1. SAHS Academy - Complete 2. EAHS Athletics - Complete 3 ... · districtwide covered play...
Transcript of 1. SAHS Academy - Complete 2. EAHS Athletics - Complete 3 ... · districtwide covered play...
![Page 1: 1. SAHS Academy - Complete 2. EAHS Athletics - Complete 3 ... · districtwide covered play pavillions status of $1,500,000.00 fund group 1 – sps,dvp,cps – under construction -](https://reader034.fdocuments.in/reader034/viewer/2022052104/603f6ef13487c064a5468715/html5/thumbnails/1.jpg)
1. SAHS Academy - Complete2. EAHS Athletics - Complete3. SAHS Athletics - Complete4. DHS Athletics - Complete5. EAHS Academy – Near Complete6. DTHS Academy – Near Complete7. DTHS Athletics – In Design
![Page 2: 1. SAHS Academy - Complete 2. EAHS Athletics - Complete 3 ... · districtwide covered play pavillions status of $1,500,000.00 fund group 1 – sps,dvp,cps – under construction -](https://reader034.fdocuments.in/reader034/viewer/2022052104/603f6ef13487c064a5468715/html5/thumbnails/2.jpg)
APPLe RENOVATIONS/ADDITIONS
APSB HAS FULL OWNERSHIP AND USE OF THE OLD LOUISIANA TECHNICAL COLLEGE BUILDING ON AIRLINE HWY IN SORRENTO
LEASE CANCELLATION DOCUMENTS WERE SIGNED, FILED AND RECORDED AT THE COURTHOUSE DATED JUNE 18, 2017
WE ARE PROCEEDING WITH DESIGN OF AN APSB APPLe AND CAREER ED PROGRAM AT THE SITE ON AIRLINE HWY IN SORRENTO
PROGRAM CONFIRMATION PHASE IS COMPLETE. SCHEMATIC DESIGN PHASE IS JUST BEGINNING
CONSTRUCTION START IS EXPECTED IN SPRING 2018
WE HAVE OVERCOME A LONGSTANDING OBSTACLE TOWARDS PIPED WATER UTILITIES AT THE SORRENTO SITE. THERE IS NOW A SERVITUDE FOR ASCENSION WATER TO GET TO THEIR WATER TO OUR SITE IN SORRENTO
STATUS
![Page 3: 1. SAHS Academy - Complete 2. EAHS Athletics - Complete 3 ... · districtwide covered play pavillions status of $1,500,000.00 fund group 1 – sps,dvp,cps – under construction -](https://reader034.fdocuments.in/reader034/viewer/2022052104/603f6ef13487c064a5468715/html5/thumbnails/3.jpg)
APPLe RENOVATIONS/ADDITIONS
![Page 4: 1. SAHS Academy - Complete 2. EAHS Athletics - Complete 3 ... · districtwide covered play pavillions status of $1,500,000.00 fund group 1 – sps,dvp,cps – under construction -](https://reader034.fdocuments.in/reader034/viewer/2022052104/603f6ef13487c064a5468715/html5/thumbnails/4.jpg)
ASCENSION HEAD START RENOVATIONS
THE GYM DEMOLITION CONTRACT HAS BEGUN
A SECOND CONTRACT WILL INCLUDE BUILDING A NEW FLOOR PLAN IN THE GYM AS WELL AS DEMO AND NEW FLOOR PLAN IN THE OLD CLASSROOM BUILDING
THE SECOND CONTRACT WILL BE BID AS SOON AS POSSIBLE SO THAT IT MAY BEGIN AFTER THE DEMOLITION PROJECT
STATUS
![Page 5: 1. SAHS Academy - Complete 2. EAHS Athletics - Complete 3 ... · districtwide covered play pavillions status of $1,500,000.00 fund group 1 – sps,dvp,cps – under construction -](https://reader034.fdocuments.in/reader034/viewer/2022052104/603f6ef13487c064a5468715/html5/thumbnails/5.jpg)
ASCENSION HEAD START RENOVATIONS
![Page 6: 1. SAHS Academy - Complete 2. EAHS Athletics - Complete 3 ... · districtwide covered play pavillions status of $1,500,000.00 fund group 1 – sps,dvp,cps – under construction -](https://reader034.fdocuments.in/reader034/viewer/2022052104/603f6ef13487c064a5468715/html5/thumbnails/6.jpg)
ASCENSION HEAD START RENOVATIONS
