1-s2.0-0266352X88900766-main
-
Upload
nilthson-norena-valverde -
Category
Documents
-
view
8 -
download
0
description
Transcript of 1-s2.0-0266352X88900766-main
Computers and Geotechnics 6 (1988) 95-129
COUPLED CONSOLIDATION ANALYSIS OF THE CONSTRUCTION AND SUBSEQUENT PERFORMANCE OF MONASAVU DAM
D. J. Naylor Department of Civil Engineering
University College of Swansea Singleton Park
Swansea SA2 8PP U.K.
D. J. Knight Sir Alexander Gibb & Partners
Farley House 427 London Road
Farley Reading RG6 1BL
U.K.
D. Ding Wuhan Institute of Hydraulic
and Electrical Engineering Wuhan,
People's Republic of China
ABSTRACT
A two--dimensional coupled consolidation finite element beck-analysis of the construction and first impounding of the dam is described. Interest centres on the relatively soft clay core. This was first modelled elastically, after which the analyses were repeated using an elasto-plastic critical state model for the clay. Comparisons are made of the measured and computed distributions of settlement, pore pressure, and vertical and horizontal stresses. Generally good agreement with measured values was obtained. The results show some arching across the core and the variations in stress (total and effective) across it. The elasto-plastic modelling supports the design expectation that the soft clay will yield plastically rather than develop tension. Conclusions are drawn that will assist designers in evaluating numerical models of embankment dams.
INTRODUCTION
Monasavu dam [1] is an 85 m high embankment with rockfill shells supporting a
very wet, and thus soft, halloysitic, residual clay core, situated at Monasavu Falls in
Viti Levu, the main island of Fiji. It was constructed for the Fiji Electricity Authority
95
Computers and Geotechnics 0266-352X/88/$03.50 © 1988 Elsevier Science Publishers Ltd, England. Printed in Great Britain
96
between 1979 and 1982. The dam site is underlain by a sequence of sedimentary rocks
into which is intruded a thick monzonite sill, constituting the river section foundations.
Immediately downstream is the top of a substantial cliff (Figure 1) where Nanuku Creek
once formed the spectacular 126 m high Monasavu Falls. Horizontally bedded
sandstones form the dam abutments. The sand grains consist of reworked tuffaceous
material and rock fragments, which the tropical climatic conditions have caused to
weather to a clay material.
The dam, its foundations and the downstream rock massif were extensively
instrumented to measure seepage, deformations, pore pressures, three-dimensional
stresses in the core and seismic behaviour during construction, impounding and
operation. Settlement cells, hydraulic piezometers and total earth pressure cells were
installed in the embankment. This instrumentation is located on three cross sections
(Figure 2). These are on the right abutment, valley centre and left abutment at the
respective Chainages 125, 175 and 210 m. The instruments were installed at three
levels: E1 705, E1 730 and E1 735, at each cross section, with a fourth at E1 680 at
Ch 175.
The results presented in this paper are obtained from coupled consolidation finite
element analyses. These are in two parts. The first part uses the Biot consolidation
theory with the soil idealised as isotropic and linear elastic [2-4]. In the second part
the soil skeleton is modelled by an elasto-plastic critical state constitutive law. The
description 'coupled' relates to the interaction between the soil skeleton stiffness and
Darcy's flow law due to the change of voids with time. With 'uncoupled' flow there
is no such interaction and the governing equations are the same as used to describe,
for example, heat flow.
The uncoupled or Terzaghi-Rendulic consolidation theory may be used to obtain
approximate solutions to two or three dimensional problems [5,6]. In view, however,
of the potential of the coupled theories to take into account the effect of soil skeleton
strains on the pore pressure field it was decided to use a coupled formulation in the
present work.
The first implementation of the Biot theory by the finite element method was
made by Sandhu and Wilson [7]. They based their method on previous work in fluid
mechanics and used Gurtin's variational principle [8]to derive a set of integral
equations. These formulations accounted for the coupling between deformation and
pore water pressure. Finite elements were used for spatial discretisation together with a
finite difference time-stepping scheme. Later, several different versions were published;
8001 700 4
600
97
L_ 500 m 5C)0 460 3(~3 2()0 I00 0 m
Section at Eh. 175
Ch.175
CIQy bor row __..---~ ~'~~~"gL'~'~,o~-~%~' <~ ~ < > ( Diversion
~7~o ' / / . ~ l l [ I / / / /J~'/JJ Morcsovu Foils Oh.175
Figure 1 Monasavu dam, plan and cross-section
98
in particular Christian et al. [9], Hwang et al. [10], Yokoo et al. [11,12], Booker [13],
Ghabonssi et al. [14] and Ding [15]. During this time nonlinear models for the soil
skeleton were being incorporated, for example, Lewis et at [16], Small et al [17,18].
ELm
800-
750-
700-
650-
600
Spillway 4 Embankment b L. .J
Instrumented sections Core borrowl I- area-
" " ~ . . ' - - ~oGtL . o _ _ ~ f - - - j ~- - ~--.~- • \.~ • ,,~/j" --~ ~.~-~ - ~ Sandstone
~ 1 --"; "" Core trench ~~r'--"~, . " ~"~.,~*~'~-~ ~ ....... 7-- - e×covat~on " ~ o o p & / - q , .~ , ~ 7 - 5 . ~ - - - - - - c o ~ e t ~ ,nf,Hs
.... ,Sandstone roc~: ~ o Conglomerate ~ . ; o ÷ . . . . o . . . . . . . . . .
