1State of NC Internal Use Only – Do Not Distribute
Project Portfolio Management
Monthly Status Report Training
2State of NC Internal Use Only – Do Not Distribute
Course Agenda
1: Introduction
2: Process Flow
3: First Status Report Requirements
4: Entering Indicator Comments
5: PPM Tab Information
6: Alert Subscriptions
7: Supporting Documents
3State of NC Internal Use Only – Do Not Distribute
Prerequisites For Class
1. User has been to PPM New User Training Class
OR
2. They are an experienced PPM user
4State of NC Internal Use Only – Do Not Distribute
IntroductionOverall Information
Status Reporting Requirements:• Projects over $500K (total investment/total life cycle costs),
must submit monthly status reports to EPMO QA staff• Projects that are part of a Program (even if they are under
$500K) must submit monthly status reports to the EPMO QA
5State of NC Internal Use Only – Do Not Distribute
IntroductionOverall Information
Editable Tabs: Risk Assessment Tab Schedule Tab Status Tab Cost Tracking Tab Issues and Risk Management tab Document Management tab
Read-Only Tabs: Project Information Tab Benefit Estimates Tab Budget Cost Tab Strategic Impact Tab Budget Resource Tab Resource Tracking Tab
• Status Reports are primarily focused on the current phase of a project• Status Reports can be completed and assessed while projects are in Gate Approval
Tab Status For Gate Approval
6State of NC Internal Use Only – Do Not Distribute
Monthly Status Reporting
Process Flow Overview
7State of NC Internal Use Only – Do Not Distribute
Monthly Status ReportingProcess Flow
Begins with Project Status Report Step attribute This should be your first stop every month when starting to enter
information for a Status Report
This attribute controls the notifications PPM sends about Status Reports
8State of NC Internal Use Only – Do Not Distribute
Monthly Status ReportingProcess Flow
Step 1
Project manager (PM) sets the Project Status Report Step attribute to “Preliminary”
PM updates the project’s status information (see later slides for details on how to update)
Step 2
PM sets Project Status Report Step to “Agency Review”
Project status reviewed within agency
This step is agency specific. In some agencies, management may review the status before having the PM send it to the EPMO QA staff, in other agencies, the agency PMO office may review it before it is sent to the EPMO QA staff.
9State of NC Internal Use Only – Do Not Distribute
Step 3By Friday of the week of the 15th of each month, all project status reports must be completed by the PM and ready for EPMO QA staff reviewPMO/PM sets Project Status Report Step to “QA Review”Step 4EPMO QA staff does their assessment Sets the indicators for the project and add indicator comments
appropriately
Add issues to the “Issues and Risks” tab (with Source = “EPMO”) if appropriate.
Reviews the agency updates to the issues that they previously enteredEPMO QA staff runs the Project Status report and saves the PDF output.EPMO QA staff does the snapshot for that month, preserving the status, and the project in the tool is ready for next month’s inputEPMO QA staff sets the Project Status Report Step to "QA Project Assessment Finalized"
Monthly Status ReportingProcess Flow
10State of NC Internal Use Only – Do Not Distribute
• If your project was classified as ‘Needs Attention’ last month, this month’s assessment can not be completed without a corrective action plan
• Status Report Due Dates
http://www.epmo.scio.nc.gov/Process/_pdf/STATDUEDATES09.pdf
Monthly Status ReportingProcess Flow - Notes
11State of NC Internal Use Only – Do Not Distribute
Monthly Status ReportingOpening Project
12State of NC Internal Use Only – Do Not Distribute
Monthly Status ReportingVerify Correct Month
Verify you are in the correct month’s “snapshot”
Note: This should be set to the month that just ended (If your status report is due January 18, 2008, the snapshot should say “December 2007”)
If the snapshot report says ‘Current Snapshot’ no snapshot has been completed for this project, additional steps will be required
13State of NC Internal Use Only – Do Not Distribute
Monthly Status ReportingStatus Tab
Set Project Status Report Step attribute to “Preliminary” This field lets anyone who looks at your project in the interim know that you are in
the process of entering your status for the month and the numbers may be a combination of last months numbers and this months number
This should be the first thing you do every month when starting to enter information for a Status Report
14State of NC Internal Use Only – Do Not Distribute
Monthly Status Reporting
First Status Report
15State of NC Internal Use Only – Do Not Distribute
Has a Snapshot been done for this project before?