![Page 7: 1. SAHS Academy - Complete 2. EAHS Athletics - Complete 3 ... · districtwide covered play pavillions status of $1,500,000.00 fund group 1 – sps,dvp,cps – under construction -](https://reader034.fdocuments.in/reader034/viewer/2022052104/603f6ef13487c064a5468715/html5/thumbnails/7.jpg)
BLUFF ROAD NEW MIDDLE SCHOOL
PRELIMINARY WETLANDS DELINEATION HAS BEEN SUBMITTED TO ARMY CORPS FOR APPROVAL
DESIGN CONTRACT WAS SIGNED IN JULY 2017
THE PROJECT IS IN SCHEMATIC DESIGN PHASE
BIDDING IS PROPOSED IN AUGUST 2018
STATUS
![Page 8: 1. SAHS Academy - Complete 2. EAHS Athletics - Complete 3 ... · districtwide covered play pavillions status of $1,500,000.00 fund group 1 – sps,dvp,cps – under construction -](https://reader034.fdocuments.in/reader034/viewer/2022052104/603f6ef13487c064a5468715/html5/thumbnails/8.jpg)
BULLION CROSSING NEW PRIMARY SCHOOL
THE DESIGN CONTRACT WAS SIGNED JULY 2017
ARCHITECT IS IN SCHEMATIC DESIGN PHASE
BIDDING IS PROPOSED IN MAY OF 2018
PRELIMINARY WETLANDS DELINEATION HAS BEEN SUBMITTED TO ARMY CORPS FOR APPROVAL
STATUS
![Page 9: 1. SAHS Academy - Complete 2. EAHS Athletics - Complete 3 ... · districtwide covered play pavillions status of $1,500,000.00 fund group 1 – sps,dvp,cps – under construction -](https://reader034.fdocuments.in/reader034/viewer/2022052104/603f6ef13487c064a5468715/html5/thumbnails/9.jpg)
HWY 73 NEW PRIMARY SCHOOL
ABATEMENT AND DEMOLITION OF BOTH HOUSES HAS BEEN COMPLETED
PRELIMINARY WETLANDS DELINEATION HAS BEEN SUBMITTED TO THE ARMY CORPS FOR APPROVAL
DESIGN CONTRACT IS DRAFTED, PENDING NEGOTIATIONS AND SIGNATURE
STATUS
![Page 10: 1. SAHS Academy - Complete 2. EAHS Athletics - Complete 3 ... · districtwide covered play pavillions status of $1,500,000.00 fund group 1 – sps,dvp,cps – under construction -](https://reader034.fdocuments.in/reader034/viewer/2022052104/603f6ef13487c064a5468715/html5/thumbnails/10.jpg)
GERMANY ROAD NEW PRIMARY SCHOOL
PRELIMINARY WETLANDS DELINEATION HAS BEEN SUBMITTED TO ARMY CORPS FOR APPROVAL
THE DESIGN CONTRACT HAS NOT BEEN DRAFTED OR SIGNED
STATUS
![Page 11: 1. SAHS Academy - Complete 2. EAHS Athletics - Complete 3 ... · districtwide covered play pavillions status of $1,500,000.00 fund group 1 – sps,dvp,cps – under construction -](https://reader034.fdocuments.in/reader034/viewer/2022052104/603f6ef13487c064a5468715/html5/thumbnails/11.jpg)
ST. AMANT HIGH – COMPLETE THE FRESHMAN ACADEMY
TARGETED RENOVATION AREA
SECURITY ADDITION
THE DESIGN CONTRACT IS SIGNED
PROGRAM CONFIRMATION PHASE
PLAN TO ADD SECURITY PORTAL WHICH WILL ALSO HELP TO MATCH THE FAÇADE OF THE ACADEMY
REPURPOSE THE CAFETERIA
RENOVATE THE OFFICE AND LIBRARY
STATUS
![Page 12: 1. SAHS Academy - Complete 2. EAHS Athletics - Complete 3 ... · districtwide covered play pavillions status of $1,500,000.00 fund group 1 – sps,dvp,cps – under construction -](https://reader034.fdocuments.in/reader034/viewer/2022052104/603f6ef13487c064a5468715/html5/thumbnails/12.jpg)
IN DESIGN
EAST ASCENSION HIGH –COMPLETE THE FRESHMAN ACADEMY
![Page 13: 1. SAHS Academy - Complete 2. EAHS Athletics - Complete 3 ... · districtwide covered play pavillions status of $1,500,000.00 fund group 1 – sps,dvp,cps – under construction -](https://reader034.fdocuments.in/reader034/viewer/2022052104/603f6ef13487c064a5468715/html5/thumbnails/13.jpg)
