1 PFP IPDR 2010/6/14 - 16 Particles and Fields Package (PFP) GSE Timothy Quinn.
1 PFP MSR, 08/17/2010 Particles and Fields Package Monthly Status Review (MSR) Aug 17, 2010 Dave...
-
Upload
shanon-jemimah-hardy -
Category
Documents
-
view
215 -
download
0
Transcript of 1 PFP MSR, 08/17/2010 Particles and Fields Package Monthly Status Review (MSR) Aug 17, 2010 Dave...
1PFP MSR, 08/17/2010
Particles and Fields PackageMonthly Status Review (MSR)
Aug 17, 2010
Dave Curtis, PFP PM
2PFP MSR, 08/17/2010
SSL Contracting Status
• Phase B/C/D Contract in place.
3PFP MSR, 08/17/2010
Schedule Status
• Slack to CDR has eroded from 4.2 to 3 weeks, mostly due to delays in EM part procurement.
• Delay in PFP EM I&T results in delays in start of next FSW build, resulting in loss of slack in FSW delivery (11.4 to 7.8 weeks)– Puts FSW on critical path– Odd because FSW is actually ahead of schedule.
• Added 8w to schedule margin due to need date slipping to the right.
4PFP MSR, 08/17/2010
Manpower
• Ramping up complete– Added final ME to SWIA/STATIC team
• New position open to augment QA team due to Ron Jackson’s retirement
5PFP MSR, 08/17/2010
Accomplishments
• Completed all pre-PDR deliverables• Completed peer reviews, IPDR, MPDR• Most EM EEE parts on order – just a few actives and
some passives left– Part qualification testing has been delayed till next FY, which
adds some schedule risk in case parts fail screening
• PWBs are in layout• EM Mechanical parts are starting to go to fab• PFP FSW Boot code ~1/2 coded• Completed LPW sensor geometry trade
• More in instrument sections…
6PFP MSR, 08/17/2010
Ongoing Work
• Supporting Project planning process• Supporting EMC, Payload, SDT working groups
• Working parts issues with PCB• Completing layouts and mechanical part level designs• Working off RFAs
7PFP MSR, 08/17/2010
PFP RFA Status
Review Actions Closed %SWEA Peer 20 20 100%
Mechanical Peer 8 8 100%Analyzer Peer 11 11 100%Power Peer 0Digital Peer 4 4 100%FSW Peer 0LPW Peer 11 11 100%MAG Peer 5 5 100%
LPW Mech Peer 7 0%
IPDR 6 0%
Totals 72 59 82%
8PFP MSR, 08/17/2010
Trades
• Considering changing LPW boom whip caging– Nick Jedrich Mechanical Peer Review recommendation– Now that sensor geometry has been decided, can proceed.– Change from caged to fixed whip
• Deletes caging mechanism mass & resources• Deletes whip hinge• Deletes an actuation• Simplifies qualification
– Concerns being investigated• Enhanced vibration on whip, preamp
– Have ideas for mitigations which look promising– Plan for building a demonstration model to vibrate this month.