~ ~ , ' ~ + Monzonite
I ; LEFT Diversion funnel ~o ~s ~5 RIGHT I I I I I I
+LO0 +300 +200 +100 0 -100
^'L.nalnage (m) ,Main instrument locations
Figure 2 Longitudinal profile along core trench
The linear-elastic stiffness parameters used for the analyses were determined from
the earlier studies [I]. The critical state model parameters (which applied to the clay
core only) were based on laboratory tests on samples taken from the dam during
construction, as detailed later in the paper. Permeability values, however, were
obtained by trial to reproduce measured pore pressure : time relations. The results
thus obtained provide both information on realistic values for the permeability
coefficients and a more comprehensive picture of the inferred distribution of stress and
pore pressure than that directly indicated by the instrumentation. It must be noted, of
course, that the instrumentation is the only means by which it is possible to measure
the dam's actual state.
99
THEORY
In this section the theory leading to the finite element formulation used for the
two types of analysis is outlined. The linear (Biot) formulation is first given and then
an incremental form is derived from it. This is suitable for both linear and non-linear
soil modeb. It applies to both sets of analyses.
The theory is based on (1) the equations of equilibrium for the total s t r e $ ~ (2)
the effective stress--strain relations for the soil skeleton and (3) the condition of
continuity for the movement of the solid and fluid components in a soil element.
a soil element b acted on by a set of ~rces and ~ in equilibrium then the
equations of equilibrium ~lating the components of the total stress and body force
intensity acting on the e~ment can be written as:
~ i j , j + FI " 0 (1)
where ~ i j - components o f the t e n s o r o f the t o t a l s t r e s s ,
compress ion c o n s i d e r e d as p o s i t i v e , and
F i - components o f the v e c t o r o f body f o r c e pe r
u n i t vo lume, u s u a l l y g r a v i t y .
The ~poated subscripts in the equation are summed from 1 to 3 and the comma
deno~s diffe~mlation with respect to the fol~wing component.
If the soil skeleton is assumed as linear elastic the effective stress--strain relation
can be written:
where
~ ' i j
61j
P
D i j k l
~kl
Uk
- 6 i j P - O i j k l ekl (2)
- components o f the e f f e c t i v e s t r e s s t e n s o r
- the K ronecke r d e l t a
- the pore w a t e r p r e s s u r e
- e l a s t i c c o e f f i c i e n t s i n the g e n e r a l i s e d Hooke 's
law f o r the s o i l s k e l e t o n
- - ( U k , 1 + U l , k ) / 2 , d i m e n s i o n l e s s components o f the
s t r a i n t e n s o r , and
- components o f the d i sp lacemen t v e c t o r
100
The relative f low of pore water is assumed to obey Darcy's law which can be
expressed generally as:
r s ~t r v i - v I - 7w ( j - p , j )
where
(3)
f v i
s v i
k i j
7w
Fj ( I f this is gravity and direction 2 is vertically upwards, F 2 = -Tw)
- c o m p o n e n t s o f t h e s u p e r f i c i a l v e l o c i t y v e c t o r ( i . e . f l ow p e r u n i t a r e a ) o f t h e f l u i d p h a s e
- c o m p o n e n t s o f t h e v e l o c i t y v e c t o r o f t h e s o l i d p h a s e
- c o e f f i c i e n t s o f p e r m e a b i l i t y i n t h e g e n e r a l D a r c y ' s law
- u n i t w e i g h t o f w a t e r
- c o m p o n e n t s o f body f o r c e on t h e w a t e r p e r u n i t vo lume
Note that velocities are measured relative to axes fixed in space, i.e. the
formulation is Lagranglan rather than Eulerian.
For engineering applications the simplification is usually made that the soil is
saturated and that the compressibility of the water and soil particles is negligible. The
divergence of the fluid velocity vector must therefore be zero, i.e.
f v i , 1 - 0
Adding the compressive strain rate of the soil skeleton,
~ v - -v~ i to b o t h s i d e s g i v e s J
f s s (v i - v t ) t - - v i , i (4)
This allows the left hand side of equation (3) to be replaced by iv-
Equations (1) to (4) are the governing equations on which the finite element
formulations are based.
Finite El©m~nt Formulat ion - Linear Case
The Blot theory for two phase linear elastic materials can be expressed as
follows:
101
Assume a finite element to have n nodes, and that i is the number of
dimensions in physical space, i.e. two or three. In addition to the displacement
variables there will be a pore pressure variable. This need not be assigned to every
node. Assume it is assigned to m nodes, m < n. The basic equations of a single
element for consolidation can then be expressed as:
l ( r + C r - - u - - p
c T r - - H r - - u
where K C
r_u
~p a_u
a_f
_-R ] --U
- - p gf
= stiffness matrix of the solid skeleton
= coupling matrix
= flow matrix
(5)
= vector of nodal displacement components (length i.n)
= rate of nodal displacement vector
= vector of nodal pore pressure (length m)
= vector of prescribed nodal forces
= vector of prescribed nodal flow
The first of the pair of matrix equations (5) expresses the equilibrium condition
and incorporates equations (1) and (2). The second represents continuity. It
incorporates equation (4), with Darcy's law of equation (3) included in the flow matrix
H .
