10/10/12...FAA 150/5380‐6B 10/10/12 14 Figure C - 12. Tem p orary Repairs of Rigid Pave me nts...
Transcript of 10/10/12...FAA 150/5380‐6B 10/10/12 14 Figure C - 12. Tem p orary Repairs of Rigid Pave me nts...
-
10/10/12
1
SWIFT‐ CAPTG 2012
BEST PRACTICES IN AIRFIELD CONCRETE PAVEMENT MAINTENANCE
PARTIAL AND FULL DEPTH PATCH REPAIRS
Hakan Ekim
Teknika Inc., Toronto
September 18,2012
Banff,Alberta
Requirements
Quick Repairs with no or minimum closures
or operaAonal delays
High Quality and long lasAng patch repairs.
They do not wish to return to the repair in a
very near future
No premature failure . FOD !
Major Challenges
Proper educaAon of the maintenance
personnel to ensure work is done as per
manufactures specs.
Not having enough data or successful case
histories.
Lack of mutual understanding in between
various parAes involved >> CommunicaAon??
-
10/10/12
2
Common denominator
It is widely accepted that effecAve repairs will
become increasingly important as many
airports may not receive the funds needed to
carry out major rehabilitaAons or re‐construct
distressed pavements
Engineering and maintenance managers can
uAlize a variety of pavement repair opAons to
extend the useful life of their pavements.
There is already enough knowledge and
experience to perform proper pavement
repairs.
Available materials and techniques are well
established and proven but yet somehow not
adapted.
Transport Canada Survey
Report No: AARMEC/ C‐02‐04 Revision,Nov.2002
Survey was made to produce :
“Pavement Preserva9on Catalogue for
Canadian Airfields”
This extensive work was based on literature
survey and review of pavement preservaWon
pracWces of Canadian Airports based on the
results and repair pracWces survey
-
10/10/12
3
No field performance studies issued by or for
Canadian Airports were located
Only 26 out of 70 operators responded
RecommendaAons of Transport Canada
The content of the Catalogue should be enhanced by
the inclusion of addiWonal technical and engineering
reports that could not be located, and by the
inclusion of new reports as they become available.
The content of the Catalogue should also be
enhanced as new pavement preservaWon
technologies are developed and addiWonal technical
informaWon is uncovered.
To obtain addiWonal technical reports and
informaWon from Canadian airport operators and
from the Canadian engineering consulWng industry
will require considerable effort.
We do need to overcome these managerial
issues and difficulAes.
We are facing a great challenge which is not
only the maintenance of the assets but also the
necessity to use exisAng faciliAes beyond their
design lives simply due to economic and
environmental condiAons.
-
10/10/12
4
Transport Canada ERD 121 (no longer updated)
Type of defects are well defined .
Defects are rated as Low, Medium, and High severity
Extent of repairs classified in between 0 and 4
(4 being extreme worse case)
CondiWon RaWng is obtained
(PCN,LCN,Fric8on Values not included not a full assesment)
Transport Canada Defect
ClassificaAons( ERD 121)
Panel Cracking
Corner Cracking
Edge Cracking
Scaling and spaling
Joint faulWng and sealant failure
Surface Crazing
D cracking
Pumping
Compression buckling
Panel Cracking (L)
-
10/10/12
5
Corner Cracking (M)
Edge Cracking (L,H)
Edge Cracking - High Severity
Scaling/Spaling
-
10/10/12
6
Joint FaulWng(M)/Sealant Failure(M)
Joint Faulting - Medium SevJoint Sealant Failure - Medium Severity
Surface Crazing (M)
“D” Cracking
-
10/10/12
7
Pumping (M) / Buckling(H)
Concrete Slab Pumping Compression Buckling at an Inserted Surface Draina
FAA AC 150/5380‐6B Chapter 3 Rigid
Pavement Distresses (2007) AC 150/5380-6B Chapter 3 – Pavement Distresses
• Rigid Pavement1. Cracking
• Longitudinal, Transverse, and Diagonal Cracks
• Corner Breaks.
• Durability "D" Cracking.
• Shrinkage Cracking.
2. Joint seal damage
3. Disintegration• Scaling, Map Cracking, and Crazing
• Joint Spalling. p g
• Corner Spalling.
• Shattered Slab/Intersecting Cracks
• Blowups
• Popouts. p
• Patching.
4. Distortion• Pumping.
• Settlement or Faulting. g
5. Loss of Skid resistance• Polished Aggregates
• Contaminants
The Keys to success of patch repairs of
PCC pavements
MUST HAVE GOOD AND SOUND PAVEMENT
MANAGEMENT SYSTEM IN PLACE
1‐ Understand the cause of the problem,
2‐ Have realisWc expectaWons,
3‐ Correct selecWon of materials and methods
according to operaWonal condiWons,
4‐ Surface preparaWon,
5‐ ApplicaWon and supervision
-
10/10/12
8
SelecAon of the repair material
depends on:
Ambient temperature
Time required for early trafficking, return to service
Size and depth of repair
Product performance
Compliance with specified properWes
Previous good experience
Cost effecWveness and delivery
Technical support from the manufacturer
The perfect repair product should have physical, chemical and mechanical, properWes, similar to the parent concrete.
Dimensional compaAbility of repair material is very important.
