1.0 | Site Report Wednesday, 4 Dec 2019 · 1.0 | Site Report Wednesday, 4 Dec 2019 Project Details...

22
1.0 | Site Report Wednesday, 4 Dec 2019 Project Details Project No: Dec19 Contract No: Client: Constructionarium Client Representative: Harry Hartman Contractor: Team One Contractor Repentative: Shift Details Shifts Worked: Day Afternoon Night Weather Details Weather location: Tarragindi, AU (latitude: -27.546981 longitude: 153.020882) Date Mean Temp (°C) Min Temp (°C) Max Temp (°C) Relative Humidity (%) Rainfall (mm) Wind Speed (km/h) Wind Direction (°) 4 Dec 2019 25.5 17.5 34.2 39.1% 0.0 8.6 177.0 Note: The highlighted row represents today's weather data which may be incomplete. Comments: Health and Safety Exposure hours (from timesheets) 135.50 Exposure headcount (from timesheets) 17 Work Progress Activity Activity Name Revised Planned Start Actual Start Revised Planned Finish Actual Finish Actual Quantity in Period Actual Quantity to Date Labour in Period Labour to Date PRELIMS - Construction Setup 3.00 Construction Setup 3 Dec 2019 3 Dec 2019 3 Dec 2019 60.00 (percentage) 13.00 23.50 Rhys (Rhys) Janssen: Head stocks at correct heights and torqued down Alexander (Alex) Ibarra: Headstocks installed and levelling process continuing Boris Tusevljak: Headstock in Rory O'Keeffe: Headstocks Installed! Harrison Thomson: Installation of headstocks to pier via crane lift Harrison Thomson: Road safety furniture installation, lowering of bunting to allow for crane access PRELIMS - Construction Setup Totals 60.00 (percentage) 13.00 23.50 PRELIMS - Preliminaries 1.00 Preliminaries 2 Dec 2019 2 Dec 2019 2 Dec 2019 70.00 (percentage) 132.00 Danah Crichton: Leveling cross beams Rhys (Rhys) Janssen: Getting SWMS signed Lee McCann: Ensuring all heads are accounted for prior to the day. Alexander (Alex) Ibarra: Pre-start meeting preparing for the day 1.011 Staff Overheads 2 Dec 2019 2 Dec 2019 6 Dec 2019 20.00 (percentage) 13.00 25.00 Doris Tang: Lunch & Learn presented by Alex: indigenous cultural learning Rory O'Keeffe: We're back in front! PRELIMS - Preliminaries Totals 90.00 (percentage) 13.00 157.00 Site Report Constructionarium 2019 Page 1 of 22

Transcript of 1.0 | Site Report Wednesday, 4 Dec 2019 · 1.0 | Site Report Wednesday, 4 Dec 2019 Project Details...

Page 1: 1.0 | Site Report Wednesday, 4 Dec 2019 · 1.0 | Site Report Wednesday, 4 Dec 2019 Project Details Project No: ... open Boris Tusevljak: Site tour start at 1015 Site Report Constructionarium

1.0 | Site Report Wednesday, 4 Dec 2019

Project DetailsProject No: Dec19 Contract No:

Client: Constructionarium Client Representative: Harry Hartman

Contractor: Team One Contractor Repentative:

Shift DetailsShifts Worked: Day Afternoon Night

Weather DetailsWeather location: Tarragindi, AU (latitude: -27.546981 longitude: 153.020882)Date Mean Temp (°C) Min Temp (°C) Max Temp (°C) Relative Humidity (%) Rainfall (mm) Wind Speed (km/h) Wind Direction (°)

4 Dec 2019 25.5 17.5 34.2 39.1% 0.0 8.6 177.0

Note: The highlighted row represents today's weather data which may be incomplete.

Comments:

Health and SafetyExposure hours(from timesheets)

135.50 Exposure headcount(from timesheets)

17

Work ProgressActivity Activity Name Revised

Planned Start

Actual Start

RevisedPlanned

Finish

Actual Finish

ActualQuantity in Period

ActualQuantity to Date

Labour in Period

Labourto Date

PRELIMS - Construction Setup

3.00 Construction Setup 3 Dec2019

3 Dec2019

3 Dec2019

60.00(percentage)

13.00 23.50

Rhys (Rhys) Janssen: Head stocks at correct heights and torqued down

Alexander (Alex) Ibarra: Headstocks installed and levelling process continuing

Boris Tusevljak: Headstock in

Rory O'Keeffe: Headstocks Installed!

Harrison Thomson: Installation of headstocks to pier via crane lift

Harrison Thomson: Road safety furniture installation, lowering of bunting to allow for crane access

PRELIMS - Construction Setup Totals 60.00(percentage)

13.00 23.50

PRELIMS - Preliminaries

1.00 Preliminaries 2 Dec2019

2 Dec2019

2 Dec2019

70.00(percentage)

132.00

Danah Crichton: Leveling cross beams

Rhys (Rhys) Janssen: Getting SWMS signed

Lee McCann: Ensuring all heads are accounted for prior to the day.

Alexander (Alex) Ibarra: Pre-start meeting preparing for the day

1.011 Staff Overheads 2 Dec2019

2 Dec2019

6 Dec2019

20.00(percentage)

13.00 25.00

Doris Tang: Lunch & Learn presented by Alex: indigenous cultural learning

Rory O'Keeffe: We're back in front!