Established procedures are used to assemble these element equations to form the
global equations to be solved for the unknown nodal displacements and pore pressures.
In the present work 8-noded quadrilaterals with some 6-noded triangles v0ere
used. These allowed quadratic displacement variations hut a pore pressure variation
that was linear for the triangles and bi-linear for the quadrilaterals. Thus there were
two displacement and a pore pressure variable at each corner node, with displacements
only assigned to midside nodes.
Incremental Formulat ion
This is derived from the above as follows. The first of equations (5) is replaced
by:
102
I( zlr u + C zl_rp - ~/-u (6)
K is now an incremental or tangential stiffness matrix. It will be the same as in
equation (5) for linear-elastic applications. In the context of elasto-plastic analysis it
will be denoted -~ep. A indicates the presumed small change in values in a time step
At. Note that, in general, loading will be applied over a period of time although load
stepping with At = 0 may be used to model ' instantaneous' loading.
[p in equation (5) can be expressed in terms of its value at tunes t and t+,%t as
follows:
+ r - ~ r + ( 1 - a ) r ; (7) - p - p
+ where -Pr - _rp(t + At )
r = r p ( t ) - - p - -
0 ~ < t ~ < l
A mid-difference scheme with c~ = ~ is used. This implies that for small time steps
r ~ £ p ( t + ~At) - p
- ; S i n c e AEp r + _p - £
r - r + c ~ r - p - p - p
e q u a t i o n (7) can be w r i t t e n
(8 )
Substituting equation (8) into the second of (5), writing £u = Ar-u/At, multiplying
through by At and rearranging, gives:
C T Ar u - ~ At H A r p - At(I t r p + _Rf) (9)
Combining equations (6) and (9) gives the incremental governing equations:
Note that the matrices K., C_, H and Rf should all be ~ for the time step
(strictly, Q = c ~ + + ( l - cOQ- where Q represents the matrix). In the present
applications C_C_ and H are constant. Mid-increment values are used for the other two.
(These are at an estimated mid- increment point in the case of _K).
Equations (10) are assembled for all the elements in the usual way.
103
FINITE ELEMENT IDEALISATION
~mlg.£ame, auMma
A plane strain idealization of the valley centre section (at chainage 175 which is
the highest part of the dam) has been made. The mesh is shown in Figure 3.
= El. in metres 752
~77&5 v73o
- - 705
. . - _ - i - i -
] I I I I L 0 50 100 150 200 250
680 ~7
x
w
300 metres
Figure 3 Finite element mesh
C o l t m ~ d o n aad l~el~rvoir Fillin¢
As large embankment dams are normally constructed in substantially horizontal
layers, this has to be incorporated in the modelling. This involves a sequence of finite
element analyses with the fill surface being raised to different element boundaries in
subsequent layers. Effective stresses, pore water pressures and displacements are
accumulated automatically from one analysis to the next. All the layers may be run in
a single batch job. Displacements are accumulated in such a way as to include
displacements of the previously placed material only. The procedure is explained by
Naylor and Mattar [19]. Eight layers were used in the mesh of Figure 3.
The continuous raising of the fill with time was approximated by assuming
instantaneous loading at the time when the fill was half way up the layer being added.
Thus an eight step loading sequence was used.
1 0 4
A similar treatment was used for the impounding analysis with the reservoir being
raised in eight stages.
It was found that a suitable length of time step was about 2% of the time for
the completion of primary consolidation. On this basis time steps of about 20 days
were used. This resulted in the use of a total of 27 time steps for the construction
analysis and 33 for the impounding and reservoir full stages.
Isotropic elasticity was assumed for the first set of analyses. Isotropy was also
assumed for the permeability. The parameters involved are therefore the Young's
modulus, E' , Poisson ratio ~,' and permeability k.
The continuous plasticity critical state model (c.p.c.s.m.) described by Naylor [20]
was used for the second set of analyses. This requires the specification of six
parameters. Four of these are material properties and comprise the two elastic
parameters E ' and ~', the critical state angle of shearing resistance, ~cs, and a
parameter, ~, which is a measure of the irreversible compressibility of the soil skeleton.
A fifth parameter, t~co, represents the preconsolidation stress state. It is more
conveniently classified as an 'initial stress' and will be considered under that heading
below. The sixth, n, is a 'tuning' parameter for the c.p.c.s.m. It controls the
amount of plastic flow generated at below yield stress states. The value 2, suggested
for n in reference [20] for lack of evidence for a different value, has been used in the
present work.
The parameter ~ replaces X, ~ and the initial voids ratio, e, (or specific volume
v) used in standard texts on the critical state model [21,22,23]. It is defined as
C C X - K c - e
X - 1 + e " 2 . 3 ( 1 + e )
where
X or C c
or C c
= voids ratio (either the initial or, preferably, an
average value for the analysis)
= the slope of the virgin consolidation line on respectively
e : Lno-' or e : Log 10 a ' plots
= corresponding slopes of the assumed reversible unloading-
reloading e : Lna ' or e : Log 1 o t~' lines.
