10/21/2015 Badan Tenaga Nuklir Nasional 1
-
Upload
truongdang -
Category
Documents
-
view
224 -
download
1
Transcript of 10/21/2015 Badan Tenaga Nuklir Nasional 1
10/21/2015 Badan Tenaga Nuklir Nasional 1
Dynamics of Policy and Program Activity NPP in Indonesia
10/21/2015 Badan Tenaga Nuklir Nasional 2
1970 1980 1990
1996
2000
Act 10/1997
Muria FS
1986
Chernobyl NPP
Accident
Economic Crisis
Act 17/2007, GR No 5/2006
BATAN had authority to build a commercial NPP BATAN has no authority to build a commercial NPP
Change of Government Regime and
Democratization Process
DG IAEA to Indonesia
BATAN has authority to build a non commercial NPP
2010
BANGKA Pre-FS
Banten Site Study
Fukushima NPP
Accident
BANGKA FS
Development of Nuclear Research Facilities
Starting for SMR Intrroduction
Starting for Non Commercial Power
Reactor Intrroduction
Background
10/21/2015 Badan Tenaga Nuklir Nasional 3
The planning of the development of NCPR is a result of long communication between BATAN-National Development Planning
Agency (BAPPENAS) and Ministry of Financing.
It had been several trilateral meeting
Some meeting have been conducted that involving main stakeholders:
MoRT, MOEMR, PT PLN, PT Pertamina, ANTAM, BAPETEN
10/21/2015 Badan Tenaga Nuklir Nasional 4
BATAN Nuclear Complex (Existing)
Planning for I-EPR and NRE
Laboratory
10/21/2015 Badan Tenaga Nuklir Nasional 5
• Act No 17 Year 2007: National Long Term Development Planning
Mandate from the Act: During 3rd Mid Term Development Plan (RPJM) 2015-2019: starting nuclear energy utilization for electricity by considering strict safety factor.
• GR No.2 Year 2014 : Licensing of Nuclear Installation and Utilization of Nuclear Material
Article 5: (1) Construction, Operation, and Decommissioning of Non-Commercial Power Reactor or Non-Commercial Non-Power Reactor is implemented by BATAN
• President Regulation 2/2015: National Mid Term Development Planning 2015-2019 give mandate to for implementing small scale of NPP
• The result of public opinion polling, 72 % agree to NPP
Non-Commercial Experimental or Demonstration
Power Reactor (Act 10/1997 and Gov. Regulation No. 2 (2014)
Nuclear Power Development Plan
NON COMMERCIAL POWER REACTOR
10/21/2015 Badan Tenaga Nuklir Nasional 7
Test Reactor Demonstration
Reactor
Experimental Reactor
Prototype Reactor
NCPR
OBJECTIVES
GENERAL /MAIN OBJECTIVES OF THE PROJECT
o To demonstrate a mini/small NPP that can operate safely and produce electricity in
the certain duration (life time will be determined later: between 20 year-40 years).
o Experimental activities
SPECIAL OBJECTIVES
o Increasing mastery of a new generation of nuclear power plant technology
that is safe
o Improving and developing BATAN facilities for research and development of
new and renewable energy
o Improving the mastery of construction project management for nuclear power
plant and its support facilities
o Mastery of NPP operation
o R & D of energy sector to meet the mandate of Act 17 of 2007
o To be integrated research and development (R & D) activities in the field of
nuclear energy systems for co-generation, renewable energy,
o To support human resources development in accordance with the national
nuclear energy programs "
10/21/2015 Badan Tenaga Nuklir Nasional
8
BENEFIT • Long term: To Support the implementation of renewable energy as a
national energy mix
• Increasing the capacity of national industry in the fields of
manufacturing, civil construction and services in support of the nuclear industry in Indonesia.
• Enhancing public acceptance of nuclear technology, especially
nuclear power plants.
• NCPR will be developed into a master nuclear power plant in
Indonesia with a power per unit of between 50 to 300 MWe, and a
thermal applications by considering the quite large domestic market
(area of mineral resources, Islands of small-to-medium power grid)
• NCPR can be developed according to the unique conditions of
Indonesia as an archipelago
• NCPR can be developed with a mixture of fuel U-Th-Pu, where resource of Th in Indonesia is considerable.
10/21/2015 9
10/21/2015 Badan Tenaga Nuklir Nasional 10
Consideration for Technology Selection
• Able to generate electricity
• Flexibility for heat application in accordance with NRE Research Development.
