1 SAN DIEGO COUNTY WATER AUTHORITY PIPELINE RELINING PROGRAM Keeping the Water Flowing.

48
1 SAN DIEGO COUNTY WATER AUTHORITY PIPELINE RELINING PROGRAM Keeping the Water Flowing

Transcript of 1 SAN DIEGO COUNTY WATER AUTHORITY PIPELINE RELINING PROGRAM Keeping the Water Flowing.

Page 1: 1 SAN DIEGO COUNTY WATER AUTHORITY PIPELINE RELINING PROGRAM Keeping the Water Flowing.

1

SAN DIEGO COUNTY WATER AUTHORITY PIPELINE RELINING PROGRAM

Keeping the Water Flowing

Page 2: 1 SAN DIEGO COUNTY WATER AUTHORITY PIPELINE RELINING PROGRAM Keeping the Water Flowing.

• Misha Troyan, P.E., EPC Consultants

• Mike Kenny, SDCWA

• Jose Martinez, R.W. Beck

Panel Members

2

Page 3: 1 SAN DIEGO COUNTY WATER AUTHORITY PIPELINE RELINING PROGRAM Keeping the Water Flowing.

Bio – Misha Troyan, P.E.

• San Diego Area Manager, EPC Consultants• B.S. Civil Engineering, University of California

at Berkeley• Construction Manager for 27,000 feet of

pipeline relining projects – EPC has been a prime or subconsultant

on four reline projects to date

3

Page 4: 1 SAN DIEGO COUNTY WATER AUTHORITY PIPELINE RELINING PROGRAM Keeping the Water Flowing.

Bio – Mike Kenny

• Senior Construction Manager, SDCWA• Oversight on $130 million in current

construction projects• B.S. Construction Management, Colorado

State University• 18 years with SDCWA including Inspection

Manager of Construction Inspection Group• Member, CMAA Board of Directors, San Diego

Chapter

4

Page 5: 1 SAN DIEGO COUNTY WATER AUTHORITY PIPELINE RELINING PROGRAM Keeping the Water Flowing.

Bio – Jose Martinez

• Construction Manager, R.W. Beck• B.S. Mechanical Engineering, United States

Naval Academy– Certified Naval Nuclear Engineer by the

Department of Energy• Construction Manager on recent design-

build & urgent pipeline relines

5

Page 6: 1 SAN DIEGO COUNTY WATER AUTHORITY PIPELINE RELINING PROGRAM Keeping the Water Flowing.

Presentation Goal

• Who is the San Diego County Water Authority?

• What is PCCP?

• Why is the Water Authority relining its pipelines?

• How does relining work?

• When did relining work start and what is the future of the program?

6

Page 7: 1 SAN DIEGO COUNTY WATER AUTHORITY PIPELINE RELINING PROGRAM Keeping the Water Flowing.

Regional Background

• More than 200 years of water development

• Major focus of dam construction at end of 19th century

• SDCWA organized in 1944 to meet area's wartime mission

• Fifth of five major pipelines completed in 1982

7

Mission Dam was constructed by Spanish settlers in 1769.

Page 8: 1 SAN DIEGO COUNTY WATER AUTHORITY PIPELINE RELINING PROGRAM Keeping the Water Flowing.

SDCWA Regional Role

• Water wholesaler provides 90% of San Diego County’s water

• 24 member agencies serving a population of 3.7 million people

8

• Active in state and federal government as advocate for regional water supply

Completed in 2003, Olivenhain Dam is the largest RCC dam in the world

Page 9: 1 SAN DIEGO COUNTY WATER AUTHORITY PIPELINE RELINING PROGRAM Keeping the Water Flowing.

Infrastructure Overview

• Key Components– 300 miles of pipe– 82.5 miles of PCCP

(gravity)– 48 to 108 inch

• Expanding treated water capability

9

Page 10: 1 SAN DIEGO COUNTY WATER AUTHORITY PIPELINE RELINING PROGRAM Keeping the Water Flowing.

Prestressed Concrete Cylindrical Pipe (PCCP)

10

Page 11: 1 SAN DIEGO COUNTY WATER AUTHORITY PIPELINE RELINING PROGRAM Keeping the Water Flowing.

Why Reline?

11

Page 12: 1 SAN DIEGO COUNTY WATER AUTHORITY PIPELINE RELINING PROGRAM Keeping the Water Flowing.
Page 13: 1 SAN DIEGO COUNTY WATER AUTHORITY PIPELINE RELINING PROGRAM Keeping the Water Flowing.