105
The rockfill was modelled as linear--elastic for both sets of analyses. This is
justified on the basis that it is very much stiffer than the clay so that displacements in
it are relatively small and are of little significance. The values of E ' and v' are the
same as used in ref.[l ] and are given in Table I.
The clay core E ' and v' for the elastic analyses were essentially those used in
Ref, 1. E ' was made to vary automatically with the vertical effective stress according
to Figure 4. These analyses were not therefore strictly linear. Hence they are
described simply as 'elastic'.
The clay core parameters for the c .p.c .s .m, were determined by the trial and
error matching of the laboratory stress-strain curves from tests on samples taken from
the clay core during construction. These parameters are given in Table I .
E I
HPa
5 - -
3 -
2
Ado
I I I I 100 200 300 ~00
a ~y kPa
o = E' caicutated from oedometer tes ts for v'=0.~
I 500
Figure 4 Variation of core Youn~'s modulus with vertical effective stress
106
TABLE 1
Parameter values
Ana ly se s P a r a m e t e r Core R o c k f i l l Comments
E'(MPa) 2-5 60 See F ig . 4 L i n e a r v' 0 .4 0 .3 e l a s t i c a ' o ( k P a ) 20 0 See t e x t
k ( n m / s ) * 3-9 ~ See t e x t
R o c k f i l l l i n e a r e l a s t i c
c . p . c . s . m .
E'(MPa) I ' f
~ ' c s ( d e g )
~co(kPa) a ' o ( k P a ) k ( n m / s ) *
24 0 .3 35 0 .02 40 60
0 . 3 - 1 2
60 0 .3
0 c o
See t e x t See t e x t
* 1 nm/s = 10 -9 m/s
Initial Stresses
For the rockfill it is reasonable to assume that the stress state is fully due to the
application of gravity. Consequently it was not assigned any initial stress.
For the clay core, h~ ever, it was necessary to assign an initial isotropic
compressive effective stress (a'xo = ~'yo = t~'o), and an equal initial pore suction (-Uo)
to model the effect of compaction. For the finite element analyses this initial suction
needs to be higher than the actual since the clay is idealized as saturated and no gain
in shear strength can occur under undrained loading. Dissipation of pore pressure is
required before an increase in shear strength can be modelled. In reality a core
material, even as wet as was used in Monasavu, will not be fully saturated when placed
and there will be a gain in shear strength during the placing of the first few metres
even if there is insufficient time for significant consolidation. Such a gain was
demonstrated on one occasion during construction when removal of fill revealed
underlying stronger material.
The initial stress ~'o for the elastic analyses was set at 20 kPa. This was
chosen fairly arbitrarily as the deformations and total stresses computed would be
unaffected by it. The selection of o ' o was considered more carefully for the c.p.c.s.m.
work, and 60 kPa was chosen. In cot:junction with this the pre-consolidation
parameter Crco was assigned the value 40 kPa. The selection of these values will now
be justified.
107
For undrained loading the path AC in Figure 5 would be followed. The choice
of a aco value slightly less then a ' o represents the soil as being lightly
over-consolidated. This will be realistic due to the compaction of the clay in thin
layers. The model therefore incorporates some negative dilatancy (or contractancy) so
that the effective stress path is deflected to the left under undrained loading as shown
in Figure 5. Yield will eventually occur at the critical state C. At this stage the
deviator stress, ~d, is 2~cSin ~cs" Neglecting the small increase of ~r c above its initial
value of 40 kPa due to strain hardening, and taking ~cs as 35", ~r d at failure is
approximately 46 kPa. c u is therefore 23 kPa. This may be compared with the
measured average of 17 kPa deduced from unconfined compression tests on samples
from the core [1]. A higher value for the model is appropriate since, as has been
mentioned, the real situation of a partially saturated soil at low stress levels will result
in the strength being increased above the measured value when a few metres of fill are
placed, quite apart from the increase in strength associated with consolidation.
O'd= 0"1-0" 3
/+0
20
//" Crii'ica[ sfafe line
/4/J 2 Sin ~cs C /
' Yield s u r f a c e
20 ~0 60 80 ~'~=c~+c~; Sfresses in kPa
Figure 5 Effective stress path for undrained shearing of point %n clay core using c.p.c.s, mode]
108
Seleetim of Permeal~Uitv O~
The assumption of isotropy for the permeability was based on preliminary tests
which showed that the results were not sensitive to variations in the horizontal
permeability, kx, if the vertical, ky, was kept constant. Consequently, k = k x = ky
was assumed for the main analyses.
For the elastic analyses it was decided to base k on the assumption of a constant
coefficient of consolidation, Cv, where
kE' ( 1 - v ' ) (11) Cv = 7 w ( l + v ' ) ( 1 - 2 v ' )
Since v' has been assumed constant this implies that k varies inversely with E' .
The program was modified to impose this requirement so that k was varied
automatically as E ' varied. Best overall agreement was obtained with c v = 3.9 mm2/s.
