1. Productivity
-
Upload
1trungson1 -
Category
Documents
-
view
217 -
download
0
Transcript of 1. Productivity
-
7/28/2019 1. Productivity
1/27
Towards increased productivity
-
7/28/2019 1. Productivity
2/27
Towards increased productivity
Why increasing productivity is necessary
Why achieving increased productivity is difficult
Factors to consider with every-day welding
Increasing productivity ideas
-
7/28/2019 1. Productivity
3/27
Todays Reality for Manufacturing Firms
Fierce global competition
Shrinking product cycles
Changing criteria for business stability
Changing product distribution channels
More demanding customers
Why increase productivity ??
-
7/28/2019 1. Productivity
4/27
The pace of change is accelerating
We must accommodate change around us
In the short term, change can create
confusion, inefficiency and loss of morale
Most people resist change
Change is the only way to improve, progress
and learnChange is inescapable
We need to understand what is changing and
why
Why increase productivity ??Seven truths about change
-
7/28/2019 1. Productivity
5/27
Typical cost break-down for manual welding(Varies by Country)
$Labour & Overheads
70%
Power
5%
Equipment
8%
Electrode
17%
Where does your welding dollar go?
-
7/28/2019 1. Productivity
6/27
Typical cost break-down for manual welding(Varies by Country)
$Electrode
70%
Power
5%
Equipment
8%
Labour and Overhead
17%
Where does your welding dollar go?
-
7/28/2019 1. Productivity
7/27An example of total cycle time
Welding
30%
Where does your welding dollar go?
Changing Reels / Cylinders
5%
Grinding10%
Cleaning
5%
Breaks
10%
Fixturing and Positioner15%
Tacking
5%Movement of parts into / out of cell
10%
Layout
15%
-
7/28/2019 1. Productivity
8/27
Heat treating
Cutting / Beveling
Layout / Assembly
Tacking / Fixtureing
Painting
Machining
Bending / Forming
Drilling / Punching
Cleaning / Grinding
Trash
Typical pre & post operations
Towards increased productivity
-
7/28/2019 1. Productivity
9/27
Equipment breakdowns
Maintenance costs
Service problems
Weld repairs
Weld finishing
Excessive electrode wastage
Excessive gas wastage
Towards increased productivityHidden costs
-
7/28/2019 1. Productivity
10/27
Electrode baking handling and storage
Gas handling and storage
Consumables shelf life
Inventory requirements
Environmental restrictions
System redundancy
Penalties for late delivery
Towards increased productivityHidden costs
-
7/28/2019 1. Productivity
11/27
Labour & Overheads
70%
Welding Cell or Work Station
7%
10% Cost
Reduction
10%Price Cut
Welding
Material30%
3%
Bottom Line Pass Through
Ways to increase productivity
-
7/28/2019 1. Productivity
12/27
Ways to increase productivity
-
7/28/2019 1. Productivity
13/27
Ways to increase productivityBasic cost of welding formula
Labour+Consumable + Overhead
Consumable = EfficiencyCost / kg
Labour + OH = (Labour + Overhead rate) x Hours to weld
Hours to weld =Deposition rate x Operating factor
Weight of weld metal required (kg)
-
7/28/2019 1. Productivity
14/27
Ways to increase productivityOperating factor
Operating Factor =Total work hours
Arc-on hours
Robotics 80%
Automatic 50%
Semi automatic 30%
Stick electrode 20% Maximum
-
7/28/2019 1. Productivity
15/27
Ways to increase productivityDeposition efficiency
Percentage of consumable that becomes weld metal
Submerged Arc 100% 10.0 kg
GMAW - Short Arc 95% 10.5 kg
GMAW - Spray Arc 90% 11.0 kg
FCAW-GS 85% 11.7 kg
FCAW-GS Metal core 98% 10.2 kg
FCAW-SS 82% 12.2 kg
Stick Electrode 60% 16.7 kg
10 kg weld metal requires:
-
7/28/2019 1. Productivity
16/27
Ways to increase productivityDeposition rate
Weight of weld metal deposited per hour (kg / hr)
4.0 mm 6013 1.7 kg / hr
4.0 mm 7024 2.8 kg / hr
1.2 mm ER70S-6 3.0 kg / hr
At 200 Amps:
1.2 mm ER70S-6 5.0 kg / hr
1.2 mm E71T-1 5.7 kg / hr
2.0 mm E70T-4 6.9 kg / hr
At 300 Amps:
-
7/28/2019 1. Productivity
17/27
Ways to increase productivityArc time (based on operating factor)
Arc time* =Deposition rate
Weight of weld metal Operating Factor
*To deposit 17 kg weld metal (100 m x 6 mm (flat) fillet)
4.0 mm 6013 50 hours
4.0 mm 7024 30 hours
1.2 mm ER70S-6 19 hours
At 200 Amps:
1.2 mm ER70S-6 11 hours
1.2 mm E71T-1 10 hours
2.0 mm E70T-4 8 hours
At 300 Amps:
-
7/28/2019 1. Productivity
18/27
6 mm fillet Vs. 8 mm fillet
Weight of weld metal for 100 m flat fillet =
Ways to increase productivityReduce over welding
6 mm = 17 kg
8 mm = 30 kg
-
7/28/2019 1. Productivity
19/27
Ways to increase productivityReduce preparation
-
7/28/2019 1. Productivity
20/27
Optimum procedure:
1.2 mm ER70S-6 300 amps 5 kg / hour
Actual procedure:
1.2 mm ER70S-6 280 amps 4.5 kg / hour
Difference:
10% decrease in deposition rate
10% increase in time, labour and overhead
Ways to increase productivityEnforce procedure control
-
7/28/2019 1. Productivity
21/27
Double bevel = 3 kg / metre
Single bevel = 6 kg / metre
Reduced welding labour
Balanced shrinkage stresses
Ensure accessibility from both sides
Ways to increase productivityConsider joint design
-
7/28/2019 1. Productivity
22/27
Dual process wire feeders / power sources
User designable waveforms
Waveform control technology
Ways to increase productivityKeep up to date with new technology
-
7/28/2019 1. Productivity
23/27
Ways to increase productivityOptimize processes
3 times faster than GTAW
Easier operation than GTAW
Low heat input
-
7/28/2019 1. Productivity
24/27
Ways to increase productivitySurface Tension Transfer
Suitable for on-shore / off-shore pipelines
STT for root pass
FCAW-SS for fill and cap
Root pass requires minimal grinding or patching
FCAW-SS can be applied immediately
-
7/28/2019 1. Productivity
25/27
Ways to increase productivity
Can be used for process piping to ASME
Surface Tension Transfer
-
7/28/2019 1. Productivity
26/27
Ask your Lincoln Country Manager
Have a survey conducted on your premises
Discuss and review opportunities
Work together and achieve documented goals
Ways to increase productivityDocumented Cost Reduction
-
7/28/2019 1. Productivity
27/27
Questions ?