PRELIMS - Preliminaries Totals 90.00(percentage)

13.00 157.00

☐ ☐ ☐

Site ReportConstructionarium 2019

Page 1 of 22

Page 2: 1.0 | Site Report Wednesday, 4 Dec 2019 · 1.0 | Site Report Wednesday, 4 Dec 2019 Project Details Project No: ... open Boris Tusevljak: Site tour start at 1015 Site Report Constructionarium

STAGE A - Bridge Stage A - LHS Endspan

4.3414 Connect Deck to Frame with Bolts 3 Dec2019

4 Dec2019

4 Dec2019

4 Dec2019

100.00(percentage)

100.00(percentage)

4.3313 Connect Deck to Frame with Bolts 3 Dec2019

3 Dec2019

3 Dec2019

4 Dec2019

100.00(percentage)

4.3415 Install Last Frame 4 Dec2019

4 Dec2019

4 Dec2019

4 Dec2019

100.00(percentage)

100.00(percentage)

4.3411 Install Permanent & Temp Bracing 3 Dec2019

3 Dec2019

4 Dec2019

4 Dec2019

50.00(percentage)

100.00(percentage)

4.3516 Lift Final Component into Place and Install 4 Dec2019

4 Dec2019

4 Dec2019

4 Dec2019

100.00(percentage)

100.00(percentage)

STAGE A - Bridge Stage A - LHS Endspan Totals 350.00(percentage)

500.00(percentage)

STAGE A - Construction Setup

3.313 Prepare Prop for Stage A 3 Dec2019

3 Dec2019

3 Dec2019

4 Dec2019

100.00(percentage)

3.315 Secure Stage A & Prop 3 Dec2019

3 Dec2019

3 Dec2019

4 Dec2019

100.00(percentage)

3.311 Survey Headstock 3 Dec2019

3 Dec2019

3 Dec2019

4 Dec2019

100.00(percentage)

3.312 Temporary Works For Stage A 3 Dec2019

3 Dec2019

3 Dec2019

4 Dec2019

100.00(percentage)

3.314 Wooden Temporary Beams in Place for Stage A 3 Dec2019

3 Dec2019

3 Dec2019

4 Dec2019

100.00(percentage)

STAGE A - Construction Setup Totals 500.00(percentage)

STAGE B - Bridge Stage B - RHS Endspan

5.00 Bridge Stage B - RHS Endspan 4 Dec2019

4 Dec2019

4 Dec2019

74.50 74.50

Michael (Gunny) Gunn: Rory confirming how good of a job we did today $$$

Rhys (Rhys) Janssen: Stage A and B lifted into position, some bolts torqued, need quality check on the 5/12/19 to ensure are bolts are tightened

Saurabh Bokde: Big crane is here.

Rory O'Keeffe: Second Major Lift! Great progress today, congratulations to PM Danah!

Shaghayegh Balali: Connect bracing with bolts using wrench

Harrison Thomson: Stage b completed, needs to undergo inspection before lifting into position

Shaghayegh Balali: Stage B

Alexander (Alex) Ibarra: first section lift

Alexander (Alex) Ibarra: second lift successfully complete

Narayanan Krishnan: stage B set up

Humza Aijaz: Client delays

Rhys (Rhys) Janssen: Abutment B headstock ready to install

Humza Aijaz: Indirect staff members working hard as they sip on their Chai Latte

Harrison Thomson: Installation of Cross bracing

Humza Aijaz: Temp bracing

Rhys (Rhys) Janssen: Connecting side trusses to deck frame

Harrison Thomson: Movement of second steel truss for Stage B

Boris Tusevljak: Simultaneous A and B stick build

Narayanan Krishnan: Set up of stage B

Doris Tang: Lollipop traffic control road closure

Humza Aijaz: Temp works in progress

Saurabh Bokde: Lift 1 - Day 2 construction

Saurabh Bokde: Implementing TMP

Doris Tang: Day 6 (build day 3) 8am toolbox meeting- roles for each person- what we’re working on- safety SWMS

Saurabh Bokde: Pre-start day 3 construction

Site ReportConstructionarium 2019

Page 2 of 22

Page 3: 1.0 | Site Report Wednesday, 4 Dec 2019 · 1.0 | Site Report Wednesday, 4 Dec 2019 Project Details Project No: ... open Boris Tusevljak: Site tour start at 1015 Site Report Constructionarium

5.4313 Connect Deck to LHS Frame with Bolts 3 Dec2019

4 Dec2019

3 Dec2019

4 Dec2019

100.00(percentage)

100.00(percentage)

5.438 Connect Deck to RHS Frame with Bolts 3 Dec2019

4 Dec2019

3 Dec2019

4 Dec2019

100.00(percentage)

100.00(percentage)

5.4414 Connect Timber Deck to Frame with Bolts 3 Dec2019

4 Dec2019

4 Dec2019

5.4415 Install Last Frame 4 Dec2019

4 Dec2019

4 Dec2019

4 Dec2019

100.00(percentage)

100.00(percentage)

5.4411 Install Permanent & Temp Bracing 3 Dec2019

4 Dec2019

4 Dec2019

4 Dec2019

100.00(percentage)

100.00(percentage)

5.4516 Lift Final Component into Place and Install 4 Dec2019

4 Dec2019

4 Dec2019

4 Dec2019

100.00(percentage)

100.00(percentage)

5.426 Lift Stage B Deck to Assembly Area 3 Dec2019

4 Dec2019

3 Dec2019

4 Dec2019

100.00(percentage)

100.00(percentage)

5.4312 Lift Stage B Left Frame to Assembly Area 3 Dec2019

4 Dec2019

3 Dec2019

4 Dec2019

100.00(percentage)

100.00(percentage)

5.437 Lift Stage B Right Frame to Assembly Area 3 Dec2019

4 Dec2019

3 Dec2019

4 Dec2019

100.00(percentage)

100.00(percentage)

5.4310 Prop Left Frame to Concrete Block 3 Dec2019

4 Dec2019

3 Dec2019

4 Dec2019

100.00(percentage)

100.00(percentage)

5.439 Prop Right Frame to Concrete Block 3 Dec2019

4 Dec2019

3 Dec2019

4 Dec2019

100.00(percentage)

