1 jkf - Actiflow · 2019. 9. 10. · •xb 1 jkf Airflow simulations of the OR - design principles...
Transcript of 1 jkf - Actiflow · 2019. 9. 10. · •xb 1 jkf Airflow simulations of the OR - design principles...
-
• xb
jkf1
Airflow simulations of the OR - design principles and fairytales NVMM symposium, 28-03-2018
ir. M.G.M. (Mike) van der HeijdenTel: +31 (0)76 542 2220©2018 Actiflow BV
-
Disclosure of speaker’s interests
(Potential) conflict of interest None / see below
Potentially relevant company relationships in
connection with event Actiflow BV
Sponserships None
Fee or other (financial) payment Actiflow BV
Shareholder None
Other relationship, i.e. None
-
Table of Contents
1) Introduction Actiflow
2) Scope & Objective
3) Design & Assessment methods
a) Design methods
b) VCCN RL7 & WIP guideline
c) Summary of methods
4) CFD Simulations
5) Simulation resultsa) Impact of ‘at rest’ vs ‘in operation’
b) Role for CFD in selection of systems & design changes?
6) General remarks and conclusions
-
Table of Contents
1) Introduction Actiflow
2) Scope & Objective
3) Design & Assessment methods
a) Design methods
b) VCCN RL7 & WIP guideline
c) Summary of methods
4) CFD Simulations
5) Simulation resultsa) Impact of ‘at rest’ vs ‘in operation’
b) Role for CFD in selection of systems & design changes?
6) General remarks and conclusions
-
Introduction Actiflow1
-
Table of Contents
1) Introduction Actiflow
2) Scope & Objective
3) Design & Assessment methods
a) Design methods
b) VCCN RL7 & WIP guideline
c) Summary of methods
4) CFD Simulations
5) Simulation resultsa) Impact of ‘at rest’ vs ‘in operation’
b) Role for CFD in selection of systems & design changes?
6) General remarks and conclusions
-
The design process of an operating theatre is mainly based on simplified design principles and in situ (‘at rest’) cleanliness measurements after completion. This presentation will focus on general airflow patterns and cleanliness ‘at operation’.
Scope & Objective2
Factors that influence cleanliness:- Location of OR table;- Location of surgical team;- Temperature of supplied clean air;- Type & shape of surgical light;- Location of surgical light;- Amount of people in OR;- Clothing system of surgical team;- Cleanliness path towards OR;- Cleaning of the OR;- Cleanroom protocols & procedures;- Gowning procedures;- Opening of doors; - Location of instrumentals and tables;- Maintenance of HVAC system;- Financial pressure- …
Postoperativeinfection
Air based contamination
CFUs in air
Direct to woundTo instrument-table
Source: Original image of P. van den Broek
-
The design process of an operating theatre is mainly based on simplified design principles and in situ (‘at rest’) cleanliness measurements after completion. This presentation will focus on general airflow patterns and cleanliness ‘at operation’.
Scope & Objective2
Postoperativeinfection
Air based contamination
CFUs in air
Direct to woundTo instrument-table
Scope of this presentationFactors that influence cleanliness:- Location of OR table;- Location of surgical team;- Temperature of supplied clean air;- Type & shape of surgical light;- Location of surgical light;- Amount of people in OR;- Clothing system of surgical team;- Cleanliness path towards OR;- Cleaning of the OR;- Cleanroom protocols & procedures;- Gowning procedures;- Opening of doors; - Location of instrumentals and tables;- Maintenance of HVAC system;- Financial pressure- … Source: Original image of P. van den Broek
-
The design process of an operating theatre is mainly based on simplified design principles and in situ (‘at rest’) cleanliness measurements after completion. This presentation will focus on general airflow patterns and cleanliness ‘at operation’.
Scope & Objective2
Postoperativeinfection
Air based contamination
CFUs in air
Direct to woundTo instrument-table
Scope of this presentationObjective with regard to airflow:- Identification of current OR design principles;- Assessment method of a OR when built;- Show difference in flow patterns with ‘at rest’ vs ‘in
operation’ conditions;- Show potential for CFD when selecting
different systems;
Source: Original image of P. van den Broek
-
Table of Contents
1) Introduction Actiflow
2) Scope & Objective
3) Design & Assessment methods
a) Design methods
b) VCCN RL7 & WIP guideline
c) Summary of methods
4) CFD Simulations
5) Simulation resultsa) Impact of ‘at rest’ vs ‘in operation’
b) Role for CFD in selection of systems & design changes?
6) General remarks and conclusions
-
Design & Assessment methods3
A very basic calculation method focusses on the people as the main contamination source, were under fully mixed conditions the steady state average CFU concentration can be estimated (max of 10 CFU/m3).
C [CFU/m3] n ∙ p [CFU/s] ɸ [m3/s]
2.96 2 ∙ 3⅓ 0.25 ms-1 x 9m2
5.92 4 ∙ 3⅓ 0.25 ms-1 x 9m2
8.89 6 ∙ 3⅓ 0.25 ms-1 x 9m2
11.85 8 ∙ 3⅓ 0.25 ms-1 x 9m2
-
Design & Assessment methods3
C [CFU/m3] n ∙ p [CFU/s] ɸ [m3/s]
2.96 2 ∙ 3⅓ 0.25 ms-1 x 9m2
5.92 4 ∙ 3⅓ 0.25 ms-1 x 9m2
8.89 6 ∙ 3⅓ 0.25 ms-1 x 9m2
11.85 8 ∙ 3⅓ 0.25 ms-1 x 9m2
A very basic calculation method focusses on the people as the main contamination source, were under fully mixed conditions the steady state average CFU concentration can be estimated (max of 10 CFU/m3).
