJECT
COMMISSIONING PROCEDURE
Class 1 Doc. No. : 11050146-CM-PRO-000-5017 Rev.A Page 48of 63
[텍스트 입력]
Construction
Phase
Pre-
commissioning
Phase
Commissioning
Phase
Ctr Cy Ctr Cy Ctr Cy
preparation of hot tap forms. (See Note 1).
b) Prior to starting the Work, Contractor to obtain Work
Permit approval for tie-in and carry out the Work, as
required by specifications and as directed by the
Company.
X R
c) Isolate, Drain and Depressure Process
Equipment/Piping to which Tie-in is being made.
X
d) Provide and Install Temporary Blinds as required. X W/I
e) If necessary, purge existing Equipment with N2 to
make existing Equipment/Piping safe for Hot Work.
X W/I
f) Remove blinds, reinstate Piping as required. X W/I
NOTE 1:
The Contractor shall be provided with minimal shutdown
period for the existing facilities during the tie-in work.
In order to obtain necessary work permits, it would be the
Contractors’ responsibility to give adequate prior notice to
the Company to obtain the necessary `shutdown’.
8.0 SAFETY & FIRE PROTECTION EQUIPMENT
a) Install relief valves or dummy spools during
construction.
X W/R
b) Submit complete PSV (Pressure Safety Valve) and/or
VSV (Vacuum Safety Valve) test authorisation
package (testform, PSV or VSV specification sheet,
P&ID) with PSV or VSV.
X R
c) Install all protective shields. X W/I
d) Arrange for on-Site testing and calibration of all PSVs
(Pressure Safety Valves) and VSVs (Vacuum Safety
Valves). Provide new tags showing the Company
serial numbering system. Paint all valve bodies per
the Company specifications.
X W/I
WARA PRESSURE MAINTENANCE PROJECT
COMMISSIONING PROCEDURE
Class 1 Doc. No. : 11050146-CM-PRO-000-5017 Rev.A Page 49of 63
[텍스트 입력]
8.0 SAFETY & FIRE PROTECTION EQUIPMENT
(Contd.)
e) Paint and/or tag all PSVs (Pressure safety valves)
and/or VSVs (Vacuum safety valves), car sealed (i.e.
locked open or locked close) valves, and safety
equipment as approved by the Company. Provide
and lock all valves per P&ID positions.
Construction
Phase
Pre-
commissioning
Phase
Commissioning
Phase
Ctr
X
Cy
W
Ctr Cy Ctr Cy
f) Inspect and tag all portable fire extinguishers. X W/R
g) Install portable extinguishers, first aid kits and similar
fire and safety equipment. Locations shall be
approved by Company based on Fire & Safety
Equipment Location Plan.
X W/R
h) Remove, prior to equipment testing, all safety devices
such as rupture discs and safety valves. Deliver
safety devices to KOC workshop for testing.
X W
i) Retrieve safety devices delivered to KOC Workshop
for testing and replace after equipment testing all
safety devices such as rupture discs and safety valves
in accordance with P&ID.
X W
j) Check the operability of sudden lighting shut-off
switch, if any.
X W
k) Commission all new fire protection equipment.
Conduct system capacity tests.
W A
l) Test safety showers for proper installation, flow rate,
and water temperature.
X W
m) Testing, Commissioning and start-up operation of the
fire pumps, diesel engine drive, flow measurement,
pressure check, performance test, etc.
X W
WARA PRESSURE MAINTENANCE PROJECT
COMMISSIONING PROCEDURE
Class 1 Doc. No. : 11050146-CM-PRO-000-5017 Rev.A Page 50of 63
[텍스트 입력]
Construction
Phase
Pre-commissioning
Phase
Commissioning
Phase
Ctr Cy Ctr Cy Ctr Cy
9.0 CIVIL / STRUCTURAL
a) Sewer and drain lines shall be flushed and
gravity tested, for leaks, then the sewers
cleaned and all clean-outs, seal pots and
service connections shall be checked for proper
installation and functioning.
X W
b) All installations shall be checked for invert
elevation using the mirror and light test.
X W
c) Operate and inspect plumbing systems to
confirm proper functioning and leak tightness.
