1 PETE 411 Well Drilling Lesson 6 Drilling Structures.
-
Upload
sherman-norris -
Category
Documents
-
view
304 -
download
21
Transcript of 1 PETE 411 Well Drilling Lesson 6 Drilling Structures.
![Page 1: 1 PETE 411 Well Drilling Lesson 6 Drilling Structures.](https://reader033.fdocuments.in/reader033/viewer/2022061507/56649eb05503460f94bb5f5a/html5/thumbnails/1.jpg)
1
PETE 411 Well Drilling
Lesson 6
Drilling Structures
![Page 2: 1 PETE 411 Well Drilling Lesson 6 Drilling Structures.](https://reader033.fdocuments.in/reader033/viewer/2022061507/56649eb05503460f94bb5f5a/html5/thumbnails/2.jpg)
2
Types of Drilling Structures
Conventional Rotary Rig for drilling on Land
Alternate Drilling Structures
Structures for deep Water or Arctic Drilling
Hydrogen Sulfide and RULE 36
![Page 3: 1 PETE 411 Well Drilling Lesson 6 Drilling Structures.](https://reader033.fdocuments.in/reader033/viewer/2022061507/56649eb05503460f94bb5f5a/html5/thumbnails/3.jpg)
3
Read:
Applied Drilling Engineering, Ch.5 (bits)
HW #3: Posted (due Sept. 18, 2002)
Find HW #3 and Lessons at:
http://pumpjack.tamu.edu/~juvkam-wold/
Homework
![Page 4: 1 PETE 411 Well Drilling Lesson 6 Drilling Structures.](https://reader033.fdocuments.in/reader033/viewer/2022061507/56649eb05503460f94bb5f5a/html5/thumbnails/4.jpg)
4Standard Derrick - Engines close to derrick - Mechanical Transmission
![Page 5: 1 PETE 411 Well Drilling Lesson 6 Drilling Structures.](https://reader033.fdocuments.in/reader033/viewer/2022061507/56649eb05503460f94bb5f5a/html5/thumbnails/5.jpg)
5
700 hp ENGINE
COMPOUND 700 hp ENGINE
700 hp ENGINE
![Page 6: 1 PETE 411 Well Drilling Lesson 6 Drilling Structures.](https://reader033.fdocuments.in/reader033/viewer/2022061507/56649eb05503460f94bb5f5a/html5/thumbnails/6.jpg)
6
Drilling Structures:
Conventional Land RigJack-up RigDrillshipSemisubmersibleJacket PlatformGravel Island Ice IslandGuyed TowerTension Leg PlatformSpar Platform
![Page 7: 1 PETE 411 Well Drilling Lesson 6 Drilling Structures.](https://reader033.fdocuments.in/reader033/viewer/2022061507/56649eb05503460f94bb5f5a/html5/thumbnails/7.jpg)
7
Pile-founded steel jacket platform
Cost increases rapidly with depth
Bending moments
Natural Frequency
Mud Line
![Page 8: 1 PETE 411 Well Drilling Lesson 6 Drilling Structures.](https://reader033.fdocuments.in/reader033/viewer/2022061507/56649eb05503460f94bb5f5a/html5/thumbnails/8.jpg)
8 Buoyed tower concept of 1970
~100 sec nat.frequency(waves ~ 6-10 sec)
Pivot at bottom(problem)
![Page 9: 1 PETE 411 Well Drilling Lesson 6 Drilling Structures.](https://reader033.fdocuments.in/reader033/viewer/2022061507/56649eb05503460f94bb5f5a/html5/thumbnails/9.jpg)
9Principal features of the Lena guyed tower
200 TON CLUMP WEIGHTS
FAIRLEAD
19831,000 ftof water
![Page 10: 1 PETE 411 Well Drilling Lesson 6 Drilling Structures.](https://reader033.fdocuments.in/reader033/viewer/2022061507/56649eb05503460f94bb5f5a/html5/thumbnails/10.jpg)
10Arctic drilling structure - Ice Island
High ice forcesWeak soildShallow water
~1,000 ft dia.