This gave k values reducing from 9 nm/s for the lowest E ' of 2 MPa. See Table 1
and Figure 4. The same values were used in the construction and reservoir filling
stages. This is considerably higher than laboratory-measured values which were in the
region of 0.1 nm/s.
For the c.p.c.s.m, analyses different permeability values were used for the
construction and reservoir filling stages. For the former k varied over the range 12
nm/s to 1.5 nm/s. For the latter the range was 1.5 to 0.3 nm/s.
RESULTS
The computed displacements, pore pressures and stresses are compared with
measurements, and their variation with time and in space is plotted in Figures 6 to 23
inclusive. The data are arranged as follows:
Figures 6 to 8
Figure 9
Figures 10 and 11
Figures 12 to 23
Settlement results
Pore pressure v. time on core centre line
Effective stress v. time on core centre line
Spatial distribution of stress and pore pressures (as the
difference between total and effective stress) at the end of
construction (April 1982) and the end of 1983 (impounding
complete in March 1983).
Computed
750
7gO Measured
730 3
720 >
i 710 700
690
680
670 I I 0 1 2
SettLement (m)
109
I - Mar. 1981 2 - Mar. 1982 3 - Mar. 1982 (end of construction)
• Mar. 1981 A Sep. 1981 • Mar. 1982 (end of construction)
Elastic - - - - c.p.c.s.m.
Figure 6 Settlement v. elevation on core centre line
110
In some of the figures the elastic and c.p.c.s.m, results are both shown, using a full
line for the former and broken for the latter. Where this would make the plots too
congested they are separated into parts (a) and (b). This applies to Figures 14 to 17
and 20 to 23.
0
- o . s - ~E
- 1 , 0 - E OJ
• -" - I . 5 -
-2,0 --
Core I_ L I _
-r I I I
A
o ~ (a) Etasf ic
Downst ream h v
200m [ I I J
A A
"6 -0.5 -
-1.0 OJ
'~ -1.5
-2.0 --
150
I I I
2
(b) c.p.c.s.m.
200m I I I I
A _ o o
Computed 1 - Sep. 1981 2 - Mar. 1982
3 - Mar. 1983
Measured A Sep. 1981
• Mar. 1982 0 Mar. 1983
Figure 7 Settlement profiles at el. 705
111
1981 1982 1983 =~- --i= --
0 IJIFIMIAIMIJIJIAIslOINIOIJIFIMIAIMIJIJIAIslO]NIOIJIFIMI,41M[JIJIAIsloINIDI
o . . . . J e ' - _ . - - - -
~_-1.5 . . . . . . $'-2.0 ] a A A /% /%
Construction .]_ Impounding ..[_ Operation
Computed a - EL 730 Measured • Et. 730 -- Etastic b - El. 705 /% El. 705 - - - - c.p.c,s.m. c- Et. 680 O Et. 680
Figure 8 Settlement v. time at three points on core centre line
750
Construction Impounding Operation
-F" -I- =
7~0
i 730 720
710 E_ 700
69~; Q.
67O
- • • 4
f ~-~--~ ~ --~-~- ~--
) . ' ~ For tegend see Figure 8
J IFIMIA IMIjIjIAISIOLNfDIJIFIMIA IMIJ FJIAIsIoINIOEJ IpIMIA[MIJIJ~ A Is101N[O
1981 ~ 1982 . ]_ 1983 d
Figure 9 Piezometric el. v. time at three points on core centre line
W ~00 o _
350
300
250
200
150
100
50
112
Consfrucfion j _ Impounding ~t_ Operation
- i--- 5- 0--.2_0 o o < ~" O m .
~ . . . . ~ = - - . . . . _ _ . " _ _ ' _ .
> 0 j IJ1FIMIAIMbblAISlOINIOIJIFIMIAIMIjblAIslolNIDtJIFIMIAIMIjIj1AIsloINIo L 1981 ..L. 1982 ~ 1983 _I
For legend see Figure 8
Figure 10 Vertical effective stress v. time at
three points on core centre line
250
200
150
~ 1 0 0
50
~ o ~
I -
Consfrucfion --L.. Impounding _L. Operation
.- ~^m--O~ O -- ----Ore--O-- --~
- c o.- "~o ~
- . . o - - > I . . . . . - - / - - - - = L = = - -
:7"r'FIMIA rMTTr~A [S~OIMDIJ IFIMIA IMIJ Ia IA Islo IN IDlE IF IMIA IMI J Ij IA Is IOINID I
1981 j _ 1982 j _ 1983
For legend see Figure 8
Figure ii Horizontal effective stress v. time at three points on core centre line
750
7~0
730
-~ 720
.~ 710
700 LtJ
690
680
670
113
Computed ~ Elastic . . . . c.p.c.sm.
Measured ~
o" = Total stress ~ \ ~ o"= Effective stress
100 300 500 700
Vertical stress (kPa)
750
740
730
720 E
c 710 0
700 OJ
LU
69O
680
670
For legend see Figure 12
i 100 300 500 700
Horizontal stress (kPa)
Figure 12 Vert. stress v. el. on core centre line at end of construction
Figure 13 Hot. stress v. el. on core centre line at end of construction
2000
7 % 1500
* z
5 1000
I 2
k ’ 500
0
2000
Upstream H 4
-
-
/
- ./ ./
0’ -
114
Core
7--== I
‘1
_.-. ,/’ ‘\.