100.00(percentage)

STAGE B - Bridge Stage B - RHS Endspan Totals 1000.00(percentage)

1000.00(percentage)

74.50 74.50

STAGE B - Construction Setup

3.413 Prepare Prop for Stage B 3 Dec2019

3 Dec2019

3 Dec2019

4 Dec2019

100.00(percentage)

100.00(percentage)

3.415 Secure Stage B & Prop 3 Dec2019

3 Dec2019

3 Dec2019

4 Dec2019

100.00(percentage)

100.00(percentage)

3.411 Sign Off Headstocks 3 Dec2019

3 Dec2019

3 Dec2019

4 Dec2019

100.00(percentage)

100.00(percentage)

3.412 Temporary Works for Stage B 3 Dec2019

3 Dec2019

3 Dec2019

4 Dec2019

100.00(percentage)

100.00(percentage)

3.414 Wooden Temporary Beams in Place for Stage B 3 Dec2019

3 Dec2019

3 Dec2019

4 Dec2019

100.00(percentage)

100.00(percentage)

STAGE B - Construction Setup Totals 500.00(percentage)

500.00(percentage)

STAGE C - Bridge Stage C - Middle Section

6.5313 Connect Deck to LHS Frame with Bolts 5 Dec2019

4 Dec2019

5 Dec2019

4 Dec2019

100.00(percentage)

100.00(percentage)

6.538 Connect Deck to RHS Frame with Bolts 5 Dec2019

4 Dec2019

5 Dec2019

4 Dec2019

100.00(percentage)

100.00(percentage)

6.5411 Install Permanent & Temp Bracing 5 Dec2019

4 Dec2019

5 Dec2019

4 Dec2019

100.00(percentage)

100.00(percentage)

6.526 Lift Stage C Deck to Assembly Area 5 Dec2019

4 Dec2019

5 Dec2019

4 Dec2019

100.00(percentage)

100.00(percentage)

6.5312 Lift Stage C Left Frame to Assembly Area 5 Dec2019

4 Dec2019

5 Dec2019

4 Dec2019

100.00(percentage)

100.00(percentage)

6.537 Lift Stage C Right Frame to Assembly Area 5 Dec2019

4 Dec2019

5 Dec2019

4 Dec2019

100.00(percentage)

100.00(percentage)

6.5310 Prop Left Frame to Concrete Block 5 Dec2019

4 Dec2019

5 Dec2019

4 Dec2019

100.00(percentage)

100.00(percentage)

6.539 Prop Right Frame to Concrete Block 5 Dec2019

4 Dec2019

5 Dec2019

4 Dec2019

100.00(percentage)

100.00(percentage)

STAGE C - Bridge Stage C - Middle Section Totals 800.00(percentage)

800.00(percentage)

STAGE C - Construction Setup

3.511 Install Headstock 5 Dec2019

3 Dec2019

5 Dec2019

4 Dec2019

100.00(percentage)

100.00(percentage)

3.513 Prepare Prop for Stage C 4 Dec2019

3 Dec2019

5 Dec2019

4 Dec2019

100.00(percentage)

100.00(percentage)

3.515 Secure Stage C & Prop 5 Dec2019

4 Dec2019

5 Dec2019

4 Dec2019

100.00(percentage)

100.00(percentage)

3.512 Temporary Works for Stage C 4 Dec2019

3 Dec2019

5 Dec2019

4 Dec2019

100.00(percentage)

100.00(percentage)

3.514 Wooden Temporary Beams in Place for Stage C 5 Dec2019

4 Dec2019

5 Dec2019

4 Dec2019

100.00(percentage)

100.00(percentage)

STAGE C - Construction Setup Totals 500.00(percentage)

500.00(percentage)

Site ReportConstructionarium 2019

Page 3 of 22

Page 4: 1.0 | Site Report Wednesday, 4 Dec 2019 · 1.0 | Site Report Wednesday, 4 Dec 2019 Project Details Project No: ... open Boris Tusevljak: Site tour start at 1015 Site Report Constructionarium

EventsEvent Event Type Event Name

EventExpected

FinishRelatedActivity

Related Activity Name Status EstimatedLabour

EstimatedDuration

PRELIMS - Construction Setup

1 Delay - Client Delay from Crane availability 3 Dec2019

3.00 Construction Setup started

STAGE B - Bridge Stage B - RHS Endspan

2 Delay - Client Site Tour from CTC 4 Dec2019

5.00 Bridge Stage B - RHSEndspan

open

Boris Tusevljak: Site tour start at 1015

Site ReportConstructionarium 2019

Page 4 of 22

Page 5: 1.0 | Site Report Wednesday, 4 Dec 2019 · 1.0 | Site Report Wednesday, 4 Dec 2019 Project Details Project No: ... open Boris Tusevljak: Site tour start at 1015 Site Report Constructionarium

Appendix A - Photos

Activity 5.00: Bridge Stage B - RHS Endspan: Rory confirminghow good of a job we did today $$$

Activity 5.00: Bridge Stage B - RHS Endspan: Stage A and Blifted into position, some bolts torqued, need quality check onthe 5/12/19 to ensure are bolts are tightened

Activity 4.00: Bridge Stage A - LHS Endspan: First section liftonto headstocks

Activity 5.00: Bridge Stage B - RHS Endspan: Big crane ishere.

Activity 4.00: Bridge Stage A - LHS Endspan: Indigenouslectures Activity 4.00: Bridge Stage A - LHS Endspan: It’s ready

Site ReportConstructionarium 2019

Page 5 of 22

Page 6: 1.0 | Site Report Wednesday, 4 Dec 2019 · 1.0 | Site Report Wednesday, 4 Dec 2019 Project Details Project No: ... open Boris Tusevljak: Site tour start at 1015 Site Report Constructionarium

Activity 5.00: Bridge Stage B - RHS Endspan: Second MajorLift! Great progress today, congratulations to PM Danah!