-
Table of Contents
1) Introduction Actiflow
2) Scope & Objective
3) Design & Assessment methods
a) Design methods
b) VCCN RL7 & WIP guideline
c) Summary of methods
4) CFD Simulations
5) Simulation resultsa) Impact of ‘at rest’ vs ‘in operation’
b) Role for CFD in selection of systems & design changes?
6) General remarks and conclusions
-
A gentle reminder of the Dutch method for testing and classification of operating theatres (with performance level 1):
- Objective A, protection for contamination from periphery;
- Objective B, quick recovery ;
- Testing and classification ‘at rest’;
- Highly recommended to take OR lights into account;
- Bases of code is in line with codes from Germany, UK, Sweden,
3
(not necessary in original version 2014, now recommended, likely mandatory
in next revision in 2019)
(fixed equipment present without taking into account persons and non-fixed
medical equipment. Including the latter would be testing ‘in operation’)
(ISO 5 in protected area, ISO 7 in periphery, protected area level 2 to 3, meaning
that cleanliness of protected area is a factor 100 to 1.000 of periphery (logarithmic)
(In case of a contamination in the protected area dilution of by a factor 100 should
occur within 3 minutes)
(differences do exist e.g. in recommended ISO levels for mixing systems ‘at
rest’, also additional requirements on minimal air change rates may be present)
France, Switzerland for UDF systems;
Dutch WIP & VCCN RL7 guidelines (after completion of OR)
-
A gentle reminder of the Dutch method for testing and classification of operating theatres (with performance level 1):
- Objective A, protection for contamination from periphery;
- Objective B, quick recovery ;
- Testing and classification ‘at rest’;
- Highly recommended to take OR lights into account;
- Bases of code is in line with codes from Germany, UK, Sweden,
3
(not necessary in original version 2014, now recommended, likely mandatory
in next revision in 2019)
(fixed equipment present without taking into account persons and non-fixed
medical equipment. Including the latter would be testing ‘in operation’)
(ISO 5 in protected area, ISO 7 in periphery, protected area level 2 to 3, meaning
that cleanliness of protected area is a factor 100 to 1.000 of periphery (logarithmic)
(In case of a contamination in the protected area dilution of by a factor 100 should
occur within 3 minutes)
(differences do exist e.g. in recommended ISO levels for mixing systems ‘at
rest’, also additional requirements on minimal air change rates may be present)
France, Switzerland for UDF systems;
BGx = Protection level at location x [-]Cx = Particle concentration at x [#/m
3]Cref = Concentration in periphery [#/m
3]
source: RL7 VCCN 2017
Dutch WIP & VCCN RL7 guidelines (after completion of OR)
-
A gentle reminder of the Dutch method for testing and classification of operating theatres (with performance level 1):
- Objective A, protection for contamination from periphery;
- Objective B, quick recovery ;
- Testing and classification ‘at rest’;
- Highly recommended to take OR lights into account;
- Bases of code is in line with codes from Germany, UK, Sweden,
3
(not necessary in original version 2014, now recommended, likely mandatory
in next revision in 2019)
(fixed equipment present without taking into account persons and non-fixed
medical equipment. Including the latter would be testing ‘in operation’)
(ISO 5 in protected area, ISO 7 in periphery, protected area level 2 to 3, meaning
that cleanliness of protected area is a factor 100 to 1.000 of periphery (logarithmic)
(In case of a contamination in the protected area dilution of by a factor 100 should
occur within 3 minutes)
(differences do exist e.g. in recommended ISO levels for mixing systems ‘at
rest’, also additional requirements on minimal air change rates may be present)
France, Switzerland for UDF systems;
BGx = Protection level at location x [-]Cx = Particle concentration at x [#/m
3]Cref = Concentration in periphery [#/m
3]
source: RL7 VCCN 2017
t0,01 = recovery time [min]t100n = time for recovery factor 100 [min]tn = start time for recovery [min]
source: RL7 VCCN 2017
emission
Measurement 1:100
Dutch WIP & VCCN RL7 guidelines (after completion of OR)
-
A gentle reminder of the Dutch method for testing and classification of operating theatres (with performance level 1):
- Objective A, protection for contamination from periphery;
- Objective B, quick recovery ;
- Testing and classification ‘at rest’;
- Highly recommended to take OR lights into account;
- Bases of code is in line with codes from Germany, UK, Sweden,
3
(not necessary in original version 2014, now recommended, likely mandatory
in next revision in 2019)
(fixed equipment present without taking into account persons and non-fixed
medical equipment. Including the latter would be testing ‘in operation’)
(ISO 5 in protected area, ISO 7 in periphery, protected area level 2 to 3, meaning
that cleanliness of protected area is a factor 100 to 1.000 of periphery (logarithmic)
France, Switzerland for UDF systems;
‘Open’-variant ‘Closed’-variant ‘Semi open’-variant
(differences do exist e.g. in recommended ISO levels for mixing systems ‘at
rest’, also additional requirements on minimal air change rates may be present)
(In case of a contamination in the protected area dilution of by a factor 100 should
occur within 3 minutes)
Dutch WIP & VCCN RL7 guidelines (after completion of OR)
-
A gentle reminder of the Dutch method for testing and classification of operating theatres (with performance level 1):