Open the project
Look under ‘Snapshot Reports’ on the Project Info tab
If it says “Current Snapshot” no snapshot has been done for this project
You are doing your first status report
Monthly Status ReportingFirst Status Report – Project Info Tab
Note: First snapshot will be for the month of the Start Date of the project on the Project Info tab
First report will be due 30 days after P&D approval by the State CIO
16State of NC Internal Use Only – Do Not Distribute
• Move budget from Level 1 to Level 4 for months you are in Initiation and Planning & Design
Necessary to allow PPM tool to determine your “Initiation” and “Planning & Design” budget costs accurately on the Cost Tracking tab (necessary for Monthly Status Report)
• Total amount of the Initiation phase budget must match the “Initiation Phase Budget” attribute on the Project Info tab• Total amount of the Planning & Design phase budget must match the “Planning & Design Phase Budget” attribute on the Project Info tab
Monthly Status ReportingFirst Status Report – Budget Cost Tab
17State of NC Internal Use Only – Do Not Distribute
Monthly Status ReportingFirst Status Report – Budget Cost Tab
• After going through Gate 1 project granularity changes from Fiscal Year to Monthly• Yearly values are divided by the number of months in that fiscal year (may not always be 12 in the first and/or last years)
18State of NC Internal Use Only – Do Not Distribute
Monthly Status ReportingFirst Status Report – Budget Cost Tab
19State of NC Internal Use Only – Do Not Distribute
Monthly Status ReportingFirst Status Report – Budget Cost Tab
The ‘Planning and Design Phase Budget’ is the amount that was approved to be spent in Planning & Design by State CIO
20State of NC Internal Use Only – Do Not Distribute
Monthly Status Reporting First Status Report – Cost Forecast Tab
• After going through Gate 1 dollars from Budget Cost tab are also copied to the Cost Forecast tab at Level 1.
• Will need to redistribute dollars to match Level 4 dollars from the Budget Cost tab
21State of NC Internal Use Only – Do Not Distribute
Monthly Status ReportingFirst Status Report – Cost Forecast Tab
22State of NC Internal Use Only – Do Not Distribute
• Cost Forecast breakdown should match the Budget Cost breakdown before doing the first Status Report
• The Cost Forecast totals should match the Total Approved Phase Budget for P&D
• After setting the Project’s Forecast you will need to manage the forecast on a month to month basis
• After the first Status Report the numbers on the Budget Cost tab will not necessarily match the Cost Forecast
Do Not update the Budget Cost numbers, just manage the Cost Forecast numbers
Monthly Status ReportingFirst Status Report – Cost Forecast Tab
23State of NC Internal Use Only – Do Not Distribute
Enter the Initiation hours spent on the project in the ‘Phase Actual Hours’ field under the Initiation Phase Cost section
Monthly Status ReportingFirst Status Report – Status Tab
24State of NC Internal Use Only – Do Not Distribute
Monthly Status ReportingFirst Status Report – Status Tab
Enter the Total Approved Phase Hours and Dollars
Note: The “Total Approved Phase Budget Dollars will need to be updated anytime a Change Request is approved
25State of NC Internal Use Only – Do Not Distribute
• Add the “Workflow” phases to the project (depending on the type of project, you may also need the SDLC phases)• Add/Validate the Planning & Design phase milestones and key deliverables
It is acceptable to not have milestones when an RFP is in the waiting phase; BUT at this time you should not have spent ANY HOURS on the project
Monthly Status ReportingFirst Status Report – Schedule Tab
26State of NC Internal Use Only – Do Not Distribute
Monthly Status Reporting
Entering Indicator Comments
27State of NC Internal Use Only – Do Not Distribute
Monthly Status ReportingEntering Indicator Comments - Notes
