11 November2014
RAILWAY SAFETY REGULATOR2014/15 FINANCIAL YEAR QUARTER 1 & QUARTER 2 PROGRESS
1
OVERVIEW
2
• INTRODUCTION
• BACKGROUND
• 2014/15 QUARTER 1 & 2 PERFORMANCE
• COMPARATIVE ANALYSIS OF QUARTERLY PERFORMANCE
INTRODUCTION
3
Strategy is an ongoing process of enriching ideas,
improving concepts and initiatives, making the
execution happen and getting RESULTS
INTRODUCTION: STRATEGIC OVERVIEW
4
5
INTRODUCTION:RSR’S NEW Strategic DIRECTION
Tim
e
Impact & Change
Impactlandscape
Collaborationlandscape
Operationallandscape
PAST
PRESENT
FUTURE
BACKGROUND
2014/15 STRATEGIC APPROACH
• Premised on Results/Outcomes-Based Management • Emphasises outcomes and impacts
• Makes explicit provision for organisational learning and accountability
• Differentiates between Strategic, Tactical and Operational Targets
• More Outwards Focussed i.e. Attention to External Environment
• Greater emphasis on Collaboration and Intra-Departmental Work
• Proactive
• Provides the basic Architecture for Good Governance 6
BACKGROUND
2014/15 STRATEGIC approach Cont.
• Supports the Policy Framework for the Government-Wide Monitoring
and Evaluation System (GWMES)
• Aims to establish a political and administrative culture characterised by
accountability, continual improvement, efficiency, a concern for ethics, and
avoidance of conflicts of interest by facilitating a clear sequence of events
based on critical reflection and managerial action in response to an analysis of
the relationships between the resource inputs, service delivery outputs, and
their associated outcomes and impacts.7
BACKGROUND
2015/16 – 2018/19 FINANCIAL YEARS:
• Focus on Strategy Execution
• Higher level focus on external impacts will require focus on critical
issues :• Value creation – contribute to the SUSTAINABLE growth of rail as a safe,
reliable, cost-effective and more energy efficient mode of transportation• Stakeholder engagements• Understanding the Risk Landscape• Practice and Demonstrate Integrated thinking• Upwards matrix – transformation journey
8
2014/15 QUARTER 1 & 2 PERFORMANCE
9
STRATEGIC OUTCOME 1: RISKS IN THE RAILWAY LANDSCAPE HAVE BEEN MITIGATED
Outcome Description: Mitigate risks of occurrences by designing and establishing an appropriate regulatory approach to oversee, monitor and enforce railway safety within the regulatory framework provided by the NRSR Act, policies, procedures, standards and other operating guidelines
Strategic Objective 1.1: Effective compliance with legislation
Objective Statement: Conduct sufficient and effective audits and investigations to ensure that operators comply with legislation as one of the key enablers to mitigate risks in the railway landscape
Strategic Key Performance Indicator (KPI)
Baseline as at 2012/13
2014 Annual Target
Quarter 1 Target Actual Performance
Q2 Target Actual Performance
Number of Inspections conducted
Number of Inspections conducted
120 Inspections conducted
25 Inspections conducted
24 Inspections conducted
30 Inspections conducted
33 Inspections conducted
Number of Audits conducted
Number of Audits undertaken
90 Audits conducted
20 Audits conducted
21 Audits conducted
25 Audits conducted
25 Audits conducted
Number of Follow-up Investigations conducted
Number of Audits undertaken
28 Follow-up Investigations conducted
7 Follow-up Investigations conducted
7 Follow –up Investigations conducted
7 Follow-up Investigations conducted
9 Follow-up Investigations conducted
Investigations conducted
Number of Investigations undertaken
32 Investigations conducted
8 Investigations conducted
4 Investigations conducted
8 Investigations conducted
12 Investigations conducted
2014/15 QUARTER 1 & 2 PERFORMANCE
10
STRATEGIC OUTCOME 1: RISKS IN THE RAILWAY LANDSCAPE HAVE BEEN MITIGATED
Outcome Description: Mitigate risks of occurrences by designing and establishing an appropriate regulatory approach to oversee, monitor and enforce railway safety within the regulatory framework provided by the NRSR Act, policies, procedures, standards and other operating guidelines
