1-s2.0-S0960148105002831-main (1)

download 1-s2.0-S0960148105002831-main (1)

of 21

Transcript of 1-s2.0-S0960148105002831-main (1)

  • 8/12/2019 1-s2.0-S0960148105002831-main (1)

    1/21

    Renewable Energy 31 (2006) 20422062

    Design of grid connected PV systems considering

    electrical, economical and environmental aspects:

    A practical case

    Alberto Ferna ndez-Infantesa, Javier Contrerasa,,

    Jose L. Bernal-Agustnb

    aE.T.S. de Ingenieros Industriales, University of Castilla-La Mancha, Avda. Camilo Jose Cela s/n.,

    13071 Ciudad Real, SpainbDepartment of Electrical Engineering, University of Zaragoza, Calle Mar a de Luna, 3., 50018 Zaragoza, Spain

    Received 5 August 2005; accepted 28 September 2005

    Available online 2 November 2005

    Abstract

    This paper presents the complete design of a photovoltaic installation that may be either used for

    internal electric consumption or for sale using the premium subsidy awarded by the Spanish

    Government. Electric optimization strategies are detailed in the project, as well as the sizing of the

    photovoltaic installation and economic and financial issues related to it. The project optimizes the

    electricity demand, improving reactive power and studying the convenience of hourly discrimination

    fees in addition to the design of the photovoltaic installation. A specific computer application for the

    automated calculation of all relevant parameters of the installationphysical, electrical, economical

    as well as ecologicalhas been developed to make the process of calculating photovoltaic

    installations easier and to reduce the design development time. Moreover, the budget of the

    photovoltaic installation is included, as well as its corresponding financial ratios and payback

    periods. Finally, the conclusions reached in the technical and economic design of the installation areshown.

    r 2005 Elsevier Ltd. All rights reserved.

    Keywords: Photovoltaic energy; Power optimization; Renewable energies; Computer application

    ARTICLE IN PRESS

    www.elsevier.com/locate/renene

    0960-1481/$ - see front matterr 2005 Elsevier Ltd. All rights reserved.

    doi:10.1016/j.renene.2005.09.028

    Corresponding author. Tel.: +34 926 295464; fax: +34 926 295361.E-mail address: [email protected] (J. Contreras).

    http://www.elsevier.com/locate/renenehttp://www.elsevier.com/locate/renene
  • 8/12/2019 1-s2.0-S0960148105002831-main (1)

    2/21

    1. A brief history of the project

    The project starts as a response to the inquiry placed by the High School Ojos del

    Guadiana (Fig. 1) in Daimiel, Ciudad Real, Spain, to the Industrial Engineering School

    at Ciudad Real to study the feasibility of a photovoltaic installation within their premises.Preliminary studies begin in September 2004 and the project is finished in March 2005.

    Within these 6 months, the forecasted electric demand, the available surface to place the

    solar arrays, overall funding, and other relevant data are exhaustively studied in order to

    build a design according to the needs of the Centre. The main innovation of this project

    resides in the development of a computer application to design the photovoltaic

    installation connected to the grid. This application considers all relevant parameters,

    allowing for an interactive design that takes into account all the electric, financial and

    economic data simultaneously. In addition, we have reduced the development time and run

    several sensitivity analysis studies to compare different solutions.

    2. Proposals for optimizing the electricity consumption

    The activities oriented to optimize the electricity consumption have produced the results

    described in the following subsections.

    2.1. Feasibility study of the electricity demand of the Centre

    The results of the preliminary study of the electrical consumption confirm a worrying

    increase in the demand: from 32,200 kWh and 23,200 kVArh in year 2000 to 44,070 kWhand 28,900 kVArh in 2004, as shown inFig. 2. In 2005, the trend is even sharper. With the

    beginning of the construction of a new annex building equipped with 2 classrooms and a

    library, demand forecasts are even bigger. The prediction of electric demand for 2005 is

    48,100 kWh and 32,000 kVArh. Thus, we plan a strategy based on three key points to

    reduce the electricity bill:

    1. Optimization of the current electricity consumption studying the possibility of including

    reactive compensation equipment and the convenience of signing for different hourly

    price discrimination fees.

    ARTICLE IN PRESS

    Fig. 1. Computer simulation of the High School Ojos del Guadiana building in Daimiel, Ciudad Real, Spain.

    A. Fernandez-Infantes et al. / Renewable Energy 31 (2006) 20422062 2043

  • 8/12/2019 1-s2.0-S0960148105002831-main (1)

    3/21

    2. Reduction of the electric demand in the next years, proposing basic rules for savingenergy and the selection of new electrical equipment in the future.

    3. Feasibility study of a photovoltaic installation connected to the low voltage network

    that would cover part of the annual demand of the Centre with solar energy.

    To calculate the demand for each bimonthly period, or even for a monthly period, is a

    complex task, due to the presence of seasonality, with peaks during the months of January

    and February (corresponding to the March invoice) and troughs during July and August,

    in which the Centre is closed (September invoice). The most precise way to adjust all data is

    to use a moving averages model of 6 periods (equivalent to 1 year).

    To predict the electricity demand for 2005 we proceed to seasonalize and deseasonalizethe consumption data from 2000 to 2005, using the centred and non-centred 6-point

    moving averages model [1]as shown below:

    Pmt

    Pt6it

    Ti

    6 , (1)

    Pmct PmtPmt1

    2 , (2)

    IEt Tt

    Pmct, (3)

    where Tiis the demand in the bimonthly period i. Assuming that the active and reactive

    energy consumptions for a 2-month period are known, we calculate the moving averages

    values for 6 periods, as indicated in (1); later, we find the centred moving average value,

    Pmci, from Pmiand Pmi1, as shown in (2). And from the moving averaged value centred

    in period iand the demand of that period, we obtain the seasonality index of period Ti,

    IEi, as shown in (3).