- Objective A, protection for contamination from periphery;
- Objective B, quick recovery ;
- Testing and classification ‘at rest’;
- Highly recommended to take OR lights into account;
- Bases of code is in line with codes from Germany, UK, Sweden,
3
(not necessary in original version 2014, now recommended, likely mandatory
in next revision in 2019)
(fixed equipment present without taking into account persons and non-fixed
medical equipment. Including the latter would be testing ‘in operation’)
(ISO 5 in protected area, ISO 7 in periphery, protected area level 2 to 3, meaning
that cleanliness of protected area is a factor 100 to 1.000 of periphery (logarithmic)
France, Switzerland for UDF systems;
‘Open’-variant ‘Closed’-variant ‘Semi open’-variant
(differences do exist e.g. in recommended ISO levels for mixing systems ‘at
rest’, also additional requirements on minimal air change rates may be present)
(In case of a contamination in the protected area dilution of by a factor 100 should
occur within 3 minutes)
Dutch WIP & VCCN RL7 guidelines (after completion of OR)
-
A gentle reminder of the Dutch method for testing and classification of operating theatres (with performance level 1):
- Objective A, protection for contamination from periphery;
- Objective B, quick recovery ;
- Testing and classification ‘at rest’;
- Highly recommended to take OR lights into account;
- Bases of code is in line with codes from Germany, UK, Sweden,
3
(not necessary in original version 2014, now recommended, likely mandatory
in next revision in 2019)
(fixed equipment present without taking into account persons and non-fixed
medical equipment. Including the latter would be testing ‘in operation’)
(ISO 5 in protected area, ISO 7 in periphery, protected area level 2 to 3, meaning
that cleanliness of protected area is a factor 100 to 1.000 of periphery (logarithmic)
France, Switzerland for UDF systems; (differences do exist e.g. in recommended ISO levels for mixing systems ‘at
rest’, also additional requirements on minimal air change rates may be present)
(In case of a contamination in the protected area dilution of by a factor 100 should
occur within 3 minutes)
van der Heijden et al. (2009)
Dutch WIP & VCCN RL7 guidelines (after completion of OR)
-
A gentle reminder of the Dutch method for testing and classification of operating theatres (with performance level 1):
- Objective A, protection for contamination from periphery;
- Objective B, quick recovery ;
- Testing and classification ‘at rest’;
- Highly recommended to take OR lights into account;
- Bases of code is in line with codes from Germany, UK, Sweden,
3
(not necessary in original version 2014, now recommended, likely mandatory
in next revision in 2019)
(fixed equipment present without taking into account persons and non-fixed
medical equipment. Including the latter would be testing ‘in operation’)
(ISO 5 in protected area, ISO 7 in periphery, protected area level 2 to 3, meaning
that cleanliness of protected area is a factor 100 to 1.000 of periphery (logarithmic)
France, Switzerland for UDF systems; (differences do exist e.g. in recommended ISO levels for mixing systems ‘at
rest’, also additional requirements on minimal air change rates may be present) van der Heijden et al. (2009)
(In case of a contamination in the protected area dilution of by a factor 100 should
occur within 3 minutes)
Dutch WIP & VCCN RL7 guidelines (after completion of OR)
-
A gentle reminder of the Dutch method for testing and classification of operating theatres (with performance level 1):
- Objective A, protection for contamination from periphery;
- Objective B, quick recovery ;
- Testing and classification ‘at rest’;
- Highly recommended to take OR lights into account;
- Bases of code is in line with codes from Germany, UK, Sweden,
3
(not necessary in original version 2014, now recommended, likely mandatory
in next revision in 2019)
(fixed equipment present without taking into account persons and non-fixed
medical equipment. Including the latter would be testing ‘in operation’)
(ISO 5 in protected area, ISO 7 in periphery, protected area level 2 to 3, meaning
that cleanliness of protected area is a factor 100 to 1.000 of periphery (logarithmic)
France, Switzerland for UDF systems; (differences do exist e.g. in recommended ISO levels for mixing systems ‘at
rest’, also additional requirements on minimal air change rates may be present)
van der Heijden et al. (2009)
(In case of a contamination in the protected area dilution of by a factor 100 should
occur within 3 minutes)
Dutch WIP & VCCN RL7 guidelines (after completion of OR)
-
A gentle reminder of the Dutch method for testing and classification of operating theatres (with performance level 1):
- Objective A, protection for contamination from periphery;
- Objective B, quick recovery ;
- Testing and classification ‘at rest’;
- Highly recommended to take OR lights into account;
- Bases of code is in line with codes from Germany, UK, Sweden,
3
(not necessary in original version 2014, now recommended, likely mandatory
in next revision in 2019)
(fixed equipment present without taking into account persons and non-fixed
medical equipment. Including the latter would be testing ‘in operation’)
(ISO 5 in protected area, ISO 7 in periphery, protected area level 2 to 3, meaning
that cleanliness of protected area is a factor 100 to 1.000 of periphery (logarithmic)
France, Switzerland for UDF systems; (differences do exist e.g. in recommended ISO levels for mixing systems ‘at
