1 TenStep Project Management Process ™ PM00.7 PM00.7 Project Management Preparation for Success *...
-
Upload
jack-mckinney -
Category
Documents
-
view
229 -
download
1
Transcript of 1 TenStep Project Management Process ™ PM00.7 PM00.7 Project Management Preparation for Success *...
1TenStep Project Management Process™
PM00.7
PM00.7PM00.7Project Management Preparation for Success Project Management Preparation for Success
* Manage Risk ** Manage Risk *
2TenStep Project Management Process™
PM00.7
Risk Management DefinitionRisk Management Definition
Master Sun-tzu: “So the rule of military operations is not to count on opponents not coming, but to rely on having ways of dealing with them; not count on opponents not attacking, but to rely on having what cannot be attacked”
“If you can always remember danger when you are secure, and remember chaos in time of order, watch out for danger and chaos while they are still formless, and prevent them before they happen. This is best of all”
The Art of War, 6th Century B.C. translated by Samuel B. Griffith
3TenStep Project Management Process™
PM00.7
Risk DefinitionRisk Definition
Risk is the probability of an undesirable event occurring and the significance of the consequence of that occurrence.
4TenStep Project Management Process™
PM00.7
Risk Characteristics Risk Characteristics
• A definable event that may occur in the future• A probability of occurrence (future)• A consequence of occurrence (impact + or -)
Risk is almost always associated with a loss; however, positive risk can also be viewed as an “opportunity”
5TenStep Project Management Process™
PM00.7
Opportunity Risks Opportunity Risks • A definable event• Probability of success• Benefit of Success
Question: Why should you take a risk?
Answer: To gain a reward
(This aspect of risk is not covered in this training)
6TenStep Project Management Process™
PM00.7
Is a Risk a Problem? Is a Risk a Problem?
No, a risk is not a problem…a problem is a risk whose time has come
• Problems - existing conditions and circumstances• Risk - future events and conditions
7TenStep Project Management Process™
PM00.7
What Affects Risk Perceptions?What Affects Risk Perceptions?• Control
– One can be placed at risk by oneself or another (flying vs. driving)
• Information available– Inadequate, unfamiliar, unreliable, unpredictable
• Time– The further into the future the more uncertainty, but more
time to identify risk and manage (future social security solvency)
• Some risks are small, but the consequences so dire, that it is hard to know what actions to take (space shuttle risks)
8TenStep Project Management Process™
PM00.7
Project Risk ManagementProject Risk Management
• Perception of risk needs to be fact-based
– Take control
– Use logic, not emotion
– Analyze the risks
• All projects have risks (maybe only small ones)
• Your client does not demand zero risk
9TenStep Project Management Process™
PM00.7
Risks Vs. AssumptionsRisks Vs. Assumptions(Refined from Define the Project)(Refined from Define the Project)
• A future event that may have a negative impact on the project– Risk. The combination of probability and impact are not acceptable
(too high)– Assumption. The combination of probability and impact are acceptable
• A future event that needs to occur for the success of the project– Risk. The combination of probability and impact are not acceptable
(too low)– Assumption. The combination of probability and impact are
acceptable
10TenStep Project Management Process™
PM00.7
Risk Management ApproachRisk Management Approach
Risk Management is the process of:
1. Identifying risks
2. Analyzing the risk – qualitative
3. Analyzing the risk - quantitative
4. Responding to the risk
5. Monitoring known risks and looking for new risks
11TenStep Project Management Process™
PM00.7
Risk Management ProcessRisk Management Process
1. Identify the risks - Initial risk assessment during project definition
• Project size
• Project structure
– Effect on the organization
– Staffing
• Project management experience
• Hardware and software
• Identify risks
• Analyze the risk – qualitative
• Analyze the risk - quantitative
• Risk response
• Risk control
12TenStep Project Management Process™
PM00.7
Identify the RisksIdentify the Risks
• Look for general inherent project risks
• Brainstorm additional specific risks
• Involve clients and sponsor
• Discussion of risk with client may result in their avoidance
– i.e. Multiple-site implementation is listed as a high-risk. Sponsor might agree to limit implementation to a single site
13TenStep Project Management Process™
PM00.7
Qualitative Risk AnalysisQualitative Risk Analysis
2. Analyze the risks - Qualitative
• Method for prioritizing risks to determine which should be resolved
• “Qualitative” implies some subjectivity applied
• Evaluate each risk event based on impact and likelihood
• Factor in the quality of the information you have as input
• Identify risks
• Analyze the risk – qualitative
• Analyze the risk - quantitative
• Risk response
• Risk control
14TenStep Project Management Process™
PM00.7
Qualitative Risk AnalysisQualitative Risk Analysis1. High negative impact to project / Highly likely to occur – High
2. High negative impact to project / Medium likely to occur - High
3. High negative impact to project / Not likely to occur - Medium / Low
4. Medium negative impact to project / Highly likely to occur - Medium
5. Medium negative impact to project / Medium likely to occur - Medium / Low