Activity 4.00: Bridge Stage A - LHS Endspan: 25T perfect forthe job!

Activity 4.00: Bridge Stage A - LHS Endspan: InstallationActivity 4.00: Bridge Stage A - LHS Endspan: But first let metake a selfie

Activity 4.00: Bridge Stage A - LHS Endspan: Commencementof lift into place Activity 4.00: Bridge Stage A - LHS Endspan: First stage lift

Site ReportConstructionarium 2019

Page 6 of 22

Page 7: 1.0 | Site Report Wednesday, 4 Dec 2019 · 1.0 | Site Report Wednesday, 4 Dec 2019 Project Details Project No: ... open Boris Tusevljak: Site tour start at 1015 Site Report Constructionarium

Activity 4.00: Bridge Stage A - LHS Endspan: Preparation forpart A lift

Activity 3.00: Construction Setup: Head stocks at correctheights and torqued down

Activity 6.00: Bridge Stage C - Middle Section: Proppingsection C Activity 6.00: Bridge Stage C - Middle Section: Lifting

Activity 1.00: Preliminaries: Leveling cross beamsActivity 4.00: Bridge Stage A - LHS Endspan: Flooring sectionA

Site ReportConstructionarium 2019

Page 7 of 22

Page 8: 1.0 | Site Report Wednesday, 4 Dec 2019 · 1.0 | Site Report Wednesday, 4 Dec 2019 Project Details Project No: ... open Boris Tusevljak: Site tour start at 1015 Site Report Constructionarium

Activity 3.00: Construction Setup: Headstocks installed andlevelling process continuing

Activity 6.00: Bridge Stage C - Middle Section: First Deckinglift complete

Activity 3.00: Construction Setup: Headstock inActivity 4.00: Bridge Stage A - LHS Endspan: BracingInstalled!

Activity 4.00: Bridge Stage A - LHS Endspan: Quality check Activity 4.00: Bridge Stage A - LHS Endspan: Scaffolding work

Site ReportConstructionarium 2019

Page 8 of 22

Page 9: 1.0 | Site Report Wednesday, 4 Dec 2019 · 1.0 | Site Report Wednesday, 4 Dec 2019 Project Details Project No: ... open Boris Tusevljak: Site tour start at 1015 Site Report Constructionarium

Activity 1.011: Staff Overheads: Lunch & Learn presented byAlex: indigenous cultural learning

Activity 4.00: Bridge Stage A - LHS Endspan: Ex changemanager turned project controls leader reminding us to takephotos of everything

Activity 5.00: Bridge Stage B - RHS Endspan: Connectbracing with bolts using wrench

Activity 5.00: Bridge Stage B - RHS Endspan: Stage bcompleted, needs to undergo inspection before lifting intoposition

Activity 4.00: Bridge Stage A - LHS Endspan: Filed tripActivity 4.00: Bridge Stage A - LHS Endspan: LHS floor beingprepared for installation into final position

Site ReportConstructionarium 2019

Page 9 of 22

Page 10: 1.0 | Site Report Wednesday, 4 Dec 2019 · 1.0 | Site Report Wednesday, 4 Dec 2019 Project Details Project No: ... open Boris Tusevljak: Site tour start at 1015 Site Report Constructionarium

Activity 4.00: Bridge Stage A - LHS Endspan: LHS bracingcomplete

Activity 4.00: Bridge Stage A - LHS Endspan: LHS headstocklowered and leveled Awaiting bolt down

Activity 5.00: Bridge Stage B - RHS Endspan: Stage BActivity 4.00: Bridge Stage A - LHS Endspan: Adjustment ofheadstock height to level (LHS A)

Activity 4.00: Bridge Stage A - LHS Endspan: Cross beamsLHS (a&b) lowered in place

Activity 4.00: Bridge Stage A - LHS Endspan: Task cardmanual handling and levelling signed for all workersassociated

Site ReportConstructionarium 2019

Page 10 of 22

Page 11: 1.0 | Site Report Wednesday, 4 Dec 2019 · 1.0 | Site Report Wednesday, 4 Dec 2019 Project Details Project No: ... open Boris Tusevljak: Site tour start at 1015 Site Report Constructionarium

Activity 3.00: Construction Setup: Headstocks Installed!Activity 4.00: Bridge Stage A - LHS Endspan: Final bolts beingtightened on LHS

Activity 5.00: Bridge Stage B - RHS Endspan: first section liftActivity 3.00: Construction Setup: Installation of headstocks topier via crane lift

Activity 5.00: Bridge Stage B - RHS Endspan: second liftsuccessfully complete Activity 5.00: Bridge Stage B - RHS Endspan: stage B set up

Site ReportConstructionarium 2019

Page 11 of 22

Page 12: 1.0 | Site Report Wednesday, 4 Dec 2019 · 1.0 | Site Report Wednesday, 4 Dec 2019 Project Details Project No: ... open Boris Tusevljak: Site tour start at 1015 Site Report Constructionarium

Event 2: Site Tour from CTC: Site tour start at 1015 Activity 5.00: Bridge Stage B - RHS Endspan: Client delays

Activity 4.00: Bridge Stage A - LHS Endspan: Stage A almostcompleted and looking good

Activity 5.00: Bridge Stage B - RHS Endspan: Abutment Bheadstock ready to install

Activity 5.00: Bridge Stage B - RHS Endspan: Indirect staffmembers working hard as they sip on their Chai Latte Activity 4.00: Bridge Stage A - LHS Endspan: Slow and steady

Site ReportConstructionarium 2019

Page 12 of 22

Page 13: 1.0 | Site Report Wednesday, 4 Dec 2019 · 1.0 | Site Report Wednesday, 4 Dec 2019 Project Details Project No: ... open Boris Tusevljak: Site tour start at 1015 Site Report Constructionarium

Activity 4.00: Bridge Stage A - LHS Endspan: Traffic controllerActivity 5.00: Bridge Stage B - RHS Endspan: Installation ofCross bracing

Activity 1.011: Staff Overheads: We're back in front! Activity 5.00: Bridge Stage B - RHS Endspan: Temp bracing

Activity 5.00: Bridge Stage B - RHS Endspan: Connectingside trusses to deck frame

Activity 4.00: Bridge Stage A - LHS Endspan: Michael fixingthe bracing, lack of wrench availavility noted as materialsmanager.

