1 Solar Update February 28, 2013 Michael E. Finn, CFO.
17
1 Solar Update February 28, 2013 Michael E. Finn, CFO
-
Upload
evan-jackson -
Category
Documents
-
view
215 -
download
0
Transcript of 1 Solar Update February 28, 2013 Michael E. Finn, CFO.
1
Solar Update
February 28, 2013
Michael E. Finn, CFO
• The contract is in the process of being assumed by Constellation Energy Group
• Decreased sizing by 5% to ensure energy savings measures do not create over production
• Plans designed in tandem with principals and construction teams
2
Solar Update
3
• Coyote Hills, Zuni Hills and Peoria High School to begin construction April 1– Elementary schools completed August 2– High School completed August 30
• Cheyenne, Desert Harbor, and Santa Fe to begin construction May 27– All completed September 27
Construction Schedule
AERIAL VIEWS AND MODIFICATIONS
4
5
6
7
8
9
10
11
12
13
14
15
16
QUESTIONS
17