• Reliable safety system o Inherent safety is very high
• Very low Probability of Evacuation Countermeasure in the severe accident postulated o it can be developed for a relatively dense population areas
• Flexibility for Nuclear Fuel Use (U, Th)
• EPC cost is still within the range of budget provided by the government or if not, then it needs to be an international consortium
10/21/2015 Badan Tenaga Nuklir Nasional 12
EPR BENEFIT (GENERAL)
Electricity
Heat Application
Process
R&D for HTGR
Technology
EPR will produce electricity for BATAN Puspiptek area
EPR
EPR will be used for research of heat application process at.
R & D related to HTGR Technology for development of design and construction of Indonesia HTGR.
Project Phase
10/21/2015 Badan Tenaga Nuklir Nasional 14
PROJECT PHASE OF NCPR
2014 2016 2015 2020/21
2022 2060
PHASE I
PHASE II PHASE III
PHASE IV
PHASE V
2025 2017
Phase I Pre-Project: 2014-2016
Phase II EPC Project (Engineering, Procurement, Construction / EPC)/
Turnkey Project (Engineering, Procurement, Construction / EPC): 2017-2020/21
Fase III Commissioning and operation of NCPR , Experiment Activities: 2020/21-2060
Phase IV Phase of development for integrated NRE research (co-generation) and heat application laboratory : 2022-2040
Phase V Deploy PLTN, commercialization based on EPR (2030-2060)
2013 2014 2015 2016 2017 2018 2019 2020 2021
Technology Selection
Pre-Project Team
Blueprint
PMO Establishment
OO Establishment
URD,DUR,
DID, Spec Tec
FS, Design Eng. SAR, EPC Bidding Doc
Bid ding
Pre-FS
SEP, SEMS
Site Licensing Process
Construction Licensing Process
Env. Licensing Process
Other Licensing
Operation Licensing Process
Commissioning Licensing Process
Doc for Const. Permit
G to G
Agreeement
Engineering, procurement, Construction, installation
Construction Management CM
Bidding
Site Dev.
Basic & Detail Engineering
Consortium
+ Sub-Con
Mech & Electr Procurement
Civil Work
Nucl. Fuel& Material
Installation
Training / OJT / HRD / Recruitment / Certification of Operators
Pre Project
Project Management
EPC Activities
Operation Activities
Licensing
HRD
Support from IAEA
Site Evaluation
15
OPERATION
MULTI YEAR PACKAGE CONTRACT
MULTI YEAR PACKAGE CONTRACT
10/21/2015 Badan Tenaga Nuklir Nasional 16
Tahun
2014 2015 2016 2017 2018 2019
Commissioning Lic. Process
Road Map Licensing Process
SITE EVALUATION SEP, SEMS
Site licensing Approval
Approval for
SEP&SEMS
Document Preparation for Construction Permit
Site Licensing Process
Construction Licensing Process
Constr Permit
Approval
Environmental Impact Assessment
Env. Licensing Process
Approval for TOR EIA
Licensing for Specific Build ing Construction and Principal Permit
IMB and Principal
Permit
Approval for EIAR, EMgP,
EMnP
2020 2021 2022
Operation Lic. Process
Constructiom and Installation Activities
10/21/2015 Badan Tenaga Nuklir Nasional 17
Tahun
2015 2016 2017 2018 2019
Basic Design OJT, Supervisory
HRD ROAD MAP
2020
Project Management, Procurement, Constr, Install, QA OJT, Supervisory
Site Development
OJT, Supervisory
ENGINEERING
OJT, Supervisory
Project
Management, QA
OJT, Supervisory
Operation, Commissioning and Maintenance OJT
Basic Training for NCPR BT NCPR BT NCPR BT NCPR
Specific Training for NCPR ST-NCPR ST-NCPR ST-NCPR ST-NCPR
Training for Operator Licensing
PROSPECT OF NCPR DEVELOPMENT
• Added Value of Natural Resources (mineral) – in line with Mineral and Coal Act/regulation
• Local economy development
• Regional competitiveness
• Acceleration of nuclear technology mastery
10/21/2015 Badan Tenaga Nuklir Nasional 18
• Electricity Production 50-300
MWe/unit
• Co-generation (NRE Development)
• Hdrogen Production and Coal
Liquifactiobn
• Steam reforming natural gas
• Hydrothermal Gasification of biomass
• Oil shell and Oil sand processing
• Petroleum Refining
• Ethanol Concentration
• Seawater desalination
• Smelter
• Utilization of Thorium as a nuclear fuel
Longer Term Strategies: Commercial Deployment
• Indonesia is unique country: archipelago, different
kind of capacity needed, unique resources of each
island
• For small island need generation plant with high
capacity factor (it mean when refueling it is just
need a short time)
10/21/2015 Badan Tenaga Nuklir Nasional 19
• Need collaboration with other stakeholder (main user) to deploy NCPR at the beginning phase of the project: PT PLN, ANTAM, PERTAMINA, Others
• NCPR will be as an NPP master in Indonesia and will be deployed in line with domestic market (if possible for international market)
• If there is already a certain reactor types in operation (already granted permission) the development of commercial nuclear power plants will be easier in terms of licensing
EPR-EXPERIMENTAL ACTIVITIES
Demonstration/experiment based on EPR • Experiment of zero power
• EPR Operation at full power
• Demonstration / Experiment for inherent safety
• Demonstration/Experiment for co-generation
• Demonstration/Experiment of Thorium Fuel Using Possibility
Development of Facilities for industrial supporting • Facilities for HTGR component test
• Facilities of benchmark for HTGR analysis software and design
• Facilities of coupling test of industrial application – co-generation
Training Center for HRD as industrial supporting of HTGR • Training Facilities and Certification for Professional Human Resource
• Experimental facilities and research for Universities.