PRAIRIEVILLE MIDDLE SCHOOL – GYM ADDITION
DEMOLITION OF BUILDINGS E, H AND J HAS BEEN AWARDED AND WILL BEGIN IN SEPTEMBER
SEWER RELOCATION IS BIDDING
CANOPY REROUTE IS BIDDING
CONSTRUCTION DOCUMENTS FOR THE NEW GYM ARE NEAR COMPLETE
STATUS
![Page 14: 1. SAHS Academy - Complete 2. EAHS Athletics - Complete 3 ... · districtwide covered play pavillions status of $1,500,000.00 fund group 1 – sps,dvp,cps – under construction -](https://reader034.fdocuments.in/reader034/viewer/2022052104/603f6ef13487c064a5468715/html5/thumbnails/14.jpg)
PRAIRIEVILLE MIDDLE SCHOOL1951 TO 2012
2015
![Page 15: 1. SAHS Academy - Complete 2. EAHS Athletics - Complete 3 ... · districtwide covered play pavillions status of $1,500,000.00 fund group 1 – sps,dvp,cps – under construction -](https://reader034.fdocuments.in/reader034/viewer/2022052104/603f6ef13487c064a5468715/html5/thumbnails/15.jpg)
PRAIRIEVILLE MIDDLE TRANSITION PHOTOS
MARCH 2015 TO SEPT 2017APRIL 2012‐MARCH 20151951 TO APRIL 2012
![Page 16: 1. SAHS Academy - Complete 2. EAHS Athletics - Complete 3 ... · districtwide covered play pavillions status of $1,500,000.00 fund group 1 – sps,dvp,cps – under construction -](https://reader034.fdocuments.in/reader034/viewer/2022052104/603f6ef13487c064a5468715/html5/thumbnails/16.jpg)
TEMPORARY CLASSROOMS
PRAIRIEVILLE MIDDLE SCHOOL
ADD CONNECTING CANOPY
DEMO BLDG E, H AND J
REROUTE SEWER
ADD GYM AND PARKING
NEXT STEPS
Gymnasium
Classrooms
OLD BUILDINGS
NEW GYM
![Page 17: 1. SAHS Academy - Complete 2. EAHS Athletics - Complete 3 ... · districtwide covered play pavillions status of $1,500,000.00 fund group 1 – sps,dvp,cps – under construction -](https://reader034.fdocuments.in/reader034/viewer/2022052104/603f6ef13487c064a5468715/html5/thumbnails/17.jpg)
DISTRICTWIDE COVERED PLAY PAVILLIONSSTATUS OF $1,500,000.00 FUND
GROUP 1 – SPS,DVP,CPS – UNDER CONSTRUCTION - $211,000.00
GROUP 2- PVP,SLP,DUP – LOW BID WAS $213,366 RECEIVED ON SEP 19, 2017
GROUP 3 – LSP,GWC,PGP – IN DESIGN
DTP, LOWERY AND THE 3 NEW PRIMARY SCHOOLS WILL BE BUILT WITH THEIR BOND PROJECTS
UNASSIGNED AS OF TODAY – SAPS, GOPS, LAKE. HAVE GYMS ON CAMPUS
GVP HAS TWO OUTDOOR PAVILLIONS
OGP HAS THE ORIGINAL MODEL PAVILLION
![Page 18: 1. SAHS Academy - Complete 2. EAHS Athletics - Complete 3 ... · districtwide covered play pavillions status of $1,500,000.00 fund group 1 – sps,dvp,cps – under construction -](https://reader034.fdocuments.in/reader034/viewer/2022052104/603f6ef13487c064a5468715/html5/thumbnails/18.jpg)
DISTRICTWIDE SECURITY IMPROVEMENTSSTATUS
• CLASSROOM DOOR HARDWARE UPGRADES –• IMPLEMENTATION WAS COMPLETE PRIOR TO FLOOD • REPLACING FLOOD DAMAGED DOORS AND HARDWARE
• VIDEO – ALL SITES HAVE VIDEO SURVEILLANCE. ADDING SOME CAMERAS AS NECCESARY
• 2 WAY RADIO COMMUNICATIONS –• IMPLEMENTATION PHASE WAS COMPLETE PRIOR TO THE FLOOD• ONGOING MAINTENANCE/SUSTAINMENT PROGRAM
• ACCESS CONTROLS –• AN RFI HAS BEEN ISSUED AND RESPONSES RECEIVED• AN RFP COMMITTEE HAS BEEN FORMED• AN RFP HAS BEEN DRAFTED• WE WILL ADVERTISE THE RFP SOON
• CONSTRUCTION IMPROVEMENTS AT SCHOOL ENTRANCES• PRIMARY – 10/16 (4 ARE IN DESIGN)• MIDDLE – 3/8 (2 ARE IN DESIGN)• HIGH – 1/5 (3 ARE IN DESIGN)• AHS – 0/5
