TENDER TOPIC:Galileo 2008-2.1.1: Simulators and Tools
1. General Overview and Context2. Purpose of the Contract3. Overall Logic and WP BS4. Tasks Description5. Eligibility Criteria for the Bidders6. Financial and Admin Aspects
•Outline
3
1. General Overview and Context 1/2
• GNSS Simulation and Testing Facilities are Key Enablers for application and receiver downstream industry
• The accesibility to this infrastructure should be ensured to any European user
• A coordinated approach is expected to provide a better service to end users
• A definition study on the potential harmonisation of the European GSTI has been launched recently (SCENIC - FP7 1st Call)
4
1. General Overview and Context 2/2FP7 1st Call Study on Harmonisation: SCENIC
5
1. General Overview and Context2. Purpose of the Contract3. Overall Logic and WP BS4. Tasks Description5. Eligibility Criteria for the Bidders6. Financial and Admin Aspects
6
• Development of a networking platform which establishes a single entry point to the European Testing Labs
• Preliminary Mission Concept for GSTI V1:• Simplified access point for European users interested in GNSS
testing services • Enhance communication and coordination of actors (users, GNSS
centres, etc)• Dynamic management of available information on European
GNSS testing facilities• Provide web-based helpdesk service to the user community• Potentially become hosting platform for publicly owned GNSS
analysis and simulation SW tools
2. Purpose of the Contract 1/2
7
• GSTI V1 System is conceived as:
• A centralised entry point to the European GNSS Testing Infrastructure
• A networking platform that should improve the coordination between European initiatives
European GSTI Web Portal
INTERNET
Austria
Bulgaria
Czech Republic
Finland
France
Germany
Greece
Ireland
Italy
Hungary
Latvia
Norway
Poland
Slovakia
Slovenia
Spain
Sweden
Switzerland
United Kingdom
Denmark
Portugal
Belgium
Netherlands
Estonia
Lithuania
Romania
Luxembourg
EUROPEAN GNSS LABORATORIES AND TEST FACILITIES
USER COMMUNITY- R&D (FP7 projects)- Universities- SMEs- Others
DB
2. Purpose of the Contract 2/2
8
1. General Overview and Context2. Purpose of the Contract3. Overall Logic and WP BS4. Tasks Description5. Eligibility Criteria for the Bidders6. Financial and Admin Aspects
9
1. Definition and Development of the GSTI V1 Platform• Task 2: USER AND SYSTEM REQUIREMENTS• Task 3: SYSTEM DESIGN AND DEVELOPMENT• Task 4: INTEGRATION AND TEST
2. System Ops&Maintenance, Awareness and Promotion, collection of User Feedback and Evolution to GSTI V2
• Task 5: INITIAL OPERATIONS AND MAINTENANCE• Task 6: USER SUPPORT, FEEDBACK COLLECTION AND AWARENESS• Task 7: PLATFORM EVOLUTION AND FINAL PLATFORM DELIVERY• Task 8: TECHNICAL STUDY ON ACCESIBILITY TO EC/GSA SW TOOLS
3. Overall Logic and WP Breakdown Structure 1/2
10
3. Overall Logic and WP Breakdown Structure 2/2WP1 Management
WP2 User and System Requirements
SRR Milestone
WP3 System Design and Development
CDR Milestone
WP4 Integration and Test
FAT Milestone
WP5 Initial Operations and Maintenance
GSTI V1.0
WP6 User Support, Feedback Collection, Dissemination and Awareness
PERR Milestone
WP7 Platform Evolution
FAR Milestone - GSTI V2.0
WP8 Analysis of Accessibility to EC/GSA SW Tools
B M E B M E B M E B M E B M E B M E B M E B M E B M E B M E B M E B M E B M E B M E B M E B M E B M E B M E B
T0 T0+3 T0+7 T0+9 T0+14 T0+18
11
1. General Overview and Context2. Purpose of the Contract3. Overall Logic and WP BS4. Tasks Description5. Eligibility Criteria for the Bidders6. Financial and Admin Aspects
12
• Overall management of the contract
• Expected outputs:
4. Tasks Description 1/8
Project Milestone Review Schedule
Kick-Off Meeting KOM T0
System Requirements Review
SRR T0 + 3
Critical Design Review CDR T0 + 7
Factory Acceptance Test FAT T0 + 9
Platform Evolution Readiness Review
PERR T0 + 14
Final Acceptance Review FAR T0 + 18
Task 1: Management
Ref Title
D1.1 Project Management Plan
D1.2.x Status Report
D1.3 Final Report
13
• Definition of user and system specification for the GSTI V1 platform• Analysis of outcomes produced in the GSTI definition study• Survey and assessment of COTS tools which may eventually used to support the implementation of the system• Expected outputs
4. Tasks Description 2/8