A? -_e 0 _’ Pore pressure
I 100 150
(a1 Elastic
200 m
Computed ------Effective stress -Total stress -.-.- Overburden (gh)
Measured o Effective stress A Total stress
01
100 150 200 m
(b) c.p.c.s.m
Figure 14 Vertical stress profile at el. 580 at end of construction
115
2000
t For legend see Figure 14
G 1000
L
>” 500
0
(a) Elastic
7% 1500 % VI
z 5 1000
0
150
(bl c.p.c.s.m.
200 m
Figure 15 Vertical stress profile at el. 705 at end of construction
116
r
For Legend see Figure 14 2000
0
2000
3 a r :
1500
2 zi -iG 1000 + s .N
P 500
0
Upstream Core Downstream u
_I_
w
f'\ /' '1. ._.-.-'
./ \
.I /
100 150 200m
(a) Elastic
r /“. ,
.-.-. 0’
1’ ‘\.,
0.
I 1 I
Figure 16
100 150
(b) c.p.c.s.m.
200m
Horizontal stress profile at el. 680 at end of construction
117
2000 r
2000
0
For legend see Figure 14
100 150
(a) Elastic
200m
.A.
A’-- .J \ ‘\
A I
\ -0e
/
100 150
(b) c.p.c.s.m.
200m
Figure 17 Horizontal stress profile at el. 705 at end of construction
750
7&O
730
E 720
.~ 710
700
690
680
670
Corn Juted - - Elastic . . . . cp.c.s,m. MeasuredA ~
100 300 500 700
Vertical stress (kPa)
118
750
7~0
730
720
g 710
700
690
680
670
For legend see m I Figure 1B
100 300 500 700
Horizontal stress (kPa)
Figure 18 Figure 19 Hor. stress v. el. on
core centre line at the
end of 1983
Vert. stress v. el. on
core centre line at the
end of 1983
O.
,.¢,_
,.¢--
>
2000
1500
1000
500
119
Upstream C o r e Downstream
For tegend see
Figure 1/+
/ ' ~ . /14"" --'~"~~'~~ - - !
I CL_~,"~- Pore pressure I /
I / I /
I v I I 100 150 200m
(a) Etastic
~ L
n
~u ¢ . .
:,v-
2000
1500
1000
500
-- A
--I"""~ '~ II I
I - - i
I 100
b A l /~. a_Li" Pore pressure
[ I 150 200m
(bl c.p.c.sm.
Figure 20 Vertical stress profile at el. 680 at end of 1983
120
t
For legend see Figure 14 2000
G 1500 a Y
: ; 1000 VI 6 2
5 500
0
2000
0
50 '100 150m
t
(a1 Elastic
150
(b) c.p.c.s.m.
200m
Figure 21 Vertical stress profile at el. 705 at end of 1983
121
For legend see Figure 14
0
2000
2 r 2 1500
: VI
E 1000 z 'C 2
500
Downstream
150
(a) Elastic
200m
0
100 150 200m
(b) c.p.c.s.m.
Figure 22 Horizontal stress profile at el. 680 at end of 1983
122
2000
x 1500 a r
:
2 1000
0
2000
0
For legend see Figure 14
Upstream Core Downstream W4 d--L-
/
lOO_----'
k-1 I
150 200m
(a) Elastic
r .p. \
.’ .-‘1.
\./ ‘1
Pore pressure
0 __--
100 150 200m
(b) c.p.c.s.m
Figure 23 Horizontal stress profile at el. 705 at end of 1983
123
DISCUSSION
Oeaeral
Knight et al [1] compared measured settlements and stresses against computed
values. These were obtained by an effective stress analysis which used the measured
pore pressures as part of the input data. A key feature of the consolidation analysis
described here is that the pore pressures are calculated. They can therefore be
compared with the measurements , thus adding the time dimension to the calibration
process.
A further feature of the present work is that it provides information on the
spatial distribution of pore pressures, stresses and displacements over the full section of
the dam. Consequently, if reasonable agreement with the measurements is obtained at
the instrumentation points, credibility is given to the computed values elsewhere.
Caution, however, is necessary as the analysis cannot take into account local
inhomogeneities in, for example, permeability which could cause local pore pressure
variations.
Stress and Pore Pressure
The variation with time of pore pressure (expressed as piezometric elevation), and
vertical and horizontal effective stresses on the core centre line are shown in Figures 9,
I0 and II respectively. Agreement with measurement is generally good. The main
differences are in the pore pressures and effective stresses towards the end of, and
following, reservoir filling. During these stages the pore pressures are less than
measured at El. 680 and 765 for both the elastic and c.p.c .s .m, analyses (Figure 9),
the vertical effective stresses are also less than measured at El. 705 for both models
(Figure I0), and the horizontal effective stresses at El. 680 are less than measured for
the elastic modelling.
A possible explanation of the lower calculated pore pressures during reservoir
filling is a reduction in compressibility associated with the dissolving of any remaining
air bobbles in the core. This could not be reproduced in the analyses. Also it is
likely that the core is negatively dilatant in the lower parts of the dam. This means
that shearing will reduce the voids under drained conditions or induce excess pore
pressures if undrained. This phenomenon is not incorporated in the elastic modelling.
