Page 1: 1 PROJECT OVERVIEW€¦ · PROJECT OVERVIEW PROJECT MILESTONE DATES: 1. Bid Opening • May 15, 2020 2. Intent to Award • May 19, 2020 3. Notice to Proceed: Start of Construction

Crabtree, Rohrbaugh & Associates

H I G H S C H O O L G E N E R ATO R

P R E - B I D P R E S E N TAT I O N

A p r i l 2 9 , 2 0 2 0

Page 2: 1 PROJECT OVERVIEW€¦ · PROJECT OVERVIEW PROJECT MILESTONE DATES: 1. Bid Opening • May 15, 2020 2. Intent to Award • May 19, 2020 3. Notice to Proceed: Start of Construction

AG

EN

DA

2

3

PROJECT OVERVIEW1

SCOPE REVIEW

BIDDING REQUIREMENTS

QUESTIONS4

Page 3: 1 PROJECT OVERVIEW€¦ · PROJECT OVERVIEW PROJECT MILESTONE DATES: 1. Bid Opening • May 15, 2020 2. Intent to Award • May 19, 2020 3. Notice to Proceed: Start of Construction

1 PROJECT OVERVIEW

Page 4: 1 PROJECT OVERVIEW€¦ · PROJECT OVERVIEW PROJECT MILESTONE DATES: 1. Bid Opening • May 15, 2020 2. Intent to Award • May 19, 2020 3. Notice to Proceed: Start of Construction

Owner: Susquehanna Township School District Superintendent: Dr. Tamara Willis Business Manager: Oslwen Anderson Director of Maintenance: Barry Seilhamer Supervisor of Buildings & Grounds: Glenn

Zimmerman

Architect: Crabtree Rohrbaugh & Associates Senior Project Manager: Anthony Colestock

Engineers: Moore Engineering – Electrical Electrical: Bill Fleischer

PROJECT OVERVIEW

Page 5: 1 PROJECT OVERVIEW€¦ · PROJECT OVERVIEW PROJECT MILESTONE DATES: 1. Bid Opening • May 15, 2020 2. Intent to Award • May 19, 2020 3. Notice to Proceed: Start of Construction

PROJECT OVERVIEW

PROJECT MILESTONE DATES:

1. Bid Opening • May 15, 2020

2. Intent to Award• May 19, 2020

3. Notice to Proceed: Start of Construction• June 1, 2020

4. Substantial Completion (82 calendar days for Construction)• August 21, 2020

Page 6: 1 PROJECT OVERVIEW€¦ · PROJECT OVERVIEW PROJECT MILESTONE DATES: 1. Bid Opening • May 15, 2020 2. Intent to Award • May 19, 2020 3. Notice to Proceed: Start of Construction

2 SCOPE REVIEW

Page 7: 1 PROJECT OVERVIEW€¦ · PROJECT OVERVIEW PROJECT MILESTONE DATES: 1. Bid Opening • May 15, 2020 2. Intent to Award • May 19, 2020 3. Notice to Proceed: Start of Construction

SCOPE REVIEW

The project consists of demolition of the

existing emergency generators/associated

equipment and replacement with a new

emergency generator/automatic transfer

switches/emergency distribution system at

the Susquehanna Township High School for

the Susquehanna Township School District.

EXISTING GENERATOR

Page 8: 1 PROJECT OVERVIEW€¦ · PROJECT OVERVIEW PROJECT MILESTONE DATES: 1. Bid Opening • May 15, 2020 2. Intent to Award • May 19, 2020 3. Notice to Proceed: Start of Construction

3 BIDDING REQUIREMENTS

Page 9: 1 PROJECT OVERVIEW€¦ · PROJECT OVERVIEW PROJECT MILESTONE DATES: 1. Bid Opening • May 15, 2020 2. Intent to Award • May 19, 2020 3. Notice to Proceed: Start of Construction

DRAWINGS AND BID COMMUNICATION:

Bidders may obtain bidding documents in hard copy and/or .pdf electronic format.

• Printed copies - $75 • Electronic copies - $50

Submit requests to [email protected]. Mail checks to Crabtree, Rohrbaugh & Associates, 401 E. Winding Hill Rd., Mechanicsburg, PA 17055

The following information shall be furnished by bidders when obtaining bidding documents:• Bidder’s mailing address• Name of Bidder’s representative• Bidder’s telephone number• Bidder’s facsimile number• Bidder’s email address (email address used to submit the .pdf’s)• Bidding documents requested, by Contract and Contract number

Bidding documents may be viewed at BX noted in the advertisement. It is highly recommended to purchase drawings and don’t rely on BX.

Submit Bid RFI’s to Anthony Colestock with CRA via email at [email protected]

To schedule a site visit contact Barry Seilhamer with Susquehanna Township School District via email at [email protected] .

BIDDING REQUIREMENTS

Page 10: 1 PROJECT OVERVIEW€¦ · PROJECT OVERVIEW PROJECT MILESTONE DATES: 1. Bid Opening • May 15, 2020 2. Intent to Award • May 19, 2020 3. Notice to Proceed: Start of Construction

KEY DATES:

Addenda are anticipated to be issued on May 8 and May 12.