X W
d) Check that all required areas are fireproofed. X W
e) Check the working areas around equipment
such as turbines, heat exchangers etc. are free
of any obstacles and properly compacted/paved
per specification.
X W
f) Check the area under suction filters of turbines
is paved, cleaned and protected against sand
drift.
X W
10.0 PIPING AND ACCESSORIES
a) Clean piping and hydrostatically or
pneumatically pressure test, as required by
codes, specifications and the Company’s
instructions.
X W
b) Before flushing/cleaning or pressure testing,
remove any control valve, orifice plate and the
like which might be damaged, and re-install
after that Work is completed.
X W/I
c) Coordinate the flushing, cleaning, pressure
testing and corrosion prevention requirements
with all other Pre-commissioning activities, such
as vessel/exchanger internal inspections, oil
system cleaning and flushing and run-in,
tightness testing and all other Work activities.
X R
d) Remove blanks and install spectacle blinds to
required positions after pressure testing.
X W/I
e) Check piping for correct slope and, for process
gas lines, that no `pocketed’ sections exist
upstream of flare. Correct as required.
X I
f) Provide and install all line vents, drums,
strainers - both temporary and permanent,
WARA PRESSURE MAINTENANCE PROJECT
COMMISSIONING PROCEDURE
Class 1 Doc. No. : 11050146-CM-PRO-000-5017 Rev.A Page 51of 63
[텍스트 입력]
Construction
Phase
Pre-commissioning
Phase
Commissioning
Phase
Ctr Cy Ctr Cy Ctr Cy
blinds and non return valves called for on
relevant drawings and specifications.
X W
WARA PRESSURE MAINTENANCE PROJECT
COMMISSIONING PROCEDURE
Class 1 Doc. No. : 11050146-CM-PRO-000-5017 Rev.A Page 52of 63
[텍스트 입력]
10.0 PIPING AND ACCESSORIES (Cont.)
Construction
Phase
Pre-
commissioning
Phase
Commissioning
Phase
Ctr Cy Ctr Cy Ctr Cy
g) Provide and install other temporary blinds and
bypasses required for Commissioning and start-up as
specified by the Company.
X W/R
h) Check packing and packing materials and lubrication
of valves, repack and lubricate as required.
X W
i) Supply and install line identification tags, signs and
flow arrows. To be coordinated with Company.
X W
j) Provide list and location of all blinds installed. X R X R X R
k) Check spring hangers, supports, guides, expansion
joints, and other pipe specialities for the removal of
all shipping and erection stops and for the
correctness of cold settings for the design service.
X W
l) Check piping to be free of bulges and imperfections. X W
m) Check piping is properly resting on support and
installed in accordance with drawings to provide
thermal movements where applicable.
X W
n) Provide all replacement gaskets, spool pieces,
hoses, temporary connections, riggings/hoistings,
and blind required for cleaning, treating, flushing and
inerting activities. Supply supervised labour and
necessary tools/equipment for air and/or water
flushing, oil flushing, chemical and/or steam treating
and flushing, as required. This will include removing
control valves, check valves/flappers, flow elements,
installation of temporary spool pieces, and
replacement of those items when the
cleaning/flushing activities are completed.
X W
o) Perform flushing operations as foreseen, after
Mechanical Completion.
X R/I
p) Perform operational tightness tests of the process
systems, using pressurised instrument quality air to
bring the process systems to their adequate
pressure.
X R/I
q) After operational tightness tests completion, purge
process piping and equipment with nitrogen per
purging procedures.
X R/I
WARA PRESSURE MAINTENANCE PROJECT
COMMISSIONING PROCEDURE
Class 1 Doc. No. : 11050146-CM-PRO-000-5017 Rev.A Page 53of 63
[텍스트 입력]
10.0 PIPING AND ACCESSORIES (Cont.)
Construction
Phase
Pre-
commissioning
Phase
Commissioning
Phase
Ctr Cy Ctr Cy Ctr Cy
r) Adjust spring hangers, supports, etc. in `Hot’
conditions.
X I
s) Prepare detailed flushing procedure for the specific
system.
X W
t) Visually check the overall system to be
Commissioned to confirm its integrity.
X W
u) Prepare purging procedure for specific system and
ensure oxygen limit to be 2% or less.
