![Page 1: 1. SMA Project Description Background Design Construction Test Conclusion Acknowledgments 2.](https://reader035.fdocuments.in/reader035/viewer/2022062417/551b84e2550346a6148b596d/html5/thumbnails/1.jpg)
1
![Page 2: 1. SMA Project Description Background Design Construction Test Conclusion Acknowledgments 2.](https://reader035.fdocuments.in/reader035/viewer/2022062417/551b84e2550346a6148b596d/html5/thumbnails/2.jpg)
•SMA•Project Description•Background•Design•Construction•Test•Conclusion•Acknowledgments
2
![Page 3: 1. SMA Project Description Background Design Construction Test Conclusion Acknowledgments 2.](https://reader035.fdocuments.in/reader035/viewer/2022062417/551b84e2550346a6148b596d/html5/thumbnails/3.jpg)
8 movable antennas Detects light colors
0.3 – 1.7 mm Wavelengths
Air HandlerConstant Temperature2 Valves
○ Cold & Recirculation4 of the 8 antennas are
upgraded currently
3
![Page 4: 1. SMA Project Description Background Design Construction Test Conclusion Acknowledgments 2.](https://reader035.fdocuments.in/reader035/viewer/2022062417/551b84e2550346a6148b596d/html5/thumbnails/4.jpg)
4
•Design and Build smaller Air Handler and cabin for testing purposes
Design Requirements:•Accurately simulate Air Handler•Use main components•Be operated by original software
Purpose:•Use as a test model•Debug•Saves time
![Page 5: 1. SMA Project Description Background Design Construction Test Conclusion Acknowledgments 2.](https://reader035.fdocuments.in/reader035/viewer/2022062417/551b84e2550346a6148b596d/html5/thumbnails/5.jpg)
5
![Page 6: 1. SMA Project Description Background Design Construction Test Conclusion Acknowledgments 2.](https://reader035.fdocuments.in/reader035/viewer/2022062417/551b84e2550346a6148b596d/html5/thumbnails/6.jpg)
First Design:
Second Design:
6
![Page 7: 1. SMA Project Description Background Design Construction Test Conclusion Acknowledgments 2.](https://reader035.fdocuments.in/reader035/viewer/2022062417/551b84e2550346a6148b596d/html5/thumbnails/7.jpg)
7
![Page 8: 1. SMA Project Description Background Design Construction Test Conclusion Acknowledgments 2.](https://reader035.fdocuments.in/reader035/viewer/2022062417/551b84e2550346a6148b596d/html5/thumbnails/8.jpg)
8
![Page 9: 1. SMA Project Description Background Design Construction Test Conclusion Acknowledgments 2.](https://reader035.fdocuments.in/reader035/viewer/2022062417/551b84e2550346a6148b596d/html5/thumbnails/9.jpg)
9
Air Handler/Mixing Box•Two 4 inch Intakes holes•2.5 inch Rear exhaust which enters into the Cabin
![Page 10: 1. SMA Project Description Background Design Construction Test Conclusion Acknowledgments 2.](https://reader035.fdocuments.in/reader035/viewer/2022062417/551b84e2550346a6148b596d/html5/thumbnails/10.jpg)
10
Temperature sensors
Heater
Solid State Relay
![Page 11: 1. SMA Project Description Background Design Construction Test Conclusion Acknowledgments 2.](https://reader035.fdocuments.in/reader035/viewer/2022062417/551b84e2550346a6148b596d/html5/thumbnails/11.jpg)
11
•4 inch dryer vent•Enlarge one axle hole•Damper motor turns 3/5 inch round bar
•Notched at one end to hold valve in place when operating
![Page 12: 1. SMA Project Description Background Design Construction Test Conclusion Acknowledgments 2.](https://reader035.fdocuments.in/reader035/viewer/2022062417/551b84e2550346a6148b596d/html5/thumbnails/12.jpg)
Universal MotorAble to use voltage
regulator to control speed
4 inch adapter on the exhaust side to be able to match with 4 inch intake valves
Temperature and Humidity Sensors
12
![Page 13: 1. SMA Project Description Background Design Construction Test Conclusion Acknowledgments 2.](https://reader035.fdocuments.in/reader035/viewer/2022062417/551b84e2550346a6148b596d/html5/thumbnails/13.jpg)
13
![Page 14: 1. SMA Project Description Background Design Construction Test Conclusion Acknowledgments 2.](https://reader035.fdocuments.in/reader035/viewer/2022062417/551b84e2550346a6148b596d/html5/thumbnails/14.jpg)
14
![Page 15: 1. SMA Project Description Background Design Construction Test Conclusion Acknowledgments 2.](https://reader035.fdocuments.in/reader035/viewer/2022062417/551b84e2550346a6148b596d/html5/thumbnails/15.jpg)
Air Handler HW Test
Room Temp: 26.6 C
Temp. Set Point: 29 C
Interval Cabin Temperature:1 26.632 29.283 30.564 30.845 31.036 30.247 29.778 29.219 28.77
10 28.8211 29.0812 29.2813 28.9414 29.1915 29.3216 29.2217 29.15
15
•Stable after one and half hours
![Page 16: 1. SMA Project Description Background Design Construction Test Conclusion Acknowledgments 2.](https://reader035.fdocuments.in/reader035/viewer/2022062417/551b84e2550346a6148b596d/html5/thumbnails/16.jpg)
Air Handler ModelUsed for testing
purposesUseful for future
hardware and software upgrades
Great ExperienceDesignFabricate Test
16
![Page 17: 1. SMA Project Description Background Design Construction Test Conclusion Acknowledgments 2.](https://reader035.fdocuments.in/reader035/viewer/2022062417/551b84e2550346a6148b596d/html5/thumbnails/17.jpg)
I would like to thank the following: Mentor – Billie Chitwood John Cheng, Kevin O’Cconnell, and Mac
Cooper. All of the SMA staff for using their tools,
material, and facilities. Lynne Raschke, Lisa Hunter, Sarah
Anderson, Hilary O’Bryan, Scott Seagroves and the rest of the CfAO staff .
All the Akamai Interns
Funding provided through the Center for Adaptive Optics, a National Science Foundation Science and Technology Center (STC), AST-987683
17
![Page 18: 1. SMA Project Description Background Design Construction Test Conclusion Acknowledgments 2.](https://reader035.fdocuments.in/reader035/viewer/2022062417/551b84e2550346a6148b596d/html5/thumbnails/18.jpg)
18