Final Request for Information (RFI’s) are due within 5 business days of Bid Opening (May 8)

Last Addenda issued 2 days prior to Bid Opening (May 13)

Bid Opening on May 15, 2:00 PM @ Susquehanna Township School District Administration Office

Drop off location:

2579 Interstate Drive

Harrisburg, PA 17109

BIDDING REQUIREMENTS

Page 11: 1 PROJECT OVERVIEW€¦ · PROJECT OVERVIEW PROJECT MILESTONE DATES: 1. Bid Opening • May 15, 2020 2. Intent to Award • May 19, 2020 3. Notice to Proceed: Start of Construction

Notice is hereby given that sealed bids for construction of Susquehanna Township High School Generator Replacement, 3500 Elmerton Avenue, Harrisburg, PA 17109 will be received at the Administrative Offices of the Susquehanna Township School District, 2579 Interstate Drive, Harrisburg, PA 17110 until 11:00 A.M., prevailing time, on May 15, 2020. Bids must be submitted to the attention of Oslwen Anderson, Business Manager. Bids shall be submitted in sealed envelopes bearing the name of the Bidder and shall be clearly marked “Susquehanna Township High School Generator Replacement”. Bids will be publicly opened and read aloud immediately after the scheduled closing time for receipt of Bids. Bids received after the above-referenced date and time shall be returned to the Bidder unopened.

ADVERTISEMENT FOR BID

BIDDING REQUIREMENTS

Page 12: 1 PROJECT OVERVIEW€¦ · PROJECT OVERVIEW PROJECT MILESTONE DATES: 1. Bid Opening • May 15, 2020 2. Intent to Award • May 19, 2020 3. Notice to Proceed: Start of Construction

Bid Attachments:

Include with (2) two copies of Bid Form:

• (2) Copies Bid Bond• (2) Copies Non-Collusion Affidavit• (2) Copies Compliance with 111 of

the Public School Code• (2) Copies Non-Discrimination

Affidavit• (2) Copies Workers Compensation

Affidavit• (2) Copies Bidder’s Qualifications, AIA

Document A305

Refer to Front End Specification for additional info and Bid Forms

You will be bidding as a Single-Prime Contractor to the STSD.

Alternates:

• None

Unit Prices:

• Extend Existing Circuit Wiring

• Duplex Receptacle & Wiring

BIDDING REQUIREMENTSBID FORMS

Page 13: 1 PROJECT OVERVIEW€¦ · PROJECT OVERVIEW PROJECT MILESTONE DATES: 1. Bid Opening • May 15, 2020 2. Intent to Award • May 19, 2020 3. Notice to Proceed: Start of Construction

BID DOCUMENTSAll bidders are required to familiarize themselves with the site, building, and all bidding documents including GeneralConditions and Requirements, Bid Package Descriptions, Temporary Facilities, etc. Submission of bid acknowledges thatbidder has done so. All subcontractors and suppliers should familiarize themselves with the bid package descriptionsfound in the Specification Sections so they can direct their quotations to the correct Prime Contractor.

INSURANCEContractors will be required to submit and maintain insurance in accordance with the General Conditions. Paragraph 11 -Insurance: The School District and Architect shall be named as additional insureds.

BID SECURITY/BONDSBid security or bid bond in the amount of 10% of base bid shall be included with each proposal copy.

WAGE RATESProject is subject to Pennsylvania Prevailing Wage Act. Certified payrolls will be required on a monthly basis withapplications for payment. Current rates are included in the specifications.

TAXESBidders are directed to review the PA Tax Exempt Entities, Section 000860. Contractors will be responsible for sales tax,consumer, and use taxes as required by law. Contractors are directed to the PA. Sales & Use Tax Guide to determinewhich items are taxable/tax exempt. The Susquehanna Township School District reserves the right to pursue sales tax paidto the State in error.

ADDITIONAL INFORMATION

BIDDING REQUIREMENTS

Page 14: 1 PROJECT OVERVIEW€¦ · PROJECT OVERVIEW PROJECT MILESTONE DATES: 1. Bid Opening • May 15, 2020 2. Intent to Award • May 19, 2020 3. Notice to Proceed: Start of Construction

ADDITIONAL INFORMATION

BIDDING REQUIREMENTS

PERFORMANCE/PAYMENT/BONDSSuccessful contractor will be required to provide Performance and Payment Bonds. Performance, Payment and BidBonds must be submitted on forms provided in the documents. Surety companies must be legally authorized to dobusiness in the State of Pennsylvania and must be listed in the latest U.S. Treasury Department Circular 570.

SUBSTITUTIONSAll substitutions must be submitted to the Architect no later than 7 days after the intent to award contracts is issued.Contractors are directed to use “Substitution Request Form” found in Section 012500. Unless materials have beenaccepted by Addendum, materials and equipment shall be furnished and installed as per the specifications.

MISCELLANEOUS ISSUESNO SMOKING OR USE OF ILLEGAL DRUGS OR TOBACCO PRODUCTS ON SCHOOL PROPERTY.THE USE OF PROFANITY IS PROHIBITED.

Act 34, Employee Background Check and Criminal History Reports will be required for all contractor employees andsubcontractor employees working onsite. Contractors were instructed that once they are notified of intent to awardthat they should file with the Pennsylvania State Police for all criminal history reports for employees to be assignedto the project.

Page 15: 1 PROJECT OVERVIEW€¦ · PROJECT OVERVIEW PROJECT MILESTONE DATES: 1. Bid Opening • May 15, 2020 2. Intent to Award • May 19, 2020 3. Notice to Proceed: Start of Construction

Crabtree, Rohrbaugh & Associateswww.cra-architects.com

QUESTIONS?