1-s2.0-S092658051000138X-main
-
Upload
jessica-oliveira -
Category
Documents
-
view
215 -
download
0
Transcript of 1-s2.0-S092658051000138X-main
-
7/29/2019 1-s2.0-S092658051000138X-main
1/11
Teaching construction project management with BIM support: Experience and
lessons learned
Forest Peterson a,, Timo Hartmann b, Renate Fruchter a, Martin Fischer a
a Stanford University, Department of Civil and Environmental Engineering, United Statesb Twente University, Department of Construction Management and Engineering, Netherlands
a b s t r a c ta r t i c l e i n f o
Article history:
Accepted 21 July 2010Available online 4 November 2010
Keywords:
Building Information Model (BIM)
Scopetimecost
Estimate
Schedule
Quantity takeoff
Construction design
Project management
Project-based learning
Situative learning
Virtual learning
Thispaperpresentsexperiences andlessons learned duringthe introduction ofBuilding Information Models (BIM)
in construction engineering project management courses. We illustratively show that the introduction of
BIM-basedproject management tools helped theteachers of twocourses to develop more realistic project-based
class assignments that supported students with learning how to apply different formal project management
methods to real-worldproject management problems.In particular,we show thatthe introduction of BIMallows
educators to design a class project that allowed the use of more realistic cases that better simulate real-world
project conditions, helped students to learn how different project management methods integrate with each
other, integrate change management tasks in a class assignment, and learn how to optimize project plans.
2010 Elsevier B.V. All rights reserved.
1. Introduction
Knowledgeof project managementtheory is importantto participate
on a project. While mistakes in the classroom result in lower marks,
mistakesin thefieldcan affectmorale, waste resources, andin theworst-
case scenario cost someone's life. Academics universally agree that
practically applicable knowledge about construction management tools
and methods is difficult to learn. This is mainly because explicit
understanding about how to apply formal methods and tools within
the unique situationsencountered on most construction projects is hard
to gain. The application of most formal tools and methods requires
project managers to have an in-depth understanding of project-specific
information. Forexample, if a critical equipment or subcontractor fails to
perform as anticipated what impacts will this have on time and cost and
whatimpact will potential alternative operationmethods have. Answers
to such questions cannot be generalized and trivialized; they cannot be
developed through the formulaic application of the necessary project
management concepts, but depend greatly on project-specific informa-
tion. This provides a problematic situation that universities face during
the development of construction management curricula. In the past,
students had to learn practical application of methods on very simple
abstract examples because of the limited time available. This approach
did not allow students to learn how to adjust the application of project
management methods to specific real-world project contexts. To
overcome this shortcoming, educators complemented their formal
illustration of the method through abstract examples with stories of
howproject managers applied the methods successfullyon pastprojects.
While this learning approach is an improvement to only learning the
formal working of the method, the retrospective characterof storytelling
does little to help students to build up an understanding about how to
apply a certain method to solve a practical problem. In hindsight, a story
of a successful application of a method to a project management
problem, in particular, if told well, sounds obvious, while applying a
method to solve a problem that onefaces is notso easy. To overcome this
dilemma a combination of the two learning methods is necessary, during
which students applyformal methods within simulated contexts of real-
world construction projects. The design of such projects within the tight
boundaries of construction management classes is not easily possible
because it simply takes too much time for students to understand the
method and all the project-specific information to apply the method.
Due to this problem, construction professionals still acquire much
knowledge through learning-by-doing [1] with on-the-job training
activities, and it is not surprising that many criticize construction
management university programs as ineffective [2].
In this paper, we argue andprovidefirst illustrativeevidencethat the
integration of project management tools based on BuildingInformation
Models (BIM) can help educators to develop project management
class projects that simulate realistic practical situations, such as the
Automation in Construction 20 (2011) 115125
Corresponding author.
E-mail address: [email protected] (F. Peterson).
0926-5805/$ see front matter 2010 Elsevier B.V. All rights reserved.
doi:10.1016/j.autcon.2010.09.009
Contents lists available at ScienceDirect
Automation in Construction
j o u r n a l h o m e p a g e : w w w. e l s ev i e r. c o m / l o c a t e / a u t c o n
http://dx.doi.org/10.1016/j.autcon.2010.09.009http://dx.doi.org/10.1016/j.autcon.2010.09.009http://dx.doi.org/10.1016/j.autcon.2010.09.009mailto:[email protected]://dx.doi.org/10.1016/j.autcon.2010.09.009http://www.sciencedirect.com/science/journal/09265805http://www.sciencedirect.com/science/journal/09265805http://dx.doi.org/10.1016/j.autcon.2010.09.009mailto:[email protected]://dx.doi.org/10.1016/j.autcon.2010.09.009 -
7/29/2019 1-s2.0-S092658051000138X-main
2/11
generation of a complete bid package based on a complete set of bid
documents. In particular, we show that BIM supports project manage-
ment learning activities with two distinctive features. First, BIM allows
the storage and generation of project-specific information in a
structured way. This structured way of working allows students to
understand the in-depth information of a specific project's context
relativelyquickly.Additionally, BIM allows the storage of project-related
information in a central database. This central storage allows for the
automation of many tedious work tasks that are required during theexecution of formal project management methods and the reduction in
repetitive tasks that students traditionally had to do redundantly. These
twoadvantages allow educatorsto designclass project assignments that
simulate real project conditions more realistically than before.
The structure of this paper is as follows: First, we elaborate
theoretically on the earlier-described practical dilemma that construc-
tion management educators face today using education theories and
develop a theoretical hypothesis of how BIM can overcome this
dilemma. After briefly discussing our research methodology, we then
provide first illustrative evidence for our hypothetical claim by
qualitatively analyzing two project management classes that applied
BIM-based applications. Afterwards, we discuss the theoretical implica-
tionsof ourfindings from analyzing the two classes. We close the paper
by briefly suggesting directions for future research and by providing a
summarizing conclusion.
2. BIM to support project management education
Project planning and execution depends on the valuing and
trading-off of the scope, time, and cost of the project [3,4]. Plans and
specifications represent theproject scope. Scope defines the work that
is required to complete the project successfully. Based on the scope,
project planners estimate the time it takes to carry out the work and
the costs of doing so. In practice, whether practitioners are aware of it
or not, project planning and execution is integrated project manage-
ment. In practice, the plans, specifications, quantity takeoff, schedule,
and estimate document the scope, time, and cost. Project managers
constantly translate information from these documents to understand
how the scope, time, and cost relate. While a number of formal projectmanagement methodsexist, suchas, Earned ValueManagement[5],AIA
Integrated Project Delivery (IPD) [6], and ConsensusDOCS 301 series BIM
addendum [7], that promise to allow forthe generation of project plans
that integrate scope, time, and cost, the application of these formal
methods in practice still depends heavily on the experience of the
project manager. Projects operate in drifting environments [8] and,
thus, it is an art, based in tacit-knowledge, to understand when and
how to apply a specific project management method during the
planning and production processes.
To help students learn how to generate integrated project plans,
educators usually base their project management courses on two
underlying technical approaches: The cognitive scheme approach and
the behavioral approach [9]. Thecognitiveapproach focuses on learning
standardized project management methods in a formal way. Educatorstry to identify the most important methods and assume that students
mainly need to internalize the theoretical working of these methods to
be able to generate professional project plans. The cognitive learning
approaches consider the psychological learning behavior of students,
but they hardly help students to learn how and when to apply the
learned project management methods in real-world situations. At best,
educators help students to learn about possible applications of those
methods using relatively basic and abstract assignments. On the other
hand, educators who apply the behavioral approach base the students
learning on the assumption that it is possible to learn integrated project
management practice by imitating the successful behavior of others. To
do so educators gather experiences, critical incidents, and specific
occurrences frompractice. Educators assume that telling students these
stories helps them to learn how to apply project management methods
in real-world contexts. In terms of successful learning, these approaches
often fail because they neglect the complexity of the multiple
intertwined factors that even for the most experienced project
managers require some time to understand for a specific project
context. Stories cannot provide the thick context needed to understand
howproject managers in thepast successfullyapplied themethod. To be
successful, educators need to integrate both of the traditional learning
methods. Such integration requires complex teachinglearning assign-
ments that enable the application of formal project managementtheories through role-play in simulated environments of real-world
project settings [9]. Only with such assignments, students can develop
the voluntary intuitions [10] that help them to not only learn formal
project management methods, but also to develop strategies that allow
them to understand when and how to apply these methods in practical
contexts.