• If you have variances or other information that you would like to explain in more detail, use the “Indicator Comments” fields associated with the various Indicators (the “Jellybeans”)
Precede your comments with your initials and the date Pick the appropriate indicator that your issue or variance refers to
• Your comments will be read by the EPMO QA group before they do this month’s assessment• EPMO QA staff will add their comments after doing the assessment• EPMO QA staff will enter a comment for every Jelly bean every month• You can delete your comments but DO NOT delete EPMO comments
28State of NC Internal Use Only – Do Not Distribute
Monthly Status ReportingEntering Indicator Comments
After selecting the appropriate Jelly Bean a separate window will pop up
1
2Character limit is 3800 on ‘Indicator Comment’ field. If you go over, attach a document to Document Management tab
29State of NC Internal Use Only – Do Not Distribute
Monthly Status Reporting
1: Introduction
2: Process Flow
3: First Status Report Requirements
4: Entering Indicator Comments
5: PPM Tab Information
6: Alert Subscriptions
7: Supporting Documents
30State of NC Internal Use Only – Do Not Distribute
Monthly Status Reporting
Project Info Tab
31State of NC Internal Use Only – Do Not Distribute
Monthly Status ReportingProject Info Tab
Verify that the “Start Date” and “End Date” are aligned with the forecast dates on the “Schedule” tabVerify that the “Benefits Start” date is correct
If the End Date of the project moves out make sure to change the Benefits Start Date
32State of NC Internal Use Only – Do Not Distribute
Verify “Deliverables” responses in Agency Document Checklist section
Ensure that responses are consistent with the project type Ex – “COTS procurement” project type must have “Hardware and
Software Procurement Plan = YES” Depending on the project type EPMO QA may need to see any deliverables
the project said it will be producing
Monthly Status ReportingProject Info Tab
33State of NC Internal Use Only – Do Not Distribute
Verify the “Enterprise Architecture Questionnaire” is completed and current
Monthly Status ReportingProject Info Tab
Answer to this question should map to the response to Question ‘05-04 Implementation Approach’ on the Risk tab
34State of NC Internal Use Only – Do Not Distribute
• EPMO QA will check to see if the PM interview has been completed• EPMO QA will also check the status of the System Design Document• The System Design document should be attached in the document management tab
Monthly Status ReportingProject Info Tab
35State of NC Internal Use Only – Do Not Distribute
Monthly Status Reporting
Risk Tab
36State of NC Internal Use Only – Do Not Distribute
Verify answers and update if appropriate
Monthly Status ReportingRisk Tab
37State of NC Internal Use Only – Do Not Distribute
• Question ’02-01 Project Funding’ determines the assignment of the ‘Project Funding (TCO)’ Jelly Bean
Full Funding = Green Partial Funding = Yellow No Funding = Red
• EPMO QA looks at answers to all Risk questions• Goal of tab is NOT to have low score, goal is to find out where project risk’s exist• If you have a ‘High’ risk project mitigation plans should be in place• High risk items should be addressed as a Risk on the Issues and Risk tab. High Risk Examples:
Greater than 10 FTEs at different locations Project length is greater than 1 year
• Risk tab should be the high level introduction to the RAMP document (available on EPMO website & Help section of PPM)
Monthly Status ReportingRisk Tab - Notes
38State of NC Internal Use Only – Do Not Distribute
Monthly Status Reporting
Cost Tracking/Cost Forecast Tab
39State of NC Internal Use Only – Do Not Distribute
Monthly Status ReportingCost Tracking Tab – Entering Actual Costs
If costs are not entered at Level 4 assessment will NOT be completed!