The ideal repair should have a modulus just lower than the parent concrete
The repair should have thermal expansion similar to the parent concrete
The repair should have shrinkage lower than the parent concrete
The repair should have strength just greater than the parent concrete
SelecAon of appropriate repair materials
Importance Of Modulus of ElasWcity
StaWc modulus of elasWcity is a
measure of sWffness.(Poisson’s raWo in
case of concrete)
HIGHER E : LESS DEFORMATION
UNDER A GIVEN LOAD
If the load is perpendicular to the
bond line higher modulus may not be
too significant. If however parallel to
the bond line load is transferred to
the higher moduli which may then
overstressed and fracture
-
10/10/12
9
Drying Shrinkage ICRI Guideline No: 03733
!n
!0
If !n = !0 No stress occurs.
If !n > !0 Shear Bond is stressed.
Coefficient Of thermal expansion α (ICRI Guideline: 03733)
-
10/10/12
10
Performance Undesirable Response Desirable PropertiesRequirements (results if wrong material is selected)
Ambient
temperature
changes
Temperature
changes within
repair material
at early ages
Atmospheric gases
Cracking in repair
material due to thermal
contraction stresses
Spalling due to thermal
expansion stresses in
substrate
Deformation due to
thermal expansion from
high exotherm
Cracking due to thermal
contraction stresses in
repair material
Corrosion of
Vjgtocn"eqghÝekgpv"similar to that of
substrate
Vjgtocn"eqghÝegpv"similar to that of
substrate
Low exotherm
during cure
Low permeability;
Tgukuvcpeg"vq"htgg¦kpi"
Coeicient of thermal expansion for concrete is 11x10-6/C.
ACI 503R Polymeric Coeicient of Thermal
Materials Expansion is 4-11 times
greater than Concrete
Therefore polymeric materials will expand/contract more than the substrate.
When movement is restrained stress is induced at the bond line
Very Important especially for large patch repairs (>2m2)
PROBABLY THE MOST IMPORTANT CRITERIA WHEN
SELECTING PATCH REPAIR MATERIALS
Texas A&M University System,Project 0‐5110‐S
Best PracAces for Concrete Pavements (Ref :10)
Dan Zollinger,David W.Fowler, Anal Mukhopadhy
Looked at 10 different materials commercially
available materials.
Modulus is the larger influence on strain due to
temperature change. The thermal stresses
induced at the interface between the concrete
and repair material should be compared to the
bond strength which resists the stress.
-
10/10/12
11
SelecAon of patch repair method
If the damage is confined to the top 1/3rd of the slab,
then parWal depth patch repairs can be OK
If the damage goes deeper than the top 3rd of the concrete slab, or
reaches dowel bars,then full depth patch repairs must be carried
out
⅓
Available Repair Materials
• CemenAous Materials
Portland Cement Concrete with an accelerator
Calcium Aluminate Cement
Magnesium Phosphate Cement
Latex Modified Cement or PMC
• Hot Mix
Resin Based
Epoxy based mortars
Polyurethane based mortars
MMA (Methyl Methacrylate) mortars
Polyester based repair mortars
Polyurea’s and Vinyl Concrete
ParAal depth repair of concrete pavements (1) Remove all deteriorated and/or
delaminated concrete as shown by survey and indicated by paint lines in accordance with preferred method of removal
Ensure size of repair is at least 50mm beyond damaged areas
The perimeter of the repair should have a verWcal face and should not be feather‐edged.
This can be done by saw cukng (preferable method) or milling.
Joint preparaWon including an appropriate bond breaker is required at joint/crack edges
-
10/10/12
12
ParAal depth repair of concrete pavements (2)
Clean concrete surface by water jekng or high pressure air blast
Mix the repair material using a forced acWon mixer
Apply the repair material in accordance with manufacturers instrucWons
CompacWon of repair material
Finishing the repair, providing skid free surface by steel Wne brush
Cure the repairs with a curing membrane with min 90% curing efficiency
ParWal depth repairs at joints must include sealing joints when finished
Fig
ure C
- 5.
Jo
int S
pa
ll Rep
air a
t Ex
isting
Rig
id P
av
emen
t Jo
int D
etail
FAA ‐150/5380‐6B
Full depth repair of concrete pavements (1)
Remove all deteriorated and/or delaminated concrete as shown by survey and indicated by paint lines in accordance with preferred method of removal
Ensure size of repair is at least 100mm beyond damaged areas
The perimeter of the repair should have a verWcal face and should not be feather‐edged.
This should be done by saw cukng
Joint preparaWon including an appropriate bond breaker is required at joint/crack edges
Check the sub‐base for soundness and if necessary, compact with a vibraWng plate
-
10/10/12
13
Full depth repair of concrete pavements (2)
Provide dowels or other load transfer mechanisms at edges
Mix the repair material using a forced acWon mixer or use ready mixed concrete
If using a prebagged material, use good quality aggregates for bulking out in accordance with manufacturers instrucWons.
Apply the repair material in accordance with manufacturers instrucWons
CompacWon of repair material Finishing the repair, providing skid free surface by steel Wne brush
Cure the repairs with a curing membrane with min 90% curing efficiency
FAA 150/5380‐6B
Fig
ure C
- 9.
