Conceptualizing, Planning and Executing a Post-course Project
1 © The Delos Partnership 2004 Project Management Executing the Project.
-
Upload
austin-blair -
Category
Documents
-
view
216 -
download
0
Transcript of 1 © The Delos Partnership 2004 Project Management Executing the Project.
1 © The Delos Partnership 2004
Project ManagementProject Management
Executing the Project
2 © The Delos Partnership 2004
Executing The ProjectExecuting The Project
At the end of this session you will have an understanding of the following:-
• Status Reporting
• Issue Management
• Technical Change Management
• Knowledge Management
• Project Mgrs Responsibilities
3 © The Delos Partnership 2004
PMI® Executing ProcessesPMI® Executing Processes
4.2 4.2 Project PlanProject PlanExecutionExecution
4.2 4.2 Project PlanProject PlanExecutionExecution
N.B. All numbering refers to the PMI® Project Management Body of Knowledge (PMBOK) Knowledge Areas
4 © The Delos Partnership 200421/04/23
Work Authorisation to Perform activities in plan
For all issues, complete an issue report, including:
Issue description Project impact Proposed resolution
Develop mitigating approach and contingency plan for risks
Review and approve resolution Assess change Develop team skills / knowledge Communicate for commitment Manage 3rd party relationships Manage Knowledge
Input OutputProcess
Maintained Project Work plan
Work Results
Status
Reports
Change
Requests
Issues
Risks
Changes
Project Plan ExecutionProject Plan Execution
© The Delos Partnership 200421/04/23
Status ReportingStatus Reporting
Communicate status and expectations to the Programme/ Project Office and therefore Management
• Inform team members and other Project Managers
• Communicate changes, issues, variances• Facilitate coordination across the programme• Share good news (as well as bad)• Demonstrate that you are in control
Why report project status?
© The Delos Partnership 200421/04/23
Syn
thes
ise
IssuesIssues
Progress AchievedProgress Achieved
RisksRisks
Activities Planned
Activities Planned
Status ReportStatus Report
Make reports comprehensiveStatus Reporting (contd)Status Reporting (contd)
Time / EffortTime / Effort
7 © The Delos Partnership 200421/04/23
Report Project StatusReport Project StatusGuiding PrinciplesGuiding Principles• Be careful what you ask for -- if you are only
concerned with task starts and completions, you will very likely get tasks that start and finish on time… but possibly at the expense of quality.
• If you ask for information, use it.
• Make sure your reporting periods are realistic.
• Be creative in designing your reports.
• Make use of exception reporting.
8 © The Delos Partnership 2004
An ISSUE is anything that is CURRENTLY or will SHORTLY affect the progress of a project or its ability to produce its stated deliverables, and about which no agreement has yet been reached.
As the Project Manager you own the issues and must address them early and drive them to resolution
Issue ManagementIssue Management
For example:• Limited availability of resources• Problems with technology• Ambiguous business requirements
© The Delos Partnership 200421/04/23
Issue Management (contd)Issue Management (contd)
• Are issues being raised?• Are the issues raised being rated appropriately?• Are issues being assigned to appropriate people for
resolution?• Do all accepted issues have a reasonable resolution
due date?• Are any resolution due dates about to be missed?• Are there any concerns with implementing the
approved resolutions?• Are there any issues you need to raise now before they
become a change request?
10 © The Delos Partnership 2004
Knowledge should be centrally managedA repository should be developed for all the information gathered and produced over the life of the programme. Its purpose is to ensure that all information is:
• Readily accessible;• Consistently presented;• Protected from damage or loss;• Coordinated and reused;
• Status Reports• Correspondence• Budgets• Deliverables• Project Plans• Project Charters• Working Papers• Contracts• Timesheets• Expense Records
Knowledge ManagementKnowledge Management
11 © The Delos Partnership 2004
What are we trying to avoid?
• Lost Information• Duplicated Information• Inconsistent Information• Wasted Effort• Lost Time
Knowledge ManagementKnowledge Management
12 © The Delos Partnership 2004
Manage changes to:
Technical Technical Change ManagementChange Management
Scope: more; less; different
Time: elapsed; actual effort
Approach: sign-off/consultation; prototype/big bang
Resource: team size; skill set
Cost: budget
13 © The Delos Partnership 200421/04/23
Technical Technical Change ManagementChange Management• Complete change request form
– Description of proposed change– Benefits of change– Implications of not making the change
• Log change request• Assign change request and due date• Investigate request and determine resolution• Review resolution• Approve resolution• Update budget, scope and work plan• Communicate
14 © The Delos Partnership 200421/04/23
Assess ChangeAssess ChangeGuiding PrinciplesGuiding Principles• Shift happens - the project world is
dynamic
• Set a tolerance level - determine the amount of change you can safely accept without formal user approval.
• When you exceed your tolerance level, use the formal change request process
• Manage expectations as well as scope.
15 © The Delos Partnership 2004
Periodically (weekly) assess and report the following project status:– Schedule -- planned, current & forecast;– Budget -- planned, current & forecast;– Issues -- number, progress & age;– Risk -- severity, likelihood & strategy;– Deliverable -- completeness, quality;– Change Request -- number, progress,
impact
Executing the ProjectExecuting the ProjectKey Project Manager ActivitiesKey Project Manager Activities
16 © The Delos Partnership 2004
• Identify variations in agreed project scope
(deliverable, functional, organisational, etc)
• Analyse impact on project schedule, resource
requirements and budget;
• Revise project schedule, budget and resource
plan if change accepted;
Executing the ProjectExecuting the ProjectKey Project Manager ActivitiesKey Project Manager Activities
17 © The Delos Partnership 2004
The PMI® Project The PMI® Project Management Life CycleManagement Life Cycle
InitiatingProcesses
InitiatingProcesses
PlanningProcesses
PlanningProcesses
ControllingProcesses
ControllingProcesses
ClosingProcesses
ClosingProcesses
ExecutingProcesses
ExecutingProcesses