Flow Diagram of I-EPR
10/21/2015 Badan Tenaga Nuklir Nasional 21
TRISO-Coated Particle Fuel
TRISO Fuel- a safety element key of HTGR:
• Some country has success for developing “TRISO” -coated particle fuel- with high quality and possibility to defect are very low
• Fuel is very robust without damage for the quality test under high radiation exposure and high temperature
• Fuel maintain / confine fission products with a very high level of safety
2
2
International Cooperation
10/21/2015 Badan Tenaga Nuklir Nasional 23
24
1. Site Evaluation for Site Permit (2014-2015) • Site Evaluation Program (SEP) and Management System of Site
Evaluation have been approved by BAPETEN on 25 February 2015 2. Pra Project Activities (2015)
• Contract with RENUKO Consortium: 24 April 2015 • Conceptual Design & Front End Engineering Design • Integrated FS (including Site Development Plan, Master
Plan/Tataletak, Cost Breakdown Structure/CBS, Work Breakdown Structure/WBS, Risk ANalysis)
• Design Information Questionnaire , Reactor Main Data, EPC Bidding document, PSAR.
3. Environmental Impact Assessment (2015) • TOR EIA have been approved by Ministry of Environment • EIA have been presented and still under evaluation
4. Cooperation and International Agreement for supporting the Project • China, Japan, Russia
5. Public Acceptance • It have been conducted intensive socialization in the community around
the project, employees of Puspiptek, as well local governments
25 Badan Tenaga Nuklir Nasional
ASPECT PROGRESS
1. Technologiy - Have been chosen using HTGR Technology, 10 MWth
2. Environmental Impact Assessment
- TOR of EIA have been approved by Ministry of Environment (24 November 2014)
- Document of Environmental Impact Assessment, Planning for Environmental Management and Environmental Monitoring is on progress
26 Badan Tenaga Nuklir Nasional
ASPEK PROGRESS
3. Cooperation and Legal
- Letter of Intents/Agreement with Japan and China for Reasearch and Development of HTGR
- it has been conducted several Workshop involving key stakeholder
- It has been prepared legal assessment for I-EPR
- Some workhop of HTGR assisted by IAEA
4. Public Acceptance - Socialization to public - Leader of Institution under Ministry
of Research, Technology and High Education coordination (BPPT, LIPI, LAPAN, BIG)
10/21/2015 Badan Tenaga Nuklir Nasional
BLUE PRINT OF I-EPR
SITE EVALUATION PROGRAM OF I-EPR
MANAGEMENT SYSTEM OF SITE
EVALUATION OF I-EPR
Document to Be Prepared and Submitted During Licensing Process
10/21/2015 Badan Tenaga Nuklir Nasional 28
SITE LICENSING
(2014-2015/16)
• DID, DUR • SEP •SEMS •SER
CONSTRUCTION Permit
(2015-2016/17) • Detail Engineering • DIQ • Operation Condition
Definition • SAR • Construction Program • Management System • Radiation Protection and
safety program • Safeguard System Doc • Physical Protection
Program Doc • Aging Management Doc • Decommissioning