Fu
ll Dep
th R
igid
Pa
vem
en
t Sla
b R
ep
air
Deta
il - Sectio
n
FAA 150/5380‐6B
-
10/10/12
14
Fig
ure C
- 12
. T
em
po
ra
ry
Rep
air
s of R
igid
Pa
vem
en
ts Usin
g F
lex
ible
Pa
vem
en
t Deta
il
FAA 150/5380‐6B
Surface preparaAon techniques In most cases, the use of a concrete saw is recommended for cukng verWcal
borders around the periphery of the delineated repair area. In such a case the
sides of the saw cut must be roughened by grit blasWng amer excavaWng the
centre of the repair
AlternaWvely, cut into the sides at an angle of 75O to form a morWce joint to hold the patch
Surface preparaAon techniques
For parWal depth repairs, the use of jack‐hammers are NOT
recommended. The impact causes micro‐cracking in the concrete and shanering of aggregate. This results in poor bond and may lead to delaminaWon of the repair.
Jack‐hammering may be used for full‐depth repairs provided that the repair area is isolated by saw cukng.
Ultra high pressure water blasWng is the preferred method for parWal depth repairs. There is no vibraWon to damage the freshly exposed concrete surface and key is bener.
Cold‐milling is a good method for removing large areas of concrete but if the concrete is weak, the aggregates may be pulled out of the bonding interface and weaken adhesion.
-
10/10/12
15
This is not surface preparaWon !!
̇̇
NO !!!
Expedient Spall Repair Methods and Equipment For Airfield Pavements
Michael I. Hammons & Athar Saeed
Document No : AFRL‐RX‐TY‐TP‐2009‐4552
Airforce Research Laboratory,Airforce Materiel Command,Tyndall Airforce Base FL
Selected equipment and procedures were evaluated to expedite repair of spalls with rapid sekng materials. The objecWve was to develop one or more methods to excavate and prepare a 2‐foot‐wide by 2‐foot‐long by 4‐inch‐deep spall for placement of a rapid‐sekng repair material in 15 minutes or less. A secondary objecWve was to correlate various excavaWon methods with a relaWve life expectancy of the repair. For five excavaWon methods, 2‐foot‐ wide by 2‐foot‐long by 4‐inch‐deep spalls were excavated in triplicate. The spalls were subsequently repaired using a commonly‐used rapid‐sekng cemenWWous repair material.
Findings of Hammons and Saeed
• Most efficient method was the Cold Planer. 58% more efficient than jack hammers.