X W
10.1 SPECIAL PROCEDURES FOR PIPE LINES
a) Verify that all components, piping, pigging facilities
are installed in accordance with the design
drawing/specification and vendor instructions.
X I
b) Prepare flushing procedure including purging. X R
c) Perform cleaning and flushing operations, after
Mechanical Completion, using storage tanks, transfer
pumps and pigging facilities.
X W
d) Perform gauging of pipeline before hydrotesting and
record the gauging results.
X W
e) Conduct functional tests on pigging facilities. X W
f) Hydrostatically pressure test pipeline, as required by
codes, specifications and the Company’s instructions.
X W
g) Undertake all elec. & inst. tests as per the relevant
sub-section of sections 2 & 3 of this document (refer
to sub-section for responsibilities).
h) De-water, dry, purge and Commissioning of pipeline
as required by codes, specifications and the
Company’s instructions.
X W
WARA PRESSURE MAINTENANCE PROJECT
COMMISSIONING PROCEDURE
Class 1 Doc. No. : 11050146-CM-PRO-000-5017 Rev.A Page 54of 63
[텍스트 입력]
11.0 FLARE SYSTEM
Construction
Phase
Pre-
commissioning
Phase
Commissioning
Phase
Ctr Cy Ctr Cy Ctr Cy
a) Verify that all components, piping, electrical and
instrumentation are installed in accordance with the
Project drawings/specification.
X I
b) All system lines shall be checked during construction
to be free of dirt and debris.
X I
c) Verify that pipe guides and anchors on flare line
allow for thermal expansion and that saddle supports
rest fully on concrete supports/slide plates. Correct
as required.
X I
d) Verify the flare lines are continuously sloping towards
ground flare, burn pit and/or stack at a specified rate
of inclination.
X W
e) Pneumatically test flare lines and service lines. X I
f) Conduct functional test on ignition system utilising
propane.
X W
12.0 VESSELS
a) Check the nameplates data for correctness, per
P&ID and specification sheets. Resolve any
differences.
X W
b) Clean out all vessels, open manholes and openings
for inspection.
X W
c) Inspect internals and coatings, signify complete and
ready for final closure.
X W/I
d) Witness inspections to extent desired. W
e) Prepare purge procedure as per code of practice
(pressure cycle procedure) and repeat the cycle until
safe limits of oxygen (2% or less) are obtained.
X W
f) Dry out, if required, and install materials such as
desiccants, catalysts, resins, chemicals etc.
X W
g) Issue to the Contractor, in writing, instructions to
close- up each vessel.
X
h) Properly close-up all vessels, manways, and
openings after final inspection (items c and d).
X W
i) Check ladders and platforms with the Company for
required access, per specification.
X W
WARA PRESSURE MAINTENANCE PROJECT
COMMISSIONING PROCEDURE
Class 1 Doc. No. : 11050146-CM-PRO-000-5017 Rev.A Page 55of 63
[텍스트 입력]
12.0 VESSELS (Contd.) Construction
Phase
Pre-
commissioning
Phase
Commissioning
Phase
Ctr Cy Ctr Cy Ctr Cy
j) Calibrate/test and designate the Company
numbering system for all safety valves including tank
pressure vacuum valves.
X W/I
13.0 COLUMNS
a) Check the nameplates data for correctness, per
P&ID and Project specification. Resolve any
differences.
X W
b) Clean out all columns, open manholes and manhole
trays for inspection.
X W
c) Inspect internals, trays as per Approved
Manufacturer’s drawings, signify complete and ready
for final closure.
X W/I
d) Witness inspection to the extent desired. W
e) Prepare purge procedure as per code of practice
(pressure cycle procedure) and repeat until the safe
limits of oxygen (2% or less) are obtained.
X W
f) Issue to the Contractor, in writing, instructions to
close- up each column.
X
g) Properly close-up all vessels, manways, and
openings after final inspection (items c and d). X W
h) Check ladders and platforms with the Company for
required access, per specification.
X W
i) Calibrate/test and designate the Company
numbering system for all safety valves including tank
pressure vacuum valves.
X W/I
14.0 TANKS
a) Open manholes for cleaning and inspection. X W/I
b) Inspect internal distributor/collectors and coating,
signify complete and ready for final closure.