Site ReportConstructionarium 2019

Page 13 of 22

Page 14: 1.0 | Site Report Wednesday, 4 Dec 2019 · 1.0 | Site Report Wednesday, 4 Dec 2019 Project Details Project No: ... open Boris Tusevljak: Site tour start at 1015 Site Report Constructionarium

Activity 5.00: Bridge Stage B - RHS Endspan: Movement ofsecond steel truss for Stage B

Activity 5.00: Bridge Stage B - RHS Endspan: Simultaneous Aand B stick build

Activity 5.00: Bridge Stage B - RHS Endspan: Simultaneous Aand B stick build Activity 4.00: Bridge Stage A - LHS Endspan: Quality check

Activity 4.00: Bridge Stage A - LHS Endspan: Heat expansionor misalignment

Activity 5.00: Bridge Stage B - RHS Endspan: Set up of stageB

Site ReportConstructionarium 2019

Page 14 of 22

Page 15: 1.0 | Site Report Wednesday, 4 Dec 2019 · 1.0 | Site Report Wednesday, 4 Dec 2019 Project Details Project No: ... open Boris Tusevljak: Site tour start at 1015 Site Report Constructionarium

Activity 5.00: Bridge Stage B - RHS Endspan: Lollipop trafficcontrol road closure

Activity 4.00: Bridge Stage A - LHS Endspan: Completedsurveying @8:49 hours

Activity 5.00: Bridge Stage B - RHS Endspan: Temp works inprogress

Activity 5.00: Bridge Stage B - RHS Endspan: Lift 1 - Day 2construction

Activity 3.00: Construction Setup: Road safety furnitureinstallation, lowering of bunting to allow for crane access

Activity 4.00: Bridge Stage A - LHS Endspan: Traffic setupcompleted @8:30 hours

Site ReportConstructionarium 2019

Page 15 of 22

Page 16: 1.0 | Site Report Wednesday, 4 Dec 2019 · 1.0 | Site Report Wednesday, 4 Dec 2019 Project Details Project No: ... open Boris Tusevljak: Site tour start at 1015 Site Report Constructionarium

Activity 5.00: Bridge Stage B - RHS Endspan: ImplementingTMP

Activity 5.00: Bridge Stage B - RHS Endspan: Day 6 (buildday 3) 8am toolbox meeting - roles for each person - whatwe’re working on - safety SWMS

Activity 5.00: Bridge Stage B - RHS Endspan: Pre-start day 3construction Activity 1.00: Preliminaries: Getting SWMS signed

Activity 1.00: Preliminaries: Ensuring all heads are accountedfor prior to the day.

Activity 1.00: Preliminaries: Pre-start meeting preparing for theday

Site ReportConstructionarium 2019

Page 16 of 22

Page 17: 1.0 | Site Report Wednesday, 4 Dec 2019 · 1.0 | Site Report Wednesday, 4 Dec 2019 Project Details Project No: ... open Boris Tusevljak: Site tour start at 1015 Site Report Constructionarium

Supervisor: Wed, 04 Dec 2019

Appendix B - Timesheets

Name Work Role Usage Code Work Allocation Hours Approval

Alexander (Alex) Ibarra (Team 1)

General Labourer N 3.00 - Construction Setup 4.00

N 5.00 - Bridge Stage B - RHS Endspan 3.50

Total Hours 7.50

Ammar Abdurrahman (Team 1)

General Labourer N 2 - Site Tour from CTC 0.50

N 4.00 - Bridge Stage A - LHS Endspan 2.00

N 5.00 - Bridge Stage B - RHS Endspan 5.50

Total Hours 8.00

Boris Tusevljak (Team 1)

General Labourer N 2 - Site Tour from CTC 0.50

N 4.00 - Bridge Stage A - LHS Endspan 2.00

N 5.00 - Bridge Stage B - RHS Endspan 5.50

Total Hours 8.00

Danah Crichton (Team 1)

General Labourer N 2 - Site Tour from CTC 0.50

N 3.00 - Construction Setup 1.00

N 5.00 - Bridge Stage B - RHS Endspan 5.50

N 6.00 - Bridge Stage C - Middle Section 1.00

Total Hours 8.00

Daniel Oberthur (Team 1)

General Labourer LWP 1.011 - Staff Overheads 8.00

Total Hours 8.00

Doris Tang (Team 1)

General Labourer N 2 - Site Tour from CTC 0.50

N 3.00 - Construction Setup 4.00

N 5.00 - Bridge Stage B - RHS Endspan 3.50

Total Hours 8.00

Harrison Thomson (Team 1)

General Labourer N 2 - Site Tour from CTC 0.50

N 4.00 - Bridge Stage A - LHS Endspan 2.00

N 5.00 - Bridge Stage B - RHS Endspan 5.50

Total Hours 8.00

Humza Aijaz (Team 1)

General Labourer N 2 - Site Tour from CTC 0.50

N 5.00 - Bridge Stage B - RHS Endspan 5.50

N 6.00 - Bridge Stage C - Middle Section 2.00

Total Hours 8.00

Lee McCann (Team 1)