Project Status Report Step will be reset to ‘Preliminary’
40State of NC Internal Use Only – Do Not Distribute
Monthly Status ReportingCost Forecast Tab
Note: Current Month and all previous months on Cost Forecast tab are Read Only
After Actual Costs are entered on Cost Tracking the dollar amount will replace the Forecast for that month
41State of NC Internal Use Only – Do Not Distribute
Monthly Status ReportingCost Forecast Tab
42State of NC Internal Use Only – Do Not Distribute
• Remaining Monthly Forecast will be used to calculate Estimate to Complete on Status Tab
• Forecast dollars are replaced with the actual dollars reported for the month
Therefore, forecast dollars for future months must be managed! Make adjustments for future months to account for late or early starts to
tasks
• Remember only the Current Phase budget is assessed Phase budget is assessed based on the budget reported on the “Cost
Tracking” tab in the Revised Budget TC column for current phase
• Total Phase Cost on Forecast tab should equal the Revised Budget TC for the phase
• If using the ‘Project Staff Hours Worksheet’ monthly total hours can be copied from current month totals
Project Staff Hours Worksheet can be found in the NC Help Section of the PPM Tool. It is called ‘Staffing Plan’
Monthly Status ReportingCost Tracking/Forecast Tab - Hints
43State of NC Internal Use Only – Do Not Distribute
Monthly Status ReportingCost Tracking/Forecast Tab Examples
Managing Forecast Cost –Example 1 - Actual Costs Less Than Forecast CostsCost Forecast for Current and the Future Months
44State of NC Internal Use Only – Do Not Distribute
Actual Cost is Different Than Forecast
Totals are then copied to Cost Forecast Tab
Monthly Status ReportingCost Tracking/Forecast Tab Examples
45State of NC Internal Use Only – Do Not Distribute
Total Forecast for the Phase is now $90,000 less
Question to Ask Yourself is: Did we get all the work done as planned? If ‘Yes’ put a note in the ‘Project Staff Utilization’ indicator explaining this If ‘No’ - Cost Forecast for future months needs to be adjusted accordingly
Monthly Status ReportingCost Tracking/Forecast Tab Examples
46State of NC Internal Use Only – Do Not Distribute
Need to Adjust Forecast accordingly
Monthly Status ReportingCost Tracking/Forecast Tab Examples
Future months forecast should equal ETC from the Status tab
47State of NC Internal Use Only – Do Not Distribute
Managing Forecast Costs –
Example 2 - Actual Costs Greater Than Forecast Costs
Monthly Status ReportingCost Tracking/Forecast Tab Examples
48State of NC Internal Use Only – Do Not Distribute
Monthly Status ReportingCost Tracking/Forecast Tab Examples
Actual Cost is Different Than Forecast
Totals are then copied to Cost Forecast Tab
49State of NC Internal Use Only – Do Not Distribute
Monthly Status ReportingCost Tracking/Forecast Tab Examples
Total Forecast cost for the Phase is now $29,000 greater
Question to Ask Yourself is: Did we get more work done (early start) OR is the work costing more
than expected?
50State of NC Internal Use Only – Do Not Distribute
If the project team got more work done than expected this month, decease the dollars for future months
Monthly Status ReportingCost Tracking/Forecast Tab Examples
If the total cost for the phase is now expected to increase, an approved Change Request is required for the extra dollars.
51State of NC Internal Use Only – Do Not Distribute
Monthly Status Reporting
Status Tab
52State of NC Internal Use Only – Do Not Distribute
• Update Hours and Dollars
Monthly Status ReportingStatus Tab – Hours and Dollars
• Note: If this is the first status report in a new phase and the last phase is complete, don’t forget to zero (0) out the monthly (NOT “To Date”) hours for actual and planned from the Preceding Phase.