• Potential damage to exposed whips during I&T– Possibly remove whip for some of ATLO
– SSL & LM current see no show-stoppers
9PFP MSR, 08/17/2010
Issues [1]
• Magnetics– Current sensor location on solar array probably does not work
• Too close to solar array strings• AC magnetics too high
– Working with Project on alternatives
10PFP MSR, 08/17/2010
Issues [2]
• SWEA Surface Treatment– Need to modify thermal characteristics of surfaces in SWEA
aperture to avoid excessive heating - candidate solutions in work– Candidate solutions need to be evaluated for Atomic Oxygen
effects, charging effects, thermal properties, and robustness• AO test in progress
– Current candidates: DAG213, Ebanol-C, Black Nickel, Black Chrome, Z307
– SWIA and STATIC also interested
• SEP detector Atomic Oxygen effects– Heritage instruments survives AO, but we would like to test a
MAVEN detector if possible.• Included in the test
11PFP MSR, 08/17/2010
Issues [3]
• Amptek HV801 failures– Seems to be a lot workmanship issue– New lot in work at Amptek, but not certain they will be better– Projects ahead of MAVEN in trouble, will have higher priority for
parts• SWIA, STATIC use HV801• Alternative VMI part has acceptable performance
– Tested in breadboard– Much too large for existing layout– Significant changes would need to be made to accommodate
• mass, schedule impact
• Micropak has built equivalent demo parts with same form factor– Parts in test (one at SSL)
12PFP MSR, 08/17/2010
Issues [4]
• SWEA Planetary Protection– CESR part of SWEA FM build in progress– Will be assembled before the breakup/burnup analysis
complete• Current PP plan indicates SWEA is likely to burn up• SWEA is small, not a large contributor even if it does not burn up
– SWEA has stringent contamination concerns due to MCP, and so is already built in very clean conditions
– Need to decide if we need extra steps such as bio assay– This is the same as the rest of MAVEN, but with a sooner
trigger date• FM fab already started, mechanical assembly starts in November
13PFP MSR, 08/17/2010
Issues [5]
• Launch Loads– The current random vibe levels in the ERD are significantly higher than
anything we have worked to on previous missions• 23GRMS for forward deck mounted instruments• 47GRMS for MAG
– MAC curve limit loads are as high as 72g– Corresponds to design loads significantly greater than 100G, which is
the usual design target at SSL– Greater than qualification level for heritage instruments which were
expected to fly with minimal changes• SWEA, SEP, LPW booms
– A concern for some structures• Historically loads come down significantly once we get CLA
– CLA is due ~October, well before CDR• PFP plan is to follow LM’s lead and not redesign to these unrealistic
loads– When CLA comes in there is a risk we will have to do some redesign
14PFP MSR, 08/17/2010
Issues [6]
• THEMIS SST Attenuator anomaly– MAVEN SEP attenuator design is identical to THEMIS SST– THEMIS attenuator life tested to ~75,000 cycles– One of 10 flight attenuators failed to completely open after ~3
years on orbit and ~4,000 cycles• MAVEN expected life is ~2,000 cycles.
– Diagnostics indicate the problem is not the end-of-travel microswitch (an early candidate), but the “Nanomuscle” actuator itself
– Looking at ways to improve the actuator reliability– MAVEN has 2 independent SEP telescopes. Failure of one
attenuator impacts part of the science from one telescope; can still meet Level 1.
15PFP MSR, 08/17/2010
Top Risks
• New risk 17
MAVEN PFP RISK MANAGEMENT Chg RANK ID Approach TITLE
1 P-04 Mitigate Solar Array Magnetics
55 10 15 20 25
2 P-10 Watch Operational Heaters
44 8 12 16 20
3 P-16 Watch Launch Loads
33 8 9 12 15
4 P-17 Watch Parts Qualification
22 4 6 8 10
5 P-14 Mitigate HV801 Problem
11 2 3 4 5
6 P-15 Mitigate SWEA Surface Charging
1 2 3 4 5
Criticality Approach
High
Medium
Low
LIKELIHOOD
Improved
Worsening
Unchanged
New this month
Mitigate
Watch
Accept
Research
CONSEQUENCES
L * C Trend
*
P15
P16
P4
P14
P10
P17
*
16PFP MSR, 08/17/2010
Risks List [1]
ID Title Type P I Crit Risk Statement Impact Term Plan Approach Comments
P-01 SSL ManpowerProject
Execution2 2 L
Delays in RBSP leads to manpower conflicts at SSL