![Page 11: 1 PETE 411 Well Drilling Lesson 6 Drilling Structures.](https://reader033.fdocuments.in/reader033/viewer/2022061507/56649eb05503460f94bb5f5a/html5/thumbnails/11.jpg)
11
![Page 12: 1 PETE 411 Well Drilling Lesson 6 Drilling Structures.](https://reader033.fdocuments.in/reader033/viewer/2022061507/56649eb05503460f94bb5f5a/html5/thumbnails/12.jpg)
12
![Page 13: 1 PETE 411 Well Drilling Lesson 6 Drilling Structures.](https://reader033.fdocuments.in/reader033/viewer/2022061507/56649eb05503460f94bb5f5a/html5/thumbnails/13.jpg)
13
Spar Platform in Transit
![Page 14: 1 PETE 411 Well Drilling Lesson 6 Drilling Structures.](https://reader033.fdocuments.in/reader033/viewer/2022061507/56649eb05503460f94bb5f5a/html5/thumbnails/14.jpg)
14
Spar Platform Installed
![Page 15: 1 PETE 411 Well Drilling Lesson 6 Drilling Structures.](https://reader033.fdocuments.in/reader033/viewer/2022061507/56649eb05503460f94bb5f5a/html5/thumbnails/15.jpg)
15
Rule 36 - TRC
Protection of the General Public from the Effects of H2S
Applicable if H2S Concentration > 100 ppm
Operator must determine the H2S Concentration and the Potential Flow Rate
Radius of ExposurePoint of Escape
![Page 16: 1 PETE 411 Well Drilling Lesson 6 Drilling Structures.](https://reader033.fdocuments.in/reader033/viewer/2022061507/56649eb05503460f94bb5f5a/html5/thumbnails/16.jpg)
16
H2S
Determination of Radius of Exposure
The 100 ppm radius of exposure (in ft)
6258.02100 xture) Q] in gas miion HMole fract( 589.1[R
R100= dist. from source where H2S conc. = 100 ppm
Q = source strength = open flow potential, SCFD
![Page 17: 1 PETE 411 Well Drilling Lesson 6 Drilling Structures.](https://reader033.fdocuments.in/reader033/viewer/2022061507/56649eb05503460f94bb5f5a/html5/thumbnails/17.jpg)
17
H2S
6258.02500 S) Q]HFraction oleM( 4546.0[R
These are the Pasquill - Gifford Equations
The 500 ppm radius of exposure (in ft)
Determination of Radius of Exposure
R500= dist. from source where H2S conc. = 500 ppm
Q = source strength = open flow potential, SCFD
![Page 18: 1 PETE 411 Well Drilling Lesson 6 Drilling Structures.](https://reader033.fdocuments.in/reader033/viewer/2022061507/56649eb05503460f94bb5f5a/html5/thumbnails/18.jpg)
18
Example
A well that is about to be drilled is estimated to have an open flow potential of 5 million SCFD. Based on other wells in the field it is estimated that the H2S mole fraction in the gas mixture will be 0.1.
Calculate the radius of exposure to H2S concentrations of 500 ppm and 100 ppm.
![Page 19: 1 PETE 411 Well Drilling Lesson 6 Drilling Structures.](https://reader033.fdocuments.in/reader033/viewer/2022061507/56649eb05503460f94bb5f5a/html5/thumbnails/19.jpg)
19
Example
0.62582500 Q]S) ion HMole Fract( 4546.0[R
6258.06 )]10*5)(1.0(4546.0[
= 2,250 ft
![Page 20: 1 PETE 411 Well Drilling Lesson 6 Drilling Structures.](https://reader033.fdocuments.in/reader033/viewer/2022061507/56649eb05503460f94bb5f5a/html5/thumbnails/20.jpg)
20
Example
= 4,924 ft
6258.02100 ]Q)Sion HMole Fract( 589.1[R
6258.06 ]10*5)1.0(589.1[
ppm 500
100R500 R100
![Page 21: 1 PETE 411 Well Drilling Lesson 6 Drilling Structures.](https://reader033.fdocuments.in/reader033/viewer/2022061507/56649eb05503460f94bb5f5a/html5/thumbnails/21.jpg)
21
To Determine Q
Use open flow potential
Where insufficient data exist for calculating
R100 (100 ppm radius):
Assume R100= 3,000 ft
![Page 22: 1 PETE 411 Well Drilling Lesson 6 Drilling Structures.](https://reader033.fdocuments.in/reader033/viewer/2022061507/56649eb05503460f94bb5f5a/html5/thumbnails/22.jpg)
22
Storage Tanks for Production
If H2S conc. > 500 ppm
(i) Post warning sign within 50’ of facility
(ii) Fencing is required in populated area