53State of NC Internal Use Only – Do Not Distribute
Calculations for Status Tab Hours
Monthly Status ReportingStatus Tab – Hours and Dollars
• Staffing Plan should match Phase Month and Phase to Date hours• EPMO QA looks at Staffing Plan every month
54State of NC Internal Use Only – Do Not Distribute
When doing your last Status Report in Implementation (last Status Report for whole project) enter the ‘Phase Projected Hours’ for the Project Closeout Phase
Monthly Status ReportingStatus Tab – Hours and Dollars
55State of NC Internal Use Only – Do Not Distribute
Schedule tab – Status tab Check
Monthly Status ReportingStatus Tab – Hours and Dollars
56State of NC Internal Use Only – Do Not Distribute
Update “Business Functional Requirements” section The number of requirements should be in sync with the Project Goals and Objectives (on
Project Info tab) They should also match the number of requirements in the Business Requirements
document If the question “Will all Requirements be Delivered” is ‘Yes’ then Project Scope jellybean
will be Green; However if you have 0 (zero) requirements you will get a Yellow jellybean for the first month and a Red jellybean for all future months that the requirements are undefined
Monthly Status ReportingStatus Tab – Business Functional Requirements
57State of NC Internal Use Only – Do Not Distribute
Monthly Status ReportingStatus Tab – Plans and Accomplishments
• Update “Accomplishments this Period” Ensure “Plans for Next Period” in last month’s status report are addressed in
the current month’s report
If you did not achieve a plan from last month’s status report DO NOT delete it; just leave it in the “Plans for Next Period” AND change the Forecast Date for the corresponding Milestone
• Update “Plans for Next Period”• ITS QA will check to see if Accomplishments are in line with Milestones and Key Project Deliverables for the month
58State of NC Internal Use Only – Do Not Distribute
• If you have variances or other information that you would like to explain in more detail, use the “Indicator Comments” fields associated with the various Indicators (the “Jellybeans”)
Precede your comments with your initials and the date Pick the appropriate indicator that your issue or variance refers to
• Your comments will be read by the EPMO QA group before they do this month’s assessment
• EPMO QA staff will add their comments after doing the assessment
• If Total Phase Estimated Hours equal Phase to Date Actual Hours then the phase should be complete (Estimate to Complete Phase Hours should be zero)
• Accomplishments are things that were completed for the month
• Accomplishments and Plans for Next Month should directly relate to Milestones and Key Project Deliverables on Schedule tab
• ETC (Status Tab) + Phase Actual Cost TC (Cost Tracking tab) = Total Cost for Phase
Monthly Status ReportingStatus Tab - Notes
59State of NC Internal Use Only – Do Not Distribute
Monthly Status Reporting
Schedule Tab
60State of NC Internal Use Only – Do Not Distribute
Monthly Status ReportingSchedule Tab - Phases
Note: If you are extending the length of a phase an Agency approved change request should be attached to the project
61State of NC Internal Use Only – Do Not Distribute
• Check Milestones and Key Deliverables, if any have completed this month but the date is different modify the Forecast Date
• If necessary add any additional Milestones/Key Deliverables
Monthly Status ReportingSchedule Tab – Milestones and Key Deliverables
• If a change request has extended the length of a phase make sure to move out the date of any necessary milestones • Milestones should relate to accomplishments for this period• Milestones should be in sync with the current workflow phase
62State of NC Internal Use Only – Do Not Distribute
• Ensure that you update the “Actual % Complete” for the overall project & the current phase• Project “Actual End Date” is equal to the “Planned End Date” for the last phase of the project (latest Phase Planned End Date)• Ensure that “Milestones and Key Project Deliverables” and “Phases” are updated either manually or via MS Project• Do Not update phase end dates without an Agency Approved Change Request• Don’t be afraid to modify the Forecast date for milestones
Monthly Status ReportingSchedule Tab – Hints
63State of NC Internal Use Only – Do Not Distribute
Monthly Status Reporting
Issues and Risks Tab
64State of NC Internal Use Only – Do Not Distribute
Any Issues/Risk listed as ‘Not Completed’ requires a response to address the respective Issue or Risk