Strategic Objective 1.2: Ensure continuous improvements in railway safety through innovation
Objective Statement: Research and implement innovative techniques and methods to ensure continuous improvements in railway safety
Strategic Key Performance Indicator (KPI)
Baseline as at 2012/13
2014 Annual Target
Quarter 1 Target Actual Performance
Q2 Target Actual Performance
Strategy to regulate the maintainer developed
Percentage implementation of the strategy to regulate the maintainer
Strategy to regulate the supplier of safety critical systems and services to the industry developed
Literature review completed
Target Achieved First draft of the strategy to regulate the maintainer developed
Target Achieved
Percentage of Safety Critical Grades certified
New Indicator Project implementation plan developed
Project Charter developed and approved
Target Achieved Implementation framework developed
Target Achieved
2014/15 QUARTER 1 & 2 PERFORMANCE
11
STRATEGIC OUTCOME 1: RISKS IN THE RAILWAY LANDSCAPE HAVE BEEN MITIGATED
Outcome Description: Mitigate risks of occurrences by designing and establishing an appropriate regulatory approach to oversee, monitor and enforce railway safety within the regulatory framework provided by the NRSR Act, policies, procedures, standards and other operating guidelines
Strategic Objective 1.3: Strengthen the regulatory framework and approach
Objective Statement: Develop regulatory tools and commands to direct enforcement, contribute towards the development of world-class safety regulatory legislation
Strategic Key Performance Indicator (KPI)
Baseline as at 2012/13
2014 Annual Target
Quarter 1 Target
Actual Performance
Q2 Target Actual Performance
Impact of Regulatory Framework and Tools assessed
New Indicator Regulatory Impact Assessment conducted
- - First Draft report completed
Target not Achieved
The RSR is looking to achieve this target.
2014/15 QUARTER 1 & 2 PERFORMANCE
12
STRATEGIC OUTCOME 1: RISKS IN THE RAILWAY LANDSCAPE HAVE BEEN MITIGATED
Outcome Description: Mitigate risks of occurrences by designing and establishing an appropriate regulatory approach to oversee, monitor and enforce railway safety within the regulatory framework provided by the NRSR Act, policies, procedures, standards and other operating guidelines
Strategic Objective 1.3: Strengthen the regulatory framework and approach
Objective Statement: Develop regulatory tools and commands to direct enforcement, contribute towards the development of world-class safety regulatory legislation
Strategic Key Performance Indicator (KPI)
Baseline as at 2012/13
2014 Annual Target
Quarter 1 Target
Actual Performance
Q2 Target Actual Performance
Number of Regulations drafted
No. of Regulations developed and/or amended
4 Regulations drafted
- - - -
2014/15 QUARTER 1 & 2 PERFORMANCE
13
STRATEGIC OUTCOME 2: RAILWAY SAFETY EFFECTIVELY PROMOTED
Outcome Description: Mitigate risks of occurrences by designing and establishing an appropriate regulatory approach to oversee, monitor and enforce railway safety within the regulatory framework provided by the NRSR Act, policies, procedures, standards and other operating guidelines
Strategic Objective 2.1: Cultivate and instil a culture of safety in the stakeholder environment
Objective Statement: Drive education initiatives and effective communication towards improved compliance by operators to contribute to a culture of safety
Strategic Key Performance Indicator (KPI)
Baseline as at 2012/13
2014 Annual Target Quarter 1 Target Actual Performance
Q2 Target Actual Performance
Education Awareness Campaigns conducted
New Indicator 2 Education Awareness Campaigns conducted on a specified safety topic
- - 1 Operator workshop conducted
Target not Achieved
Due to other operational activities the workshops were postponed to Q3