So far, developing such complex real-world situations for learning
integrated project management is not easily possible [11]. Due to time
and resource constraints it is not possible to design assignments during
which students would need to createa project plan that integrates scope,
time, and cost with project data that represent real-world detail. The
manualgeneration of an integrated project plan is a labor-intensive task.
Students need to understand the project drawings and specifications,
take off the quantities, find matching data about costs and productivity
rates in standard databases, and finally, establish a schedule and a cost
estimate to show the relation between scope, time, and cost. Within the
scope of most construction management curricula the workload of
project planning makes it impractical to learn cost and time manage-
ment as an integrated topic [12]. If integrated project management is
presented to the students, the case project details that practicing project
planners need to account for in the field must either be simplified to a
large extent or the case focused on challenging niche scenarios that
students would encounter as construction engineers.
Educational researchers have long established that computer
technologies are an important component to support project-based
learning [13,14]. The advancement of BIM-based project management
tools has the potential to overcome thesepracticaleducational problems
and, with further advancement, additional practical educational pro-
blems,such as learning rates.This is no differentwith theintroduction ofintegrated BIM-based tools in project management courses. There have
been significant achievements made in the use of BIM software tools to
teach architectural design and quality analysis [15,16].
An adaptable BIM system has taken form [1720] since the
introduction of computers into the construction industry. The construc-
tion industry has applied BIM in practice. Engineers and project
managers are applying BIM-based tools on a number of projects [21].
While general issues with collaboration and representation of context
are still stumbling points [17,22], several key changes supporting BIM
tools' capacity to structure and centrally store data has allowed for their
introduction in university classes. In particular, such an introduction is
now possible because:
the availability of toolsfrom multiple vendors provides robustness. the sufficient support for integration and interoperability provides
adaptability of the tools.
the widespread adoption of BIM provides a suitable selection of case
material.
the level of detail transition functions built into most BIM tools
resolves issues with representation across inherently different
abstractions of scope, time, and cost, and
the improved function for storing and linking information with BIM
components provides integrated data reuse.
These recent improvements in BIM tools allow educators to provide
their students with off-the-shelf software tools thatoffer them structured
support with integrating scope, time, and cost of a project plan in a way
that was not easily possible earlier. First, the application of BIM-based
116 F. Peterson et al. / Automation in Construction 20 (2011) 115125
-
7/29/2019 1-s2.0-S092658051000138X-main
3/11
tools reduces the time that students need to spend on some of the
labor-intensive tasks. BIM-based tools, for example, decrease the time for
students to take off the quantities to generate the bill of materials,
schedule,and estimate [23]. Further, theintegration of modernBIM-based
tools with existing standard cost and productivity databases reduces the
time that students need to spend on collecting and keying these data
manually. Additionally, BIM-based tools theoreticallyallowthe integrated
application of several project management tools for one project. For
example, BIM-based tools allow the integration of traditional CPM Ganttchart visualization methods of schedules with 4D visualizations and
line-of-balance visualizations [24]. With traditional tools that did not rely
on an integrated BIM database to accommodate iterations in design or
optimization checks, students had to adjust changes in the underlying
project data in each of the representations manually. Due to these
workload constraints,it wasdifficult foreducatorsto facilitatethe learning
of different methods in an integrated fashion. Hence, educators
traditionally introduced and presented each method in isolation and
designed assignments that only addressed one of these methods. With
BIM-based project management software, it is now possible to use
different methods that all use data from one data source. This allows
students to learn how to use different methods in an integrated fashion.
Another advantage of the use of BIM-based project management tools
during project management class assignments is the possibility to
introduce teaching of change management methods and principles.
Incorporating changes in project plans is one of the most important tasks
of project managers in practice. Since construction projects exist in
drifting environments they require the frequent adjustment of project
plans to reflect changing conditions. In current project management class
projects,changemanagement,however, plays a rather minor rolebecause
the incorporation of changes in already established project plans is a very
time-consuming and labor-intensive task. BIM-based project manage-
ment tools allow for the storage of once established relations between
scope, time, and cost and thus enable the automatic update of most parts
of a project plan when changing one of the sub-parts.
All these advantages together allow educators to design better class
projects that allow students to learn how to optimize project plans.
Having an integrated BIM that allows different applications to calculate
schedules and estimates and to visualize project plan information, BIMshould allow students to find bottlenecks, wrong assumptions, and
other deficiencies in their project plan. Additionally, with the help to
changeone part of the integrated project plan and automatically seethe
consequences on the other parts, students are theoretically able to
evaluate, even within the restricted time and resource constraints of a
project management course, different alternatives to mitigate discov-
ered deficiencies. Overall, this functionality should allow students to
understand how to optimize project plans, something that was not
possible before.
Concluding, we hypothesize that the application of BIM-based
project management tools allows educatorsto design class projects that
allow for:
1. the use of holistic real-world cases.2. the combined teaching of different integration methods for project
planning information.
3. the incorporation of change management tasks in assignments, and
4. increased opportunities to teach project plan optimization.
3. Research methodology
To provide evidence for the aforementioned hypotheses, we
qualitatively analyze how BIM supported the learning of project
management methods in two construction management university
classes:The ManagingFabrication and Construction class at Stanford
University and the Integrated Project Management class at the
Twente University in The Netherlands. This multiple case study
allowed us to investigate the phenomenon of how BIM can support
construction management education within a real-world educational
context [25]. We selected both cases mainly because of our familiarity
with the classes. The first author of the paper worked as a teaching
assistant for the Stanford University class for two years. The second
author also assisted the Stanford class for one year and since has
designed the class at Twente University based on the experiences
gained teachingthe class at Stanford. Thethird author routinelyselects
from the Stanford student pool of knowledge for another course and
provides the opportunity to observe the students utilizing the skillsthey gained the previous quarter compared to students from other
universities [26]. The fourth author of the paper was the driving force
behind developing a class that integrates BIM-based technologies at
Stanford in thefirstplace. Theobservation of students in a consistently
presented classroom environment provides some degree of a
repeatable context and therefore allows some comparison of observa-
tions across multiple academic years. Both classes are well suited to
replicate findings across two quite different educational settings.
While the one class allowed us to provide evidence for the paper's
hypotheses using the setting of a research school in the Silicon Valley
with many non-local students, the second case allowed us an
opportunity to replicate these findings in the setting of a Western
European school with a mainly local student population.
The experimenters collected data, as will be described later, to allow
analysis that will lead to improvements in the classes, to allow
comparison between classes and to share results with others that
want to implement a similar class. Our close participation with the two
classes allowed us to collect detailed data from a number of sources.
First, and maybe most importantly, we were able to observe the
students and their progress closely. Additionally, we collected other
class-related information such as lecture notes, slides, assignment texts
and solutions,and intermediate andfinal grades. Additionally, through-
out teachingthe classes, students were encouragedto provide feedback
on the learning process and the class design. The different data sources
together allowed us to increase the reliability of our research results
through thetriangulation of data [25,27]. One tool that proved helpful to
provide structure to these rather messy and ad-hoc data collection
efforts was the generation of a number of research reports during our
early and ongoing problem definition and during our later data analysis[28]. Those drafts helped us to understand the data and observations
from the classes better and served, as mentioned by Jorgensen [29], a s a
valuable addition to the often irregular and unsystematic data
collection. A comparison of the final grades from one class (the other
class followed a stricter problem-based form and so did not include an
examination) withprevious and successive class quarters compares the
affect of the BIM-based environment on the students' examination
scoresand provides insight into anychanges in thepatterns of strengths
and weaknesses in knowledge.
The participant research set-up allowed us to gain insights into the
classes and collect data from different sources without influencing
learning processes by artificially introducing outside observers that
most likely would have influenced the natural behavior of both
educators and students. We can assume that students and educatorsbehaved in a normal classroom manner. While the direct involvement
with thedesign andexecution of thetwo classes allowedus to gain deep
insights into the learning activities and progress of the students [29], it
might have caused observer bias during dataanalysis. To counteract the
inherently biased analysis of data, we engaged the third author of the
paper, who did not actively participate in the classes, to review the
findings from an outsider's perspective [30]. In this way, we were
hopefully able to counteract some biases during the analysis of our
observations from the classes.