Schedule erosion, cost to recover
Near Term
Hire new people to take routine tasks off key personnel
Mitigate Review in March 2010Add extra Power Converter person 1/2010Add extra ME 2/2010Add extra QA 8/2010
P-04Solar Array Magnetics
Mission Performance
4 4 H
Proximity of MAG sensor to solar arrays results in not meeting the magnetics requriements
Magnetics [MRD84]
Near Term
Consider ways to increase distance between MAG and cells
Mitigate Magnetics Working Group working on options
P-07Delayed LPW
Boom Deployment
Mission Performance
1 3 L
Waiting till after MOI to deploy LPW booms results in them sitting undeployed for over a year, increasing the risk of deployment failure
Potential severe degradation of LPW measurement
Far Term
Investigate if LPW booms can be deployed early
Research Early deployment of LPW booms reduces this risk. Actual risk of failure is very low. Risk that we may be asked to do an expensive verification is moderate
P-08
EUV sensor damaged by exposure to atmosphere
Mission Performance
1 3 L
If EUV does not close its door before deep dips (or any periapsis where EUV points into the RAM direction) sensor can be damaged
Degradation of EUV Lyman Alpha sensor
Far Term
- Include EUV door close to instrument autonomy rules.- Add MOC/SOC flight rule to reduce risk that human error results in incorrect operational script
Mitigate
P-10Operational
HeatersProject
Execution4 4 H
If operational heater reequirement to survive eclipse is significant, could impact power budget
Power Mid Term
Pending thermal analysis Watch Pending thermal models, spacecraft environments (after PDR)
P-13 Atomic OxygenMission
Performance2 3 L
If atomic oxygen degrades exposed surfaces, thermal, ESC, or other characteristics could be impacted
Thermal, ESC Mid Term
Test materials if existing data is insufficient
Mitigate AO test selected materials
17PFP MSR, 08/17/2010
Risks List [2]
ID Title Type P I Crit Risk Statement Impact Term Plan Approach Comments
P-14 HV801 ProblemProject
Execution2 3 L
If HV801 not available a redesign would be required to use alternate (larger) parts
Schedule, Mass Mid Term
Watch what programs ahead of MAVEN do; look into alternate parts
Mitigate Micropak alternate part in test
P-15SWEA Surface
ChargingMission
Performance2 3 L
If SWEA (and to a lesser extent, STATIC) surfaces charge as STEREO did will lose low energy measurement
Performance Near Term
Do not use material which exhibited charging on STEREO. Verify any new material does not (difficult as the mechanisism for how the material charged is not fully understood)
Mitigate Material also needs to be insensitive to AO (P-13)
P-16 Launch LoadsProject
Execution3 3 M
If launch loads do not come down, will have to redesign instruments
Schedule Near Term
Wait for CLA before redesigning for unrealistically high loads
Watch Expect CLA ~9/2010, in time to redesign by CDR
P-17Parts
QualificationProject
Execution3 3 M
If parts fail qualification then system would have to be redesigned for alternate (which may also have to be qualified and may have lower performance)
Schedule, Cost, Performance
Mid Term
Start parts qualification as soon as possible (but delayed to FY11 for funding)
Watch
18PFP MSR, 08/17/2010
PFP Mass
• PDR masses• NTE reallocation per CCR182• EUV mass growth due to mechanism change
Instrument QuantityCBE Each
[kg]CBE
Total [kg] Cont. (%)Total [kg] (CBE+cnt)
Particles and Fields 21.30 28% 27.19LPW Total 6.50 17% 7.62
LPW Booms 2 5.482 20% 6.578EUV Assembly 1 1.014 2% 1.039
STATIC Total 2.36 35% 3.19SWEA Total 1.60 21% 1.94SWIA Total 2.02 30% 2.62SEP Total 1.27 20% 1.52MAG Total 0.65 20% 0.78PFDPU Total 4.88 20% 5.86PF Intra-Instrument Harness Total 2.03 81% 3.67
19PFP MSR, 08/17/2010
Mass Tracking Chart
PFP Mass Trend
15.00
20.00
25.00
30.00
35.00
10/1/2009 11/20/2009 1/9/2010 2/28/2010 4/19/2010 6/8/2010 7/28/2010
Date
kg
15%
20%
25%
30%
35%
Mass CBE, kg
Mass NTE, kg
Mass Margin %
20PFP MSR, 08/17/2010
PFP Power
• Increase in SEP power due to calculation error in previous version
• Liens:– Expect to need operational heat during eclipse
• None allocated for most instruments; amount needed pending thermal analysis• Preliminary estimates included for MAG and EUV• IPDR numbers for the remaining instruments are up to 13.3W (worst case cold)