Historical Failures

• February 1979 – 66” (1959)• December 1980 – 66” (1959)• May 1982 – 66” (1959)• October 1990 – 84” (1972)• November 1993 – 96” (1972)*• May 2006 – 66” (1959) *• October 2008 – 72” (1976)*

* High pressure section13

Page 14: 1 SAN DIEGO COUNTY WATER AUTHORITY PIPELINE RELINING PROGRAM Keeping the Water Flowing.

Aqueduct Protection Program (APP)

• Established by SDCWA Board in 1991 in response to failures and concern about pipeline condition

• Risk Management role– May 2006 Failure = $6 million– Feb 2008 Replacement = $1 million– May 2008 Carbon Fiber Urgent Repair = $530k

• $41 million over the next 30 years; 4 regular staff plus support staff (as of 2003)

14

Page 15: 1 SAN DIEGO COUNTY WATER AUTHORITY PIPELINE RELINING PROGRAM Keeping the Water Flowing.

APP – What Does it Do?

• Monitors and mitigates corrosion related damage

• Identifies pipeline nearing end of service life and schedules rehabilitation/replacement

• Documentation• Determines remaining service life and pipeline

decay index (PDI) for analysis

15

Page 16: 1 SAN DIEGO COUNTY WATER AUTHORITY PIPELINE RELINING PROGRAM Keeping the Water Flowing.

Condition Assessment Tools

• In Service– Failures– Acoustical Monitoring

• Out of Service– Visual/Sounding– Remote Field Eddy Current– Impact Echo (limited effectiveness)

16

Page 17: 1 SAN DIEGO COUNTY WATER AUTHORITY PIPELINE RELINING PROGRAM Keeping the Water Flowing.

Acoustic Fiber Optics (AFO)

17

• Real-time monitoring of prestressing wires – Hydrophone Arrays– Acoustic Fiber Optic Cable

• Authority Pipelines Currently Being Monitored– Pipeline 3 = 19,715 feet– Pipeline 4 = 20,167 feet– Pipeline 5 = 65,000 feet– Crossover Pipeline = 39,600 feet

Page 18: 1 SAN DIEGO COUNTY WATER AUTHORITY PIPELINE RELINING PROGRAM Keeping the Water Flowing.

Handwriting On The Wall

18

Page 19: 1 SAN DIEGO COUNTY WATER AUTHORITY PIPELINE RELINING PROGRAM Keeping the Water Flowing.

Got Corrosion?

19

Page 20: 1 SAN DIEGO COUNTY WATER AUTHORITY PIPELINE RELINING PROGRAM Keeping the Water Flowing.

Visual Inspection

20

Page 21: 1 SAN DIEGO COUNTY WATER AUTHORITY PIPELINE RELINING PROGRAM Keeping the Water Flowing.

Visual Inspection

21

Deformed Cylinder

Thin Mortar Lining Cracked and Exposed Steel Cylinder

Page 22: 1 SAN DIEGO COUNTY WATER AUTHORITY PIPELINE RELINING PROGRAM Keeping the Water Flowing.

Sounding

22

• Examination of External PCCP Wires

• Sounding and removal of delaminated mortar coating

• Cleaning and inspection of pre-stressed wires

Page 23: 1 SAN DIEGO COUNTY WATER AUTHORITY PIPELINE RELINING PROGRAM Keeping the Water Flowing.

Remote Field Eddy Current

23

• 30 broken wires estimated

• 27 broken wires found

Page 24: 1 SAN DIEGO COUNTY WATER AUTHORITY PIPELINE RELINING PROGRAM Keeping the Water Flowing.

Condition Assessment

24

• Pipeline Decay Index (PDI)– Summary of all factors– Determines remaining service life– Determines maintenance schedule– Regular data reviews and updates

• Potential impacts via GIS maps– Watercourse, schools, homes, roads,

commercial zones, etc.

Page 25: 1 SAN DIEGO COUNTY WATER AUTHORITY PIPELINE RELINING PROGRAM Keeping the Water Flowing.

Lessons Learned

• In-Plant inspection is key– Proper coating and lining– Steel can condition

• Consider bedding and environment – San Diego has very corrosive soils high in chlorides– Rock backfilled against pipe cracks coating– Poor diapers at joints on older PCCP

• Effect of shutdowns on PCCP25

Page 26: 1 SAN DIEGO COUNTY WATER AUTHORITY PIPELINE RELINING PROGRAM Keeping the Water Flowing.

Relining Considerations• Costs:

– Average reline cost = $1,300/ft– New Steel Pipe = $1,462/ft (rural) & $2,055/ft (urban)– Carbon fiber repair = $7,500/ft• Time:– Reduced OOS duration– 24-hour work• Community impacts:– Out of sight, out of mind• Environmental:– Minimizes dust, noise and impacts to habitat

26

Page 27: 1 SAN DIEGO COUNTY WATER AUTHORITY PIPELINE RELINING PROGRAM Keeping the Water Flowing.