    Since the algorithm based on moving averages condenses all the data of the year in a few

    values, we use linear interpolation for year 2005 to approximate more accurately. Fromavailable data of the JanuaryFebruary periods for the years 20002004, we extrapolate

    the same data for the year 2005, and the same process is repeated for all bimonthly periods.

    With the actual data from 2000 to 2004 and the first forecast for 2005 we proceed to

    ARTICLE IN PRESS

    0

    10000

    2000030000

    40000

    50000

    60000

    kWh/kVArh

    Active Energy Reactive Energy

    2000 2001 2002 2003 2004 2005

    Year

    Fig. 2. Annual development of the electricity demand of the Centre and future trend obtained using interpolation.

    A. Fernandez-Infantes et al. / Renewable Energy 31 (2006) 204220622044

  • 8/12/2019 1-s2.0-S0960148105002831-main (1)

    4/21

    calculate the seasonality indexes for each of the periods. Once this is done, we order theseasonality indexes in columns and we calculate the seasonality indexes corresponding to

    each of the bimonthly periods, so that the sum of all of them is equal to 6, which is the

    number of periods considered in a yearly cycle. With this we obtain the factors to weigh the

    linear estimation for the complete year (obtained from the overall consumption data in

    previous years, as shown inFig. 3). In this way, we obtain the weighted demand for each of

    the bimonthly periods. To approximate the demand profile even more, we have distributed

    the result for each bimonthly period between the two months, using a smooth distribution

    function that considers the number of working days of the month.

    2.2. Compensation of reactive energy

    The compensation of reactive energy may result in a 4% bonus in the electricity bill, as

    opposed to the current 5% penalty, if it were possible compensate between 90% and 98%

    of the total reactive energy demand. Currently, for every billing period, the average value

    of the power factor cos j is given by

    cos j Eaffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffi

    E2aE2r

    q , (4)

    where Ea and Er are the values of the active and reactive energy demands, respectively,during the billing period.

    Using Eq. (5) we can calculate the penalty or the bonus applied by Spanish law; it is

    limited to 47% in case of penalty, and to 4% in case of bonus:

    kr% 17ffiffiffiffiffiffiffiffiffiffiffiffiffi

    cos2 jp 21. (5)

    In our calculations we specifically take this fact into account for the year 2005. Later, we

    compare the bills with and without compensation to obtain the annual savings.

    Likewise, we calculate the reactive power of the equipment necessary to compensate the

    reactive demand, based on the total amount of the demand (with the exception of a baselevel demand of the entire year, which is consumed by static equipment and concentrated

    within the daily 8 h with the highest demand). Thus, a piece of equipment of 17.5 kVAr

    should meet the demand 100% of the time, smaller units ranging from 12.5 to 15 kVAr

    ARTICLE IN PRESS

    Cos

    0

    2000

    4000

    6000

    8000

    10000

    12000

    Jan-00 May-00 Sep-00 Jan-01 May-01 Sep-01 Jan-02 May-02 Sep-02 Jan-03 May-03 Sep-03 Jan-04 May-04 Sep-04 Jan-05

    kVAh/kVArh

    0.00

    0.20

    0.40

    0.60

    0.80

    1.00

    1.20

    Active Energy Reactive Energy Cos

    Fig. 3. Development of the active and reactive electricity demands of the Centre, showing seasonalities.

    A. Fernandez-Infantes et al. / Renewable Energy 31 (2006) 20422062 2045

  • 8/12/2019 1-s2.0-S0960148105002831-main (1)

    5/21

    may be unable to meet the demand sometimes, and the compensation would not be

    optimal (98% of reactive demand).

    2.3. Reduction of electricity consumption

    We present a series of actions for the following years, especially for 2005, where the

    demand shows a marked trend to increase. The suggested actions are fundamental to keep

    a certain level of independence with respect to the future incomes obtained from

    photovoltaic generation. The actions can be reduced to the following ones:

    Rational use of energy. Replacement of obsolete equipment of high consumption whenever possible. Progressive renewal of current lighting equipment by new equipment with reflectors and

    electronic ballasts.

    Discarding the use of electricity for heating (furnaces, convectors, accumulators, etc.),only allowing it for heat pumps and refrigerators.

    Adaptation of the computer equipment: selection of moderate consumption feeders andLCD-type screens.

    Publicity campaign oriented to the students promoting consumption moderation andenvironmental consciousness in public and in private.

    Periodic reporting of the energy savings results.

    3. Photovoltaic installation design method

    Once the convenience of having a solar photovoltaic installation has been decided, we have

    to consider the limited economic funds available to the Centre. Thus, instead of choosing a

    traditional design based on power from generators and inverters we seek a more flexible design

    method that takes into account all the parameters that can have an influence on: performance,

    production, financial data, available subsidies, remuneration for selling electricity, taxes

    applied to the remuneration, annual quota in concept of repayment once the electricity sales

    income is discounted, etc. This custom-made concept is the most innovative feature of this

    project;Fig. 4reflects the main differences between both design philosophies.

    In this way, our automated calculation of the solar photovoltaic installation generates

    numerous advantages compared to a traditional design method:

    It considers many more parameters, in fact, more than 60. It allows for a better-adjusted design where we can alter parameters such as power,

    surface, orientation, production of energy, profitability, etc.