rest’, also additional requirements on minimal air change rates may be present)
van der Heijden et al. (2009)
(In case of a contamination in the protected area dilution of by a factor 100 should
occur within 3 minutes)
Dutch WIP & VCCN RL7 guidelines (after completion of OR)
-
A gentle reminder of the Dutch method for testing and classification of operating theatres (with performance level 1):
- Objective A, protection for contamination from periphery;
- Objective B, quick recovery ;
- Testing and classification ‘at rest’;
- Highly recommended to take OR lights into account;
- Bases of code is in line with codes from Germany, UK, Sweden,
3
(not necessary in original version 2014, now recommended, likely mandatory
in next revision in 2019)
(fixed equipment present without taking into account persons and non-fixed
medical equipment. Including the latter would be testing ‘in operation’)
(ISO 5 in protected area, ISO 7 in periphery, protected area level 2 to 3, meaning
that cleanliness of protected area is a factor 100 to 1.000 of periphery (logarithmic)
France, Switzerland for UDF systems; (differences do exist e.g. in recommended ISO levels for mixing systems ‘at
rest’, also additional requirements on minimal air change rates may be present)
van der Heijden et al. (2009)
(In case of a contamination in the protected area dilution of by a factor 100 should
occur within 3 minutes)
Dutch WIP & VCCN RL7 guidelines (after completion of OR)
-
A gentle reminder of the Dutch method for testing and classification of operating theatres (with performance level 1):
- Objective A, protection for contamination from periphery;
- Objective B, quick recovery ;
- Testing and classification ‘at rest’;
- Highly recommended to take OR lights into account;
- Bases of code is in line with codes from Germany, UK, Sweden,
3
(not necessary in original version 2014, now recommended, likely mandatory
in next revision in 2019)
(fixed equipment present without taking into account persons and non-fixed
medical equipment. Including the latter would be testing ‘in operation’)
(ISO 5 in protected area, ISO 7 in periphery, protected area level 2 to 3, meaning
that cleanliness of protected area is a factor 100 to 1.000 of periphery (logarithmic)
France, Switzerland for UDF systems; (differences do exist e.g. in recommended ISO levels for mixing systems ‘at
rest’, also additional requirements on minimal air change rates may be present)
van der Heijden et al. (2009)
(In case of a contamination in the protected area dilution of by a factor 100 should
occur within 3 minutes)
Dutch WIP & VCCN RL7 guidelines (after completion of OR)
-
A gentle reminder of the Dutch method for testing and classification of operating theatres (with performance level 1):
- Objective A, protection for contamination from periphery;
- Objective B, quick recovery ;
- Testing and classification ‘at rest’;
- Highly recommended to take OR lights into account;
- Bases of code is in line with codes from Germany, UK, Sweden,
3
(not necessary in original version 2014, now recommended, likely mandatory
in next revision in 2019)
(fixed equipment present without taking into account persons and non-fixed
medical equipment. Including the latter would be testing ‘in operation’)
(ISO 5 in protected area, ISO 7 in periphery, protected area level 2 to 3, meaning
that cleanliness of protected area is a factor 100 to 1.000 of periphery (logarithmic)
France, Switzerland for UDF systems; (differences do exist e.g. in recommended ISO levels for mixing systems ‘at
rest’, also additional requirements on minimal air change rates may be present)
(In case of a contamination in the protected area dilution of by a factor 100 should
occur within 3 minutes)
Dutch WIP & VCCN RL7 guidelines (after completion of OR)
-
A gentle reminder of the Dutch method for testing and classification of operating theatres (with performance level 1):
- Objective A, protection for contamination from periphery;
- Objective B, quick recovery ;
- Testing and classification ‘at rest’;
- Highly recommended to take OR lights into account;
- Bases of code is in line with codes from Germany, UK, Sweden,
3
(not necessary in original version 2014, now recommended, likely mandatory
in next revision in 2019)
(fixed equipment present without taking into account persons and non-fixed
medical equipment. Including the latter would be testing ‘in operation’)
(ISO 5 in protected area, ISO 7 in periphery, protected area level 2 to 3, meaning
that cleanliness of protected area is a factor 100 to 1.000 of periphery (logarithmic)
France, Switzerland for UDF systems; (differences do exist e.g. in recommended ISO levels for mixing systems ‘at
rest’, also additional requirements on minimal air change rates may be present)
(In case of a contamination in the protected area dilution of by a factor 100 should
occur within 3 minutes)
Dutch WIP & VCCN RL7 guidelines (after completion of OR)
-
Summary of methods3
There is a substantial difference between design calculations and the quality assessment measurement when built.
Differences exist in for instance:
a) Design calculation ‘in operation’;b) Assessment when built ‘at rest’;
a) Design calculation PI = CFU concentration;b) Assessment PI = protected area or recovery time;
a) Design calculation airflow patterns not taken into account;b) Assessment specific airflow is taken into account;
-
Summary of methods3
There is a substantial difference between design calculations and the quality assessment measurement when built.