![Page 23: 1 PETE 411 Well Drilling Lesson 6 Drilling Structures.](https://reader033.fdocuments.in/reader033/viewer/2022061507/56649eb05503460f94bb5f5a/html5/thumbnails/23.jpg)
23
Storage Tanks for Production
In general, If R500 > 50 ft:
(i) Post warning signs on access roads
(ii) Post marker signs at public crossing
e.g. Poison Gas and Caution
in Black and Yellow colors
![Page 24: 1 PETE 411 Well Drilling Lesson 6 Drilling Structures.](https://reader033.fdocuments.in/reader033/viewer/2022061507/56649eb05503460f94bb5f5a/html5/thumbnails/24.jpg)
24
Need Contingency Plan if:
(i) R100 > 50 ft
• and includes public area other than public road
100 ppm can cause throat irritation in < 1 hr
(ii) or R500 > 50 ft
• and includes public road 500 ppm can cause unconsciousness in < 2
min death in ~1/2 hr
(iii) or R100 > 3,000 ft
{600 ppm can cause death after a few minutes}
![Page 25: 1 PETE 411 Well Drilling Lesson 6 Drilling Structures.](https://reader033.fdocuments.in/reader033/viewer/2022061507/56649eb05503460f94bb5f5a/html5/thumbnails/25.jpg)
25
The Contingency Plan
Must provide for action of alerting and protecting the public following accidental release of a potentially hazardous volume of H2S.
Plan must include (names and) phone numbers of people to be notified…e.g.
• Supervisor • Hospital and Fire Dept./ Sheriff or Police• District Railroad Commission etc.• Local Residents
![Page 26: 1 PETE 411 Well Drilling Lesson 6 Drilling Structures.](https://reader033.fdocuments.in/reader033/viewer/2022061507/56649eb05503460f94bb5f5a/html5/thumbnails/26.jpg)
26
Drilling Provision:
,ft000,3R100 If we also need to:
(i) Maintain protective breathing equipment at the well site
(ii) Install and maintain automatic H2S detection and alarm equipment
(iii) Provide means for flaring the gas
![Page 27: 1 PETE 411 Well Drilling Lesson 6 Drilling Structures.](https://reader033.fdocuments.in/reader033/viewer/2022061507/56649eb05503460f94bb5f5a/html5/thumbnails/27.jpg)
27
Drilling Provision
(iv) Provide remote control of BOP and choke equipment - at safe distance
(v) DST of H2S zones only during daylight
(vi) Notify railroad commission prior to performing such DST
etc.
![Page 28: 1 PETE 411 Well Drilling Lesson 6 Drilling Structures.](https://reader033.fdocuments.in/reader033/viewer/2022061507/56649eb05503460f94bb5f5a/html5/thumbnails/28.jpg)
28
Certificate must be approved before commencing activities
ft000,3R If 100
• Provide training for personnel
• Submit certificate of compliance (with all the rules)
30 days prior to commencement of drilling or WO
![Page 29: 1 PETE 411 Well Drilling Lesson 6 Drilling Structures.](https://reader033.fdocuments.in/reader033/viewer/2022061507/56649eb05503460f94bb5f5a/html5/thumbnails/29.jpg)
29
Altered conditions may require submittal of amended certificate
Certificates are non-transferable
Completion reports for new wells must include the H2S conc. of the gas if in excess of 100 ppm
ft000,3R If 100
![Page 30: 1 PETE 411 Well Drilling Lesson 6 Drilling Structures.](https://reader033.fdocuments.in/reader033/viewer/2022061507/56649eb05503460f94bb5f5a/html5/thumbnails/30.jpg)
30
Buoyancy is the net effect of all the pressure forces acting on a submerged body.
The buoyancy force is equal to the weight of fluid displaced.
For example, a one-cubic-ft rock submerged in a tank containing water would experience a buoyancy force equal to the weight of 1 cu. ft of water, i.e., 62.4 lbf.
What is Buoyancy?
![Page 31: 1 PETE 411 Well Drilling Lesson 6 Drilling Structures.](https://reader033.fdocuments.in/reader033/viewer/2022061507/56649eb05503460f94bb5f5a/html5/thumbnails/31.jpg)
31
The End