Relining Background

• New steel pipeline within PCCP

• Process developed in early 1980s by SDCWA Assistant Chief Engineer, Buckley L. Ogden– Ogden’s pipe carrier

• Process used around the nation and at the Water Authority today

27

Page 28: 1 SAN DIEGO COUNTY WATER AUTHORITY PIPELINE RELINING PROGRAM Keeping the Water Flowing.

Basic Relining Process

• Portal Development

• Liner installation & Welding

• Grouting

• Cement Mortar Lining

• Closure Pieces

• Portal Restoration

28

Page 29: 1 SAN DIEGO COUNTY WATER AUTHORITY PIPELINE RELINING PROGRAM Keeping the Water Flowing.

29

Portal Development

Page 30: 1 SAN DIEGO COUNTY WATER AUTHORITY PIPELINE RELINING PROGRAM Keeping the Water Flowing.

30

Portal Development

Page 31: 1 SAN DIEGO COUNTY WATER AUTHORITY PIPELINE RELINING PROGRAM Keeping the Water Flowing.

31

Liner Installation

Page 32: 1 SAN DIEGO COUNTY WATER AUTHORITY PIPELINE RELINING PROGRAM Keeping the Water Flowing.

32

Liner Installation

Page 33: 1 SAN DIEGO COUNTY WATER AUTHORITY PIPELINE RELINING PROGRAM Keeping the Water Flowing.

33

Bell & Spigot Fit-up

Page 34: 1 SAN DIEGO COUNTY WATER AUTHORITY PIPELINE RELINING PROGRAM Keeping the Water Flowing.

34

Welding

Page 35: 1 SAN DIEGO COUNTY WATER AUTHORITY PIPELINE RELINING PROGRAM Keeping the Water Flowing.

35

Grouting

Page 36: 1 SAN DIEGO COUNTY WATER AUTHORITY PIPELINE RELINING PROGRAM Keeping the Water Flowing.

36

Grouting

Page 37: 1 SAN DIEGO COUNTY WATER AUTHORITY PIPELINE RELINING PROGRAM Keeping the Water Flowing.

37

Cement Mortar Lining

Page 38: 1 SAN DIEGO COUNTY WATER AUTHORITY PIPELINE RELINING PROGRAM Keeping the Water Flowing.

38

Cement Mortar Lining

Page 39: 1 SAN DIEGO COUNTY WATER AUTHORITY PIPELINE RELINING PROGRAM Keeping the Water Flowing.

39

Closure Pieces

Page 40: 1 SAN DIEGO COUNTY WATER AUTHORITY PIPELINE RELINING PROGRAM Keeping the Water Flowing.

40

Closure Pieces

Page 41: 1 SAN DIEGO COUNTY WATER AUTHORITY PIPELINE RELINING PROGRAM Keeping the Water Flowing.

41

Concrete Encasement

Page 42: 1 SAN DIEGO COUNTY WATER AUTHORITY PIPELINE RELINING PROGRAM Keeping the Water Flowing.

42

Concrete Encasement

Page 43: 1 SAN DIEGO COUNTY WATER AUTHORITY PIPELINE RELINING PROGRAM Keeping the Water Flowing.

43

Portal Restoration

Page 44: 1 SAN DIEGO COUNTY WATER AUTHORITY PIPELINE RELINING PROGRAM Keeping the Water Flowing.

44

Portal Restoration

Page 45: 1 SAN DIEGO COUNTY WATER AUTHORITY PIPELINE RELINING PROGRAM Keeping the Water Flowing.

Emergency Repairs

• Emergency vs. Urgent Repairs

• Same Process, Compressed Timeline

• Additional Variables

• Communication

45

Page 46: 1 SAN DIEGO COUNTY WATER AUTHORITY PIPELINE RELINING PROGRAM Keeping the Water Flowing.

Carbon Fiber Repair

46

Page 47: 1 SAN DIEGO COUNTY WATER AUTHORITY PIPELINE RELINING PROGRAM Keeping the Water Flowing.

Reline Program Status

47

• Total Budget: $787 million

• Spent to date: $100 million

• May 2006 Failure, $6 million

• AFO repairs

• Feb 2008 replacement,

$1 million

• May 2008 carbon fiber,

$530k

26%

74%

Relined To date Remaining

61 Miles

21.5 Miles

Page 48: 1 SAN DIEGO COUNTY WATER AUTHORITY PIPELINE RELINING PROGRAM Keeping the Water Flowing.

Anything Else?

Questions & Answers

48