To provide evidence for the four hypotheses the next sections
describe illustratively two different project management classes that
incorporated BIM-based project management tools in their class
assignments. We provide background about the classes, describe the
data we collected, and provide evidence for the hypotheses.
117F. Peterson et al. / Automation in Construction 20 (2011) 115125
-
7/29/2019 1-s2.0-S092658051000138X-main
4/11
4. Case description
4.1. Managing fabrication and construction class Stanford University
4.1.1. Class background
The first example of a BIM supported project-based learning format
is the graduate-level Managing Fabrication and Construction course
taught at Stanford University. The class has been incrementally moving
towards the BIM-based format as permitted by software tools since1994. The class consisted of a mixture of lectures, in-class exercises,
assigned labs, team projects, presentations, discussions, and examina-
tion. With parallel coursework in cost estimating, expected undergrad-
uate coursework in a dedicated scheduling course, and the practical
experience that graduate students typically have from internships and
employment, most students were already proficient in the non-
integration aspects of project management. To extend the prior
knowledge of the students, the course's goal was to provide an
environment for students to learn advanced project management
topics,such as the significance of integrating scope takeoff, time process
scheduling, and cost estimating; as well as less easily observable issues,
such as accounting for time-variable cost, identifying the driving
production rates, understanding the implications of large and small
batching of work operations, and minimizing wasted resources. In
general, throughout the course, the students should have gained an
intuition for maximizing productivity, ensuring feasibility, and mini-
mizing risk. Through the introduction of BIM-based project manage-
ment software tools into the labs and a team project, the students had
the opportunity to engage in holistic real-world cases in a learning-by-
doing environment. In this environment, the students applied several
project management methods to develop and optimize a project plan
with the goal that they achieve an intuitive understanding of when to
apply these methods.
The course format relied on documents from recently constructed
projects as case study material. The use of real documents from a recent
or ongoing project presented the students the same medium they will
encounter as construction managers, therefore representing real-world
conditions closely. The case project's project manager provided the
students with thearchitectural scope andspecifiedquality intheformofa BIM. Hence, the students were not responsible for BIM modeling
themselves. The autumn 200809 quarter serves as the case example
usedhere,while previous and subsequentquartersprovide comparative
context. The 39 enrolled students divided themselves into 13 project
teams of three. In the autumn 200910 class, rather than use a
pre-designed BIM system, each group designed the system integration
from a selection of available software tools. Accompanying the software
set-up, lectures presented the underlying theories for the use of
ontological breakdown structure languages to convey context, the
inherent trade-offsbetween scope,time, andcost, andthe strengthsand
weaknesses of these abstract concepts. The class started with the
introductionof thecase project, a simplified BIM, and several BIM-based
applications that manage scope, time, and cost. The goal of this
introduction was to allow students to form their teams, visit the project,gain familiarity with the project documents and the lab environment,
install the BIM software tool, and acquaint themselves with the
software's user interface.
During the first lab, students learned to use the software tools and
generate an initial project schedule using the critical path method at an
operations level of detail without consideration for a feasible location
breakdown. The students developed a time plan using the software tools
as individual components without integration. The student teams relied
on spreadsheet software and paper notes to represent calculations for
quantities and durations. In this stage, the students typically found that
the limitations of the system were in the one off trait of the non-
integrated system. Changes in non-integrated plans resulted in rework of
nearly the entire plan. The students presented the results using the
provided simple BIM integrated with their time schedule as a 4D model.
This simple integration served as a first introduction of the integration
concept. Lectures at this phase emphasized case studies that illustrate
misrepresentations and context breakdowns of project management
typical of non-integrated project plans. After the initial introduction and
lab, the teaching assistantintroducedthe students to the three integration
software tools necessary to complete the integrated project plan (Table 1).
In the second lab, the students used the actual project case study
material to complete one full cycle of passing data through the
integrated project plan BIM system, resulting in an initial integratedprojectplan.The baseline wasa significant turningpointin thecourse as
students spent a significant amount of time intensively learning the
integration details necessary to complete an iteration or first pass. Lab
assistance and sometimes vendor technical support was necessary to
complete this lab. The students used the line-of-balance project
management method and iterated several times to find a solution
with a consistent workflow and labor resources. Professor Fischer
provided the students international project contacts after the second
lab. From this list, the students selected a project and contacted the
projectmanagerto obtainproject documentsand collaborate to develop
a BIM for the project. The students identified contradictions and
opportunities for optimization. The students then shared the results
with the class and sponsor through a presentation and written report.
Overall, the students' learning process replicated to some degree
practical experience in a controlled environment.
4.1.2. Case analysis
Thestudentswereable to createa completely integrated projectplan
witha mixof software from multiple vendors within theconstraintsof a
lab assignment. The students could not have produced a comparable
project plan without BIM in the same or less time at the same level of
detail and with the same completeness. The completeness and detail in
the integrated project plan then provided the holistic and thick context
that created a more realistic environment for the students. The student
preparation for this lab took several weeks and the after-lab reports and
presentations required a similar period. No one vendor specifically
supported the integrated system, but most software had import/export
functions that coupled with interoperable formats and software
specifically intended to allow universal import/export functionalityand provided for a non-vendor-specific integrated system. To provide
context, thecase study material provided a 40 MBBIM (does notinclude
the quantity takeoff, schedule or estimate). Student teams consistently
required over thirty lab hours to iterate through the fully integrated
system of scope, time, and cost. This duration is with support from a
couple of lab assistants and sometimes vendor technical support; with
less support the students would have taken longer. Compiling the
integrated projectplan consisted of seven steps: (1) operation selection,
(2) takeoff or linking of BIM components to the operations, (3) deriving
recipe-formulas for operations without a corresponding component in
the BIM, (4) scheduling, (5) compiling a 4D model check, (6) cost
estimating, and (7) an audit review. The operation selection took the
students two hours, presumably longer than typical, since they were
learning the software tools at the same time. The students used astandard database with a work breakdown structure the BIM repre-
sented automatically in each component; therefore, the operation
selection included defining the work breakdown structure. The linking
of BIMcomponents to the operations list for the takeofftook aboutnine
hours (thehoursgiven areteam hours)to complete 240 distinct links to
component groups for a BIM with 15 element types and 66 locations to
define the foundation, eight floors, and six structural and two
architectural workzones. The next step was the derivation of specific
recipe-formulas for each input to, in this case, thirty output quantities;
this step took about six hours. The schedule calculations of duration,
network sequence, and resource leveling turned out to be significantly
faster using the line-of-balance software than Gantt chart or CPM
software. Compiling activities from operations, determining the driving
production rate, linking network logic, assigning crews, and optimizing
118 F. Peterson et al. / Automation in Construction 20 (2011) 115125
-
7/29/2019 1-s2.0-S092658051000138X-main
5/11
took twelve hours to complete. The scheduling tool imported the
quantities by location through an XML interface from the recipe-
formulas. The students calculated durations from the product of the
quantities, production rates,and crew assignments.At this level of detail
and stage of iteration in optimizing, it would have required significantly
more time with common CPM tools. A preceding class attempted a
detailed location-based schedule with a CPM software tool and
considered the task impractical. The students compiled a 4D model
from the BIM and the corresponding schedule; the students corrected
the errors in the schedule they noticed and made iterative checks of
workflow, resource leveling, key milestones, and total duration. The 4D
model required 400 distinct links between the activities and BIMcomponents, requiring about two hours. The number of distinct links in
the quantity takeoff (240 links) and the 4D model (400 links) differ
because of the methodthat eachsoftwaretool'slink function works.The
quantity takeoff tool represents locations in the operations list and links
the BIM components by location automatically, therefore resulting in a
reductionof one-sixtiethin thelinking effort.The 4D modeling tooldoes
not automatically recognize location (unless the students use a perfectly
precise BIM component and schedule activity naming standard) but the
increaseis notsixtyfold. This is because thescheduleis at a lower level of
detail than the quantity takeoff so there are fewer items to link to an
equal number of BIM components, overall still resulting in more links
than the quantity takeoff. The next step was to pass the quantities from
the recipe-formulas and the time-variable quantities from the schedule
to the cost estimate. This step took one half hour. Professionals andstudents alike often ignore or at best abstract the time-variable
quantities in non-integrated plans. This is likely because they must
complete the schedulefirstand then update theestimate if theschedule
changes. The reuse of quantities for the estimate removed a data entry
task and reduced the data entry error rate typically 10% or greater
reducing rework and mistakes. The last step was to audit for mistakes
and pass through the process again. Since the students had previously
formed the links the corrections did not require linking or derivation of
recipe-formulas, the most time consuming steps, and so was nearly
instant. This last task usuallytook onehalf hour. Thestudentsperformed
thesesteps sequentially. This thirtyhour duration includes assumptions.
