MuTRG-FEE UpgradeStatus
RIKEN/RBRC
Itaru Nakagawa
![Page 2: 1 MuTRG-FEE Upgrade Status RIKEN/RBRC Itaru Nakagawa.](https://reader036.fdocuments.in/reader036/viewer/2022081519/56649f2c5503460f94c46eb5/html5/thumbnails/2.jpg)
2
Schedule
![Page 3: 1 MuTRG-FEE Upgrade Status RIKEN/RBRC Itaru Nakagawa.](https://reader036.fdocuments.in/reader036/viewer/2022081519/56649f2c5503460f94c46eb5/html5/thumbnails/3.jpg)
3
• Station-1 Scaffold Construction Completed
• Station-2 Scaffold underway.+2weeks?
• Cable trays are installed• Infrastructures
– Ran LV/Signal Cables• Oct-5,6,7,8
– Chassis Mount– Cooling Water
South Arm InstallationMuTRG-FEE Racks
![Page 4: 1 MuTRG-FEE Upgrade Status RIKEN/RBRC Itaru Nakagawa.](https://reader036.fdocuments.in/reader036/viewer/2022081519/56649f2c5503460f94c46eb5/html5/thumbnails/4.jpg)
4
New Cable Trays
![Page 5: 1 MuTRG-FEE Upgrade Status RIKEN/RBRC Itaru Nakagawa.](https://reader036.fdocuments.in/reader036/viewer/2022081519/56649f2c5503460f94c46eb5/html5/thumbnails/5.jpg)
5
Chassis & ADTX-FEE Cables• Completed Chassis test completed (Katsuro,
Ken’ichi, Yudai, Kazufumi, Murakami)– Water leak– Dry air blow – Backplane test (1 bad)– Conductivity test
• ADTX-FEE cable test completed (Katsuro, Kazufumi, Seiko, Yudai)
![Page 6: 1 MuTRG-FEE Upgrade Status RIKEN/RBRC Itaru Nakagawa.](https://reader036.fdocuments.in/reader036/viewer/2022081519/56649f2c5503460f94c46eb5/html5/thumbnails/6.jpg)
6
Chassis MountInstalled Before Run09
Newly Mounted
• St-1: Octant-1,2,3,4,5 Chassis are mounted.• St-2&3: Oct-1,8,7,6,5 Chassis are mounted.• Modified ground cables in St-2&3
Station-1 Station-2
![Page 7: 1 MuTRG-FEE Upgrade Status RIKEN/RBRC Itaru Nakagawa.](https://reader036.fdocuments.in/reader036/viewer/2022081519/56649f2c5503460f94c46eb5/html5/thumbnails/7.jpg)
7
Station-1 CablingRan St-1 LV&Fiber Cables
Yudai, Kazufumi, Seiko, Itaru
![Page 8: 1 MuTRG-FEE Upgrade Status RIKEN/RBRC Itaru Nakagawa.](https://reader036.fdocuments.in/reader036/viewer/2022081519/56649f2c5503460f94c46eb5/html5/thumbnails/8.jpg)
8
Trunk Cable Setup at Rackroom
•Patch Bay Labeling and install•Trunk cable connection at back•Cable guide mount for trunk cables
![Page 9: 1 MuTRG-FEE Upgrade Status RIKEN/RBRC Itaru Nakagawa.](https://reader036.fdocuments.in/reader036/viewer/2022081519/56649f2c5503460f94c46eb5/html5/thumbnails/9.jpg)
9
Board QA
•Setup ready : Ken’ichi•Actually QA proceed byYudai and Seiko