![Page 19: 1. SAHS Academy - Complete 2. EAHS Athletics - Complete 3 ... · districtwide covered play pavillions status of $1,500,000.00 fund group 1 – sps,dvp,cps – under construction -](https://reader034.fdocuments.in/reader034/viewer/2022052104/603f6ef13487c064a5468715/html5/thumbnails/19.jpg)
DISTRICTWIDE SECURITY IMPROVEMENTSSECURITY FENCING STATUS
• Fence Types Include:• Pipe Rail Fences (Parking Lots)• Black Vinyl Chain link Fences (Back Yards)• Decorative Metal – Select Locations for Aesthetics
• 80%-100% Complete with District Wide Fencing Installations• Exceptions:
• EAH Freshmen Academy Sites (due to ongoing construction)• SAH Freshmen Academy Sites (due to ongoing construction)• Galvez Middle (due to Flood Recovery)• Primary Schools w/ PE on Bus Loading Until Covered Pavilion Complete
• Sorrento Primary• Spanish Lake Primary• Prairieville Primary
• Security Fences are ready for Access Controls where Applicable
![Page 20: 1. SAHS Academy - Complete 2. EAHS Athletics - Complete 3 ... · districtwide covered play pavillions status of $1,500,000.00 fund group 1 – sps,dvp,cps – under construction -](https://reader034.fdocuments.in/reader034/viewer/2022052104/603f6ef13487c064a5468715/html5/thumbnails/20.jpg)
LOWERY CLASSROOM AND OFFICE ADDITION
THE PROJECT IS IN THE CONSTRUCTION DOCUMENTS PHASE
THE ANTICIPATED BID DATE IS JAN. 2018
STATUS
![Page 21: 1. SAHS Academy - Complete 2. EAHS Athletics - Complete 3 ... · districtwide covered play pavillions status of $1,500,000.00 fund group 1 – sps,dvp,cps – under construction -](https://reader034.fdocuments.in/reader034/viewer/2022052104/603f6ef13487c064a5468715/html5/thumbnails/21.jpg)
DHS ‐ REPURPOSE THE OLD LIBRARY
Design start expected in spring 2018
Need to confirm the needs of the current Administration
STATUS
![Page 22: 1. SAHS Academy - Complete 2. EAHS Athletics - Complete 3 ... · districtwide covered play pavillions status of $1,500,000.00 fund group 1 – sps,dvp,cps – under construction -](https://reader034.fdocuments.in/reader034/viewer/2022052104/603f6ef13487c064a5468715/html5/thumbnails/22.jpg)
DUTCHTOWN PRIMARY CLASSROOM ADDITION
PROGRAM CONFIRMATION PHASE IS COMPLETE
ATTEMPTING TO BRING THE HARD BUILDING CAPACITY UP TO MATCH THE K-5 PROTOTYPE
INCLUDES CLASSROOM ADDITION, SPACE ASSIGNMENT MODIFICATIONS TO INCREASE THE ADMIN AREA, SECURITY FEATURES AND COVERED PLAY
SCHEMATIC DESIGN PHASE BEGAN SEPT 20
STATUS
![Page 23: 1. SAHS Academy - Complete 2. EAHS Athletics - Complete 3 ... · districtwide covered play pavillions status of $1,500,000.00 fund group 1 – sps,dvp,cps – under construction -](https://reader034.fdocuments.in/reader034/viewer/2022052104/603f6ef13487c064a5468715/html5/thumbnails/23.jpg)
FUTURE HIGH SCHOOL – SITE PLANNING AND PERMITTING
Architectural Selection for Site Planning and Permitting was completed in 2016
Remson Haley Herpin and Domain Design were selected as the Design Team
We will begin site planning process in Spring 2018
We will reapply for a Wetlands Permit once a preliminary site plan has been agreed upon
STATUS
![Page 24: 1. SAHS Academy - Complete 2. EAHS Athletics - Complete 3 ... · districtwide covered play pavillions status of $1,500,000.00 fund group 1 – sps,dvp,cps – under construction -](https://reader034.fdocuments.in/reader034/viewer/2022052104/603f6ef13487c064a5468715/html5/thumbnails/24.jpg)
FUTURE HIGH SCHOOL – SITE PLANNING AND PERMITTING