Number of Stakeholder Engagements conducted
New Indicator 4 Stakeholder Engagement sessions conducted
1 Stakeholder Engagement sessions conducted
Target Achieved 1 Stakeholder Engagement sessions conducted
Target Achieved
Profiling campaigns conducted
New Indicator 12 Profiling campaigns conducted
2 Profiling campaigns conducted
Target Achieved 5 Profiling campaigns conducted
Target Achieved
1 Railway Safety Conference planned and hosted
Railway Safety Conference concept paper approved
Target Achieved Progress Report Target Achieved
2014/15 QUARTER 1 & 2 PERFORMANCE
14
STRATEGIC OUTCOME 2: RAILWAY SAFETY EFFECTIVELY PROMOTEDOutcome Description: Mitigate risks of occurrences by designing and establishing an appropriate regulatory approach to oversee, monitor and enforce railway safety within the regulatory framework provided by the NRSR Act, policies, procedures, standards and other operating guidelines
Strategic Objective 2.2: Inform stakeholders on State of Safety in rail
Objective Statement: Use the State of Safety Report to increase public knowledge and guide stakeholders of the issues and challenges in the rail environment to increase safety awareness
Strategic Key Performance Indicator (KPI)
Baseline as at 2012/13
2014 Annual Target Quarter 1 Target Actual Performance
Q2 Target Actual Performance
Report to RSA nation on the State of Safety
State of Safety Report developed
State of Safety Report disseminated
- - State of Safety report approved by the Board
Target Achieved
Number of External Technical Safety workshops conducted
New Indicator 10 External Technical Safety workshops conducted
2 External Technical Safety workshops conducted
Target Achieved 3 External Technical Safety workshops conducted
Target Achieved
2014/15 QUARTER 1 & 2 PERFORMANCE
15
STRATEGIC OUTCOME 3: NEW INVESTMENTS IN RAIL INFRASTRUCTURE AND TECHNOLOGIES IMPACTS POSITIVELY ON RAILWAY SAFETY
Outcome Description: Ensure investments in rail infrastructure and technologies address safety improvements
Strategic Objective 3.1: A process for RSR safety assurance of rail investment and technology changes
Objective Statement: Guide industry investment and technology changes to ensure safety compliance and improvements
Strategic Key Performance Indicator (KPI)
Baseline as at 2012/13
2014 Annual Target Quarter 1 Target Actual Performance
Q2 Target Actual Performance
Technology Reviews conducted
% of Technology Reviews undertaken
80 % of the total Technology Reviews received for the financial year conducted
80 % of the total Technology Reviews received in Quarter 1 conducted
Target Achieved 80 % of the total Technology Reviews received in Quarter 2 conducted
Target Achieved
28 of 35 Reviews received conducted
2014/15 QUARTER 1 & 2 PERFORMANCE
16
STRATEGIC OUTCOME 4: SUSTAINABLE INSTITUTIONAL GROWTH AND DEVELOPMENT
Outcome Description: Enrich organisational governance processes and procedures to promote integrated thinking and collaboration and to enable the sustainable growth and development of the RSR
Strategic Objective 4.1: Assure corporate sustainability and growth
Objective Statement: Develop corporate institutional capabilities to ensure sustainability and to effectively manage organisational growth and development
Strategic Key Performance Indicator (KPI)
Baseline as at 2012/13
2014 Annual Target
Quarter 1 Target Actual Performance Q2 Target Actual Performance
Number of Initiatives to assist SADC countries
Number of Initiatives undertaken to assist SADC countries
2 SADC Initiatives completed
Infrastructure and rolling stock audits in Namibia
Target not AchievedA number of initiatives are scheduled to take place in Namibia that requires a set amount of days to be completed. RSR did not secure sufficient time to conclude these audits due to conflict of schedules between RSR and the Operator
- -
Communication Strategy implemented
New Indicator 1 Customer Care Call Centre established