The teaching assistant checked the project plan in depth only for
completeness, total cost, anda quickreview forquality.He assumed that
the quality of the plan is suitable, that student teams applied their
resources equally, and that the team efficiency and coordination was
perfect. Therefore, in reality, the true duration to complete the
integratedproject planmay have been greater or smaller thanobserved
and the true experiences of students we observed may have been
inconsistent. This would result in a false measure of performance. For a
given level of effort to create the project plan, with BIM the students
could better document their work for future reference or iteration. For
example, the students produced six files for the integrated system:
takeoff, estimate, recipe-formula, schedule, 4D, and BIM. Some students
with professional experience in estimating intuitively understood the
value of theBIM-based system,but believed thatthey could complete an
estimate in less time using a non-BIM format. To them, the value of BIMlay in the repeatable aspect. Non-BIM iteration often takes an equal
amountof time since thestudents must mostlyreconstructthe schedule
and cost information each time. The students with professional
experience perceived that with BIM, the first iteration took longer, but
all subsequent iterations reduced the workload significantly.
The students' experience with learning project management
practices through a BIM-based system resulted in key observations
made by the students of how they were able to save time by the
following advantages that BIM offered during the process of generating
an integrated project plan:
BIM System workflow
With the BIM system, corrected mistakes propagated throughout
the integrated project plan and significantly reduced reworkdelays(non-integrated formats tendto fall apart if students do not
find their mistakes prior to progressing to the next component of
the plan).
Integrated functions (recipe-formulas) for the quantities of BIM
components that were not included in the BIM allowed reduced
workload and facilitated the integration of the project plan across
multiple levels of detail.
Reduced data entry allowed increased levels of detail, allowing
greater accuracy per item.
The BIM-based process contributed to reduced waste of project
resources often attributed to miscommunication between the
quantity takeoff engineer, the scheduler, and the estimator. The
students accomplished this reduction through BIM-enabled cross-
functional communication.
Table 1
Software used in the Stanford University class. The relative sequence that software tools are listed represents the integration path, there are multiple integration paths, in particular
the 200910 class.
Year BIM (pre-made) Scope Time Cost and database Integration|
interoperable
Ontology
language
200607
10 teams
AutoCAD 2006 Architectural
Desktop (ADT)
Primavera P5.0
Graphisoft
Control 2007 v2532
Navisworks
JetStream v5.5
CIFE WBS [28]
200708
17 teams
AutoCAD 2007 ADT Tocoman iLink3 2007
ADT v3.0.9.1
Primavera Project Manager
P5.0
Sage-Timberline Estimating
Extended v9.4.3
Common Point 4D AROW [31]
Vico Control 2007 v2614 Sage-Timberline RSMeans
Commercial Knowledgebase
Tocoman Express
v2.0
Tocoman Quantity
Manager
200809
13 teams
Revit 2009 Archi. Tocoman iLink3 2009 Revit
Beta v3.0.10.4
Primavera Project Manager
P6.1 | P6.2
Sage-Timberline Estimating
Extended v9.5 prerelease
Navisworks Manager
2009.1
MasterFormat
2004 [32]
Vico Control 2009 Beta
v47284
Sage-Timberline RSMeans
Commercial Knowledgebase
Tocoman Express
v2.0.3
Microsoft Project Tocoman Quantity
Manager
200910
10 teams
Tekla 15.0
Revit 2010 Archi.
Tocoman iLink3 2009 Tekla
Autodesk QTO
Vico Constructor
Micr osof t Pr oj ect 2007 Vico Estimat or Naviswo rks Man age
2010
Varies per
student team
Vico Control 2009 Tocoman Express
v2.0.3
Tocoman Quantity
Manager Vico Presenter
119F. Peterson et al. / Automation in Construction 20 (2011) 115125
-
7/29/2019 1-s2.0-S092658051000138X-main
6/11
With these time savings, students were able to learn advanced
project management concepts, such as:
Time-based quantities: Among the quantities that are most
difficult to derive for project managers are time-based quantities,
for example, the quantity takeoff unit for a crane. The students
derived this quantity from the schedule rather than the BIM.
Intuition for workflow: Another difficult concept to learn in a
classroom environment is an intuition for workflow. With the
line-of-balance project management methodstudents gained this
intuition through observation of scenarios where slowing an
operation to better align the workflow resulted in reduced project
duration.
Projectmonitoring: TheBIM-based system provided the expected
quantities by location and time, therefore providing a better
understanding of project monitoring.
Project management fundamentals: Most field hands can intui-
tively explain the fundamentals of project management; they
learn this through years of practical experience. The BIM-based
process represented the same knowledge through a formal
representation of context and relations.
The learning-by-doing format exposed the students to a less
predictable environment than typical of a classroom. This was animportant point to providing a practical experience. To help counter
inherent issues with software, the teaching assistant established a
relationship with a specific IT specialist at each vendor. In this way,
when necessary,support andpatches were available withinhours.As BIM
becomes an increasingly common component of project management
tools, the skills to set up and maintain the BIM system will become
increasingly important. Through this dynamic unstructured experience,
the students learned to adapt to andmitigate issuesas theyappeared.This
same skill should prove useful when dealing with longstanding project
managementissues identified throughearlyapplications of BIM [17], such
as model-sharing, process knowledge, stakeholder motivation, human
computer interface limitations, informationflow, and the lackof generally
accepted exchange standards [22].
The BIM-based format helped students to form an intuitiveunderstanding of the critical path (CPM), location-based scheduling
(LBS), and 4D visualization project management methods. These
methods helped to illuminate the need for greater interaction between
the BIM modeler, takeoff engineer,scheduler,and estimator.Often,once
students had completed the scheduling sub-part of the integrated
project plan, having then fulfilled the two roles of BIM modeler and
scheduler, they grasped the significance of integration and became
aware of the reduced workload and significance this would have on the
completenessand detail they would be able to represent. TheBIM-based
system helped the students to learn optimization of the schedule, a goal
when maximizing productivity while ensuring constructability. The
optimization was feasible with the location-based scheduling applica-
tion using the line-of-balance view. The students optimized for
workfl
ow, resource leveling, and duration. They iterated throughthese three optimization foci until changes were negligible. Without
the BIM the connection between the quantities and the schedule and
from the schedule to the costs would have been lost, and the students
would not have gained as holistic an understanding of the scope, time,
and cost relations.
4.2. Integrated project management Twente University
4.2.1. Class background
The second case example is the Master class Integrated Project
Management at Twente University in The Netherlands. The class
introduced BIM-based technologies to support students with efforts to
integrate the three projectmanagement aspects of scope, time, and cost
using an in-class project that closely resembled realistic conditions. In
particular, students had to explore the current technological possibil-
ities to integrate project management databy learning the functionality
of BIM-based applications and applying them to establish an integrated
project plan for a real-world project.
During the 2009 class,students successfully developed an integrated
project plan for a two storey mixed use building for a local theater
company in Hengelo, The Netherlands. The functions of the planned
building comprise the storage of the group's theater props, the hosting
of thegroup's offices, andthe provision of a recitalroom.The projectwas
in close proximity to the university which allowed students to visit the
building site to obtain location-specific site information. The educator
provided the students with the complete set of bid documents for thisproject as the information basis for the generation of the integrated
project plan. Therefore, we can very well state that the class project
resembled real-world conditions very closely.
Overall, 14 Construction Management and Engineering graduate
students participated in the class. For the project assignment, the
instructor divided these 14 students into three groups offive, five, and
four students. In the first two weeks of the class, the instructor
introduced thestudents to theconcept of BIMand gavethemthe task to
evaluate a number of BIM-based project management applications
(Table 2) and choose an initial application suite for establishing an
integrated projectplan. At the beginning of every consecutive week, the
instructor then addressed one aspect of integrated project management
during a one to two hour lecture.