Pore pressures greater than calculated would therefore result from the shear stresses in
the core caused by the rising reservoir. Negative dilatancy is, however, incorporated in
124
the c.p.c.s.m, and it is significant that this has reduced the discrepancy (Figure 9).
The undercalculation of the vertical effective stresses (and also the total stresses)
at the core centre is probably due to the actual arching being less than calculated (see
below). This may be due tO undercalculation of shear strains within the initially soft
core which would allow it to settle relative to the shoulders thus reducing hang up in
the upper regions and allowing the core to be supported within itself rather than by
shear and arching to the shoulders. There may be rheological effects which are not
incorporated in the numerical models. This is reassuring as it implies a greater
resistance to hydraulic fracturing after impounding than indicated by the analyses.
Regarding the horizontal effective stresses, the discrepancy in the elastic analyses at the
bottom level disappears with the c.p.c.s.m. This is the most marked difference in the
results from the two sets of analyses and suggests that the c.p.c.s.m, work is the more
realistic.
Figures 12 and 13 show the variation of total and effective vertical and horizontal
stresses, and the pore pressures as the differences between them, with elevation on the
core centre at the end of construction. The same information is provided on
horizontal sections at the lower two instrumentation levels (El. 680 and 705) in Figures
14 to 17 inclusive. These data extend the information available from the
instrumentation to other parts of the dam as has been mentioned above. There are no
very great differences between the analyses and the measurements at this stage.
The stress distributions at the end of construction shown in Figures 14, 15, 16
and 17 are of particular interest for two reasons. Firstly the vertical stress distribution
(Figures 14 and 15) indicates some load transfer, or arching, from the core to the rock
fill shoulders. The difference between the total vertical stress (full lines) and the
theoretical overburden pressure, i.e. the self weight of a column of overlying material,
(chain dotted line) demonstrates this. (The overburden pressure distribution will differ
significantly from the triangular shape of the cross section; furthermore the density of
the core material is only about 75% of the density of the shoulders.) Secondly the
data reveal any tendency for tensions to develop in the core by the minimum
compressive effective stress developed. This is everywhere positive at the end of
construction. This is not quite the case at the end of impounding as will now be
considered.
The reservoir-full stress and pore pressure distributions presented in Figures 18 to
23 inclusive show limited regions near the upstream edge of the core where the
effective stresses are at or close to zero. They are marginally tensile in the elastic
125
modelling (Figures 2Oa, 21a, 22a and 23a), These stresses are higher for the
c.p.c .s .m, and are all compressive except for the horizontal effective stresses in Figures
22b and 23b which just touch zero at the core/upstream fill interface. In view of the
fact that these tensile regions are ~ r y localized, being sharp dips in the calculated
stress profiles which would disappear if smoothed lines were drawn, it may be
concluded that tension is not indicated by the modelling. Furthermore, as already
discussed, the effective stresses measured in the core are generally higher than those
calculated, thus providing reassurance on this point.
D e t o ~ a o ~
The computer deformations shown in Figures 6 and 7 give good agreement
between measurement and calculation at the end of construction. The elastic results
tally closely with those presented in Reference 1. This is a consequence of the good
agreement in the calculated pore pressures at this stage. (In Reference 1 measured
pore pressures were used as data). The c.p.c .s .m, deformations are little different
from the elastic at the core centre.
The measured settlements slightly exceed those calculated for the during and after
impounding stages (Figures ? and 8). This is attributed to the rheological effects not
incorporated in the modelling.
CONCLUSIONS
Two-dimensional coupled consolidation analyses, incorporating f'wst elastic and
then the continuous plasticity critical state elasto-plastic model for the clay core, have
been used to provide comparison with measured values of settlement, pore pressure and
stress during construction, reservoir filling, and for most of the subsequent year.
The generally good agreement between the computed and measured values
demonstrates the ability of the modelling techniques to reproduce realistic distributions
of settlement, pore pressure and stress in space and time. Since the analyses were
beck-analyses, with some of the parameters adjusted to provide a good overall fit with
the measurements, conclusions cannot be drawn about the predictive role of the
modelling. The tests on the clay core samples did, however, provide realistic stiffness
and strength parameters for the critical state model, but the permeability values
obtained from these tests were much lower (about one order of magnitude) than the
best overall fit values.
126
The results enhance the data from the instrumentation by allowing these to be
extrapolated across the dam section for various idealisations.
The calculated distributions of stresses across horizontal sections provide some
indication of hang-up at the edges of the core due to the relatively stiff shoulders.
These show low, but positive, effective stresses in the unusually low density core.
I.zcalised tensile values at the core/upstream shoulder interface calculated by the elastic
analyses are concluded to be unrealistic. Any tendency for tensile stresses to develop
will be prevented by plastic yielding. This is supported by the elasto-plastic
(c.p.c.s.m.) analyses, which show compressive effective stresses in this region.
The tendency for the calculated pore pressure to be less than measured towards
the end of impounding is tentatively attributed to an actual reduction in pore-fluid
compressibility as the core became fully saturated in the early stages of impounding.