• Second efficient method was gang saw
• Only Cold Planar was able excavate 2’x2’x4” area in 15 minutes
• GREATEST MEAN PULL OFF STRENGTH WAS FOR THE COLD PLANAR (IN BOTH PRE AND POST TRAFICKING .
• OTHER METHODS WERE ½ OF THE COLD PLANAR
-
10/10/12
16
Surface preparaWon techniques
High pressure water blasAng
Milling machine and drum
-
10/10/12
17
Abrupt Slope changes must be avoided Reference: Dept. of the Air Force.,Engineering Technical Lener ETL 07‐08
Figure 7. Repair with Abrupt Slope Change (Not Recommended)
Figure 8. Repair without Abrupt Slope Chang(Recommended)
Ensure size of repair is at least 50mm(2”)
beyond damaged areas. ??????
Î̇
̇̇̇
̇ -'(*%̇̇
Large repairs, red lines added where saw cuts should have been
made
Reference: Dept. of the Air Force.,Engineering Technical Lener ETL 07‐08
The Same Repair with Red Lines Added to Indicate
-
10/10/12
18
NaWonal Concrete Pavement Technology Centre Guide For ParWal Depth Repair of Concrete Pavements
April 2012
Iowa State University PublicaWon
#Ø-ØR²±や©Œや²æı±やßØ²æ©Łやı-ªœ³ŁØや²æØやŒ©œœ©¹ı-º╈ゃや *²やı±やª©±²まØTت²ıµØ╆
ゃや .©±²やª°Ø¹±や̶°Øや²½¬ıª̶œœ½やŒ̶ßıœı̶°や¹ı²æや²æı±やßØ²æ©Ł╆
%°̶¹Æ̶ªø±や©Œや²æı±やßØ²æ©Łやı-ªœ³ŁØや²æØやŒ©œœ©¹ı-º╈ゃや 8̶²Ø°やŒ°©ßや±̶¹ı-ºやœØ̶µØ±や²æØや̶°Ø̶や±̶²³°̶²ØŁ╇や¬©±±ıÆœ½や
ŁØœ̶½ı-ºや²æØや°Ø¬̶ı°や¬°©ªØ±±╆
ゃや 8ı²æ©³²やª̶°Ø╇や²æØやÆغı--ı-ºや©Œや±¬̶œœı-ºやª̶-や©ªª³°や̶²や²æØやł̶ªøæ̶ßßØ°やœı-Øや©³²±ıŁØや²æØや±̶¹やª³²╆
ゃや 5æı±やßØ²æ©Łやı±や²ıßØやª©-±³ßı-ºや̶-Łやı±や-©²や̶±やª©±²やØTت²ıµØやŒ©°やœ̶°ºØや¬̶°²ı̶œまŁØ¬²æや¬°©łØª²±や̶±やª©œŁやßıœœı-º╆
$©œŁやßıœœı-ºやı±や̶-©²æØ°や©¬²ı©-やŒ©°や°Øß©µı-ºやŁØ²Ø°ı©°̶²ØŁやª©-ª°Ø²Ø╆や5æØやßıœœı-ºや©¬Ø°̶²ı©-やª̶-や¬°©ªØØŁやØı²æØ°や̶ª°©±±やœ̶-رや©°や¬̶°̶œœØœや²©や²æØや¬̶µØßØ-²やªØ-²Ø°œı-Øや〉'ıº³°Øやアカや̶-Łや'ıº³°Øやアキ《╆や
.ıœœı-ºや̶œ©-ºや²æØやł©ı-²や©°やª°̶ªøやı±やØTت²ıµØやŒ©°や°Øß©µı-ºや±¬̶œœı-ºや̶-Łや¬°©Ł³ªØ±や̶や°Øª²̶-º³œ̶°ま±æ̶¬ØŁや°Ø¬̶ı°や̶°Ø̶╇や¹æØ°Ø̶±やßıœœı-ºや¬Ø°¬Ø-Łıª³œ̶°や²©や²æØやł©ı-²や©°やª°̶ªøやı±やØŒŒØª²ıµØやŒ©°や±ß̶œœØ°╇やı-ŁıµıŁ³̶œや±¬̶œœ±や̶-Łや¬°©Ł³ªØ±や̶やŁı±æま±æ̶¬ØŁや°Ø¬̶ı°や̶°Ø̶╆や
.ıŁ¹Ø±²Ø°-や±²̶²Ø±や±²̶°²ØŁや³±ı-ºや̶やßıœœやŒ©°やª©-ª°Ø²Øや°Øß©µ̶œやı-や²æØやØ̶°œ½やアケクー±や̶-Łやæ̶µØやæ̶Łや±³ªªØ±±やœØ̶µı-ºや²æØや°©³-ŁØŁやØŁºØやŒ©°や5½¬Ø±やアや̶-Łやイや¬̶°²ı̶œまŁØ¬²æや°Ø¬̶ı°±や〉'ıº³°Øやアク╇や'ıº³°Øやアケ╇や̶-Łや'ıº³°Øやイー《╆や8ı²æや²æØやßıœœı-ºや±½±²Øßや̶-Łや²æØı°や©¹-や¬̶°²ı̶œまŁØ¬²æや°Ø¬̶ı°や²Øªæ-ı®³Ø±╇や.ıŁ¹Ø±²Ø°-や±²̶²Ø±やæ̶µØやæ̶Łやı-ª°Ø̶±ØŁや±³ªªØ±±や¹ı²æや̶œœや²æØı°やßıœœØŁや¬̶°²ı̶œまŁØ¬²æや°Ø¬̶ı°±やª©ß¬̶°ØŁや²©や±̶¹ま̶-Łまªæı¬や°Øß©µ̶œや¹æØ-や²æØや¬©œı±æØŁやµØ°²ıª̶œやØŁºØやı±やœØWやı-や¬œ̶ªØ╆