– Hoping to improve on that using the LM-provided environments, pending
Instrument CBE [W] Cont. (%) NTE [W] CBE [W] Cont. (%) NTE[W] CBE [W] Cont. (%) NTE[W]Particles and Fields
Off (heater only) 0.00 0.00 10.58 18% 12.46 10.58 18% 12.46Standby 9.30 35% 12.52 3.81 15% 4.39 13.11 29% 16.91Nominal 19.20 16% 22.29 3.40 15% 3.91 22.60 16% 26.20
Peak 31.90 16% 37.01 15.90 15% 18.29 47.80 16% 55.30Orbit Average 19.31 16% 22.39 3.40 15% 3.91 22.71 16% 26.30
Orbit Average:LPW 4.77 15% 5.49 0.00 0% 0.00 4.77 15% 5.49EUV 0.16 15% 0.18 1.80 15% 2.07 1.96 15% 2.25STATIC 4.39 19% 5.21 0.00 0% 0.00 4.39 19% 5.21SWEA 1.07 15% 1.24 0.00 0% 0.00 1.07 15% 1.24SWIA 2.05 22% 2.50 0.00 0% 0.00 2.05 22% 2.50SEP 2.60 -14% 2.24 0.00 0% 0.00 2.60 -14% 2.24MAG 2.47 15% 2.84 1.60 15% 1.84 4.07 15% 4.68PFDPU 1.78 51% 2.69 0.00 0% 0.00 1.78 51% 2.69
Operational Heater Total
21PFP MSR, 08/17/2010
PFP Power Trend
PFP Power Trend
15.00
20.00
25.00
30.00
10/1/2009 11/20/2009 1/9/2010 2/28/2010 4/19/2010 6/8/2010 7/28/2010
Date
W
0%
10%
20%
30%
Power CBE, W
Power NTE, W
Power Margin %
22PFP MSR, 08/17/2010
PFP Data Rate
• Per 2009-6-9 allocations from Bruce
Rate [bps]Particles and FieldsLPW/EUV 717.0STATIC 2000.0SWEA 600.0SWIA 604.0SEP 160.0MAG 660.0PFDPU 30.0
Total 4771.0
Instrument
23PFP MSR, 08/17/2010
Requirements Verification Status
• Nothing to report
24PFP MSR, 08/17/2010
MAVEN Magnetometer Status
Aug 5, 2010
Connerney, Sheppard, Schnurr, etc.
25PFP MSR, 08/17/2010
GSFC/MAG - Accomplishments Last Month(s)
• MAG supported to a successful conclusion IPDR (at UCB) and Mission PDR
(GSFC – 07/12-15/2010).
• Closed out all MAG-related RFA’s (per email 08/03 Ken Wagner)
• Received circuit boards for MAG a/c heater circuit.
• Initiated procurement of long-lead items:– Mil spec CMOS quad bilateral switches (4066’s).
– LTC1604 ADCs and Aeroflex PWM 5032 for new heater design.
– Fabrication of sensor assembly parts (currently out for bids).
• Continued discussions with Project and GSFC management re SIP (budget).
• Provided Solar Array design tutorial, SA qual coupon test plan, Juno SA qual
coupon test results, support to GSFC/LM magnetics working group.– Recommend sensor accommodation on extended SA substrate (1” thick M55J
Aluminum honeycomb/CC facesheet panel) at max separation that can be
affordably achieved (>1m). Recommended independent (GSFC) analysis of
mechanical design.
26PFP MSR, 08/17/2010
Near Term Plans & Open Issues
• Support (now weekly) budget discussions with Project, Code 600 management, and Director’s management.
• Complete EM board layout.• Initiate winding of magnetics (transformers, inductors).• Completion of procurement activity to meet GSFC cut-off
dates– Aug 11 for transfer of funds – Aug 13 for funds commitment
• Assist MAG Sensor accommodation trade (design).– Extend the SA panel substrate (1.5 m from SA strings may be
possible).
27PFP MSR, 08/17/2010
MAVEN PFP SWIA Status
Aug 2010
Jasper Halekas, SWIA Lead
28PFP MSR, 08/17/2010
SWIA Progress
• PDR Passed– No major issues, all actions and recommendations completed
• Active and passive parts lists complete– Long lead items: MCPs and A121 preamps ordered
• Schematics for all boards complete– Anode board in layout– Mechanical details on preamp/MCP board in progress– HVPS prototype testing ongoing– Digital board and LVPS board ready for layout
• Mechanical design maturing– First priority: Support layout– Second priority: Flesh out and fabricate attenuator mechanism
and anode/MCP housing– Third priority: Finish and fabricate full analyzer
• FPGA Testing in progress
29PFP MSR, 08/17/2010
SWIA Issues
• Staffing– ME staffing continues to be an issue
• Dalton largely busy with RBSP• Johnson splitting time between RBSP, STATIC, SWIA
– Layout queue is tight– Many people out on vacations after PDR
• Parts concerns– VMI multipliers– Switches– MOBI actuators– TiNI pin-pullers
30PFP MSR, 08/17/2010
SWIA Simulated Test FPGA Output
• FPGA simulation tested with 24 constant count rates for each anode
• Output de-commutated and plotted using SSL standard IDL routines (different color scales)
• Working Nominally!