Differences exist in for instance:
a) Design calculation ‘in operation’;b) Assessment when built ‘at rest’;
a) Design calculation PI = CFU concentration;b) Assessment PI = protected area or recovery time;
a) Design calculation airflow patterns not taken into account;b) Assessment specific airflow is taken into account;
-
Table of Contents
1) Introduction Actiflow
2) Scope & Objective
3) Design & Assessment methods
a) Design methods
b) VCCN RL7 & WIP guideline
c) Summary of methods
4) CFD Simulations
5) Simulation resultsa) Impact of ‘at rest’ vs ‘in operation’
b) Role for CFD in selection of systems & design changes?
6) General remarks and conclusions
-
From the information provided up to this point it has become clear that there might be a need for a design- and assessment method which are more coherent to each other. In order to show the impact of ‘at rest’ vs ‘in operation’ conditions Computational Fluid Dynamics (CFD) is used to assess the protected area under different conditions.
CFD simulations4
Reference case- Dimensions 7.5m x 7.5m x 2.8m;- Plenum 3m x 3m;- 8 returns in walls;- 5 people + patient;- Plenum inlet velocity 0.25 m/s;- Localized heatload per persons (Sens 80W);- Heatload of Lights (100W per light)- Operating table with patient;- Instrument tables (4x);
Simulation settings- Number of cells 4.066.941 [-];- OpenFOAM solver (buoyantBoussinesq)- Mesh made with ANSA- 5 prims layers (y+ checked)- Non orthogonality mesh check and quality control
7.5m
7.5m
2.8m
ɸ [m3/s]
-
From the information provided up to this point it has become clear that there might be a need for a design- and assessment method which are more coherent to each other. In order to show the impact of ‘at rest’ vs ‘in operation’ conditions Computational Fluid Dynamics (CFD) is used to assess the protected area under different conditions.
CFD simulations4
Reference case- Dimensions 7.5m x 7.5m x 2.8m;- Plenum 3m x 3m;- 8 returns in walls;- 5 people + patient;- Plenum inlet velocity 0.25 m/s;- Localized heatload per persons (Sens 80W);- Heatload of Lights (100W per light)- Operating table with patient;- Instrument tables (4x);
Simulation settings- Number of cells 4.066.941 [-];- OpenFOAM solver (buoyantBoussinesq)- Mesh made with ANSA- 5 prims layers (y+ checked)- Non orthogonality mesh check and quality control
-
From the information provided up to this point it has become clear that there might be a need for a design- and assessment method which are more coherent to each other. In order to show the impact of ‘at rest’ vs ‘in operation’ conditions Computational Fluid Dynamics (CFD) is used to assess the protected area under different conditions.
CFD simulations4
Reference case- Dimensions 7.5m x 7.5m x 2.8m;- Plenum 3m x 3m;- 8 returns in walls;- 5 people + patient;- Plenum inlet velocity 0.25 m/s;- Localized heatload per persons (Sens 80W);- Heatload of Lights (100W per light)- Operating table with patient;- Instrument tables (4x);
Simulation settings- Number of cells 4.066.941 [-];- OpenFOAM solver (buoyantBoussinesq)- Mesh made with ANSA- 5 prims layers (y+ checked)- Non orthogonality mesh check and quality control
-
From the information provided up to this point it has become clear that there might be a need for a design- and assessment method which are more coherent to each other. In order to show the impact of ‘at rest’ vs ‘in operation’ conditions Computational Fluid Dynamics (CFD) is used to assess the protected area under different conditions.
CFD simulations4
Reference case- Dimensions 7.5m x 7.5m x 2.8m;- Plenum 3m x 3m;- 8 returns in walls;- 5 people + patient;- Plenum inlet velocity 0.25 m/s;- Localized heatload per persons (Sens 80W);- Heatload of Lights (100W per light)- Operating table with patient;- Instrument tables (4x);
Simulation settings- Number of cells 4.066.941 [-];- OpenFOAM solver (buoyantBoussinesq)- Mesh made with ANSA- 5 prims layers (y+ checked)- Non orthogonality mesh check and quality control
-
From the information provided up to this point it has become clear that there might be a need for a design- and assessment method which are more coherent to each other. In order to show the impact of ‘at rest’ vs ‘in operation’ conditions Computational Fluid Dynamics (CFD) is used to assess the protected area under different conditions.
CFD simulations4
Reference case- Dimensions 7.5m x 7.5m x 2.8m;- Plenum 3m x 3m;- 8 returns in walls;- 5 people + patient;- Plenum inlet velocity 0.25 m/s;- Localized heatload per persons (Sens 80W);- Heatload of Lights (100W per light)- Operating table with patient;- Instrument tables (4x);
Simulation settings- Number of cells 4.066.941 [-];- OpenFOAM solver (buoyantBoussinesq)- Mesh made with ANSA- 5 prims layers (y+ checked)- Non orthogonality mesh check and quality control
-
CFD simulations4
From the information provided up to thispoint it has become clear that there mightbe a need for a design- and assessmentmethod which are more coherent to eachother. In order to show the impact of ‘atrest’ vs ‘in operation’ conditionsComputational Fluid Dynamics (CFD) isused to assess the protected area underdifferent conditions.
-
CFD simulations4
From the information provided up to thispoint it has become clear that there mightbe a need for a design- and assessmentmethod which are more coherent to eachother. In order to show the impact of ‘atrest’ vs ‘in operation’ conditionsComputational Fluid Dynamics (CFD) isused to assess the protected area underdifferent conditions.