Progress report on the process of establishing the call centre completed
Target Achieved Progress report on the process of establishing the call centre completed
Target Achieved
2014/15 QUARTER 1 & 2 PERFORMANCE
17
STRATEGIC OUTCOME 4: SUSTAINABLE INSTITUTIONAL GROWTH AND DEVELOPMENT
Outcome Description: Enrich organisational governance processes and procedures to promote integrated thinking and collaboration and to enable the sustainable growth and development of the RSR
Strategic Objective 4.1: Assure corporate sustainability and growth
Objective Statement: Develop corporate institutional capabilities to ensure sustainability and to effectively manage organisational growth and development
Strategic Key Performance Indicator (KPI)
Baseline as at 2012/13
2014 Annual Target
Quarter 1 Target Actual Performance Q2 Target Actual Performance
Communication Strategy implemented
New Indicator 4 Branding Initiatives conducted
Draft report on the process of Branding the RSR developed
Target not Achieved
The process of branding the RSR is being addressed in the Communication strategy that is still in the process of being developed
4 Branding Initiatives conducted
Target Achieved
Co-operative Agreements between RSR and external parties implemented
Number of Agreements renewed, concluded and implemented
11 Agreements implemented
3 Agreements implemented
Target Achieved 3 Agreements implemented
Target Achieved
2014/15 QUARTER 1 & 2 PERFORMANCE
18
STRATEGIC OUTCOME 4: SUSTAINABLE INSTITUTIONAL GROWTH AND DEVELOPMENT
Outcome Description: Enrich organisational governance processes and procedures to promote integrated thinking and collaboration and to enable the sustainable growth and development of the RSR
Strategic Objective 4.2: Guarantee effective resource management
Objective Statement: Enable effective and efficient management of organisational resources to support the sustained growth and development of the RSR
Strategic Key Performance Indicator (KPI)
Baseline as at 2012/13
2014 Annual Target
Quarter 1 Target
Actual Performance Q2 Target Actual Performance
Percentage of Revenue effectively collected
New Indicator 95 % of Revenue generated from exchange transactions collected
10 % of Revenue generated from exchange transactions collected
Target not Achieved
The Gazette containing the new Permit Fees schedule was issued in May resulting in RSR having to grant extensions to permits expiring in Q1
35 % of Revenue generated from exchange transactions collected
Target Achieved
NIMS implemented
% implementation of the ICT Strategy
100 % NIMS Phase 2 implemented
Rolled out Permit management module to the production environment
Target Achieved Implemented the Occurrences Management module
Target not Achieved
The implementation of the module was delayed due to the late signoff of the functional specification.
2014/15 QUARTER 1 & 2 PERFORMANCE
19
STRATEGIC OUTCOME 4: SUSTAINABLE INSTITUTIONAL GROWTH AND DEVELOPMENT
Outcome Description: Enrich organisational governance processes and procedures to promote integrated thinking and collaboration and to enable the sustainable growth and development of the RSR
Strategic Objective 4.2: Guarantee effective resource management
Objective Statement: Enable effective and efficient management of organisational resources to support the sustained growth and development of the RSR
Strategic Key Performance Indicator (KPI)
Baseline as at 2012/13
2014 Annual Target
Quarter 1 Target Actual Performance Q2 Target Actual Performance
Procurement from Black Owned Enterprises
% implementation of the BBBEE Strategy
60 % of new procurements from BBBEE Enterprises
60 % of new procurements from BBBEE Enterprises
Target not Achieved
The target of 60 % was not aligned to the RSR procurement demand
60 % of new procurements from BBBEE Enterprises
Target not AchievedRSR will endeavour to achieve 60 % for the financial year.
QUARTERLY PERFORMANCE: COMPARATIVE ANALYSIS