    Fast sensitivity analysis of influential parameters. Faster design process with many scenarios that reflect particular needs. For a quick modification of the parameters we link our application to a database that

    includes the main features of the most popular photovoltaic panels and inverters; by

    typing the code and the number of units, the application collects all data necessary to

    proceed with the calculations.

    The main factors considered in our computer application that affect the performance of

    the photovoltaic generators are described in following subsections.

    ARTICLE IN PRESSA. Fernandez-Infantes et al. / Renewable Energy 31 (2006) 204220622046

  • 8/12/2019 1-s2.0-S0960148105002831-main (1)

    6/21

    3.1. Solar irradiation data variability

    While theAtlas of Solar Radiation in Spain provides the most optimistic data, the most

    conservative data come from theNASAweb site[2], showing a standard deviation of 3.6%

    and a variability greater than 7%. We use data fromNASA Surface Meteorology and SolarTables (SSE). As shown in Table 1 obtained from [3], it can be observed that actual

    readings obtained in the same place by different sources provide results that vary around

    10%. Thus, we consider adequate using the most pessimistic available data.

    ARTICLE IN PRESS

    Fig. 4. Diagram comparing the traditional design process versus our flexible calculation method.

    Table 1

    February and yearly averages of the daily horizontal global irradiation in Algiers, according to different sources

    Information source February Gd(0) (kWh/m2) Yearly average (kWh/m2)

    CDER 3.03 4.23

    Capde rou 3.20 4.60Censolar 3.00 4.37

    NASA 2.90 4.45

    Meteonorm 3.00 4.52

    A. Fernandez-Infantes et al. / Renewable Energy 31 (2006) 20422062 2047

  • 8/12/2019 1-s2.0-S0960148105002831-main (1)

    7/21

    3.2. Losses due to shading over the PV panels

    They can be due to distant shading (trees, posts, nearby buildings, etc.) if shadows

    interpose between the sun and the panels during the day, or due to direct shading, if there

    are several rows of panels arranged in the same horizontal plane.Losses can be important, because of that, the location must be carefully chosen to avoid

    distant shading as much as possible, whereas, to avoid direct shading, we can opt to split

    each row of panels arranged in the same plane, or to elevate them on an inclined surface.

    To estimate losses due to distant shading we use the method proposed by the Institute for

    diversification and energy savings(IDAE)[4] of Spain, by superposing the profile of visible

    obstacles observed from the installation point to a graph of solar trajectories (see Fig. 5).

    Each sector of the graph has an associated loss coefficient that varies according to the

    orientation and the slope of the panels. We calculate each of the sectors intercepted by the

    shading profile and we add up the corresponding coefficients obtained from a table,

    depending on the orientation and slope of the panels. This results in a loss percentage for a

    particular location. This is the only loss contribution that is not automated in our

    program; Fig. 5 shows that there are no obstacles in the solar trajectory and losses are

    negligible (0.2%).

    On the other hand, losses due direct shading are estimated to be around 2% [4]. Lower

    values cannot be considered for a flat-grounded placement, even if the distance between

    two consecutive rows is greater than the one shown in (6), such that

    dmin hvertical

    k , (6)

    where coefficientkis calculated as [tan(611latitude)]1. The latitude of the location is 391

    050 N; therefore coefficient k is: [tan(611391050)]1 [tan(211550)]

    1 2.4855.

    We obtain the height of the panel, according to its dimensions and optimal slopes, from

    Eq. (7). Also, we can deduce the minimum spacing between rows of modules using Eq. (8).

    hverticalLmodsinb hsup, (7)

    dmin kLmod sinb hsup 2:4855 1:593sin30:67 0

    ffi2:55m, 8

    ARTICLE IN PRESS

    Fig. 5. Superposition of the solar trajectories diagram to a panoramic view of the roof for shading calculation.

    A. Fernandez-Infantes et al. / Renewable Energy 31 (2006) 204220622048

  • 8/12/2019 1-s2.0-S0960148105002831-main (1)

    8/21

    where b is the inclination angle that turns out to be 30.671, as shown in Section 3.4. See

    Fig. 6for a pictorial description of the calculations.

    3.3. Losses due to electric conductors

    These losses are important in DC, when the voltage is low. It is crucial to conveniently

    size the conductor sections so that the voltage drop is less than 1.5%. It is also important:

    to place the generators close to the inverters, to work at the maximum DC voltage that the

    panels and the inverters can withstand, to increase the conversion performance, and to

    reduce ohmic losses. Depending on the conductor section considered, our computerapplication calculates losses due to voltage drop in DC.

    3.4. Slope, orientation and glass surface reflexivity of the PV panels

    Usually, if the PV panels are not perfectly oriented to the south (azimuth 01 in the

    northern hemisphere), their orientation can originate a considerable loss of efficiency.

    Likewise, the slope of the panels should be changed two to four times a year to maximize

    the solar absorption, since the optimum slope in the summer is not the same as the

    optimum one in the winter.

    Glass surface reflexivity protects the panels from the accumulation of dirt in the surface;a dirty glass reflects a percentage of energy that increases with the divergence of the

    incidence angle with respect to a perpendicular line to the glass surface plane (a glass

    reflects more light and looks dirtier when you observe it from the side). This causes the

    panels to reflect part of the direct radiation and the majority of the diffuse radiation

    available. Rain can solve this problem, but in the summer season the efficiency of the

    radiation is significantly reduced unless the surface of the panels is cleaned on a regular

    basis.