-
CFD simulations4
From the information provided up to thispoint it has become clear that there mightbe a need for a design- and assessmentmethod which are more coherent to eachother. In order to show the impact of ‘atrest’ vs ‘in operation’ conditionsComputational Fluid Dynamics (CFD) isused to assess the protected area underdifferent conditions.
-
In order to visualize the impact of equipment and persons on the airflow patterns in an operating theatre, the following situations are addressed by computational fluid dynamics.
First session:
- Situation A = airflow patterns with only patient in OR;
- Situation B = situation A + heatload;
- Situation C = situation B + surgeon;
- Situation D = situation C + instrumentalist;
- Situation E = situation D + OR Lights;
- Situation F = situation D + two persons;
- Situation G = situation F + 4 x tables and anaesthetist
Second session:
- Impact of shape OR lights;
- Impact of location OR lights;
- Type of system;
Outline of simulations4
-
In order to visualize the impact of equipment and persons on the airflow patterns in an operating theatre, the following situations are addressed by computational fluid dynamics.
First session:
- Situation A = airflow patterns with only patient in OR;
- Situation B = situation A + heatload;
- Situation C = situation B + surgeon;
- Situation D = situation C + instrumentalist;
- Situation E = situation D + OR Lights;
- Situation F = situation D + two persons;
- Situation G = situation F + 4 x tables and anaesthetist
Second session:
- Impact of shape OR lights;
- Impact of location OR lights;
- Type of system;
Outline of simulations4
-
In order to visualize the impact of equipment and persons on the airflow patterns in an operating theatre, the following situations are addressed by computational fluid dynamics.
First session:
- Situation A = airflow patterns with only patient in OR;
- Situation B = situation A + heatload;
- Situation C = situation B + surgeon;
- Situation D = situation C + instrumentalist;
- Situation E = situation D + OR Lights;
- Situation F = situation D + two persons;
- Situation G = situation F + 4 x tables and anaesthetist
Second session:
- Impact of shape OR lights;
- Impact of location OR lights;
- Type of system;
Outline of simulations4
-
In order to visualize the impact of equipment and persons on the airflow patterns in an operating theatre, the following situations are addressed by computational fluid dynamics.
First session:
- Situation A = airflow patterns with only patient in OR;
- Situation B = situation A + heatload;
- Situation C = situation B + surgeon;
- Situation D = situation C + instrumentalist;
- Situation E = situation D + OR Lights;
- Situation F = situation D + two persons;
- Situation G = situation F + 4 x tables and anaesthetist
Second session:
- Impact of shape OR lights;
- Impact of location OR lights;
- Type of system;
Outline of simulations4
-
In order to visualize the impact of equipment and persons on the airflow patterns in an operating theatre, the following situations are addressed by computational fluid dynamics.
First session:
- Situation A = airflow patterns with only patient in OR;
- Situation B = situation A + heatload;
- Situation C = situation B + surgeon;
- Situation D = situation C + instrumentalist;
- Situation E = situation D + OR Lights;
- Situation F = situation D + two persons;
- Situation G = situation F + 4 x tables and anaesthetist
Second session:
- Impact of shape OR lights;
- Impact of location OR lights;
- Type of system;
Outline of simulations4
-
In order to visualize the impact of equipment and persons on the airflow patterns in an operating theatre, the following situations are addressed by computational fluid dynamics.
First session:
- Situation A = airflow patterns with only patient in OR;
- Situation B = situation A + heatload;
- Situation C = situation B + surgeon;
- Situation D = situation C + instrumentalist;
- Situation E = situation D + OR Lights;
- Situation F = situation D + two persons;
- Situation G = situation F + 4 x tables and anaesthetist
Second session:
- Impact of shape OR lights;
- Impact of location OR lights;
- Type of system;
Outline of simulations4
-
In order to visualize the impact of equipment and persons on the airflow patterns in an operating theatre, the following situations are addressed by computational fluid dynamics.
First session:
- Situation A = airflow patterns with only patient in OR;
- Situation B = situation A + heatload;
- Situation C = situation B + surgeon;
- Situation D = situation C + instrumentalist;
- Situation E = situation D + OR Lights;
- Situation F = situation D + two persons;
- Situation G = situation F + 4 x tables and anaesthetist
Second session:
- Impact of shape OR lights;
- Impact of location OR lights;
- Type of system;
Outline of simulations4
-
In order to visualize the impact of equipment and persons on the airflow patterns in an operating theatre, the following situations are addressed by computational fluid dynamics.
First session:
- Situation A = airflow patterns with only patient in OR;
- Situation B = situation A + heatload;
- Situation C = situation B + surgeon;
- Situation D = situation C + instrumentalist;
- Situation E = situation D + OR Lights;
- Situation F = situation D + two persons;
- Situation G = situation F + 4 x tables and anaesthetist
Second session:
- Impact of shape OR lights;
- Impact of location OR lights;
- Type of system;
Outline of simulations4
-
In order to visualize the impact of equipment and persons on the airflow patterns in an operating theatre, the following situations are addressed by computational fluid dynamics.
First session:
- Situation A = airflow patterns with only patient in OR;
- Situation B = situation A + heatload;
- Situation C = situation B + surgeon;
- Situation D = situation C + instrumentalist;
- Situation E = situation D + OR Lights;
- Situation F = situation D + two persons;
- Situation G = situation F + 4 x tables and anaesthetist
Second session:
- Impact of shape OR lights;
- Impact of location OR lights;
- Type of system;
Outline of simulations4
-
In order to visualize the impact of equipment and persons on the airflow patterns in an operating theatre, the following situations are addressed by computational fluid dynamics.