#Ø-ØR²±や©Œやßıœœı-ºや̶°Øや̶±やŒ©œœ©¹╈ゃや 5æØや¬̶²ªæや±ı¾Øやı±や³-ıŒ©°ßやŒ©°やœ©-ºま²Ø°ßや±³ªªØ±±╆
ゃや 5æØや°©³ºæ╇やı°°Øº³œ̶°や±³°Œ̶ªØや¬°©ß©²Ø±やÆ©-Łı-º╆
ゃや .ıœœı-ºやı±やØUªıØ-²や̶-Łやت©-©ßıª̶œや¹æØ-や°Ø¬̶ı°ı-ºやœ̶°ºØや̶°Ø̶±╆
ゃや %ØÆ°ı±やı±やØ̶±½や²©や°Øß©µØや¹ı²æや̶や±æ©µØœや̶-ŁやÆ°©©ßや©°や̶や±øıŁやœ©̶ŁØ°や¬ıªø³¬やÆ°©©ß╆
ゃや .ıœœı-ºや°Ø®³ı°Ø±やœØ±±やœ̶Æ©°や²æ̶-やł̶ªøæ̶ßßØ°や°Øß©µ̶œ╆
%°̶¹Æ̶ªø±や©Œや²æı±やßØ²æ©Łや̶°Øや̶±やŒ©œœ©¹╈
ゃや .ıœœı-ºやª°Ø̶²Ø±や̶や±²̶-Ł̶°Łや±ı¾Ø╇や¹æıªæやß̶½や-©²やª©-Œ©°ßや²©や±ı²Ø╆や
ゃや &¼²°̶やßıœœı-ºやß̶½やÆØや°Ø®³ı°ØŁや²©や¹ıŁØ-や²æØや©°ıºı-̶œやßıœœØŁやªæ̶--Øœ╇やر¬Øªı̶œœ½や¹æØ-やßıœœı-ºやœ©-ºやª°̶ªø±や〉Ø╆º╆╇やœ©-ºı²³Łı-̶œ《や²©やª°Ø̶²Øや̶やßı-ıß³ßやŁı±²̶-ªØや©Œやウやı-╆や²©や̶-や©³²±ıŁØやßıœœØŁやŒ̶ªØや〉'ıº³°Øやアケ《╆
ゃや &®³ı¬ßØ-²や̶-Łやß©Æıœı¾̶²ı©-やß̶½やÆØやª©±²œ½やŒ©°や±ß̶œœや¬°©łØª²±╆
Figure 16. Milling along the joint or crack
#Ø-ØR²±や©Œや²æı±やßØ²æ©Łやı-ªœ³ŁØや²æØやŒ©œœ©¹ı-º╈ゃや *²やı±やª©±²まØTت²ıµØ╆
ゃや .©±²やª°Ø¹±や̶°Øや²½¬ıª̶œœ½やŒ̶ßıœı̶°や¹ı²æや²æı±やßØ²æ©Ł╆
%°̶¹Æ̶ªø±や©Œや²æı±やßØ²æ©Łやı-ªœ³ŁØや²æØやŒ©œœ©¹ı-º╈ゃや 8̶²Ø°やŒ°©ßや±̶¹ı-ºやœØ̶µØ±や²æØや̶°Ø̶や±̶²³°̶²ØŁ╇や¬©±±ıÆœ½や
ŁØœ̶½ı-ºや²æØや°Ø¬̶ı°や¬°©ªØ±±╆
ゃや 8ı²æ©³²やª̶°Ø╇や²æØやÆغı--ı-ºや©Œや±¬̶œœı-ºやª̶-や©ªª³°や̶²や²æØやł̶ªøæ̶ßßØ°やœı-Øや©³²±ıŁØや²æØや±̶¹やª³²╆
ゃや 5æı±やßØ²æ©Łやı±や²ıßØやª©-±³ßı-ºや̶-Łやı±や-©²や̶±やª©±²やØTت²ıµØやŒ©°やœ̶°ºØや¬̶°²ı̶œまŁØ¬²æや¬°©łØª²±や̶±やª©œŁやßıœœı-º╆
$©œŁやßıœœı-ºやı±や̶-©²æØ°や©¬²ı©-やŒ©°や°Øß©µı-ºやŁØ²Ø°ı©°̶²ØŁやª©-ª°Ø²Ø╆や5æØやßıœœı-ºや©¬Ø°̶²ı©-やª̶-や¬°©ªØØŁやØı²æØ°や̶ª°©±±やœ̶-رや©°や¬̶°̶œœØœや²©や²æØや¬̶µØßØ-²やªØ-²Ø°œı-Øや〉'ıº³°Øやアカや̶-Łや'ıº³°Øやアキ《╆や
.ıœœı-ºや̶œ©-ºや²æØやł©ı-²や©°やª°̶ªøやı±やØTت²ıµØやŒ©°や°Øß©µı-ºや±¬̶œœı-ºや̶-Łや¬°©Ł³ªØ±や̶や°Øª²̶-º³œ̶°ま±æ̶¬ØŁや°Ø¬̶ı°や̶°Ø̶╇や¹æØ°Ø̶±やßıœœı-ºや¬Ø°¬Ø-Łıª³œ̶°や²©や²æØやł©ı-²や©°やª°̶ªøやı±やØŒŒØª²ıµØやŒ©°や±ß̶œœØ°╇やı-ŁıµıŁ³̶œや±¬̶œœ±や̶-Łや¬°©Ł³ªØ±や̶やŁı±æま±æ̶¬ØŁや°Ø¬̶ı°や̶°Ø̶╆や
.ıŁ¹Ø±²Ø°-や±²̶²Ø±や±²̶°²ØŁや³±ı-ºや̶やßıœœやŒ©°やª©-ª°Ø²Øや°Øß©µ̶œやı-や²æØやØ̶°œ½やアケクー±や̶-Łやæ̶µØやæ̶Łや±³ªªØ±±やœØ̶µı-ºや²æØや°©³-ŁØŁやØŁºØやŒ©°や5½¬Ø±やアや̶-Łやイや¬̶°²ı̶œまŁØ¬²æや°Ø¬̶ı°±や〉'ıº³°Øやアク╇や'ıº³°Øやアケ╇や̶-Łや'ıº³°Øやイー《╆や8ı²æや²æØやßıœœı-ºや±½±"²Øßや̶-Łや²æØı°や©¹-や¬̶°²ı̶œまŁØ¬²æや°Ø¬̶ı°や²Øªæ-ı®³Ø±╇や.ıŁ¹Ø±²Ø°-や±²̶²Ø±やæ̶µØやæ̶Łやı-ª°Ø̶±ØŁや±³ªªØ±±や¹ı²æや̶œœや²æØı°やßıœœØŁや¬̶°²ı̶œまŁØ¬²æや°Ø¬̶ı°±やª©ß¬̶°ØŁや²©や±̶¹ま̶-Łまªæı¬や°Øß©µ̶œや¹æØ-や²æØや¬©œı±æØŁやµØ°²ıª̶œやØŁºØやı±やœØWやı-や¬œ̶ªØ╆
#Ø-ØR²±や©Œやßıœœı-ºや̶°Øや̶±やŒ©œœ©¹╈ゃや 5æØや¬̶²ªæや±ı¾Øやı±や³-ıŒ©°ßやŒ©°やœ©-ºま²Ø°ßや±³ªªØ±±╆
ゃや 5æØや°©³ºæ╇やı°°Øº³œ̶°や±³°Œ̶ªØや¬°©ß©²Ø±やÆ©-Łı-º╆