P0 First Energy StepP0 First Energy Step
P2 First Energy StepP2 First Energy StepP1 First Energy StepP1 First Energy Step
31PFP MSR, 08/17/2010
MAVEN PFP SWEA Status
August 2010
Dave Mitchell, SWEA Lead
32PFP MSR, 08/17/2010
SWEA Status
• Mechanical– New mechanical parts fabrication and coating – ongoing (expect to
complete in September)
• Front-end Electronics (MCP, HVPS)
– Electronic parts procurement – done
– PCB fabrication – done
– HV optocouplers – procured, fabrication in progress, final assembly in September
– Transformers fab & test – fab complete, not yet tested
• LVPC & Digital– LVPC design/parts selection – done
– Digital design – schematic and final parts list done, checking PCB part information and footprint
33PFP MSR, 08/17/2010
• Surface Coating for Deflectors and Toroidal Grids– Current candidates are: black chrome, black nickel, DAG213, Z307,
and Ebanol-C.
– Samples procured and delivered to GSFC for testing.
– Laboratory tests are underway to measure electrical & thermal properties before and after exposure to atomic oxygen.
• Mechanical Design of Aperture– Current mechanical loads spec exceeds SWEA’s tolerance.
– Awaiting results of CLA analysis (expected October 2010).
– May need to redesign support ribs to make them stronger.
– Results in schedule delay, but still plenty of margin at CESR and SSL to handle delay.
SWEA Work in Progress
34PFP MSR, 08/17/2010
MAVEN PFP STATIC Status
August 2010
Jim McFadden, STATIC Lead
35PFP MSR, 08/17/2010
STATIC Accomplishments
• RFAs from peer-review and PDR closed• Carbon foil carrier frames ordered, carbon foils re-ordered• Foil floating and carrier mounting scheme established – next
step involves mounting carbon foils on flight carriers• Mechanical details of TOF modified for to accommodate thermal
expansion and modeled for stiffness and vibration modes.• TOF mechanical drawings completed and sent out for quote• Anode board layout reworked to accommodate new test pulse
connectors• TDC parts changes to schematic completed• Calibration room equipment removed from 320E and prepared
for painting• MCP quote from Photonis received• Thick foil quote from Luxel received• FPGA daughter board mechanical design complete
36PFP MSR, 08/17/2010
STATIC Open Issues
• STATIC HV Sweep testing resumed – new HV opto-coupler testing started, still debugging HV oscillations.
• TDC needs layout changes to accommodate parts changes and remove ground bounce (add some capacitance) – negotiating for tech layout time
• STATIC FPGA still in development – need new test setup for complete throughput test (anode-preamp-TDC-Digital).
• Mechanical Attenuator still in development • Mechanical details of HV connectors still in development• MCP clamping spring force calculations in processes• New 15 kV / MCP board layout to proceed when EE is
available, VMI multipliers need to be ordered.• Waiting on order for carbon foils and carbon foil carrier frames • Waiting on feedback from campus with regard to refurbishing
the clean room (320D).