In the first week of generating the integrated project plan, thestudents generated a 3D BIM from the project drawings and specifica-
tions. Each student group selected a hierarchical modeling approach by
dividing the different components of the building into a product
breakdown structure (PBS).The groups then assigned the responsibility
to model in BIM the different components of the PBS to different group
members. During the 3D building information modeling, all groups
reported struggles with missing details in the 2D drawings. This forced
students to make assumptions about the scope of the project to allow
them to generate a complete BIM suitable for project management.
In the second week of the project planning effort, the students then
created an initial cost estimate using quantities extracted automatically
from their BIM linked to cost recipes. If the vendor provided standard
recipes the students used these,else, the students createdtheir own. Such
recipes, or assemblies, expand from the BIM the required representationof the construction steps and resources in the production information to
allow the calculation of costs based on the BIM components quantities
extracted from the BIM [33]. Within one week, all groups were able to
Table 2
Software used in the Twente University class.
Year BIM Scope Time Cost and database Integration Ontology
200809
5 teams
Revit 2009 Archi.
Vico Constructor
Tocoman iLink3 2009
Revit v3.0.10.4
Microsoft Project Tocoman Excel
Estimator
Navisworks Manager
2009.1
Vico Control 2009 Tocoman Express v2.0.3
Vico Constructor Tocoman Quantity
Manager
Vico Estimato r Vico Pr esen ter
120 F. Peterson et al. / Automation in Construction 20 (2011) 115125
-
7/29/2019 1-s2.0-S092658051000138X-main
7/11
produce a cost estimate that was closely integrated with the scope
modeled in the BIM. Based on the chosen recipes the students then
developed a construction schedule in the next week of the class.
During the final two weeks of the class, students then optimized
their project plan. In week five, students analyzed and improved their
construction sequence by linking the geometrical scope of the project
with their construction schedule using 4D technology [21,34]. This
technology allowed them to visualize their planned construction
sequence spatially and to encounter and solve technical and spatialconflicts inherent in their initially planned construction sequence. In
week six, students used line-of-balance diagrams [24] in an effort to
optimize the schedule to ensure the balanced use of all the required
resourcesover theproject duration. To track theprogress foreach week,
thestudents summarized their week'swork withina weeklyreport. The
report outlined the strategy they used during the week, described the
newparts of theintegrated projectplan,and evaluatedthe usefulness of
theBIM-basedsoftware thegroup hadchosen to support thegeneration
of that aspect of the project plan.
At the end of the class, the students incorporated a number of
changes into their final integrated project plan. Students had to
change their integrated project plan in consideration of a number of
hypothetical events. The main objective of this last assignment was to
assess how well the students had integrated each of the project
management sub-concepts into their overall project plan by testing
howgood each group wasable to quickly changeany of the integrated
aspects of scope, time, or cost and determine the effects of changes on
one of these aspects on the other two. The change scenarios for the
students were:
Task 1: The client company requests a change in the design of the
facility. Enlarge the area of the storage space by 30%, change your
integrated project plan accordingly and generate a report that
clearly communicates the influence of this design change on the
overall cost and duration of the project.
Task 2: Due to a strike of all workers, all construction work stops
during weeks three and four after the start of your project. What
are the effects of this stop on the costs and on the schedule in yourintegrated project plan?
Task 3: The client asks you to accelerate work to make up the time
you lost during the strike. He offers to pay an additional Euro
50,000 if you manage to bring the project home at the originally
planned completion date. Please assess whether you are able to
accelerate your project plan within this additional budget to reach
the initially planned completion date.
4.2.2. Case analysis
In summary, each of the three groups was able to develop an
integrated project planwithin theclass duration of lessthan ten weeks.
The value of theirintegrated project plans became particularly evident
when each of the groups was able to complete the three final projecttasks that required them to incorporate scope, schedule, and resource
changes into their project plan. It would not have been possible forthe
students to finish this assignment without the availability of a truly
integrated project plan.
It is questionable whether the students would have been able to
generate the integrated project plan without the help of BIM-based
applications in the first place. In particular, the quantity take-off task
would have probably been too labor intensive. Despite the inexperience
of the students with cost estimating and the unfamiliarity with the
specific project, all student groups were able to generate a reasonably
detailed and complete estimate within a week. We can attribute this
increased productivity during the estimatingtask of the second week to
advantages discussed in the next paragraph that BIM provides the
students during their work.
These advantages relates to the general requirement of a cost
breakdownstructure for estimates that categorizes the components of
a building into different cost categories. To develop such meaningful
cost categories estimators require a good understanding about the
technical functions of the building design. Students reported that
modeling theproject in BIMhelped them to understand theimportant
technicaland geometricaspects of thebuilding. This hints towards the
possibility that the structured way of modeling a project in BIM
supported students with their efforts to understand project drawingsand specification at the start of a class project. This better
understanding, in turn, allowed students to develop different cost
categories that helped them to structure their estimating effort. In
addition to the time savings due to a faster understanding of the
building design, the automated functionality of taking-off quantities
directly reduced the time that students had to spend manually
counting and measuring the quantities for each of the cost categories
defined previously. Overall, the time saved allowed students to focus
on more important conceptual tasks related to project details that
they would probably not have been able to account for without the
use of BIM-based project management tools.
Next to the overall success with generating an integrated project
plan, students were also able to apply different project management
methods simultaneously using the integrated project information. All
groupscreated a 4D model,a line-of-balance schedule,and a cash flow
diagram that allowed for a meaningful analysis of their project plans.
However, even with these advanced project management tools at
hand, students were not able to optimize their integrated project plan
on a global level. The advanced tools used project information in
different formats and levels of detail than the integrated project plan.
To use these tools, students, therefore, had to change and enter
information that they imported from the integrated project plan
manually within the advanced project management tool. This
required change with respect to the level of detail making it difficult
forstudentsto understand howthe problems they identified using the
advanced tools would affect the integrated project plan on a global
level. While students were able to understand a part of their project
plan better using these advanced methods and find deficiencies of the
plan at the detailed level of functionality of the advanced projectmanagement tool, they were not able to optimize their project plans
globally according to the problems they realized. This finding might
point to a general trade-off that project managers have to make when
planning with integrated project management software. On one hand,
a completely integrated project plan can save much time and effort
during the planning phase and allow for quick adjustment of specific
information. On the other hand, there are situations when an
integrated project plan cannot display information in a meaningful
way to enable sound project management decisions. In this case,
project managers should recreate some information using another
format making it likely that the format is not directly interoperable
with the rest of the project plan and, thus, obstructing the core benefit
of BIM to store all project related information in a central data
repository. In the next section, we will describe the findings from thetwo cases.
5. Case analysis, findings, and implications
5.1. Comparison of the Stanford class exams
The grades of the course's final exams provide an indicator of the
students' knowledge at the end of the class. The class exam is paper-
based. To provide as transparent a representation as we could, we
chose to compare theexam results for thefour years of available exam
results, starting with 2006:
2006: the last time the class was taught without the use of BIM-
based project management tools for all students and all aspects of
121F. Peterson et al. / Automation in Construction 20 (2011) 115125
-
7/29/2019 1-s2.0-S092658051000138X-main
8/11
scope, schedule, and cost management (called non-BIM in this
paper)
2007: the class was taught with a number of BIM tools, but not yet
as a completely integrated project plan. The students built an
integrated project plan as a finalproject butcould notintegrate the
cost sub-part and so completed this separately.
2008: thefirst time students used BIM to integrate all parts of their
project plan.
2009: the BIM format was changed from a single system compiled
from multiple vendor tools prior to the class to a format allowing
the students to design a system or select a system provided by a
vendor.
While the overall structure of the exam did not change over the
years, the 2006 non-BIM exam did not include integration-based topics,
such as the work breakdown structure ontology, theories of different
planning methods, and integrated project modeling. A comparison of
scores in the main project management topics can provide answers to
how the introduction of an integrated project plan allowed by
BIM-based tools changed the learning patterns of students compared
to the students that did not learn with an integrated toolset for topics
like project task networks, critical path method, location based
scheduling, and schedule float. To account for differences in the exam
questions for each of the main topic areas over the years, we chose to
compare the questions for the areas that did not change. To allow for a
quantitative comparison of the scores we present the average scores of
students for each of the four years as percentages of the maximum
number of possible points.
