100% of External Plastering work...

17

Transcript of 100% of External Plastering work...

Page 1: 100% of External Plastering work completed.hazelproject.in/wp-content/themes/twentyfourteen/images/Nov-2017/... · 1st Coat of external paint completed & 2nd coat is in progress.
Page 2: 100% of External Plastering work completed.hazelproject.in/wp-content/themes/twentyfourteen/images/Nov-2017/... · 1st Coat of external paint completed & 2nd coat is in progress.
Page 3: 100% of External Plastering work completed.hazelproject.in/wp-content/themes/twentyfourteen/images/Nov-2017/... · 1st Coat of external paint completed & 2nd coat is in progress.

100% of External Plastering work completed.

100% of 2nd coat of External putty work completed.

1st Coat of external paint completed & 2nd coat is in progress.

2nd Coat of internal putty completed.

1st coat of internal painting completed.

UPVC door/Windows/ventilator installation completed.

Window grill installation completed in all flats.

Doors painting , Window grills & Balcony hand railing 1st coat of painting work is completed.

Tiling Work completed in all flats.

Kitchen Granite slab completed in all flats.

Kitchen Wall tile dadoing completed in all flats.

Main door installation completed in all 140 units.

Internal bedroom door installation work completed in all flats.

Page 4: 100% of External Plastering work completed.hazelproject.in/wp-content/themes/twentyfourteen/images/Nov-2017/... · 1st Coat of external paint completed & 2nd coat is in progress.

Bathroom false ceiling grid fixing work is completed in 140 flats and board fixing completed.

Internal Electrical work completed in all flats.

Wiring to DB box is completed 140 Flats and panel end termination work is in progress.

Wiring work is progress in stilt and basement floor.

OTS putty 100% completed and OTS Painting is in progress.

OTS platform hand railing work is 95% completed.

OTS platform concrete has been completed.

Staircase granite installation work completed till 14th floor.

Staircase Railing work completed.

Passenger lift installation is completed and commissioning is in progress .

Lift wall granite cladding work completed.

Common Area Tiling completed till 14th floor.

Terrace Waterproofing work completed.

Shaft plumbing work is completed.

Shaft Cable tray fixing and Electrical cable laying work completed.

Page 5: 100% of External Plastering work completed.hazelproject.in/wp-content/themes/twentyfourteen/images/Nov-2017/... · 1st Coat of external paint completed & 2nd coat is in progress.

Basement back filling work completed.

Basement floor screed concrete is 100% completed.

Stilt floor screed concrete 90% completed.

Basement ceiling painting work completed.

Basement and stilt floor plumbing work is completed.

Domestic / Non- Domestic plumbing testing and commissioning work completed.

Terrace shaft closing works completed.

LMR roof top flooring work is completed.

OTS covering structural steel work completed and sheet work is completed.

Stilt floor painting is completed.

Sewage line connection along with chamber construction with STP in External area is in progress.

Shaft closing with SHERA board is nearing completion.

Plumbing materials has been delivered to site, installation is in progress from 1st floor to 6th floor.

Vertices work completed , basement work is in progress.

Page 6: 100% of External Plastering work completed.hazelproject.in/wp-content/themes/twentyfourteen/images/Nov-2017/... · 1st Coat of external paint completed & 2nd coat is in progress.

Terrace PPG sheet work has been completed.

Pump has been delivered to the site.

FA / PA work is in progress .

Electrical stilt and basement wiring completed.

Page 7: 100% of External Plastering work completed.hazelproject.in/wp-content/themes/twentyfourteen/images/Nov-2017/... · 1st Coat of external paint completed & 2nd coat is in progress.

Basement pipe line works

Page 8: 100% of External Plastering work completed.hazelproject.in/wp-content/themes/twentyfourteen/images/Nov-2017/... · 1st Coat of external paint completed & 2nd coat is in progress.

Basement flooring

Page 9: 100% of External Plastering work completed.hazelproject.in/wp-content/themes/twentyfourteen/images/Nov-2017/... · 1st Coat of external paint completed & 2nd coat is in progress.

Stilt flooring

Page 10: 100% of External Plastering work completed.hazelproject.in/wp-content/themes/twentyfourteen/images/Nov-2017/... · 1st Coat of external paint completed & 2nd coat is in progress.

Stilt pipe line works

Page 11: 100% of External Plastering work completed.hazelproject.in/wp-content/themes/twentyfourteen/images/Nov-2017/... · 1st Coat of external paint completed & 2nd coat is in progress.

Sanitary fittings and cp fittings

Page 12: 100% of External Plastering work completed.hazelproject.in/wp-content/themes/twentyfourteen/images/Nov-2017/... · 1st Coat of external paint completed & 2nd coat is in progress.

Fire hydrant line FA / PA work

Page 13: 100% of External Plastering work completed.hazelproject.in/wp-content/themes/twentyfourteen/images/Nov-2017/... · 1st Coat of external paint completed & 2nd coat is in progress.

Shaft closing with SHERA board

Page 14: 100% of External Plastering work completed.hazelproject.in/wp-content/themes/twentyfourteen/images/Nov-2017/... · 1st Coat of external paint completed & 2nd coat is in progress.

False ceiling work Dinning area wash basin

Page 15: 100% of External Plastering work completed.hazelproject.in/wp-content/themes/twentyfourteen/images/Nov-2017/... · 1st Coat of external paint completed & 2nd coat is in progress.

OTS Covering sheet work

Page 16: 100% of External Plastering work completed.hazelproject.in/wp-content/themes/twentyfourteen/images/Nov-2017/... · 1st Coat of external paint completed & 2nd coat is in progress.

Delivered Pump

Page 17: 100% of External Plastering work completed.hazelproject.in/wp-content/themes/twentyfourteen/images/Nov-2017/... · 1st Coat of external paint completed & 2nd coat is in progress.