37PFP MSR, 08/17/2010
MAVEN PFP SEP Status
August 15, 2010
Davin Larson, SEP Lead
38PFP MSR, 08/17/2010
SEP Accomplishments
• DAP board is in layout. – All parts are placed.– Shaping section is finished.– Routing continuing on digital section.– 75% complete
• Foils are ordered from Luxel.• Mechanical parts mostly ordered (a few parts still left)• Determined that leftover yokes from THEMIS are fine for
MAVEN EM• Detector Order placed with LBNL
39PFP MSR, 08/17/2010
SEP Open issues
• DFE Board Layout must be started still• Not completely finalized cable connector pinout yet.• Must begin magnet selection for magnet cage.• THEMIS Anomaly
– Need to decide if any changes are needed to attenuator design to improve reliability
40PFP MSR, 08/17/2010
MAVEN PFP PFDPU, Power Converter & GSE Status
August 2010
Dorothy Gordon
41PFP MSR, 08/17/2010
DCB Status
• PFDPU Processor DCB Schematics have been completed External Contractor selected for the DCB and FPGA Daughter Board Layouts DCB PCB Layout has been started
Parts Definition and Placement in process Routing to begin next week
DCB FPGA Detailed Design has been started• FPGA Daughter Card
PCB Layout contract in place for both daughter boardsParts Definition and Placement in processCoordinating mechanical design with the mother boards
Voltage Nominal Current
Max Current
+5VA 20mA 50mA -5VA 25mA 50mA +5VD 5mA 10mA
+3.3VD 220mA 450mA +1.5VD 150mA 350 mA Estimated DCB Power Supply Requirements
42PFP MSR, 08/17/2010
DCB and FPGA Daughter Board Placement
43PFP MSR, 08/17/2010
GSE Status
• GSE Hardware– MISG #1 has been built and is undergoing test
• ZestET1 daughter card is integrated • FPGA code is under development
• GSE Software– Set up software version control server (SVN)
• Located at https://maven.ssl.berkeley.edu/svn – Available as a resource for the SSL MAVEN Team
– Transitioned all software (GSEOS, SSG) to SVN system. – Set up system on GSEOS to convert instrument command and
telemetry definition files to the format required by GSEOS• Modeled after flight software CTM document • Input is an Excel Spreadsheet• Output is a set of GSEOS configuration files
44PFP MSR, 08/17/2010
Power Converter Status
• Schematics– Preliminary Schematics are being finalized in preparation for
PCB Layout• DRC Removal • Incorporation of footprint and detailed parts information
– REG Board Circuit Revised• Initial safing circuit timer used capacitors that were too
consumptive of real estate. This circuit has been redesigned and incorporated into the new schematics.
• To reduce power consumption the AD823s were replaced with LTC2054HVs in four of eight locations.
– IIB Schematics are in process
45PFP MSR, 08/17/2010
Power Converter Status
• Testing and Development– SWIA, SWEA and STATIC Buck regulators and resonant supplies
topologies have been tested• Prototype circuits have been evaluated for output voltage,
ripple, regulation, consumption, and stability. • We have proven the basic topologies intended for ETU on the
three boards above and several of the supplies used on the IIB.
– The next candidate for the bench testing is the ± 90 volt supply. – Magnetics development
• The buck regulator magnetics have been developed for SWIA and SWEA
• STATIC still pending (similar to the others)
46PFP MSR, 08/17/2010
VI Curves for SWIA LVPS (1)
VI Curve
11.00
12.00
13.00
14.00
15.00
16.00
17.00
0.000 0.002 0.004 0.006 0.008 0.010 0.012
12V AnalogVI Curve
5.50
6.00
6.50
7.00
7.50
8.00
8.50
9.00
0.000 0.010 0.020 0.030 0.040 0.050 0.060
6V Digital
VI Curve
23.00
25.00
27.00
29.00
31.00
33.00
35.00
37.00
39.00
0.000 0.020 0.040 0.060 0.080 0.100 0.120
28V Analog
47PFP MSR, 08/17/2010
VI Curves for SWIA LVPS (2)
VI Curve
4.50
5.00
5.50
6.00
6.50
7.00
7.50
8.00
8.50
0.000 0.050 0.100 0.150 0.200 0.250
+5V Analog VI Curve
5.00
5.50
6.00
6.50
7.00
7.50
8.00
8.50
0.000 0.002 0.004 0.006 0.008 0.010
-5V Analog
48PFP MSR, 08/17/2010
MAVEN PFP Flight Software Status
August 6 2010
Peter Harvey
49PFP MSR, 08/17/2010
Schedule Tracker
Progress Points=Telecons with GSFC. 1 pt for each telecon, 0 if the telecon did not happen.
Management Effort. Expected 10% or less, but has required phase A requirements and plans to be written in phase B.
