Punj Lloyd Limited
Safety Tool Box Tal k/ Training Reco rd
Date of Talk Time
Engineer / Supervisor Activity
TOPICS: CUTTING AND WELDING (FIRE PREVENTION)
1. Fire kills over thousands of people every year and injuries many more; it destroys jobs
and property and costs millions of rupees in the payment of insurance claims.
2. The practical steps, which you can take to prevent fire, are a cost effective investment,
which may bring great benefits. The large majority of fire can be prevented by taking
simple precaution and by adopting safe working practice.
3. Every fire no matter how large the end result starts from a small beginning, but certain
fundamentals are common to every incident.
4. Remember 3 factors are necessary for a fire (a) Heat (b) Oxygen (c) Fuel, if one factor
is isolated or removed fire will be extinguished.
5. So to avoid unplanned fire in Gas Cutting activities,
Keep all gas cylinders vertical and chained.
Wet cloth should be placed upon the DA cylinder.
Every cylinder must be equipped with a flash back arrestor.
Check all hose, hose connection, regulator and cutting torch before starting ofwork, use only hose clamp.
Color code of Gas Cylinders and Hoses to be known to all (Refer
attached sheet for color code)
In no case the hoses to be interchanged.
The key should always be near cylinder
Check that dry grass is not nearby
6. For welding activity
Check all electrical connection,
Use proper industrial plug
Generator is earthed properly (Copper cable with brass pin which is requiredto be inserted in soil, the soil is required to be made wet using water)
Welding cable is insulated properly
Ensure that holders are having insulation on electrode holder, Proper earthing to the job (not loose, it should not be of broken file but
preferably of same material as that of job),
Working area must be free from combustible material, proper cable
management, no power cable or gas hose should be coiled with welding
cables, hot electrode piece must not be thrown here and there.
In pay welder no leaked diesel / oil is collected
Notes:
Maximum time of talk is 15 minutes Persons attending write / sign their names on the rear side of sheet / attached
sheet.
-
7/27/2019 1 TBT Gas Cylinder-1
2/6
Punj Lloyd Limited
Safety Tool Box Tal k/ Training Reco rd
Date of Talk Time
Personalize toolbox talk, Check feedback, show picture, activity, equipment
etc. to improve understanding.
It should preferably cover one subject
Hosecolor is notcorrectItshouldbeOrange, Noclampused
-
7/27/2019 1 TBT Gas Cylinder-1
3/6
Punj Lloyd Limited
Safety Tool Box Tal k/ Training Reco rd
Date of Talk Time
No cylinder caps,Storage areanotdefined
-
7/27/2019 1 TBT Gas Cylinder-1
4/6
InstallationofFlashBackArrestor
Punj Lloyd Limited
Safety Tool Box Tal k/ Training Reco rd
Date of Talk Time
Hoses are Cracked
-
7/27/2019 1 TBT Gas Cylinder-1
5/6
Hoses are Cracked
Punj Lloyd Limited
Safety Tool Box Tal k/ Training Reco rd
Date of Talk Time
-
7/27/2019 1 TBT Gas Cylinder-1
6/6
Punj Lloyd Limited
Safety Tool Box Tal k/ Training Reco rd
Date of Talk Time