This change in compressibility could not be modelled. A further reason in the case of
the elastic analyses was their inability to model negative dilatancy (or contractancy), the
existence of which would in reality cause an increase in pore pressure as the core
deformed in shear. The higher pore pressures from the c.p.c.s .m, are attributed to its
ability to model this.
The undercalculation of effective vertical stresses in the core at the later stages is
attributed to undercalculation of shear strains at yield stress states in the clay core, and
to the inability of the modelling to incorporate rheologicai (creep) effects which would
in practice reduce the load transfer from the core to the relatively rigid shells.
The undercalculation of core settlements at the later stages is also attributed to
these factors.
ACKNO~ ~nG[~.MENTS
The authors thank the Fiji Electricity Authority and their Consulting Engineers
Gibb Australia (Pry) Ltd for permission to publish this paper. They are also grateful
to Sir Alexander Gibb & Partners for their support in the joint collaboration involved.
Thanks are also due to the Science and Engineering Research Council, and to
Mr. S. L. Tong who was employed as a Research Assistant under S .E.R.C. ' s Grant
OR/D/23886. Parallel research on the Monasavu Dam was done under this grant which
made a significant contribution to the work presented in this paper.
1.
2.
3.
4.
5.
6.
7.
8.
9.
127
I~_.,I~NC]F__~
Knight, D. J . , Naylor, D. J. ~ I)avis, P. D.
Stress-strain behaviour of the Monasavu soft core rockfill dam: prediction
performance and analysis, Proc. of 15th Int. Cong. on Large Dams, Lausanne, 1,
1299-1326, 1985.
Blot, M. A.
General theory of three dimensional consolidation, J. of App. Phys. 12, 155-164,
1941.
Blot, M. A.
Theory of elasticity and consolidation for a porous anisotropic solid; J. of App.
Phys. 26, 182-185, 1955.
Blot, M. A.
General solutions of the equations of elasticity and consolidation for a porous
material, J. of App. Phys., 27, 91-96, 1956.
Gibson, R. E., Knight, K. and Taylor, P. W.
A critical experiment to examine theories of three-dimensional consolidation, Pro¢.
of European Conf. Soil Mechanics and Foundation Engg. 1, 69-76, 1963.
~.hiffman, R. L., Chert, A. T. and Jordan, J. C.
An analysis of consolidation theories, Pro¢. ASCE, 95, SM1, 285-312, 1969.
Sandhu, R. S. and Wilson, E. L.
Finite element analysis of seepage in e~stic media,
641-652, 1969.
Proc. ASCE, 95, EM3,
Gurtin, M. E.
Variational principles for elastodynamics, Arch. Rational Mech. Anal. 16, 34-50,
1964.
Christian, J. T. and Boehmer, J. W.
Plane strain consolidation by finite elements, Proc. ASCE, 96, SM4, 1435-1457,
1970.
128
10. Hwang, C. T., Morganstern, N. R. and Murray, D. W.
On solution of plane strain problems by finite element methods, Can. Geot. J. 8,
109-118, 1971.
11. Yokoo, Y., Yaml~ta, K. and Nagaoka, H.
Finite element method applied to Biot's consolidation theory, Soils and Found.
Vol. 11, No.l, 29-46, 1971.
12. Yokoo, Y., Yamagata, K. and Nagaoka, H.
Variational principle for consolidation, Soils and Foundations, VoI.15, No.4, 28-35,
1971.
13. Booker, J. R.
A numerical method for the solution of Biot's consolidation theory, Quart. J.
Mech. Appl. Math. 26, 457-470, 1973.
14. Ghaboumi, J. and Wilson, E. L.
Flow of compressible fluid in porous elastic solids, Int. J. Num. Meth. Engng. 5,
419-442, 1973.
15. D i ~ D.
Consolidation analysis of embankm¢nt dams,
Ph.D. thesis, University of Wales, 1988.
16. Lewis, R. W., Roberts, G. K. and Zienkiewicz, O. C.
A non-linear flow and deformation analysis of consolidation problems,
ICNMG, Vol. 2, 1106-1118, Virginia 1976.
Proc. 2nd
17. Small, J. C., Booker, J. R. and Davis, E. H.
Eiasto-piastic consolidation of soil, Int. J. Solids Struct. 12, 431-448, 1976.
18. Carter, J. P., Booker, J. R. and Small, J. C.
The analysis of finite elasto-plastic consolidation, Int. J. Num.Anal. Meth. Geom.
3,
107-129, 1979.
19. Naylor, D. J. and Mattar, Jr., D.
Layered analysis of embankment construction, Proc. Int. Conf. on Num. Meth. in
20. Naylor, D. J.
A continuous plasticity version
Meth.Engng., 21, 1187-1204, 1987.
129
of the critical state model, Int. J. Num.
21. ~hofleld, A. N. and Wroth, C. P.
Critical St~¢ S0il Mechanics, McGraw-Hill, 1969.
22. A t H ~ n , J. H. and Brlmsby, P. L.
The Mechanics of Soils, McGraw-Hill, 1978.
23. Brltto, A. M. and Otmm, M. J.
Critical Sta~e Soil Mechanics via Finite Elements, Ellis Horwood, 1987.