As would seem intuitive, overall, the students who learned withBIM
were better at concepts related to integrated scope, time, and cost, but
were not as good at calculating scope, time, andcost manually (Table 3).
They performed equally on qualitative schedule network logic analysis,
that is, defining where critical activities, activity float and total float
reside, scheduling best practices, and planning. The scores from the
resource-leveling question do not show any change in understanding.
Thismay bedue tothe use inall fourclasses of a line-of-balance tool that
included resource leveling as a core component, possibly some studentsintuitively grasped this concept well while othersdid not.Therefore, the
students in thebaselinecourse mayalready have realized the benefitsof
learning the resource-leveling as an integrated topic. The comparison
shows that students instructed without BIM appear equivalent or better
at computationally preparing a critical pathmethod (CPM)schedule,are
better at location-based scheduling (LBS) concepts, and better at
calculating float. We must be cautious with this conclusion since the
overlap in scores indicates that the difference between the means may
not be significant. Students that learned without BIM appear better at
ontological work breakdown(WBS)concepts andtheirscores indicate a
more cohesive group. Without a baseline this trend is not precise. One
trend that may be a factor is software vendors have increasingly
included the WBS in their software as an automated function, removing
the students' focus on this item. For example, Revit automaticallyassociates components with the work breakdown structure ontology
from MasterFormat, Uniformat, and OmniFormat. The main conclusion
for the impact of advanced planning methods we can draw is that the
range of student scores appears to have tightened, indicating a more
cohesive learning experience for the students. The shift in advanced
planning scores may be due to the multi-BIM format; the tradeoff could
be that while thestudents become more competent in building the BIM
system itself they may not be building a BIM system that covers all the
methods and topics. The single-BIM and non-BIM course material was
selected and specifically checked that it provided a complete context to
the course topics. The exam comparison indicates that with respect to
the class that partially integrated BIM, the class that completelyintegrated the BIM had a deeper knowledge about how to use multiple
methods, such as line of balance, CPM, and 4D scheduling. In contrast,
the class that used multiple BIM tools lost some of this understanding,
although the best and average students had gained an understanding
comparable to the previous two years, but understood integrated
project modeling topics better. It appears that students did better on
conceptual questions and questions about how to best optimize a
project plan and worse on questions about standard CPM procedures,
such as CPM network scheduling or calculating project float. The exam
results reflect a shift from a quantitatively technical understanding to a
qualitatively holistic understanding of project management methods.
The advanced and integrated project management tools remove the
repetitive and predictable tasks, which are typically computational and
can be testedmore easily, while those tasks thatare holistic and difficult
to define and test remain as manual tasks. Therefore, students exposed
to a series of advanced BIM tools showed some degree of strength in
these manual, more conceptual tasks over understanding the detailed
mechanisms of the computational and repetitive tasks that are now
automated.
5.2. Cross case analysis
The case studies at both universities, while including a different
student demographic and being conducted independently by different
experimenters, found similarities (Table 4). Both student groups were
able to compile an integrated scopetimecost project plan within the
constraints of a class. The Twente format allowed the students to
complete the BIM process on a different timeline than Stanford's,Twente presented the material with a linear series of weekly
deliverables compared to the Stanford approach that emphasized the
final generation and presentation of the integrated project plan. Both
experimenters found the inclusion of either a product breakdown
structure or a work breakdown structure to represent the integrated
projectplan sub-parts andtheir level of detail as a critical attribute. Both
cases included the use of multiple project management methods, with
parallel implementation of 4D modeling, location-based scheduling, and
CPM. Student teams in both classes delivered reasonably detailed
project plans at the unit cost and master schedule levels of detail. Both
experimenters believe that it would not be possible to achieve the level
of detail and the plan completeness without the use of BIM. The failure
or breaking points of both cases were also consistent. Neither class was
able to include the goal of a meaningful global optimization iteration,something that has notbeen attained by anyof theclass observed. It still
requires a significant effort for the students to deliver the level of detail
and completeness; hence, the students were exhausted at the end of
Table 3
Historical comparisons of the final examgrades forCase 1. Percentages indicate the average ratioof examscore to the maximum reachable score for selected questions in each ofthe
exam topics; standard deviation is indicated in parentheses.
Task
network
Resource
leveling
Critical path
method
Location based
scheduling
Float
analysis
WBS
ontology
Advanced planning
methods
Integrated project
modeling
Overall
Non-BIM 86% (18) 83% (13) 85% (23) 91% (13) 82% (10) 85% (3)
Partial-BIM 82% (13) 91% (18) 70% (21) 89% (26) 53% (16) 78% (15) 76% (10) 79% (21) 77% (12)
Single-BIM 82% (13) 86% (14) 78% (17) 73% (26) 74% (22) 61% (18) 87% ( 9) 77% (10) 77% (8)
Multi-BIM 88% (15) 50% (23) 75% (30) 69% (27) 49% (27) 48% (13) 90% (10) 67% (18)
Average 85% ( 3) 77% (19) 77% ( 6) 80% (11) 70% (15) 63% (15) 70% (20) 82% ( 7) 76%
122 F. Peterson et al. / Automation in Construction 20 (2011) 115125
-
7/29/2019 1-s2.0-S092658051000138X-main
9/11
their marathon BIM modeling, quantities scoping, and planning,
scheduling, and estimating sessions and were not interested to push
the assignment boundaries. In earlier non-integrated assignments,
exploration outside the assignment bounds was common amongst the
top ten percent of students, but the experimenters did not observe this
activity on the integrated assignment. However, the average project
plan delivered in the BIM classes was comparable to the solutions
deliveredby the top students in thenon-BIM class.Both classesalso had
trouble with format and level of detail in exchanged data that
additionally restricted the optimization of the project plan.
The core differences between the Stanford University and Twente
classes were the inclusion of BIM modeling, change management, and a
cash flow analysis at Twente. While the BIM modeling and cash flow
were important inclusions that the Stanford teaching assistants should
adopt, it is the changemanagement aspect thatis truly interesting. If the
changeis in project scope or methodof construction, forexample,due to
a changed quality specification, then this is the catalyst for iterative
globalchanges to theintegrated projectplan.Incorporating changes as a
simulation of typical post-award project work is an important
component to move the experience of the students from the typical
class exercise replicating an estimating office to the holistic represen-
tation of the field office environment.
5.2.1. Findings
The aforementioned cases clearly show that the introduction of
BIM-base project management tools allows the integration of morerealistic project situations in project management classes. This
integration, in turn, allows the students to learn theoretical project
management methods, such as estimating and scheduling using
complex real-world project scenarios. The cases illustrate that BIM-
based project management tools allow students to generate integrated
projectplansfor real-world complex projects.Our findings, in particular
the comparison of the first case with earlier classes that did not use
BIM-based tools, show that this generation would not have been easily
possible without the use of the BIM tools.
The cases show that BIM-based project management tools provide
students with a structured way to understand project documents and
automated many repetitive tasks and thus helped students to focus on
more in-depth project planning details. Hence, the cases illustrate that
BIM reduced the workload on students with respect to traditionalproject management tasks like quantity take off and thus freed time to
include more realistic project details, therefore exhausting the students
with this level of detail on such a scale. The reduced workload, in turn,
made the introduction of realistic project assignments into the tight
timeframes of the above classes possible. Overall, though, the workload
for the students has increased from the more formulaic version of the
class. However, it would be inconceivable to ask students to deliver an
integrated project plan for an actual project with the traditional,
fragmented project management methods.
The findings from the two cases also show that the integration of
BIM-based project management tools improved the learning activities
of thestudents relative to integrated projectmanagement. By using BIM
tools in class, the students of the class could go beyond learning project
management methods theoretically and then applying them on small
independent examples. In bothcases, the educators were able to design
assignments during which students needed to generate detailed
integrated project plans. Hence, the two classes allowed their students
to learn about the true application of different project management
methods in an integrated and realistic real-world case. For example,
Twente students in the second case used the same projects to apply 4D
line-of-balance scheduling and cash flow diagrams to optimize their
project plans.
