  • 188 PLOT PLAN

    INDEX

    GUIDELINES FOR PREPARING PLOT PLAN 189 TYPES OF FACILITIES 189 PLOT PLAN DRAWING 192

  • 189 PLOT PLAN

    PLOT PLAN

    It consists of all the facilities required for a plant or a complex or industry. It also consists of the future

    facilities required for the complex, plant or industry.

    GUIDELINES FOR PREPARING PLOT PLAN:

    1. Prepare the list of all the facilities require for the plant

    2. The list must also include the future facilities required for the plant

    3. The type of future expansion should be clear before the start of the plot plan

    4. The list must be approved by the client, this is a must before the start of the plot plan

    TYPES OF FACILITIES:

    1. PLANT FACILITIES

    2. NON PLANT FACILITIES

    1. PLANT FACILITIES:

    Process unit/units

    Utility units: boiler unit, compressor unit, C unit, HAVC unit, hot water unit(

    compressor, filter , dryer), chilled water unit, chilled brine unit, ETP/STP unit

    Efficient treatment plant/sewage treatment plant, fire fighting unit, power facilities,

    potable water unit, demineralised water unit etc.

    Power facilities:

    1) .

    Captive power plant( plant producing power for own use)

    DG( diesel generators) sets

    Turbines( seat gas,CC)

    Fuel storage( coal, gas)

    Boiler

    2) Government supply:

  • 190 PLOT PLAN

    Fire fighting system:

    Fire/raw water storage

    Pump house

    Fire officer accommodation

    Fire tenders parking area( engine)

    Fire water network

    Fire hydrant

    Foam storage

    Infrastructure:

    Roads : each unit should have minimum 3 surrounding roads

    Secondary road: (10/4 m)

    Railway lines

    Sea transport

    Harbor

    Jetty

    Drainage system

    Chemical drain(CBD)closed blow down

    Oil water drain

    Domestic drain

    Pipe rack

  • 191 PLOT PLAN

    Sleepers: for carrying heavy pipes- concrete structure above( 800 mm from ground)

    Material handling facility:

    - Conveyer belts

    Flare

    Cold vent

    Loading/unloading system

    Storage: (raw m/L, finished product, intermediate product)

    Tank farm

    Liquids

    Compressed gases

    Warehouse:

    Solid storage

  • 192 PLOT PLAN

    2. NON PLANT FACILITIES:

    Admin building( as per client architect)

    Canteen ( 1st shift + general shift)

    Parking ( 1st shift + general shift)

    Security

    Prayer area

    Recreation area

    Health care ( as per govt rules)

    Workers colony

    R&D center

    Convocation/convection/assembly area

    Guest house

    Green belt( it should be about 30% of the plot area and should be surrounding the plant

    as per govt rules)

    CIVIL INFORMATION REQUIRED:

    1. For control levels( plot surveying)

    2. Soil data nature of the soil, soil load bearing capacity( 8 to 10 metric tons/ 8-10 MT/2 )

    3. Accessibility to the plant( roads , railway line, sea port availability)

    ELECTRICAL INFORMATION REQUIRED:

    1. Availability of the electricity in the area

    2. Accessibility cost of electricity

    PLOT PLAN DRAWING:

    Drawing is carried out in two stages:

    STAGE 1 DRAWING:

    It consists of the following details:

    i) Land map with surrounding details such as roads, railway lines, water lines, electricity lines

    etc.

    ii) True north, plant north and prevailing wind direction

    iii) Green belt surrounding the plot

    iv) Area statement ( plot area, green belt area, plat area)

    v) Hatch portion of the land showing the proposed plant area in the plot

  • 193 PLOT PLAN

  • 194 PLOT PLAN

    STAGE 2 DRAWING:

    It consists of the following:

    i) Plot plan along with the key plan shown at a small scale located at the right hand side of the

    drawing

    ii) The proposed plant area is shown in more detail in this drawing drawn to scale with the help

    of grid lines.

  • 195 PLOT PLAN

    NOTES:

    I. The total area of the plant facilities is double to accommodate the infrastructure of the plant

    such as roads

    II. The process unit shall be located at the highest elevation of the area

    III. ETP plant shall be located at the lowest level of the plot to have gravity flow ( free floor)

    IV. The flare shall be located on the upstream side of the process unit w.r.t wind direction

    V. Cooling tower shall be located on the downstream side of the area w.r.t wind direction

    VI. The plant facility shall be located near the m/L entry gate and the non plant facility shall be

    located near the main entry gate

    VII. Pipe rack location should be based on connectivity of it to different units to supply pipe b/w

    them.

  • 196 PLOT PLAN