    We use Eq. (9) to calculate the optimal slope [5]:

    bopt 3:7

    0:69f, (9)where bopt is the inclination angle that optimizes the incident radiation over the panel

    surface for a year, and f is the latitude of the location point. The optimal angle that is

    obtained from Eq. (9) is 30.671.

    ARTICLE IN PRESS

    Fig. 6. Minimum spacing between two consecutive rows of panels as a function of the geometric parameters.

    A. Fernandez-Infantes et al. / Renewable Energy 31 (2006) 20422062 2049

  • 8/12/2019 1-s2.0-S0960148105002831-main (1)

    9/21

    Provided the optimal angle and the annual irradiation over a horizontal surface, (Ga(0)),

    it is possible to calculate the value of the annual irradiation for the optimal anglebopt using

    Gabopt

    Ga0

    14:46104 bopt1:19104 b2opt

    . (10)

    Finally, we calculate the incident effective annual irradiation over the generators surface,

    denoted byGeffb; a, using Eqs. (11) and (12) proposed in[5], including orientation, slope,and reflexivity due to dirt on the surface of the glass

    Geffb; a

    Gabopt g1b bopt

    2 g2b bopt g3, (11)

    gig1ijaj2 g2ijaj g3i; i 1; 2; 3, (12)

    wherea is the azimuth, and the coefficientsg1i,g2i,g3idepend on the degree of dirtiness ofthe panel. For a medium-dirtiness case, the values of these coefficients correspond to the

    ones shown inTable 2.

    3.5. Efficiency of the inverters

    Despite being electrical equipment of high performance in DC/AC conversion, they

    never reach 100% efficiency [6]; they reach their optimum performance in the range of

    8596% efficiency for power values close to the nominal rating, while for the generation of

    small amounts of powerin conditions of cloudiness, start-ups, sunrise and sunsetthe

    efficiency can diminish considerably. Spanish law [7] makes the use of inverters with aminimum efficiency at 25% of the nominal power compulsory, which means selecting good

    equipment turns out to be fundamental. Also, the monitoring of the point of maximum

    power and the adaptation to the variable conditions of generation involves a small loss of

    power during normal operation conditions. For single-phase inverters, the sum of all the

    losses can be about 820% of the total energy generated, depending on the quality of the

    equipment. The data provided by the manufacturers for each model is included in the

    database of the computer application; we also consider a loss factor by monitoring the

    Maximum Power Point (MPP) and the start-up/shutdown of the inverters.

    3.6. Actual power produced by the PV panels

    It is usually lower than the nominal value in catalogues [8]. Spanish law[7]establishes

    that the power, measured in standard conditions, cannot be lower than 90% of the

    ARTICLE IN PRESS

    Table 2

    Coefficients used in (11), with 97% transmittance due to dirt

    Tdirty0=Tclean0 0:97

    Coefficients i 1 i 2 i 3

    gi1 8 109 3.8 107 1.218 104

    gi2 4.27 107 8.2 106 2.892 104

    gi3 2.5 105 1.034 104 0.9314

    A. Fernandez-Infantes et al. / Renewable Energy 31 (2006) 204220622050

  • 8/12/2019 1-s2.0-S0960148105002831-main (1)

    10/21

    nominal power value in catalogues. A breach of contract could be reason for refund

    (almost all the manufacturers freely replace the panels if they do not comply with the

    specification of the 90% of power), but one must consider that the standard conditions:

    1000 W/m2, 25 1C in the surface of the cells and spectral distribution 1.5 AM, in which the

    nominal power is measured, do not correspond to the real working conditions.To reach a temperature of 25 1C in the cells of the panel, it is necessary that the ambient

    temperature is, approximately, 5 1C. Provided that the ambient temperature is usually

    greater than this value, there can be a decrease in the power delivered by the panels because

    the open circuit voltage and the maximum power voltage diminish when the temperature

    increases with respect to the nominal condition (25 1C). However, the current delivered by

    the panel does not significantly depend on the temperature. Therefore, the power delivered

    by the panels is usually lower than the nominal one.

    Our computer application considers the nominal power minus 10%, or the maximum

    percentage guaranteed by the manufacturer, if it were smaller. Then, it is multiplied by a

    variable coefficient[8]that takes into account: (i) the average temperature at noon for each

    month in the considered location and (ii) the decrease of power due to temperature, as

    explained above.

    The relation between the power output of the panels and the nominal power of the PV is

    calculated in

    Preal Pnom 100devnom%

    100

    100 DP 25Tcell

    100

    , (13)

    where devnom (%) is the maximum deviation of power guaranteed by the provider [W], DP

    is the power variation for each degree increase in the temperature with respect to the 251

    Cnominal value [W/1C], and Tcell is the average temperature of the cell during operating

    conditions (atmospheric temperature while the sun is at its zenith plus an empirical

    increment between 8 and 20 1C, depending on the climate).

    Note that ageing and degeneration of the modules causes them to slightly decrease their

    performance each year: due to UV irradiation, severe temperature changes have a

    cumulative effect over the electrical production.

    4. Final design of the grid connected PV installation

    Once all data described in Section 3 are considered, we proceed to obtain the overall

    electricity production for each monthly period, according to the longitude and latitude

    data obtained, using Eq. (14) [5].

    Emonth Pnom Geffect

    G

    FShadow Feff

    kWh

    month

    , (14)

    where Pnom is the nominal power, as indicated by the manufacturer of the photovoltaic

    panels in standard conditions, Geffect is the effective annual incident irradiation over the

    panel surface considering the orientation angle and the panel slope, G is the value of the

    irradiation for whichPmaxis measured: 1000 W/m2, 25 1C,FShadowis a factor that considersthe losses due to shading in the panel, Feffis an efficiency factor including the losses in the

    inverter, the losses in the generators at temperatures greater than 25 1C, and the voltage

    drops in the lines.