General Labourer N 2 - Site Tour from CTC 0.50

N 4.00 - Bridge Stage A - LHS Endspan 2.00

N 5.00 - Bridge Stage B - RHS Endspan 3.50

N 6.00 - Bridge Stage C - Middle Section 2.00

Total Hours 8.00

Michael (Gunny) Gunn (Team 1)

General Labourer N 2 - Site Tour from CTC 0.50

N 4.00 - Bridge Stage A - LHS Endspan 2.00

N 5.00 - Bridge Stage B - RHS Endspan 5.50

Total Hours 8.00

Narayanan Krishnan (Team 1)

General Labourer N 2 - Site Tour from CTC 0.50

N 4.00 - Bridge Stage A - LHS Endspan 2.00

N 5.00 - Bridge Stage B - RHS Endspan 5.50

Total Hours 8.00

Rhys (Rhys) Janssen (Team 1)

General Labourer N 2 - Site Tour from CTC 0.50

N 3.00 - Construction Setup 4.00

N 5.00 - Bridge Stage B - RHS Endspan 3.50

Total Hours 8.00

Rory O'Keeffe (Team 1)

General Labourer N 2 - Site Tour from CTC 0.50

N 4.00 - Bridge Stage A - LHS Endspan 2.00

N 5.00 - Bridge Stage B - RHS Endspan 3.50

N 6.00 - Bridge Stage C - Middle Section 2.00

Total Hours 8.00

Saurabh Bokde General Labourer N 2 - Site Tour from CTC 0.50

Site ReportConstructionarium 2019

Page 17 of 22

Page 18: 1.0 | Site Report Wednesday, 4 Dec 2019 · 1.0 | Site Report Wednesday, 4 Dec 2019 Project Details Project No: ... open Boris Tusevljak: Site tour start at 1015 Site Report Constructionarium

(Team 1) N 4.00 - Bridge Stage A - LHS Endspan 2.00

N 5.00 - Bridge Stage B - RHS Endspan 5.50

Total Hours 8.00

Shaghayegh Balali (Team 1)

General Labourer N 2 - Site Tour from CTC 0.50

N 4.00 - Bridge Stage A - LHS Endspan 2.00

N 5.00 - Bridge Stage B - RHS Endspan 5.50

Total Hours 8.00

Theja Dilshan WijesingheMinigammana Vidanelage (Team 1)

General Labourer N 2.00 - Procurement 0.50

N 4.00 - Bridge Stage A - LHS Endspan 2.00

N 5.00 - Bridge Stage B - RHS Endspan 5.50

Total Hours 8.00

Trent Day (Team 1)

General Labourer LWP 1.011 - Staff Overheads 5.00

N 4.00 - Bridge Stage A - LHS Endspan 1.00

N 5.00 - Bridge Stage B - RHS Endspan 2.00

Total Hours 8.00

Site ReportConstructionarium 2019

Page 18 of 22

Page 19: 1.0 | Site Report Wednesday, 4 Dec 2019 · 1.0 | Site Report Wednesday, 4 Dec 2019 Project Details Project No: ... open Boris Tusevljak: Site tour start at 1015 Site Report Constructionarium

Appendix C - Equipment UsageThere is no timesheet data for any equipment items on this day.

Site ReportConstructionarium 2019

Page 19 of 22

Page 20: 1.0 | Site Report Wednesday, 4 Dec 2019 · 1.0 | Site Report Wednesday, 4 Dec 2019 Project Details Project No: ... open Boris Tusevljak: Site tour start at 1015 Site Report Constructionarium