Milestone PDRDescription Apr-10 May-10 Jun-10 Jul-10 Aug-10 Sep-10 Oct-10 Nov-10 Dec-10Product Characteristics
Project Name MAVEN MAVEN MAVEN MAVENLanguage C C C C
Software Domain (FSW) FSW FSW FSW FSWSLOC Expected 9180 9180 9180 9180
SLOC To Date 0 0 771 1645Software Progress
Major Events Planned 1 1 1 0Major Events Actual 1 1 1 0
Progress Points Planned 1 1 1 1 1 1 1 1 1Progress Points Actual 0 1 0 1
Effort-Software Planned 90% 90% 90% 90% 90% 90% 90% 90% 90%Effort-Software Actual 0% 0% 24% 45%
Risks (Low) 0 3 4 4Risks (Med) 0 0 0 0Risks (High) 0 0 0 0
Project PlanningCost/Schedule Revs Planned 0 0 1 0
Cost/Schedule Revs Actual 1 0 1 0Effort-Management Planned 10% 10% 10% 10% 10% 10% 10% 10% 10%
Effort-Management Actual 24% 79% 37% 10%Software Functionality
Requirements Planned 8.1 16.2 24.3 32.4 40.5 55.75 71Requirements Actual 0 0 19 28
Software QualityFSW Defect Count 0 0 0 0 0 0 0 0 0
non-FSW Defect Count 0 0 0 0Inspections Planned 0 0 0 0 0 0 1 0 0
Inspections Actual 0 0 0 0Effort-Quality Planned 0 0 0 0 0 0 0.2 0 0
Effort-Quality Actual 0 0 0 0Configuration Management
VDD Reviews Planned 0 0 0 0 0 0 1 0 0VDD Reviews Actual 0 0 0 0
CM Meetings Planned 0 0 0 0 0 0 0 0 0CM Meetings Actual 0 0 0 0
Requirements ManagementRequirements Changes 0 0 2 0
Requirement TBDs-STATIC 0 0 0 0Requirement TBDs-SEP 0 0 0 0
Requirement TBDs-SWIA 0 0 0 0Requirement TBDs-SWEA 0 0 0 0
Requirement TBDs-LPW 0 0 0 0Requirement TBDs-MAG 0 0 0 0
Requirement TBDs-TOTAL 0 0 0 0Effort-Engineering 24% 0% 3% 0%
50PFP MSR, 08/17/2010
Technical Status
Technical Status Command module : message decoding, buffering, distribution, RTS execution, time
message recognition. Loader module : Memory loading, bit manipulation Software tests being performed using Code Warrior simulator, breakpoints, etc.
Upcoming
Update Level 5’s (derived from Level 4’s)
51PFP MSR, 08/17/2010
Action Items
PFISPDRRFA2 – Command and Telemetry Database
Action: When creating the Command and Telemetry Database for the PFIS follow mnemonic naming standards so that the database can be delivered to the Asist and OASIS teams.
Rationale: The developers of the FSW should be the originator of their respective database. Since the PFIS team is using their own flavor of GSE, they should create the database so that it is compatible with the project Command and Telemetry Database.
Originator: Tom Jackson/GSFC
Activity:Contact with LM regarding naming conventions have been through email. No document is readily apparent.Commands: 16 character limit, Upper Case Only, no special characters except “_”Telemetry: Upper and Lower Case UsedInstrument Prefixes:
SWE – SWEA instrumentSWI – SWIA InstrumentSTA – STATIC InstrumentSEP – SEP InstrumentLPW – LPW InstrumentEUV – EUV InstrumentMAG – Magnetometer instrumentPFP – PFP commands/telemetry not directly related to a single instrument.
52PFP MSR, 08/17/2010
1-Page Fever Chart
BOOT Apr-10 May-10 Jun-10 Jul-10 Aug-10 Sep-10 Oct-10 Nov-10 Dec-10RequirementsSpecificationsSoftware DevelopmentTesting
OPERATIONAL Apr-10 May-10 Jun-10 Jul-10 Aug-10 Sep-10 Oct-10 Nov-10 Dec-10RequirementsSpecificationsSoftware DevelopmentTesting
LegendGreat. Ahead of ScheduleConcern about somethingProblems!