6. Medium negative impact to project / Not likely to occur - Low
7. Low negative impact to project / Highly likely to occur - Low
8. Low negative impact to project / Medium likely to occur - Low
9. Low negative impact to project / Not likely to occur - Low
15TenStep Project Management Process™
PM00.7
Qualitative Risk AnalysisQualitative Risk Analysis
Probability Impact
Low Medium High
Low Ignore Ignore Ignore
Medium Ignore Caution Response
High Caution Response Response
16TenStep Project Management Process™
PM00.7
Qualitative Risk AnalysisQualitative Risk Analysis
• Likelihood (example)– High .8
– Medium .5
– Low .2
• Impact (example)– High .9
– Medium .6
– Low .3
• Overall numerical risk is (Likelihood * Impact)
17TenStep Project Management Process™
PM00.7
Quantitative Risk AnalysisQuantitative Risk Analysis
3. Analyze the risks - Quantitative
• Uses more sophisticated techniques to arrive at more objective risk analysis
• Allows overall risk to be quantified in terms of cost, schedule and effort
• Helps identify projected target dates and budget based on risk
• Identify risks
• Analyze the risk – qualitative
• Analyze the risk - quantitative
• Risk response
• Risk control
18TenStep Project Management Process™
PM00.7
Quantitative Risk AnalysisQuantitative Risk Analysis
Examples• Risk surveys and interviews with a wide variety of
stakeholders• Simulations, i.e. Monte Carlo• Three point probabilities for each risk (high, medium,
and low) to come up with overall risk probability• Other more sophisticated statistical techniques
19TenStep Project Management Process™
PM00.7
Quantitative Risk AnalysisQuantitative Risk Analysis
• Cost implications can be determined for overall risk contingency budget– Risk probability is 30%, impact is $10,000. Risk
contingency is $3,000. ($10,000 * .30)
– Add overall risk contingency to the budget
• Schedule implications can be determined– Risk probability is 30%. Schedule impact is 5 days.
Schedule contingency is 1.5 days (5 days * .30)– Add overall risk contingency to schedule
20TenStep Project Management Process™
PM00.7
Risk Management ProcessRisk Management Process
4. Risk Response
• High level risks - create a plan to ensure that a risk response is in place
• Medium level risks - determine if the impact is severe enough that they should have a risk plan created
• Low level risk - see whether they should be listed as assumptions
• Move the activities associated with the risk plans to the project workplan
• Identify risks
• Analyze the risk – qualitative
• Analyze the risk - quantitative
• Risk response
• Risk control
21TenStep Project Management Process™
PM00.7
Risk responses1. Leave it
2. Monitor the risk
3. Avoid the risk
4. Move the risk
5. Mitigate the risk
Weigh the cost of the risk response against the consequences
Risk Management ProcessRisk Management Process
22TenStep Project Management Process™
PM00.7
Develop Contingent ActionsDevelop Contingent Actions• Identify actions to take if a risk actually occurs (issues
management)• Add the contingency actions to the workplan • Worst case - the project may need to be stopped• Example
– Risk - hardware may not be available in time at a remote pilot test site
– Contingent action - hold the pilot test in a site that already has the hardware
23TenStep Project Management Process™
PM00.7
Risk Management ProcessRisk Management Process
5. Risk Control• Monitor the risk plans to ensure
they are being executed successfully
• Assess risks at the end of each major stage / milestone, or on a scheduled basis
• Identify risks
• Analyze the risk – qualitative
• Analyze the risk - quantitative
• Risk response
• Risk control
24TenStep Project Management Process™
PM00.7
Poor Alternatives to Risk ManagementPoor Alternatives to Risk Management• Add unjustified padding to your estimates • Prepare ahead of time for whom to blame if things go
wrong • Be prepared to beg forgiveness by stating you were too
busy focusing on delivering results to worry about future events
• Discuss how you are not a fortune teller, and that the risk could not be foreseen
• Act casual and say that 'risk happens' - there is nothing you can do about it
• Eliminate other project management or team infrastructure items to make up for having to solve the problems when they arise
25TenStep Project Management Process™
PM00.7
Risk Management ToolsRisk Management Tools• Risk Management Plan
• Risk Factors
• Risk Strategies
• Project Definition
– Project risks
26TenStep Project Management Process™
PM00.7
Case Study #10 - Risk ManagementCase Study #10 - Risk Management• Review the case study project
• Identify four project risks
• Prepare risk management plan and contingency actions for two of the identified risks
27TenStep Project Management Process™
PM00.7
Manage the ProjectManage the Project
Manage workplan
Manage issues
Manage scope
Manage communication
Manage risk
• Manage documentation
• Manage quality
• Manage metrics
28TenStep Project Management Process™
PM00.7
Learning ObjectivesLearning Objectives
By the end of class, each participant should be able to:Understand the value of project management processesReview the various aspects of defining a projectBuild and maintain an appropriate project workplan Identify and manage issues, scope and communication Identify and manage project risks• Determine methods to manage project documentation• Identify and manage to the appropriate level of quality• Identify metrics to improve processes and declare success