Program
COMMISSIONING (2018-2021)
• Safety Analysis Report • Operation Condition
Definition • Commissioning Program • Maintenance Program • Radiation Protection and
safety Program • Safeguard System doc • Physical Protection
Program Doc • Management System Doc • Aging Management Prog. • Decommmissioning Prog • Emergency Preparedness
Prog • Environmental Permit
Implementation Report • Construction Activities
Result Report • As built drawing of
Reactor
OPERATION
(2020-2021) • SAR • Operation Condition
Definition • Radiation Protection
and safety Program • MaintenanceProgram • Safeguard System doc • Physical Protection
Program Doc • Management System
Doc • Deccommisioning
Prog • Emergency
Preparedness Prog • Environmental Permit
Implementation Report
General Specification • Reactor Power : 10 MW
• Type : HTGR
• Fuel : Triso
• Output : Electricity (3-4 MWe), Co-generation,
Available for Experimental Facilities stage-1
• Operation Mode: In line with the Experimental Needs (electricity, co-generation, inherent safety)
• Life time : 40 Years
• Local Participation : as much as possible
• Site Requirement : Should be comply safety Reg -> site characteristic
1. Seismic Hazard
2. Volcanic Hazard
3. Geotechnic and Fondation
4. Meteorology,
5. Hydrology
6. Human Induced Events
7. Dispersion (including Population
Distribution, Land Water Use, and
Emergency Planning)
ASPECT OF SITE EVALUATION BCR No 5 Site Evaluation
Geological Structure Survey
10/21/2015 Badan Tenaga Nuklir Nasional 31
Wilayah Dekat Radius 5-25 km
Wilayah Dekat Radius 5 km
Gravity Survey
10/21/2015 Badan Tenaga Nuklir Nasional 32
Trenching
10/21/2015 Badan Tenaga Nuklir Nasional 33
10/21/2015 34
Micro earthquake Monitoring
Magnetoteluric Measurement
10/21/2015 Badan Tenaga Nuklir Nasional 35
Geotechnical drilling
10/21/2015 Badan Tenaga Nuklir Nasional 36
106,656 mE106,657 mE106,658 mE106,659 mE 106,66 mE106,661 mE106,663 mE106,662 mE106,664 mE106,665 mE
0,20,20,20,20,20,20,20,20,20,20,20,20,20,20,20,20,20,20,20,20,20,20,20,20,20000000000000000000000000 0,10,10,10,10,10,10,10,10,10,10,10,10,10,10,10,10,10,10,10,10,10,10,10,10,1
kilometerskilometerskilometerskilometerskilometerskilometerskilometerskilometerskilometerskilometerskilometerskilometerskilometerskilometerskilometerskilometerskilometerskilometerskilometerskilometerskilometerskilometerskilometerskilometerskilometers
CH-2CH-2CH-2CH-2CH-2CH-2CH-2CH-2CH-2CH-2CH-2CH-2CH-2CH-2CH-2CH-2CH-2CH-2CH-2CH-2CH-2CH-2CH-2CH-2CH-2
DH-1DH-1DH-1DH-1DH-1DH-1DH-1DH-1DH-1DH-1DH-1DH-1DH-1DH-1DH-1DH-1DH-1DH-1DH-1DH-1DH-1DH-1DH-1DH-1DH-1
DH-2DH-2DH-2DH-2DH-2DH-2DH-2DH-2DH-2DH-2DH-2DH-2DH-2DH-2DH-2DH-2DH-2DH-2DH-2DH-2DH-2DH-2DH-2DH-2DH-2
DH-IDH-IDH-IDH-IDH-IDH-IDH-IDH-IDH-IDH-IDH-IDH-IDH-IDH-IDH-IDH-IDH-IDH-IDH-IDH-IDH-IDH-IDH-IDH-IDH-I
DH-3DH-3DH-3DH-3DH-3DH-3DH-3DH-3DH-3DH-3DH-3DH-3DH-3DH-3DH-3DH-3DH-3DH-3DH-3DH-3DH-3DH-3DH-3DH-3DH-3