    ARTICLE IN PRESSA. Fernandez-Infantes et al. / Renewable Energy 31 (2006) 20422062 2051

  • 8/12/2019 1-s2.0-S0960148105002831-main (1)

    11/21

    With all this, Feffoscillates between 0.7and 0.9 for a standard installation, and mainly

    depends on the quality of the equipment selected. IfFeffwere lower than 0.7 it would imply

    a deficient performance of one or several components.

    The optimal dimension of the photovoltaic installation that meets all High School

    requirements is a plant composed of 72 modules, each module with a peak production of160 peak power or Wp (total production is 11,520 Wp). The plant is arranged in 12 groups

    of 6 modules, where each group produces 960 Wp. The modules are connected in series and

    operate at 210 V and 4.55 A in nominal rate. Every 3 groups of 6 modules are also

    connected to the inverter through a pair of wires, so each pair of wires (4 pairs in total)

    operates at 210 V, 13.65 A and 2880 W (nominal rate). SeeFig. 7for details. The panels are

    oriented to the south forming an angle of 11.231with respect to the main orientation of the

    roofs of the building. The modules are manually mounted on inclinable supports to

    maximize the electric power generation. The optimum slope in case of fixed supports is

    30.671, as calculated in Eq. (9).

    As shown inFig. 8, the generation plant is connected to 3 single-phase inverters; two of

    them withstand 2600 W during nominal operation, and the other one withstands 4600/

    5200 W. The latter can be connected either to 5 or to 6 basic groups of 6 photovoltaic

    modules to reduce total investment without modifying the optimal performance

    ARTICLE IN PRESS

    Fig. 7. Arrangement and connections of the photovoltaic modules.

    A. Fernandez-Infantes et al. / Renewable Energy 31 (2006) 204220622052

  • 8/12/2019 1-s2.0-S0960148105002831-main (1)

    12/21

    conditions. Each inverter comes with its own electrical protections and is connected to oneof the phases (R, S, T) of the low voltage grid, delivering power ranging from 9800 to

    10,400 W. To ensure the optimal protection of the electrical equipment and the inverters

    from their environment, they are located within a 1.50 2.50 m brick-made shelter placed

    beside the High Schools gym, conveniently insulated against rain and humidity and

    adequately ventilated. SeeFig. 9 for an overall 3D view of the installation, including the

    inverters shelter, andFig. 10for a detailed view of the solar panels.

    The power ratio (PGenerator=PInverters) is near 1.10. The efficiency of the inverters istypically 94% (maximum efficiency is 96%). The section of the cables has been enlarged by

    design to reduce DC losses, and the location of the power lines and inverters has been

    chosen to reduce the distance to the MV/LV transformer substation. The lines from themodules to the inverters are aerial, whereas the three-phase line to the main grid is buried

    underground.

    The electrical production of the installation would approximately meet 29% of the

    estimated demand for 2005, as shown in Fig. 11, but it would have met 43% of it in the

    year 2000, 42% in 2001, 35% in 2002, and 32% in 2003. That is why it is equally important

    to take actions to also reduce the electric consumption, as detailed in Section 3.2. The

    calculation of the photovoltaic power production is automated in our computer

    application from data inputs.Fig. 12compares the forecast of the photovoltaic generated

    energy versus the forecast of electrical demand of the High School per month. The energy

    produced per kWp in such conditions is about 1207 kWh per year. This data is far from theoptimistic forecasts of many photovoltaic manufacturers, who predict values between 1300

    and 1500 kWh per year. Note that our installation is optimized for normal operation and

    does not have shading effects [9].

    ARTICLE IN PRESS

    Fig. 8. One-line diagram of the proposed photovoltaic plant.

    A. Fernandez-Infantes et al. / Renewable Energy 31 (2006) 20422062 2053

  • 8/12/2019 1-s2.0-S0960148105002831-main (1)

    13/21

    5. Environmental analysis

    The final design has resulted in an electric power plant composed of photovoltaic

    modules based on polycrystalline silicon technology with a peak power of 11,520 Wp and 3

    single-phase inverters, one of 5200 W and two of 2600 W, totaling 10,400 W in nominal

    operation. Each inverter injects its current to one of the phases (R,S,T) of the low voltage

    grid. The area of each photovoltaic module is 1.26 m

    2

    (1.16 m

    2

    of active area) so that the 72projected modules add up to a collector area of 90.57 m2, whose active area is

    approximately 83.61 m2.

    The estimated electrical efficiency of the modules is approximately 13.5%, losses related

    to orientation, slope and dirt of the modules are estimated around 6.88%, losses due to

    indirect shading are negligible and direct shading losses are around 2%. In addition, power

    losses due to temperature are around 4.42%, assuming that the cells surface temperature is

    12 1C higher than the monthly average temperature when the sun is at its zenith. Power

    losses due to voltage drops are estimated around 1%, due to oversized cable sections. All

    things considered, the power plant generates an average of 1.287 MWh each month, as

    shown in detail inTable 3.On average, 1.158 MWh are injected to the grid per month, considering all types of

    losses, with an 85% efficiency factor. Compared to the thermal data, the electric

    production is equivalent to the combustion of 1.195Tons of Oil Equivalents(TOE) or 1.708

    Tons of Coal Equivalents (TCE), even after assuming a 100% efficiency factor in

    generation, transformation and distribution of the electric power. Considering a more

    realistic scenario and assuming that:

    (1) The electricity would be generated from a combined cycle or an equivalent technology

    whose efficiency factor could be around 50% on the average.