X W/I
c) Perform hydrostatic test of tank and internal piping, if any. Clean tank after testing.
X W
d) Perform settlement survey prior to, during and after hydrostatic test.
X W/I
e) Inspect tank internals and gauging equipment, painting/coating, P.V. valves and foam pourers, signify as complete and ready for final closure.
X W/I
WARA PRESSURE MAINTENANCE PROJECT
COMMISSIONING PROCEDURE
Class 1 Doc. No. : 11050146-CM-PRO-000-5017 Rev.A Page 56of 63
[텍스트 입력]
14.0 TANKS (Contd.)
Construction
Phase
Pre-
commissioning
Phase
Commissioning
Phase
Ctr Cy Ctr Cy Ctr Cy
f) Check tank for required access, with the Company, per Project specification.
X W/I
g) Calibration measurements, calculations and tables. (Tank Strapping)
X
h) Calibrate/test and designate the Company numbering system for all safety valves all over the Facility including tankage pressure vacuum valves.
X W/I
i) N2 purging of tanks. X W
15.0 EXCHANGERS
15.1 SHELL AND TUBE EXCHANGERS
a) Perform internal inspection or testing in field, if
required, of exchangers that have previously been shop inspected. (To be done only if specially called in Specifications or Drawings.)
X W
b) Open channel heads on covers of exchangers that have been tested with water at the shop.
X W
15.2 AIR COOLED EXCHANGERS
a) Inspect exchangers to ensure that temporary
shipping supports and erection materials have been removed.
X W
b) Adjust fan assemblies to obtain specified tip clearance and test.
X W/I
c) Check operation of louvres, if any, and operating linkage.
X W/I
d) Open ten (10) plugs at each bundle of the exchangers that have been tested with water at the shop.
X W/I
15.3 PLATE HEAT EXCHANGERS
a) Open inlet and outlet connections for inspection.
Remove any temporary shipping supports.
X W/I
GENERAL:
Calibrate/test and designate Company numbering system
for all safety valves all over the Facility including tankage pressure vacuum valves.
X W/I
WARA PRESSURE MAINTENANCE PROJECT
COMMISSIONING PROCEDURE
Class 1 Doc. No. : 11050146-CM-PRO-000-5017 Rev.A Page 57of 63
[텍스트 입력]
Construction
Phase
Pre-
commissioning
Phase
Commissioning
Phase
Ctr Cy Ctr Cy Ctr Cy
16.0 PUMPS
a) Rotate pumps by hand to ascertain that they turn freely.
X W
b) Check motor for rotation, run-in four (4) hours uncoupled and check bearings. Submerged oil pump/motor may be run-in coupled after oil flushing activities are completed. Recouple pump to motor.
X W/R
c) Align pump with driver after motor run-in and coupling installation.
X W/R
d) Check for and eliminate any loads imposed on the pumps by piping connections (to be done simultaneously to alignment operation).
X W/R
e) Install proper lubricants prior to Commissioning after review by Company.
X W
f) If the pump is to be used for flushing, install temporary packing if permanent packing or mechanical seal is not suitable for flushing.
X W
g) Install temporary strainers in suction piping. X W
h) Re-install permanent packing if permanent packing or mechanical seal on any pump used for flushing, if required.
X W/I
i) Make final cold alignment on any pump used for flushing (items f and h).
X W/R
j) Check and run-in pumps, maintain them after Mechanical Completion; make final alignment check, and do any required dowelling of the pumps and drivers.
X W
k) When necessary, clean pump strainers and remove temporary suction strainers after pumps have been in operation for a reasonable period.
X W
l) Check the general compatibility of the pumps with respect to any cavitation problem, discharge head, undue or excessive vibrations, excessive noise etc. which may hint at the abnormal operation of the pump.
X X I
m) Obtain the assistance of the Approved Manufacturers if required.
X X
WARA PRESSURE MAINTENANCE PROJECT
COMMISSIONING PROCEDURE
Class 1 Doc. No. : 11050146-CM-PRO-000-5017 Rev.A Page 58of 63
[텍스트 입력]
Construction
Phase
Pre-
commissioning Phase
Commissioning
Phase
Ctr Cy Ctr Cy Ctr Cy
17.0 COMPRESSORS
a) Ensure suction and discharge piping has been correctly installed according to Approved Manufacturer requirements or recommendations.
