1 Selection & Implementation of Shipmanagement Software George Spyrou, Financial Manager Navigo Shipmanagers, Limassol, Cyprus www.navigo-cy.com Digital Ship Posidonia 2006

Transcript of 1 Selection & Implementation of Shipmanagement Software George Spyrou, Financial Manager Navigo...

Page 1: 1 Selection & Implementation of Shipmanagement Software George Spyrou, Financial Manager Navigo Shipmanagers, Limassol, Cyprus  Digital.

1

Selection & Implementation of Shipmanagement Software

George Spyrou, Financial Manager Navigo Shipmanagers, Limassol,

Cyprus

www.navigo-cy.com

Digital Ship Posidonia 2006

Page 2: 1 Selection & Implementation of Shipmanagement Software George Spyrou, Financial Manager Navigo Shipmanagers, Limassol, Cyprus  Digital.

2

Selection & Implementation of Shipmanagement Software

Digital Ship Posidonia 2006

Navigo Shipmanagers Medium sized Company established in 1985 Member of the Schulte Group in Germany Founding Member of ISMA ISO 9001certified for shipmanagement & crewmanagement Manages a fleet of 50 vessels of various types

- 2 -

Page 3: 1 Selection & Implementation of Shipmanagement Software George Spyrou, Financial Manager Navigo Shipmanagers, Limassol, Cyprus  Digital.

3

Selection & Implementation of Shipmanagement Software

Digital Ship Posidonia 2006

Presentation Outline

1. Selection Process of a software system

2. Implementation Process

3. Key Success Factors

- 3 -

Page 4: 1 Selection & Implementation of Shipmanagement Software George Spyrou, Financial Manager Navigo Shipmanagers, Limassol, Cyprus  Digital.

4

Selection & Implementation of Shipmanagement Software

Digital Ship Posidonia 2006

1. Selection Process

a. Analyze the company’s business processes.

List the company’s business processes in place.

Evaluate these processes.

Consider whether some processes need to be improved, streamlined, or discontinued.

Find out what users think about them (i.e. effectiveness, time consuming).

- 4 -

Page 5: 1 Selection & Implementation of Shipmanagement Software George Spyrou, Financial Manager Navigo Shipmanagers, Limassol, Cyprus  Digital.

5

Selection & Implementation of Shipmanagement Software

Digital Ship Posidonia 2006

1. Selection Process

b. Set the selection criteria

Technical Specifications

Supplier’s reliability

System’s Cost

- 5 -

Ability of the system to fit the company’s business processes

Page 6: 1 Selection & Implementation of Shipmanagement Software George Spyrou, Financial Manager Navigo Shipmanagers, Limassol, Cyprus  Digital.

6

Selection & Implementation of Shipmanagement Software

Digital Ship Posidonia 2006

1. Selection Process

c. Search for suitable systems available

Market research.

Internet research

Business Magazines

IT conferences

- 6 -

Page 7: 1 Selection & Implementation of Shipmanagement Software George Spyrou, Financial Manager Navigo Shipmanagers, Limassol, Cyprus  Digital.

7

Selection & Implementation of Shipmanagement Software

Digital Ship Posidonia 2006

1. Selection Process

d. Evaluate systems and select the most suitable

List the strengths and weaknesses of each system on the basis of selection criteria.

Ask for software presentations from those suppliers that look promising, involving all managers and key users.

Make a shortlist of 2 or 3 suppliers and request installation of Demo versions for testing by users.

Collect feedback from users, evaluate and finally select the most suitable system.

- 7 -

Page 8: 1 Selection & Implementation of Shipmanagement Software George Spyrou, Financial Manager Navigo Shipmanagers, Limassol, Cyprus  Digital.

8

Selection & Implementation of Shipmanagement Software

Digital Ship Posidonia 2006

2. Implementation Process

a. Sell the idea of the new system to all users internally

Use of change management strategies like:

Education. Explain the reasons for changing the system and how they will benefit.Participation. Actively involve people in the change process i.e. be part of the selection & implementation teamFacilitation. Help people adapt and accept change i.e. training and support.

- 8 -

Page 9: 1 Selection & Implementation of Shipmanagement Software George Spyrou, Financial Manager Navigo Shipmanagers, Limassol, Cyprus  Digital.

9

Selection & Implementation of Shipmanagement Software

Digital Ship Posidonia 2006

2. Implementation Process

b. Appoint Project Manager

Must have sufficient power, authority and technical knowledge to ensure the the IT project is:Delivered in timeDelivered within the budgetDelivered at high quality

- 9 -

Page 10: 1 Selection & Implementation of Shipmanagement Software George Spyrou, Financial Manager Navigo Shipmanagers, Limassol, Cyprus  Digital.

10

Selection & Implementation of Shipmanagement Software

Digital Ship Posidonia 2006

2. Implementation Process

c. Plan the timing of the various implementation stages:

Office modules:Hardware acquisition and preparationSoftware installation by the supplierData conversion from the old systemInput of static data and system setupUsers’ training using real life data whenever possibleParallel running periodGoing live

- 10 -

Page 11: 1 Selection & Implementation of Shipmanagement Software George Spyrou, Financial Manager Navigo Shipmanagers, Limassol, Cyprus  Digital.

11

Selection & Implementation of Shipmanagement Software

Digital Ship Posidonia 2006

2. Implementation Process

c. Plan the timing of the various implementation stages:Vessel modules:

Set up of vessel simulation environment in the office. Testing of all on board modules and communication on the simulation. Training of key crew members (Master and C/E) preferably in the office based simulation. On board installation, configuration and crew training by supplier’s engineer together with office superintendent.

- 11 -

Page 12: 1 Selection & Implementation of Shipmanagement Software George Spyrou, Financial Manager Navigo Shipmanagers, Limassol, Cyprus  Digital.

12

Selection & Implementation of Shipmanagement Software

Digital Ship Posidonia 2006

2. Implementation Process

d. Agree on customizations

Must be carefully specified in writing and agreed by both parties.Must be specified after training in the standard version is completedSupplier must propose the most efficient way to adjust the software in order to achieve the desired results.Supplier must proceed with development of customizations in accordance with schedule and time agreed.

- 12 -

Page 13: 1 Selection & Implementation of Shipmanagement Software George Spyrou, Financial Manager Navigo Shipmanagers, Limassol, Cyprus  Digital.

13

Selection & Implementation of Shipmanagement Software

Digital Ship Posidonia 2006

3. Key Success factors

Top Management involvement.

Choose the right software package.

Appoint a capable Project Manager.

Stick to the implementation plan and dates.

Availability of staff for the extra work and time involved.

- 13 -

Page 14: 1 Selection & Implementation of Shipmanagement Software George Spyrou, Financial Manager Navigo Shipmanagers, Limassol, Cyprus  Digital.

14

Selection & Implementation of Shipmanagement Software

Digital Ship Posidonia 2006

Thank you all for listening ! !

www.navigo-cy.com

Page 15: 1 Selection & Implementation of Shipmanagement Software George Spyrou, Financial Manager Navigo Shipmanagers, Limassol, Cyprus  Digital.

15

Selection & Implementation of Shipmanagement Software

Digital Ship Posidonia 2006

?