    (2) A 95% efficiency factor in each successive voltage adjustment: from 12,000 V-

    250,000 V, from 250,000 V-20,000 V and from 20,000 V-380 V.

    (3) Additional losses of 5% in low voltage distribution, then, we would have an

    approximate overall efficiency factor of 40%.

    ARTICLE IN PRESS

    Fig. 9. 3D view of the installation showing the DC circuit and the location of the inverters shelter.

    A. Fernandez-Infantes et al. / Renewable Energy 31 (2006) 204220622054

  • 8/12/2019 1-s2.0-S0960148105002831-main (1)

    14/21

    ARTICLE IN PRESS

    August 3%

    July 4%

    June 4%

    May 3%

    April 3%

    March 2%

    February 2%

    Forecast 71%

    September 3%October 2%

    December 1%November 1%

    January 1%

    Fig. 11. Monthly PV generation forecast vs. annual electric demand of the Centre.

    Fig. 10. 3D detail view of the solar panels arrangement on the roof.

    A. Fernandez-Infantes et al. / Renewable Energy 31 (2006) 20422062 2055

  • 8/12/2019 1-s2.0-S0960148105002831-main (1)

    15/21

    So, to generate the same electric power using fossil fuel [10], it would be necessary toburn up to 2.934 TOEor up to 4.197 TCEevery year, even without considering the cost

    and power needed to extract, refine and deliver the fuel, which would increase prices even

    more.

    All of this implies that, throughout a life-span of 25 years for the entire installation, the

    photovoltaic modules would produce the same power as 73.35 tons of oil or 104.93 tons of

    coal, with the subsequent reduction in emissions of CO2, NOX and SOX. So, the

    consideration of the environmental impact changes the global appreciation of the

    installation [11], especially if we take into account the relatively small dimensions and

    the power produced in the plant.

    6. Complete budget of the PV installation: economic and financial case studies

    We show inTable 4the complete budget of the PV installation.

    Current legislation in Spain[12]regarding the production of electrical energy originated

    from renewable energy sources, waste and cogeneration, allows all the energy generated by

    the PV system to be injected into the grid. In addition, the energy consumed by the PV

    system can be bought back at a much lower price than the one paid to the PV system for its

    production.

    For installations with less than 100 kW of installed power, the energy tariff is establishedat 575% of the average electric tariff, or the reference tariff (updated yearly) for the first 25

    years of the installation, decreasing to 460% in the following years.

    We carry out two different economic and financial case studies using the methodology

    in [10]. In the first case study we assume that the investment is financed through a loan

    of 90% of the total value, and the remaining 10% comes from the Centres own funds. In

    the second case study, the investment is completely financed with external funds from

    a loan that covers the part of the investment that is not subsidized by the Spanish

    Government[13].

    Next, we present the financial parameters:

    Required investment without Value Added Tax (VAT): 64,577 h. VAT: 16% (10,332 h). Taxes not related to subsidies are 8472 h, they are refundable a

    year later.

    ARTICLE IN PRESS

    0

    1000

    2000

    3000

    4000

    5000

    6000

    7000

    Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec

    [kWh/mon

    th]

    PV Generation

    Electric Demand

    Fig. 12. Monthly PV generation forecast vs. monthly electric demand of the Centre.

    A. Fernandez-Infantes et al. / Renewable Energy 31 (2006) 204220622056

  • 8/12/2019 1-s2.0-S0960148105002831-main (1)

    16/21

    ARTICLE IN PRESS

    Table3

    Averagesola

    rirradiation,

    temperature-relatedlosses,generatedandgrid-delivered

    powerandincomefromelectricitysalesoftheproposedinstallation

    (aminussign

    indicatespositiveearnings)

    Month

    IrradiationG

    eff

    (b,a

    )(kWh/m2

    month)

    Temperature

    lossescoefficient

    Photovoltaic

    gen.power

    (kWh/month)

    Griddelivered

    power(kWh/

    month)

    Economic

    remunerationa

    (h)

    Electricitybill

    (h)

    Monthly

    differencea

    (h)

    January

    68.0

    0

    1.027

    665.4

    9

    598.9

    4

    288.3

    5

    560.5

    8

    272.2

    3

    February

    85.5

    7

    1.015

    827.4

    9

    744.7

    4

    358.5

    4

    673.8

    5

    315.3

    0

    March

    138.3

    2

    1.001

    1319.05

    1187.1

    5

    571.5

    4

    575.8

    5

    4.3

    2

    April

    159.4

    1

    0.990

    1504.27

    1353.8

    4

    651.7

    9

    463.3

    6

    188.4

    3

    May

    195.7

    6

    0.971

    1811.78

    1630.6

    0

    785.0

    3

    423.4

    7

    361.5

    6

    June

    211.4

    9

    0.941

    1895.86

    1706.2

    8

    821.4

    6

    381.2

    9

    440.1

    8

    July

    238.0

    1

    0.904

    2050.85

    1845.7

    7

    888.6

    2

    263.4

    5

    625.1

    7

    August

    210.9

    4

    0.902

    1813.59

    1632.2

    3

    785.8

    1

    192.5

    9

    593.2

    2

    September

    159.4

    1

    0.923

    1401.71

    1261.5

    4

    607.3

    5

    417.7

    4

    189.6

    1

    October

    104.9

    8

    0.966

    966.5

    7

    869.9

    2

    418.8

    1

    537.1

    8

    118.3

    7

    November

    67.0

    9

    1.001

    639.7

    7

    575.8

    0

    277.2

    1

    589.7

    2

    312.5

    1

    December

    56.7

    8

    1.022

    553.1

    1

    497.8

    0

    239.6

    6

    441.0

    7

    201.4

    1

    Total

    1695.7

    9

    15,4

    49.5

    5

    13,9

    04.5

    9

    6694.1

    7

    5520.1

    5

    1

    174.0

    2

    Monthly

    average

    141.3

    2

    0.97

    1287.46

    1158.7

    2

    557.8

    5

    460.0

    1

    97.8

    4

    aWithoutVAT.