X W/I
b) Check that the cold alignment and grouting have been carried out satisfactorily and that documentary evidence of this is to hand.
X W/I
c) Chemically clean any completed lube and seal oil system, when specified. Disposal of wastes and cleaning media in accordance with the Company’s instructions.
X W/A
d) Charge the lube oil, control oil, and oil cooling systems with the flushing oil and circulate for cleaning purposes. Dispose of any flushing oil on accordance with the Company’s instructions.
X W/A
e) Charge the lube oil, control oil, and oil cooling systems with the operating oil recommended by the Approved Manufacturer in accordance with the Company’s specifications.
X W X W
f) Operate the autochange over of the oil coolers and
oil filters.
X X W
g) Operate equipment and carry out vibration, trip,
governor and safety device checks and any operating tests and adjustments, as required.
X W
h) Obtain the assistance of Approved Manufacturer, if required.
X X X
i) Perform all the tests as specified in the relevant data sheets and specifications.
X W/I X W/I X W/I
17.1 SPECIAL TEST FOR RECIPROCATING COMPRESSORS
a) Check fit and clearance of bearings, connecting rod, crankshaft and cross-head slides.
X W/I
b) Check run-out of piston rod and cross-head slide. X W/I
c) Check valve lift. X W/I
d) Check rod seal assembly. X W/I
e) Check that vent lines from seals and distance housings are free from obstruction and routed to safe location.
X W/I
f) Obtain the assistance of Approved Manufacturer to perform the specified test.
X X X
WARA PRESSURE MAINTENANCE PROJECT
COMMISSIONING PROCEDURE
Class 1 Doc. No. : 11050146-CM-PRO-000-5017 Rev.A Page 59of 63
[텍스트 입력]
17.0 COMPRESSORS (Contd.)
Construction
Phase
Pre-
commissioning Phase
Commissioning
Phase
Ctr Cy Ctr Cy Ctr Cy
17.2 SPECIAL TESTS FOR SCREW
COMPRESSORS
a) Check carefully compatibility of operating oil
recommended by Approved Manufacturer with process product in order to avoid problems during run-in.
X R
b) Obtain the assistance of Approved Manufacturer and perform all the tests as per the relevant specifications and data sheets.
X X X
18.0 GAS TURBINES
a) Check physically for any damage, defects on the surface, mountings and leakage etc.
X
b) Remove all rust preventatives, oils, paints and blinds used to protect the equipment during shipment and construction period whenever these protective materials will be detrimental to operation.
X W
c) Check that the cold alignment and grouting have been carried out satisfactorily with the documentary evidence. As the gas turbine is to drive compressor and/or pump, the suction and discharge should have been aligned and freed of stresses.
X W/I
d) Inspect the combustion chamber/plenum chamber and the enclosure.
X W/I
e) Check and prepare starting system in accordance with the Approved Manufacturer’s recommendations.
X W/I
f) Check and prepare burner system in accordance with the Approved Manufacturer’s recommendation.
X W/I
g) Prepare and charge lube oil and control oil systems in accordance with the Approved Manufacturer’s recommendations. (Operating oil shall be in accordance with Company’s Specifications.) Check the control and the oil system.
X W/R
h) Check and conduct all blowing operations on gas
lines.
X W
i) Operate equipment and carry out vibration, trip, governor and safety checks and any operating tests and adjustments, as required, in accordance with Approved Manufacturer’s instructions.
X W/R
WARA PRESSURE MAINTENANCE PROJECT
COMMISSIONING PROCEDURE
Class 1 Doc. No. : 11050146-CM-PRO-000-5017 Rev.A Page 60of 63
[텍스트 입력]
18.0 GAS TURBINES (Contd.) Construction
Phase
Pre-
commissioning Phase
Commissioning
Phase
Ctr Cy Ctr Cy Ctr Cy
j) Check and run turbines, maintain them after Mechanical Completion in accordance with Approved Manufacturer’s operating manual instructions.