DH-4DH-4DH-4DH-4DH-4DH-4DH-4DH-4DH-4DH-4DH-4DH-4DH-4DH-4DH-4DH-4DH-4DH-4DH-4DH-4DH-4DH-4DH-4DH-4DH-4 DH-10DH-10DH-10DH-10DH-10DH-10DH-10DH-10DH-10DH-10DH-10DH-10DH-10DH-10DH-10DH-10DH-10DH-10DH-10DH-10DH-10DH-10DH-10DH-10DH-10
DH-6DH-6DH-6DH-6DH-6DH-6DH-6DH-6DH-6DH-6DH-6DH-6DH-6DH-6DH-6DH-6DH-6DH-6DH-6DH-6DH-6DH-6DH-6DH-6DH-6
DH-14DH-14DH-14DH-14DH-14DH-14DH-14DH-14DH-14DH-14DH-14DH-14DH-14DH-14DH-14DH-14DH-14DH-14DH-14DH-14DH-14DH-14DH-14DH-14DH-14
DH-11DH-11DH-11DH-11DH-11DH-11DH-11DH-11DH-11DH-11DH-11DH-11DH-11DH-11DH-11DH-11DH-11DH-11DH-11DH-11DH-11DH-11DH-11DH-11DH-11 DH-12DH-12DH-12DH-12DH-12DH-12DH-12DH-12DH-12DH-12DH-12DH-12DH-12DH-12DH-12DH-12DH-12DH-12DH-12DH-12DH-12DH-12DH-12DH-12DH-12
DH-9DH-9DH-9DH-9DH-9DH-9DH-9DH-9DH-9DH-9DH-9DH-9DH-9DH-9DH-9DH-9DH-9DH-9DH-9DH-9DH-9DH-9DH-9DH-9DH-9DH-8DH-8DH-8DH-8DH-8DH-8DH-8DH-8DH-8DH-8DH-8DH-8DH-8DH-8DH-8DH-8DH-8DH-8DH-8DH-8DH-8DH-8DH-8DH-8DH-8DH-7DH-7DH-7DH-7DH-7DH-7DH-7DH-7DH-7DH-7DH-7DH-7DH-7DH-7DH-7DH-7DH-7DH-7DH-7DH-7DH-7DH-7DH-7DH-7DH-7
DH-16DH-16DH-16DH-16DH-16DH-16DH-16DH-16DH-16DH-16DH-16DH-16DH-16DH-16DH-16DH-16DH-16DH-16DH-16DH-16DH-16DH-16DH-16DH-16DH-16DH-15DH-15DH-15DH-15DH-15DH-15DH-15DH-15DH-15DH-15DH-15DH-15DH-15DH-15DH-15DH-15DH-15DH-15DH-15DH-15DH-15DH-15DH-15DH-15DH-15 DH-17DH-17DH-17DH-17DH-17DH-17DH-17DH-17DH-17DH-17DH-17DH-17DH-17DH-17DH-17DH-17DH-17DH-17DH-17DH-17DH-17DH-17DH-17DH-17DH-17
DH-13DH-13DH-13DH-13DH-13DH-13DH-13DH-13DH-13DH-13DH-13DH-13DH-13DH-13DH-13DH-13DH-13DH-13DH-13DH-13DH-13DH-13DH-13DH-13DH-13
P-3P-3P-3P-3P-3P-3P-3P-3P-3P-3P-3P-3P-3P-3P-3P-3P-3P-3P-3P-3P-3P-3P-3P-3P-3
P-2P-2P-2P-2P-2P-2P-2P-2P-2P-2P-2P-2P-2P-2P-2P-2P-2P-2P-2P-2P-2P-2P-2P-2P-2
P-1P-1P-1P-1P-1P-1P-1P-1P-1P-1P-1P-1P-1P-1P-1P-1P-1P-1P-1P-1P-1P-1P-1P-1P-1
DH-5DH-5DH-5DH-5DH-5DH-5DH-5DH-5DH-5DH-5DH-5DH-5DH-5DH-5DH-5DH-5DH-5DH-5DH-5DH-5DH-5DH-5DH-5DH-5DH-5
DH-18DH-18DH-18DH-18DH-18DH-18DH-18DH-18DH-18DH-18DH-18DH-18DH-18DH-18DH-18DH-18DH-18DH-18DH-18DH-18DH-18DH-18DH-18DH-18DH-18
10/21/2015 Badan Tenaga Nuklir Nasional 37
2015
Geotechnical drilling
Simulation of Inundation of Cisadane River
10/21/2015 Badan Tenaga Nuklir Nasional 38
10/21/2015 Badan Tenaga Nuklir Nasional 39
POPULATION DISTRIBUTION
RADIUS 80 KM
RADIUS 25 KM
Audiency/ courtesy call with 3 Ministers and Key Institution Leader
10/21/2015 Badan Tenaga Nuklir Nasional 40
10/21/2015 Badan Tenaga Nuklir Nasional 41
Public Consultation
Signing the Contract (BATAN-RENUKO, 24 APRIL 2015)
10/21/2015 Badan Tenaga Nuklir Nasional 42
PRELIMINARY ENGINEERING DESIGN FOR I-EPR
Internal Audit
Verification And Audit of Site Evaluation Activities By BAPETEN
Verification And Audit of Site Evaluation Activities By BAPETEN
• I-EPR will be an” Indonesian NPP mastery” for future NPP commercialization especially for SMR size
• I-EPR is expected to be operated at 2020/2021
10/21/2015 Badan Tenaga Nuklir Nasional 46
Terimakasih