Learning project management with BIM tools allows students to
understand the complexrelation and interplay betweenthe advantages
and disadvantages of the project management methods and to see how
and when they help to optimize project plans. Additionally, thefindings
from case two show that the integration of BIM-based tools in a project
management class project allows for the integration of change
management tasks in class projects. The students of the second case
would have hardly been able to complete thefinal change management
assignment in one week without having an integrated project plan that
allows for the automatic update of the impacts of changes in one of the
factors scope, time, or cost on all others. In this way, the BIM-based
project management tools allow students to learn how to react to
changes and how to adjust project plans to counteract unwanted
consequences of project changes.
In summary, the cases provide illustrative evidence for our
hypothesis that the integration of BIM-based project management
tools in project management class assignments helps to use projects
that are more complex, increases the opportunity to learn how to use
different project management methods for a single project, and how toincorporate changes. However, the cases do not sufficiently illustrate
that theintegrationof BIMtools allow students to learn how to optimize
their project plans usingadvanced projectmanagementmethodologies.
Despite the integrated application of 4D and line-of-balance method-
ologies, we could not determine if students were able to optimize their
project plan and to detect deficiencies in an existing plan. We assume
that despite the use of modern tools, the true optimization of project
plans still relies on work experience and that we still fail to support our
students to acquire this knowledge through action-based learning
methods.
6. Limitations and suggestion for future research
Overall, we observed similar characteristics in both classes and are
confident that the reported observations are real. While our observa-
tions provide a degree of predictability for other classes that the
integration of BIM-basedtools will also allow forthe integration of more
detailed and realistic class projects, we must caution for the overall
generality of the findings for all project management classes. It is
necessary to review the inherent weaknesses in spite of this intuitive
confidence in the results. A study that is based upon only two case
studiesopensdiscussionsaboutthe generality of thefindings. Therefore,
throughout this paper, we cannotand do notclaimthat ourobservations
are applicable for the implementation of BIM-based project manage-
ment tools in other educational settings than the two we provide
exemplarily here. However, the insights of the two cases clearly show
how the application of BIM improved specific learning activities within
Table 4
Evidence how the use of BIM increased our ability to teach.
School Use of real-world case Integration of different PM methods Change management Project plan optimization
Stanford
University
Multi-story steel framed structure with
concrete foundation. BIM modeled from
the original contract documents.
Students learned how to apply critical path, line-of-
balance, and 4D scheduling techniques.
No evidence. Local optimization of
workflow, time duration,
and resource leveling.
University of
Twente
Two storey mixed use building for a
theater company. BIM modeled from
the original contract documents.
Students learned critical path, line of balance, and 4D
schedulingtechniques. Additionally, students usedresource
leveling and cash flow time series visualizations.
Onthefinalassignment,students
integrated changes with respect
to scope, time, and cost.
No evidence.
123F. Peterson et al. / Automation in Construction 20 (2011) 115125
-
7/29/2019 1-s2.0-S092658051000138X-main
10/11
these classes, which might serve as a strong indicator of the general
applicability of thefindingsbeyond the specific two-class settings of the
paper. Nevertheless, to improve thefindings' generality we suggest that
future research explores empirically to what extent the application of
BIM can increase the opportunity to design more realistic project
management assignments. One way to gain more in-depth insights into
this area is the application of a more sophisticated case study research
plan, for example, a standardized and validated exam or questionnaire.
To resolve the exam format issue of learning through a virtualenvironment and the examination in a paper-based format, we suggest
researching a method to administer the exams virtually. We suggest
that researchers conduct structured experiments using control groups
and intervention groups that do not use BIM-based tools and that work
on the same project case, with the same tasks and deliverables. Such a
study will allow for the direct comparison of the effect BIM-based tools
have on the amount of realistic project detail educators can integrate in
their class projects. Additionally, we suggest that researchers develop
survey instruments that allow the collection of data for more formal
statistic data analysis. Such research can then provide quantitative
results for the improvements that BIM allow with respect to different
factors, such as the level of detail of thecaseusedin class settings or the
understanding for which types of project management tasks BIM saves
time and for which tasks it increases time in educational settings.
In addition to a more structured case and survey studies, we suggest
thatresearchers also evaluate howotheradvantages of BIMcan improve
the design of university classes. One often-discussed advantage of BIM
in the literature is the benefits that BIM offers to improve the
communication between different project participants, see for example
[34,35] and [21]. Future research could, for example, show how BIM
supports the design of classes that facilitates students to learn multi-
disciplinary distributed project management.
Finally, we alsosuggest that researchers conduct longitudinalstudies
that not only show how BIMcan support the design and learning within
educational settings, but also provides evidence that students (or
continued education of projectteams to tackle anticipated niche project
scenarios) wholearn with BIM perform better within their practical job.
The question is, to what degree can the presence of BIM-competent
engineers be expected to reduce project risk, that is, contingency. Ourclaim that more realistic class projects support the education of better
project managers is, while logically convincing, not based on any
empirical evidence about better long-term performance in practice.
Researchers should also test the application of BIM-supported project-
based learning within other cultural settings than the presented
Western United States and Western Europe situations. Different
cultures respond differently to various learning styles and the
assumption that an action-based learning style improves project
management competencies of students varies to an unknown degree
between cultural contexts [36].
7. Conclusion
In this paper, we show that the introduction of BIM-based projectmanagement tools helped educators of two project management
courses to develop class assignments based on more realistic project
settings andinformation to support students with learning howto apply
different formal project management methods to real-world project
management problems. In particular, we show that the introduction of
BIM allowed the educators to design class projects that include more
realistic cases that better simulate real-world project conditions, helped
students to learn how different project management methodsintegrate
with each other, and integrate change management tasks in a class
assignment. We analyzed the learning activities of two project
management classes that integrated the use of BIM-based project
management tools in their learning activities.
In general, we believe that the advantages illustrated here show that
BIM-based project management tools can significantly increase the
quality of education delivered by project management programs that
are more in tune with the challenges the students will face in practice
over the next few years. By integrating more detail and reality in class
projects, students will be able to learn better how to apply different
formal project management methods to specific project contexts. The
better education of students, in turn, should reduce the timethat newly
hired professionals need to spend on learning-by-doing assignments in
the field until they become valuable contributors to a project team. In
conclusion, we believe that the integration of BIM-based projectmanagement tools into university curricula already has the potential
to increase project management skills.
Acknowledgements
We appreciate the software tools and support provided by the
vendors: Autodesk, Vico, Tocoman, Primavera, Sage, and Tekla. We are
also thankful to the students that took the courses and provided the
feedback on their experiences.We thank thereviewers of this paper and
its earlier drafts, including Tobias Maile, Amir Kavousian, Jung In Kim,
Tony Dong, Olli Seppanen, Tomi Tutti, Richard See, Dana Probert, and
Thomas Wingate. We are thankful for the BIM modeling provided by
Sangwoo Cho. In earlier classes, Atul Khanzode developed a substantial
portion of the course material that eventually became the integrated
BIM component. We are also grateful for the course material contribu-
tions of teaching assistants Maria Brilaki and Mauricio Toledo and their
willingness to share the results from the classes they supported.
References
[1] J. Dewey, Experience and nature. New York: Dover, 1928, 1958.[2] J. Thomas,T. Mengel,Preparing projectmanagers to deal withcomplexity advanced
project management education, Issue 3, Excellence in Teaching & Learning for ProjectManagement, International Journal of Project Management, 0263-7863vol. 26, April2008, pp. 304315, doi:10.1016/j.ijproman.2008.01.001, http://www.sciencedirect.com/science/article/B6V9V-4S26K50-1/2/afe84e67f2ba2b40e03c48588d1526d9 .
[3] G. Winch, Managing Construction Projects: an Information Processing Approach,Blackwell Publishing, 2002.
[4] R. Clough, G. Sears, S. Sears, Construction Project Management, 4th ed.John Wiley &sons, Inc., New York, New York, 2000.
[5] A Guide to the Project Management Body of Knowledge (PMBOK Guide), 4th ed.Project Management Institute978-1-933890-51-7, 2008.
[6] Integrated Project Delivery Guide: version 1, American Institute of Architects, 2007http://www.aia.org/contractdocs/AIAS077630.