    A. Fernandez-Infantes et al. / Renewable Energy 31 (2006) 20422062 2057

  • 8/12/2019 1-s2.0-S0960148105002831-main (1)

    17/21

    Depreciation period of the investment: 20 consecutive years. Total electrical power produced by the photovoltaic modules: 11,520 Wp. Inverter estimated production: 10,400 W. Photovoltaic estimated production: 13,904 kWh/year. Electric reference tariff (ERT): 0.083728 h/kWh, as shown in the Official State Bulletin

    of Spain, BOE (12/31/2004).

    Electric remuneration (h/kWh): 575% of the ERTduring 25 years; 460% of the ERTuntil the end-of-life of the installation.

    EURIBOR interest rate for a 6 months loan (%): 2.5% yearly. Period to pay back the subsidized loan: 7 years. Amount of the subsidized loan: 57,494 h (90% of total investment minus the total value of a

    diesel-engine alternator which could generate the same power for 8000h of use/year). Non-recoverable subsidy given by IDAE: 20% of the subsidized amount, or 11,499 h. Inter-annual inflation: 2.5%. Inter-annual energy inflation: 2%. Self-financed investment: 6457 h. VATreturn: 8472 h. Period to return the VATof the installation: 7 years. Economic Activity Tax (EAT): 0.7212 h/installed kWp; nevertheless, the installation

    would be free of this tax since it would not reach 37.24 h (corresponding to a 51 kWp

    installation).

    State taxes: 35% of net profit (excluding depreciation of equipment+VAT). Estimated maintenance costs: 0.018 h/generated kWh. Insurance cost to cover defective equipment: 0.4% of the installation value each year. Investment required to generate an equivalent amount of electric power using a diesel-

    engine alternator: 801 h for a 1.74 kW engine working 8000 h/year.

    Depreciation of the equipment: Although it is expected that the photovoltaic modulescan be operative after 25 years of use, its salvage value is 0 h.

    Considering all the costs involved, earnings from electricity sales (after taxes) for thetwo studied cases are shown as follows.

    Scenario 1: mixed financing: 10% self-funding,90% external funding.

    Internal rate of return (IRR): 14.65%. Payback period: 6 years and 6 months.

    ARTICLE IN PRESS

    Table 4

    Complete budget of the PV installation

    Description Total (h)

    Photovoltaic modules, supports and accessories 49,720.08

    DC circuit, connection to the grid and grounding 883.70

    Inverters and related devices 6980.95

    Civil engineering project work 2593.80

    Labor costs and equipment installation 2060.30

    Civil engineering project management work 1805.36

    Total 64,044.41

    A. Fernandez-Infantes et al. / Renewable Energy 31 (2006) 204220622058

  • 8/12/2019 1-s2.0-S0960148105002831-main (1)

    18/21

    Aggregate profit: 110,916.80 h. Net Present Value (NPV): 73,696.31 h. Costbenefit ratio: 0.46 in 10 years, 1.24 in 15 years, 2.08 in 20 years, and 2.85 in 25

    years.

    Scenario 2: 100% external financing.

    Internal rate of return (IRR): 16.00%. Payback period: 7 years and 2 months. Aggregate profit: 109,561.07 h. Net present value (NPV): 73,079.76 h. Costbenefit ratio: 0.42 in 10 years, 1.20 in 15 years, 2.05 in 20 years, and 2.82 in 25 years.

    In the second case study, the cash flow is basically the same as in the first one; only the

    development of the income varies: the aggregate profit during the payback period (first 7

    years) is less positive compared to the first case. Also, the IRR has a higher value because

    the interest of the loan (subsidized by IDAE) is not affected by inflation; in addition, the

    interest of the consumer credit does not affect the NPVand the aggregate profit value,

    since high interest rates of up to 20% have been tested without significant variation in the

    aggregate profit.

    To conclude,Fig. 13depicts the annual cash flow for scenarios 1 and 2, which is almost

    identical in both cases.Figs. 14 and 15present the development of the annual incomes for

    scenarios 1 and 2, respectively.

    7. Conclusions

    After calculating the dimensions of the PV installation, the estimated power production,

    the total budget and two financial case studies, these are the main conclusions that we have

    reached:

    The installation requires an initial investment several times greater than the costof diesel-engine alternator equipment that can generate the same amount of power in

    1 year.

    Economic incentives, like subsidies for part of the investment, and the chance to sell allthe electricity generated at 6 times its market price, are required to make a photovoltaic

    installation profitable.

    An even greater investment is necessary to generate the electricity required to meet thedemand of the Centre completely only using photovoltaic energy, since the installation

    can only meet 30% of the annual electrical demand. Nevertheless, the income from sales

    of the electricity generated is greater than the amount of the electricity bills.

    Developing an installation of this type promotes the use of environmentally conscioussources of energy and motivates students to use renewable energies.