ゃや .ıœœı-ºやı±やØUªıØ-²や̶-Łやت©-©ßıª̶œや¹æØ-や°Ø¬̶ı°ı-ºやœ̶°ºØや̶°Ø̶±╆
ゃや %ØÆ°ı±やı±やØ̶±½や²©や°Øß©µØや¹ı²æや̶や±æ©µØœや̶-ŁやÆ°©©ßや©°や̶や±øıŁやœ©̶ŁØ°や¬ıªø³¬やÆ°©©ß╆
ゃや .ıœœı-ºや°Ø®³ı°Ø±やœØ±±やœ̶Æ©°や²æ̶-やł̶ªøæ̶ßßØ°や°Øß©µ̶œ╆
%°̶¹Æ̶ªø±や©Œや²æı±やßØ²æ©Łや̶°Øや̶±やŒ©œœ©¹╈
ゃや .ıœœı-ºやª°Ø̶²Ø±や̶や±²̶-Ł̶°Łや±ı¾Ø╇や¹æıªæやß̶½や-©²やª©-Œ©°ßや²©や±ı²Ø╆や
ゃや &¼²°̶やßıœœı-ºやß̶½やÆØや°Ø®³ı°ØŁや²©や¹ıŁØ-や²æØや©°ıºı-̶œやßıœœØŁやªæ̶--Øœ╇やر¬Øªı̶œœ½や¹æØ-やßıœœı-ºやœ©-ºやª°̶ªø±や〉Ø╆º╆╇やœ©-ºı²³Łı-̶œ《や²©やª°Ø̶²Øや̶やßı-ıß³ßやŁı±²̶-ªØや©Œやウやı-╆や²©や̶-や©³²±ıŁØやßıœœØŁやŒ̶ªØや〉'ıº³°Øやアケ《╆
ゃや &®³ı¬ßØ-²や̶-Łやß©Æıœı¾̶²ı©-やß̶½やÆØやª©±²œ½やŒ©°や±ß̶œœや¬°©łØª²±╆
Figure 18. Type 1 spot milling
Figure 19. Type 2A joint milling
NaWonal Concrete Pavement Technology Centre
Guide For ParWal Depth Repair of Concrete Pavements
April 2012
Iowa State University PublicaWon
Æ©-Ł±やÆØmØ°や²©や²æØやؼ¬©±ØŁやª©-ª°Ø²Øや©-や̶や²̶¬Ø°ØŁやØŁºØや²æ̶-や©-や̶やµØ°²ıª̶œやØŁºØ╆や5æØや²̶¬Ø°や̶œ±©やØœıßı-̶²Ø±や²æØやª©°-Ø°や̶²や²æØやÆ©m©ßやØŁºØや©Œや²æØや°Ø¬̶ı°やŒ°©ßや¹æıªæやæıºæまªØßØ-²やßı¼Ø±やª̶-や±æ°ı-øや̶-Łや¬°ØµØ-²やÆ©-Łı-º╆や5æØや²̶¬Ø°ØŁやØŁºØや̶œ±©や±ØØß±や²©やª°Ø̶²ØやœØ±±や±¬̶œœı-ºや̶-Łやªæı¬¬ı-ºや²æ̶-や̶やµØ°²ıª̶œやßıœœØŁやØŁºØ╆
&¼¬Ø°ıØ-ªØやæ̶±やŁØß©-±²°̶²ØŁや²æ̶²や̶や²̶¬Ø°ØŁや7まæØ̶Łやßıœœや©°や°©³-ŁØŁやßıœœやª̶-やÆØや³±ØŁや©-や̶œœや¬̶°²ı̶œまŁØ¬²æや°Ø¬̶ı°や¬°©łØª²±╆や.ıœœı-ºや¹ı²æや²æØや7まæØ̶Łや©°や°©³-ŁØŁやæØ̶Łやæ̶±やÆØØ-や³±ØŁやµØ°½や±³ªªØ±±Œ³œœ½や©-や²°̶-±µØ°±Øやł©ı-²±や¹ı²æ©³²や̶-½や̶ŁŁı²ı©-̶œや±̶¹ı-º╇や¹ı²æや©-œ½やßı-©°やªæı¬¬ı-ºや̶²や²æØやØŁºØや©Œや²æØや°Ø¬̶ı°╆や*Œや̶-½やªæı¬¬ı-ºやŁ©Ø±や©ªª³°╇や²æØやßıœœやæØ̶Ł±や-ØØŁや²©やÆØやªæتøØŁやŒ©°や±æ̶°¬-ر±╆や0-や©ªª̶±ı©-±や¹æØ-や̶やßıœœやæØ̶Łやı±や-©²や³±ØŁや²©やŒ©°ßや²æØやØŁºØ±╇や²æØやØŁºØ±や̶°Øや²̶¬Ø°ØŁや³±ı-ºや̶や±ß̶œœやł̶ªøæ̶ßßØ°や²©や°Øß©µØや²æØやµØ°²ıª̶œやØŁºØ±やœØWやƽや²æØや±̶¹ı-ºや©¬Ø°̶²ı©-╆
5æØや±²̶²Ø±や©Œや,̶-±̶±や̶-Łや4©³²æや%̶ø©²̶やß©ŁıRØŁや.ı--ر©²̶‒±やßıœœı-ºや̶¬¬°©̶ªæやƽや°Ø®³ı°ı-ºや²æ̶²や̶やµØ°²ıª̶œ╇やı-±²Ø̶Łや©Œや²̶¬Ø°ØŁ╇やØŁºØやÆØやœØWやƽや²æØやßıœœや〉'ıº³°Øやイオや̶-Łや'ıº³°Øやイカ《╆や.ıœœı-ºや̶やµØ°²ıª̶œやŒ̶ªØやª̶-やœØ̶µØやß©°Øやªæı¬¬ı-ºや̶²や²æØや²©¬やØŁºØ╇や±©や±©ßØや±²̶²Ø±や±³ªæや̶±や,̶-±̶±や°Ø®³ı°Øや̶や±̶¹やª³²やŒ©°や̶œœや²°̶-±µØ°±Øやł©ı-²±や°Ø¬̶ı°ØŁや¹ı²æや¬̶°²ı̶œまŁØ¬²æやßıœœı-º╆や
Figure 22. V-head milling
5æØやß©±²やª©ßß©-やßıœœやæØ̶Ł±や³±ØŁや²©Ł̶½や̶°Øや²æØや⦆7をや©°や°©³-ŁØŁやæØ̶Łや̶-Łや²æØやµØ°²ıª̶œやØŁºØ╆や
.ıœœØŁやæØ̶Ł±やß̶-³Œ̶ª²³°ØŁや²©やª°Ø̶²Øや̶や⦆7をや±æ̶¬Øや〉'ıº³°Øやイアや̶-Łや'ıº³°Øやイイ《や©°や°©³-Łや±æ̶¬Øや〉'ıº³°Øやイウや̶-Łや'ıº³°Øやイエ《やª̶-やÆØや³±ØŁや©-や²°̶-±µØ°±Øや̶-Łやœ©-ºı²³Łı-̶œやł©ı-²±や̶-Łやª°̶ªø±╆や5æØや¬°ØŒØ°°ØŁや±æ̶¬Øやı±や̶や²̶¬Ø°ØŁやØŁºØや̶-½¹æØ°ØやŒ°©ßやウーや²©やカーやŁØº°Øرや²©や²æØやÆ©m©ßや©Œや²æØやł©ı-²╆や5æØや¬̶²ªæやß̶²Ø°ı̶œや