Monthly Status ReportingIssues and Risks Tab – Editing New Issues
65State of NC Internal Use Only – Do Not Distribute
Monthly Status ReportingIssues and Risks Tab – Editing New Issues
66State of NC Internal Use Only – Do Not Distribute
• Issues/Risks should not be closed until resolution is complete
• A ‘State’ of Closed will prevent any additional entries or modifications to that particular Issue or Risk
• Ensure that all open issues/risks have a “Due Date”, “Resolution Description” and “Owner of Issue/Risk” assigned
• Ensure that the status of all updated issues and risks are approved by agency management
• The ‘Owner’ is the person with a PPM license who will be primarily responsible for the issue/risk (usually the PM)
• The ‘Owner of Issue/Risk’ is usually the person best suited for resolving the Issue/Risk (they don’t need a PPM Tool license)
• Open Issues/Work in Progress Issues should be updated periodically with:
Progress made towards resolution OR If no progress was made, why no progress was made
• Change the due date of open Issues if necessary
Monthly Status ReportingIssues and Risks Tab - Hints
67State of NC Internal Use Only – Do Not Distribute
Monthly Status Reporting
Document Management Tab
68State of NC Internal Use Only – Do Not Distribute
Attach appropriate supporting documentation
This may include (but not limited to): Any Agency approved change requests Staffing Plan / Project Staff Hours Worksheet Any document referenced in the ‘Agency Document Checklist’ with
a ‘YES’ response System Design Document
When creating New folders make sure to create them as Public folders
Private Folders and any documents in them can ONLY be seen by You
Monthly Status ReportingDocument Management Tab
69State of NC Internal Use Only – Do Not Distribute
Monthly Status Reporting
Project Reports Tab
70State of NC Internal Use Only – Do Not Distribute
Once all fields are updated, review “Project Status Report” for accuracy:
Run the Project Status Report by single clicking on the Adobe Acrobat icon
Review the Project Status Report to make sure that no additional edits are required
Compare the Status Report to the ‘PPM Project Status Indicator Settings Guidelines’
Check that ETC calculations for Hours and Dollars are correct
Check that ‘Total Approved Phase Budget Dollars’ is correct
After comparison to the ‘PPM Project Status Indicator Settings Guidelines’ document the PM should know what color Jellybeans they are going to receive
Monthly Status ReportingProject Reports Tab
71State of NC Internal Use Only – Do Not Distribute
Monthly Status Reporting
Process Flow Details
72State of NC Internal Use Only – Do Not Distribute
• Set “Project Status Report Step” attribute to ‘Agency Review’
Monthly Status ReportingProcess Flow – Status Tab
• Report should be reviewed and approved by appropriate agency personnel• PMO/PM then sets “Project Status Report Step” attribute to “QA Review”
73State of NC Internal Use Only – Do Not Distribute
• When the agency has approved the project status report and set the “Project Status Report Step” attribute to ‘QA Review’, the EPMO QA group will be electronically notified• When the EPMO QA group has completed the project assessment, the “Project Status Report Step” will be set to “QA Review Finalized”• If the agency has set up an “Alert” they will be notified electronically when the assessment is finalized
Monthly Status ReportingProcess Flow – Status Tab
74State of NC Internal Use Only – Do Not Distribute
Monthly Status Reporting
Adding Alert Subscriptions
75State of NC Internal Use Only – Do Not Distribute
• From Project Info tab select ‘Alert Subscription’
Monthly Status ReportingAlert Subscription
• Click on the ‘Add Subscription’ tab
76State of NC Internal Use Only – Do Not Distribute
• Create a New Subscription
Monthly Status ReportingAlert Subscription
77State of NC Internal Use Only – Do Not Distribute
Monthly Status ReportingAlert Subscription
• Fill in the details
• With the condition set to ‘Value has Changed’ the tool will notify you anytime the Project Status Report Step is changed
78State of NC Internal Use Only – Do Not Distribute
Monthly Status ReportingSupporting Documentation
79State of NC Internal Use Only – Do Not Distribute
Monthly Status ReportingSupporting Status Reporting Documentation
80State of NC Internal Use Only – Do Not Distribute
Contact Information
EPMO QA
Richard McGee
919-754-6607
Shaw Erfani
919-754-6608
PPM Tool Questions
Charles Richards
919-754-6612
Janet Stewart
919-754-6555