First session:
- Situation A = airflow patterns with only patient in OR;
- Situation B = situation A + heatload;
- Situation C = situation B + surgeon;
- Situation D = situation C + instrumentalist;
- Situation E = situation D + OR Lights;
- Situation F = situation D + two persons;
- Situation G = situation F + 4 x tables and anaesthetist
Second session:
- Impact of shape OR lights;
- Impact of location OR lights;
- Type of system;
Outline of simulations4
-
In order to visualize the impact of equipment and persons on the airflow patterns in an operating theatre, the following situations are addressed by computational fluid dynamics.
First session:
- Situation A = airflow patterns with only patient in OR;
- Situation B = situation A + heatload;
- Situation C = situation B + surgeon;
- Situation D = situation C + instrumentalist;
- Situation E = situation D + OR Lights;
- Situation F = situation D + two persons;
- Situation G = situation F + 4 x tables and anaesthetist
Second session:
- Impact of shape OR lights;
- Impact of location OR lights;
- Type of system;
Outline of simulations4
-
In order to visualize the impact of equipment and persons on the airflow patterns in an operating theatre, the following situations are addressed by computational fluid dynamics.
First session:
- Situation A = airflow patterns with only patient in OR;
- Situation B = situation A + heatload;
- Situation C = situation B + surgeon;
- Situation D = situation C + instrumentalist;
- Situation E = situation D + OR Lights;
- Situation F = situation D + two persons;
- Situation G = situation F + 4 x tables and anaesthetist
Second session:
- Impact of shape OR lights;
- Impact of location OR lights;
- Type of system;
Outline of simulations4
-
In order to visualize the impact of equipment and persons on the airflow patterns in an operating theatre, the following situations are addressed by computational fluid dynamics.
First session:
- Situation A = airflow patterns with only patient in OR;
- Situation B = situation A + heatload;
- Situation C = situation B + surgeon;
- Situation D = situation C + instrumentalist;
- Situation E = situation D + OR Lights;
- Situation F = situation D + two persons;
- Situation G = situation F + 4 x tables and anaesthetist
Second session:
- Impact of shape OR lights;
- Impact of location OR lights;
- Type of system;
Outline of simulations4
-
Table of Contents
1) Introduction Actiflow
2) Scope & Objective
3) Design & Assessment methods
a) Design methods
b) VCCN RL7 & WIP guideline
c) Summary of methods
4) CFD Simulations
5) Simulation resultsa) Impact of ‘at rest’ vs ‘in operation’
b) Role for CFD in selection of system & changes?
6) General remarks and conclusions
-
Results - ‘at rest’ vs ‘in operation’5Included in model:
- UDF Plenum;
- Eight returns;
- Patient without heat-source;
-
Included in model:
- UDF Plenum;
- Eight returns;
- Patient without heat-source;
Results - ‘at rest’ vs ‘in operation’5
-
Included in model:
- UDF Plenum;
- Eight returns;
- Patient with heat-source;
Results - ‘at rest’ vs ‘in operation’5
-
Included in model:
- UDF Plenum;
- Eight returns;
- Patient with heat-source;
- Surgeon with heat-source;
Results - ‘at rest’ vs ‘in operation’5
-
Included in model:
- UDF Plenum;
- Eight returns;
- Patient with heat-source;
- Two surgeons with heat-source;
Results - ‘at rest’ vs ‘in operation’5
-
Included in model:
- UDF Plenum;
- Eight returns;
- Patient with heat-source;
- Two surgeons with heat-source;- Two Lights (RL7 position);
Results - ‘at rest’ vs ‘in operation’5
-
Included in model:
- UDF Plenum;
- Eight returns;
- Patient with heat-source;
- Four surgeons with heat-source;- Two lights (RL7 position);
Results - ‘at rest’ vs ‘in operation’5
-
Included in model:
- UDF Plenum;
- Eight returns;
- Patient with heat-source;
- Four surgeons with heat-source;- Two lights with heat-source (RL7 position);
- Anaesthetist with heat-source;
- Instrument tables (4x)
Results - ‘at rest’ vs ‘in operation’5
-
Included in model:
- UDF Plenum;
- Eight returns;
- Patient without heat-source;
--
-
-
Results - ‘at rest’ vs ‘in operation’5
-
Included in model:
- UDF Plenum;
- Eight returns;
- Patient without heat-source;
--
-
-
Results - ‘at rest’ vs ‘in operation’5
1:100 periphery concentration
-
Included in model:
- UDF Plenum;
- Eight returns;
- Patient with heat-source;
--
-
-
Results - ‘at rest’ vs ‘in operation’5
-
Included in model:
- UDF Plenum;
- Eight returns;
- Patient with heat-source;
- One surgeon with heat-source;-
-
-
Results - ‘at rest’ vs ‘in operation’5
-
Included in model:
- UDF Plenum;
- Eight returns;
- Patient with heat-source;
- Two surgeons with heat-source;-
-
-
Results - ‘at rest’ vs ‘in operation’5
-
Included in model:
- UDF Plenum;
- Eight returns;
- Patient with heat-source;
- Two surgeons with heat-source;- Two lights (RL7 position);
-
-
Results - ‘at rest’ vs ‘in operation’5
-
Included in model:
- UDF Plenum;
- Eight returns;
- Patient with heat-source;
- Four surgeons with heat-source;- Two lights with heat-source (RL7 position);
-
-
Results - ‘at rest’ vs ‘in operation’5
-
Included in model:
- UDF Plenum;
- Eight returns;
- Patient with heat-source;
- Four surgeons with heat-source;- Two lights with heat-source (RL7 position);