Æ©-Ł±やÆØmØ°や²©や²æØやؼ¬©±ØŁやª©-ª°Ø²Øや©-や̶や²̶¬Ø°ØŁやØŁºØや²æ̶-や©-や̶やµØ°²ıª̶œやØŁºØ╆や5æØや²̶¬Ø°や̶œ±©やØœıßı-̶²Ø±や²æØやª©°-Ø°や̶²や²æØやÆ©m©ßやØŁºØや©Œや²æØや°Ø¬̶ı°やŒ°©ßや¹æıªæやæıºæまªØßØ-²やßı¼Ø±やª̶-や±æ°ı-øや̶-Łや¬°ØµØ-²やÆ©-Łı-º╆や5æØや²̶¬Ø°ØŁやØŁºØや̶œ±©や±ØØß±や²©やª°Ø̶²ØやœØ±±や±¬̶œœı-ºや̶-Łやªæı¬¬ı-ºや²æ̶-や̶やµØ°²ıª̶œやßıœœØŁやØŁºØ╆
&¼¬Ø°ıØ-ªØやæ̶±やŁØß©-±²°̶²ØŁや²æ̶²や̶や²̶¬Ø°ØŁや7まæØ̶Łやßıœœや©°や°©³-ŁØŁやßıœœやª̶-やÆØや³±ØŁや©-や̶œœや¬̶°²ı̶œまŁØ¬²æや°Ø¬̶ı°や¬°©łØª²±╆や.ıœœı-ºや¹ı²æや²æØや7まæØ̶Łや©°や°©³-ŁØŁやæØ̶Łやæ̶±やÆØØ-や³±ØŁやµØ°½や±³ªªØ±±Œ³œœ½や©-や²°̶-±µØ°±Øやł©ı-²±や¹ı²æ©³²や̶-½や̶ŁŁı²ı©-̶œや±̶¹ı-º╇や¹ı²æや©-œ½やßı-©°やªæı¬¬ı-ºや̶²や²æØやØŁºØや©Œや²æØや°Ø¬̶ı°╆や*Œや̶-½やªæı¬¬ı-ºやŁ©Ø±や©ªª³°╇や²æØやßıœœやæØ̶Ł±や-ØØŁや²©やÆØやªæتøØŁやŒ©°や±æ̶°¬-ر±╆や0-や©ªª̶±ı©-±や¹æØ-や̶やßıœœやæØ̶Łやı±や-©²や³±ØŁや²©やŒ©°ßや²æØやØŁºØ±╇や²æØやØŁºØ±や̶°Øや²̶¬Ø°ØŁや³±ı-ºや̶や±ß̶œœやł̶ªøæ̶ßßØ°や²©や°Øß©µØや²æØやµØ°²ıª̶œやØŁºØ±やœØWやƽや²æØや±̶¹ı-ºや©¬Ø°̶²ı©-╆
5æØや±²̶²Ø±や©Œや,̶-±̶±や̶-Łや4©³²æや%̶ø©²̶やß©ŁıRØŁや.ı--ر©²̶‒±やßıœœı-ºや̶¬¬°©̶ªæやƽや°Ø®³ı°ı-ºや²æ̶²や̶やµØ°²ıª̶œ╇やı-±²Ø̶Łや©Œや²̶¬Ø°ØŁ╇やØŁºØやÆØやœØWやƽや²æØやßıœœや〉'ıº³°Øやイオや̶-Łや'ıº³°Øやイカ《╆や.ıœœı-ºや̶やµØ°²ıª̶œやŒ̶ªØやª̶-やœØ̶µØやß©°Øやªæı¬¬ı-ºや̶²や²æØや²©¬やØŁºØ╇や±©や±©ßØや±²̶²Ø±や±³ªæや̶±や,̶-±̶±や°Ø®³ı°Øや̶や±̶¹やª³²やŒ©°や̶œœや²°̶-±µØ°±Øやł©ı-²±や°Ø¬̶ı°ØŁや¹ı²æや¬̶°²ı̶œまŁØ¬²æやßıœœı-º╆や
Figure 25. Vertical edge milling
5æØやß©±²やª©ßß©-やßıœœやæØ̶Ł±や³±ØŁや²©Ł̶½や̶°Øや²æØや⦆7をや©°や°©³-ŁØŁやæØ̶Łや̶-Łや²æØやµØ°²ıª̶œやØŁºØ╆や
.ıœœØŁやæØ̶Ł±やß̶-³Œ̶ª²³°ØŁや²©やª°Ø̶²Øや̶や⦆7をや±æ̶¬Øや〉'ıº³°Øやイアや̶-Łや'ıº³°Øやイイ《や©°や°©³-Łや±æ̶¬Øや〉'ıº³°Øやイウや̶-Łや'ıº³°Øやイエ《やª̶-やÆØや³±ØŁや©-や²°̶-±µØ°±Øや̶-Łやœ©-ºı²³Łı-̶œやł©ı-²±や̶-Łやª°̶ªø±╆や5æØや¬°ØŒØ°°ØŁや±æ̶¬Øやı±や̶や²̶¬Ø°ØŁやØŁºØや̶-½¹æØ°ØやŒ°©ßやウーや²©やカーやŁØº°Øرや²©や²æØやÆ©m©ßや©Œや²æØやł©ı-²╆や5æØや¬̶²ªæやß̶²Ø°ı̶œや
m
m
m
m
W
m
B.#$&-0,'%&,-'$".-!:)$3*@$,.#$9'-!,$/7$3#&.%0*&%:$3#%0"$
WT
W
Figure 37. View of cardboard cut to fi t irregular random crack
WW
m
m %+"
,H%3";,+3/&,+3"4E(:=+%"FC?"E(:=+%"FF?",)3"E(:=+%"F698"
m
W
This could only be
temporary repair and
needs to be monitored
closely to prevent FOD
-
10/10/12
19
-
10/10/12
20
-
10/10/12
21
Shrinkage Cracks
Some recommended repair techniques
Over‐sawing the edges of repairs can lead to corner
cracking
Use a 4” core to cut neat rounded corners, then cut into
these cores with a saw
-
10/10/12
22
Some recommended repair techniques
Coring is an excellent technique for preparing patch