Company: Team 1Status: Entered

Company: Team 1Status: Entered

Company: Team 1Status: Entered

Company: Team 1Status: Entered

Company: Team 1Status: Entered

Company: Team 1

Appendix D - DocketsDocket: TEA-F-AA-20191204-1Docket Date: 4 Dec 2019

Resource Role Type WorkDate

StartTime

EndTime

Break UsageCode

Rate Code Work Reference Amount UoM

AmmarAbdurrahman

GeneralLabourer

Person 4 Dec2019

8:00 am 5:00 pm 1.00 Normal ConstructionManager

2: Site Tour from CTC 0.50 hours

AmmarAbdurrahman

GeneralLabourer

Person 4 Dec2019

8:00 am 5:00 pm 1.00 Normal ConstructionManager

4.00: Bridge Stage A - LHSEndspan

2.00 hours

AmmarAbdurrahman

GeneralLabourer

Person 4 Dec2019

8:00 am 5:00 pm 1.00 Normal ConstructionManager

5.00: Bridge Stage B - RHSEndspan

5.50 hours

Docket: TEA-F-AI-20191204-1Docket Date: 4 Dec 2019

Resource Role Type WorkDate

StartTime

EndTime

Break UsageCode

Rate Code Work Reference Amount UoM

Alexander (Alex)Ibarra

GeneralLabourer

Person 4 Dec2019

8:00 am 5:00 pm 1.00 Normal GeneralLabour

3.00: Construction Setup 4.00 hours

Alexander (Alex)Ibarra

GeneralLabourer

Person 4 Dec2019

8:00 am 5:00 pm 1.00 Normal GeneralLabour

5.00: Bridge Stage B - RHSEndspan

3.50 hours

Docket: TEA-F-BT-20191204-1Docket Date: 4 Dec 2019

Resource Role Type WorkDate

StartTime

EndTime

Break UsageCode

Rate Code Work Reference Amount UoM

BorisTusevljak

GeneralLabourer

Person 4 Dec2019

8:00 am 5:00 pm 1.00 Normal Project ControlsManager

2: Site Tour from CTC 0.50 hours

BorisTusevljak

GeneralLabourer

Person 4 Dec2019

8:00 am 5:00 pm 1.00 Normal Project ControlsManager

4.00: Bridge Stage A - LHSEndspan

2.00 hours

BorisTusevljak

GeneralLabourer

Person 4 Dec2019

8:00 am 5:00 pm 1.00 Normal Project ControlsManager

5.00: Bridge Stage B - RHSEndspan

5.50 hours

Docket: TEA-F-DC-20191204-1Docket Date: 4 Dec 2019

Resource Role Type WorkDate

StartTime

EndTime

Break UsageCode

Rate Code Work Reference Amount UoM

DanahCrichton

GeneralLabourer

Person 4 Dec2019

8:00 am 5:00 pm 1.00 Normal ProjectManager

2: Site Tour from CTC 0.50 hours

DanahCrichton

GeneralLabourer

Person 4 Dec2019

8:00 am 5:00 pm 1.00 Normal ProjectManager

3.00: Construction Setup 1.00 hours

DanahCrichton

GeneralLabourer

Person 4 Dec2019

8:00 am 5:00 pm 1.00 Normal ProjectManager

5.00: Bridge Stage B - RHSEndspan

5.50 hours

DanahCrichton

GeneralLabourer

Person 4 Dec2019

8:00 am 5:00 pm 1.00 Normal ProjectManager

6.00: Bridge Stage C - MiddleSection

1.00 hours

Docket: TEA-F-HA-20191204-1Docket Date: 4 Dec 2019

Resource Role Type WorkDate

StartTime

EndTime

Break UsageCode

Rate Code Work Reference Amount UoM

HumzaAijaz

GeneralLabourer

Person 4 Dec2019

8:00 am 5:00 pm 1.00 Normal GeneralLabour

2: Site Tour from CTC 0.50 hours

HumzaAijaz

GeneralLabourer

Person 4 Dec2019

8:00 am 5:00 pm 1.00 Normal GeneralLabour

5.00: Bridge Stage B - RHSEndspan

5.50 hours

HumzaAijaz

GeneralLabourer

Person 4 Dec2019

8:00 am 5:00 pm 1.00 Normal GeneralLabour

6.00: Bridge Stage C - MiddleSection

2.00 hours

Docket: TEA-F-HT-20191204-1

Site ReportConstructionarium 2019

Page 20 of 22

Page 21: 1.0 | Site Report Wednesday, 4 Dec 2019 · 1.0 | Site Report Wednesday, 4 Dec 2019 Project Details Project No: ... open Boris Tusevljak: Site tour start at 1015 Site Report Constructionarium

