108 delancey street
-
Upload
davidmulrich -
Category
Documents
-
view
778 -
download
2
description
Transcript of 108 delancey street
108 Delancey StreetLower Eastside Manhattan
April 4, 1984
By: David M. Ulrich and Keith MalmbergDrawings by David M. Ulrich in AutoCAD
2010
Purpose : To retrofit a concrete masonry unit (CMU) and wood floor construction building with structural steel and concrete slab on metal decking
DMAConsultants and Construction Managers
1st Floor
2nd Floor
3rd Floor
4th Floor
5th Floor
Cross section of existing building
• Five floors of wood flooring (beams/joists)
Building 1 Building 2
• Two buildings share central load-bearing wall
• Building 1 and Building 2 interiors are completely separate
• Current system utilizes continuous CMU stem wall footings
1st Floor
2nd Floor
3rd Floor
4th Floor
5th Floor
Proposed Retrofit Agenda
• Remove 2nd Floor and Central CMU bearing wall
Building 1 Building 2
• Replace 1st floor with structural steel and slab-on-metal decking
• Retrofit continuous stem wall footings into three main spread footings
• Utilize wide-flange columns, beams, and girders in lieu of structural masonry
• Removal of 2nd floor resulting in large space with vaulted ceiling
Cross section of proposed retrofit
2nd Floor
• Installation of three spread footings into existing bearing wall (Epoxy Installation)
• Support the multi-wythe CMU bearing wall from 3rd Floor to Roof
Base Plate with(4) 3/4" Threaded rods
W10x49 ColumnW12x26 Beam
3 1/2" conc. slabon 22ga. metal deck
W12x50 Girder
Steel retrofit design
Here are some basic components of the proposed retrofit design
W 12 x 50What Does This Mean?
12” Flange-to-Flange dimension
50 lbs per linear foot
W Shape
13" UNO 10" min embed
Footing to steel column connection
Concrete Slab-on-Grade
Wide Flange column
Spread Footing
Non-shrink groutBase Plate + Threaded Rods
Footing Installation
Subgrade assessment
Form Installation
Undisturbed Native Soils?No
Firm and Unyielding Soils?
Use a flat bucket for excavation
Replace soils removed
Footing Dimensions
Location
No
Over excavate to dense soils
Adequate form bracing to support lateral load of concrete
Ensure column will load footing as designed
1
2
Spread Footing Concrete Placement
1
2
3
Secure rebar prior to concrete placement (3” from earth per ACI)
Place anchor bolts correctly in relation to the rebar mat per plans
Mechanically consolidate concrete with a vibrator
4 Leave adequate clearance below base plate template for non-shrink grout
3 Inches
Footing ‘spreads’ load from the footing bottom to earth beneath
Notice the column assemblyIn the center of the footing
Correct Spread Footing Load Path
Spread Footing Loading
OK NOT OK NOT OK NOT OK
1 2 3 4
GOODBAD
Eccentric LoadingStandard Central Loading
To Remove Floor #1 and #2 we will need Shoring.
• Floors need to be shored prior to removal of load-bearing wall sections
• Shoring can be rented until concrete has reached full strength and is adequate for support
• Falsework of this magnitude is not to be ‘site-designed’ by a contractor.
• Consult with an engineer for shoring design
Adjustable screw with baseplate
108 Delancey Street
12" CMU Block Wall
8" CMU Block Wall
Spread Footings
104 Delancey St 106 Delancey St
5 S
torie
s A
bove
Concrete stem wall foundation and Concrete Masonry Unit walls (CMU blocks)
Three critical spread footings along shared central wall
Multi-wythe CMU walls of different block width
1
2
3
Floor Plan
A
B
C
A vague list of what went wrong
• Lack of field supervision and inspection oversight• Lack of step-by-step construction sequence resulting in lateral instability• No shop drawings
• Spread footings were installed incorrectly• Spread footings were installed below 50% of design strength
• Spread footings were eccentrically loaded
• Shoring schedule out of sequence• Removal of 3rd floor and pouring one side created a twisting force
• Lack of lateral support coupled with eccentrically loaded footings created an inevitable collapse
What went wrong with the footings?
• Footing dimensions were installed wrong (contractor at fault)
• Footing were eccentrically loaded (contractor at fault)
Actual footing installationA
B C
• Some of the footings were less than 40% design size
Did the contractor have structural plans?
Footing dimensionsAS DESIGNED BY ENGINEER
Footing Length Width Ft2 % Design
A 8'6 5'6 47 ft2
44%A 4'8 4'7 21 ft2
B 5'6 7'0 39 ft2
51%B 5'9 3'6 20 ft2
C 5'6 7'0 39 ft2
36%C 4'2 3'4 14 ft2
Designed Footing DimensionsInstalled Footing Dimensions
44%51% 36%
What went wrong with the shoring?
1. The contractor removed both sides the 3rd floor
2. The contractor only poured back one side of floor 3
3. Floor 3 had no lateral stability when it began to twist
THE END