    With the subsidized loans given by the IDAE, the installation becomes viable in areasonable period (nearly 8 years) and generates profits from the beginning; these profitscan be used to partially pay the Centres electric bills. Once the investment has been

    repaid, the annual earnings from PV electric generation can fully compensate the

    electricity bill, which would allow for considerable budget savings.

    ARTICLE IN PRESSA. Fernandez-Infantes et al. / Renewable Energy 31 (2006) 20422062 2059

  • 8/12/2019 1-s2.0-S0960148105002831-main (1)

    19/21

    The remuneration given to PV electric generation in Spain (575% of the ERTestablished by law for a 25 years period) allows making a profit from the investment in

    the long term. Also, non-recoverable subsidies reduce the payback period. The actual

    cost of this remuneration scheme represents just 2% of the special electricity taxes,

    approximately 0.08% of the electricity bill, whereas the nuclear moratorium tax almost

    absorbs 40%, or 1.6% of the electricity bill. The aggregate profit in the long term, 2025 years, doubles the initial value of the

    installation. The NPV is also positive and the IRR guarantees that an increase in

    inflation will not affect the profitability of the installation.

    ARTICLE IN PRESS

    -10000

    -5000

    0

    5000

    10000

    15000

    0 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25

    Years

    Economic ActivityTax

    Financing installments

    VAT

    Electricity income

    1

    Fig. 13. Annual cash flow components for scenarios 1 and 2.

    -8000

    -6000

    -4000

    -2000

    0

    2000

    4000

    6000

    0 4321 5 9876 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25

    Years

    Fig. 14. Annual income development for scenario 1 (mixed financing: 10% self-funding, 90% external-funding).

    A. Fernandez-Infantes et al. / Renewable Energy 31 (2006) 204220622060

  • 8/12/2019 1-s2.0-S0960148105002831-main (1)

    20/21

    The durability of the equipment guarantees optimal operation for 25 years, exceptaccidents, for which a specific insurance can be purchased until the installation is totally

    repaid in about 8 years, just after the subsidized loans are fully repaid.

    Finally, the remuneration obtained from the sale of PV-generated electricity canproduce profits that can both repay the necessary loans to get the installation started

    and also the electricity bill, even if the electric consumption remains constant during thefollowing years.

    References

    [1] Newbold P. Statistics for business and economics, 5th ed. Englewood Cliffs, NJ: Prentice-Hall; 2002.

    [2] National Aeronautics and Space Administration.http://www.nasa.gov

    [3] Labed S, Lorenzo E. The impact of solar radiation variability and data discrepancy on the design of PV

    systems. Renewable Energy 2004;29:100722.

    [4] Technical conditions for PV installations connected to the grid [in Spanish]. Report available from the

    publication services of the Institute for Diversification and Energy Savings, Spain. http://www.idae.es, 2002.[5] Lorenzo E. Energy collected and delivered by PV modules. In: Luque A, Hegedus S, editors. Handbook of

    photovoltaic science and engineering. West Sussex, UK: Wiley; 2003. p. 90570.

    [6] Caamano E, Lorenzo E. Inverters in PV grid connected systems: an assessment on the proper selection. In:

    Proceedings of the 13th European photovoltaic solar energy conference, Nice, France, October 1995.

    p. 19001903.

    [7] Royal Decree 1663/2000 on the connection of photovoltaic installations to the low voltage network [in

    Spanish]. September 29, 2000. Available at http://www.boe.es

    [8] Caaman o E. Grid connected photovoltaic buildings: characterisation and analysis. PhD thesis, Polytechnic

    University of Madrid, Superior Technical School of Telecommunication Engineers, Madrid, Spain, 1998 [in

    Spanish].

    [9] Caaman o E, Lorenzo E. Photovoltaics in grid-connected buildings: energy flow and economic aspects. Prog

    Photovoltaics: Res Appl 1995;3:13543.[10] Bernal-Agustn, JL, Dufo-Lopez, R. Economical and environmental analysis of grid connected photovoltaic

    systems in Spain. Renewable Energy, in press, doi:10.1016/j.renene.2005.06.004.

    [11] Spiegel RJ, Kern EC, Greenberg DL. Demonstration of the environmental and demand-side management

    benefits of grid-connected photovoltaic power systems. Sol Energy 1998;62(5):34558.

    ARTICLE IN PRESS

    -2000

    -1000

    0

    1000

    2000

    3000

    4000

    5000

    0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25

    Years

    Fig. 15. Annual income development for scenario 2 (100% external financing).

    A. Fernandez-Infantes et al. / Renewable Energy 31 (2006) 20422062 2061

    http://www.nasa.gov/http://www.idae.es/http://www.boe.es/http://localhost/var/www/apps/conversion/tmp/scratch_5/dx.doi.org/10.1016/j.renene.2005.06.004http://localhost/var/www/apps/conversion/tmp/scratch_5/dx.doi.org/10.1016/j.renene.2005.06.004http://www.boe.es/http://www.idae.es/http://www.nasa.gov/
  • 8/12/2019 1-s2.0-S0960148105002831-main (1)

    21/21

    [12] Royal Decree 436/2004 establishing the methodology for the update and systematisation of the legal and

    economic regime of the activity of production of electrical energy in special regimes [in Spanish]. March 12,

    2004. Available athttp://www.boe.es

    [13] Line of financing ICO-IDAE for renewable energies and power efficiency projects [in Spanish], 2005.

    Available athttp://www.idae.es

    ARTICLE IN PRESSA. Fernandez-Infantes et al. / Renewable Energy 31 (2006) 204220622062

    http://www.boe.es/http://www.idae.es/http://www.idae.es/http://www.boe.es/