Ref TitleD2.1 User Requirements Document (URD)
D2.2 System Requirements Document (SRD)
D2.3 Survey Report on IT COTS tools
Task 2: User and System Requirements
14
• Develop logical and physical design for GSTI platform• Use of COTS SW solutions should be favoured• Prepare integration activities and define test cases• Expected outputs:
4. Tasks Description 3/8
Ref TitleD3.1 Architectural Design Document (ADD)
D3.2 Design Justification File (DJF)
D3.3 Ext. Interface Control Document (ICD)
D3.4 Inventory of IT COTS HW/SW
D3.5 Preliminary delivery of web GUI
Task 3: System Design and Development
Ref TitleD3.6 Integration and Test Plan
D3.7 Configuration Management Plan
15
• Achieve system integration Complete (successfully!) the full test battery according to plan
• Populate tools’ database• Prepare operations and maintenance plan• Eventually make the system available to the user community• Expected outputs:
4. Tasks Description 4/8
Ref TitleD4.1 Integration and System Test Report
D4.2 GSTI V1 Platform
D4.3 GSTI V1 User Manual
Task 4: Integration and Testing
Ref TitleD4.4 GSTI V1 Initial Operational Procedures
D4.5 GSTI V1 Maintenance Plan
16
• Procurement of hosting, operations and maintenance services for the GSTI platform from qualification (FAT) to end of activities (FAR)
The contractor shall keep the system “alive” during the whole duration of this task• Further develop operational procedures• Expected outputs:
4. Tasks Description 5/8
Ref TitleD5.1 Observation and Non Conformance Reports
D5.2.x Periodical reports on Operations
D5.3 GSTI V2 Operational Procedures
Task 5: Initial Operations and Maintenance
17
• Support users through a helpdesk• Collect and synthesize user feedback to be taken into account for service improvements to be implemented in a
new system release• Promote the developed system by attending key conferences and/or establishing a user forum• Expected outputs:
4. Tasks Description 6/8
Ref TitleD6.1 GSTI User and Facilities feedback report
D6.2 Report on conducted awareness activities
D6.3 Delta features for next system release (GSTI V2)
Task 6: User Support, Feedback Collection & Awareness
18
• Develop a new version of the tool taking into account feedback collected during the initial operations phase
• Address additional system evolutions and recommendations in an GSTI service roadmap• Expected outputs:
4. Tasks Description 7/8
Ref TitleD7.1 GSTI V2 Platform
D7.2 GSTI V2 User Manual
D7.3 GSTI Service Roadmap
D7.4 System Test report GSTI V2
D7.5 Hosting Site Interface requirements
Task 7: Platform Evolution and Final Platform Delivery
19
• Assess suitability of the GSTI platform to provide public access to EC/GSA owned tools• Analyse implementation options for some specific tools (effort limited to 2 or 3 cases)
to be proposed at KO• Expected outputs:
4. Tasks Description 8/8
Ref TitleD8.1 TN on integration of EC/GSA SW RD tools in the GSTI web portal
Task 8: Technical Study on Accessibility to EC/GSA Tools
20
1. General Overview and Context2. Purpose of the Contract3. Overall Logic and WP BS4. Tasks Description5. Eligibility Criteria for the Bidders6. Financial and Admin Aspects
21
5. Eligibility Criteria for the Bidders1. Thorough understanding of global satellite navigation systems and
augmentation technologies2. Thorough understanding of the simulation and test field in satellite
navigation: main public and private actors, institutional framework, facilities, tools, etc.
3. Outstanding background on design, development and integration of IT systems and network features.
4. Sound experience on the development of web-based applications and knowledge management databases.
5. Sound experience in operations of web-based distributed networks and systems.
6. Good knowledge of the GNSS user community needs, present applications, trends, etc., especially related to simulation and testing activities.
22
1. General Overview and Context2. Purpose of the Contract3. Overall Logic and WP BS4. Tasks Description5. Eligibility Criteria for the Bidders6. Financial and Admin Aspects
23
6. Financial and Administrative Aspects• Firm Fixed Price Contract 100% Funded by EC• Indicative Budget: 500.000 Euro• Duration of the contract: 18 Months
• Call for Tender to be released soonIt will be announced in the usual communication channels