repairs
Popout cored and filled
Cored corners of patch repairs
Milled Surface
Patched repairProper Mix Consistency
-
10/10/12
23
NEW ICRI GUIDE
& EUROPEAN REPAIR GUIDE
Guideline for Inorganic Repair Material Data
Sheet Protocol.
Guideline : 320.3R‐2012
EN 1504 ‐2006 : European Repair SpecificaWon
-
10/10/12
24
Resources
1. Guide for Selec8ng and Specifying Materials for Repair of Concrete Surfaces
ICRI ,InternaWonal Concrete Repair InsWtute,
Technical Guidelines, Guideline No:03733
2. Guidelines and Procedures for Maintenance of Airport Pavements.
FAA Advisory Circular,AC No: 150/5380‐6B‐2007,
3. Expedient Spall Repair Methods and Equipment for Airfield Repairs
Michael I Hammons,Air Force Research Laboratory and Athar Seed,Applied Research
Associates.
Airbase Technologies Division, Air Force Research Laboratory, Air Force Material Command,
Tyndall Air Force Base FL.
4. Engineering Technical LeVer 07‐08:Spall Repair of PCC Airfield Pavements in Expedi8onary
Environments,
Department of The Air Force,
AFCESA/CEO,Tyndall AFB, FL
Resources 5. Guide for Par8al Depth Repair of Concrete Pavements
NaWonal Concrete Pavement Technology Centre,IOWA State University, InsWtute for
TransportaWon . April 2012
6. Pavement Preserva8on Catalogue for Canadian Airfields.
Report No: AARME/C‐02‐04
The Technical EvaluaWon Engineering Division
Aerodrome Safety Branch
Transport Canada, Onawa, Ontario, November 2002
7. Guidelines Respec8ng Airport Pavement Structural Condi8on Surveys
Engineering Reference Document ERD 121 January 2004
Transport Canada, InternaWonal AviaWon & Technical Programs Branch, Engineering Division
Onawa, Ontario.
8. Maintenance and Repair of Airport PCC Pavements
Engineering Reference Document ERD 125‐02, November 2004,
Transport Canada, InternaWonal AviaWon&Technical Programs Branch, Engineering Division
Onawa,Ontario.
Resources 9. Materials and Procedures for the Repair of Par8al Depth Spalls in Concrete Pavements
Concrete Pavement Repair Manual of PracWce
Strategic Highway Research Program, SHRP‐H‐349
NaWonal Research Council
10. Inves8ga8on of Spall Repair Materials for Concrete Pavement:Summary Report
Report No :0‐5110‐S May 2006
Dan G.Zollinger,David W.Fowler,Anal Mukhopadhyay
Texas TransportaWon InsWtute,The Texas a&M University System
-
10/10/12
25
THANK YOU