- Anaesthetist with heat-source;
- Instrument tables (4x)
Results - ‘at rest’ vs ‘in operation’5
-
Results - ‘at rest’ vs ‘in operation’5Included in model:
- UDF Plenum;
- Eight returns;
- Patient with heat-source;
- Four surgeons with heat-source;- Two lights with heat-source (RL7
position);
- Anaesthetist with heat-source;- Instrument tables (4x)
-
Results - ‘at rest’ vs ‘in operation’5Included in model:
- UDF Plenum;
- Eight returns;
- Patient with heat-source;
- Four surgeons with heat-source;- Two lights with heat-source (RL7
position);
- Anaesthetist with heat-source;- Instrument tables (4x)
-
Results - ‘at rest’ vs ‘in operation’5Included in model:
- UDF Plenum;
- Eight returns;
- Patient without heat-source;
-
Summery of first-results5
Based on a comparison for a 1T plenum between ‘at rest’ and ‘in operation’ conditions, there are indications that:
1) The dimension and shape of the protected area (level 2) in the operating theatre is dependent of the location of people and equipment;
2) Location of lights and tables does have a significant influence;
3) There are indications that the protected area can increase by instrument tables etc., however this extended area might become less stable.
‘at rest’ without lights ‘in operation’ with lights
-
Summery of first-results5
Based on a comparison for a 1T plenum between ‘at rest’ and ‘in operation’ conditions, there are indications that:
1) The dimension and scape of the protected area (level 2) in the operating theatre is dependent of the location of people and equipment;
2) Location of lights and tables does have a significant influence;
3) There are indications that the protected area can increase by instrument tables etc., however this extended area might become less stable.
‘at rest’ without lights ‘in operation’ with lights
-
Table of Contents
1) Introduction Actiflow
2) Scope & Objective
3) Design & Assessment methods
a) Design methods
b) VCCN RL7 & WIP guideline
c) Summary of methods
4) CFD Simulations
5) Simulation resultsa) Impact of ‘at rest’ vs ‘in operation’
b) Role for CFD in selection of systems & design changes?
6) General remarks and conclusions
-
Included in model:
- UDF Plenum;
- Eight returns;
- Patient with heat-source;
- Four surgeons with heat-source;- Two lights with heat-source (RL7 position);
- Anaesthetist with heat-source;
- Instrument tables (4x)
Results - impact of OR lights5
-
Results - impact of OR lights5
Semi-openSmallWider location realistic
Semi-openSmallWider location realistic
-
Results - impact of OR lights5
Semi-openSmallWider location realistic
Semi-openSmallWider location realistic
-
Results - impact of OR lights5
Semi-openOR lights
SmallOR lights
-
Results - impact of different systems5
2TPlenum
Supply inPeriphery
-
Results - impact of different systems5
2TPlenum
Supply inPeriphery
-
Table of Contents
1) Introduction Actiflow
2) Scope & Objective
3) Design & Assessment methods
a) Design methods
b) VCCN RL7 & WIP guideline
c) Summary of methods
4) CFD Simulations
5) Simulation resultsa) Impact of ‘at rest’ vs ‘in operation’
b) Role for CFD in selection of systems & design changes?
6) General remarks and conclusions
-
General remarks and conclusions6
1) There is a strong indication that the airflow patterns under ‘at rest’ vs ‘in operation’ - conditions differ substantially from each other;
2) In line with current guidelines it has been found that the shape and location of the lights has a substantial impact;
3) Computational fluid dynamics might breach the gap between the design phase and calibration &testing when built.
The results shown in this presentation lead to the following conclusions:
-
General remarks and conclusions6The results shown in this presentation lead to the following conclusions:
Future outline – Determination of CFU concentration with persons as contamination source in CFD
Neck as CFU source
Design based on ‘in operation’ - conditions & CFU concentration
1) There is a strong indication that the airflow patterns under ‘at rest’ vs ‘in operation’ - conditions differ substantially from each other;
2) In line with current guidelines it has been found that the shape and location of the lights has a substantial impact;
3) Computational fluid dynamics might breach the gap between the design phase and calibration &testing when built.
-
General remark
The objective of this study was to identify the difference in airflow between ‘at rest’ vs ‘in operation’. The results show that the airflow pattern is influenced significantly by people, lights and e.g. instrument tables. The results aren’t meant to show the advantage or disadvantage of a certain system nor the preference for a certain type of system. Moreover, the results are mainly valet for this reference case, additional research is necessary for more generic conclusions about specific airflow patterns under different circumstances and dimensions of the operating room. In conclusion, in this presentation the difference in airflow patterns is shown between ‘at rest’ vs ‘in operation’, for any other conclusions additional research is necessary.
-
ir. M.G.M. (Mike) van der HeijdenBouwfysisch & FSE adviseurTel: +31 (0)76 5422 220Actiflow B.V.