[7] ConsensusDOCS300 series collaborative documents, http://consensusdocs.org/.[8] L. Kreiner, In search of relevance: project management in drifting environments,
Scandinavian Journal of Management 11:4 (1995) 335346.[9] S. Weber, Boundary-crossing in the context of intercultural learning, in: T. Tuomi-
Grhn, Y. Engestrm (Eds.), Between School and Work: New Perspectives onTransfer and Boundary-crossing, Emerald Group Publishing, 2003.
[10] L.S. Vygotski, Mind in society: The development of higher psychological processes:Harvard University Press. Translated by Cole, M., & John-Steiner, V., 1978. pp 101.
[11] J. Kunz, R. Levitt, M. Fischer, Management and Leadership Education for CivilEngineers: Teaching Virtual Design and Construction for Sustainability, StanfordUniversity, CIFE Working Paper # 079, September 2003, http://www.stanford.edu/group/CIFE/online.publications/WP079.pdf.
[12] F. Peterson, M. Fischer, T. Tutti, Integrated Scope-schedule-cost model system forcivil works, in: K. Belloni, J. Kojima, I. Sepp (Eds.), VTT Symposium 258: 1stInternational Conference on Improving Construction and Use Through IntegratedDesign Solutions, Julkaisija - Utgivare, Helsinki, Finland, ISBN: 978-951-38-6341-8,2009, pp. 176199, http://www.vtt.fi/inf/pdf/symposiums/2009/S259.pdf.
[13] R. Wilson, The Use of Computers in Industrial Engineering Education, University ofMichigan Ford Foundation Project, Curriculum Report, Final Report, 1962.
[14] R. Fruchter,Dimensionsof teamworkeducation,InternationalJournalof EngineeringEducation vol.17 (Nos. 4 and 5) (2001) 426430 http://www.akademik.unsri.ac.id/download/journal/files/ijee/IJEE1222.pdf.
[15] J. Plume and J. Mitchell, Collaborative design using a shared IFC building model learning from experience, Automation in Construction, Volume 16, Issue 1, CAADFutures, 2005, January 2007, Pages 28-36, ISSN 0926-5805, DOI: 10.1016/j.autcon.2005.10.003, http://www.sciencedirect.com/science/article/B6V20-4HNYMGD-4/2/5cdbee78b977373b0e1dd3e26e5606f3).
[16] M.J. Clayton, R.B.Warden,T.W.Parker,Virtualconstruction ofarchitectureusing3D CADand simulation, Automation in Construction (ISSN: 0926-5805) Volume 11 (Issue 2)(February 2002) 227235,doi:10.1016/S0926-5805(00)00100-X http://www.science-direct.com/science/article/B6V20-448Y6N4-B/2/1d649edf8e0b36f5b1d977615ee
5bd01.
124 F. Peterson et al. / Automation in Construction 20 (2011) 115125
http://dx.doi.org/10.1016/j.ijproman.2008.01.001http://www.sciencedirect.com/science/article/B6V9V-4S26K50-1/2/afe84e67f2ba2b40e03c48588d1526d9http://www.sciencedirect.com/science/article/B6V9V-4S26K50-1/2/afe84e67f2ba2b40e03c48588d1526d9http://www.sciencedirect.com/science/article/B6V9V-4S26K50-1/2/afe84e67f2ba2b40e03c48588d1526d9http://www.aia.org/contractdocs/AIAS077630http://consensusdocs.org/http://www.stanford.edu/group/CIFE/online.publications/WP079.pdfhttp://www.stanford.edu/group/CIFE/online.publications/WP079.pdfhttp://www.vtt.fi/inf/pdf/symposiums/2009/S259.pdfhttp://www.vtt.fi/inf/pdf/symposiums/2009/S259.pdfhttp://www.vtt.fi/inf/pdf/symposiums/2009/S259.pdfhttp://www.vtt.fi/inf/pdf/symposiums/2009/S259.pdfhttp://www.akademik.unsri.ac.id/download/journal/files/ijee/IJEE1222.pdfhttp://www.akademik.unsri.ac.id/download/journal/files/ijee/IJEE1222.pdfhttp://www.akademik.unsri.ac.id/download/journal/files/ijee/IJEE1222.pdfhttp://www.akademik.unsri.ac.id/download/journal/files/ijee/IJEE1222.pdfhttp://www.sciencedirect.com/science/article/B6V20-4HNYMGD-4/2/5cdbee78b977373b0e1dd3e26e5606f3http://www.sciencedirect.com/science/article/B6V20-4HNYMGD-4/2/5cdbee78b977373b0e1dd3e26e5606f3http://dx.doi.org/10.1016/S0926-00)00100-http://www.sciencedirect.com/science/article/B6V20-448Y6N4-B/2/1d649edf8e0b36f5b1d977615ee5bd01http://www.sciencedirect.com/science/article/B6V20-448Y6N4-B/2/1d649edf8e0b36f5b1d977615ee5bd01http://www.sciencedirect.com/science/article/B6V20-448Y6N4-B/2/1d649edf8e0b36f5b1d977615ee5bd01http://www.sciencedirect.com/science/article/B6V20-448Y6N4-B/2/1d649edf8e0b36f5b1d977615ee5bd01http://www.sciencedirect.com/science/article/B6V20-448Y6N4-B/2/1d649edf8e0b36f5b1d977615ee5bd01http://www.sciencedirect.com/science/article/B6V20-448Y6N4-B/2/1d649edf8e0b36f5b1d977615ee5bd01http://dx.doi.org/10.1016/S0926-00)00100-http://www.sciencedirect.com/science/article/B6V20-4HNYMGD-4/2/5cdbee78b977373b0e1dd3e26e5606f3http://www.sciencedirect.com/science/article/B6V20-4HNYMGD-4/2/5cdbee78b977373b0e1dd3e26e5606f3http://www.akademik.unsri.ac.id/download/journal/files/ijee/IJEE1222.pdfhttp://www.akademik.unsri.ac.id/download/journal/files/ijee/IJEE1222.pdfhttp://www.vtt.fi/inf/pdf/symposiums/2009/S259.pdfhttp://www.stanford.edu/group/CIFE/online.publications/WP079.pdfhttp://www.stanford.edu/group/CIFE/online.publications/WP079.pdfhttp://consensusdocs.org/http://www.aia.org/contractdocs/AIAS077630http://www.sciencedirect.com/science/article/B6V9V-4S26K50-1/2/afe84e67f2ba2b40e03c48588d1526d9http://www.sciencedirect.com/science/article/B6V9V-4S26K50-1/2/afe84e67f2ba2b40e03c48588d1526d9http://dx.doi.org/10.1016/j.ijproman.2008.01.001 -
7/29/2019 1-s2.0-S092658051000138X-main
11/11
[17] P. Teicholz, M. Fischer, Strategy for computer integrated construction technology,Journal of ConstructionEngineeringand Management 120 (1994) 117, DOI:10.1061/(ASCE)0733-9364(1994)120:1(117).
[18] S. Staub, M. Fischer, The practical need of integrating scope, cost, and time,durability of building materials and components, in: M.A. Lacasse, D.J. Vanier(Eds.), Institute for Research in Construction, Ottawa ON, K1A 0R6, Canada, 1999,pp. 28882898.
[19] M. Fischer, F. Aalami, R. Akbas, Formalizing product model transformations: caseexamples and applications,Lecture Notes in Computer Science: Artificial Intelligencein Structural Engineering, vol. 1454/1998, Springer Berlin / Heidelberg, 1998,pp. 113132, www.springerlink.com/content/d1kq94t315782068/fulltext.pdf.
[20] M. Fischer, Formalizing Construction Knowledge for Concurrent Performance-basedDesign, EG-ICE 2006, LNAI 4200, in: I.F.C. Smith (Ed.), Springer-Verlag BerlinHeidelberg, 2006, pp. 186205, http://www.springerlink.com/content/a236364870334918/fulltext.pdf.
[21] T. Hartmann, J. Gao, M. Fischer, Areas of application for 3D and 4D models onconstruction projects, Journal of Construction Engineering Management 134:10(2008) 776785.
[22] M. Fischer, C. Kam, PM4D final report, Stanford University, CIFE Technical Report#143, , October 2002 http://cic.vtt.fi/vera/Documents/PM4D_Final_Report.pdf.
[23] A.M. Alder, Comparing time