X W X I
k) Obtain the assistance of Approved Manufacturer and perform all the tests and checks as per data sheets and specifications
X X X I
19.0 HEATERS
a) Check physically for any damage, leakage etc. X
b) Remove all temporary support, bracing or other foreign objects that were installed in heaters to prevent damage during shipping, storage and erection, and repair any damage sustained.
X W
c) Inspect the heater for completeness and correctness of installation and perform all non- operating pre-firing check in accordance with the Approved Manufacturer’s instructions.
X W/I
d) Blow fuel lines, check them for cleanliness, and connect burner piping. Internally inspect oil bath heaters to ensure all dirt and debris is removed.
X W/R
e) Obtain and charge liquid heat transfer media, if required in accordance with the Approved Manufacturer’s instructions.
X W
f) Precommission and Commission auxiliaries as
detailed elsewhere under the appropriate equipment type.
X W X I
g) Conduct refractory dry out with necessary adjustments to firing to establish temperature profiles in accordance with refractory Approved Manufacturer’s instructions.
X W/R
h) Conduct all operating tests and obtain the certification, if required, in accordance with the Approved Manufacturer’s instructions.
X W/I
i) Obtain the assistance of Manufacturer, if required.
X X X
20.0 MISCELLANEOUS
a) Install all miscellaneous mechanical equipment such as cranes, hoists, etc., carry out all the required site tests including based test and provide test certificate from testing and certifying authority (e.g. Lloyds, Bureau Veritas, ABS etc.).
X W
WARA PRESSURE MAINTENANCE PROJECT
COMMISSIONING PROCEDURE
Class 1 Doc. No. : 11050146-CM-PRO-000-5017 Rev.A Page 61of 63
[텍스트 입력]
20.0 MISCELLANEOUS (Contd.) Construction
Phase
Pre-
commissioning Phase
Commissioning
Phase
Ctr Cy Ctr Cy Ctr Cy
b) Install, lubricate as required, perform mechanical
check and adjust all equipment prior to turning over to the Company.
X W/I
c) Provide and install guards, barriers warning signs
and other safety devices in accordance with Contract Safety Requirements.
X I
d) Provide noise reduction devices or noise `walls’ if required to comply with specifications.
X I X I
21.0 CHEMICALS
a) Store and protect chemicals, desiccants, oils, refrigerants and other fluids/gases to be filled or charged into the Work, in a sheltered area.
X
b) All fluids/gases per item (a) to be labelled, and located in a safe and proper area outside the Work area until ready for installation.
X
c) Test samples of transformer insulating oils, and any other fluids deemed necessary by Equipment Manufacturer’s to confirm that such meets with the requirements and/or Company standards.
X W
d) Replace and/or refill fluids with permanent charge where required, this includes, but not limited to, halon (after halon discharge test) nitrogen (for inerting and/or tightness test).
X
e) Allocate proper sheltered areas in the Gathering Centre for storage of chemicals, desiccants and lubricants, etc.
X A/R
22.0 PACKAGE UNITS
a) Check physically for any damage, defects on the
surface, mountings and leakage etc.
X
b) Remove all rust preventatives, oils, paints and blinds used to protect the equipment during shipment and construction period whenever these protective materials will be detrimental to operation.
X W
c) Inspect package for completeness and correctness of installation and perform all non-operating checks in accordance with Approved Manufacturer’s instructions.
X W/I
d) Obtain and charge liquid, chemical as required. X W
e) Pre-commission and Commission auxiliaries as detailed elsewhere under the appropriate equipment type.
X W X W/I
WARA PRESSURE MAINTENANCE PROJECT
COMMISSIONING PROCEDURE
Class 1 Doc. No. : 11050146-CM-PRO-000-5017 Rev.A Page 62of 63
[텍스트 입력]
22.0 PACKAGE UNITS (Contd.)
Construction
Phase
Pre-
commissioning Phase
Commissioning
Phase
Ctr Cy Ctr Cy Ctr Cy
f) Pre-commission and Commission piping, electrical,
instrumentation as detailed elsewhere under the relevant section.
X W X W/I
g) Conduct initial start, making the associated checks
and adjustments in accordance with Approved Manufacturer’s instructions.
X W/I
h) Conduct all operating test and obtain the certification,
if required, in accordance with Approved Manufacturer’s instructions.
X W
i) Obtain the assistance of Approved Manufacturer, if
required.
X X X