1 | Program Name or Ancillary Text eere.energy.gov
Water Power Peer Review
51-Mile Hydroelectric Power Project PI: Jim Gordon
Earth By Design, Inc.Email: [email protected] (541) 385-1135November, 2011
Demonstrating new methodologies and technology to reduce the LCOE for small, hydropower development
Advanced Technologies and Methodologies for Small Hydropower Development
2 | Wind and Water Power Program eere.energy.gov
Purpose, Objectives, & Integration
Project Purpose:• Promote cost effective, sustainable small hydropower through advanced
technologies & methodologies.• Reduce the LCOE to less than $0.07 per kWh.
• Capitalize on the undeveloped resource potential offered by sustainable, small hydropower
• Demonstrate the advanced project technologies and assessment of its cost, performance & reliability
Relation to Program Objectives:• Effectively transfer the technical and economic results of the project
based on real-world construction and operations to facilitate widespread adoption of this new technology with reduced costs, times, and risks to the industry.
• Demonstrate reliable, cost-effective, highly-efficient and flexible technology to capitalize on small scale hydropower opportunities previously unattainable.
3 | Wind and Water Power Program eere.energy.gov
Technical Approach
4 | Wind and Water Power Program eere.energy.gov
Technical Approach
Additional Key Issues:• Refining Levelized Cost of Energy model for hydropower using the
innovative methodologies in construction and advanced technology.
• Providing publications that can be used to develop cost-models for future hydro projects where previously considered cost-prohibitive due to capital costs and/or low-income.
• ORNL will review and comment on the computer tools developed by CleanPower, that are based on the empiric data from model testing.
5 | Wind and Water Power Program eere.energy.gov
Plan, Schedule, & Budget
Schedule• Initiation date: 10/1/2011• Planned completion date: 10/1/2014
– [This is one month later than previously anticipated based on date of award received]• Milestones
– Preliminary Permitting, licensing, interconnection and financing by April 2012– Manufacturing and review of equipment by October 2012– Construction and commissioning by April 2013– Operations and testing by September 2014
• Go/no-go decision points – Project Financing by February 2012– Permitting and Licensing of project by April 2012– Construction completion by January 2013
Budget: • There have been no variances in the proposed budget to date.• [Identify what portion of the project budget has been expended to date.]
Proposed Budget
FY2011 FY2012 FY2013
DOE Cost-share DOE Cost-share DOE Cost-share
$1,096,574 $2,539,428 $221,456 986,527 $181,970