Status: Entered

Company: Team 1Status: Entered

Company: Team 1Status: Entered

Company: Team 1Status: Entered

Company: Team 1Status: Entered

Company: Team 1Status: Entered

Docket Date: 4 Dec 2019

Resource Role Type WorkDate

StartTime

EndTime

Break UsageCode

Rate Code Work Reference Amount UoM

HarrisonThomson

GeneralLabourer

Person 4 Dec2019

8:00 am 5:00 pm 1.00 Normal TrafficController

2: Site Tour from CTC 0.50 hours

HarrisonThomson

GeneralLabourer

Person 4 Dec2019

8:00 am 5:00 pm 1.00 Normal TrafficController

4.00: Bridge Stage A - LHSEndspan

2.00 hours

HarrisonThomson

GeneralLabourer

Person 4 Dec2019

8:00 am 5:00 pm 1.00 Normal TrafficController

5.00: Bridge Stage B - RHSEndspan

5.50 hours

Docket: TEA-F-LM-20191204-1Docket Date: 4 Dec 2019

Resource Role Type WorkDate

StartTime

EndTime

Break UsageCode

Rate Code Work Reference Amount UoM

LeeMcCann

GeneralLabourer

Person 4 Dec2019

8:00 am 5:00 pm 1.00 Normal GeneralLabour

2: Site Tour from CTC 0.50 hours

LeeMcCann

GeneralLabourer

Person 4 Dec2019

8:00 am 5:00 pm 1.00 Normal GeneralLabour

4.00: Bridge Stage A - LHSEndspan

2.00 hours

LeeMcCann

GeneralLabourer

Person 4 Dec2019

8:00 am 5:00 pm 1.00 Normal GeneralLabour

5.00: Bridge Stage B - RHSEndspan

3.50 hours

LeeMcCann

GeneralLabourer

Person 4 Dec2019

8:00 am 5:00 pm 1.00 Normal GeneralLabour

6.00: Bridge Stage C - MiddleSection

2.00 hours

Docket: TEA-F-MG-20191204-1Docket Date: 4 Dec 2019

Resource Role Type WorkDate

StartTime

EndTime

Break UsageCode

Rate Code Work Reference Amount UoM

Michael (Gunny)Gunn

GeneralLabourer

Person 4 Dec2019

8:00 am 5:00 pm 1.00 Normal GeneralLabour

2: Site Tour from CTC 0.50 hours

Michael (Gunny)Gunn

GeneralLabourer

Person 4 Dec2019

8:00 am 5:00 pm 1.00 Normal GeneralLabour

4.00: Bridge Stage A - LHSEndspan

2.00 hours

Michael (Gunny)Gunn

GeneralLabourer

Person 4 Dec2019

8:00 am 5:00 pm 1.00 Normal GeneralLabour

5.00: Bridge Stage B - RHSEndspan

5.50 hours

Docket: TEA-F-NK-20191204-1Docket Date: 4 Dec 2019

Resource Role Type WorkDate

StartTime

EndTime

Break UsageCode

Rate Code Work Reference Amount UoM

NarayananKrishnan

GeneralLabourer

Person 4 Dec2019

8:00 am 5:00 pm 1.00 Normal EngineeringManager

2: Site Tour from CTC 0.50 hours

NarayananKrishnan

GeneralLabourer

Person 4 Dec2019

8:00 am 5:00 pm 1.00 Normal EngineeringManager

4.00: Bridge Stage A - LHSEndspan

2.00 hours

NarayananKrishnan

GeneralLabourer

Person 4 Dec2019

8:00 am 5:00 pm 1.00 Normal EngineeringManager

5.00: Bridge Stage B - RHSEndspan

5.50 hours

Docket: TEA-F-RJ-20191204-1Docket Date: 4 Dec 2019

Resource Role Type WorkDate

StartTime

EndTime

Break UsageCode

Rate Code Work Reference Amount UoM

Rhys (Rhys)Janssen

GeneralLabourer

Person 4 Dec2019

8:00 am 5:00 pm 1.00 Normal GeneralLabour

2: Site Tour from CTC 0.50 hours

Rhys (Rhys)Janssen

GeneralLabourer

Person 4 Dec2019

8:00 am 5:00 pm 1.00 Normal GeneralLabour

3.00: Construction Setup 4.00 hours

Rhys (Rhys)Janssen

GeneralLabourer

Person 4 Dec2019

8:00 am 5:00 pm 1.00 Normal GeneralLabour

5.00: Bridge Stage B - RHSEndspan

3.50 hours

Docket: TEA-F-RO-20191204-1Docket Date: 4 Dec 2019

Resource Role Type Work Start End Break Usage Rate Code Work Reference Amount UoM

Site ReportConstructionarium 2019

Page 21 of 22

Page 22: 1.0 | Site Report Wednesday, 4 Dec 2019 · 1.0 | Site Report Wednesday, 4 Dec 2019 Project Details Project No: ... open Boris Tusevljak: Site tour start at 1015 Site Report Constructionarium

Company: Team 1Status: Entered

Company: Team 1Status: Entered

Company: Team 1Status: Entered

Company: Team 1Status: Entered

Date Time Time Code

RoryO'Keeffe

GeneralLabourer

Person 4 Dec2019

8:00 am 5:00 pm 1.00 Normal GeneralLabour

2: Site Tour from CTC 0.50 hours

RoryO'Keeffe

GeneralLabourer

Person 4 Dec2019

8:00 am 5:00 pm 1.00 Normal GeneralLabour

4.00: Bridge Stage A - LHSEndspan

2.00 hours

RoryO'Keeffe

GeneralLabourer

Person 4 Dec2019

8:00 am 5:00 pm 1.00 Normal GeneralLabour

5.00: Bridge Stage B - RHSEndspan

3.50 hours

RoryO'Keeffe

GeneralLabourer

Person 4 Dec2019

8:00 am 5:00 pm 1.00 Normal GeneralLabour

6.00: Bridge Stage C - MiddleSection

2.00 hours

Docket: TEA-F-SB-20191204-1Docket Date: 4 Dec 2019

Resource Role Type WorkDate

StartTime

EndTime

Break UsageCode

Rate Code Work Reference Amount UoM

ShaghayeghBalali

GeneralLabourer

Person 4 Dec2019

8:00 am 5:00 pm 1.00 Normal GeneralLabour

2: Site Tour from CTC 0.50 hours

ShaghayeghBalali

GeneralLabourer

Person 4 Dec2019

8:00 am 5:00 pm 1.00 Normal GeneralLabour

4.00: Bridge Stage A - LHSEndspan

2.00 hours

ShaghayeghBalali

GeneralLabourer

Person 4 Dec2019

8:00 am 5:00 pm 1.00 Normal GeneralLabour

5.00: Bridge Stage B - RHSEndspan

5.50 hours

Docket: TEA-F-SB-20191204-2Docket Date: 4 Dec 2019

Resource Role Type WorkDate

StartTime

EndTime

Break UsageCode

Rate Code Work Reference Amount UoM

SaurabhBokde

GeneralLabourer

Person 4 Dec2019

8:00 am 5:00 pm 1.00 Normal Project ServicesManager

2: Site Tour from CTC 0.50 hours

SaurabhBokde

GeneralLabourer

Person 4 Dec2019

8:00 am 5:00 pm 1.00 Normal Project ServicesManager

4.00: Bridge Stage A - LHSEndspan

2.00 hours

SaurabhBokde

GeneralLabourer

Person 4 Dec2019

8:00 am 5:00 pm 1.00 Normal Project ServicesManager

5.00: Bridge Stage B - RHSEndspan

5.50 hours

Docket: TEA-F-TD-20191204-1Docket Date: 4 Dec 2019

Resource Role Type Work Date StartTime

EndTime

Break UsageCode

Rate Code Work Reference Amount UoM

Trent Day GeneralLabourer

Person 4 Dec2019

8:00 am 12:00 pm 1.00 Normal GeneralLabour

4.00: Bridge Stage A - LHSEndspan

1.00 hours

Trent Day GeneralLabourer

Person 4 Dec2019

8:00 am 12:00 pm 1.00 Normal GeneralLabour

5.00: Bridge Stage B - RHSEndspan

2.00 hours

Docket: TEA-F-TM-20191204-1Docket Date: 4 Dec 2019

Resource Role Type WorkDate

StartTime

EndTime

Break UsageCode

Rate Code Work Reference Amount UoM

Theja Dilshan WijesingheMinigammana Vidanelage

GeneralLabourer

Person 4 Dec2019

8:00am

5:00pm

1.00 Normal GeneralLabour

2.00: Procurement 0.50 hours

Theja Dilshan WijesingheMinigammana Vidanelage

GeneralLabourer

Person 4 Dec2019

8:00am

5:00pm

1.00 Normal GeneralLabour

4.00: Bridge Stage A -LHS Endspan

2.00 hours

Theja Dilshan WijesingheMinigammana Vidanelage

GeneralLabourer

Person 4 Dec2019

8:00am

5:00pm

1.00 Normal GeneralLabour

5.00: Bridge Stage B -RHS Endspan

5.50 hours

Site ReportConstructionarium 2019

Page 22 of 22