8/12/2019 1 - Tutorial Criação Goose ABB
http://slidepdf.com/reader/full/1-tutorial-criacao-goose-abb 1/13
SA.T. Training Product Integration REC670 2007-01-15 Page 1
ABB Power Technologies AB
Västerås - Sweden REC670 Product Integration Training
Substation Automation & ProtectionTraining
• Start CCT tool and create a new project:
• Give a “Project name” and browse for the folder
• Import into CCT the exported SCL-file from PCM
8/12/2019 1 - Tutorial Criação Goose ABB
http://slidepdf.com/reader/full/1-tutorial-criacao-goose-abb 2/13
SA.T. Training Product Integration REC670 2007-01-15 Page 2
ABB Power Technologies AB
Västerås - Sweden REC670 Product Integration Training
Substation Automation & ProtectionTraining
• The structure of your project shown by CCT should look like this
8/12/2019 1 - Tutorial Criação Goose ABB
http://slidepdf.com/reader/full/1-tutorial-criacao-goose-abb 3/13
SA.T. Training Product Integration REC670 2007-01-15 Page 3
ABB Power Technologies AB
Västerås - Sweden REC670 Product Integration Training
Substation Automation & ProtectionTraining
Data Set Engineering
• Navigate your “REC670” object down to LD0/LLN0 level:
• Add a new data set into LLN0 and rename it to “GOOSE”.
8/12/2019 1 - Tutorial Criação Goose ABB
http://slidepdf.com/reader/full/1-tutorial-criacao-goose-abb 4/13
SA.T. Training Product Integration REC670 2007-01-15 Page 4
ABB Power Technologies AB
Västerås - Sweden REC670 Product Integration Training
Substation Automation & ProtectionTraining
• Click/select on ”GOOSE” dataset. Under “IED Data Model” browse and select thesignals you want to add :
-reservation request:
-acknow. the reservation request
8/12/2019 1 - Tutorial Criação Goose ABB
http://slidepdf.com/reader/full/1-tutorial-criacao-goose-abb 5/13
SA.T. Training Product Integration REC670 2007-01-15 Page 5
ABB Power Technologies AB
Västerås - Sweden REC670 Product Integration Training
Substation Automation & ProtectionTraining
-apparatus position
QB1+QB2
QB2
QB1
8/12/2019 1 - Tutorial Criação Goose ABB
http://slidepdf.com/reader/full/1-tutorial-criacao-goose-abb 6/13
SA.T. Training Product Integration REC670 2007-01-15 Page 6
ABB Power Technologies AB
Västerås - Sweden REC670 Product Integration Training
Substation Automation & ProtectionTraining
• The complete GOOSE dataset for Line bay should look like this:
• Create GOOSE dataset for Bus Coupler bay.
• Add resp. signals from ”IED Data Model” :
8/12/2019 1 - Tutorial Criação Goose ABB
http://slidepdf.com/reader/full/1-tutorial-criacao-goose-abb 7/13
SA.T. Training Product Integration REC670 2007-01-15 Page 7
ABB Power Technologies AB
Västerås - Sweden REC670 Product Integration Training
Substation Automation & ProtectionTraining
GOOSE Control Engineering
• Define a GOOSE control block and insert your dataset.(have remain on the same level in the project structure)
• Click on Goose Control Engineering and then on GSE Control
• Associate your GOOSE dataset to this NewGSEControl:
8/12/2019 1 - Tutorial Criação Goose ABB
http://slidepdf.com/reader/full/1-tutorial-criacao-goose-abb 8/13
SA.T. Training Product Integration REC670 2007-01-15 Page 8
ABB Power Technologies AB
Västerås - Sweden REC670 Product Integration Training
Substation Automation & ProtectionTraining
• Click on and then define the MAC Address of your GOOSE message:
• Save
• Do the same procedure for BusCouplers IED.:
• Define a new MAC Address of your GOOSE message:
• Save
• Drag and drop the REC670 (client-IED) to REC670_BC (sending-IED) Goose ControlEngineerings window .
8/12/2019 1 - Tutorial Criação Goose ABB
http://slidepdf.com/reader/full/1-tutorial-criacao-goose-abb 9/13
SA.T. Training Product Integration REC670 2007-01-15 Page 9
ABB Power Technologies AB
Västerås - Sweden REC670 Product Integration Training
Substation Automation & ProtectionTraining
• You can now see the REC670 (client-IED) in the structure
• Update the data flow you just created and Save.
• You can now see the “Inputs” for REC670 (client-IED):
• Do the same procedure for Line Bay IED. Drag and drop the REC670_BC (client-IED)to REC670 Goose Control Engineerings window .
8/12/2019 1 - Tutorial Criação Goose ABB
http://slidepdf.com/reader/full/1-tutorial-criacao-goose-abb 10/13
SA.T. Training Product Integration REC670 2007-01-15 Page 10
ABB Power Technologies AB
Västerås - Sweden REC670 Product Integration Training
Substation Automation & ProtectionTraining
• Update the data flow. Save
• Verify that you can see the “Inputs” under REC670_BC
• Export SCD file from CCT, now containing the GOOSE part.
• Import SCD file to PCM600.
8/12/2019 1 - Tutorial Criação Goose ABB
http://slidepdf.com/reader/full/1-tutorial-criacao-goose-abb 11/13
SA.T. Training Product Integration REC670 2007-01-15 Page 11
ABB Power Technologies AB
Västerås - Sweden REC670 Product Integration Training
Substation Automation & ProtectionTraining
• Start SMT, do the connection both Line bay REC670………
…….and BusCoupler REC670_BC:
• Save.
• Close SMT.
8/12/2019 1 - Tutorial Criação Goose ABB
http://slidepdf.com/reader/full/1-tutorial-criacao-goose-abb 12/13
SA.T. REC670 Product Integration Training Course
2007-01-16 Page 12
ABB Power Technologies AB
Västerås - Sweden REC670 Product Integration Training
Substation Automation & ProtectionTraining
• Start PST. You need to activate IEC61850 communication and GOOSE messaging.
Settings for REC670:
Settings for REC670_BC:
8/12/2019 1 - Tutorial Criação Goose ABB
http://slidepdf.com/reader/full/1-tutorial-criacao-goose-abb 13/13
SA.T. REC670 Product Integration Training Course
2007-01-16 Page 13
ABB Power Technologies AB
Västerås - Sweden REC670 Product Integration Training
Substation Automation & ProtectionTraining
• Save and close PST.
• Download to IEDs1. CAP-configuration2. PST (settings)3. SMT4. GDE (If necessary)
• Verify that horizontal communication (GOOSE) is working.